Turkmenistan Gas CongressGas Projects : Concepts & Strategies
22 May, 2013
Vassili Rybkin
8/20/2019 1368815394 Honeywell ENG
2/15
Honeywell Corporate Overview
• Founded in 1886• 116,000 employees in more
than100 countries
• A $34 billion Fortune 500company
• Global leader in advancedtechnology products, services
and solutions
SPECIALTYMATERIALS
AUTOMATION ANDCONTROLSOLUTIONS (ACS)
TRANSPORTATION AND POWERSYSTEMS
AEROSPACE
Financially Strong and Global
8/20/2019 1368815394 Honeywell ENG
3/15
Honeywell Proprietary
Honeywell.com
3
Document control number
Natural Gas Production
• E. Europe / Eurasia will have highest cumulative gas production by 2035
• Gas production is predicted to go up by 250 bcm/yr before 2030
• Gas trade is expected to double in volume by 2035 – Share of LNG will increase from 26% to 42%
IEA WEO Oct 2009
Natural Gas Production by Region in the Reference Scenario
8/20/2019 1368815394 Honeywell ENG
4/15
Honeywell Proprietary
Honeywell.com
4
Document control number
Primary exporters: Eurasia (FSU), Middle East,
and other non-OECD producers.
World Gas Trade
(Source: IEA WEO, Oct 2009)
Inter-Regional Natural Gas Exports / Imports
Export
Import
ur si
8/20/2019 1368815394 Honeywell ENG
5/15
Honeywell Proprietary
Honeywell.com
5
Document control number
Natural Gas to Olefins
Gas to Liquids
CNG
GasProcessingTechnology
Needs
ImproveOperations
Capture MoreValue via
Petrochemicals
Gas ExportInfrastructure
CaptureMore Value in
Gas Processing
Reduce Riskand Schedule
in Project
Execution
New Pipelines
New Export
Facilities
CIS Challenges and Needs
Gas ExportInfrastructure
Capture MoreValue via gas
products
Dehydration
Physical and CyberSecurity
Safety
Improve
Operational Stability
Reduce Human
Error
Improve Availability
and Reliability
Enhance Asset Life
Improve Efficiency
Single Source for
Process Technology
Integrated Main
Automation
Contractor
Containment
Removal
NGL Recovery
Dehydration
Sulfur Recovery
Conversion
Upgrading
Additional Plants
8/20/2019 1368815394 Honeywell ENG
6/15
Honeywell Proprietary
Honeywell.com
6
Document control number
UOP’s Gas Treating TechnologiesTechnology
Membranes
Benfield
Amine GuardMolecular Sieves
Merox
MDTM Trays
Selexol
PSA
# Units
130
650
550
2,000
1,700
800
60
800
1000
100
10
1.0
0.1Scavengers
MolSiv™ Ads
PSA
Selexol™Process
Amine Guard™FS Process
Separex™Membrane
Tech
Benfield™Process
P a r t i a l P r e s s u r e A c i d G
a s i n F e e d , p s i a
Partial Pressure Acid Gas in Product, psia
0.001 0.01 0.1 1.0 10 100
1000
100
10
1.0
0.1
ProductLines
8/20/2019 1368815394 Honeywell ENG
7/15
Honeywell Proprietary
Honeywell.com
7
Document control number
Liquefaction
Gas monetization processes
Shipping
Production
Revapor-ization
Synthesis gas
production
Hydrocarbonsynthesis
Upgrading
Ethylene
PropyleneMTOMethanol
synthesis
PolymersPolyethylene
Polypropylene
Production
Shipping Export of
natural gas NGNatural
gas
Naturalgas
Liquid fuels
LNG
GTL
GTO
GTP
8/20/2019 1368815394 Honeywell ENG
8/15
Honeywell Proprietary
Honeywell.com
8
Document control number
UOP Gas Processing Plant Offerings
Packaged Plants & Cryo Technology Expand Available UOP Offering
NaturalGasoline
Mixed
Butanes
Propane
Ethane
Raw NGL
Sulfur Sulfur
Recovery
NGLRecovery
Dehydration/
Hg Removal
Acid Gas
Removal
Wellhead
Dehydration DrySweet Gas
NaturalGas
LNG
Products
Liquefaction
NGLFractionation
Packaged Plant = Modular Equipment
Acid Gas
Russell PackagedPlant:
Russell PackagedPlant:
Potential
Cryo
Cryo
Amine
Adsorbents
Nitrogen
Rejection
Russell CoreOffering
Russell/UOPSynergistic Offering
UOP PackagedPlant:
UOP PackagedPlant:
Amine
Membrane
UOP Licensed
Technology:
UOP Licensed
Technology:
AdsorbentsTwister
Adsorbents Amine
Cryo, Int’l Only
