RECEIVERS 10TH SCHEDULE OF PAYMENTS
TO BE MADE PURSUANT TO THE 1ST INTERIM PLAN 1
IN THE UNITED STATES DISTRICT COURT
FOR THE NORTHERN DISTRICT OF TEXAS
DALLAS DIVISION
SECURITIES AND EXCHANGE COMMISSION,
Plaintiff,
v.
STANFORD INTERNATIONAL BANK, LTD., ET AL.,
Defendants.
Case No. 3:09-CV-0298-N
______________________________________________________________________________
RECEIVERS 10TH SCHEDULE OF PAYMENTS
TO BE MADE PURSUANT TO THE 1ST INTERIM PLAN
______________________________________________________________________________
Receiver Ralph S. Janvey (the Receiver) hereby files this 10th Schedule of
Payments to be Made Pursuant to the 1st Interim Plan (the 10th Schedule), respectfully stating
as follows:
On May 30, 2013, the Court granted the Receivers Motion for Approval of
Interim Distribution Plan (the 1st Interim Plan). [See Doc. 1877.] The Courts Order
approving the 1st Interim Plan instructed the Receiver as follows:
Payments under the Interim Plan shall be made on a rolling basisas certifications in response to Certification Notices are receivedand processed. Prior to making a group of payments pursuant tothe Interim Plan, the Receiver shall file a schedule of the paymentsto be made. Each such schedule shall be filed at least ten (10) daysprior to the subject payments being made. The schedules shallinclude claim ID numbers and the amount of the associatedpayments but shall not contain information from which the
individual Investor CD Claimants can be identified.
[Id. at 8.]
The Receiver is filing the 10th Schedule (attached hereto as Exhibit 1) in
accordance with the above instructions and expects to begin the process of sending the payments
Case 3:09-cv-00298-N Document 2084 Filed 09/05/14 Page 1 of 4 PageID 56790
8/11/2019 10th Schedule Re 1st Interim Plan
2/20
RECEIVERS 10TH SCHEDULE OF PAYMENTS
TO BE MADE PURSUANT TO THE 1ST INTERIM PLAN 2
listed therein once the schedule has been on file with the Court for ten (10) days. The 10th
Schedule shows that the Receiver intends to make payments totaling $2,462,426.69 to the
claimants who submitted the referenced claim numbers. This 10th Schedule will be followed by
others, each of which will be submitted by the Receiver on a rolling basis as additional responses
to Certification Notices are received and processed.
Case 3:09-cv-00298-N Document 2084 Filed 09/05/14 Page 2 of 4 PageID 56791
8/11/2019 10th Schedule Re 1st Interim Plan
3/20
RECEIVERS 10TH SCHEDULE OF PAYMENTS
TO BE MADE PURSUANT TO THE 1ST INTERIM PLAN 3
Dated: September 5, 2014 Respectfully submitted,
BAKER BOTTS L.L.P.
By: /s/ Kevin M. Sadler
Kevin M. SadlerTexas Bar No. [email protected] D. PowersTexas Bar No. [email protected] T. ArlingtonTexas Bar No. [email protected] San Jacinto Center98 San Jacinto Blvd.
Austin, Texas 78701-4039(512) 322-2500(512) 322-2501 (Facsimile)
Timothy S. DurstTexas Bar No. [email protected] Ross AvenueDallas, Texas 75201(214) 953-6500(214) 953-6503 (Facsimile)
ATTORNEYS FOR RECEIVER RALPH S.JANVEY
Case 3:09-cv-00298-N Document 2084 Filed 09/05/14 Page 3 of 4 PageID 56792
8/11/2019 10th Schedule Re 1st Interim Plan
4/20
RECEIVERS 10TH SCHEDULE OF PAYMENTS
TO BE MADE PURSUANT TO THE 1ST INTERIM PLAN 4
CERTIFICATE OF SERVICE
I certify that on September 5, 2014, I electronically filed the foregoing documentwith the Clerk of the Court for the Northern District of Texas, Dallas Division, using the
CM/ECF system. The ECF system will send a Notice of Electronic Filing to all counsel ofrecord who have consented in writing to accept service of this document by electronic means.
I further certify that on September 5, 2014, I served a true and correct copy of theforegoing document and the notice of electronic filing by United States Postal Service CertifiedMail, Return Receipt requested, to the persons noticed below who are non-CM/ECF participants:
R. Allen Stanford, Pro SeInmate #35017183Coleman II USPPost Office Box 1034
Coleman, FL 33521Via Certified Mail, Return Receipt Requested
/s/ Kevin M. Sadler
Kevin M. Sadler
Case 3:09-cv-00298-N Document 2084 Filed 09/05/14 Page 4 of 4 PageID 56793
8/11/2019 10th Schedule Re 1st Interim Plan
5/20
EXHIBIT 1
10th Schedule of Payments
to be Made Pursuant to the 1st Interim Plan
Case 3:09-cv-00298-N Document 2084-1 Filed 09/05/14 Page 1 of 16 PageID 56794
8/11/2019 10th Schedule Re 1st Interim Plan
6/20
ClaimID(s)
PaymenttobeMade
Pursuanttothe1stInterimPlan
STANFORD40012484,STANFORD40012492,STANFORD40017834 728.23$
STANFORD10078622,STANFORD50002600,STANFORD50032275 3,141.11$
STANFORD60004622,STANFORD60008601,STANFORD60010614,STANFORD60011513,STANFORD60012030,
STANFORD60012390 5,596.34$
STANFORD10076409,STANFORD40007677,STANFORD40007685,STANFORD40007707,STANFORD40007715,
STANFORD40007723,STANFORD40007731,STANFORD40007766,STANFORD60029110 1,012.48$
STANFORD10008128,STANFORD60026219 485.03$
STANFORD10008624 2,678.14$
STANFORD10007628 144.50$
STANFORD10140727,STANFORD10140735,STANFORD10146636,STANFORD10149104,STANFORD50009508,
STANFORD50013963 8,589.63$
STANFORD10077561,STANFORD50014528 892.81$
STANFORD40004651,STANFORD50043048,STANFORD50105019 2,952.67$
STANFORD10115528,STANFORD60004002 257.24$STANFORD10079777,STANFORD10079785,STANFORD10079793,STANFORD10079807,STANFORD10079815,
STANFORD10079823,STANFORD10079939,STANFORD10079947,STANFORD10079955,STANFORD10079998,
