7/14/2019 064 Method Statement for Construction of Air-Cooled Condens
http://slidepdf.com/reader/full/064-method-statement-for-construction-of-air-cooled-condens 1/13
Kier Construction Limited MVV O&M GmBH
22/03/11 Page 1 of 13
METHOD STATEMENT
MVV O&M GmBH,South West Devon Waste Partnership
& Kier Construction Limited
Document No: CMS/ E0788 /002
FOR
Energy from Waste CHP FacilityACC Foundations
DOCUMENT HISTORY
DATE ISSUE COMMENTS ORIGINATOR CHECKEDBY
APPROVEDBY
20/01/11 1 For Planning Application Only SMC22/03/11 2 Minor update following client
commentsSMC
7/14/2019 064 Method Statement for Construction of Air-Cooled Condens
http://slidepdf.com/reader/full/064-method-statement-for-construction-of-air-cooled-condens 2/13
Kier Construction Limited MVV O&M GmBH
22/03/11 Page 2 of 13
CONTENTS
Scope 3
Introduction 3
Construction Sequence 6
Site Set-up 6
Consent to Discharge 8
Preparation of Area 9
Creation of Embankment 9
Installation of Piled Foundations 12
Monitoring 12
PPE 13
Quality 13
Safety 13
7/14/2019 064 Method Statement for Construction of Air-Cooled Condens
http://slidepdf.com/reader/full/064-method-statement-for-construction-of-air-cooled-condens 3/13
Kier Construction Limited MVV O&M GmBH
22/03/11 Page 3 of 13
Scope
This document describes the procedures and method of work for carrying
out the installation of the foundations for the Air Cooled Condenser (ACC)
for the new Energy from Waste (EfW) CHP Facility at Devonport. This ACCcomprises 5 individual units arranged in-line. Given the proximity of the
structures to the existing tidal watercourse known as Weston Mill Creek,
environmental considerations are of a high priority. This is to ensure that
the ecology of the area is not unduly disturbed and that the risk of contamination and pollution to the watercourse is managed and
minimised.
Introduction
The ACC is to be constructed to the east of the main EfW building,
alongside the current site boundary fencing, to the north of the proposedsite. Although not evident from the aerial photo below, this location is
currently a steep slope leading down to the Creek. This means it willfirstly be necessary to build up to level of the ground in order to create a
stable embankment in which to be able to construct the foundations.
Locationof ACC
7/14/2019 064 Method Statement for Construction of Air-Cooled Condens
http://slidepdf.com/reader/full/064-method-statement-for-construction-of-air-cooled-condens 4/13
Kier Construction Limited MVV O&M GmBH
22/03/11 Page 4 of 13
A plan of this area can be seen in the figure above.
Each of the ACC units is supported by steelwork which in turn rests on
piled reinforced concrete foundations. A sketch showing a typical pilelayout and dimensions can be seen on the next page.
7/14/2019 064 Method Statement for Construction of Air-Cooled Condens
http://slidepdf.com/reader/full/064-method-statement-for-construction-of-air-cooled-condens 5/13
Kier Construction Limited MVV O&M GmBH
22/03/11 Page 5 of 13
7/14/2019 064 Method Statement for Construction of Air-Cooled Condens
http://slidepdf.com/reader/full/064-method-statement-for-construction-of-air-cooled-condens 6/13
Kier Construction Limited MVV O&M GmBH
22/03/11 Page 6 of 13
Construction Sequence
Site Set-up
Prior to the project starting, a Site Waste Management Plan (SWMP) will
be drawn up for continuous monitoring throughout the project under theSite Waste Management Plans Regulations 2008.
The project team will be experienced in their designated areas of
responsibility. The integrated project team will ensure the work is
competently supervised in accordance with the detailed construction riskassessment and method statement (RAMS), and Kier Construction
procedures. These will take into account environmental issues in addition
to health, safety and quality.
All personnel will have attended the mandatory Kier Construction and MVV
site inductions and will have been briefed on the contents of the RAMSand Control of Substances Hazardous to Health (COSHH) assessments
relevant to their operations.
The site will be surrounded by a secure 2m high fence to prevent
unauthorised access and to clearly show the area that will be under special
rules owing to its proximity to the watercourse.
These rules will include:• a designated, bunded plant refuelling area situated well away from
the stream,
• use of biodegradable hydraulic fluid in machines that will workwithin the boundary,
• all plant must be inspected daily for fluid leaks and must not beused until any leak is rectified,
• no plant, materials, labour or debris may be allowed to enter the
water,• emergency spill kits must be made available and maintained at all
times.
All site personnel will be briefed on the environmental emergency
response procedure. A flow chart depicting the Kier Environmental
Incident Response Procedure is show on the following page.
