97
AFRICAN DEVELOPMENT BANK Original: English Language: English PROJECT: Emergency Power Infrastructure Rehabilitation Project COUNTRY: ZIMBABWE ........................................................................................................................................................ PROJECT APPRAISAL REPORT Date: 15 February 2011 Appraisal Team Team Leader Mrs. E. MUGUTI Senior Power Engineer ONEC.2 3267 Team Members Mr. N. KULEMEKA Principal Social ONEC.3 2336 Mr. Z. BELLOT Investment Officer ONEC.2 2276 Mr. A. OWUSU-ANSAH Consultant Power Engineer ORSA Mr. M. BEDROUS Consultant Environmentalist ONEC.3 Sector Manager Mr. E. B. NZABANITA ONEC.2 3081 Sector Director Ms. H. CHEIKHROUHOU ONEC 2140 Regional Director Mr. E. FAAL ORSA 3775 Mr. F. KANONDA Senior Financial Analyst ONEC.2 2723 Mr. E. ALEMSEGED Senior Water & Sanitation Engineer OWAS 3489 Mr. J.P. MUTSINZI Principal Power Engineer ONEC.1 2300 Peer Review Ms. R ARON Senior Social Development Specialist ONEC.3 2792 Mr. U. DURU Environmental Engineer ONEC.3 3817 Mr. C.VWALA-ZIKHOLE Senior Disbursement Specialist FFCO.3 2746

Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

Embed Size (px)

Citation preview

Page 1: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

AFRICAN DEVELOPMENT BANK

Original: English

Language: English

PROJECT: Emergency Power Infrastructure Rehabilitation Project

COUNTRY: ZIMBABWE

…........................................................................................................................................................

PROJECT APPRAISAL REPORT

Date: 15 February 2011

Appraisal Team

Team Leader Mrs. E. MUGUTI Senior Power

Engineer ONEC.2 3267

Team Members Mr. N. KULEMEKA Principal

Social ONEC.3 2336

Mr. Z. BELLOT

Investment Officer

ONEC.2 2276

Mr. A. OWUSU-ANSAH Consultant Power

Engineer ORSA

Mr. M. BEDROUS Consultant

Environmentalist ONEC.3

Sector Manager Mr. E. B. NZABANITA ONEC.2 3081

Sector Director Ms. H. CHEIKHROUHOU ONEC 2140

Regional Director Mr. E. FAAL ORSA 3775

Mr. F. KANONDA Senior Financial Analyst ONEC.2 2723

Mr. E. ALEMSEGED Senior Water & Sanitation Engineer OWAS 3489

Mr. J.P. MUTSINZI Principal Power Engineer ONEC.1 2300

Peer Review

Ms. R ARON Senior Social Development Specialist ONEC.3 2792

Mr. U. DURU Environmental Engineer ONEC.3 3817

Mr. C.VWALA-ZIKHOLE Senior Disbursement Specialist FFCO.3 2746

Page 2: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

TABLE OF CONTENTS

1. INTRODUCTION 1

2. BACKGROUND 1

2.1 General Background ....................................................................................................... 1

2.2 Institutional Set Up and Governance of Power Sector ................................................... 2

2.3 Overview of the Power Sector ......................................................................................... 2

2.4 Project Linkages & Strategic Context ............................................................................ 4

2.5 Rationale for Bank’s Involvement ................................................................................... 5

2.6 Donor Activities and Aid Coordination .......................................................................... 6

3. PROJECT DESCRIPTION 6

3.1 Project Outcomes ............................................................................................................ 7

3.2 Project Outputs ............................................................................................................... 7

3.3 Project Goals and Objectives ......................................................................................... 7

3.4 Project Design and Detailed Description ....................................................................... 9

3.5 Project Costs and Financing Arrangements ................................................................... 9

3.6 Socio-Economic and Environmental Impacts ................................................................. 9

3.7 Financial Performance……………………………………………………………………… .10

3.8 Environmental and Social Impacts………………………………………………………… 11

4. PROJECT IMPLEMENTATION 15

4.1 Implementation Arrangements ....................................................................................... 15

4.2 Implementation Schedule ............................................................................................... 16

4.3 Procurement Arrangements ........................................................................................... 16

4.4 Disbursement Arrangements and Financial Management ............................................ 16

4.5 Monitoring and Evaluation ............................................................................................ 17

5. PROJECT JUSTIFICATION, SUSTAINABILITY & RISK MANAGEMENT…… 17

5.1 Project Justification 17

5.2 Project Sustainability 18

5.3 Risk Management 18

6. CONCLUSIONS AND RECOMMENDATIONS 19

6.1 Conclusions..................................................................................................................... 19

6.2 Recommendations ........................................................................................................... 20

Page 3: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

i

Annexes

Annex 1 - Map of the Country and Project Location

Annex II – Project Cost Estimate

Annex III - Zimbabwe: Overall Power Infrastructure Rehabilitation Excercice

Annex IV- Implementation Diagram

Annex V – Procurement Arrangements

Annex VI – Project Management Teams

Annex VII – Economic performance

Annex VIII – Environmental and Social Analysis

Annex VIII.1- Environmental and Social Management Management Plan Summary

Annex VIII.2 - TOR for Environmental and Social Audit.

Annex IX.1 - Short Term Emergency Recovery Programme (Strep) – Budget.

Annex IX.2 – Procurement plan

Annex X - ZESA Holding Group Performance Analysis

Page 4: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

ii

Currency Equivalents

January 2011

1UA = US Dollar (USD) 1.54

FISCAL YEAR:

1 Jan – 31 Dec

Acronyms and Abbreviations ADB African Development Bank

ADF African Development Fund

DFID Department for International

Development, UK

EA Executing Agency

EPIRP Emergency Power

Infrastructure Rehabilitation

Project

ESIA Environmental and Social

Impact Assessment

EMA Environmental Management

Agency

FSF Fragile State Facility

GOZ Government of Zimbabwe

GPA General Political Agreement

ICB International Competitive

Bidding

IG

IPP

Inclusive Government

Independent Power Producer

MDTF

MMD

MEPBF

Multi Donor Trust Fund

Mines and Mineral

Development

Macro-Economic Policy and

Budget Framework

MOE Ministry of Environment

MOEP Ministry of Energy and Power

MOF Ministry of Finance

MOWRDM Ministry of Water Resources

Development and Management

MPDE Matrix for Project Design and

Evaluation

NCB National Competitive Bidding

NGO Non-Governmental

Organization

NOCZIM National Oil Company of

Zimbabwe

O&M Operation and Maintenance

QPR Quarterly Progress Report

PA

PMT

Procurement Agency

Project Management Team

REA Rural Electrification Agency

SADC

SAPP

STERP

Southern African Development

Community

Southern African Power Pool

Short Term Emergency

Rehabilitation Program

T&D

UN

Transmission and Distribution

United Nations

USD United States Dollar

WACC Weighted Average Cost of

Capital

WB The World Bank

ZESA Zimbabwe Electricity Supply

Authority

ZETDC

ZERC

Zimbabwe Electricity

Transmission and Distribution

Company

Zimbabwe Electricity

Regulatory Commission

ZPC

ZRA

Zimbabwe Power Company

Zambezi River Authority

Zim-Fund Zimbabwe Trust Fund

Page 5: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

iii

ZIMBABWE: EMERGENCY POWER INFRASTRUCTURE REHABILITATION PROJECT

MPDE MATRIX

HIERARCHY OF OBJECTIVES EXPECTED

RESULTS

PROJECT

BENEFICIARIES

PERFORMANCE

INDICATORS, SOURCE,

PERIODICITY

INDICATIVE

TARGETS,

TIMEFRAME

RISKS, MITIGATING

MEASURES

Goal:

To support the implementation of the

Government’s Short Term Emergency Recovery

Program (STERP) by assisting implementation of

the emergency power infrastructure rehabilitation

program to increase access to affordable and

reliable electricity supply at competitive prices

Impact:

Increased access to

affordable and reliable

electricity supply at

competitive prices.

The Electricity Consuming

public in Zimbabwean

Impact Indicators

Access to reliable electricity;

Source:

ZESA demand and supply statistics

ZETDC customer Accounts

The Electricity consuming

public having access to reliable

electricity by 2012.

Source:

ZESA demand and supply

statistics

ZETDC Customer Accounts

Continued improvements and

stabilization in the political and

socio-economic conditions in

the Country.

Continued injection of

investment capital by GOZ and

ZESA into the Zimbabwean

Power Sector, especially into

ongoing Hwange rehabilitation

Purpose:

1. To improve the reliability of power supply in

an environmentally sound manner through the

rehabilitation of the Ash Plant at Hwange Power

Station (HPS) and the sub-transmission and

distribution facilities in the country.

Outcomes:

Improved Ash handling at

HPS

Improved reliability of

sub-transmission and

distribution networks

Improved electricity

supply to the treatment

plant of Harare City and

other urban water supply

systems.

Improved environmental

management at HPS

The entire electricity

consuming public in

Zimbabwe

Population of Greater

Harare Metropolitan and

other municipalities

HPS staff and impacted

surrounding communities

Outcome Indicators:

Increased generation output.

No of customers to whom service is

restored

Reduction in number of system outages

due to incidents in T&D network

Sources

Operational reports of HPS and ZETDC;

Environmental & Safeguards Reports of HPS

Electricity supply services

restored to about 22,000

customers in various

neighborhoods across the

country by end of 2012.

Efficiency of Procurement

Agent and Implementing Entity

to mitigate implementation risk.

.

Effective involvement of

Project Management Teams s to

contribute to implementation

success;

Adequate measures designed to

control vandalism of T&D

network to ensure network

integrity and security

Improvements in institutional

setup for environmental

management both at HPS and

ZESA to ensure effective

implementation of ESMP

Page 6: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

iv

Activities:

- Provide engineering services;

- Replace and refurbish components in the Ash

handling plant such as slurry pumps, ash pumps,

sluicing water pumps, booster pumps, sealing

water pumps, beilge pumps and overflow sump

pumps; replace 4 discharge lines; 4 clinker

grinders; 1 fluid coupling; 500m of 11kV

transformer cable and 500m of 3.3kV 3-core

cables.

- Reinforce Sub-Transmission and Distribution

Systems

procure and install sixteen sub-transmission level

transformers

Procure and install 800-900 33/0.4kV distribution

transformers

Procure and install 800-900 11/0.4kV distribution

transformers

-Procurement of TA to conduct Environmental &

Social Audit and prepare ESMP for HPS

Procure electrostatic precipitators and air quality

monitoring equipment

Inputs/resources (in millions):

Zim-Fund : USD 35.00m (UA 22.727m)

Total : USD 35.00 m (UA 22.727m)

Outputs:

Fully rehabilitated Ash

Plant at HPS

A rehabilitated T&D

network

Improved operation of

Ash plant for ash removal

and disposal.

Rehabilitated sub-

transmission and

distribution networks

An updated and

comprehensive ESMP for

HPS

Environmental mitigation

equipment

The manufacturers and

suppliers of electro-

mechanical equipment

Consultants in electrical

field and environmental

and social safeguards

Contractors, sub-

contractors, communities

getting jobs.

Electricity consuming

public in Zimbabwe

Hwange Power Station

Output Indictors

Tender documents prepared, Contracts

awarded and works supervised;

Ash Handling Plant at HPS

rehabilitated and refurbished

Restoration of Service to electricity

customers in various neighborhoods

across the country by December 2012.

An updated and comprehensive ESMP Prepared by December 2012

Electrostatic precipitators and air

quality monitoring equipment installed

Source,

ZPC – Operational Reports ZETDC – Operational Report

Number of Engineering

Services Contracts awarded and

signed by Oct.2011.

Implementing Entity assisted by

ZESA constituted Project

Management Teams (PMTs).

Project coordination and

management services

Service restored to 22,000

electricity consumers by

December 2012

Signed contracts and

completion of E&S Audit and

preparation of ESMP by Dec

2012

Equipment installed and

functioning by December 2012

Risk of implementation delays.

To be mitigated through close

follow-up and monitoring of

progress by the Bank through

Procurement Agent and MMU;

Coordination problem will be

mitigated by the PSC to be

established with reps from

stakeholder entities.

Delayed creation of an EMU at

HPP and recruitment of staff.

Risk of implementation delays.

To be mitigated through close

follow-up and monitoring of

progress by the Bank through

Procurement Agent and MMU

Page 7: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

v

Summary

Electricity is fundamental to Zimbabwe’s economic and social development. Electricity supply

interruptions, including shortages therefore have serious repercussions on any efforts of Zimbabwe’s

Inclusive Government (IG) to successfully turnaround the economy and to achieve sustainable economic

and social growth.

In its Short Term Emergency Recovery Program (STERP) of February 2009 and subsequently the current

Three Year Macro-Economic Policy and Budgetary Framework (MEPBF) (2010-12) the Government of

Zimbabwe (GoZ) has prioritized the rehabilitation of dilapidated generation and transmission

infrastructure to restore electricity generation capacity and supply reliability as a key factor in the

economic turnaround strategy. The Government’s efforts are however stifled by resource constraints

owing to the sheer magnitude of financial resources required for infrastructure rehabilitation generally

and for power infrastructure in particular which is estimated at about USD 1.0 billion.1

The Zimbabwe Multi-Donor Trust Fund ( “Zim-Fund”) established on 31 May 2010 by a group of donors

and administered by the African Development Bank to complement the on-going Analytical Multi-Donor

Trust Fund (“AMDTF”), administered by the World Bank, seeks to contribute to the Government’s

economic recovery efforts through infrastructure rehabilitation amongst others.

The proposed Emergency Power Infrastructure Rehabilitation Project will improve the provision of

adequate and reliable electricity in an environmentally sound manner by the rehabilitation of the Ash

Handling Plant at the Hwange Power Station (HPS) and the power transmission and distribution facilities

in the country. The project comprises the refurbishment of the Ash Plant and replacement of Sub-

Transmission and Distribution level infrastructure throughout the country. The project will also generate a

comprehensive environmental and social management plan ESMP for the HPS that will help reduce the

negative environmental effects of the coal fired power station when implemented. Improving availability

of grid electricity reduces the demand for firewood from urban households. A typical urban household in

Zimbabwe uses electricity for cooking and water heating. Frequent power outages have seen areas around

the urban centres being deforested from tree cutting for firewood. In addition business entities

increasingly rely on diesel power generation which pollutes the local environment and yields higher

carbon dioxide emissions than grid electricity since the generation systems in Zimbabwe is mixed hydro

and thermal. Most of the electrical equipment being refurbished will achieve higher energy use

efficiencies and therefore consume less energy when they are re-commissioned.

The total project cost is estimated at USD 35.00 million (UA 22.727 million) and will be financed solely

from the Zim-Fund. Zim-Fund resources of USD 14.87 million (UA 9.656 million) will finance the

rehabilitation of the Ash Plant at the Hwange Thermal Power Station while an additional USD 14.96

million (UA 9.714 million) finances the rehabilitation of sub-transmission and distribution networks. A

further USD 5.17 million representing the cost of Environmental consulting services for the design of an

ESMP for HPS, environmental impacts mitigation equipment as well as Engineering Supervision and

Project Accounts Auditing will also be provided by the Fund. The works will be implemented over a

period of 21 months under the supervision of an engineering supervision consultancy- the Implementing

Entity, assisted by Project Management Teams (PMTs) at HPS and ZETDC for the generation and T&D

components respectively. Procurement of all goods, works and services will be handled by a Procurement

Agent (PA) hired by the Bank on behalf of the Government of Zimbabwe. The project will receive

overall guidance from a steering committee to be constituted as elaborated in section 4.1.6.

1 Short Term Emergency Recovery Programme (STERP) Budget is presented in Annex IX

Page 8: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

1

1. INTRODUCTION

1.1 Physical infrastructure and the related soft infrastructure systems are the means through which

trade and other social – economic activities take place and at the same time act as building blocks

towards economic development. Zimbabwe faces a number of Infrastructure challenges due to lack of

resources for maintenance and new investments. Power supplies for instance are only 40% of installed

capacity, and provide about half of national peak demand, even with the reduced economic activity

engendered by the political crisis in the country. Currently, the country is unable to meet its electricity

requirements despite import of about 300 MW to supplement local generation and has resorted to daily

load shedding to address the problem. The rehabilitation of key power sector assets in the generation,

transmission and distribution systems has been identified as the fastest and least cost option for

restoring capacity to increase electricity supply in order to meet current electricity demand and enhance

system stability. Similarly, it is important to strengthen the revenue collection capability of the

electricity utility to enable internal mobilization of resources for the maintenance of the power system.

1.2 Following the signing of the Global Political Agreement (GPA), the Inclusive Government’s

(I.G.) agenda was defined by The Short Term Emergency Recovery Program (STERP) of February

2009. A key priority area of STERP was the rehabilitation and upgrading of the country’s power sector

infrastructure. Completion of ongoing rehabilitation works at the Hwange thermal power station and

rehabilitation of transmission and distribution infrastructure were specifically identified as critical

interventions underpinning the success of the plan. At the close of program implementation in

December 2009, a review of the STERP indicated very limited progress made on infrastructure

restoration, due to inadequate funding.

1.3 The STERP was followed by a three year Macro-Economic Policy and Budget Framework

(MEPBF) (2010-2012), which aims at building on the gains of the latter and achieving rapid and

sustainable economic growth and development. The MEPBF has again prioritized the rehabilitation,

and upgrading of infrastructure including that of water supply, sanitation, power, transportation and

telecommunication. Since 2009 the IG has made resources available to the electricity utility - ZESA to

address critical needs at two important generation assets; the Hwange and Kariba Power Stations as

well as support some transmission and distribution system improvements. However, these are

inadequate compared to the resources required for rehabilitation of both generation and transmission

systems to restore operational capacity and system reliability and stability.

1.4 It is against this background that a number of Donors have established a Multi-Donor Trust

Fund (Zim-Fund) to provide additional resources required to assist the IG of Zimbabwe to continue

with emergency rehabilitation works in various sectors in order to restore the services in the country

and boost economic recovery. The Bank has been mandated to administer the Zim-Fund from which

assistance to the proposed Emergency Power Infrastructure Rehabilitation Project will be drawn.

2. BACKGROUND

2.1 General Background

2.1.1 In spite of imports of about 35% of its power requirements from Mozambique, South Africa,

Zambia and the Democratic Republic of Congo, the country continues to face power supply deficits

due to under-performance of its generation facilities as a result of obsolescence of plant and equipment.

Power import now places significant constraint on the already strained foreign currency availability.

Page 9: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

2

2.2 Institutional Set Up and Governance of Power Sector

2.2.1 The Ministry of Energy and Power Development has oversight responsibility for the energy

sector with a mandate for policy formulation, performance monitoring, regulation, development and

promotion of renewable energy. The Ministry also supervises and oversees the National Oil Company

of Zimbabwe (NOCZIM) and Zimbabwe Electricity Supply Authority.

2.2.2 Since 2002, the GOZ through the Electricity Act and the Rural Electrification Fund Act both of

2002 has pursued a reform agenda that has led to the unbundling of the electricity company into ZESA

Holdings and its subsidiaries, Zimbabwe Power Company (ZPC) and Zimbabwe Electricity

Transmission and Distribution Company (ZETDC). The reforms also led to the creation of a Rural

Electrification Agency and an electricity regulator, the Zimbabwe Electricity Regulatory Commission

(ZERC). Although reforms were meant to encourage private sector participation through Independent

Power Producers (IPPs), there has been limited investment from private participants thus far. The

power sector is therefore dominated by ZESA Holdings who through its subsidiaries ZPC and ZETDC,

imports, generates and distributes electricity in the country.

2.2.3 Recent reform in the power sector has not yielded much result, particularly that of attracting

Independent Power Producers due the uncertainties in the political climate. Investor confidence in the

sector however is beginning to grow. According to the Minister of Energy and Power Development,

Zimbabwe has licensed five independent power producers whose projects are aimed at helping a

struggling power sector by doubling current electricity output to 4,450 megawatts versus the current

2,000 MW capacity.

2.2.4 Other institutional players include the Zambezi River Authority (ZRA) which was established

by Acts in both the Zimbabwean and Zambian parliaments to operate, monitor and maintain the Kariba

dam complex and other dams on the Zambezi within the jurisdictions of the two countries. Coal, coal

bed methane and other energy-related minerals are under the jurisdiction of the Ministry of Mines and

Minerals Development (MMD). The MMD supervises Hwange Colliery Company which owns the

largest operational coal mine in Zimbabwe and has been the sole supplier to HPS until very recently.

2.3 Overview of the Power Sector

2.3.1 Zimbabwe’s power sector plays a strategic role in enabling and promoting economic activity

across the economy, as well as delivering key social services. Due to its geographic location,

Zimbabwe’s power network provides a strategic hub for the transfer of power within the Southern

Africa Power Pool (SAPP). Until 2000 ZESA was amongst the top three performing utilities in sub-

Saharan Africa; today the Zimbabwe power sector has been physically and financially compromised.

2.3.2 The quality and reliability of electricity supply services in Zimbabwe have been affected by the

economic downturn, falling revenue streams for the power sector utility ZESA, lack of investments in

generation, transmission and distribution infrastructure and lack of capacity to manage an aging

infrastructure. These constraints present serious challenges for the power sector in Zimbabwe.

2.3.3 Dilapidated generation infrastructure: Generation infrastructure in the country is rundown as

a result of lack of investments and needs urgent rehabilitation to restore lost capacity. Zimbabwe has

two major power supply sources: the Hwange coal-fired thermal power station with an installed

capacity of 920 MW, and the Kariba South Bank hydro power station with an installed capacity of 750

MW. There are also 3 minor coal fired stations with a combined capacity of 150 MW. Overall installed

generation capacity is about 1960 MW but available capacity presently stands at just over 1100 MW.

Page 10: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

3

The Hwange thermal power plant presently produces between 400-550MW of power out of its 920

MW capacity due to regular failures of components in both the generation blocks as well as common

auxiliary facilities and lack of spares for maintenance. Current national peak demand is estimated at

between 1800 and 2100 MW resulting in power supply shortfalls of between 700 and 900 MW This

situation has given rise to the ongoing power curtailment exercise whereby between 400 - 600 MW of

national load is shed despite imports of about 300 MW. Zimbabwe Power Supply Capacity is

summarized in Table 1.

Table 1: ZIMBABWE POWER SUPPLY CAPACITY (MW)

Installed Capacity 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009

Hwange 920 920 920 920 920 920 920 920 920 920

Kariba 694 722 736 750 750 750 750 750 750 750

Small Thermals 290 290 290 290 290 290 290 290 290 290

Total 1 904 1 932 1 946 1 960 1 960 1 960 1 960 1 960 1 960 1 960

Dependable Capacity

Hwange 780 780 780 780 780 780 780 780 780 780

Kariba 694 722 736 750 750 750 750 750 750 750

Small Thermals 245 245 245 245 245 245 245 245 245 245

Total 1 719 1 747 1 761 1 775 1 775 1 775 1 775 1 775 1 775 1 775

Available Capacity

Hwange 496 716 659 498 583 579 435 421 388 342

Kariba 511 531 588 701 723 725 711 727 747 743

Small Thermals 133 105 101 43 110 42 26 26 34 18

Total 1 140 1 352 1 348 1 242 1 416 1 346 1 172 1 174 1 169 1 103

Peak Demand 1 986 2 013 2 028 2 007 2 069 2 066 1 904 1 758 1 779 1 800

Supply Deficit -845 -662 -680 -765 -654 -720 -732 -584 -610 -697

Sources: ZESA Operational Statistics 2010

2.3.3 Dilapidated and Vandalized Transmission and Distribution infrastructure: Zimbabwe’s

Transmission and Distribution network is made up of 420kV, 330kV, 220kV, 132kV, 88kV and 66 kV

lines and substations. The distribution system is made up of 33kV, 22kV 11kV and 380/220V lines and

substations. The transmission and distribution lines have a total length of over 120,000 (one hundred

and twenty thousand) km servicing a customer base of close to 600,000 (six hundred thousand)

customers. The Zimbabwe Electricty Transmission and Distribution Company (ZETDC) is responsible

for the development, operation and maintenance of the transmission and distribution network. In

addition, ZETDC is responsible for meter reading, billing, cash collection, and credit control of the

retail business.

