ZORLU ENERJI PAKISTAN
56.4 MW
WIND POWER PLANT September 2013
ZORLU ENERGY
GROUP
ZORLU INDUSTRIAL PAKISTAN
Engineering,Design, Construction
Services for Power Plants
ZORLU ENERJI PAKISTAN
•56.4 MW WPP under
construction
•Up to 300 MW Expansion
ZORLU O&M PAKISTAN
Operation and Maintenance
Services for Power Plants
ZORLU ENERGY IN PAKISTAN
WF ZORLU
ZORLU PAKISTAN WPP PROJECT LOCATION
HISTORY OF ZORLU ENERGY WIND POWER PROJECT
2007
• First Wind Mast of 85 m height in Pakistan
• Approvals from Authorities and arrangements for Phase I (6 MW) and Phase II (43.5 MW)
2008 • Construction works starts (Phase I – 6 MW) 5 Vensys 1.2 MW
2009
• Despite the economical crisis, Zorlu Energy completed Phase-I with %100 Equity.
• 6 MW Phase I starts to generate electricity.
2010 • New financing opportunities are arisen.
2011
• Vestas V90 1.8 MW for Phase II and the total capacity increased to 56.4 MW. All approval are renewed. Financial arrangements are done.
2012
• Energy Purchase Agreement and Implementation Agreement signed with Goverrnment of Pakistan. EPC and O&M agreements are signed. The construction is started. Financial Close is done.
2013 • 25th July 2013, COD Achieved (3 months before Required COD)
HISTORY – PHASE I CONSTRUCTION
2007
2009
2008
HISTORY – PHASE I INAGURATION (19th April 2009)
HISTORY – PHASE II CONSTRUCTION
2013
HISTORY 2008 - 2013
2008 2013
PROJECT MILESTONES
2013
Civil Works Jan ‘12 Dec `12 Turbines Deliveries Apr’12 July`12
Mechanical Works Jul’ 12 Nov`12
Electrical Works Sep’ 12 Dec`12 Pre-commissionning Jan’ 13 May`13
Energisation of the Complex May`13 Hot-commissionning and Run Tests May 2013 July 2013
COD 25.07.2013 25.07.2013
PAKISTAN WIND POWER PROJECT DETAILS
Project: Pioneer in Wind Sector (Zorlu Enerji)
Location: Jhimphir, District Thatta
Installed Capacity: 56.4 MW
Expected Generation: 159.010 GWh
Number of Turbines: 5*Vensys 62 1.2 MW (Phase I)
28*VestasV90 1.8 MW (Phase II)
Project Area: 1,148 acres
Project Cost*: 143.7 M $
Debt/Equity: 70:30
Loan Amount: 100.2 M $
Foreign Lenders : IFC / ADB / ETDB
Local Lender : HBL
COD Achieved: July’13
Required COD Date: November 2013
DEVELOPMENT STAGE
ALTERNATIVE ENERGY DEVELOPMENT BOARD (AEDB)
Letter of Intent (LOI) 01 Month
Allocation of Land 3 Months
Feasibility Study
Wind Assessment
Soil Investigation
Environmental Study
Selection of Technology
6 Months
National Electric Power Regulatory Authority (NEPRA)
1. Tariff Determination 03 Months
CENTRAL POWER PURCHASING AGENCY (CPPA)
EPA Negotiations 6 Months
IA Agreement 01 Month
Financial Closure 01 Month
Issues
• Lengthy Procedure
• Lack of Wind
Knowledge
• Communication
Execution
1. Local Issues
2. Security Issues
3. Transport & Logistics Problems
4. Land Issues
Protest at ZEPL Site
2008 2013
BLADE DAMAGE
ILLEGAL SETTLEMENTS
OPERATION PHASE
• EPA COMPLIANCE:
• BILLING
FUTURE DEVELOPMENTS
• LAND ACQUISATION
• SLOW TRANSMISSION
INFRASTRUCTURE
• BAD ROAD INFRASTRUCTURE
• SECURITY ISSUES