STANFORD10080007,STANFORD10080015,STANFORD50046616 140.37$
STANFORD50007890 568.34$
STANFORD40008290,STANFORD40009181,STANFORD50014773 1,100.10$
STANFORD50033166 656.85$
STANFORD50023888 24,541.85$
STANFORD10036440,STANFORD50043960 1,160.23$
STANFORD10015221,STANFORD10015230,STANFORD10015248,STANFORD10015361,STANFORD10015370,
STANFORD1001538
8 1,957.67$
STANFORD10015213,STANFORD10015264,STANFORD10015396,STANFORD10015400 1,039.05$
STANFORD10010823 2,966.36$
STANFORD10023500,STANFORD10023518,STANFORD50010360 1,124.20$
STANFORD10019405,STANFORD10020152,STANFORD10022945,STANFORD10022953,STANFORD40003043,
STANFORD40003078,STANFORD40003086,STANFORD40003116,STANFORD50008390,STANFORD50012118,
STANFORD50016148,STANFORD50037927,STANFORD50041983,STANFORD50041991,STANFORD50042009,
STANFORD50042017,STANFORD50042025,STANFORD50042033,STANFORD50042050,STANFORD50042068,
STANFORD50042076,STANFORD50042084,STANFORD50042092,STANFORD50042106,STANFORD50042130,
STANFORD50042149,STANFORD50042165,STANFORD50042173,STANFORD50042190,STANFORD50042211,
STANFORD50042220,STANFORD50042246,STANFORD50042254,STANFORD50042262,STANFORD50042270,
STANFORD50042289,STANFORD50042297 24,634.19$
STANFORD10129880,STANFORD10129901,STANFORD10129910,STANFORD10152547,STANFORD10154388,
STANFORD10155384,STANFORD50005669,STANFORD50021885,STANFORD50025899 1,690.58$
STANFORD10065172,STANFORD10065180,STANFORD10066152,STANFORD10066160,STANFORD50012592,
STANFORD5003052
3 3,765.94$
STANFORD10101446,STANFORD50016970 7,250.26$
STANFORD10004050 2,264.07$
STANFORD40006360 369.49$
STANFORD10013857,STANFORD10013865,STANFORD10013873,STANFORD50041240,STANFORD50103075 651.51$
STANFORD10146008,STANFORD50029320 420.49$
STANFORD40006948 614.26$
STANFORD50038818 2,781.69$
STANFORD10039309,STANFORD60000716 814.02$
STANFORD10024743,STANFORD10026088,STANFORD10026096,STANFORD10026185,STANFORD10026240 8,655.55$
STANFORD10027157,STANFORD10027165,STANFORD10027173,STANFORD10027181,STANFORD10027190,
STANFORD10027203,STANFORD10027211,STANFORD10027220,STANFORD10027793 3,092.51$
STANFORD50016580,STANFORD60005025,STANFORD60008849,STANFORD60010738 2,264.03$
STANFORD5002812
0 265.19$
STANFORD50017314 731.52$
STANFORD50027581 1,016.57$
STANFORD40014177 572.04$
STANFORD10095969,STANFORD10158901,STANFORD50000560 348.01$
STANFORD50017098 1,498.14$
STANFORD50001000,STANFORD50008897,STANFORD50021125 4,349.73$
STANFORD10110798,STANFORD50105043 1,718.67$
STANFORD10008411 1,405.00$
STANFORD10010610 500.00$
STANFORD50046462 800.03$
STANFORD50020692 2,014.82$
Case 3:09-cv-00298-N Document 2084-1 Filed 09/05/14 Page 2 of 16 PageID 56795
8/11/2019 10th Schedule Re 1st Interim Plan
7/20
ClaimID(s)
PaymenttobeMade
Pursuanttothe1stInterimPlan
STANFORD10004246 1,000.00$
STANFORD10021000,STANFORD10021396,STANFORD10037535,STANFORD10037543,STANFORD40012190,
STANFORD40012263,STANFORD40012271 9,510.61$
STANFORD40000958,STANFORD40000966,STANFORD40001008,STANFORD50001051 6,071.14$
STANFORD40005879,STANFORD60000287,STANFORD60005866 106.68$
STANFORD10109935,STANFORD10126066,STANFORD50011049,STANFORD50011790 605.93$
STANFORD50047019,STANFORD50047027 738.06$
STANFORD
4000510
0 200.00$STANFORD10081100,STANFORD50024728,STANFORD50025600 1,499.75$
STANFORD40014134,STANFORD60004878,STANFORD60008741,STANFORD60010673,STANFORD60011556 2,349.54$
STANFORD40016307,STANFORD40016323 700.00$
STANFORD50023403,STANFORD50041258,STANFORD50049208 2,488.90$
STANFORD10094695,STANFORD50003674,STANFORD50021028,STANFORD50030892 1,143.82$
STANFORD10008292,STANFORD50040049 500.00$
STANFORD50047604,STANFORD50048406,STANFORD50048414,STANFORD50048422,STANFORD50048430 3,777.43$
STANFORD50004123,STANFORD50020366,STANFORD50020374,STANFORD50024434,STANFORD50032020 4,750.00$
STANFORD10118217,STANFORD10118225,STANFORD10118233,STANFORD10118241,STANFORD50036092 4,461.45$
STANFORD40024652,STANFORD50025058 199.90$
STANFORD10005404 3,499.55$
STANFORD50037129 1,467.33$
STANFORD10038248,STANFORD50021737,STANFORD50050281 2,898.48$
STANFORD10048499,STANFORD50046810,STANFORD50048651,STANFORD50049283,STANFORD50049291,
STANFORD50049305,STANFORD50049313,STANFORD50049321,STANFORD50049330 2,244.21$
STANFORD10048464,STANFORD50049259,STANFORD50049267,STANFORD50049275 1,422.65$
STANFORD40009203,STANFORD40009262,STANFORD50025619,STANFORD50030221,STANFORD60027088 1,251.01$
STANFORD40001717,STANFORD50052985 597.31$
STANFORD50103539 1,000.00$
STANFORD50103547 500.00$
STANFORD40017575,STANFORD40017583,STANFORD40019020,STANFORD40019055,STANFORD40022064,
STANFORD40022072 2,543.14$
STANFORD10160639,STANFORD50009320 1,758.20$
STANFORD40029123,STANFORD50049372 4,691.80$STANFORD40013766,STANFORD60002085,STANFORD60003146,STANFORD60003154,STANFORD60006692,
STANFORD6000755
9,
STANFORD
6000756
7,
STANFORD
6000968
3,
STANFORD
6001009
6,
STANFORD
6001010
0,
STANFORD60011033,STANFORD60011785,STANFORD60012218 929.47$
STANFORD10101454,STANFORD50024809 125,954.88$
STANFORD40000796 496.10$
STANFORD40013367,STANFORD50000837 4,835.14$
STANFORD10100458,STANFORD10101012,STANFORD50028880 2,000.00$
STANFORD10001174,STANFORD60013125,STANFORD60013133,STANFORD60013141,STANFORD60013150 3,230.36$
STANFORD10075046,STANFORD50019406 702.48$
STANFORD10033637,STANFORD50025490 10,000.00$
STANFORD10000020,STANFORD10000917,STANFORD40003965,STANFORD50017390 2,000.00$