2.3.4 During the peak of the economic crisis in the country, a number of transmission line structures

(tower, towers members), transformers, distribution network terminal equipment, overhead line cables

and communication equipment were vandalized by the public, posing a serious challenge to the

stability and reliability of the transmission and distribution system as a whole. Presently about 22,000

customers of the utility in various neighborhoods all over the country are without electricity as a result

of vandalism of some 1,400 distribution transformers scattered within the network. These network

elements need to be replaced while measures are adopted by the utility to prevent potential vandalism

in the future.

Page 11: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

4

2.3.5 Financial insolvency: Due to a long history of sub economic tariffs, and despite recent tariff

adjustments, the utility remains financially insolvent. The impacts of the economic crisis during the last

three years (hyperinflation and price controls) have aggravated the situation, rendering the utility

technically insolvent and unable to pay either its trade creditors (electricity imports) or to service its

external debt. ZESA has external debt amounting to USD 426 million and about USD 98 million of

trade creditor arrears for power imports2. The dollarization of the economy in 2009, receivables

negotiations with large consumers and the rollout of prepaid metering program in 2010 helped the

utility to earn revenues of about USD 40 million per month as compared to USD 6 million per month

earned in the previous year. A top priority therefore is to improve electricity revenue collection by

strengthening and expanding the prepaid metering program and the general billing system.

2.3.6 Legacy Issues. There has been a steady decline in ZESA’s operational, commercial and

financial performance since 2000 when ZESA was collecting about 97% of what it billed for energy

sales, with customer receivables standing at 32 days. The macro-economic situation of the past several

years, characterized by hyperinflation and price controls, lack of access to domestic/foreign financing,

and the downturn in economic activity, has left the power sector struggling to free itself from a huge

financial burden and degradation of physical assets. ZETDC and ZPC were struggling to reach a break-

even position on a cash-flow basis in 2009. The most significant financial consequences/legacy issues

are the increasing level of unpaid foreign debt and trade creditor arrears to regional utilities, and the

quality and collectability of customer accounts receivable. Additionally, there has been a massive

“brain drain” which led to a deterioration of institutional capacity that gradually eroded ZESA’s prior

reputation for efficient management and financial practices. ZESA has begun to rebuild its capacity

through a vigorous training program, but will require time and more resources to regain its former

competencies.

2.4 Project Linkages & Strategic Context

2.4.1 In February 2009, the Southern African Development Community (SADC) brokered political

solution (the Global Political Agreement-GPA) led to the formation of an IG which moved quickly to

prepare the STERP. The key priority areas of STERP included: the economy, infrastructure, social and

human rights. On infrastructure, the STERP prioritized the upgrading of the country’s electricity

generation, transmission and distribution infrastructure. Completion of the rehabilitation of Hwange

power plant and rehabilitation of transmission and distribution infrastructure was specifically identified

as a critical factor underpinning the success of the plan. It was in this context that the Government

requested the Bank’s financial assistance for the rehabilitation of Hwange thermal power plant and

transmission and distribution facilities all over the country. The STERP came to a close at the end of

2009. A progress review of the program revealed that significant gains were made in some areas

particularly those relating to the economy, including inflation reduction, resuscitation of business

activity, elimination of price distortions, better management of public resources, normalization of

financial services, dialogue with the international community, as well as confidence building. Limited

progress was however made in the restoration of basic services such as water supply and sanitation and

power supply, largely due to inadequate funding which seriously constrained infrastructure

rehabilitation initiatives. This project is targeted at enhancing power infrastructure restoration.

2.4.2 Since 2009, the IG has made resources available to ZESA to address critical needs at both

Hwange and Kariba Power Stations as well as support some transmission and distribution system

improvements. The resources required for rehabilitation of both generation and transmission systems

2 Source: ZESA Financial Statement: September 2010

Page 12: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

5

are massive, estimated at about USD1.0 billion. Resources availed by the IG so far have resulted in

some improvement but these are still too little compared to requirements for achieving operational

capacity and system reliability and stability. This project is an effort to augment infrastructure

rehabilitation resources and complement government initiatives in this sector

2.5 Rationale for Bank’s involvement

2.5.1 Zimbabwe has been under non-accrual status with the Bank Group since 2000 when it started

accumulating arrears on its loans repayments. Although the Bank had to suspend all its operations in

the country because of this status, it has remained engaged through policy and arrears dialogue and

provision of humanitarian assistance. Since the imposition of sanctions, the Bank has only been able to

provide the country with humanitarian assistance in response to food crisis in 2002 and 2005 and

cholera outbreak of 2008.

2.5.2 Zimbabwe has also been isolated from much of the international community and International

Financial Institutions due to the political situation that has prevailed in recent years, and will need

support on reengagement. Consistent with the Bank mandate, the GOZ has requested the African

Development Bank (ADB) to play a leading role in efforts to revitalize the Zimbabwean economy.

2.5.3 In response to this request, the Bank in April 2009 prepared a Short Term Strategy for

Zimbabwe anchored on supporting the IG in the implementation of the STERP in a non-financing role

within the broader donor effort, and with the eventual goal of full reengagement with Zimbabwe. The

Strategy centered on unlocking resources to develop and support a recovery and reform program, while

collecting data on infrastructure needs which would support the formulation of immediate and medium

term action plans. In the long term, the strategy is aimed at stimulating a strong private sector led

economy, including through strategic investment in selected infrastructure and capacity building. These

were identified as key in supporting social and economic activities, and thereby realizing Zimbabwe’s

full potential as a self-sustaining country. A needs assessment carried out jointly by the ADB with the

World Bank and UN identified the rehabilitation of the Hwange Power Station (HPS) and the

transmission and distribution system as urgent priority projects. After the needs assessment, the Bank

was given the lead role in the sectors within the infrastructure cluster.

2.5.4 The proposed Emergency Power Infrastructure Rehabilitation Project to be supported by a

Grant from the Multi Donor Trust Fund managed by the Bank therefore is consistent with the Bank's

strategy of supporting the IG in the implementation of outstanding priorities of the STERP and new

priorities of the current MEPBF. The project is also in response to the mandate given by the Donor

community to the Bank, to play a lead role in the infrastructure sector in Zimbabwe. It is consistent

with the Bank's short-term goal of unlocking resources to develop and support a recovery and reform

programme in Zimbabwe while at the same time using data collected on infrastructure needs to

formulate and implement immediate and medium term action plans. Strategically this provides a way

for the Bank to re-engage at a practical level with Zimbabwe. It is consistent with the Bank's longer-

term aim for the revival of a strong private sector led economy through amongst others, strategic

investment in selected infrastructure, and capacity building. Finally, the project supports the objectives

of the Government's Draft Energy Policy such as (i) increasing access to affordable energy services to

all sectors of the economy, (ii) improving capacity in the various players in the energy development

and delivery chain and (iii) managing energy related environmental and social impacts.

Page 13: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

6

2.6 Donors Activities and Aid Coordination

2.6.1 As part of the process for re-engagement by the donor community in Zimbabwe, a Joint

“Scoping” Mission was undertaken in April 2009 by ADB, EU, the United Nation agencies (UN) and

the World Bank (WB) to work on the development of an appropriate framework for re-engagement,

subject to performance from the IG and satisfactory agreements on a number of issues, including the

arrears that the country has with ADB and other institutions.

2.6.2 The objective of the Scoping Mission were to: (1) agree on priority sectors; (2) agree on the

modus operandi for sector specific Joint Needs Assessment missions to be undertaken by sector

specialists from the various institutions; (3) identify required resources, both financial and technical

expertise and (4) identify modalities and implications of other processes, such as the ongoing dialogue

between the government and partner countries.

2.6.3 Since then, the World Bank and UNDP have organised semi-annual donor coordination

meetings with all the main donors to discuss issues pertaining to the political and economic situation

and where possible propose coordinated interventions in various sectors. Donor assistance has recently

focused on humanitarian, governance and HIV/AIDS related activities, and the funding is mostly

channelled through NGOs and the UN System.

2.6.4 The selection of priority sectors was largely guided by the STERP. The Electricity sector was

identified as a key sector in this plan. The STERP estimated the funding requirements for the sector at

USD 1 billion over the medium term, representing 12% of the estimated funding requirements across

all sectors of the economy (USD 8.4 billion)3.

2.6.5 The African Development Bank has been requested by a group of donors to assist Zimbabwe to

establish and administer the Zimbabwe Multi-Donor Trust Fund (the “Zim-Fund”), as a complement to

the on-going Analytical Multi-Donor Trust Fund (“AMDTF”), administered by the World Bank. The

purpose of the Zim-Fund, is to contribute to early recovery and development efforts in Zimbabwe by

mobilizing donor resources and promoting donor coordination in Zimbabwe, so as to channel financial

assistance to such efforts. Complementary to other existing funding mechanisms, the thematic scope of

the Zim-Fund focuses initially on infrastructure investments in the areas of water & sanitation and

energy. To achieve these goals, financial and technical support to activities that are consistent with the

Government’s recovery priorities; mobilization of pooled donor resources based on a common

understanding of the country’s recovery needs and effective coordination and complementarities with

other related activities funded outside the trust fund are critical.

3. PROJECT DESCRIPTION

3.1 The Project Outcomes

3.1.1 The main outcomes of the project include (i) improved environmental management at HPS (ii)

improved reliability of power transmission and distribution infrastructure in the country, (iii) improved

electricity supply to the treatment plant of the Harare city water supply as well as urban water supply

systems with a possible contribution to the reduction in the incidence of cholera and other water related

diseases.(iv) reduction in greenhouse gas emissions currently resulting from extensive tree felling for

firewood used by urban households and greenhouse gas emissions resulting from system inefficiency

and frequent failures. (v) reduced transmission and distribution losses due to rehabilitated and upgraded

equipment hence increased system efficiency.

3 Financing requirements identified in the STERP are included as Annex 1

Page 14: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

7

3.2 Projects Outputs

3.2.1 Project outputs will be a refurbished Ash Handling Plant at HPS and reinforced sub-

transmission and distribution networks which will improve system reliability and allow the restoration

of supply services to about 22,000 customers in various neighborhoods across the country who

presently have no access to electricity services. There will also be a new ESMP for HPS that is based

on a thorough audit of the plant and its impacted environs.

3.3 Project goals and objectives

3.3.1 The overall goal of the proposed project is to support the implementation of the Government’s

Short Term Emergency Recovery Program (STERP) through increased access to affordable and

reliable electricity supply at competitive prices by implementation of the emergency power

infrastructure rehabilitation program.

3.3.2 The objective of the project is to assist improve the provision of adequate and reliable power

supply in an environmentally sound manner through the rehabilitation of the Ash Plant at HPS and the

sub-transmission and distribution facilities in the country.

3.3.3 The project will also help to improve the reliability of electricity supply to the treatment plant of

the Harare city water supply and other urban water supply systems and thereby help prevent another

cholera outbreak in the country. The project creates synergies with the “Emergency Water Supply and

Sanitation Rehabilitation Project” also financed by the ZimFund.

3.4 Project design and detailed description

3.4.1 The project is a segment of an ongoing power sector infrastructure rehabilitation program

identified by ZPC and ZETDC, subsidiaries of ZESA mandated to operate and maintain the Hwange

Power Station and T&D networks respectively. Components included in the proposed project are

selected from a list of critical interventions that need to be conducted in the rehabilitation of power

infrastructure to bring the power system to an acceptable level of performance. The full list of activities

and their associated costs under the program is presented in Annex III. During preparation and

appraisal of the Zim-Funded EPIRP, field visits were made to project sites at the HPS and consultations

held with stakeholders at ZESA, ZPC and ZETDC, the Energy ministry and the Finance ministry to

identify components in the list of activities that can be supported by the limited funds available. The

project has been defined to comprise five main components: (A) Rehabilitation of the Ash Handling

Plant at Hwange Thermal Power Station and (B) Rehabilitation of sub-transmission and distribution

facilities (C) Conduct of an Environmental and Social Audit and implementation of re-designed

Environmental and Social Management Plan, (D) Project Supervision and (E) Project Accounts

Auditing. Detailed equipment to be procured under components A and B are presented in Annex II.

The shaded components in Annex III indicate how the interventions being financed by the Zim-Fund

dove-tails into the Government/ZESA’s overall power sector rehabilitation exercise.

3.4.2 (A) The rehabilitation of the Ash Plant is critical for the continuous operation of generating

units at the Hwange Power Station by preventing the build-up of Ash in the boilers that can lead to a

complete shutdown of generating units. It is also necessary for the reduction of the negative

environmental impacts as a result of poor ash handling. The process of generating electricity in a coal-

fired plant involves the delivery of coal by conveyor belts from opencast mines to the plant, pulverizing

coal in coal mills associated with the generating units and blowing the pulverized coal by primary air

fans into the furnace where it is mixed with hot air and burnt to raise steam from water contained in the

boiler tubes. The steam drives steam turbines to produce electricity in a generator. The by-product of

Page 15: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

8

the burnt coal, ash, then builds up in the furnace and needs to be pumped out, mixed with water and

discharged through Ash Lines to an Ash dam.

3.4.3 Presently, the Ash Plant for the four units of Stage I has only 1 pump out of 3 in service while

that at Stage 2 it has one pumping line available out of 2 in service. These plants are available 50% of

the time. Additionally only 2 lines out of 4 that take ash to the ash dam are working, restricting the

capacity to move ash from the boilers to the disposal dams and leading to an ash build-up in the boilers.

Frequent breakdowns of the remaining Ash plant always necessitate the shutdown of generating units

in order to prevent ash build up.

3.4.4 The rehabilitation of the Ash Plant comprises the replacement or refurbishment of slurry pumps,

ash pumps, sluicing water pumps, booster pumps, sealing water pumps, beilge pumps and overflow

sump pumps, all complete with motors and spares; replacement of 4 discharge lines; 4 clinker grinders

with spares; 1 fluid coupling with spares; 500m of failed 11kV transformer cable and 500m of damaged

3.3kV 3-core cables. The refurbishment of the ash plant will contribute to increase the availability of

generating units and also help reduce the negative environmental impacts of the plant such as reducing

atmospheric ash within the plant and its vicinity.

3.4.5 (B) Rehabilitation of Sub-Transmission and Distribution facilities – The rehabilitation of the

Sub- Transmission and Distribution system is essential for improving the reliability of electricity

supply to consumers in Zimbabwe. As elaborated under section 2.3.3 and 2.3.4, about 22,000

customers of the utility in various neighborhoods all over the country are without electricity as a result

of vandalism of some 1,400 distribution transformers scattered within the network. Also vandalized are

other network elements like transmission line towers and overhead distribution cables. These network

elements need to be replaced while measures are adopted by the utility to check future vandalism.

Activities included in this component are:

SUB-TRANSMISSION SYSTEM REINFORCEMENT: This comprises the installation of six

transformers and replacement of sixteen (16) faulty circuit breakers (16x132kV breakers) at various

sub-transmission substations. A new transformer will also be installed to boost power supply to the

Harare city water treatment plant to augment the reliability of water supply to the city.

DISTRIBUTION SYSTEM REINFORCEMENT: In the distribution network between 800 and 900

33/0.4kV distribution transformers and the same quantity of 11/0.4kV distribution transformers will

be procured and installed. The replacements have been necessitated by the large number of

distribution transformers that were vandalised during the peak of the economic crises in Zimbabwe.

Transformer oil was drained from a number of transformers resulting in damage to the

transformers. Additionally, about 460 km of 11kV and 33 kV Underground Cables as well as

Aluminium Conductors Steel Reinforced (ACSR) and & HAD overhead conductors will be

installed. The reinforcement of the distribution system will restore supply services to some of the

22,000 existing customers who are currently in darkness dues to vandalism of distribution

infrastructure.

3.4.6 (C) Environmental Consultancy: - Consultancy will be procured to carry out an Environmental

and Social Audit of the whole Hwange power plant and its operations and a comprehensive

Environmental and Social Management Plan prepared for the plant.

3.4.7 (D) Consultancies for Supervision - This component includes a consultancy for the supervision

of works at HPS and the T&D system.

3.4.8 (E) Consultancy for Project accounts auditing

Page 16: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

9

3.5 Technical solution retained and other alternatives explored

3.5.1 An alternative solution that was explored was to apply all the Zim-Fund resources available for

the Power sector to interventions in the electricity Transmission, Sub-transmission and Distribution

networks. This alternative presented some attractions such as the opportunity to rehabilitate the 330 kV

transmission level substations at Warren and Chertsey by the installation of two transformers at these

stations as well as replacement of seven (330kV) circuit breakers at these and other high voltage

stations. Additionally, this alternative would have provided for the replacement of obsolete and

malfunctioning system protection and communication equipment in the grid such as protection relays

and remote terminal units that could contribute greatly to system stability and reliability. This

alternative would have limited the Zim-Fund interventions to only the Transmission and Distribution

System and allowed for easier project management and measurement of impacts. However, this

alternative was rejected because of concerns that had been expressed at project inception about ash

handling at the Hwange Power Station, particularly about the Ash dam whose safety was called into

question at the time and was said to pose some health hazards to the communities at the plant. It was

therefore considered expedient to include some interventions in the Ash handling at HPS, hence this

alternative was rejected.

3.5.2 A second alternative which included the provision of environmental monitoring equipment and

training of environmental monitoring staff at HPS, ZESA and the Zimbabwean environmental

management agency EMA could not be pursued purely for reasons of resource limitation. This

alternative aimed at addressing air pollution at HPS by providing proper monitoring equipment and

training. At project inception, air pollution resulting mainly from oxides of Sulphur, Nitrogen and

Carbon as well as Mercury and dust emitted from the stacks during the combustion of coal, was

identified as posing health hazards to local ecosystems, wildlife, workers and the surrounding

populations. This alternative was also shelved with the hope that it can be re-visited when additional

funds are made available for power sector interventions.

3.5.3 The technical solution adopted partially addresses environmental concerns at HPS by

generating a comprehensive ESMP which will provide the guidelines for any future environmental

management at HPS. A well-functioning Ash plant at HPS will also improve plant availability and

therefore power availability for the consuming public. This solution further addresses some of the

bottlenecks in the transmission and distribution networks that will allow industrial, commercial and

domestic customers to have access to electricity once supply is made available. It is hoped that,

ongoing rehabilitation works being implemented by the Government and ZESA will progress as

scheduled and deliver the expected outcome of increased power supply, which will allow a reduction in

the power curtailment exercise and help industries to resume operating at their full capacities and

thereby boost economic growth. Furthermore, it is expected that ongoing interventions at the ash dam

being funded by Government will be completed to address the environmental, health and safety

concerns identified at project inception.

3.6 Project cost and financing arrangements

3.6.1 The total cost of the Emergency Power Infrastructure Rehabilitation Project (EPIRP) is

estimated at USD 35.00 million (UA 22.727 million) net of taxes and duties, and excluding the cost of

procurement services which will be financed separately through the Fragile States Facility (FSF). The

total project cost is based on recent prices obtained from suppliers during similar maintenance

activities. Table 2 summarises aggregate costs of the various project components described under

section 3.4 while detailed cost break down is provided in Annex II.

Page 17: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

10

Table 2a: - Project Cost by Component (USD million)

Table 2b: Project Cost by Category of Expenditure (USD million)

3.6.2 The project will be fully financed from the Zim-Fund. The tentative financing plan is

summarized in Table 3 below while details are given in Annex IV.

Table 3: - Financing Plan by Component (USD million)

3.6.3 Table 3 indicates that, Zim-Fund resources will mainly finance rehabilitation of the Ash Plant at

the HPS at a cost of USD14.870 million and the rehabilitation of the sub-transmission and distribution

networks at an additional cost of USD 14.960 bringing the total expenditure on works to USD 29.83

million. A further USD5.17 million will be required for services that include consultancies for

environmental and social audits, engineering supervision and project accounts auditing as well as the

purchase of environmental monitoring equipment and capacity building.

3.7 Financial Performance

3.7.1 ZESA Holdings’ operating environment for the year ended 31 December 2009 improved

significantly from that obtaining in 2008 mainly because of the introduction of a multicurrency system

which saw inflation tumbling and many economic and business variables stabilising. However as the

year progressed new challenges crept in, the major one being liquidity problems that seriously inhibited

ZIMFUND Total

A. Rehabilitation of Ash Plant at Hwange Power Station 14.870 14.870

B. Sub-Transmission & Distribution reinforcement 14.960 14.960

C. Consultancy for Environmental and Social Audit 1.200 1.200

D. Consultancy for Project Supervision 1.500 1.500

E. Consultancy for Project Accounts Audit 0.070 0.070

F Environmental Monitoring and Capacity Building 2.400 2.400

Total 35.000 35.000

Category of Expenditure (USD million) (UA million)

A. Works 32.13 20.863

B. Services 2.87 1.864

C. Miscellaneous 0.000 0.000

Total 35.000 22.727

ZIMFUND (UA million)

Rehabilitation of Ash Plant at Hwange Power Station 14.870 9.656

Sub-Transmission & Distribution reinforcement 14.960 9.714

Consultancy for Environmental and Social Audit 1.200 0.779

Consultancy for Project Supervision 1.500 0.974

Consultancy for Project Accounts Audit 0.070 0.045

Environmental Monitoring and Capacity Building 2.400 1.558

Total 35.000 22.727

Page 18: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

11

economic activity. The group adopted the United States Dollar (USD) as its functional currency with

effect from 1st February 2009. Year on year inflation rose to about 231,000,000% in July 2008 after

which compilations were suspended, but tumbled to an average of 7.9% in 2009 as availability of

goods improved mostly through imports. This brought about stability in planning and operations of the

Group.

3.7.2 Tariffs were adjusted to 7.53 USc/kWh from almost zero in USD terms after February 2009,

resulting in defaults on the part of many customers who found the new rates too high due to a

combination of the global financial crisis and liquidity challenges in the local economy. This

negatively impacted the Group’s liquidity position. However, the rollout of a prepayment meter

program in 2010 helped the utility to earn revenues of about USD 40 million per month as compared to

USD 6 million earned in previous months. As at 30 September 2010, total loans on ZESA’s books

amounted to US $426.6 million, comprising 72% foreign debt of USD309.1 million and 28% local

debt of USD117.5 million Out of the total loan amount, 93% or USD 395.1 million constitute the

current portion, which represents loan capital repayments falling due within twelve months.

Table 4: FINANCIAL INDICATORS 2010

Profitability Ratios

Return on Sales

Historical Cost

12.13%

Return on Sales 12.13%

Return on Total Assets 4.83%

Return on Capital Employed 4.09%

Acid Test Ratio 0.33: 1

Debtors Collection Period 287 Days

3.7.3 Profitability Ratios: The Return on Sales recorded a positive 12.13%. This shows a favorable

rate of return on sales. However it should be noted that the operating expenditure level is suppressed

due to cash flow constraints.

The Return on Total Assets is a positive 4.83%. This ratio reflects a favorable return on the use of the

group’s assets. However it should be noted that some of the group’s operational assets are due for

replacement.

The Return on Capital Employed is a favorable 4.09%. This ratio shows a fair rate of return on capital.

However the capital is mainly made up of a Non Distributable Reserve which resulted from

dollarization. There is need to enhance the share capital.

3.7.5 Liquidity Ratios: The Group has an unfavorable liquidity position clearly shown by a current

ratio of 0.44:1 and an acid test ratio of 0.33:1. The ratios are well below the recommended standard

ratios of 2:1 (current ratio), and 1:1 (acid test ratio). The Group’s Debtor’s Collection Period is 287

days. This indicates that whilst making a profit as shown in the above ratios and results, the cash flow

position is strained due to the delay in settling of accounts by customers.

3.8 Environmental and Social Impacts

3.8.1 Project Environmental Classification. The envisaged project is situated in Hwange district

which is predominantly a mining district and has, in addition to Hwange Power Station, Southern

Mining Coke Plant, Hwange Coal Gasification Plant, and Hwange Colliery. The project is likely to

induce positive environmental and social impacts, but as a coal-fired power plant, it induces significant

adverse environmental and social impacts. At commissioning in the 80s, the HPS had no legal

requirement for a full environmental and social impact assessment (ESIA). Never-the-less, the

Page 19: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

12

Zimbabwe Environmental Management Agency (EMA) obliged Hwange Power Station, under the new

law to prepare an Environmental and Social Management Plan (ESMP) in lieu of a full ESIA. The

Bank reviewed this ESMP and given the current situation and the planned rehabilitation to be

conducted under this project, which to a larger extent would be positive to environmental and social

impacts, the project has been classified as Category 2 as per AfDB policies and guidelines stipulated in

the Environmental and Social Assessment Procedures (ESAP) (See Annex VIII for detailed analysis). It

is however clear that given the condition of the equipment; the Plant has failed to fully comply with

environmental measures stipulated by the EMA; hence a revised/re-designed ESMP has been prepared

to comply with both national requirements and AfDB policies and EMA requirements. The Executive

Summary of the revised ESMP was posted on the Bank’s website on 16 February, 2011.