7/14/2019 064 Method Statement for Construction of Air-Cooled Condens
http://slidepdf.com/reader/full/064-method-statement-for-construction-of-air-cooled-condens 7/13
Kier Construction Limited MVV O&M GmBH
22/03/11 Page 7 of 13
7/14/2019 064 Method Statement for Construction of Air-Cooled Condens
http://slidepdf.com/reader/full/064-method-statement-for-construction-of-air-cooled-condens 8/13
Kier Construction Limited MVV O&M GmBH
22/03/11 Page 8 of 13
Consent to Discharge
In most cases, consent/permission must be obtained from the relevant
enforcing authority, in this case, the Environment Agency (EA), before
disposing of any water into a storm drain or controlled water course suchas a ditch, stream, pond, lake, river or aquifer. However, if the worksmeet the criteria outlined in the EA’s Regulatory Position Statement for
Temporary Water Discharges from Excavations, it would be possible to
discharge the water without the need for such a permit. In this case, it
must be ensured that all work on site follows the advice in PollutionPrevention Guideline 6 entitles ‘Working on Construction and Demolition
Sites’.
The enforcing authority will require that any water discharged into a drain
or controlled water course is free from pollutants, such as silts or
hydrocarbons. They may, as a condition of the consent, set absolute limitson the amount of suspended solids or other pollutants the discharged
water can contain. Therefore, the quality of the discharged water, for
example that pumped out of an excavation and into a watercourse, mustbe regularly monitored. If it is suspected that the water has become
polluted, the discharge must stop until the source of pollution is identified
and stopped. The frequency of inspections will be agreed with the
regulator. The findings of each inspection will be recorded on the SHE
Monitoring Form.
Therefore temporary run-off collection bund must be constructed before
any disturbance of the ground adjacent to the stream takes place andmust be of a large enough volume to prevent over-topping in the event of
heavy rain and/or discharge being temporarily suspended.
7/14/2019 064 Method Statement for Construction of Air-Cooled Condens
http://slidepdf.com/reader/full/064-method-statement-for-construction-of-air-cooled-condens 9/13
Kier Construction Limited MVV O&M GmBH
22/03/11 Page 9 of 13
Preparation of Area
1. A full survey of existing services (buried or otherwise) will becarried out using a Cable Avoidance Tool, existing statutory
undertakers’ plans and ground-penetrating radar and all services
shall be clearly marked using wooden pegs, or other marks. Before
any excavation can commence, a lined run-off water collection bundwill be constructed at the bottom of theexisting batter to the east of the ACC location
and along the full length of the interface with
Weston Mill Creek. The capacity of this bund
will be determined from rainfall records.Water from the bund will be pumped using a
‘silent’ pump through a series of settlement tanks (e.g. “Silt-
Busters” – see photo) and then carefully discharged into the creek.
The discharge will be regularly monitored for turbidity and other
pollutants before it enters the stream. To prevent solids entering
the bund a barrier will be constructed along the full length which willnot impede rainwater run-off, but will stop earth or stone entering
the bund (e.g. debris netting). This is to be continually monitored
during excavation and filling and manually cleared of materialwhenever necessary.
2. Relocate existing boundary fence closer to the waterway to allow
space for works to be carried out within the secure site perimeter.
Creation of Embankment
1. Existing slope to be built up to required ground level for foundation
construction (level TBC). This is to be done using geo-grid (Tensar)reinforced earth/backfill.
2. The ground is reduced using 360o excavators in accordance with the
earthworks design.
3. The pile locations are set out and 900mm diameter UPVC/concretepipes will be set vertically to terminate at finished ground levels
minus 300mm. These are to act as guide tubes for drilling into the
subsoil / rockhead through the completed reinforced earth and will
further reduce the risk of excess water content dissipating into the
ground water.4. Scaffold tubes are to be erected at base of proposed slope at an
angle of approximately 70 degrees. Wooden boards to be erected
between the poles to create the slope face. This will also provide
two other functions:• To act as a working platform
• To act as a preliminary line of defence (using debris netting)
against soil falling into the stream.
5. Geo-grid (e.g. Tensar) will be laid along the bottom of the area to
be filled and up along the inside face of the wooden boards, withthe trailing end of the geo-grid hanging loose over the other side of
the slope face while the slope is backfilled. Sections will be cut outof the geo-grid to facilitate the laying of the geo-grid around the
guide tubes where applicable.
7/14/2019 064 Method Statement for Construction of Air-Cooled Condens
http://slidepdf.com/reader/full/064-method-statement-for-construction-of-air-cooled-condens 10/13
Kier Construction Limited MVV O&M GmBH
22/03/11 Page 10 of 13
6. After the first layer of geo-grid has been laid, the inside face of the
slope is to be lined by seeded soil bags to a height of half way upthe first backfill layer in order to provide stability to the slope face.