STANFORD10008586,STANFORD50024973 500.00$
STANFORD40015564 4,908.49$
STANFORD10008748,STANFORD10008756,STANFORD50050575,STANFORD50050583 5,500.00$
STANFORD50019783 158.58$
STANFORD40004848,STANFORD40004856 760.78$
STANFORD10002375,STANFORD10002499,STANFORD10005463,STANFORD10005471,STANFORD50015630,
STANFORD50027336 8,511.12$
STANFORD10144633,STANFORD10144641,STANFORD50024906 2,116.56$
STANFORD10010653 1,000.00$
STANFORD40017672,STANFORD60028785 1,947.73$
STANFORD50021591 1,900.00$
STANFORD10086935,STANFORD10086943,STANFORD50027158 999.90$
STANFORD40014630 5,110.00$
STANFORD10060286 7,078.91$
STANFORD40004813 1,826.60$
STANFORD40015343 5,000.00$
Case 3:09-cv-00298-N Document 2084-1 Filed 09/05/14 Page 3 of 16 PageID 56796
8/11/2019 10th Schedule Re 1st Interim Plan
8/20
ClaimID(s)
PaymenttobeMade
Pursuanttothe1stInterimPlan
STANFORD50025864 9,481.28$
STANFORD40025586,STANFORD50051440 350.35$
STANFORD10016538,STANFORD10045961 1,196.45$
STANFORD50019791 8,121.11$
STANFORD10098160,STANFORD10098640,STANFORD40009971 200.58$
STANFORD10021507 3,250.55$
STANFORD50018507 7,824.53$
STANFORD4001669
2,
STANFORD
6002942
0 2,500.21$
STANFORD40006166 542.26$
STANFORD50013335,STANFORD50031597 100.00$
STANFORD10007989,STANFORD10120955,STANFORD50036661 2,500.00$
STANFORD10002103 399.92$
STANFORD40012379,STANFORD60031247 1,133.52$
STANFORD10047727,STANFORD50016741 2,000.00$
STANFORD50000462,STANFORD50016792,STANFORD50024647 1,500.00$
STANFORD10099425,STANFORD10099468,STANFORD10099476,STANFORD10099492,STANFORD40009106,
STANFORD40009122,STANFORD40009130,STANFORD50048023 8,570.68$
STANFORD50041770 204.70$
STANFORD10006540 1,200.00$
STANFORD50049461,STANFORD50103679,STANFORD60002450 176.40$
STANFORD50008714 7,500.00$
STANFORD40008916,STANFORD40008940 1,000.05$
STANFORD10003967,STANFORD10059911,STANFORD10059920 8,148.29$
STANFORD50103636 12,300.00$
STANFORD10003622 17,500.33$
STANFORD10005986 2,625.37$
STANFORD40002250,STANFORD40002268,STANFORD60029498 5,418.73$
STANFORD10008942,STANFORD10008950 3,500.00$
STANFORD40004732 16,580.78$
STANFORD40004716 1,333.96$
STANFORD40016153 1,986.74$
STANFORD10015973,STANFORD10015981,STANFORD50053671 1,128.96$
STANFORD10115048,STANFORD50029207 2,499.90$
STANFORD10037020,STANFORD40003094 590.24$STANFORD10015582,STANFORD10015590,STANFORD10015604,STANFORD10015612,STANFORD10023968,
STANFORD10023976,STANFORD10023984,STANFORD10023992,STANFORD40008690,STANFORD40008738,
STANFORD
4000874
6,
STANFORD
4000876
2 4,505.74$STANFORD40013324,STANFORD40013375,STANFORD40013383 19,824.10$
STANFORD40004864,STANFORD40034020,STANFORD40034208 1,683.51$STANFORD10037519,STANFORD60002794,STANFORD60007273,STANFORD60009977,STANFORD60011203,
STANFORD60011882,STANFORD60012277,STANFORD60012510,STANFORD60012668,STANFORD60012781,
STANFORD60012870 5,001.51$
STANFORD10016473 1,132.27$
STANFORD40034003,STANFORD60001160 1,061.44$
STANFORD10118187,STANFORD50045750,STANFORD50045768 9,000.00$
STANFORD10022228 7,000.00$
STANFORD10009159 2,148.15$
STANFORD50042432 409.48$
STANFORD10005722 249.90$
STANFORD40012565,STANFORD40012573 503.14$
STANFORD40013855 600.00$
STANFORD1011690
7,
STANFORD
5000798
0 2,000.00$
STANFORD10014691 2,500.00$
STANFORD40009807 107.56$
STANFORD10009566,STANFORD10009574 10,310.00$
STANFORD10023135 5,000.00$
STANFORD10024425,STANFORD50043641 2,132.98$
STANFORD10003010,STANFORD50033603 3,600.00$
STANFORD10003711,STANFORD50033581 2,500.00$
STANFORD40004759,STANFORD40004767,STANFORD40004775,STANFORD40004783,STANFORD40004791,
STANFORD40004805 1,575.65$
STANFORD50014510 124.20$
STANFORD50008420 2,586.12$
Case 3:09-cv-00298-N Document 2084-1 Filed 09/05/14 Page 4 of 16 PageID 56797
8/11/2019 10th Schedule Re 1st Interim Plan
9/20
ClaimID(s)
PaymenttobeMade
Pursuanttothe1stInterimPlan
STANFORD10104593,STANFORD10104607,STANFORD10124454,STANFORD10124462,STANFORD10135731,
STANFORD10135740,STANFORD40027066,STANFORD40027074 8,983.61$
STANFORD10002995 6,000.00$
STANFORD40009572 4,533.90$
STANFORD10106529,STANFORD40028860 2,986.39$
STANFORD10086579,STANFORD10093680,STANFORD50006150,STANFORD50052900 1,519.89$
STANFORD40005844,STANFORD40005852,STANFORD40005860 3,733.66$
STANFORD
1001996
0,
STANFORD
1004143
5 5,000.00$STANFORD40029000,STANFORD40029034,STANFORD50009311,STANFORD50017381 2,500.00$
STANFORD10014829,STANFORD10014837,STANFORD10014845,STANFORD10014853 4,906.96$
STANFORD10016546,STANFORD10016554,STANFORD10021540,STANFORD10023798,STANFORD10025359,
STANFORD10025545 528.24$
STANFORD10031626,STANFORD50054074 504.80$
STANFORD40012450,STANFORD50013777,STANFORD50026461,STANFORD50031058 7,688.61$
STANFORD40003469,STANFORD50015834 1,000.00$
STANFORD10006699,STANFORD10006753,STANFORD50039911 5,500.00$
STANFORD10031618,STANFORD50054082 2,599.80$
STANFORD10002960,STANFORD40000699,STANFORD50048724 500.00$
STANFORD10005218 3,000.00$
STANFORD10026380 1,000.00$
STANFORD10002090,STANFORD10002251,STANFORD50043269,STANFORD50043277 2,500.00$
STANFORD50020358 1,348.96$
STANFORD4000482
1,
STANFORD
4000483
0 1,718.44$
STANFORD40011364 1,000.00$
STANFORD10011021 5,599.93$
STANFORD10010394,STANFORD10052607,STANFORD10109684 7,499.75$
STANFORD50014307 391.35$
STANFORD50002538,STANFORD50004239,STANFORD50037722 5,000.00$
STANFORD10015760,STANFORD10015779 1,999.59$
STANFORD10059210,STANFORD50017691,STANFORD50025244 5,000.00$
STANFORD10007040,STANFORD50017861 500.00$