3.8.2 Environmental Impacts and Mitigation Measures. The project activities will mainly

comprise repairs and replacement of existing equipment and limited civil works. This will have

minimum negative impacts on the local environment with waste and sludge management and disposal

being the significant source of impacts. The ESMP will clearly elucidate the measures to be taken to

protect the environment including observing proper working methods, replacement of destroyed

vegetation, ensuring proper disposal of discarded equipment and materials that may contaminate the

soil and ground water; prevention of nuisance in terms of dust, noise, odour, etc. The project provides

protective clothing for personnel engaged in the laying or cleaning of sludge / sewers and will also look

at fencing and/or covering some of the infrastructure which poses a great danger to humans such as

open manholes and ponds. The project will also provide air quality monitoring equipment and

electrostatic precipitators for the power plant. Among positive outcomes, the project is proposed to

remedy and mitigate a number of impacts due to lack of maintenance of the Hwange power plant. Such

works shall result in (i) significant reduction in air pollutants; (ii) significant improvement to the coal

handling and disposal system; (iii) significant improvement and safety considerations for the Ash Dam

and Ash Dam area; (iv) significant development of capacity building; and (v) significant enhancement

of the environment and health protection of workers and people residing in the surrounding areas.

3.8.3 Environmental and Social Audit. The Bank's environmental guidelines, stipulate that when

involved in financing a retrofitting or expansion project for an existing power generation or industrial

facility with significant social and environmental consequences, an Environmental and Social Audit

should be conducted which will objectively evaluate and obtain comprehensive information on the

sources, causes and impacts on the environment through a systematic, independent and documented

process. The project has, therefore, included in its design, carrying out such as an audit utilizing the

criteria developed in an ESMP against which to evaluate project compliance. The ESMP will also

provide a management and monitoring tool for environmental and social aspects during project

supervision and implementation; and provide information about any past or present impacts resulting

from the project that were not so far anticipated. A provisional sum has been included in the project

cost for the consultants to carry out the audit estimated at US$2 million (Abridged TORs are provided

in Annex VII).

3.8.4 Climate Change. The project supports a coal-fired plant with a technology that results in

production of most Green House Gases (GHG) such as CO2 emissions. However, modifications which

the project targets through refurbishment and rehabilitation will lead to a specific reduction of CO2

emissions. In other words, the reduction of emissions volume per unit of power generated. Although

modifications will lead to environmental improvements, they will also lead to increased availability,

meaning higher coal fuel consumption and an absolute increase of the CO2 emissions. The specific

reduction of emissions however, is considered a key enhancement for the existing technology that

complies with the Bank's policies in promoting sustainable development. Reduction in duration of load

shedding and subsequent reduction in usage of inefficient alternative fuels like firewood, liquefied

Page 20: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

13

petroleum gas, diesel generators, petrol generators and paraffin will be beneficial to the country as a

whole. This will cut production costs, carbon emissions and improve on efficient utilization of fuel.

3.8.5 Frequent power outages encourage households, especially urban households, to use fire wood

for cooking. This has led to deforestation around urban centres with obvious tree loss in the surrounds

of Harare. Such tree loss has led to loss of carbon sinks. Attempt to replant these trees will not achieve

results till urban households have access to a reliable and affordable electricity supply. Households and

other electricity users also rely on diesel generators which yield higher carbon emissions than the grid

in Zimbabwe given that the grid is mixed hydro and coal fired thermal. Equipment that will be

refurbished or replaced will lead to increased energy efficiency which in turn yields lower carbon

emissions. The electrostatic precipitators will also reduce the emissions of SOx & NOx and particulate

emissions, effectively mitigating environmental impacts. Frequent power plant outages at Hwange lead

to increased fuel use for plant start-up (12-16 hours of diesel consumption for start-up and coal

consumption for heating up steam boilers before generation of electricity). Increased reliability of

Hwange Power Station would reduce cold starts and therefore lead to lower fuel use intensity and

carbon emissions.

3.8.6 Gender: The project is not envisaged to have any gender related negative impacts, on the

contrary it will result in improvements that will benefit both men and women at project level and wider

context. At national level, Zimbabwe has set out priorities for gender mainstreaming and empowerment

of women for the period 2008-2012. The National Gender Policy Implementation Strategy and Work

Plan seek to operationalize the commitments to gender equality and women's empowerment. Both

ZESA and ZPC have developed gender consciousness and appointed gender focal points to ensure that

interests of both men and women are taken on board in policy formulation and decision making.

3.8.7 During project implementation, however, women may disproportionately be exposed to the

spread of HIV/AIDS. The sub-contractors to carry out the rehabilitation works are likely to bring in

labor from distant places such as Harare, most likely men without families. The national HIV/AIDS

prevalence rate is at 13.6% but biased towards women4 who are subjected directly by men who tend to

lure girls into unprotected sex, and also to wives who become the victims on the receiving end when

husbands return home infected. The HIV/AIDS Policy of ZPC promotes practices that unite families in

order to reduce the spread of disease and mitigate its effect on the affected individual and his/her

family by creating a supportive environment.

3.8.8 Women’s Employment Opportunities. Currently the Hwange Power Station on average

employs 724 people on regular jobs among which 81 (11%) are women mostly in semi- and unskilled

jobs. While this outcome is as a result of the nature of jobs and remoteness of the site, ZPC is making

an effort to encourage more women to seek non-traditional jobs and take advantage of existing

vacancies which stand at 8% within Hwange Power Station itself. Zimbabwe being a member of SADC

is expected to implement the Gender Protocol which demands that women participation in the job

market should be at par with that of their male counterparts. A Gender Focal point has been appointed

at ZPC headquarters whose job among others is to ensure gender equity in recruitment. The project

will, in addition, ensure that the environmental monitoring training includes 50% women. In the

broader context, women have been impacted by lack of reliable power supply through job losses. Most

women are employed in horticultural and farming industries which have been significantly negatively

impacted.

4 According to Zimbabwe National EPP-Spectrum Estimates, 2009, out of the national prevalence rate of 13.6%, women

represented 60% of it and women at ages between 15-24 represented 77% of the prevalence.

Page 21: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

14

3.8.9 Impact on Domestic Power Needs. An important aspect to be recognized is that women and

girls have suffered most due to lack of reliable electricity at household level. Traditionally, it is the

responsibility of women and girls to fetch water hence effects on water supply caused by lack of

electricity has put a burden on women and girls who have to stand for long hours queuing for water, or

may have to walk long distances in search of alternative sources of water. Therefore, the rehabilitation

project will stand to alleviate the suffering of women and girls and improve their well being. Similarly,

lack of electricity especially in urban areas impacted on women who have had to switch sources of

energy for lighting and cooking to charcoal or wood. This has had negative impacts on women and

girls who have to go fetching wood or charcoal and also who have to endure hazardous kitchen smoke

during preparation of meals. In both instances, women and girls will benefit from time and labor

savings from either queuing or walking for long periods.

3.8.10 Social: The rehabilitation project is likely to bring in direct and indirect; short-term and long-

term benefits to the communities around the project area and to the economy and population as a whole

While the rehabilitation project will impact the surrounding population of Hwange District, it should be

noted that the main project related outcomes and target population will be much wider. The social

services such as water and health have also suffered from the insufficient power generation and supply.

The rehabilitation project will improve availability and reliability of power; improve service provision

by municipalities especially in the area of water supply and health services delivery through reliable

supply of power to water pumping stations.

During implementation and operation, communities shall benefit directly through job creation.

Zimbabwe’s unemployment rate was at 90% (under-employed and disguised) in 2010. Currently HPS

employs 724 people with a vacancy level of 56 against the establishment. During implementation

additional people may be employed on short term basis. Most of these will be in skilled and semi-

skilled jobs.

3.8.11 Workers Health and Safety: Given the nature of work and environment, the workers may be

exposed to safety and health hazard associated with coal power plants and exposure to sharp objects

and to air and water pollution. Just like is the case for the regular staff of Hwange Power Station, the

sub-contractors will be expected to adhere to safety and occupational health and environment

management policy of ZPC; and adherence to Risk Management Policies of ZESA. Compliance to the

set principles shall become an integral part of special clauses in sub-contractor’s contracts.

3.8.12 Communicable Diseases: Exposure to HIV/AIDS and malaria are most critical. The

HIV/AIDS prevalence rate is estimated at 13.6% at national level with most rural areas having slightly

above average rates, The risk of contracting the disease is minimized by the on-going HIV/AIDS

awareness and prevention programs guided by both ZESA and ZPC’s Policies. The risk however, rests

more on the sub-contractors who will bring in labour from outside Hwange area. To minimize the risk,

the subcontractors will be obliged to incorporate ZPC guidelines on HIV/AIDS awareness, prevention

and mitigation measures. In addition, the sub-contractors will collaborate with district level National

Aids Council to ensure parallel and long-term programs complementing these efforts are national and

local level activities funded by agencies such as DIFD, USAID, Global Fund, and programs like “Local

AIDS Control Efforts (PLACE), etc., which focus on communities including school going girls and sex

workers. Regarding malaria and other water borne diseases, the project interventions especially in the

ash dam and other drainage related activities will assist in eliminating any stagnant water.

3.8.13 Outbreaks of Cholera and other waterborne diseases: The lack of/or unreliability of power

supply has affected the water sector with catastrophic consequences on health and hygienic practices.

Page 22: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

15

Following the Cholera epidemic of 2008/09, there is new evidence that the risk is emerging due to

regular interruptions of electricity power supply to the water utilities leading to low volumes of water

production with increased production costs.5 The project will offer the opportunities of uninterrupted

water supply to water treatment works to ensure sufficient water is pumped and supplied to areas most

needed such as highly populated and vulnerable urban areas and growth centers.

3.8.14 Involuntary Resettlement: Given the nature of the project which has been under operation

since mid 80s, there are no people directly affected who may need to be displaced or compensated.

However, an ESMP has been prepared which spells out other environmental and social concerns of the

project and its operations. (Annex VIII.1: ESMP Summary)

4. PROJECT IMPLEMENTATION

4.1 Implementation Arrangements

4.1.1 The beneficiaries of the grant will be the two ZESA subsidiary companies ZPC and ZETDC.

The two companies will benefit from the financing in accordance with the highly prioritized needs as

already indicated in the project components.

4.1.2 Procurement services will be provided by an experienced PA appointed for the Zim-Fund

financed projects. The PA will be delegated by the GOZ to carry out procurement functions including

but not limited to the procurement of (i) Goods and Works and (ii) Environmental consultant for the

Audit of HPS (iii) signing of contracts and processing of invoices for payments following certification

by the Implementing Entity. The PA will be based off-shore.

4.1.3 An independent Project Implementation Entity (PIE) will be responsible for detailed project

design, implementation coordination and monitoring. The PIE will be assisted by Project Management

Teams (PMTs) that will be set up within ZPC and ZETDC for the Hwange and T&D rehabilitations

respectively to take responsibility of the day-to-day project implementation activities. The PIE shall

have expertise in power systems, preferably in thermal power, T&D, proven capacity, reputation and

documented financial standing as well as knowledge of Zimbabwe. The PMTs shall also have the

requisite knowledge and expertise in coal-fired plant operations and maintenance, T&D system

operations and maintenance and project management. CVs for these teams have already been submitted

to the appraisal team for the Bank's review and recommendation for approval or otherwise. (See Annex

VI for CVs for PMTs).

4.1.4 The PIE shall prepare the scope of works specifications and bills of quantities in addition to any

related technical input required for the preparation of project tender documents and assist the PA in the

preparation of tender documents as well as evaluation of bids for works contracts. The PIE shall also be

responsible for all project record keeping and reporting of the project activities to the PA, the Zim-

Fund and the GOZ. It shall be a liaison between the PA, the Zim-Fund and ZESA as well as

government institutions within the power sector and address all issues pertaining to the project

implementation with assistance from the PMT's.

4.1.5 Implementation of environmental and social mitigation measures through implementation of the

ESMP is the responsibility of the Hwange Power Station Environmental Unit. However, it is expected

that ZESA will beef up the capacity in terms of human resources, equipment and training to ensure full

implementation of the ESMP.

5 Zimbabwe experienced worst Cholera outbreaks in 2008/09 which resulted in 98,531 cases and left 4,282 dead by June

2009.

Page 23: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

16

4.1.6 A Project Steering Committee comprising one representative each from ZESA Holdings and its

subsidiaries, one representative each from the Ministries of Energy and Finance and the Zim-Fund shall

be constituted with a member the PIE in attendance. The Committee will, as appropriate, address all

major issues arising, and provide overall guidance during project implementation. ZESA as the lead

beneficiary institution will ensure that there is coordinated support for the project implementation from

the government side at all times.

4.1.7 Project Audit: An independent Audit firm shall be recruited to carry out both technical and

financial audit of the project as implemented.

4.1.8 Environmental Audit Consultancy: An environmental consultant will be hired to carry out a

thorough and comprehensive environmental impact assessment of the Hwange plant to be conducted

whilst project implementation is underway. An environmental management plan will be prepared at the

end of this exercise.

4.2 Implementation Schedule

4.2.1 The project will be implemented over a period of 21 months. The key milestones will be the

recruitment of the PA and commencement of the works, respectively scheduled for Mid-March 2011

and November 2011. It is anticipated that, , beginning from April 2011 a period of about 3 months will

be needed for the selection of the Implementing Entity and a further 5 months for the preparation,

issuance and evaluation of tenders. By late November 2011 contracts for the various project

components should have been signed to signal the commencement of works. Project completion is

slated for end of December 2012. A tentative implementation schedule detailing the Procurement plan

is given in Annex V of this report.

4.3 Procurement Arrangements

4.3.1 An experienced Procurement Agency will be engaged to take overall project procurement

responsibilities. The procurement of Goods, Works and Services under the project will be in

accordance with the Bank’s Rules and Procedures for the Procurement of Goods and Works as well as

the Bank’s Rules for the Use of Consultant and as elaborated in the Operational Manual of the Zim-

Fund. The works which will be carried out in two contract packages shall include (1) Works for the

rehabilitation of the Ash Plant Hwange thermal power plant, and (2) Sub- Transmission and

Distribution System Rehabilitation. These will be procured through international competitive bidding,

of prequalified contractors. The recruitment of the Implementing Entity for engineering supervision

will be done based on a short list with Quality and Cost Based Selection (QCBS) method. The

procurement of the Environmental Consultant will be done based on a short list with Quality and Cost

based Selection (QCBS) method The Auditing Firm will be procured based on a short list and the

selection method will be Least Cost Selection (LCS). Details of the procurement arrangements are

provided in Annex VI.

4.4 Disbursement Arrangements and Financial Management

4.4.1 Payment for all services and works will be made by direct disbursement to the service providers

and contractors. The PIE will maintain separate accounts for the Project clearly showing all the

required financial details, including expenditures by component, category and financing source. The

PIE will be responsible for preparation and submission of disbursement applications through the PA to

the Zim-Fund. An allocation has been made in the cost of the project to cover the cost of the external

auditing services. The PIE shall provide all financial statements as well as technical reports to the

Page 24: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

17

Auditors. Certified copies of audited accounts will be submitted to all project stakeholders once

completed.

4.5 Monitoring and Evaluation

4.5.1 The PIE with assistance from ZESA’s internal PMT's will be responsible for the overall

monitoring and evaluation of the project activities. The PIE will produce monthly progress reports on

the status of the various project activities, financial and procurement status, asset management,

safeguard and risks mitigation measures. Once substantial completion of the project is achieved, the

Implementing Entity shall prepare a project completion report providing all accounts of the project

implementation, financial, procurement, asset, safeguard and measures of the achievements of the

project against the indicators in the log frame. The report shall also provide lessons for future

operations. The project will be audited annually.

4.5.2 Monitoring of ESMP implementation and adherence to prescribed mitigation measures is the

responsibility of the Chief Environmental Planner at ZESA who should be a member of the PMT. The

Environmental Management Agency (EMA) also plays a part in inspecting and monitoring compliance

with the environmental laws. It has been observed, however, that HPS needs advanced monitoring

equipment and associated training at all levels (HPS, ZESA and EMA)

5. PROJECT JUSTIFICATION, SUSTAINABILITY & RISK MANAGEMENT

5.1 Economic Justification

5.1.1 Boost to Economic Activities: The restoration of power generation and improvements in

transmission and distribution networks will contribute to re-invigorate the country’s economic

performance. Load shedding as a result of Power shortages has mostly affected manufacturing

industries (which shrunk by 2% in 2009), agriculture, mining, and services. As elaborated under Annex

VII, energy consumption for industry for example dropped from an average of 3 579 GWh for the years

1995 – 2006 to the current 1,400GWh, suppressing industrial production levels and contributing to the

economic meltdown. It is estimated that industrial performance has dropped to less than 40% of it 2006

level resulting in large numbers of jobs losses. Improvements in electricity supply availability and

reliability will contribute to a recovery in the industrial sector. Similarly energy consumption in the

mining sector dropped from an average of 1 500GWh for 1995-2006 to 809 GWh in 2009 largely due

to previous economic hardships in the sector compounded by erratic power supplies. In the short-to-

medium term, envisaged improvements in supply reliability from Hwange coupled with increased

imports will contribute to recovery in the mining sector as demand for energy from the sector rises.

5.1.2 The agricultural sector is one of the largest employers in the economy and contributes

approximately 19% to GDP. The sector is one of the most adversely affected by power shortages.

Energy consumption in the sector also dropped from an average of 1 125GWh in 2005 to the current

599GWh, partly due to policy issues associated with land ownership and reduced power availability

and reliability. It is expected that by 2015 new mechanisms would have been put in place to boost

agricultural productivity and food security. In the short to medium term however, improved supply

reliability of supply enable farmers expand irrigation schemes as well as operate agro-machinery and

boost production.

5.1.3 A recovery in the industrial, mining and agricultural sectors will create jobs and contribute to

poverty alleviation. In 2004, 68% of the population was estimated to be living below the poverty line.

Improvements in the T&D network would enable the restoration of supply services to about 22,000

Page 25: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

18

existing customers and households who are currently without electricity and allow small to medium

scale enterprises to resume operations by 2012.

5.1.4 Technical Losses: the current state of disrepair of the transmission and distribution system has

resulted in increased total losses. Total losses as at 2009 stood at 15.1% of total energy sales, with 12%

constituting distribution losses and 3.1% being transmission losses. The proposed T&D network

rehabilitation will help reduce such losses, to 2006 levels of 11.3% comprising 8.9% in distribution

losses and 3.8% in transmission losses, thus improving efficiency in the whole system.

5.2 Sustainability

5.2.1 The Ministry of Energy and Power, ZESA Holdings, and ZPC are doing their utmost to prevent

Hwange power plant from total collapse. The staff at the plant demonstrated technical skill and

innovation in maintaining and keeping the plant running under difficult circumstances. The appraisal

team was convinced that ZPC and the technical staff at the plant have sufficient skills and experience to

implement the rehabilitation program and upgrade the plant output and reliability to the desired level.

Both the IG and ZESA have showed their commitment to sustainability through allocating budgets to

the rehabilitation of HPS

5.2.2 ZETDC is also capable of implementing the rehabilitation project and maintaining the power

distribution facilities at the required reliability level. Existence of local transformer factories (namely

ZENT, a subsidiary of ZESA Holdings and South Wales Electric) is an added advantage as it is

providing means to have transformers replaced or maintained at short notice as the need arises.

5.3 Risk Management

5.3.1 High Debenture: ZESA’s debt is currently at about USD 400 million which results in an

average ratio of debt to equity of 3:4 which is considered high and represents a source of concern.

Capping the amount of additional debt that ZESA can obtain and improving their distribution,

metering, billing and collection systems are some of the mitigation measures.

5.3.2 Low Tariffs: Tariffs were extremely low prior to February 2009. The dollarization of the

economy in February 2009 enabled the company to charge a more cost reflective tariff and avoid the

extremely high inflationary effects on its working capital. However, the current tariff is still below the

required break-even levels. Bearing in mind the political and social implication of tariff policies, ZESA

is working on all fronts to sensitize all stakeholders about the importance of recovering its costs of

operations and ensure its continuity. ZESA is also exploring advanced “Targeted Tariffs policies” to

achieve a cross subsidy framework where the rich pay for the subsistence levels of the poor and where

tariffs change dynamically depending on the level and time of usage of electricity.

5.3.3 Commercial Losses: The sudden migration to the new tariffs met significant resistance

particularly from households who were used to monthly electricity bills below 1 USD and are now

asked to pay 20 times more. This resulted in non-payment of bill by many households subsequently

reducing ZESA revenue base. To address this problem, ZESA is investing in improvements to its

billing and monitoring systems and its collection efficiency. One example is the issuance of bills via

email and the opening of new banking halls to keep queuing to a minimum.

5.3.4 Another recent policy adopted by ZESA to address the growing accounts receivables and debt to

customers is the systematic disconnection of customers who are not or have not been paying their bills.

Albeit widely criticized, this drastic policy has had significant and immediate impact on ZESA cash

flows soaring from the tune of USD 6 million per month to about USD 46 million in monthly revenue

collected in cash since the implementation of this policy. Lastly, the utility has embarked on an ambitious

program to install prepayment meters for over 600,000 of its customers.

Page 26: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

19

5.3.5 Technical Losses: the current state of disrepair of the distribution system causes enormous

distribution losses. The proposed distribution network rehabilitation will help reduce such losses, thus

improving efficiency in the whole system.

5.3.6 Vandalism: there is a risk of repetition of vandalism and other negative behaviors that caused the

deterioration of the system in the past to re-occur in the future. This is partially mitigated by the general

change in the political framework which promises improvements in general living conditions and will

help reduce incentives for vandalism in addition to extremely harsh legal actions against such behaviors

i.e. a person convicted of vandalism was sentenced to 30 years in prison which was highly publicized

and was intended to set an example in the community. The availability of diesel and fuel oil supply in

the country also reduces the incentives for people to steal transformer oil (which used to be drained and

used as fuel). In addition improvements in system reliability ensures that the T&D system is live most

of the time; a strong deterrent to would be vandals

5.3.7 Weakening of the Ash Dam: In addition to natural disasters, it was noted that the ash dam next

to the Hwange power plant has not been fenced adequately and may collapse should a heavy storm

strike the area and may inundate the whole plant. Fencing of the Ash Damn is required to address this

potential risk.

5.3.8 Lack of environmental mitigation and monitoring equipment. The HPS electrostatic precipitators

have not been replaced for a long time, hence are no longer effective, consequently significant

pollution is released into the environment. The installation of this equipment will reduce emissions and

the installation of air quality monitoring equipment will enable verification of the impact of this

intervention.

6. CONCLUSIONS AND RECOMMENDATIONS

6.1 Conclusions

6.1.1 Zimbabwe faces a number of Infrastructure challenges due to lack of resources for maintenance

and new investments. The rehabilitation of key power sector assets in the generation, transmission and

distribution systems has been identified as the fastest and least cost option for restoring generation

capacity to increase electricity supply in order to meet current demand and enhance system stability.

Since 2009 the IG has made resources available to the Electricity Utility - ZESA to address critical

needs at two important generation assets; the Hwange and Kariba Power Stations as well as

improvements of some transmission and distribution systems, but these are limited compared to the

level of resources required. The Bank administered Zim-Fund has been established by Donors to

provide additional resources required to assist the IG of Zimbabwe to continue with these emergency

rehabilitation works.

6.2 Recommendations

6.2.1 Considering the many socio-economic and environmental benefits of the Emergency Power

Infrastructure Rehabilitation project presented above, it is recommended that the Bank approves a grant

from the Zim-Fund not exceeding USD 35.00 million (UA 22.727) for the proposed project.

Page 27: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

20

6.2.2 Conditions Precedent to:

A. Entry into Force of the Grant Protocol Agreement

(i) The Grant Agreement shall enter into force upon its signature;

B. Conditions Precedent to First Disbursement of the Grant:

ii) Provide evidence of having constituted a Project Steering Committee as recommended in

section 4.1.6

iii) Framework contract and specific project agreement signed between the Ministry of Finance and

the Procurement Agency to enable it to perform its duties on behalf of the Government of

Zimbabwe. Policies and guidelines of the Bank will be applied.