8/20/2019 1368815394 Honeywell ENG
9/15
Honeywell Proprietary
Honeywell.com
9
Document control number
UOP Russell Packaged Plant CapabilitiesPackage process technology as skid-mounted, shop-fabricated packages for
Lower cost fabrication versus on-site construction
Faster installation
Trusted process and mechanical performance
High on-stream efficiency
Ideal candidates for packaged units
Units sized for 200 MMSCFD or less
Remote locations
Plants with multiple trains
9
UOP Russell technology solutions (CO 2 removal, dew pointing and NGLrecovery) delivered as pre-fabricated modules
8/20/2019 1368815394 Honeywell ENG
10/15
Honeywell Proprietary
Honeywell.com
10
Document control number
UOP Russell Packaged NGL Plant
Modular Design
Rapid Gas Monetization
19 weeks later …
8/20/2019 1368815394 Honeywell ENG
11/15
Honeywell Proprietary
Honeywell.com
11
Document control number
One Honeywell Approach: Multiple Offerings
Offshore
FPSO / FLNGOil & Gas Platform
OnshoreOil & Gas Reserves
Shale Oil & Gas
Offloading & Storage
Chemical PlantRefinery
Gas TreatmentStorage
PipelineTransfer
LiquefactionLNG CNG
Oil & Gas Value Chain AreasHoneywell Business Units Honeywell Technology Offerings
Gas To Liquids NGL Separation
Acid Gas Removal
Gasification
Dehydrogenation
Gas Purification
High Purity Hydrogen H2
UOP GP&H
UOP GP&H Flare Stack
Burners
Oxidizers
Honeywell Process
HPS
DCS Control Systems
Gas Measurement & Metering
Sensors & Wireless Transmitters
Honeywell Life Safety
HFSHA
HSP
Fire & Smoke Detection Systems
Gas & Flame Detectors
Personal Protective Equipment
PPE
Honeywell Security
Integrated Security/CIP
Access & Monitoring
Control Systems
Sensors & Controls Sensors, Actuators
8/20/2019 1368815394 Honeywell ENG
12/15
Honeywell Proprietary
Honeywell.com
12
Document control number
Flame, Smoke, GasDetectors
Integrated Safety & Security Solutions
Intrusion Detection
Radar Surveillance, T-Hawk(Micro Air Vehicle), Lift Barr ier
Access Control
Video Surveillance
Command & Control
Extended Perimeter
Fence Sensors, PE Beams
Muster Reader, Card Reader
Fixed Camera, PTZ Camera
Common HMI in Control Room
Multiple Layers of Protection
Safety Manager
Cyber Securi ty
8/20/2019 1368815394 Honeywell ENG
13/15
Honeywell Proprietary
Honeywell.com
13
Document control number
• Asset Management• Boundary Management• Corrosion Detection• Training Simulators / Operator Training
• Wireless Solutions / Handheld Devices• Open Systems Management• Migration Path Solutions
Minimizeunscheduled
downtime and
enhance assetlifecycle
Performance Improvement and reliability
• Integrated Control, Safety, Fire and Gas• Industrial and Cyber Security
• Disaster Recovery / Continuity• Equipment Health Monitoring• Alarm Rationalization and Management• Abnormal Situation Management• Early Warning Process Diagnostics
Comply withcritical
infrastructureprotection
regulations andreduce incidents
Achieve Reliability Improvement of 7-10%.
8/20/2019 1368815394 Honeywell ENG
14/15
Honeywell Proprietary
Honeywell.com
14
Document control number
Summary -‘Start with End in Mind’• We see that CIS demand for new Gas
projects will not cease - Export demand,increasing local demand – Industrial Power,City Gas, CNG
• Best Projects need to consider less traditionalapproach for technology, important to assessearly any operations benefits
• Single point of responsibility for focusedtechnology integration
• Ensure competition is still strong under eachtechnology area to ensure best pric ing forany commodity goods
• Realisation that initial project price is importantbut even more so is the total price/cost ofownership over 20 yrs operations
• Give TIME and SPACE for the technologyneeds and technology strategydiscussion…….in your business