STANFORD10002901,STANFORD10008551 4,500.00$
STANFORD10010386,STANFORD10014020 1,250.00$
STANFORD10036768,STANFORD60003979,STANFORD60008172 1,150.00$
STANFORD50009176 3,503.50$
STANFORD50021206 500.00$
STANFORD4001781
8 3,636.75$
STANFORD10001166,STANFORD50043293 2,000.00$
STANFORD10000968,STANFORD50050974,STANFORD50052403 11,095.89$
STANFORD50005731 622.75$
STANFORD50003860 643.99$
STANFORD40016820 202.16$
STANFORD40022110,STANFORD50049941 165.38$
STANFORD10003495 500.00$
STANFORD10022317 3,000.00$
STANFORD10006494 2,500.00$
STANFORD10024263,STANFORD10024271 600.00$
STANFORD40014452,STANFORD50005537 3,000.00$
STANFORD40013251,STANFORD50006436 9,579.48$
STANFORD50042904 3,738.78$
STANFORD10002693,STANFORD50021303 15,000.00$
STANFORD10017020,STANFORD50013513 25,000.00$
STANFORD10020772,STANFORD60003278,STANFORD60007648,STANFORD60010142,STANFORD60011300,
STANFORD60011939,STANFORD60012315,STANFORD60012536,STANFORD60012676 1,764.82$
STANFORD40007219,STANFORD50008730 783.20$
STANFORD10002120,STANFORD50000080 500.00$
STANFORD40010198 320.27$
STANFORD10058958,STANFORD50036262 1,000.00$
STANFORD40007987 2,000.00$
STANFORD50040162 5,000.00$
STANFORD10021981 882.72$
STANFORD50021532 4,000.00$
Case 3:09-cv-00298-N Document 2084-1 Filed 09/05/14 Page 5 of 16 PageID 56798
8/11/2019 10th Schedule Re 1st Interim Plan
10/20
ClaimID(s)
PaymenttobeMade
Pursuanttothe1stInterimPlan
STANFORD10036202,STANFORD50026119 5,000.00$
STANFORD10019421 148.01$
STANFORD10004076,STANFORD40027309 2,028.86$
STANFORD40005208,STANFORD40006484 1,000.00$
STANFORD50004310 500.00$
STANFORD50044753 428.85$
STANFORD10117938,STANFORD50008382 5,476.85$
STANFORD1000434
3,
STANFORD
5010472
1 2,398.83$
STANFORD50017683 946.54$
STANFORD10004890,STANFORD10092170 1,000.00$
STANFORD50015893,STANFORD60025875 2,499.90$
STANFORD40003310,STANFORD50021001 1,500.00$
STANFORD10008381 4,183.35$
STANFORD40010180 497.95$
STANFORD50001892 2,480.35$
STANFORD40006506 4,293.07$
STANFORD50004247 1,500.00$
STANFORD10132465,STANFORD10138471,STANFORD50038451,STANFORD50038460 8,453.10$
STANFORD40005798,STANFORD40005801,STANFORD40005810,STANFORD50008447,STANFORD50013912,
STANFORD50028332,STANFORD60043253 1,008.82$
STANFORD10001204 500.19$
STANFORD40000788 727.85$
STANFORD10002707 2,150.00$
STANFORD50013742 1,000.00$
STANFORD10018891 644.00$
STANFORD10001077,STANFORD10001085 799.89$
STANFORD40034631,STANFORD50034553 462.95$
STANFORD10023259,STANFORD10023267 4,900.00$
STANFORD10006362,STANFORD10102922 280.85$
STANFORD50028715 352.21$
STANFORD10008152,STANFORD60027177 4,231.83$
STANFORD10009051 2,498.47$
STANFORD50013254,STANFORD50017268,STANFORD50028847 148.11$
STANFORD10006567 520.31$
STANFORD50013246,STANFORD50025171 118.11$
STANFORD60013427 1,880.00$
STANFORD1000655
9 920.00$
STANFORD50005545 100.20$
STANFORD40000753 700.00$
STANFORD50045024 1,000.00$
STANFORD50011022 117.37$
STANFORD50028910 668.42$
STANFORD10004475 1,503.05$
STANFORD50008811 277.86$
STANFORD50106287 12,603.81$
STANFORD50031457,STANFORD50032291 3,889.96$
STANFORD50000454,STANFORD50020650 500.00$
STANFORD50050370 8,959.92$
STANFORD10079068,STANFORD50035070 215.48$
STANFORD50020625 500.00$
STANFORD6000488
6 465.77$
STANFORD40038459,STANFORD50037013 500.00$
STANFORD10012869 4,343.10$
STANFORD10005358,STANFORD10005366 4,107.67$
STANFORD10023526 1,300.00$
STANFORD10015183 200.00$
STANFORD10007504 1,286.63$
STANFORD10008349,STANFORD10008357,STANFORD50018175,STANFORD50021842 3,545.05$
STANFORD50011960 12,736.69$
STANFORD10002391 3,500.00$
STANFORD50010310 6,560.83$
STANFORD10003002 5,904.50$
Case 3:09-cv-00298-N Document 2084-1 Filed 09/05/14 Page 6 of 16 PageID 56799
8/11/2019 10th Schedule Re 1st Interim Plan
11/20
ClaimID(s)
PaymenttobeMade
Pursuanttothe1stInterimPlan
STANFORD50020340 3,353.43$
STANFORD50017500 1,000.00$
STANFORD50047680,STANFORD50049984 1,500.00$
STANFORD50049836 1,860.77$
STANFORD10006486,STANFORD50007939,STANFORD50037935 2,965.88$
STANFORD40017850 644.20$
STANFORD10030263,STANFORD10154850 468.25$
STANFORD1003353
0 675.27$
STANFORD10030930,STANFORD10030972,STANFORD10032460,STANFORD10032479 1,300.00$
STANFORD10038175 404.10$
STANFORD40018113,STANFORD50106180 403.62$
STANFORD10023224,STANFORD10023240 1,410.04$
STANFORD10039180 2,431.66$
STANFORD10034676 7,163.54$
STANFORD10038159,STANFORD10038167 315.14$
STANFORD10039090 14,013.89$
STANFORD10035532 199.85$
STANFORD10029290 136.93$
STANFORD10040811,STANFORD50032330,STANFORD50035169,STANFORD50046500,STANFORD50046578,
STANFORD50051946 3,531.48$
STANFORD10038086 399.90$
STANFORD40018199,STANFORD40018202 249.80$
STANFORD10038329 1,000.00$
STANFORD10038019,STANFORD10099808 5,000.00$
STANFORD10034439 500.10$
STANFORD10031820,STANFORD40017931 612.36$
STANFORD10060529,STANFORD40017940 349.50$
STANFORD10034196 2,618.40$
STANFORD10065857,STANFORD10066349,STANFORD10070338,STANFORD10070346,STANFORD40018040 209.90$
STANFORD10020314,STANFORD10040870,STANFORD10043640 300.00$
STANFORD10038000,STANFORD10099816 2,500.00$
STANFORD10033734 500.00$
STANFORD10072470,STANFORD40018938 500.00$
STANFORD10035460 1,087.22$
STANFORD10034200 1,000.00$
STANFORD4001898
9,
STANFORD
4001899
7,
STANFORD
4001900
4 249.90$
STANFORD10035451 775.63$
STANFORD10035443 900.00$
STANFORD10036113 1,120.00$
STANFORD10049630 1,316.67$
STANFORD10042822 4,536.66$
STANFORD10046895,STANFORD10048642,STANFORD10048650 1,249.98$