C. Other Conditions associated with Bank’s intervention

(i) Creation of an Environmental Management Unit (EMU) at Hwange Power Station and its

staffing

(ii) Report, on a quarterly basis and in a form acceptable to the Fund, on the status of

implementation of the re-designed ESMP in accordance with EMA and AfDB policies and

guidelines.

Page 28: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

TECHNICAL ANNEXES

Page 29: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

1

Annex I - Map of the Country and Location of the Project Areas

Page 30: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

2

Annex II: Project Cost Estimate: Emergency Power Infrastructure Rehabilitation Project

No. COMPONENT

NAME COMPONENT DETAIL

Funding Required

ZIM-FUND (USD)

Hwange Power Station:

1 Ash Plant Purchase and install 4 new clink grinders 1,800,000

Purchase 3 new ash slurry pumps, 2 casings & spares to overhaul

2 pumps

1,600,000

Replace all 4 discharges lines 4,500,000

Replace 500m 11kV cable & replace failed transformer cables 500,000

Purchase 5 new ash pump motors and bearings to overhaul 4 2,000,000

Purchase 4 new sluicing water pumps complete with motors, 3

casings and spares to overhaul 2 pumps

1,200,000

Purchase bearings and overhaul 6 sluicing pump motors 300,000

Purchase 2 new booster pumps, 2 casings & spares to overhaul 2 900,000

Purchase 1 new fluid coupling and spares to overhaul 1 250,000

Purchase 5 new sealing water pumps & motors 750,000

Purchase 3 new beilge pumps & motors 400,000

Purchase 2 new overflow sump pumps & motors 270,000

Purchase 500m 3.3kV 3 core and replace all damaged cables 400,000

Sub-total for Ash Plant at Hwange Power Station: 14,870,000

Transmission and Distribution System Reinforcement:

2 Sub-

Transmission

System

Reinforcement

132 kV SS

Install Urgently Needed Transformers at Six Substations 3,000,000

Install one (1) Transformer to augment Harare city water supply. 1,000,000

Replace sixteen (16) faulty sub-transmission breakers (16x132kV

breakers)

960,000

Sub-total for Sub-Transmission System reinforcement 4,960,000

3 Distribution

System

Reinforcement

Install 800-900 11/0.4kV Distribution Transformers 3,000,000

Install 800-900 33/0.4kV Distribution Transformers 2,000,000

Install 460.8 km of 11 7 33 kV Underground Cables 3,000,000

Install ACSR & HAD Overhead conductors. 2,000,000

Sub-total for Distribution System Reinforcement 10,000,000

Consultancies for Environmental, Supervision & Auditing

4 Environmental and Social Audit 1,200,000

Supervision - PIE 1,500,000

Auditing 70,000

Environmental Monitoring and Capacity Building 2,400,000

Sub-total for Environmental, Supervision & Auditing 5,170,000

Total Resource Requirements for Project as Appraised 35,000,000

Page 31: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

3

Annex III: Zimbabwe: Overall Power Infrastructure Rehabilitation Exercise

PHASE 1

2011 PROPOSED ALLOCATION

No. COMPONENT

NAME COMPONENT DETAIL

Total

Funding

Required

ZESA

Resources Zim-Fund GOZ

Hwange Emergency Rehabilitation

1 Ash Plant Purchase and install 4 new clink grinders 1,800,000 1,800,000

Purchase 3 new ash slurry pumps, 2 casings &

spares to overhaul 2 pumps

1,600,000 1,600,000

Replace all 4 discharges lines 4,500,000 4,500,000

Replace 500m 11kV cable & replace failed

transformer cables

500,000 500,000

Purchase 5 new ash pump motors and

bearings to overhaul 4

2,000,000 2,000,000

Purchase 4 new sluicing water pumps

complete with motors, 3 casings and spares to

overhaul 2 pumps

1,200,000 1,200,000

Purchase bearings and overhaul 6 sluicing

pump motors

300,000 300,000

Purchase 2 new booster pumps, 2 casings &

spares to overhaul 2

900,000 900,000

Purchase 1 new fluid coupling and spares to

overhaul 1

250,000 250,000

Purchase 5 new sealing water pumps &

motors

750,000 750,000

Purchase 3 new beilge pumps & motors 400,000 400,000

Purchase 2 new overflow sump pumps &

motors

270,000 270,000

Purchase 500m 3.3kV 3 core and replace all

damaged cables

400,000 400,000

14,870,000 14,870,000

Page 32: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

4

2 Stage 1

Excitation

Upgrade Units 1, 2, 3 & 4 excitation system 3,700,000 3,700,000

3 Turbine

Auxiliaries

Replace Stage II oil purifiers 3,000,000 3,000,000

Purchase and Install 3 extraction pumps

Replace DC lube oil pumps

4 Coal Plant Refurbish all coal plant structures 1,000,000 1,000,000

Refurbish dust suppression and dewatering

systems

1,550,000 1,550,000

Install a manual panel backup to PLC 250,000 250,000

Purchase 3 new coal weighers 800,000 800,000

Refurbish all protection systems 250,000 250,000

Purchase & install 5 new hold back units 500,000 500,000

Overhaul 4 tripper cars 400,000 400,000

Refurbish tripper panels & flap valves panels 200,000 200,000

Refurbish magnetic separation (5off) 400,000 400,000

Purchase & install 5 new fluid couplings 750,000 750,000

Purchase 4 new cable rell drums 280,000 280,000

Purchase & install new flap valves &

actuators

700,000 700,000

Purchase 3 vibratory feeders complete with

motors

2,700,000 2,700,000

Purchase & install 4 sump pumps in the

reclaim hoppers

400,000 400,000

Purchase spares & overhaul conveyor

gearboxes (13)

1,700,000 1,700,000

11,880,000 11,880,000

5 Boiler Plant Replace coal burners, diffusers and ceramic

line in PF

2,800,000 2,800,000

pipe work

Page 33: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

5

Purchase fuel oil pumps and compressors 1,200,000 1,200,000

Replace Unit No. 6 economizer and platen

s/heater

2,500,000 2,500,000

elements

Replace 4 Stage I super heater safety valves 600,000 600,000

Replace Stage I Lockheed pumps & motors 1,600,000 1,600,000

Replace air heater tubes on units 1 and 2 300,000 300,000

Refurbish Stage II precipitators 450,000 450,000

Replace Stage II air heater baskets

Replace flaustal compensator seals on Stage I

units

300,000 300,000

9,750,000 5,750,000 4,000,000

6 Water Treatment

Plant

Refurbish switchgear and controls for water

transfer pumps

200,000 200,000

Replace portable water and degassed water

pumps and motors

400,000 400,000

Refurbish raw water and degassed water

pumps and motors

200,000 200,000

800,000 800,000

7 DEKA Pump

Station & Pipe

Line

Purchase and install 2 high lift pumps, 4 low

lift and 8 sump pumps & motors

2,900,000 2,900,000

Purchase spares and overhaul 4 HL pumps &

motors

800,000 800,000

Resuscitate portable water treatment plant 50,000 50,000

Desilt and reline vertical and horizontal joints

on high lift setting tank

65,000 65,000

Refurbish 11kV/380V LL transformers and

replace power cables

500,000 500,000

Purchase new switchgear and instrumentation

for LL & HL

390,000 390,000

Overhaul suction, discharge & non return

valves and replace actuators

650,000 650,000

Page 34: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

6

5,355,000 65,000 5,290,000

8 Laboratory Purchase laboratory equipment and resuscitate

online analyzer equipment

1,100,000 1,100,000

9 Stage II Units 5 & 6 Major Overhaul Spares 20,000,000 20,000,000

10 Milling Plant Purchase Overhaul Spares for all Stage I& II

units

8,000,000 0

11 Draft Plant Purchase PA and ID fans impellors and

bearings

3,500,000 0

12 Auxiliary Plant Refurbish hydrogen and Chlorine plants 3,000,000 3,000,000

Refurbish Cooling water Systems

Purchase Spare Station & Generator

Transformer

13 Dirty Drains Replace Stage 1 & Stage II dirty drains

pumps & motors

1,500,000 1,500,000

Sub-Total for Hwange Emergency Rehabilitation : 86,455,000 25,915,000 14,870,000 45,670,000

Transmission and Distribution System Reinforcement

14 Customer

Metering

Prepayment Meters/Smart Meters 7,500,000 7,500,000

Test Benches (Harare - Bulawayo) 400,000 400,000

Three Phase Meters 1,000,000 1,000,000

Susbstations Indication Instruments 2,500,000 2,500,000

11,400,000 11,400,000

15 Sub-

Transmission

Install Urgently Needed Transformers at Six 3,000,000 3,000,000

Page 35: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

7

System

reinforcement

Substations

132 kV SS Install one (1) Transformer to augment Harare

city water supply.

1,000,000 1,000,000

Replace sixteen (16) faulty sub-transmission

breakers (16x132kV breakers)

960,000 960,000

4,960,000 4,960,000

16 Transmission

System

Install one (1) 330/132/11 kV Tx at Chertsey

SS (1x90 MVA)

4,100,000 4,100,000

Reinforcement

(330 KV)

Install one (1) 330/132 kV Tx at Warren SS

(1x90 MVA accessories)

700,000 700,000

Replace faulted breakers at transmission

substations (7x330kV breakers)

700,000 700,000

5,500,000 5,500,000

17 Distribution

System

Reinforcement

Install 800-900 11/0.4kV Distribution

Transformers

3,000,000 3,000,000

Install 800-900 33/0.4kV Distribution

Transformers

2,000,000 2,000,000

Install 460.8 km of 11 7 33 kV Underground

Cables

3,000,000 3,000,000

Install ACSR & HAD Overhead conductors. 2,000,000 2,000,000

10,000,000 10,000,000

18 System

Protection and

Communications

Replace Obsolete RTUs on National Grid

SCADA

320,000

Replace Obsolete Substations Control

Systems (Kariba, Sherwood, Norton and

Marvel)

936,000

Replace Obsolete and Malfunctioning

National Grid Distance Protection Relays

(Over 30 Years Old and No Spares) at Kariba,

Alaska, Sherwood, Norton, Warren, Dema,

Bindura, Orange Grove, Haven, Chetsey and

Tokwe

640,000

Page 36: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

8

Replace Backup Protection Equipment for the

Above Grid Substation

640,000

Replace Malfunctioning Telecommunication

Signal Carriers (Power line Carriers with

Optical Fibre on the National Grid) at

Songo - Bindura (161km) 805,000

Bindura - Dema (91.2km) 456,000

Alaska - Sherwood (156.6km) 783,000

Alaska - Kariba (169.4km) 847,000

Chetsey - Tokwe (130km) 650,000

Optical Fibre Multiplexes for the Above

Optic Fibre Links (10)

250,000

6,327,000

Sub-total for Transmission and Distribution System

Reinforcement:

38,187,000 17,727,000 14,960,000 5,500,000

19 Cost of ES Audit 1,200,000 0 1,200,000 0

20 Supervision 1,500,000 0 1,500,000 0

21 Auditing 70,000 0 70,000 0

22 Environmental Monitoring and Capacity Building 2,400,000 0 2,400,000 0

Grand Total Resource Requirements: Generation,

Transmission & Distribution

129,812,000 46,812,000 35,000,000 51,170,000

Page 37: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

9

Annex IV Implementation Diagram

Certified Invoice

ADB / ZIM Fund

Zim Fund MMU

GOZ

Project Implementing Entity

(PIE) assisted by ZESA

constituted Project

Management Teams (PMTs).

Project coordination and

management services

Procurement Agent

Consultants/Contractors/suppliers

Nominal Grant recipient

Procurement approval

Contractual relation

Contractual relation

Delegation of implementation

Prj. Management

Payment

Disb. application

Project management and

supervision services

and Coordination

Implementation Arrangement Diagram

Payment

Project Steering Committee

Page 38: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

10

Annex V – Procurement Arrangements

All procurement of goods and works and acquisition of consulting services financed by the Zim-Fund will be in

accordance with the Bank's Rules and Procedures for Procurement of Goods and Works or, as appropriate, Rules

and Procedures for the Use of Consultants as well as the Zim-Fund operations manual, using the relevant Bank

Standard Bidding Documents. A Procurement Agent will be responsible for the procurement of goods/works/

service contracts, consulting services, training and miscellaneous items as detailed below. A table of the

Procurement milestones is shown below, while the detailed Procurement Plan will be presented separately.

Summary of Procurement Arrangements

Categories

USD (million)

ICB Other Short List * Total

A. Works

A1 –Ash Plant rehab. Hwange

Thermal Power Station.

A2- Transmission & Distribution

rehab.

14.870

14.960

14.870

14.970

A.3 Environmental Monitoring

equipment

2.300 2.300

B. Services

B1. Engineering Supervision

services – Implementing Entity

1.500 1.500

B2. ESIA Audit and ESMP

production

1.200 1.200

B3. Accounts Audit Services 0.070 0.070

B.4. Environmental Monitoring

capacity

0.100 0.100

GRAND TOTAL 32.13 2.870 35.00

* Short List applies to the use of consulting services only.

_ other may be LIC, International or National Shopping, Direct Purchase or Force Account.

Electro-Mechanical Works

Procurement of Electromechanical Works associated with Ash Plant rehabilitation and T&D rehab works is

divided into two packages as shown above. (A1 for an amount of USD 14.870 million – Ash Plant and A2 for

an amount of USD 14.960 million – T&D). These will be carried out under International Competitive Bidding

procedures of prequalified contractors. An amount of USD2.4 million will be used to procure environmental

mitigation equipment. The contractors will be required to submit their bids as per specifications outlined in

tender documents.

Consulting Services

Procurement of the Implementing Entity - consulting firm for engineering supervision and monitoring will be

carried out by the MMU at a contract value not exceeding USD 1.500 million. Environmental auditing as well

as project accounts auditing will be carried out in two packages with total contracts values not exceeding USD

1.200 million for environmental and social audit services and USD 0.070 million for Project Accounts Audit.

The process for selections shall be through Short List and the method for evaluation is Quality and Cost Based

Selection (QCBS). The process for selection shall be through Short List and the method for evaluation is Quality and

Page 39: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

11

Cost Based Selection (QCBS). Project Accounts Audit valued at USD 0.070 million shall be through a short list and the

process for evaluation shall be Least Cost Selection (LCS).

General Procurement Notice

The text of a General Procurement Notice (GPN) will be issued for publication in UN Development Business

online and on the Bank’s web site, upon approval of the Grant Proposal.

Review Procedures

The following documents are subject to review and approval by the Zim-Fund before promulgation: General

Procurement Notice, Specific Procurement Notices, Prequalification Documents [if applicable], Tender

Documents or Requests for Proposals from Consultants,Tender Evaluation Reports, including

recommendations for Contract Award (goods/works), or Reports on Evaluation of Consultants' Proposals, ,

Draft contracts (goods/works), if these have been amended and differ from the drafts included in the tender

documents, Reports on Evaluation of Consultants' Financial Proposals, including recommendations for

Contract award, minutes of negotiations and duly initialed contracts documents.

Post Review

Post review will not be applicable under this project. projects

Executing Agency

A Procurement Agent will be responsible for the procurement of goods/works/consulting services/training

services (as appropriate).

Procurement Plan

The Zim-Fund shall review the procurement arrangements proposed by the Procurement Agent in the

Procurement Plan for its conformity with the grant Agreement and its Rules. The Procurement Plan shall cover

an initial period of at least 21 months. The Plan will be updated on an annual basis or as needed always

covering the next 21 months period of project implementation. Any revisions proposed to the Procurement Plan

shall be furnished to the Zim-Fund for its prior approval.

Page 40: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

12

Annex VI – Project Management Teams

TRANSMISSION AND DISTRIBUTION

Team Leader : ENGINEER IKHUPULENG DUBE

Team Member : MR. FREDY MAZANA

Team Member : ENGINEER BUKOSI SISO

GENERATION PROJECT TEAM:

Team Leader : ENGINEER PHILLIP MBENGERANWA

Team Member : MR MUYEDZO NEBARWE

Team Member : ENGINEER BENARD CHIZENGEYA

CURRICULUM VITAEs FOR TEAM MEMBERS:

CURRICULUM VITAE FOR ENGINEER BUKOSI SISO

Qualifications

Bachelor of Science Degree in Engineering

Masters in Business Administration

African Development Bank Tendering procurement Procedures Certificate

Years of Experiences : 25 years

Areas of Expertise

Distribution planning

Procurement of electrical materials and services

Standardization

Research and development

Regulatory compliance

CURRICULUM VITAE FOR MR FREDY MAZANA

Qualifications

Bachelor of Commerce Degree in Accounting

Years of Experiences: 14 years

Page 41: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

13

Areas of Expertise

Financial Administration

Management of accounts payables and receivables

Procurement

Financial report

CURRICULUM VITAE FOR ENGINEER IKHUPULENG DUBE

Qualifications

Masters of Science Degree in Engineering

Years of Experiences: 21 years

Areas of Expertise

Project Management

System Studies

Designs and Specifications

Regulatory Compliance

Network Operations and Maintenance

Research and Development

Policy Studies and Analysis

CURRICULUM VITAE FOR ENGINEER PHILLIP MBENGERANWA

Qualifications

Bachelor of Science Degree in Engineering

Years of Experiences: 21 years

Areas of Expertise

Procurement

Power station operation

Power station Management

CURRICULUM VITAE FOR ENGINEER BENARD CHIZENGEYA

Qualifications

Bachelor of Science Degree in Engineering

Years of Experiences: 27 years

Page 42: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

14

Areas of Expertise

Power station maintenance

Power station Operation

CURRICULUM VITAE FOR MUYEDZO NEBARWE

Qualifications

Management of Business Administration (Nottingham Trent UK)

Post Graduate Diploma Certificate (Nottingham Trent UK)

B. Comm (Hon) Accounting Midlands State University

B.Comm Cost and Management Accounting SAQA Part C CIS

ZAAT Diploma Certificate and Foundation Certificate

Years of Experiences: 12 years

Areas of Expertise

Financial Management Power Stations

Accounting Management Power Stations

Page 43: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

15

Annex VII – ECONOMIC IMPACT ASSESSMENT

8.1 Economic Sectors Electricity Consumption Review

8.1.1 Mining Sector The sector resulted in only 809 GWh sales in 2009 compared to an average of

1,500GWh for the period 1995 to 2006 with a percentage drop of 46%. The main reason for this percentage

drop is system viability problems due to previous economic hardships compounded by erratic power supplies.

The demand for mining is expected to rise in the medium term due to envisaged improvement of supplies at

Hwange, increased imports (with mechanisms being put in place to allow miners to import power directly and

or restructuring of the import arrears debt), and more availability of power to the productive sector as a result of

the implementation of demand side management and energy efficiency programmes.

8.1.2 Industry Sector Industry is currently constrained and is operating below 60%. It has dropped in

terms of sales by over 50% from an average of 3 579 GWh for the years 1995- 2006, to the current 1,400GWh

which is 40% drop. It is estimated that 270 MW is currently out due to suppressed production levels as a result

of the economic meltdown. The problems of industry have been compounded by erratic supply. In the medium

and short term the growth in demand is expected from recovery of industry, which is closely linked to economic

policies that are in place to resuscitate industry.

8.1.3 Commercial Sector This is the only sector that has not shown any decline since major commercial

centres are usually exempted from load shedding. Commercial also affected by Rural Electrification since the

Rural Electrification Programme is targeted at schools, government offices, clinics and rural business centres.

8.1.4 Agricultural Sector Agriculture dropped from an average of 1125GWh registered in 2005 to the

current 599GWh. The main reasons for the decrease in energy consumption for the sector can be attributed to

lower energy usage by newly resettled farmers due to lack of funding for energy intensive farming activities,

unclear ownership of existing infrastructure and its maintenance and erratic power supplies for irrigation

activities. It is assumed by 2015 new mechanisms would have been put in place to boost agricultural

productivity and food security. In the short to medium term, a number of projects in Middle Sabi, Chisumbanje

and Mwenezi areas are lined up to produce ethanol from sugar cane. The energy requirements will be minimal

since the same projects will be implementing co-generation. The long term plans to construct dams such as

Tokwe-Mukosi, Biri -Manyame etc will result in increase in irrigation and power consumption.

8.1.5 Domestic Sector Domestic sales will remain subdued in the short and medium term because of lack

of large scale housing infrastructure currently taking place. Notable developments are electrifying houses

developed by individuals and investors estimated at 89,000 currently not connected. In the long term it is

assumed that as the economy recovers, housing infrastructure will be put in place to alleviate housing problems.

On the same note it is expected that the rural electrification project will result in a significant number of

households being connected. The number of urban connections will progressively increase from 5,000 per

annum in the short term rising to an average of 20,000 per annum in the medium to long term. Total

electrification in urban areas is expected to be achieved by 2025.In rural areas, the base case scenario assumes

that about 5,000 households will be connected in the short term and then the number of connections will rise to

10,000 per annum in the medium term and then rising to over 20,000 in the long term (after total electrification

of urban areas).

It is assumed that household incomes will be constrained hence lower connection rates. Also erratic electricity

supplies would mean that in the short term households will have to rely on other substitutes such as fuelwood,

standby generator, kerosene, batteries and candles. These energy forms are inferior to electricity, have indoor

Page 44: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

16

pollution and are generally higher than the average monthly electricity bill of a household as shown on the table

below.

The projected Number of Customer Accounts with ZETDC is presented below:

2010 2015 2020 2025 2030

Estimated Population 13,424,400 14,604,936 15,889,287 17,354,574 20,452,742

Households

Urban 404,947 479,947 579,947 650,947 766,947

Rural 117,806 152,806 202,806 269,806 364,806

Sub-total 522,753 632,753 782,753 920,753 1,131,753

Commercial Establishments

Mining Industry 637 664 681 698 715

Other Industry 13,679 13,858 14,208 14,566 14,934

Sub-total 14,316 14,521 14,888 15,264 15,650

National and Local Government 3814 12814 21814 30814 39814

Other Accounts 46,609 47,786 48,993 50,230 51,498

Overall Average 587,492 707,874 868,448 1,017,061 1,238,715

Household Electrification Rate (%) 31.2 34.7 39.4 42.4 44.3

Growth In Accounts (% p.a) 4.8 3.8 4.3 3.0

Household Electrification Rate (%)

Urban Electrification rate (%) 80.4 87.6 97.3 100.0 100.0

Rural Electrification rate (%) 10.0 12.0 14.6 17.8 20.4

8.2 Energy Price Comparison (per customer) as at 30 April 2010

MONTHLY

USAGE AVERAGE UNIT

PRICE (US$)

MONTHLY COST

TO CUSTOMER

(US$)

MONTHLY

COST TO

ZESA (US$)

SUBSIDY

(US$)

COOKING AND 250 KWh 0.07 17.48 18.83 1.35

HEATING 30 Litres Paraffin 1.00 30.00 NIL

(2 MEALS PER 60 Bundles of Firewood 1.00 60.00 NIL

DAY) 6 Kg Gas 2.35 14.00 NIL

20 Kg Gel Fuel 2.08 41.50 NIL

LIGHTING 20 KWh 0.07 1.40 1.51 0.11

(3 ROOMS LIT 4

hrs/day) 40 Candles 400g 0.28 11.33 NIL

RADIO 12 KWh 0.07 0.84 0.90 0.06

(8 hrs/day) 4 Torch Cells 1.15 4.60 NIL

Page 45: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

17

8.3 Energy Projections

The following tables shows the energy sales for each customer category, The total energy sales for each

scenario (low case, base case and high case), energy at bulk supply point, energy sent out and system maximum

demand.

