  • ZTEInstallation Requirement

  • Site Cleaned: The site, including the floor, should be cleaned, and no evident dust

    can be felt by hand on any device. There are no sundries (installation materials

    irrelevant to operation, like cartons or remnant cables or wastes left after construction.

  • All sites need install the same,there is no space between each device ,keep it

    like the right side picture showing to us .

  • For the transmission signal cable to DDF,should be circle well and tie to the

    side of the rack ,and make it tied well .

  • Cable compression modules is not installed and all the bolts should be fasten

    well

  • For power cable go through the Right hole , the grounding cable and the Single

    cable go through the left hole ,and every cable should be using the cable tier ,tie

    with the cabinet well .

  • For the redundant fiber cable ,do not reverse the cable like the picture showing

    to us.

  • For the redundant fiber cable ,do like

    the picture showing to us, and must be

    using the flexible hose for protection .

  • At the bottom of the RC rack ,the dust seal module should be

    block by the silicona materials without leaving any blank holes .

  • For any RF connector must be FASTEN BY THE SPANNER .

  • Sliding window in cabinet base,for the power and grounding cables go through to

    the back one ,and the signal cables go through an other one ,which depends on

    the situation on site . Power & Grounding cable and Signal cable using separate

    sliding window .

  • For any bolts should be fasten well and using the right tools to do the

    work ,not only showing in this picture .

  • Cable route should be go with the CABLE

    TRAY.and use tier separate the power and

    signal cables ,tie with the cable tray ,and

    the cable route should be go straight ,not

    like the water waves up and down .

  • For the redundant cables must be well routed and organized ,and tied with

    the cable tray . Careful with the RF cables ,they have the minimum circle

    diameter .the minimum diameter for jumper is 120mm.

  • When there are redundant crimping positions on a ground busbar, one

    bolt can only crimp one terminal. When there are inadequate crimping

    positions on a ground busbar, one bolt can crimp two terminals at most.

  • For the redundant jumper cable ,we need deal with like the picture

    showing to us ,first of all ,keep 200-300mm straight ,then we can circle

    the redundant cables and tie this part nearby .

  • For waterproofing ,especially the jumper connector ,the Badge wrap

    direction should like the picture showing to us ,and the waterproof

    badge should make sure the waterproof in a good performance and

    also the outlook should smoothly going from the big side to the smoler

    ending like the right side of the picture show to us .

  • An

    tenn

    a

    NodeB

    Waterprofing standard procedure ( 1+3+3) .

  • For waterproof,If every output is in use ,we do the standard

    procedure( 1+3+3 ),If output is not in use,we also need to do the

    waterproof ( 1+1+1 ) to ensure the connector will be carefully protected

    for future.

  • The adjacent racks spacing should be aligned between 2 to 3mm.

  • Outdoor grounding terminals on grounding bar should be with

    anti-corrosion treatment.

  • When the tie are tightened, the excessive part should be cut off leaving

    no burr. When used outdoors, the tie end can be reserved properly

    without any burr, but there should not be more than 10 knots.

  • White ties only used for indoor.Black ties only used for outdoor.

  • The labels should be pasted about 20mm away from joints. The

    adjacent labels should be aligned on the same level with the tails

    pointing to the same direction.