STANFORD10049428,STANFORD10051791 349.49$
STANFORD10049452 500.00$
STANFORD10042830 3,750.00$
STANFORD10044825 244.16$
STANFORD40019470 250.00$
STANFORD10042695 1,500.00$
STANFORD10045694 2,250.00$
STANFORD10042660 1,005.36$
STANFORD10042717 1,000.00$
STANFORD10045651 195.26$
STANFORD10065717,STANFORD10072748,STANFORD40019373 159.60$
STANFORD10033300,STANFORD10045619 5,141.72$
STANFORD10060871 1,181.46$
STANFORD10031723,STANFORD10031731 767.43$
STANFORD10032860 456.74$
STANFORD10039538 20,767.90$
STANFORD10028099 191.31$
STANFORD10039430 1,084.57$
STANFORD10018719 7,147.97$
Case 3:09-cv-00298-N Document 2084-1 Filed 09/05/14 Page 7 of 16 PageID 56800
8/11/2019 10th Schedule Re 1st Interim Plan
12/20
ClaimID(s)
PaymenttobeMade
Pursuanttothe1stInterimPlan
STANFORD10037560 485.06$
STANFORD10056459 702.69$
STANFORD10063021,STANFORD10063064,STANFORD10083456,STANFORD10083464 680.06$
STANFORD10058982 504.40$
STANFORD10055746 180.03$
STANFORD10044124,STANFORD60024895 3,550.00$
STANFORD10044116 1,277.86$
STANFORD1005455
3,
STANFORD
5001740
3 781.03$
STANFORD40020223 2,147.04$
STANFORD10027831 1,468.76$
STANFORD10058141,STANFORD10059261 2,631.77$
STANFORD10039490 3,432.30$
STANFORD40020444 650.00$
STANFORD40020460 1,850.00$
STANFORD10062866 656.42$
STANFORD10037721 5,000.00$
STANFORD10057439 3,220.87$
STANFORD10056475 500.00$
STANFORD10046763,STANFORD10046771,STANFORD10048731 1,225.69$
STANFORD10021230 6,100.00$
STANFORD10055266,STANFORD10055274,STANFORD50011855,STANFORD50015982,STANFORD50016873,
STANFORD50050605,STANFORD50051660,STANFORD50051687,STANFORD50052640 8,260.04$
STANFORD10062130 2,745.75$
STANFORD10060472 17,995.35$
STANFORD10059962 2,209.32$
STANFORD10055495 385.79$
STANFORD10018069 1,468.30$
STANFORD10037764 3,413.14$
STANFORD10063153 1,807.95$
STANFORD10037110 4,055.16$
STANFORD10039651 429.23$
STANFORD10050051 1,500.00$
STANFORD10050035,STANFORD10050043,STANFORD10050060 2,000.00$
STANFORD10040242 100.00$
STANFORD10047018,STANFORD10050922 255.32$
STANFORD40019799,STANFORD40019853,STANFORD40019888 1,500.00$
STANFORD1002882
0 1,294.03$
STANFORD40019969,STANFORD40019977,STANFORD40019985 1,117.34$
STANFORD10036512 100.00$
STANFORD40019993 1,001.15$
STANFORD10016791 87.41$
STANFORD10047514,STANFORD10056858 100.00$
STANFORD10059121 1,599.54$
STANFORD10028030 553.25$
STANFORD10039716 3,779.70$
STANFORD10028919 1,296.18$
STANFORD10050809 119.27$
STANFORD10063323,STANFORD10063340,STANFORD10083502,STANFORD10085378 344.98$
STANFORD10039481,STANFORD60030232 99.90$
STANFORD10059563,STANFORD10059571 1,845.11$
STANFORD1005954
7,
STANFORD
1005955
5 1,846.53$
STANFORD10054103 2,500.00$
STANFORD10043888,STANFORD10050337 5,605.51$
STANFORD10059431 1,014.43$
STANFORD10039287,STANFORD60030224 529.13$
STANFORD10051465 156.80$
STANFORD10046755 1,288.51$
STANFORD10095551,STANFORD10097406,STANFORD40020347 144.00$
STANFORD10075275,STANFORD10160981,STANFORD40020746 636.07$
STANFORD40020860 1,353.68$
STANFORD40020576 2,181.14$
Case 3:09-cv-00298-N Document 2084-1 Filed 09/05/14 Page 8 of 16 PageID 56801
8/11/2019 10th Schedule Re 1st Interim Plan
13/20
ClaimID(s)
PaymenttobeMade
Pursuanttothe1stInterimPlan
STANFORD10061860,STANFORD10061878,STANFORD10061886,STANFORD10061894,STANFORD10061908,
STANFORD10061916,STANFORD10061924,STANFORD10061932,STANFORD10061940 9,000.00$
STANFORD40020614 1,999.35$
STANFORD40020924 229.80$
STANFORD10063374,STANFORD50019651 2,500.00$
STANFORD10066446 2,121.17$
STANFORD10064362 1,151.00$
STANFORD
1008248
4,
STANFORD
4002119
0 122.99$STANFORD10066934 1,137.45$
STANFORD10064460,STANFORD10064478,STANFORD10064486 3,509.03$
STANFORD10077006,STANFORD10078657,STANFORD40021505 26,750.00$
STANFORD10067760 1,073.56$
STANFORD10068554,STANFORD10068562 3,926.43$
STANFORD10046160,STANFORD10047441 1,152.40$
STANFORD10045163 341.15$
STANFORD10033483,STANFORD10033491,STANFORD50035835 520.59$
STANFORD40022099 3,533.11$
STANFORD10061681 3,575.77$
STANFORD10071210 300.00$
STANFORD10053441 448.61$
STANFORD10053433 507.49$
STANFORD10071431,STANFORD10071440,STANFORD60029005 1,512.90$
STANFORD10049673 137.80$
STANFORD10071288 600.00$
STANFORD10069976 1,170.00$
STANFORD40022471,STANFORD40022480 759.78$
STANFORD40022447,STANFORD60030828 304.84$
STANFORD10017135,STANFORD10031162,STANFORD10043691 1,099.30$
STANFORD10040331 1,668.75$
STANFORD10073698 9,650.00$
STANFORD10073680 556.27$
STANFORD10073744 1,000.71$
STANFORD10073752 500.00$
STANFORD10065008 1,000.00$
STANFORD10071806 857.32$
STANFORD10025480 1,140.92$
STANFORD4002053
3 2,562.76$
STANFORD10066900 712.49$
STANFORD10071318 517.17$
STANFORD10037357 604.25$
STANFORD10065288 160.00$
STANFORD10017402,STANFORD60004541 154.90$
STANFORD10066721,STANFORD50018540 1,301.70$
STANFORD10069984 3,000.00$
STANFORD10058974,STANFORD50036270 500.00$
STANFORD10042679,STANFORD50105353 837.87$
STANFORD10070680 5,438.03$
STANFORD10075402,STANFORD10076395 551.51$
STANFORD10075399 159.79$
STANFORD10070389,STANFORD60025085 2,613.32$
STANFORD4002331
1,
STANFORD
4002333
8 477.38$
STANFORD10072527 1,747.80$
STANFORD10072535 5,080.19$
STANFORD10072829,STANFORD10072837 3,628.98$
STANFORD10073396,STANFORD10076549 100.02$
STANFORD10075925 500.00$
STANFORD40023389 3,251.09$
STANFORD40023427 234.07$
STANFORD40023672 102.20$
STANFORD40023680 280.77$
STANFORD10079173 2,030.80$