Historical Sales and Forecast by Customer Category

MINING INDUSTRIAL COMMERCIAL FARMING DOMESTIC

ZESA

UNITS TOTAL

%

Growth

1995 1595 3780 1333 758 1672 23 9160 5.4

1996 1589 4003 1510 868 1832 19 9821 7.2

1997 1707 3848 1800 927 1991 21 10294 4.8

1998 1580 3532 1800 1123 2098 17 10150 -1.4

1999 1642 3961 1625 1304 2230 18 10780 6.2

2000 1429 3884 1540 1291 2316 34 10494 -2.7

2001 1346 3634 1548 1324 2349 25 10226 -5.1

2002 1443 3550 1493 1308 2487 38 10319 -1.7

2003 1426 3447 1451 1245 2728 71 10368 0.5

2004 1420 3121 1432 1197 2884 63 10116 -2.4

2005 1410 3233 1628 1303 2796 38 10408 2.8

2006 1379 2959 1838 846 3262 7 10307 -1.0

2007 10293 -0.1

2008 7476 -27.2

2009 802 1404 1631 599 2609 7 7052 -4.1

Forecast

2010 865 1685 1680 600 2687 8 7525 6.6

2011 908 1735 1730 618 2768 8 7768 3.2

2012 1017 2603 1782 643 2851 8 8904 14.6

2013 1058 2681 1818 668 2936 8 9170 3.0

2014 1143 3083 1872 695 3025 8 9826 7.2

2015 1234 3392 1947 723 3327 8 10631 8.2

2016 1333 3731 2025 795 3660 8 11552 8.7

2017 1439 4104 2106 875 4026 8 12558 8.7

2018 1555 4514 2190 962 4428 8 13658 8.8

2019 1679 4966 2278 1059 4871 8 14860 8.8

2020 1813 5214 2369 1164 5358 8 15927 7.2

2021 1958 5318 2464 1281 5626 8 16656 4.6

2022 2037 5425 2563 1409 5795 8 17236 3.5

2023 2118 5533 2665 1550 6027 8 17901 3.9

2024 2203 5644 2772 1705 6207 8 18539 3.6

2025 2291 5757 2883 1773 6394 8 19105 3.1

2026 2383 5872 2998 1844 6585 8 19690 3.1

2027 2478 5989 3118 1918 6783 8 20294 3.1

2028 2577 6109 3242 1994 6987 8 20917 3.1

2029 2680 6231 3372 2074 7196 8 21562 3.1

2030 2787 6356 3507 2157 7412 8 22227 3.1

ENERGY IN GWH

Page 46: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

18

8.4 Economic Impact of the Emergency Power Infrastructure Rehabilitation Project

The proposed project is expected to have both direct and indirect economic impacts on various stakeholders; the

section below describes these impacts in more in-depth.

8.4.1 Direct Economic Impact due to the improvement of the ash plant: Ash plant rehabilitation will have

an immediate impact on the surrounding communities in terms of reduced infection rates of ash pollution

related diseases and associated averted costs to public health and to local households. In addition, the ash plant

improvement will result in less ground and water pollution hence an averted cost to the economy related to site

cleaning and restoration as well as cost accrued to various hindrances to agricultural and fishing activities.

8.4.2 Direct Economic Impact due to the reinforcement of the Transmission and Distribution networks:

transmission and distribution systems reinforcement will significantly improve the reliability of the power grid

and reduce the portion technical losses and assuring a stable constant supply of electricity to vital sectors of the

economy, particularly in the water sector which depends largely on power hungry water treatment plants. The

increased availability of the units will enable consistent supply of electricity to the economy.

8.4.3 Indirect Economic Impact: The restoration of power generation and improved distribution will re-

invigorate the country’s economic activities and boost industrial production and contribute towards poverty

alleviation which was estimated at 68% (2004) of the people living below the poverty line. Power shortages and

shedding have mostly affected manufacturing industries (which shrunk by 2% in 2009), agriculture, mining, and

services. It is estimated that due to the economic down-turn industrial performance has been at less than 40%.

Reduced productivity in these industries and sectors has meant large number of jobs lost. The agricultural sector

which contributes approximately 19% to GDP and employs over 400,000 people (66%) also has been adversely

affected by power shortages. It is, therefore, critical to restore power supply and distribution to optimal levels.

8.5 Conclusion: The proposed intervention will certainly contribute to the efforts currently undertaken by

the Government of Zimbabwe and ZESA to restore the power infrastructure in the country. Nevertheless, the

available funding risks reduce the impacts of this particular intervention as far as the optimization of the power

infrastructure in Zimbabwe is concerned given the long list of items required as depicted in Annex III. More

funding is required to ensure higher impacts

Page 47: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

19

Annex VIII – ENVIROMENTAL AND SOCIAL ANALYSIS

8.1 Environment

Initial Environmental and Social Examination (IESE)

8.1.1 The examination conducted by the Bank Mission has revealed that lack of regular maintenance

according to specifications by equipment vendors and shortage of spare parts has resulted in degraded

performance with negative consequences on the environment. Urgent actions are needed to improve the

environmental performance of the power station and auxiliary plant systems. The rehabilitation measures

envisaged ranging from the power house, control systems, coal feeding system, precipitators, ash disposal,

water cooling and pumping system and testing and laboratory systems will address a very critical need given the

current state of the plant.

8.1.2 The electrostatic precipitator runs at around 40% of its full capacity, which means that about 60% of the

fly ash is being released into the atmosphere through the stacks. The power plant lacks essential cleaning

systems associated with coal fired power plants, e.g. desulphurization systems and de-noxing operations. Hence

large amounts of Sulphur Dioxide and Nitrogen Oxides are also released into the atmosphere annually without

any form of control measures. Among most significant environmental and social impacts are linked to the ash

disposal area and the entire ash disposal system, including the management of liquid effluents and the ash dam.

Associated with the ash are heavy metals which represent a real threat to humans, plants, animals and water

bodies in the vicinity of the plant (approximately 5 – 10 km radius).

8.1.3 Most critical of the items from environmental and social points of view are measures consistent with all

electronic and mechanical equipment that are in need of refurbishment and which, if installed, will directly

result in improved environmental and social conditions in the plant and its auxiliaries. These can be

summarized as follows:

(i) Rehabilitation of boilers to improve combustion

(ii) Refurbishment of electrostatic precipitators (ESP)

(iii) Refurbishment of the ash plant to ensure optimal operation that will minimize excessive ash being

sucked back into the ESP,

(iv) Remedial actions on ash slurry disposal system and management of the ash dam

8.1.4 Further investigations are needed to select de-noxing systems to be installed with the most appropriate

control instruments of NOx emissions in boiler operation. Desulphurization methodologies need to be studied to

select an effective methodology capable of decreasing SO2 emissions to the least possible limit and in

conformity, at the same time, with the available resources. These would include items such as scrubber system,

limestone and coal washing options.

Negative Project Impacts

8.1.5 The project activities will mainly comprise repairs and replacement of existing equipment and limited

civil works. This will have minimum negative impacts on the local environment with waste and sludge

management and disposal being the significant impact. The bid documents will clearly outline the measures to

be taken to protect the environment including observing proper working methods, replace any destroyed

Page 48: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

20

vegetation, and protecting the surrounding areas by ensuring proper disposal of discarded equipment and

materials. The environmental and social management plan will entail how the upgrade should be undertaken

such that the sludge is not disposed of in a manner that will contaminate the soil and groundwater resources.

Included in the mitigation measures would be the prevention of nuisance in terms of dust, noise, odors etc. The

project provides protective clothing for personnel engaged in the laying or cleaning of sludge/ sewers and will

also look at fencing and/or covering some of the infrastructure which poses a great danger to humans such as

open manholes and ponds. The Agency responsible for project implementation will closely monitor the

execution to ensure that any negative impacts arising are mitigated as entailed in the ESMP.

Mitigation Measures

8.1.6 A strategy for dealing with the above-mentioned environmental and safety concerns would be built

around the following actions:

(i) An Air Quality Management Plan is required to deal with air pollution from the stack. Electrostatic

precipitators (de-sulphurisation equipment) are required and need to be installed. A management strategy for

disposal of all trapped substances is also needed to avoid further pollution of soil and water from substances like

mercury trapped by the precipitators. There is also a need to improve combustion efficiency within the plant to

reduce carbon monoxide and other gas emissions. (Concentration levels should not exceed 5 ppm for each of

the gases of concern: SO2, CO, and NO).

(ii) An Environmental Management Plan is required for the ash dam. The main issue is to prevent wind from

blowing away the ash at the dam. This can be addressed by keeping the entire ash under wet conditions.

Sprinklers need to be installed for continuous spraying of the ash dam. Run-off from the dam will also need to

be collected and recycled.

(iii) A series of interventions is required to address the other environmental concerns, including: (a) provision

for capturing and recycling waste water runoff from other locations at the plant; (b) adoption of a procedure for

managing accidental spillage of hazardous substances; (c) development of a procedure for containment of gas

and evacuation of personnel in the event of accidental release of gas from coke ovens; (d) additional equipment,

including pumps, and storage tanks, are needed to collect used oil and a site for its disposal, including recycling,

needs to be developed.

(iv) With respect to the safety of the Hwange Ash dam itself, a technical assessment of the dam wall is

required. One or more engineers with an appropriate background in dam safety are required for an independent

assessment of the ash dam wall. Not-with-standing the on-going works at the dam, in the event that there is

need for further remedial actions the inspection team would be required to develop a specific Action Plan for

immediate implementation.

Anticipated Positive Environmental Impacts

8.1.7 The Emergency Power Infrastructure Rehabilitation Project is proposed to remediate and mitigate a

number of negative environmental impacts resulting from the current operations of the Hwage power plant.

These include the following:

(i) Air pollution from the stack. Emissions include dust, sulphur dioxide, nitrogen oxides, and mercury

from burning coal, carbon monoxide and carbon dioxide. These emissions are affecting workers at the

Page 49: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

21

site and the surrounding population. Atmospheric emissions of carbon dioxide are increased due to

inefficient combustion and inefficient operation. Acid rain from the combination of sulphur dioxide and

oxides of nitrogen and moisture in the air is thought to be contributing to increased acidity of local

ecosystems and loss of flora and fauna.

(ii) Air pollution from ash disposal has also been identified as major source of pollution for the working

environment at the plant site. It is also a significant threat to the health of the surrounding communities

who are exposed to the dust. The dust may contain heavy metals such as arsenic, lead, mercury,

selenium, which are a threat to water supplies and human health, including cancer, birth defects and

other problems. These pollutants can also decimate fish, bird and frog populations in and around the

dam site.

(iii) Ash is deposited at the ash dam through wet slurry. There has been environmental monitoring around

the ash dam to determine the impact of ash on groundwater. Samples from boreholes are taken to the

National Water Quality Laboratory each month. Results to date suggest no significant groundwater

contamination from the ash.

(iv) Disposal of waste water is a likely source of pollution of surface and ground water in the area. There is

no treatment of waste water before it is discharged into surface water streams. Further work is required

to determine the extent of the water contaminants, but it is clear that treatment of the water is required

before its release.

(v) The power plant makes use of a number of hazardous substances, including sulphuric acid, caustic soda,

chlorine, and hydrogen. Accidental spillage can be another source of pollution.

(vi) Accidental release of gas from coke ovens is another potential source of air pollution at the work site

and in surrounding communities.

(vii) Current practices for the disposal of used oils, including diesel, grease and engine oil, is also a threat to

the environment.

(viii) A salient environmental and safety concern at the Hwange Plant site is the ash dam itself. These concern

centers on the fragility of the ash dam retention wall due to inadequate maintenance. The proposed

project will undertake investigations and recommend ways to strengthen the dam retention wall. It must

be noted that the HPS has already done significant amount of work to address this issue through

compacting the ash dam retention walls as well as planting trees and grass on the wall to reduce erosion

as well as strengthen the wall. However in the unlikely event that the ash dam retention wall were to

collapse on account of heavy rains, it could result in the destruction of the entire plant which is situated

in the valley directly below the dam wall. This would result in a substantial reduction in total domestic

power availability that, in turn, would cause social and economic hardship. It would reduce power

availability for water treatment plants and increase the risk of outbreaks of cholera and other water borne

diseases.

Environmental and Social Audit

8.1.8 The Bank's environmental guidelines, stipulate that when involved in financing a retrofitting or

expansion project for an existing power generation or industrial facility with significant social and

environmental consequences, an Environmental and Social Audit should be conducted by an independent

consulting firm to objectively evaluate and obtain comprehensive information on the sources, causes and

impacts on the environment through a systematic, independent and documented process. The project has,

therefore, included in its design carrying out such as an audit utilizing the criteria developed in an ESMP

against which to evaluate project compliance. Since the Power Plant was prepared prior to 1992, where ESIAs

for Category 1 project was not mandatory, is the reason why the current ESMP may not have been sufficient for

such a plant and associated facilities. The ESMP will therefore be developed as part of a Compliance Audit, to

provide a management and monitoring tool for environmental and social aspects during project supervision and

Page 50: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

22

implementation. This will also provide information about any past or present impacts resulting from the project

that were not anticipated by the ESIA. A provisional sum has been included in the project cost for the

consultants to carry out the audit estimated at US$1.2 million (Abridged TORs are provided in Annex VIII.2).

Climate Change

8.1.9 Regarding the GHG emissions, the technology used in the power plant to produce electricity from coal

as a fuel is inefficient in terms of producing high CO2 emissions per unit of power generated. However, the

modifications which the project targets through refurbishment and rehabilitation will lead some reduction of

CO2 emissions. In other words, there will be a reduction of emissions volume per unit of power generated.

8.1.10 The technological modifications will lead to environmental improvements, they will also lead to

increased plant availability and consequently consistent power resulting from reduced stoppages. The specific

reduction of emissions is considered a key enhancement for the existing technology that complies with the

Bank's policies in promoting sustainable development.

8.1.11 Zimbabwe is in dire need for electricity for its economic and social development. Besides, its energy

resources greatly depend on coal as an indigenous resource for energy. The sustainable development of energy

in a country like Zimbabwe includes the use of clean coal technologies. That is in accordance with the Bank’s

desire to strengthen and promote sustainable development in Africa through a lower carbon growth path.

8.1.12 CO2 emissions per capita in Zimbabwe are low at around 0.1compared to Egypt which is at 2.3 and

Nigeria at 0.9. Zimbabwe is categorized according to Kyoto Protocol as a non Annex- I country, i.e. has no

obligations for emission reductions but good practice encourages low carbon development path..

Public Consultation and Disclosure of ESMP

8.1.13 In order to ensure that the views and interests of all project stakeholders are considered in the project

design, public consultations are a requirement in the guidelines of the AfDB and the Zimbabwean

Environmental Management Agency (EMA). Through ZESA, stakeholder consultations have been carried out

through making announcement/advertisement in media describing the project and inviting interested parties to

review the draft final ESMP report; and distribution of an invitation and copy of the non technical summary

describing the context of the power plant, the technology employed, the impact on environment, the mitigation

measures and the ESMP.

8.2 Gender

8.2.1 The National Gender Policy. At national level, Zimbabwe has set out priorities for gender

mainstreaming and empowerment of women for the period 2008-2012. The National Gender Policy

Implementation Strategy and Work Plan seek to operationalize the commitments to gender equality and

women's empowerment derived from various national policies, statutes and decisions. Both ZESA and ZPC

have developed gender consciousness and appointed gender focal points to ensure that interests of both men and

women are taken on board in policy formulation and decision making.

8.2.2 Risk of HIV/AIDS Infections. Implementation of the rehabilitation project may not necessarily

disadvantage any particular gender group; per se. However, given that the rehabilitation works are likely to be

Page 51: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

23

sub-contracted to service providers who are likely to bring in labor from distant places such as Harare, and often

times this labor force is likely to be men, comes the risk of the spread of HIV/AIDS. The national prevalence

rate at 13.6% shows a skewed bias towards women6 who are subjected directly by men who tend to lure girls

into unprotected sex, but also to wives who become the victims on the receiving end when husbands return

home infected. The Project Preparation Team, was presented with HIV/AIDS Policy of ZPC which promotes

practices that unite families in order to reduce the spread of HIV/AIDS and mitigate its effect on the affected

individual and his/her family by creating a supportive environment. In addition ZPC provides to all staff with

the information and education necessary to increase their awareness on the issues related to HIV infection and

AIDS. Complementing these efforts are programs that are being carried out by at national and local levels

funded by agencies such as DIFD, USAID, Global Fund, and programs like “Local AIDS Control Efforts

(PLACE), etc., which focus on school going girls and sex workers. Resuscitating the power plant presents the

potential for creating more job opportunities for both men and women.

8.2.3 Women’s Employment Opportunities. Currently the Hwange Power Station on average employs 724

people on regular jobs among which 81 (11%) are women mostly in semi- and unskilled jobs. While this

outcome is created by nature of jobs and remoteness of the site, ZPC is making an effort to encourage more

women to seek non-traditional jobs and take advantage of existing vacancy rate which stand at 8% within

Hwange Power Station itself. Zimbabwe being a member of SADC is expected to implement the Gender

Protocol which demands that women participation in the job market should be at par with that of their male

counterparts. A Gender Focal point has been appointed at ZPC headquarters whose job among others is to

ensure gender equity in recruitment. The project will, in addition, ensure that the environmental monitoring

training includes 50% women. In the broader context, women have been impacted by lack of reliable power

supply through job losses. Most women are employed in horticultural and farming industries which have been

significantly negatively impacted. So many Zimbabweans have lost their jobs due to scaling down of operations

in the farming sector. Rehabilitation of the power plant will bring back power supply to almost 2006 levels

hence bringing back activities to normality and creating job opportunities for women

8.2.4 Impact on Domestic Power Needs. An important aspect to be recognized is that women and girls have

suffered most due to lack of reliable electricity at household level. Traditionally, it is the responsibility of

women and girls to fetch water hence effects on water supply caused by lack of electricity has put a burden on

women and girls who have to stand for long hours queuing for water, or may have to walk long distances in

search of alternative sources of water. Therefore, the rehabilitation project will stand to alleviate the suffering of

women and girls and improve their well-being. Similarly, lack of electricity especially in urban areas, as noted,

impacted on women who have had to switch sources of energy for cooking to charcoal or wood. This has had

negative impacts on women and girls who have to go fetching wood or charcoal and also who have to endure

hazardous kitchen smoke during preparation of meals. In both instances, women and girls will benefit from time

and labor savings from either queuing or walking for long periods.

6 According to Zimbabwe National EPP-Spectrum Estimates, 2009, out of the national prevalence rate of 13.6%, women represented

60% of it and women at ages between15-24 represented 77% of the prevalence.

Page 52: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

24

8.3 Social

8.3.1 The rehabilitation project is likely to bring in direct and indirect; short-term and long-term benefits and

negative impacts to the communities around the project area and to the economy and population as a whole.

Reduction of duration of load shedding and subsequent reduction in usage of inefficient alternative fuels like

firewood, liquefied petroleum gas, diesel generators, petrol generators and paraffin. This will cut production

costs, carbon emissions and improve on efficient utilization of fuel.

8.3.2 Employment Opportunities: It is estimated that in 2010 unemployment rate was at 90% (substantially

under-employed and disguised). The project will therefore offer as direct benefits in the short-term creation of

job opportunities both during implementation and operation. Currently the operation employs 724 people with a

vacancy level of 56 against the establishment. It is, therefore, expected that once the rehabilitation works are

completed, the station will be operating at close to optimal staffing levels. During implementation the works

will be outsourced to sub-contractors who are expected to directly employ additional people though on short-

term basis. Most of these will be in skilled and semi-skilled jobs recruited from the local communities hence

contributing towards poverty alleviation for many people through the multiplier effect.

8.3.3 Boost to Economic Activities: The restoration of power generation and improved distribution will re-

invigorate the countries economic activities and boost industrial production and contribute towards poverty

alleviation which was estimated at 68% (2004) of the population living below the poverty line. Power shortages

and shedding have mostly affected manufacturing industries (which shrunk by 2% in 2009), agriculture, mining,

and services. It is estimated that due to the economic down-turn industrial performance has been at less than

40%. Reduced productivity in these industries and sectors has meant large number of jobs lost. The agricultural

sector which contributes approximately 19% to GDP and employs a large number of people has also been

adversely affected by power shortages. It is, therefore, critical to restore power supply and distribution to

optimal levels.

Health Links

8.3.4 Workers Health and Safety: Some of the expected short-term and long-term negative impacts of the

project are health and safety related. Given the nature of work and environment, the workers may be exposed to

safety and health hazard associated with coal power plants and exposure to sharp objects and to air and water

pollution. Just like is the case for the regular staff of Hwange Power Station, the sub-contractors will be

expected to adhere to safety and occupational health and environment management policy of ZPC; and

adherence to Risk Management Policies of ZESA. Compliance to the set principles shall become an integral

part of special clauses in sub-contractor’s contracts.

8.3.5 Communicable Diseases: Regarding communicable diseases, exposure to HIV/AIDS and malaria are

most critical. The prevalence rates of HIV/AIDS are estimated at 13.6% at national level. The Hwange Power

Station is an existing concern hence the risk of workers exposing themselves to the scourge of HIV/AIDS is

minimized by the on-going HIV/AIDS awareness and prevention programs guided by both ZESA and ZPC’s

Policies. The risk however, rests more on the sub-contractors who will bring in labor from outside Hwange area

and who may come to the site without their spouses. To minimize the risk, the subcontractors will be obliged to

incorporate ZPC guidelines on HIV/AIDS awareness, prevention and mitigation measures. In addition, the sub-

contractors will collaborate with district level National Aids Council to ensure parallel and long-term programs

Page 53: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

25

are implemented for the workers and communities they likely to interface with. Regarding malaria and other

water borne diseases, the project interventions especially in the ash dam and other drainage related activities

will assist in eliminating any potential for stagnant water within the project area both during implementation

and operation. Regular disposal of water at the ash dam will minimize possibility of creating such water ponds

that would be breeding areas for mosquitoes.

8.3.6 Outbreaks of Cholera and other waterborne diseases: In the recent past Zimbabwe has experienced

serous outbreaks of Cholera and other waterborne diseases. In August 2008 a nationwide cholera epidemic

resulted in 98,531 cholera cases and left 4,282 by June 2009. The underlying causes of cholera and other

waterborne diseases including typhoid are connected to the state of the water, sanitation and hygiene situation in

the country. Lack of adequate power generation has forced ZESA to load shed in so doing impacting on ability

to pump, treat and supply water to major cities, towns and growth centers. Since it takes time to fill the

pipelines after a shut-down, impact on the ability to pump is worse than indicated by the power availability

figures alone. Inability to supply water leads residents to go to unsafe sources. It also impacts on the ability of

the local authority to raise revenue from sale of water in order to pay for its costs to provide water. Based on

data from the UNICEF Report (August 2010), 7 of 10 major cities (excluding Harare) experienced power

shortages 7.9 hours per day. This project would, therefore, offer the opportunities of uninterrupted water supply

to water treatment works to ensure sufficient water is pumped and supplied to areas most needed such as highly

populated and vulnerable urban areas and growth centers.

8.4 Implementation arrangements

8.4.1 Implementation of environmental and social mitigation measures through implementation of the ESMP

is the responsibility of the Hwange Power Station Environmental Unit. The capacity in terms of human

resources, equipment and training are a critical requirement to ensure full implementation of the ESMP. The

project has included in its design re-designing the current ESMP being implemented by Hwange Power Station;

and upon recruitment of additional and dedicated environmental staff, conduct training. Approximately USD1.2

million has been budgeted for these activities including monitoring equipment.

8.5 Monitoring

8.5.1 Monitoring of ESMP implementation and adherence to prescribed mitigation measures is the

responsibility of the Chief Environmental Planner at ZESA headquarters. The Environmental Management

Agency (EMA) also plays a part in inspecting and monitoring compliance with the environmental laws. Both

EMA Officers at Headquarters and the Environmental Officer at Hwange district also play a key role in

monitoring implementation of the ESMP. The project has included in the design procurement of monitoring

equipment of pollutants and training for all environmental staff at Hwange, ZESA and EMA.

8.6 Scaling-up Institutional Capacity

8.6.1 The ESMP will take into consideration the establishment and enhancement of capacity building

concerning weaknesses of the structures and capacity for implementing, supervising and monitoring

environmental and social mitigation measures of the power plant, particularly the following weaknesses:

Page 54: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

26

Absence of the Environmental Management Unit(s) in place at any level (i.e. the Ministry of Energy,

Ministry of Energy, ZESA, ZETC and ZPC).

Lack of systematic monitoring processes and monitoring equipment.

Following fixing of the two issues above, there will be need for capacity building of ZESA and ZPC in

terms of environmental management and monitoring.

Page 55: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

27

Annex VIII.1 – ENVIROMENTAL AND SOCIAL MANAGEMENT PLAN SUMMARY

1. BRIEF DESCRIPTION OF THE PROJECT AND KEY ENVIRONMENTAL AND SOCIAL

COMPONENTS

The objective of the project is to improve the provision of adequate and reliable power supply in an

environmentally sound manner through the rehabilitation of the Hwange Power Station (HPS) and the power

transmission and distribution facilities in the country.

