1
Boone High Bridge
Todd Wimmer – UPRR December 4, 2009
1
2
Boone High Bridge
Agenda :
• History of the Kate Shelley Bridge• Reason for repairs and replacement
Ne Boone High Bridge• New Boone High Bridge• Project Construction and Issues• Questions
2
3
Kate Shelley Bridge
Kate Shelley Bridge - location
Portland
SeattleEastport
Twin Cities
Duluth
Oakland SLCKC
Omaha
Twin Cities
Denver
Chicago
LA
Calexico
St. Louis
DallasMemphis
Calexico
Nogales El Paso
Eagle Pass Houston
Laredo
DallasNew
Orleans
3
BrownsvilleLaredo
4
Kate Shelley Bridge - location
Location of new line and bridge location
Boonelocation.
4
Moingona
5
Kate Shelley Bridge - facts Bridge Information :C&NW line Chicago to Omaha Located 155 milesOmaha. Located 155 miles east of Omaha.
Spans the Des Moines River Valley.Valley.
Construction Started early 1899.
Bridge opened May 19th, 1901.
Length : 2685’Height : 190’
22 steel formed towers resting on stone pier foundations. Spans ranging from 45’ to 75’.
5
300’ pin connected deck truss
6
Kate Shelley Bridge Who is Kate Shelley ?
Bridge originally named the Boone Viaduct.
July 1881 thunderstorm flooded Des Moines river bottom washing out a bridge over a small ravine east of the river near Moingona.
A freight train derailed into the flooded waters killing the fireman whose body was never found The engineer survivednever found. The engineer survived.
Kate Shelley, then 15 yrs of age, knew of the derailment / washout and that a passenger train should soon be near. During the storm and heavy rains, with a lantern in hand, crossed the old Des Moines River bridge flagging the approaching passenger train to a stop.
6
In 1926 the bridge was dedicated to the memory of Kate Shelley.
7
Kate Shelley Bridge - construction
7
8
Kate Shelley Bridge – construction
8
9
Kate Shelley Bridge - construction
9
10
Kate Shelley Bridge - testing
10
11
Kate Shelley Bridge – opened May 19th, 1901
11
12
Kate Shelley Bridge - then At this time, it is said that the Boone ViaductAt this time, it is said that the Boone Viaduct was the longest railroad bridge, both for single or double track, in the world.
12
13
Kate Shelley Bridge - now
13
14
190 ft. high
14
15
Kate Shelley Bridge – Reasons for Replacement
Prior to 2002 1 train @ 35 mph•Prior to 2002, 1 train @ 35 mph.•After 2002, 2 trains @ 25 mph.•Creates a bottleneck and traffic congestion.•Bridge is 104 years of age.•Structural wear and degradation•Structural wear and degradation.
15
16
Kate Shelley Bridge – Reasons for Replacement
Crack in floor beam connection Section loss due to rusting
16
17
Kate Shelley Bridge – Reasons for Replacement
Broken stiffener at a cross frameSection loss and cracking at connection
17
18
Kate Shelley Bridge – Reasons for Replacement
18
19
Repairs made in 2002
Kate Shelley Bridge – Repairs and strengthening
Repairs made in 2002
19
Lateral bracing rodsLateral struts and bottom diagonals
20
Kate Shelley Bridge – Repairs and strengthening
Repairs made in 2002
20
21
Kate Shelley Bridge – Repairs and strengthening
Top chord strengthening
Cross frame lateral bracingCross frame lateral bracing
21
Bottom diagonals
22
Kate Shelley Bridge – Repairs and strengthening
22
23
Kate Shelley Bridge – Repairs and strengthening
B fBefore After
23
24
Kate Shelley Bridge – Repairs and strengthening
24
25
Kate Shelley Bridge
25
26
New Boone High Bridge
•Design speed 70 MPH.•Double Track on 20 ft centers.•Original length 2550 ft long.•Revised length 2813ft long.
•Original Project Cost : $43 millionD i d 2005 2006•Designed 2005 -2006
•Started Construction late 2006•Original completion Nov 2008•Revised completion Aug. 20, 2009
26
27
New Boone High Bridge
• 26 concrete column bents ( 5 towers )• Spans ( 6@30’ PCB, 20@110’DPG and 6@70’ DPG x2 )
0 0416% d• 0.0416% grade• Nearly 560,000 yd^3 earthwork• Nearly 26,000 yd^3 concrete used• Nearly 2.9 million lbs steel rebar• Nearly 1 2 million lbs structural steel and embeds
27
• Nearly 1.2 million lbs structural steel and embeds• Total weight estimated near 13.6 million lbs
28
20 ‘
15.5 ‘
7 ‘
28
29
29
30
30
31
31
32
32
33
33
34
34
35
35
36
36
37
37
38
38
39
39
40
40
41
Slide plane
41
42
Key :1. Original ground line2. Designed slope3. Current slope4. Approx. shale layer5 Estimated failure plane
Original Design5. Estimated failure plane
Bent #2 East Abutment
1.2.
3.
4.
5.
42
43
Proposed DesignKey :1. Proposed slope2. New 70’ span3. New east approach ( 3 x 30’ spans )
1.
2.
3.
43
44
Boone High Bridge – Revised DesignEastWest EastWest
New 70’ steel span
102’ new west end approach
Original Slopes
90’ new east end approach
New slopes
44
45
45
46
46
47
47
48
48
49
49
50
50
51
51
52
52
53
53
54
54
55
55
56
56
57
57
58
58
59
59
60
60
61
61
62
62
63
63
64
64
65
65
66
66
67
67
68
68
69
69
70
70
71
Boone High BridgeTh k YThank You
71