STANFORD10077820 792.17$
Case 3:09-cv-00298-N Document 2084-1 Filed 09/05/14 Page 9 of 16 PageID 56802
8/11/2019 10th Schedule Re 1st Interim Plan
14/20
ClaimID(s)
PaymenttobeMade
Pursuanttothe1stInterimPlan
STANFORD10087982 4,500.00$
STANFORD40026949 462.02$
STANFORD10082166,STANFORD10082174,STANFORD10082964,STANFORD10082972 537.36$
STANFORD10086625 12,132.62$
STANFORD40028569,STANFORD40028593 1,994.96$
STANFORD10076557,STANFORD10076565 117.77$
STANFORD40029263 1,843.45$
STANFORD1008938
1 1,111.61$
STANFORD10088008 500.00$
STANFORD40025810 773.90$
STANFORD40024105,STANFORD40024113 1,497.65$
STANFORD10089411 2,021.04$
STANFORD40030849 415.35$
STANFORD40030229 144.82$
STANFORD40025772 2,174.84$
STANFORD40024342,STANFORD40024377 1,686.82$
STANFORD10079050,STANFORD50035045 499.73$
STANFORD10077618 7,772.93$
STANFORD40027562 2,924.41$
STANFORD40026205 2,687.98$
STANFORD40025594,STANFORD40025608 2,457.74$
STANFORD
1007744
8,
STANFORD
6003044
5 1,392.95$
STANFORD40024873 249.90$
STANFORD10100407,STANFORD40025578 948.58$
STANFORD10087524,STANFORD10087532,STANFORD10103147 6,664.77$
STANFORD10084681 554.02$
STANFORD40028631 823.10$
STANFORD10100415,STANFORD40025560 384.14$
STANFORD10084975 5,000.00$
STANFORD10084967 5,000.00$
STANFORD40027198,STANFORD40027210,STANFORD40027236 300.00$
STANFORD10084690 579.85$
STANFORD40024750,STANFORD40024768 1,587.80$
STANFORD10081488 4,000.00$
STANFORD10121455,STANFORD40029280 789.84$
STANFORD10089322 5,000.00$
STANFORD40029727 2,487.06$
STANFORD10087508 7,066.30$
STANFORD10101977,STANFORD10101985,STANFORD10101993,STANFORD10102000 12,186.11$
STANFORD40030075,STANFORD40030083 5,750.00$
STANFORD10077146 89.79$
STANFORD10089780 447.94$
STANFORD10108475,STANFORD10108483,STANFORD40026108,STANFORD40026132,STANFORD40026213 1,919.40$
STANFORD40027864,STANFORD40027880 2,183.17$
STANFORD40025667 1,000.00$
STANFORD10079114 500.00$
STANFORD10082980 280.00$
STANFORD10081887,STANFORD10081895,STANFORD10082298 1,245.96$
STANFORD10079980 172.63$
STANFORD1008656
0,
STANFORD
5000117
5,
STANFORD
5001428
5,
STANFORD
5005291
8 1,001.14$
STANFORD10082530 899.95$
STANFORD10089772 376.63$
STANFORD10089632 4,000.00$
STANFORD10087966 559.28$
STANFORD10078630 300.00$
STANFORD10080732,STANFORD10080740,STANFORD10080759,STANFORD10080767 299.90$
STANFORD10087958 2,636.10$
STANFORD10082190,STANFORD10082514 300.00$
STANFORD10083847,STANFORD10083855 1,250.41$
STANFORD40031802 260.26$
Case 3:09-cv-00298-N Document 2084-1 Filed 09/05/14 Page 10 of 16 PageID 56803
8/11/2019 10th Schedule Re 1st Interim Plan
15/20
ClaimID(s)
PaymenttobeMade
Pursuanttothe1stInterimPlan
STANFORD10092064,STANFORD10092617,STANFORD10097562,STANFORD10097783,STANFORD10098062,
STANFORD10098070,STANFORD10098089,STANFORD10100849,STANFORD10100865,STANFORD10101063,
STANFORD10101152,STANFORD10105522,STANFORD10106243,STANFORD10124845 5,550.02$
STANFORD10094075 1,500.00$
STANFORD10092684 4,500.00$
STANFORD40032361 2,000.00$
STANFORD40031608 699.30$
STANFORD40032450,STANFORD40032515 3,495.67$
STANFORD10093249,STANFORD10093257 1,580.03$
STANFORD10094750 310.00$
STANFORD10110240,STANFORD40033260,STANFORD60030321 106.00$
STANFORD10097660 5,085.39$
STANFORD40033732 3,702.74$
STANFORD10095829,STANFORD10095837 1,936.85$
STANFORD10094784,STANFORD10094792,STANFORD10094806 100.00$
STANFORD10096760 9,481.88$
STANFORD10096493 250.00$
STANFORD10095926,STANFORD10095942,STANFORD10099115,STANFORD10099123 1,500.00$
STANFORD10097333 5,855.49$
STANFORD10099980,STANFORD10099999,STANFORD10100008 5,333.92$
STANFORD10099913,STANFORD10101497 554.70$
STANFORD1009781
3,
STANFORD
1009814
3 508.93$
STANFORD10098178 4,065.47$
STANFORD10099638 1,000.00$
STANFORD40035387,STANFORD40036227,STANFORD40036251 1,444.72$
STANFORD40035344,STANFORD40036154 173.00$
STANFORD10104437,STANFORD10104445 2,748.90$
STANFORD10104739 722.63$
STANFORD10101772,STANFORD10101780,STANFORD10101799 21,261.41$
STANFORD40035891 310.75$
STANFORD10155694,STANFORD40037258,STANFORD40038394 1,499.44$
STANFORD10102884 178.02$
STANFORD10102043 948.21$
STANFORD10128670,STANFORD40036766 1,500.13$
STANFORD10101926,STANFORD10101934 295.45$
STANFORD1010339
2 884.06$
STANFORD10104135,STANFORD10106227 299.40$
STANFORD40038106,STANFORD40038165 1,122.69$
STANFORD10103740 2,239.02$
STANFORD40036065,STANFORD40036073 293.76$
STANFORD40036383 5,000.00$
STANFORD40036618 1,098.40$
STANFORD10099972 9,790.56$
STANFORD10105956 2,830.00$
STANFORD10146253,STANFORD40036120 1,480.88$
STANFORD10102663 2,340.61$
STANFORD10101918 433.28$
STANFORD10106669 2,013.27$
STANFORD60017970,STANFORD60017988,STANFORD60017996,STANFORD60018003,STANFORD60018011 3,022.04$
STANFORD1010692
8,
STANFORD
1010693
6,
STANFORD
1010694
4 9,500.00$
STANFORD10105190 300.00$
STANFORD10105182 4,787.33$
STANFORD60019182 398.03$
STANFORD10107215,STANFORD10107223 1,105.75$
STANFORD60015527,STANFORD60015535 2,000.00$
STANFORD60020016 1,000.00$
STANFORD10107142 4,497.89$
STANFORD10106804,STANFORD10106812 10,527.35$
STANFORD60016841,STANFORD60016850 1,612.74$
STANFORD60017473,STANFORD60017481 4,745.79$
STANFORD10107398 493.03$
Case 3:09-cv-00298-N Document 2084-1 Filed 09/05/14 Page 11 of 16 PageID 56804
8/11/2019 10th Schedule Re 1st Interim Plan
16/20
ClaimID(s)
PaymenttobeMade
Pursuanttothe1stInterimPlan
STANFORD60022396 11,572.66$
STANFORD10105760 3,713.22$