The envisaged project is situated in Hwange District within Matebeleland Province. Hwange district lies North

West of Harare at the very western part of the country. The district is predominantly a mining district and the

area has, in addition to Hwange Power Station, Southern Mining Coke Plant, Hwange Coal Gasification Plant,

and Hwange Colliery.

The project consists of the following main components: (A) Rehabilitation of the Hwange Power Plant

facilities; (B) Implementation of the re-designed ESMP; procurement of monitoring equipment and training; (C)

Conduct an Environmental and Social Audit and design of an Environmental and Social Management Plan; and

(D) Project Supervision and Auditing.

Project outputs will be refurbished items in the main generation blocks such as boiler feed pumps and feed

heaters in the boiler plant, turbine auxiliaries, excitation systems and induced draft fans which will lead to

increased plant capacity and reliability. Plant availability will also increase from around 65% to 90%. Other

outputs are refurbished auxiliary facilities such as the Boiler plant, Ash plant, Coal plant, cooling water pump

station at Deka and generator transformers that will result in an overall improvement in plant operations and

allow plant available capacity to increase from 450MW to 780MW.

2. MAJOR ENVIRONMENTAL AND SOCIAL IMPACTS

The project activities will mainly comprise repairs and replacement of existing equipment and limited civil

works. This will have minimum negative impacts on the local environment with waste and sludge management

and disposal being the significant source of impacts (See Annex VIII). The ESMP will clearly elucidate the

measures to be taken to protect the environment including observing proper working methods, replacement of

destroyed vegetation, ensuring proper disposal of discarded equipment and materials that may contaminate the

soil and ground water; prevention of nuisance in terms of dust, noise, odour, etc. The project provides protective

clothing for personnel engaged in the laying or cleaning of sludge / sewers and will also look at fencing and/or

covering some of the infrastructure which poses a great danger to humans such as open manholes and ponds.

Among positive outcomes, the project is proposed to remediate and mitigate a number of impacts due to lack of

maintenance of the Hwange power plant. Such works shall result in (i) significant reduction in air pollutants; (ii)

significant improvement to the coal handling and disposal system; (iii) significant improvement and safety

considerations for the Ash Dam and Ash Dam area; (iv) significant development of capacity building; and (v)

significant enhancement of the environment, livelihood and health protection of workers and people residing in

the surrounding areas.

Page 56: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

28

3. ENHANCEMENT AND MITIGATION PROGRAM

Zimbabwe Power Company / Zimbabwe Electricity Supply Authority (ZPC/ZESA) is committed to

rehabilitating and operating the Hwange Power Plant (HPP) to high environment, health and safety (EHS)

standards.

The following measures build on the design criteria for the power plant in order to reduce to a minimal level

any further potential negative impacts. Main areas where positive impacts can be introduced or maximized are

as the following.

3.1 Mitigation Program during Auditing

3.1.1 Air Quality

Emissions from the Stack:

Conduct an air quality dispersion modeling study to identify the locations of maximum concentrations of

pollutants emitted from the stack (SO2, NOx, TSP, PM10, PM2.5, CO).

Determine the most representative points to locate background air quality monitoring shelters of an air

quality monitoring system composed of at least three monitoring shelters.

Use the air quality dispersion modeling study to check the existing stack height. Examination of stack

height (around 100-110m for all stacks) should include testing of elongated stack heights up to the order

of 150m.

As a minimum requirement, the World Bank’s ambient air quality guidelines (in g/m3) for background

atmosphere will be followed.

A specialized Engineering Consulting Firm (ECF) is to be selected to undertake a comprehensive study

for identifying the most appropriate cleaning systems (pollution controllers) for the following abatement

measures:

1. Desulphurization system.

2. De-noxing processes.

3. Upgrading techniques for thermal generation efficiency.

Electrostatic Precipitators are to be refurbished for operating at full capacity, where more than 95% of

emitted dust particulates could be captured.

Emissions from the Ash Dam:

A specialized Engineering Consulting Firm is to be selected to undertake an integrated study for

identifying the most appropriate solution (pollution control measures) for the following ash treatment

issues:

1. Ash plant collection and disposal system.

2. Management of the Ash Dam:

→ Methods of preventing blown-out ash from dispersion into the atmosphere at the Ash Dam will be

investigated.

Page 57: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

29

→ Safety of the Hwange Ash Dam will be assessed and effective remedial action will be selected and

implemented immediately.

3.1.2 Effluent Water Quality

Study the potential for optimum treatment, reuse, and recycle of the effluent water in various wastewater

streams within the power plant, including: cooling tower blow-down; ash handling wastewater; material

storage runoff; metal cleaning wastewater; and low-volume wastewater, such as air heater and

precipitator wash water, boiler blow-down, boiler chemical cleaning waste, floor and yard drains and

sumps, and back-flush from ion exchange boiler water purification units.

Identify most effective ways to control/eliminate contamination arises from demineralizers; lubricating

and auxiliary fuel oils; trace contaminants in the fuel (introduced through the ash-handling wastewater

system discharge); and chlorine biocides, and other chemicals used to manage the quality of water in

cooling system.

Cooling towers blowdown will be investigated against toxic chemicals that may be present in cooling

towers additives (including chemicals containing chromium and Zink whose use should be eliminated).

Recommended water treatment and wastewater conservation methods are to be studied for best selection

of the optimum solutions.

Procure New Laboratory equipment and refurbish online analyzer equipment

Ash Handling:

Alternative Systems for ash handling, such as dry handling of fly ash, which is capable of eliminating surface

impoundments, will be studied and investigated by a specialized Engineering Consulting Firm for potential

alleviation / elimination of ash disposal related impacts. Methods of potential economic use of such ashes

should be also examined.

3.2 Mitigation Program during Rehabilitation

3.2.1 Air Quality

Dust Emissions

Implementation of good site practices including:

rehabilitation method is not blasting, but is top-down deconstruction for replaced/ removed equipment, in the

reverse order to that of construction / erection, progressive, level by level having regard to type of

replacement;

wherever possible, external non-load bearing cladding shall be removed first;

debris to be removed at frequent intervals and stockpiles shall not be allowed to build up. Waste shall be

removed on a daily basis as far as reasonably practicable;

appropriate siting and maintenance of stockpiles of demolished materials as well as reconstruction materials

so as to minimize dust blow;

minimizing drop heights for material transfer activities;

roads will be kept damp via a water bowser;

Page 58: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

30

roads will be compacted and graveled if necessary;

site roads will be maintained in good order;

regulation of site access;

sheeting of lorries transporting demolished materials and spoil;

enforcement of vehicle speed limits on dust roads to <35 km/h;

Coal Handling

Resuscitate the dust suppression system in the local plant;

Monitor quality of coal and control levels of fines; and

Modify/maintain pulverized coal ductwork to reduce incidence of pf leaks.

Ash Disposal

Look at possibility of selling the ash to road construction and cement manufacturing companies.

For ash dam dust there is need to plant grass on slopes and all exposed surfaces.

Need to compact the ash.

Install an irrigation system.

3.2.2 Liquid Effluent

Generation of site-run off

Mitigation activities will include the following:

No discharge of effluents into the surrounding environment - all effluents shall be collected and treated on

site or removed off site for treatment by approved firms.

Development of a site drainage plan which reduces flow velocity and sediment load.

Protection of temporary stockpiles of soil from erosion by using a reduced slope angle where practical,

sheeting and by incorporating sediment traps in drainage ditches.

Maintenance of well kept rehabilitation site.

Proper site management to minimize surface water run-off, soil erosion, soil remediation activities and the

impacts of liquid effluents.

Adequate maintenance of drainage systems to prevent any overflow.

Critical areas within the site shall be clearly marked and provided with protective measures to control site

run-off.

Temporary channels shall be provided to facilitate run-off discharge into the appropriate watercourses, via a

silt retention pond.

Drainage channels shall incorporate sediment basins or traps and baffles to enhance deposition rates.

Page 59: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

31

Wheel washing facilities will be installed to ensure no earth, mud and debris is deposited on roads. Sand and

silt in the wash water from such facilities shall be settled out and removed before (in line with effluent

discharge standards discharging the used water into water drains.

The contractor shall not discharge directly or indirectly into any public sewer storm water drain or any

effluent or contaminated water without the prior written consent of the site engineer in consultation with the

Assistant Plant Manager.

Contamination of the Aquatic Environment

Mitigation activities will include the following:

no discharge of effluents into the surrounding environment- all effluents shall be collected and removed off

site for treatment by approved firms;

development of a site drainage plan which reduces flow velocity and sediment load;

protection of temporary stockpiles of soil from erosion by using a reduced slope angle where practical,

sheeting and by incorporating sediment traps in drainage ditches.

maintenance of well kept construction site.

Ash Slurry System

Ash discharge lines are corroding and need to be replaced.

Noise Impacts

Implementation of good site practices including:

enforcement of vehicle speed limits;

strict controls of vehicle routing;

rehabilitation plant equipment to be fitted with silencers;

no noisy rehabilitation activities at night;

prohibition of heavy vehicle movements at night;

use of protective hearing equipment for workers;

carry out preventative maintenance of equipment and machinery to avoid excessive vibrations;

repair all steam leaks in the steam cycle;

monitor noise levels in workshops and surrounding areas;

provide the appropriate protective clothing and/or equipment; and

develop procedures for action to be taken in the event of noise levels being experienced which are above the

stipulated limits.

Socio-Economic Environment

Gender

The project is envisaged to have improvements that will benefit both men and women at project level

and wider context.

Page 60: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

32

ZPC is to make an effort to encourage more women to seek non-traditional jobs and take advantage of

existing vacancy rate which stands at 8% within HPP.

Potential relief of women’s and girls’ suffering due to reliable electricity supply at household level and

improvement to their well being.

ZPC/HPP is to create a supportive environment in order to reduce effect of HIV/AIDS on the individual

and their families due to influx of labor force to the area during rehabilitation activities.

Social

Reduction in duration of load shedding and subsequent reduction in usage of inefficient forms of

alternative energy sources.

Potential cut in production costs, carbon emissions and efficient utilization of energy sources.

Job creation will benefit surrounding communities through employing around 200 people during

rehabilitation phase and 56 people during full operation of the HPP.

Boost to economic activities via securing electricity supply enhances industry, agriculture, mining and

services and maintain jobs, which contributes to poverty alleviation.

Activities related to rehabilitation work take place on the construction site, i.e. on ZPC/HPP land.

Public and Industry Relations will be maximized through open dialogue between ZPC (through the

Assistant Plant Manager who has direct responsibility for EHS Liaison) and local authority, public and

industry representatives.

Health and Hygienic Practices

The contractors will be responsible for complete adherence to safety and occupational health and

environment management policy of ZPC and adherence to Risk Management Policies of ZESA.

Mandatory compliance to the set principles as an integral part of special clauses in Sub-contractor’s

contracts.

Waterborne Diseases

Project interventions to eliminate any stagnant water, especially in the ash dam area and other drainage

related activities for combating malaria and other waterborne diseases.

Enhance uninterrupted water supply to water treatment facilities and alleviate possible catastrophic

consequences on health and hygienic practices resulted previous due to unreliability of power supply.

Communicable Diseases

Subcontractors are obliged to incorporate ZPC guidelines on HIV/AIDS awareness, prevention and

mitigation measures.

Page 61: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

33

Subcontractors are obliged to collaborate with district levels National Aids Council to ensure parallel and

long-term programs complementing these efforts on national and local levels activities funded by agencies

such as DIFD, USAID, Global Fund and programs like “Local Aids Control Efforts (PLACE), etc., which

focus on communities including school going girls and sex workers.

Training programs and health and safety measures will include knowledge about HIV/AIDS awareness,

prevention and treatment.

Specialized service provider will be sub-contracted by the Consulting Engineer and included in the BoQ

depending on the approach.

The service provider would also talk about other communicable diseases.

The information would be imparted to construction workers especially those coming in from outside the

project area through seminars, pamphlets and peer discussions.

Occupational Health & Safety

Good local and international construction practice in Environment, Health and Safety (EHS) will be applied at

all times during rehabilitation and refurbishment activities and account will be taken of local customs, practices

and attitudes.

Asbestos Control

There is a potential for finding Asbestos Containing Materials (ACM) during dismantling or rehabilitated

processes for reconstruction or re-erection of rehabilitation parts. If found, standard good practice measures will

be implemented as follows:

any ACM present in the superstructures shall be removed before commencement of the rehabilitation

works;

removal of asbestos materials in certain locations may run more smoothly if both asbestos contractors and

civil rehabilitation contractors work in tandem. This is due to the convenience of the main civil

rehabilitation contractor providing access (scaffolding etc.) to the ACM, for the asbestos contractor and

avoiding duplication of effort;

work actually involving the removal of ACM, that involves the handling of the ACM shall be carried out

by a Specialist Asbestos Contractor;

all remaining ACM on the site is not accessible to the general public.

Waste Management

Collection, segregation, re-use, recycling, storage, transportation and disposal measures are recommended to

avoid or minimize potential adverse impacts. The Contractor will incorporate these recommendations into a

Waste Management Plan that incorporates site specific factors, such as the designation of areas for the

segregation and temporary storage of reusable and recyclable materials

Page 62: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

34

3.2 Mitigation Measures during Operation

3.3.1 Air Quality

Emissions Guidelines

Several specific measures will be taken to reduce stack emissions from the power plant and to comply

with Zimbabwean and/or the World Bank/IFC(7)

standards.

Stack emissions to the air from the Hwange Power Plant are expected to be within the Zimbabwean, as

well as the World Bank guidelines(8)

, with possible increases of some pollutants depending on the

technology employed.

To the best expectations, the Hwange power plant is intended to operate within the EMA standards or, at

least, the following WB/IFC emission guidelines:

Emissions (in mg/m3)

(Dry Gas, Excess O2 Content 6%)

Pollutant

Non-degraded

Airshed

Degraded

Airshed(*)

PM 50 30

SO2 200-850 200

NOx 510 200

(*) DA= Degraded airshed (poor air quality); Airshed should be considered as being degraded if nationally

legislated air quality standards are exceeded or, in their absence, if WHO Air Quality Guidelines are

exceeded significantly.

Air Quality Guidelines

As described above, ZPC/HPP is committed to rehabilitating the boiler house and the pollution control systems

for achieving lower levels of background concentrations of pollutants.

3.3.2 Aquatic Environment

The design of the rehabilitation works will incorporate measures to reduce impacts on the aquatic environment.

In order to minimize potential impacts to water quality, ZPC/HPP will ensure implementation of good site

management practices including the following measures:

wastewater will be collected and treated before being discharged into the discharge system;

(

7) World Bank/IFC standards are considered international standards that could be used for acceptable reference.

(8) World Bank/IFC Pollution Prevention and Abatement Handbook - Part III: Thermal Power - Guidelines for New Plants, July 1998,

and its updates of 2008.

Page 63: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

35

no solid wastes will be discharged into the liquid effluents;

design of drainage systems on site will be reviewed to prevent any contaminated surface run-off from

being discharged into the discharge system without prior oil separation and neutralization of any other

contamination; and

all effluent discharges will comply with local Zimbabwean and World Bank standards.

Put up oil interceptors at various points in the plant.

Write out procedure for handling and disposing of new and used oil.

Procure used oil receiver pneumatic operated pumps for topping up oil in engines.

Develop and implement a used oil management plan.

Avoid unnecessary spillage when decanting diesel.

Repair diesel leaks from oil burners.

Avail pump in diesel separator sump.

3.3.2 Noise Emissions

A number of noise mitigation measures will be built into the design of the plant in order to ensure that noise

levels are minimized and that all items of plant are operating to local and international standards.

Specific design mitigation measures include:

steam turbine generators, air compressors, pumps, and the emergency diesel engines will be enclosed in

sound enclosure, if necessary;

air compressors will be equipped with air silencers; and

noisy outdoor equipment will be reviewed and managed to be within to a noise limit of 90 dB(A) at one

meter.

In addition, all personnel working in noisy areas will be required to wear hearing protection.

3.3.3 Solid and Hazardous Waste Impacts

The mitigation and management measures during rehabilitation described above relate to both the rehabilitation

and operation phases.

Additional mitigation measures include:

Develop a site hazardous chemical register.

Develop a procedure for handling, transportation, storage and use of hazardous chemical.

Page 64: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

36

Develop emergency procedures to manage accidental spillage of hazardous substances i.e Clean up

procedures (SPILL PLAN).

Acquire PCB test kit to monitor PCBs in transformer oils.

3.3.4 Health and Safety

The operational health and safety measures during rehabilitation will be carried forward into the

operational phase of the power plant.

The mitigation and management measures will ensure that the health and safety of staff and any visitors on and

to the site is not jeopardized during operation of the plant.

4.MONITORING PROGRAM AND COMPLEMENTARY INITIATIVES

4.1 Baseline Audit and Environmental Survey Program

An Environmental and Social Audit (ESA) will be conducted for the Hwange Power Plant to provide a

systematic assessment of past and present environmental and social liabilities associated with the project prior

to the physical implementation of the rehabilitation program. The Audit results will constitute the findings,

conclusions and recommendations that will be carried forward into the ESMP and require follow-up actions,

namely corrective and preventive actions. The findings will be used to revise, re-design, and improve the ESMP

where necessary. The ESMP will be a condition of the loan for first disbursement.

4.2 Monitoring of Impacts during Power Plant Operation

4.2.1 Stack Emissions

Stack emissions will be monitored continuously during plant operation at a representative point in the stack.

Operational monitoring of stack emissions shall comprise monitoring the levels of: Sulfur Dioxide; Oxides of

Nitrogen; TSP; and Carbon Monoxide.

The automatic monitoring system used will be linked to an alarm to warn when emission limits for each

pollutant are being approached.

Concentrations will be recorded as hourly rolling averages and reports on stack emissions monitoring will

compare recorded emissions against determined levels and Zimbabwean and WB/IFC guidelines. Reports will

be submitted to the EMA, the AfDB and any other concerned authority on an annual basis (or as required).

4.2.2 Ambient Air Quality-Continuous SO2, NOx, C.

TSP / PM10 / PM2.5 Analyzers

The use of a continuous SO2, NOx, CO and TSP/PM10/PM2.5 analyzer allows for baseline air quality monitoring

on a continuous basis. The provision of three continuous monitors will provide the basis for “validating” the

calculations made via dispersion modeling and conditions set in the ESMP. The monitors will also include a

Page 65: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

37

weather station (embedded in the station that will be placed at the power plant site) providing data on air

temperature, wind speed, wind direction, wind direction variability and mixing heights on a continuous basis.

4.2.3 Aquatic Environment

Monitoring of impacts of the power plant on the aquatic environment will include monitoring of the quality of

the effluents discharged from the power plant.

The operational monitoring of cooling towers and effluent discharge will include the parameters summarized in

Table-6 below.

Monitoring data will be analyzed and reviewed at regular intervals and compared with Zimbabwean and World

Bank guidelines. Records of monitoring results will be kept in a suitable format and will be reported (in

summary format with any exceptions identified) to the responsible government authorities and the AfDB or any

other concerned authority as required. As a result, the project company, in discussion with the ZESA, EMA and

the AfDB, in addition to any other concerned authority, will review the need to implement any additional

mitigation features, such as provision of further water treatment facilities on site and also on the need to

continue monitoring.

4.2.4 Waste Monitoring

Wastes generated on site and collected for disposal by skilled firms will be referenced, weighed and recorded.

Environmental audits will be undertaken which will assess the quality and suitability of on- and off-site waste

management procedures.

General Monitoring for a Coal-fired Steam Power Plant

Item Monitoring

Parameters

Sampling Frequency Monitoring Locations

Baseline

A baseline monitoring program may be required if existing data is insufficient for

decision making; such a program may be more rigorous than the rehabilitation and

operation monitoring programs.

Construction/Rehabilitation Phase

Air Quality Particulate

Matter

Every 2 to 4 weeks 4 locations minimum; at

nearest residences and site

boundary

Noise Decibels(Db) Weekly 6 locations minimum: at

nearest residences and site

boundary

Vibration Weekly

Page 66: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

38

Water

Quality

Oil and

grease

Total

Suspended

Solids

BOD

Total and

fecal

coliform

Total

ammonia

Daily

Daily

Weekly

Weekly

Weekly

At all discharges including

run-off

At all discharges including

run-off and waste water

discharges

At waste water discharges

At waste water discharges

At waste water discharges

Operations Phase

Air Quality

* Gas Plants

Sulfur

dioxide

Nitrogen

oxides

Carbon

monoxide

Particulate

Matters

Continuous/passive -2/4

weeks

Continuous/passive -2/4

weeks

Continuous/passive -2/4

weeks

Continuous/passive -2/4

weeks

Noise Bi-annually to annually 6-10 sites at nearest

residences around the plant

Water

Quality of

discharge

water

Biological

Oxygen

Demand

Total and

fecal

cloakrooms

Total

ammonia

PH

Temperature

Weekly

Weekly

Weekly

Continuous with alarm

Continuous with alarm

Daily

At waste water discharges

At waste water discharges

At waste water discharges

In discharged water

In discharged water

In discharged water

Page 67: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

39

Oil and

grcase

Total residue

chlorine

Total

Suspended

Solids

Suite of

heavy metals

including

copper, iron,

zinc as a

minimum

Temperature

increase at

the edge of

the mixing

zone

Daily

Daily

Monthly

Seasonal

In discharged water

In discharged water and

wastewater discharges

In discharged water

At edge of mixing zone

5. INSTITUTIONAL ARRANGEMENTS AND CAPACITY BUILDING REQUIREMENTS

5.1 Capacity Building during Auditing

Establishment of the Environmental Management Unit (EMU) on the ZPC/HPP level.

Establishment of the Environmental Management Unit (EMU) on the ZESA level.

Establishment of the Environmental Management Unit (EMU) on the Ministry of Energy (MoE) level.

Basic training of persons employed to operate the environmental activities.

Basic training of persons employed to operate the monitoring activities.

Basic induction training for all employees on good rehabilitation and site management practice.

Capacity Building during Rehabilitation and Operation

Environmental Management Units (EMUs) at all levels: ZPC/HPP, ZESA and MoE receive support and

enhancement to undertake environmental management and monitoring activities on a continuous basis.

Basic training of persons employed to operate the environmental activities.

Basic training of persons employed to operate the monitoring activities.

Induction, specific and refresher training for all employees on good operation management practice.

Training methods, facilities & manuals

Page 68: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

40

5.2 Complementary Initiatives

ZPC/HPP/ZESA will have the overall responsibility for environmental monitoring activities and will

provide regular reporting both to the Bank and EMA as well as any other concerned authority.

EMA (as part of their regular activities), will be involved in the monitoring of the rehabilitation and

operation activities in order to ensure that proper environmental mitigation measures are employed.

The supervision missions of the Bank will validate and crosscheck whether the agencies responsible for

environmental management and monitoring have ensured that the mitigation measures have been carried

out.

Suitably qualified and experienced contractors will be responsible for the detailed design and

rehabilitation works of the power plant. Rehabilitation workers will be required to demonstrate

appropriate skills, qualifications and/or experience prior to employment.

During rehabilitation, HPP/ZPC/ZESA will ensure that all contracts with Contractors and sub-

contractors stipulate all management measures (as given in this ESMP), operational design criteria and

environment, and health and safety standards which must be implemented at the project site.

Implementation of these measures will be enforced and supervised by the Assistant Plant Manager, who

will have direct responsibility for the Environment, Safety and Quality Assurance program on site

during rehabilitation and operation. The Assistant Plant Manager is responsible for ensuring that

rehabilitation works comply with the requirements of the ESMP and all environmental permits.

During operation, direct responsibility for environmental compliance and the implementation of the

mitigation, management and monitoring measures described in this ESMP report, will continue to be

with the Assistant Plant Manager. He will report directly to the Chairman/General Manager of

HPP/ZPC/ZESA.

All staff employed at the plant will be trained in the following:

The training will include induction courses when staff are first employed at the power plant, with specialist and

refresher training as required by the job role. Training will be updated annually and occupational health and

safety procedures will be included within the Operations Manual for the power plant.

6. PUBLIC CONSULTATIONS AND DISCLOSURE REQUIREMENTS

In order to ensure that the views and interests of all project stakeholders are taken into account, a Public

Consultation was undertaken in accordance with EMA and AfDB requirements as part of the Environmental

and Social Examination process. This also included coordination with other government agencies involved in

the project, obtaining views of local people and affected groups.