The area behind these bags will then be backfilled using materials
brought in by dumpers, spread using a 360o excavator and
compacted using a sheep’s foot roller.7. Geo-grid is then to be wrapped over the top of the soil bags and fill,
including all the edges of the trench, and held in place with pins.
The length of the geo-grid used is to be determined in order to
provide sufficient frictional force to maintain the slope face. The
use of the geo-grid in this way minimises the amount of materialthat can fall into the watercourse by providing a physical barrier to
large contaminants or pollutants.
8. This procedure to then be repeated until the ground level meets the
required height by extending the scaffold tubes and boards to
increase the height of the slope face to be backfilled.
This process is shown as a series of sketches on the following page.
7/14/2019 064 Method Statement for Construction of Air-Cooled Condens
http://slidepdf.com/reader/full/064-method-statement-for-construction-of-air-cooled-condens 11/13
Kier Construction Limited MVV O&M GmBH
22/03/11 Page 11 of 13
7/14/2019 064 Method Statement for Construction of Air-Cooled Condens
http://slidepdf.com/reader/full/064-method-statement-for-construction-of-air-cooled-condens 12/13
Kier Construction Limited MVV O&M GmBH
22/03/11 Page 12 of 13
Installation of Piled Foundations
1. Before the piling rig is moved into position, a temporary piling matmust be constructed in order to create a stable platform. This willbe in the form of layers of compacted stone to achieve a specified
CBR value.
2. The piling rig will be set up in position and drill down to a specified
depth, dependant upon bearing capacity indicated by the siteinvestigation. In the embankment, 800mm concrete piles will be
rotary-bored through the voids created in the slope by the guide
tubes. In the undisturbed ground below the earthworks, the piles
will be bored directly into the ground in accordance with the pile
design.
3. The concrete for these in-situ piles will be delivered ready-mixed byroad-truck and will be poured into the newly bored hole from a
position that will not allow any concrete to spill near to the
watercourse or its banks. Any concrete that does spill will bedisposed of in a specially designated skip and this skip will also be
used to contain the water used for washing out the mixer. The
skip’s contents will be disposed of as inert waste when all the
cement has cured.
4. Reinforcement will be pushed into the wet concrete and thecompleted pile left to cure before the top is cut off to the correct
level to suit the design and disposed of as inert waste at a licensed
disposal facility in accordance with the SWMP.5. Upon completion of the piling works, the piling mat will be removed
for re-use elsewhere on the site.6. A mini-excavator will then be used to excavate the areas for the
concrete pile caps, which will be cast in-situ.
Monitoring
During these works, the stream and its banks will be continually monitored
so prevent anything falling in and also to assess the stability of the banks.
7/14/2019 064 Method Statement for Construction of Air-Cooled Condens
http://slidepdf.com/reader/full/064-method-statement-for-construction-of-air-cooled-condens 13/13
Kier Construction Limited MVV O&M GmBH
22/03/11 Page 13 of 13
PPE
All personnel accessing the site will be subject to KCL and MVV site rules
and will wear PPE as required.
In addition to the above, all operatives will wear appropriate PPE relevantto the tasks being carried out. These include the mandatory long sleeves,long trousers, safety boots, task-specific gloves, safety helmet, and safety
glasses. Other task-specific PPE may include disposable overalls, face
protection, hearing protection, Wellington boots (for concreting works) or
full body safety harness.
Quality
All project operations will be controlled by Kier’s quality procedures,
industry standards and project specific quality control plans. The quality
control plans will define all project documents required including ITP’s, allapprovals, project hold points, records required, and verifying authorities.
Safety
The following Risk Assessments are relevant to the works and will be
attached to the detailed Method Statement in accordance with the
Construction Phase Plan:
Initial site setup
Manual Handling
Working at HeightWorking over Water
Confined spaces and Rescue planSlips, trips and falls
Power tools and abrasive wheels
Working near mobile plant and plant movement
COSHH Assessment for all hazardous productsWeil's Disease
Lift Plans
All personnel will be fully briefed on the safe method of work, via the use
of a site specific induction and operation specific SMART (Specific MethodAnd Risk Training) briefings, prior to the works being carried out.
All crane movements will be controlled by the lift supervisor and SQEP
banks-men.
The site safety will be continually monitored via weekly site inspections.
These inspections are carried out independently of the project
management and are recorded. Inspection results will be made available
upon request. The Health and Safety Plan will also be continuallyreviewed, the results recorded and changes implemented.