STANFORD10107886,STANFORD10107894,STANFORD10120149 4,491.70$
STANFORD10119221,STANFORD60019921 1,033.38$
STANFORD10107487 966.64$
STANFORD10100989 390.66$
STANFORD10108890,STANFORD10116249 5,758.82$
STANFORD1010695
2,
STANFORD
4002184
0 2,280.47$
STANFORD10108823,STANFORD10108831,STANFORD10108840,STANFORD10108858 4,000.00$
STANFORD10109013 116.25$
STANFORD10115498 2,674.40$
STANFORD10109943 99.66$
STANFORD10111077,STANFORD10111085 1,500.00$
STANFORD10111093 3,000.00$
STANFORD10115064,STANFORD10115072,STANFORD10146300,STANFORD10146318,STANFORD10146326 20,874.52$
STANFORD10111670,STANFORD10111689 1,917.60$
STANFORD10114424 2,000.00$
STANFORD10110224,STANFORD40026612 6,004.86$
STANFORD10114416,STANFORD10114432 3,000.00$
STANFORD10111883,STANFORD10111891 4,981.06$
STANFORD10113525 9,000.00$
STANFORD10107541 822.64$
STANFORD10115331 9,144.98$
STANFORD10113681 1,125.00$
STANFORD10114300,STANFORD10114319,STANFORD10114327,STANFORD10114335 4,773.10$
STANFORD10120734 3,156.12$
STANFORD10114726 2,410.01$
STANFORD10122427 4,070.00$
STANFORD10122214,STANFORD10122222,STANFORD10122230,STANFORD10122249,STANFORD10122257,
STANFORD10122265,STANFORD10122273,STANFORD10122281 2,644.95$STANFORD10123741,STANFORD10123750,STANFORD10123768,STANFORD10123776,STANFORD10123989,
STANFORD10124012,STANFORD10124020,STANFORD10124039,STANFORD10124047,STANFORD10124055,
STANFORD10124071,STANFORD10142274 3,590.74$
STANFORD10118071,STANFORD10118080 2,216.49$
STANFORD10118110,STANFORD10118128 2,216.49$
STANFORD10112170 4,754.69$
STANFORD10121200,STANFORD10121218 4,374.11$
STANFORD10111336 3,243.64$
STANFORD10116478 950.00$
STANFORD10116486 949.90$
STANFORD10116508 1,000.00$
STANFORD10110828,STANFORD10124772,STANFORD10124870 2,935.57$
STANFORD10123385 3,656.42$
STANFORD10116460 101.14$
STANFORD10117636 2,500.00$
STANFORD10116494 299.80$
STANFORD10116036 2,500.00$
STANFORD10117725,STANFORD10150498,STANFORD50049607,STANFORD50051423,STANFORD50103610 4,800.78$
STANFORD10112286,STANFORD10112294,STANFORD10112308,STANFORD10112316,STANFORD10145460,
STANFORD
1014723
3,
STANFORD
1014724
1,
STANFORD
1014725
0 5,785.20$
STANFORD10125264 2,378.54$
STANFORD10118853 648.55$
STANFORD10120203 994.33$
STANFORD10120181,STANFORD10151265 1,124.60$
STANFORD10120190,STANFORD10153365 430.07$
STANFORD10119434 5,708.28$
STANFORD10123008,STANFORD10139311 1,804.38$
STANFORD10123091 1,278.27$
STANFORD10119167 100.00$
STANFORD10120378 388.41$
STANFORD10124861 3,769.37$
Case 3:09-cv-00298-N Document 2084-1 Filed 09/05/14 Page 12 of 16 PageID 56805
8/11/2019 10th Schedule Re 1st Interim Plan
17/20
ClaimID(s)
PaymenttobeMade
Pursuanttothe1stInterimPlan
STANFORD10118861 1,987.00$
STANFORD10128948,STANFORD10147519 358.24$
STANFORD10129219,STANFORD10129561,STANFORD50000969 1,500.00$
STANFORD10127666 209.86$
STANFORD10119159 174.90$
STANFORD10120130 349.80$
STANFORD
1012650
3,
STANFORD
1012651
1,
STANFORD
1012734
8,
STANFORD
1014475
7,
STANFORD
1014476
5 5,000.00$STANFORD10124381 5,932.79$
STANFORD10128646,STANFORD10128654,STANFORD10128662 2,661.74$
STANFORD10121498,STANFORD10129545 2,094.93$
STANFORD10126694,STANFORD10126708,STANFORD10126716,STANFORD10127623 2,931.25$
STANFORD10121544,STANFORD10130349,STANFORD10134662 18,079.47$
STANFORD10131000 227.63$
STANFORD10131744 1,379.51$
STANFORD10128107 129.16$
STANFORD10132783 1,000.00$
STANFORD10130152 2,421.10$
STANFORD10132473,STANFORD10132481,STANFORD10132490,STANFORD10132503,STANFORD10132511,
STANFORD10132520,STANFORD10132538,STANFORD10132546,STANFORD10132554,STANFORD10132562 47,867.34$
STANFORD10132830 626.00$
STANFORD1012989
8,
STANFORD
1015255
5,
STANFORD
5001822
1,
STANFORD
5002852
9 515.68$
STANFORD10077600 20,297.54$
STANFORD10053530 1,298.96$
STANFORD10139834 8,048.11$
STANFORD10137645 2,559.35$
STANFORD10134395,STANFORD10134409,STANFORD10134417,STANFORD10134425 7,395.20$
STANFORD10133984,STANFORD10133992,STANFORD10134000,STANFORD10134018,STANFORD10134026,
STANFORD10134034 3,899.80$
STANFORD10136509 1,916.67$
STANFORD10138170,STANFORD10143025 1,500.00$
STANFORD10134816,STANFORD10134824 2,749.85$
STANFORD10135553 267.34$
STANFORD10141375 262.24$
STANFORD10135030 1,260.00$
STANFORD10135049 3,000.00$
STANFORD10137394 3,996.83$
STANFORD10139320 232.82$
STANFORD10136320 1,000.00$
STANFORD10153217 1,244.58$
STANFORD10142266 1,629.85$
STANFORD10146849 17,438.29$
STANFORD10145958 302.27$
STANFORD10146024,STANFORD10146032,STANFORD10146040,STANFORD10146059,STANFORD60025190 625.40$
STANFORD10147543,STANFORD10151877 150.02$
STANFORD10146270,STANFORD10146946,STANFORD10149228 355.03$
STANFORD10142185,STANFORD10142193,STANFORD10154582,STANFORD10154639 1,493.75$
STANFORD10141766,STANFORD10141790 144.83$
STANFORD10143777 5,000.00$
STANFORD1014693
8 512.61$
STANFORD10153632 730.35$
STANFORD10155236 1,747.18$
STANFORD10146539 112.80$
STANFORD10146458 309.50$
STANFORD10142134,STANFORD10142142 4,526.18$
STANFORD10146440 694.12$
STANFORD10146822 261.81$
STANFORD10147071 269.90$
STANFORD10140336 163.98$
STANFORD10139184,STANFORD10139940,STANFORD10141154,STANFORD10141162,STANFORD10145826,
STANFORD10145834,STANFORD50050826,STANFORD50051954 14,600.02$
Case 3:09-cv-00298-N Document 2084-1 Filed 09/05/14 Page 13 of 16 PageID 56806
8/11/2019 10th Schedule Re 1st Interim Plan
18/20
ClaimID(s)
PaymenttobeMade
Pursuanttothe1stInterimPlan
STANFORD10151699,STANFORD10151702,STANFORD10151710,STANFORD10151729 2,850.00$