The objectives of consultation and disclosure are to ensure that all stakeholders and interested parties, are fully

informed of the rehabilitation project, have the opportunity to voice their concerns and that any issues resulting

from this process are addressed in the ESMP and incorporated into the design and implementation of the

project.

The adopted methodology for the public consultation comprises basic elements, namely:

Page 69: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

41

discussions with local stakeholders and interested parties during preparation of the environmental

documents for First Examination and any local permitting requirements, including EMA requirements;

discussions with local stakeholders during Audit process and preparation of the Audit Report;

on-going consultation through an “open-door” policy during rehabilitation and operation of the power plant.

As far as public disclosure is concerned, major initiatives to inform the public and interested parties about the

rehabilitation project include the following:

disclosure of information describing the project; and

Disclosure of the Draft Final ESMP Report locally and via the AfDB Public Information Center (PIC).

During the preparation for Audit and the ESMP-Report, consultations are to be undertaken with a variety of

organizations to assist them in further identification of environmental and social concerns and the overall

development of the project. These stakeholders include the Zimbabwe Electricity Supply Authority (ZESA),

Zimbabwe Electricity Transmission and Distribution company (ZETDC), Zimbabwe Power Company (ZPC),

Zimbabwe Trust Fund (Zim-Fund), Ministry of Finance (MoF), Ministry of Energy and Power (MoEP),

Ministry of Water Resources Development and Management (MoWRDM), Hwange Power Station,

Environmental Management Agency (EMA) of Zimbabwe, and local population leaders.

The purpose of these consultations was primarily to provide information regarding the project, identify

published and non-published sources of relevant data and information relating to the site and surrounding area,

obtain views on the scope of the project, and open channels for ongoing discussions.

7. ESTIMATED COSTS

Since many of the mitigation measures presented are considered an essential, integrated component of the

rehabilitation and operation works, it is not possible to separate the specific costs of their implementation from

the overall construction and operation costs. However, an attempt for best estimate the relevant cost is presented

in the ESMP tables. The total envisaged costs is estimated around 3.62 million US Dollars, of which the Zim

Fund will ear-mark US Dollars 1.2 million.

8. IMPLEMENTATION SCHEDULE AND REPORTING

Environmental and Social Management and Monitoring activities will be implemented (according to the

ESMP), following the same project schedule, as all activities are mainstreamed in the project design.

Achievements/problems will be reported in the project quarterly progress reports and should be timely

addressed by the project management and the Bank.

Page 70: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

42

Annex VIII.2 – TOR FOR ENVIROMENTAL AND SOCIAL AUDITS

Introduction

This ToRs present the required Terms of Reference for the modalities & procedures of the Hwange Power Plant

Audit system. This is intended for use by auditors to provide a step-by-step guide to conducting an audit for the

Hwange Power Plant (HPP) from start to finish.

Being established during 1980s, the HPP had no legal requirement for a full Environmental and Social Impact

Assessment (ESIA). Due to the fact that Zimbabwe Power Company (ZPC) didn't conduct an ESIA at all, this

Audit is actually an Elaborated Audit, which includes some examination lies beyond the boundary of traditional

auditing.

1.1 The Purpose of the Auditing

In order to obtain the “Funding Approvals” of rehabilitation for the Hwange Coal-fired Power Plant, the

Zimbabwe Power Company (ZPC), an afiliate company to the Zimbabwe Electricity Supply Authority (ZESA)

has to Carryout an indepent Audit which will have to comply with the Auditing Guidelines of the AfDB.

The Bank's environmental guidelines, stipulate that when involved in financing a retrofitting or expansion

project for an existing power generation or industrial facility with significant social and environmental

consequences, an Environmental and Social Audit should be conducted which will objectively evaluate and

obtain comprehensive information on the sources, causes and impacts on the environment through a systematic,

independent and documented process. The project has, therefore, included carrying out such as an audit utilizing

the criteria developed in an ESMP against which project compliance should be evaluated.

1.2 Environmental Aspects

The operation of the Hwange Coal-fired Power Plant produces certain impacts on the local environment and the

surrounding communities.

The major aspects of the Hwange Power Plant that are presently impact the environment and the socity include

the following:

(ix) Air pollution from the stack.

(x) Air pollution from ash disposal, which is also a significant threat to the health of the surrounding

communities who are exposed to the dust.

(xi) Ash is deposited at the ash dam through wet slurry with potential threat to groundwater.

(xii) Disposal of waste water is a likely source of pollution of surface and ground water in the area.

(xiii) Accidental spillage of hazardous substances can be another source of pollution.

(xiv) Accidental release of gas from coke ovens is another potential source of air pollution at the work site and

in surrounding communities.

(xv) Current practices for the disposal of used oils, including diesel, grease and engine oil, is also a threat to

the environment.

(xvi) Fragility of the ash dam retention wall due to inadequate maintenance is a dangerous potential hazard that

could result in the destruction of the entire plant situated in the valley directly below the dam wall.

Page 71: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

43

1.3 The Consultant will have to:

1. integrate a specialized team of experts required to undertake the Audit;

2. conduct several visits, with the team of experts, to the site for carrying out site survey and data collection;

3. audit the environmental and social impacts of the operation activities; and develop an environmental

management and monitoring plan for to manage these impacts; and

4. compile, edit and prepare for final print a Final Environmental and Social Audit Report containing

standardized parts of the Audit Report.

Background

2.1 Current Status of the Power Plant

The Hwange Coal-fired Power Plant has installed capacity of 920 MW. However, current output is about 450

MW. Decline in the output is due to failure of components in both the generation blocks as well as common

station facilities.

Main items in the generation blocks that need replacement and maintenance are boiler feed pumps, feed heaters,

generator transformers, excitation system and induced draft fans.

Main items in the auxiliary (peripheral) service facilities needing refurbishment are:

Deka Pump Station: Deka Pump Station at Zambezi River is 47km from Hwange Power Plant. The

pipeline is protected from corrosion by Cathodic protection which is out of service. Water reservoirs are

both leaking and require re-lining. On top of that, the water treatment plant is in a state of disrepair and

can only produce 50% of the required water.

Coal Plant: Coal is handled by Front End Loaders (FEL) at the stock yard. Only 1 out of 3 FELs is

available. This limits the power that can be generated from the station by 50%.

H2 Plant: The hydrogen plant which produces hydrogen for cooling the six generators is only 50%

reliable and require refurbishment.

The Chlorine Plant: Chlorine is used to kill algae in the cooling water and cooling towers. This plant is

defective hence cooling tower efficiency is reduced.

Ash plants: Ash plants are 50% available. Stage I ash plant has 1 pump out of 3 in service. At Stage 2

ash plant one pumping line is available out of 2.

Ash lines: Only 2 lines out of 4 that take ash to the ash dam are working. This restricts the capacity to

move ash from the boilers to the disposal dams.

2.2 Rehabilitation and Refurbishment Project

The goal of the project is to improve the provision of adequate and reliable power supply in an environmentally

sound manner through the rehabilitation of the Hwange Power Plant (HPP).

Components included in the proposed project forms the critical activities that need to be conducted in the

rehabilitation of power infrastructure to bring the system to an acceptable level of performance. In order to

document the basis for the detailed audit of environmental impacts, the following plant design and operation

information, at a minimum, will be provided:

General description of the plant layout, buildings, and facilities.

Description of the location and design of cooling water intake and cooling water system structures.

Description of wastewater treatment facilities and other pollution control equipment.

Water balance diagram and quantities of wastewater discharge, temperature, and composition.

Description of facilities and practices for the disposal of water treatment sludges, used paints and

solvents, and other wastes.

Page 72: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

44

Description of facilities and practices for the storage and handling of oil and chemicals.

Description of the chimney design (location, height, number of flues, flue diameter, etc.).

Data on flue gas emissions (flow rate; exit velocity and temperature; emissions of sulfur dioxide,

nitrogen oxides, and total particulate matter in milligrams per cubic meter of flue gas and in nanograms

per joule of heat input).

Data on noise levels at various distances from operating plant equipment.

Description of coal handling and coal plant systems.

Description of ash disposal system and ash dame area.

Description of equipment and provisions for monitoring air pollution emissions, wastewater discharges,

and noise during plant operation.

Description of the location and design of any offsite facilities or connections to be operated by ZPC.

Description of the practices that are used to control noise, dust, erosion, and other adverse environmental

impacts during operation of the power plant and any offsite facilities.

Description of the facilities (housing, transportation, drinking water, sanitation, etc.) that are provided

for workers involved in the operation of the power plant and offsite facilities.

Summary of manpower employed at the HPP.

The Auditing Process

The auditing process takes place in 3 steps: Pre audit preparations, on site audit activities and post audit

reporting. The process is shown in Figure 1 below.

1.1. Step 1: Pre-audit preparations

The aim of pre audit preparations is to plan the on -site activities so that the audit can be conducted effectively

and efficiently. The major task during the pre audit preparations is reviewing the audit ToR, integrating the ToR

into a comprehensive audit plan and getting the audit team prepared for on site activities.

1.1.1. The Audit Plan

The audit team leader should prepare the plan for the on-site audit activities. This should be reviewed and

accepted by the auditee. This plan provides detailed information to the audit team, auditee, ZPC and ZESA. It

also facilitates scheduling and co-ordination of the audit activities. The contents of the Audit Plan will include

the following:

The reviewed Audit ToR (objectives, audit scope and criteria).

Dates and places where the audit is to be conducted.

Identification of the individuals having direct responsibilities for the auditee's organisational and functional

units to be audited including its managerial system processes (organisation chart).

Identification of the auditee’s sites and activities and (environmental) management systems that are

essential to meeting audit objectives (area and location maps).

Audit schedule (start and end dates, places, and persons to talk to including schedule of meetings with

auditee’s management, audit team meetings, inspections and interviews etc.).

References to work documents like guidelines, audit questionnaire, checklists and preliminary information

provided by the ZPC/ auditee and/or Task Manager of the AfDB.

Working and reporting language(s) of the audit.

Audit report topics, format and structure, expected date of issue and distribution.

Logistic arrangements (travel, etc.).

Budget.

Page 73: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

45

If the auditee objects to any provisions in the audit plan, such objections should be made known to the Task

Manager. They should be resolved between the Task Manager and the auditee before conducting the audit. Any

revised audit plan should be agreed between the parties concerned before or during the audit.

The extent of detail provided in the final audit plan may differ between the first and subsequent audit plans. The

details should also be adapted to suit the size and complexity of the power plant.

The audit plan should be sufficiently flexible to permit changes, such as any changes in emphasis, which may

become necessary as the on-site auditing activity progress.

Figure-1. Auditing Process

PROCESS AUDIT ACTIVITIES Supporting DOCUMENTS

1. Pre-audit

preparations

Check audit Conditions/ToR

(objectives, scope & criteria)

Audit program, ToR,

Environmental & Social

Management Plan, Project

Objectives, Project Logical

Framework

Plan audit Audit Plan

Appoint audit team

Contact auditee Audit questionnaire

Prepare work documents

Initial document review

2. Onsite

auditing

activities

Opening meeting

Page 74: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

46

Collect evidence:

Documents, interviews,

observations

Audit team meetings

Checklist,

Register of interviews,

Register of documents,

Register of observations

Audit findings:

Non-compliance/ issue of concern

Findings

Conclusions

Recommendations

Closing meeting

3. Post audit

reporting

Report Report, Environmental &

Social Management Plan

Elaborated Scope for the Audit Plan

The Auditors would identify a range of immediate environmental and safety concerns at the Hwange site, and

identify further actions that address issues identified by the Audit.

The Audit Plan should include, at a minimum requirement, the following investigations and examinations:

The major focus directed to the point source emission standards and Environmental and Social Auditing will

necessarily examine ambient air and water quality impacts, noise impacts, solid waste and socio-economic

impacts.

This investigation is presented to clearly describe the relationship between the activities and the work products

that comprise the Audit Report.

At the beginning of work, communications with concerned parties will focus on the important aspects of the

Environmental and Social Audit. A thorough discussion with representatives of various stakeholders will be

conducted.

Page 75: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

47

Local level officials from communities near the site will be contacted for information as a part of the Audit

procedures. Every effort should be taken to include broad representation from all economic and social sectors,

especially the potentially marginalized groups such as women, lower socioeconomic standard, etc.

This process will provide a basis for reviewing the issues that should be considered in the Audit. It is expected

that the issues will include fuel delivery systems, air emissions and ambient concentrations of pollutants,

impacts on water quality and quantity, development of the land surrounding the site and in the general area.

Analysis

Subsequent to gathering of data, the environmental issues will be addressed in terms of the environmental risks

associated with the operation of the power plant and the routine and non-routine operation of the facilities.

Mathematical models will be used. Mathematical models will be mainly required for modeling the air quality

impact of the stack, water impacts on the Zambezi River related to cooling water intake structures and

operations, including bankline equilibrium, bankline morphology, and noise impact in the work environment

and on the nearby community. The methods of inspection/analysis for the environmental issues not utilizing

mathematical model will follow the basic good engineering principles.

Based on practices to date, the issues to be addressed will cover, at a minimum, the following elements:

Noise impact auditing.

Air quality impact auditing.

Wastewater effluent auditing.

Solid waste auditing.

Site location and local conditions.

Socio-economic impact auditing.

Proposed environmental monitoring.

Specific focus of the Audit shall include points listed below:

Noise

Classification of site environment.

present background noise level.

Applicable noise limits and location of boundary.

Describe management plan envisaged.

Air Quality

Classification of site environment.

Present background air pollutants via thorough measurements.

Applicable ambient air quality limits for the area.

Recommended stack height and local dimensioning practice.

Recommended other pollution minimization methods / technologies that cope with the present situation.

Page 76: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

48

Wastewater & Solid Waste

Map local disposal options and associated quality requirements.

List generated types of waste and treatment existed/ recommended.

Comparison and examination.

Review Socio-economic Issues

All the impacts resulted have significant social consequences, and may also have social safeguard

issues that will have to be audited.

The findings of the Audit should indicate any subsequent studies that may be necessary if there are

social safeguard issues to be addressed.

According to this TOR, the Audit should take into account the nature, environment, human health

and safety, social and global environments aspects. The audit should consider natural and social

aspects in an integrated way. While the challenges associated with developing an integrated

approach are recognized a somewhat more consistent approach to social issues would nevertheless

be incorporated.

All these issues will be addressed in accordance with appropriate guidelines, particular those of the National

Environmental Authorities, the AfDB and the World Bank.

The recommendations will explicitly consider the mitigation measures that are considered necessary including

the effect of these measures on the operation of the power plant and most importantly the environmental

benefits. Environmental mitigation plans will also be recommended in terms of the requirements for

implementation including procedures and staff. The recommendation for, and duties of, a pollution control unit

at the plant, if necessary, will be addressed.

Review/Investigation of the Environment

This task will assemble, evaluate and present data on the relevant environmental characteristics of the

surrounding area. Data will include information on the following:

Physical environment: climate and meteorology; ambient air quality; surface and groundwater hydrology;

existing sources of air emissions; existing water pollution discharges; and receiving water quality.

Biological environment: flora and fauna including both terrestrial environment at and around the site

location, and aquatic environment, including Zambezi River; rare or endangered species; sensitive habitats,

including parks or preserves, significant natural sites, etc.; and species of commercial importance.

Present Socio-cultural environment: population; land use; planned development activities; community

structure; employment; distribution of income, goods and services; recreation; public health; cultural

prosperities; tribal peoples and customs, aspirations and attitudes.

Development of Environmental and Social Management Plan (ESMP)

This task should include details of the management initiatives to be implemented during both the rehabilitation and operation of the project. The ESMP should have three main components:

Institutional capacity issues.

Page 77: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

49

Environmental abatement/mitigation implementation program; and

Monitoring program.

Environmental Monitoring Plan

Monitoring should aim towards achieving the optimal operation performance as consistently as possible. This will require maintaining the combustion temperature and excess oxygen level within the optimal band in which PM, SO2 and NOx emissions are minimized simultaneously. Monitoring should address both emission and ambient levels of pollutants where these may be detrimental to human health.

EMA guidelines present emissions and ambient quality standards, however if not attainable for the present technology, World Bank guidelines could be used as an international guidance.

Monitoring Plan will establish a detailed procedure to monitor the implementation of abatement/ mitigating measures and continuously monitor the impacts of the project during rehabilitation and operation. The Monitoring Program should include continuous monitoring of the pollutants emitted from the facility, ambient air as well as air monitoring of the workspace (for dust, noise, etc...). The type and nature of the wastewater discharge will determine if surface water quality monitoring will be required. Costs of the monitoring facilities will be estimated.

1.1.2. Audit Conditionalities (ToRs)

The audit conditionalities/ToRs should as a minimum address the following items:

1. Start date: Begin date of the audit.

2. Status: Compliance, pre-approval or other audit).

3. Audit objective, scope and criteria.

4. Information and facilities: Information and facilities required for the audit.

5. Timing in operation cycle: specification of when the audit(s) take place in the operation cycle.

6. Reporting: Date and type of report required.

7. Confidentiality: Requirements concerning confidentiality.

8. Independence: Requirements concerning independence of auditors.

When the audit is scheduled the set conditions or the ToR needs to be reviewed prior to execution and worked

out more in detail. When the Task Manager has approved the set conditions or the ToR, the auditors should start

preparing the audit plan. Following the designation of the audit team, the audit team members work the audit

plan out more in detail.

1.1.3. Audit objectives

Objectives of the Audit include the following:

To determine the extent of compliance of the auditee with the power plant Environmental & Social

Management or Action Plan and or any environmental/social conditionalities in the project loan.

To determine the extent of compliance of a project with national legislative requirements.

To provide an in-depth view of environmental and social remedies associated with the power plant

operation.

1.1.4. Audit scope

The audit scope describes the extent and boundaries of the audit in terms of factors such as location and

boundaries, activities, organisation(s) and processes. The scope is plant dependent and should be decided by the

Task Manager. The audit scope should address the following issues:

Page 78: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

50

- The auditee’s organisational and functional units to be audited (institutional boundaries).

- The auditee’s area, sites / locations and activities (physical and geographical boundaries).

- Consultations with organisations other than the auditee (e.g. governmental organisations, NGO’s, power

plant beneficiaries).

- The time period covered by the audit.

- The focus (within the scope area, topics requiring specific attention).

1.1.5. Audit Criteria

Audit criteria are the policies, procedures, requirements or standards against which collected evidence is

compared. These audit criteria should be selected. They should be:

- In line with the audit objective.

- Relevant to the power plant or plant organisation (auditee).

- As specific as possible to avoid discussions on the legitimacy of findings during the close out meeting and the

report.

- Understood by the audit team and agreed upon with the auditee.

In the conditions/ToRs drafted in the framework of the of the audit program the criteria may be defined in

general. During audit plan preparation the criteria should be made as specific as possible. Audit criteria may

include:

Plant specifics:

Environmental Management Plan resulting from an assessment.

Logical Framework developed by Task Manager for plant supervision.

Company / organisation policies (where existing).

ADB policies & guidelines:

AfDB Environmental and Social Auditing Guidelines

AfDB Environmental and Social Assessment Procedures (ESAP)

AfDB Policies on Environment: Population & Health, Population Policy, Gender Policy, Poverty

Alleviation.

AfDB Guidelines for the Industry Sector.

AfDB Easy Reference Guides: PIPA ERG, PISCE ERG.

Other MFI Guidelines:

World Bank Pollution Prevention Handbook.

Industry Best practice.

Best practice manuals (e.g. Power Generation Sector).

Legislation:

Relevant international conventions and national legislation in Zimbabwe (the country of audit).

National Action Plans of Zimbabwe.

The audit objective, scope, audit criteria and any subsequent changes to these should be agreed upon with the

audit client and the auditee.

Page 79: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

51

1.1.6. Establishing the audit team

The audit team is established in consultation with the Task Manager and may comprise of auditors, auditors-in-

training and technical experts, working under the direction of the audit team leader.

1.1.7. Audit team tasks

The audit team is appointed in consultation with the Task Manager. The audit team leader, in consultation with

the audit team, should assign to each team member responsibility for auditing specific management processes,

functions, sites, areas or activities. Such assignments should take into account requirements for auditor

independence, expertise and efficient use of the resources. Changes to the work assignments may be made to

ensure the achievement of the audit objectives. The audit team members should review all relevant information

related to their audit assignments and prepare any work documents required for those assignments.

1.1.8. Initial contact with the auditee

The audit team leader should contact the auditee to establish communication channels, request documentation,

records, or other information if needed, and to initiate the arrangements (e.g. logistic) for the audit. An Audit

Questionnaire can be used to facilitate the collection of information. The need for a guide for the audit team

should be agreed.

1.1.9. Audit questionnaire

A specific Audit Questionnaire for the power plant should be developed by the audit team and sent to the auditee

to provide the audit team with information on past and present environmental and social conditions associated

with the power plant. The questionnaire should be plant and audit specific (focussed on the objective, scope and

criteria). The plant specific questionnaire should be as specific as possible to avoid being overloaded with non-

relevant information or information that cannot be used as audit evidence.

1.1.10. Working documents

Working documents are documents that should be used to guide and support an individual audit. Most of these

working documents are standard documents. These working documents are generic and should only be used as

guidelines and should not restrict the scope of audit activities, they should be made specific to each audit.

Working documents that can be used by the audit team include:

- Initial documented information provided by the ZPC / auditee and or Task Manager.

- The Registers to record information: of Findings, Interviews, Observations and Documents.

- Audit Checklist (generic).

- Audit Questionnaire (generic).

- Template for the Audit Report.

- Template for an Environmental & Social Management Plan.

The working documents are contained in. Working documents should be retained as specified in the relevant

documented procedures, at least until audit completion; the audit team members should suitably safeguard those

involving confidential or proprietary information.

1.1.11. Initial document review

Relevant project management documentation and records belonging to the auditee, possibly including recent

audit reports, should be subjected to an initial review by the audit team to prepare the audit plan including

working documents or the drafting of preliminary findings.

Page 80: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

52

The documentation should be reviewed for its adequacy, taking into account the size and complexity of the

power plant, and the objectives of the audit. If insufficient or inadequate information is available, further

requests should be made to gather additional information.

If the documentation is found to be inadequate, such that it does not satisfy the audit objectives or scope, the

ZPC and the auditee should be informed. Further resources should not be expended on the audit until such

concerns are resolved to the satisfaction of the audit team leader.

1.1.12. Audit Checklist

The Audit Checklist is a generic checklist containing lists of items that need to be arranged and issues that need

to be addressed while preparing and conducting the audit. As such the audit checklist provides an easy reference

tool for auditors, in particular for the team leader to check if all issues have been covered. Parts of the generic

audit checklist provided in the working documents should be made specific to the type of the power plant, audit

objective, scope and criteria and initial document review. The audit checklist should be used as a general guide

only as during the conduct of the audit. There are most likely more and other issues that need to be addressed

and more questions that should be asked during the on site audit.

1.2. Step 2: On site auditing activities

The execution of the audit in the field i.e. `on -site` involves an opening meeting with the ZPC, document

reviews, inspections, interviews, (team) meetings, preparation of findings and a close out meeting.

1.2.1. Opening meeting

An opening meeting should be held with the auditee’s management, and where applicable, representatives of the

plant’s owner company. Opening Meeting Checklist will include:

mutual introduction of the participants, including an outline of their roles and encouragement of active

participation in the audit;

review of the audit objectives and scope;

agreement on the audit timetable and other relevant arrangements with the auditee, such as the time and date

for the closing meeting, any interim meetings between the audit team and the auditee's management, and

any late changes;

a short presentation of the methods and procedures to be used to conduct the audit;

confirmation of official communication links between the audit team and the auditee;

confirmation that any resources and facilities needed by the audit team are available;

confirmation of matters relating to confidentiality;

confirmation of relevant work safety, emergency and security procedures for the audit team;

confirmation that during the audit, the auditee will be kept informed of progress and, if the audit objectives

appear to become unattainable, the audit team leader will discuss the reasons with the auditee and the ZPC;

confirmation of availability, roles and identity of any guides; and

confirmation of logistics and check whether it is allowed to take photographs.

1.2.2. Roles and responsibilities of guides

A guide, where assigned, should assist the audit team and act on request of the audit team leader. They may

witness the audit on behalf of the auditee and also have additional duties, such as ensuring that rules concerning

safety and security procedures are known and respected by the auditors on site. Care should be taken by the

auditors to ensure that guides do not exercise undue influence or interference.