STANFORD10147225 1,259.97$
STANFORD10155481 345.03$
STANFORD10147438 850.05$
STANFORD10149945 510.65$
STANFORD10129642,STANFORD60024003,STANFORD60024011 3,757.05$
STANFORD10154957,STANFORD10154973 2,119.64$
STANFORD1015496
5 10,069.47$
STANFORD10155899 4,500.00$
STANFORD10134140 375.00$
STANFORD50006134 2,970.68$
STANFORD10055690,STANFORD10055754,STANFORD10058885,STANFORD10058915,STANFORD10065920 149.59$
STANFORD10158472 699.98$
STANFORD10040552 1,100.00$
STANFORD10077758 13,405.00$
STANFORD60030100 6,279.81$
STANFORD10113010 1,000.00$
STANFORD10073434 1,876.88$
STANFORD10076247,STANFORD50005235 1,000.50$
STANFORD60039680 1,033.93$
STANFORD50034464,STANFORD60039949 1,639.28$
STANFORD50041312,STANFORD60045124 493.61$
STANFORD60044780 5,148.89$
STANFORD60037172 185.62$
STANFORD60039817 1,605.22$
STANFORD60039981 241.66$
STANFORD60039884 422.38$
STANFORD50034448,STANFORD60037946 524.59$
STANFORD60035668 326.26$
STANFORD60031760 3,391.61$
STANFORD60038780 1,192.80$
STANFORD60033282,STANFORD60033290 2,938.85$
STANFORD50018710,STANFORD60046147 957.27$
STANFORD60038993 401.50$
STANFORD60034424 6,204.38$
STANFORD6004375
0 2,364.16$
STANFORD60034882 1,031.02$
STANFORD60039000 271.76$
STANFORD60045426 2,347.89$
STANFORD60045299 359.30$
STANFORD50040952,STANFORD60002751,STANFORD60039965 616.70$
STANFORD60037199,STANFORD60045809,STANFORD60045965 11,157.47$
STANFORD60032863 1,322.05$
STANFORD60032308,STANFORD60037121,STANFORD60037130,STANFORD60037148 17,402.57$
STANFORD60032049 4,924.60$
STANFORD60031697 1,478.58$
STANFORD60033940 3,197.87$
STANFORD60031590 13,605.77$
STANFORD60032871,STANFORD60039779 5,729.05$
STANFORD1012508
6,
STANFORD
6003852
7 251.05$
STANFORD60031883 326.75$
STANFORD10075453,STANFORD60044918 6,560.38$
STANFORD60032286 10,102.58$
STANFORD40013049,STANFORD40013065,STANFORD40013073,STANFORD60039272 1,301.61$
STANFORD50041118,STANFORD60043962 2,215.12$
STANFORD60033983 2,500.00$
STANFORD60034688 144.32$
STANFORD50029010,STANFORD60044462 1,070.70$
STANFORD60042290 1,123.15$
STANFORD10072381,STANFORD60031999 2,510.00$
STANFORD50039040,STANFORD60042400 2,756.85$
Case 3:09-cv-00298-N Document 2084-1 Filed 09/05/14 Page 14 of 16 PageID 56807
8/11/2019 10th Schedule Re 1st Interim Plan
19/20
ClaimID(s)
PaymenttobeMade
Pursuanttothe1stInterimPlan
STANFORD10075038,STANFORD60038063 1,350.00$
STANFORD60040092 300.00$
STANFORD60044225 4,883.41$
STANFORD60032898 6,978.47$
STANFORD60043229 449.90$
STANFORD60032944 109.63$
STANFORD60038942 2,059.39$
STANFORD6004533
7 3,054.05$
STANFORD60042095 2,500.00$
STANFORD60041749 2,172.75$
STANFORD60045310 6,693.74$
STANFORD60044373 787.52$
STANFORD50006061,STANFORD60038128 1,002.14$
STANFORD60043865 800.00$
STANFORD60038772 2,028.23$
STANFORD60043733 3,500.00$
STANFORD60036494 1,500.00$
STANFORD60036850 3,666.67$
STANFORD50000810,STANFORD50016920,STANFORD60037202 1,284.59$
STANFORD60045647 199.90$
STANFORD60039760 2,049.70$
STANFORD
6004280
0 565.24$
STANFORD60045302 645.04$
STANFORD10058940 1,000.00$
STANFORD10130705,STANFORD10137246,STANFORD10137254 2,344.25$
STANFORD40006700 2,770.18$
STANFORD40000540 11,925.28$
STANFORD10039988 1,455.98$
STANFORD10087672 3,950.00$
STANFORD10160540 651.92$
STANFORD10161147 2,232.99$
STANFORD10039600,STANFORD40014851 587.10$
STANFORD10132570,STANFORD10132589,STANFORD10132597,STANFORD10132600,STANFORD10132619,
STANFORD10132627 38,510.08$
STANFORD10054480,STANFORD10054650 152.43$
STANFORD10076042,STANFORD10076050,STANFORD10076069 743.42$
STANFORD1002039
0,
STANFORD
1003271
1,
STANFORD
4000971
8 252.08$
STANFORD10084380 531.59$
STANFORD10103120 1,647.29$
STANFORD10154175,STANFORD10154183 3,424.47$
STANFORD40004392 438.45$
STANFORD10161511 2,500.00$
STANFORD10009434 11,500.00$
STANFORD10158588 3,810.70$
STANFORD10157670 556.68$
STANFORD10158936,STANFORD10158944 1,200.00$
STANFORD10157239,STANFORD10157247 3,010.49$
STANFORD10159924 700.00$
STANFORD10158910,STANFORD10160000 448.72$
STANFORD10029818 1,360.78$
STANFORD1002983
4 10,884.15$
STANFORD10029850 11,008.19$
STANFORD10029869 11,400.00$
STANFORD10029877 3,663.16$
STANFORD10029885 16,336.84$
STANFORD10029893 14,818.06$
STANFORD10029907 2,194.90$
STANFORD10029915 4,307.42$
STANFORD10029826 10,605.46$
STANFORD10029842 11,103.22$
STANFORD10045414 1,116.74$
STANFORD50046403,STANFORD60041790 1,163.47$
Case 3:09-cv-00298-N Document 2084-1 Filed 09/05/14 Page 15 of 16 PageID 56808
8/11/2019 10th Schedule Re 1st Interim Plan
20/20
ClaimID(s)
PaymenttobeMade
Pursuanttothe1stInterimPlan
STANFORD60034475 1,966.75$
STANFORD10161570 450.00$
STANFORD50043846 1,060.18$
STANFORD50046861 621.39$
STANFORD40006719 6,221.46$
STANFORD40025527 1,800.00$
STANFORD50103571,STANFORD60024356 4,647.62$
STANFORD1011594
3,
STANFORD
1011595
1,
STANFORD
1011596
0,
STANFORD
1011597
8,
STANFORD
1012736
4,
STANFORD10127470,STANFORD10127488,STANFORD10127496 2,991.86$
STANFORD10161910 568.00$
STANFORD10142568,STANFORD50019899 511.04$
STANFORD10162038 3,658.18$
STANFORD10121277 7,104.06$
STANFORD10121633 100.00$
STANFORD10064885,STANFORD10066098,STANFORD50047647 1,809.35$
STANFORD10088040,STANFORD10088059,STANFORD50047744 1,254.31$
STANFORD10085653,STANFORD10085661,STANFORD10085670,STANFORD50047833,STANFORD60002417,
STANFORD60006960,STANFORD60009837,STANFORD60011130 1,358.17$
TOTAL 2,462,426.69$