Page 81: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

53

1.2.3. Orientation tour

Prior to the document reviews, inspections and interviews an orientation tour should be organised to provide the

audit team with a general overview of the project area or location and its current activities. The audit team leader

in consultation with the auditee should chalk out the route. A typical orientation tour takes approximately 10%

of the time available for onsite activities. While doing the orientation tour the audit team should take notes on

any situation related to the objective of the audit as they may influence the original audit plan.

1.2.4. Collecting and verifying information: Documents

Information should be collected to allow the audit team to determine whether the audit objectives will be met.

Some information may have been collected during the pre audit preparations and some may have been collected

by the auditee for review. The auditors, using alternative sources where necessary should verify, using various

types available for measurements, the information collected during the audit. Such information, after

verification, can be considered to be audit evidence. Information may be obtained and verified in different ways

from several sources, which include:

interviews;

observations of activities and the surrounding work environment and conditions;

documentation, for example; contracts, policy, objectives, plans, documented procedures, instructions,

licences and permits, specifications, drawings, orders;

documents; records, such as inspection records, meeting minutes, reports or logbooks on customer

complaints, audit reports, monitoring programmes and existing results of measurements;

data summaries, analyses, metrics and performance indicators;

reports from other sources, for example, customer or beneficiary feedback, regulatory authorities inspection

reports and external reports;

any sampling programmes, quality control of sampling and measurement processes.

any measurements, using appropriate instrumentation and measuring equipment, for any of the measured

parameters, such as gaseous pollutants from the stack and background concentrations of pollutants in the

ambient atmosphere; and

any modelling techniques that is used for identifying the locations of maximum pollutants concentrations for

best measuring the direct effect from the power plant.

1.2.5. Communication with the auditee

During the audit, the audit team leader should periodically communicate the status of the audit and any concerns

to the auditee as appropriate. Any concern about an issue outside the scope of the audit should be noted and

reported to the audit team leader, for possible communication to the AfDB Task Manager and auditee. Any need

for changes in scope, which may become apparent during on-site auditing, should be reviewed with and

approved by the Task Manager.

Where the available evidence indicates that the audit objectives are unattainable, the audit team leader should

report the reasons to the Task Manager and auditee to determine the appropriate action, which may include

termination of the audit or a change in the audit objectives.

1.2.6. Audit findings

Collected evidence should be evaluated against the audit criteria to generate the audit findings. An audit finding

can either be a Non-conformance or an Issue of Concern. Audit findings are based on information collected

through document review, inspections and interviews.

Page 82: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

54

Non-conformance

A non-conformance is a statement of fact about the deviation or deficiency of the auditee in fulfilling a criterion.

The statement contains a clear and concise description of the departure from a specific criterion.

Issue of concern

An issue of concern is a clear and concise statement of fact which indicates a potential departure / or deviation

from the criteria, a concern over an issue not previously identified as a criterion.

Findings should be supported by objective evidence gathered through document review, inspections, modelling

& measurements and interviews and should as a minimum contain the following information:

- A clear and concise statement of facts describing the non-conformance including the time / date and

location.

- Reference to documents, observations, modelling & measurements and interviews that support the non-

conformance as evidence.

- Reference to applicable criteria.

Audit findings must be recorded in a clear and concise manner and understood by the auditee and supported by

audit evidence.

The audit team should review and make final decisions about the audit findings (Non-conformances & issues of

concern) and the supporting audit evidence during the audit team meetings at the end of each audit day. The

audit findings should be accepted by:

- The interviewed persons (at end of the interview).

- The auditee representative (end of the day) to obtain acknowledgement of the factual basis.

- The auditee’s management (end of the audit).

Every attempt should be made to resolve any divergence of opinion concerning the facts, and unresolved points

should be recorded.

The information collected during an audit will inevitably be only a sample of the information available, since an

audit is conducted during a limited period of time and with limited resources. There is thus an element of

uncertainty inherent in all audits, and attention of users of the audit conclusions should be drawn to this

uncertainty.

1.2.7. Conclusions

The conclusions should be based on the findings and provide a true picture of the compliance status of the power

plant. Whereas findings are based on objective evidence providing a list of non compliance’s and issues of

concern, the conclusions reflect the opinion of the audit team on the situation taking into account the criticality

and significance of each finding in relation to the criteria and project objective.

1.2.8. Recommendations: Environmental and Social Management Plan (ESMP)

The recommendations should focus on the establishment of an Environmental & Social Management Plan

(actually an elaboration, and possibly completion or refinement, to the revised / redesigned ESMP presented by

the AfDB), in addition to any corrective and preventive measures (compliance audit).

Page 83: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

55

Recommended ESMP, including any corrective and preventive measures should be formulated based on the

conclusions and be specific for the direction in which solutions for identified problems can be sought. The

recommendations made by the audit team can be shared with the auditee during the closing meeting. The

formulation of concrete recommendations is the joint responsibility of the auditee in close cooperation with the

AfDB's Task manager and is not the prime responsibility of the audit team as this would jeopardise the position

of the audit team when conducting any follow up audit.

1.2.9. Preparation for the closing meeting

The audit team should confer prior to the closing meeting. The issues that should be discussed include:

review the findings and any other appropriate information collected during the audit;

prepare a complete list of audit findings;

write out list of non-conformities and issues of concern;

reach consensus on the audit conclusions –the team leader has the final word and decision;

agree on roles and tasks for the closing meeting;

prepare recommendations, including ESMP; and

Discuss subsequent audit follow-up, if applicable.

1.2.10. Closing meeting with the auditee

A closing meeting, chaired by the audit team leader, should be held with the auditee's management and those

responsible for the functions audited. The purpose of this meeting is to present audit findings to ensure that they

are clearly understood and acknowledged by the auditee.

Any outstanding diverging opinions between the audit team and the auditee should be discussed and if possible

resolved. If not resolved, both opinions should be recorded. A record of the closing meeting should be made.

The audit team leader should then present the team's conclusions and recommendations. Any comments by the

auditee should be noted. The conclusions and recommendations remain the final responsibility of the audit team.

1.3. Step 3: Post audit reporting

The final stage of the audit involves producing an audit report stating the findings, conclusions and

recommendations. The wording of the findings should not deviate from those agreed upon in the closing

meeting.

1.3.1. Audit report preparation

The audit team leader is responsible for the preparation, accuracy and completeness of the audit report.

1.3.2. Report content

The audit report provides an accurate record of the audit and should be based on the Environmental and Social

Audit Report template (see Annex 1) unless there are good reasons to deviate from this format. The requirement

for an Environmental and Social Management Plan as an addendum to the report should be discussed with the

AfDB's Task Manager.

Page 84: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

56

The audit report should contain the following information:

Executive summary

Table of contents

Introduction

Project description

Audit objective, scope and criteria

Audit process

Audit team

Findings

Conclusions

Recommendations, including ESMP

Annexes

1.3.3. Report approval and distribution

The audit report should be issued within 4 weeks after the closing meeting. The report should be sent to:

- Task Manager/Project Officer.

- Division Chief.

- AfDB.

- Auditee.

- ZPC.

- ZESA.

The audit report should be dated and signed by the audit team leader and reviewed and approved as defined in

appropriate documented procedures. The audit report is the property of the ZPC and confidentiality should be

respected and appropriately safeguarded by the audit team members and all report recipients.

1.3.4. Retention of documents

Work documents and reports pertaining to the audit should be retained or destroyed (depending on

confidentiality) by agreement between the Task Manager and audit client.

1.3.5. Audit completion

The audit is completed when all activities in the audit plan have been concluded, including the distribution of the

approved audit report.

Page 85: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

57

Audit Report (Appendix 1)

Introduction

It is recommended that the audit report include at least the following sections. Data that can be used direct from

AfDB documents in the AfDB Audit System and Working Documents are indicated in italics. Data that can be

obtained from AfDB documents are in bold.

Generic Audit Report

i Colofon

Name of Client

Signatures of the audit team members and the representative of the auditee

ii Executive Summary

A concise summary of all significant environmental and social areas of non-conformance and issues of

concern and a brief summary of the conclusions and recommendations (including ESMP).

iii Contents

The contents of the report should include the following sections:

1. Introduction

Client and auditee

2. Project Description:

Concise description of the project, the project organisation, the area / location and past and current

operations. The description should focus on project components with potential environmental and social

aspects in line with the defined audit objective, scope and criteria.

3. Audit Objective, Scope and Criteria

Audit objective, Scope and Criteria

4. Audit Process

Audit Plan: The date of the audit and brief description of the process e.g. pre audit activities, on site audit

activities including site inspection, interviews and document reviews and post audit activities. Exceptions

and deviations from the audit plan

5. Audit team

Audit Team: This section includes names of the audit team leader and team members

6. Findings

List of Findings; This chapter contains the individual findings of the audit subdivided in :

Non conformances

Issues of concern

The above paragraphs may be subdivided with headings based to the type of issues (environmental and

social) or the type of criteria applied.

7. Conclusions

Contains conclusions based on aggregated level, criticality or significance of the individual findings in

relation to the audit objectives, scope or criteria.

Page 86: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

58

8. Recommendations

Contains (a set of) recommendations concerning corrective actions (compliance audit) and the

establishment of an Environmental and Social management Plan based on the audit findings and

conclusions

Annexes

1. Project organisation chart (auditee)

2. Area, location chart

3. Criteria (detailed list of the criteria)

4. Register of documents

5. Register of interviews

6. Register of observations

7. Register of modelling studies and measurements conducted.

Page 87: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

59

ANNEX IX.1 – Project Implementation Schedule

Activity Responsible

POC approval project pipeline / Brief MMUProject preparation and appraisal MMU/ORSA/ONEC Zim Task Force (Zim TF) Zim TFOperations Committee (OC) Approval OCPOC Project Appraisal Approval POCNegotiation MMU/ORSA/ONECTranslation and processing for Board MMU/NECBoard Approval BoardSigning GECL/GOZEffectiveness GECL/GOZRecruitment of engineering supervision consultant Procurement Agent (PA) and MMUDesign and preparation of works bidding docs PA & Eng. Consultant Prequalification of Contractors & Env. Consultants PA & Eng. Consultant

Procurement of Contractors & Env. Consultants PA, PMTs and eng. ConsultantRehabilitation Works PMTs, Eng. Consultant and Works contractors Environmental and Social Audit Env. ConsultantProject completion

1Advance Contracting is considered for the engineering consultant the advance contracting can only start when the procurement agent is on the ground

Feb Oct Nov DecApr May Jun Jul Aug SepSep Oct Nov Dec Jan

Schedule for Emergency Power Infrastructure Rehabilitation Project

2010 2011 2012Oct Nov Dec Jan Feb Mar MarApr May Jun Jul Aug

Page 88: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

60

ANNEX IX.2 Procurement Plan

Procurement Packages with Methods

and Time Schedule

Description*Lot

NumberIFP Received

IFP No-

Objection Date

IFP Publication

Date (UNDB)

Estimated

Amount in UA

(Million)

Lumpsum or

Unit Rate

Procurement

Method

Pre-

Qualification

(Y/N)

Dom/Reg.

Preference

(Y/N)

Prior or Post

Review

Bid Closing

Date

Plan/

Revised/

Actual

Bid

Documents

Received

No- Objection

DatePQ Doc Issued Closing Date

Evaluation

Report

Received

No- Objection

Date

Bid Invitation

Date

Bid Closing-

Opening

Bid

Evaluation

Report

Received

No- Objection

Date

Draft

Contract

Received

No- Objection

Date

Contract

Amount in

UA(000)

Date

Contract

Award

Date

Contract

Signature

Start Date End Date

1 15 August 2011 18 August 2011 25 August 2011 14.870 Unit Rate ICB Yes Not Applicable Prior 19 Dec. 2011 Plan 17 Oct. 2011 24 Oct. 2011 25 August 2011 06 Oct. 2011 27 Oct. 2011 03 Nov. 2011 07 Nov. 2011 19 Dec. 2011 12 Jan 2012 25 Jan. 2012 8 Feb. 2012 10 Feb. 2012 25 Jan. 2012 15 Feb. 2012 15 Feb. 2012

Revised

Actual

2 22 August 2011 25 August 2011 01 Sept. 2011 14.960 Unit Rate ICB Yes Not Applicable Prior 22 Dec. 2011 Plan 17 Oct. 2011 24 Oct. 2011 01 Sept. 2011 13 Oct. 2011 03 Nov. 2011 07 Nov. 2011 10 Nov. 2011 22 Dec. 2011 19 Jan 2012 02 Feb 2012 15 Feb. 2012 17 Feb. 2012 02 Feb. 2012 24 Feb. 2012 24 Feb. 2012

Revised k

Actual

Bid Documents Bidding PeriodPre-Qualification Pre-QualificationBasic Data

Transmission and Distribution Rehabilitation

Draft ContractBid Evaluation

Ash Plant Rehabilitation Hwange Thermal

Power Station

Contract ImplementationContract Award

Procurement Packages with

Methods and Time Schedule

Description*Date EOI

ReceivedDate No-Objection

Selection

Method

Lumpsum or

Time-Based

Estimated

Amount in UA

(Million)

Prior/Post

Review

Bid Closing

Date

Plan/

Revised/

Actual

Date

Published

Closing

DateDate Received

Date No-

Objection

Date

Received

Date No-

ObjectionDate Received

Date No-

ObjectionIssuance Date

Submission/

Opening

Date

Submission

Evaluation

Report (T)

No-objection

Evaluation

Report (T)

Opening

Financial

Proposals

Draft

Contract

Received

Draft Contract

Amount in

Currcy. (000)

Date No-

Objection

Final

Contract

Received

Contract

Amount in UA

(000)

Contract

Award Date

Contract

SignatureStart Date End Date

Not Applicable (a) Not Applicable (a) QCBS Lumpsum 2.000 Prior 26 May 2011 Plan 01 Mar 2011 15 Mar 2011 07 April 2011 14 April 2011 07 April 2011 14 April 2011 07 April 2011 14 April 2011 21 April 2011 26 May 2011 09 June 2011 23 June 2011 30 June 2011 14 July 2011 21 July 2011 30 July 2011 21 July 2011 30 July 2011 30 July 2011

Revised

Actual

01 April 2011 08 April 2011 QCBS Lumpsum 1.200 Prior 01 July 2011 Plan 15 April 2011 29 April 2011 13 May 2011 20 May 2011 13 May 2011 20 May 2011 13 May 2011 20 May 2011 27 May 2011 01 July 2011 15 July 2011 29 July 2011 05 August 201119 August 2011 26 August 2011 02 Sept. 2011 26 August 2011 02 Sept. 2011 02 Sept. 2011

Revised

Actual

03 Nov. 2011 10 Nov. 2011 LCS Lumpsum 0.500 Prior 30 Jan. 2012 Plan 17 Nov. 2011 01 Dec. 2011 15 Dec. 2011 22 Dec. 2011 15 Dec. 2011 22 Dec. 2011 15 Dec. 2011 22 Dec. 2011 02 Jan. 2012 30 Jan. 2012 13 Feb. 2012 27 Feb. 2012 05 March 2012 19 March 2012 26 March 2012 02 April 2012 26 March 2012 02 April 2012 02 April 2012

Revised

Actual

Total Cost 3.70 Plan 0.00

0.00 Revised

0.00 Actual 0.00

Draft Contract Contract AwardShort List Proposal PeriodRequest for Expression of

Interest

Procurement of Engineering Supervision

Consultant

Accounts Audit Services

ESIA Audit and ESMP Production

Basic Data Terms of Reference Request for ProposalBid Evaluation

Technical (T) & Financial (F)Contract Implementation

Page 89: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

Annex IX.3 SHORT TERM EMERGENCY RECOVERY PROGRAMME (STREP) –

BUDGET

Sector Requirement

($ million)

Humanitarian assistance 640

Agricultural support 980

Water & sanitation 1,040

Local authorities 450

Other public infrastructure (trunk & access roads, bridges and rail) 600

Health 820

Education 800

Civil service skills retention 890

Electricity 1,040

Power imports 60

Power transmission & distribution

networks rehabilitation

80

Kariba South Bank extension 400

Hwange 7 & 8 expansion 500

Total 7,260

Lines of credit for companies 1,150

Grand Total 8,410

Page 90: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

62

Annex X - ZESA HOLDING GROUP PERFORMANCE ANALYSIS

10.1 ZESA Institutional Framework and Industry Structure

Following the passing of two Acts by the Parliament of Zimbabwe, the Electricity Act

(Chapter 13:19) and the Rural Electrification Fund Act (Chapter 13:20) comprehensive

reforms have since been experienced in the electricity industry. The Electricity Act also

ushered in the formation of five successor companies, the Zimbabwe Power Company (ZPC),

Zimbabwe Electricity Transmission Company (ZETCO), Zimbabwe Electricity Distribution

Company (ZEDC), ZESA Enterprises and Powertel Communications.

In line with the approved structure, all power generation assets and operations are under

ZESA Holdings generation subsidiary, the Zimbabwe Power Company (ZPC) formed in

October 1996. Distribution assets and supply functions fall under the Zimbabwe Electricity

Distribution Company (ZEDC), ZESA Enterprises, another subsidiary of ZESA Holdings

comprises of four business units namely ZESA Technology Centre, Production and Services,

Transport Logistics and Projects. It is a flexible investment arm for ZESA Holdings that has a

diversified business portfolio. Transmission grid assets and operations fall under the

Zimbabwe Electricity Transmission Company (ZETCO),

A separate Rural Electrification Fund, a Board and Agency have been set up under the Rural

Electrification Fund Act, passed in January 2002. The Agency is administering a special fund

formed under this Act to finance rural electrification projects. The Board is accountable to the

Minister of Energy and Power Development.

Zimbabwe Electricity Industry Structure

MINISTRY OF ENERGY & POWER DEVELOPMENT

ZIMBABWE ELECTRICITY REGULATORY COMMISSION (ZERC)

Independent Power Producers (IPPs)

ZESA HOLDINGS (PVT) LTD

ZIMBABWE POWER COMPANY (PVT) LTD (ZPC)

ZIMBABWE ELECTRICITY TRANSMISSION AND

DISTRIBUTION COMPANY (PVT) LTD (ZETDC)

ZESA ENTREPRISES (PVT) LTD (ZENT)

RURAL ELECTRIFICATION AGENCY (REA)

Page 91: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

63

10.2 Staffing and Human Resource Development

The severe brain drain of technical and professional staff continued during 2008 when the

group lost 43 engineers, 122 artisans/technicians, 9 accountants and 13 IT personnel. The

year 2009 witnessed a slowdown of the brain drain with a loss of 8 engineers 29

artisans/technicians and 2 IT personnel. In response to the loss of skills to the diaspora

particularly to Britain, Australia, New Zealand, Botswana, Namibia and South Africa, efforts

were made to attract skilled former ZESA employees in order to minimize the gap created by

the brain drain. Assessment interviews were carried out and 57 candidates have so far been

appointed to vacant posts. The exercise is ongoing since there are still some vacant posts to

be filled. The table below shows the Group’s Human Resources by Employee Categories:

ZESA Group Manning Levels – Dec. 2009

Employee Category Established

Strength

Var.

% in

Place Male Female Total

Exec. Mgmt. 9 8 0 8 1 89

Snr. Mgmt. 68 58 7 65 3 96

Mid. Mgmt 205 141 25 166 39 81

Professionals 824 555 79 634 190 77

Skilled 1664 976 179 1155 509 69

Semi-Skilled 4509 3066 454 3520 989 78

Gen. Workers 235 75 8 83 152 35

Total 7514 4879 752 5631 1883 75

10.3 Accounting, Internal Control and Audit

The directors are responsible for the maintenance of adequate accounting records as well as

the preparation and integrity of the financial statements and related information in a manner

that fairly presents the state of affairs and the results of the Group’s operations. External

auditors (KPMG Chartered Accountants (Zimbabwe)) are responsible for carrying out an

independent examination of the financial statements in accordance with International

Standards on Auditing and reporting their findings thereon.

The directors are also responsible for the Group’s systems on internal financial control. There

are designed to provide reasonable, but not absolute, assurance as to the reliability of the

financial statements and to safeguard, verify and detect misstatement and losses.

In preparing the Group’s financial statements, appropriate accounting policies have been

applied, as have the relevant International Financial Reporting Standards, unless otherwise

stated and are supported, where necessary, by reasonable and prudent judgment and

estimates.

10.4 Financial Performance

The operating environment for the year ended 31 December 2009 improved significantly

from that obtaining in 2008 mainly because of the introduction of a multicurrency system

which saw inflation tumbling and many economic and business variables stabilising.

However as the year progressed new challenges crept in, the major one being liquidity

problems that seriously inhibited economic activity. The group adopted the United States

Dollar (USD) as its functional currency with effect from 1st February 2009. Year on year

inflation which rose to reach about 231,000,000% in July 2008 after which compilations was

Page 92: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

64

suspended tumbled to an average of 7.9% in 2009 as availability of goods improved mostly

through imports. This brought about stability in planning and operations of the Group.

The jump of the tariff from the Z$ one which in USD terms was almost zero to the adjusted

new tariff of 7.53 USc/kWh was too high for customers who were affected by the

combination of the global financial crisis and liquidity challenges in the local economy

resulting in many customers defaulting and the Group experienced liquidity problems. The

rollout of a prepayment meter program in 2010 helped the utility to earn revenues of about

USD 40 million per month as compared to USD 6 million earned in previous months.

Total loans as at 30 September 2010 amount to US $426.6 million, of which foreign loans

constitute USD309.1 million that is 72% of the total loans and local debt makes up 28% or

USD117.5 million of the total debt. Out of the total loan amount, USD 395.1 million or 93%

make up the current portion, which represents loan capital repayments falling due within

twelve months.

ZESA Holdings Group Management Accounts for period ending 30 September 2010 are

presented in the remaining sections of this annex. It is worth noting that the external auditors

had expressed an adverse opinion on the group financial performance and cash flows and

qualified opinion on the group financial position as reported to the honourable minister of

Energy and Power Development in the independent auditors’ report of 30 September 2010

accompanying ZESA holdings group annual report 2009. The basis for stated auditors’

opinion and qualifications relate to the effects of changes in foreign exchange rates and

financial reporting in hyperinflationary economies in addition to reliance on estimate rather

than actual usage to determine revenue relating to Zimbabwe Electricity Distribution

Company (private) Limited, a subsidiary of ZESA holdings (Private) Limited and lack of

audit evidence to determine the reliability of the estimates and evaluate whether revenue is

materially misstated and the corresponding effects on trade receivables.

Page 93: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

65

STATEMENT OF COMPREHENSIVE INCOME FOR PERIOD ENDED 30

SEPTEMBER 2010

THIS MONTH YEAR TO DATE

DESCRIPTION NOTES ACTUAL BUDGET VARIANCE % ACTUAL BUDGET VARIANCE %

Revenue

Electricity Sales 1.1 39 091 545 50 484 700 (11 393 155) ( 23) 379 331 440 503 627 877 (124 296 437) (25)

Other Income 1.2 5 184 584 7 086 001 ( 1 901 417) ( 27) 44 187 357 59 073 905 (14 886 548) (25)

Total Revenue 44 276 129 57 570 701 ( 13 294 572) (23) 423 518 797 562 701 782 ( 139 182 985) (25)

Expenditure

Payroll Costs 2.1 9 865 945 9 022 179 (843 766) ( 9) 83 120 175 79 452 538 ( 3 667 637) ( 5)

Generation Costs 2.2 5 663 619 21 746 341 16 082 722 74 71 674 703 193 181 886 121 507 183 63

Electricity Imports 2.3.3 4 589 773 8 305 800 3 716 027 45 49 719 277 71 143 534 21 424 257 30

Transmission & Distribution Costs 2.3 3 914 428 9 424 681 5 510 253 58 51 480 149 73 200 470 21 720 322 30

ZESA Holdings 2.6 271 897 2 105 089 1 833 192 87 2 271 172 2 290 089 18 917 1

ZESA Enterprises 2.5 1 475 286 2 204 481 729 195 33 15 705 324 17 721 096 2 015 772 11

Powertel Communications 2.4 589 262 418 155 (171 107) (41) 3 487 328 3 339 942 ( 147 386) (4)

Provision for Bad debts 2.3 1 584 007 79 621 (1 504 386) (1889) 31 508 451 732 464 (30 775 987) (4202)

Depreciation 7 020 052 7 516 986 496 935 7 63 189 192 66 038 608 2 849 416 4

Total Expenditure 34 974 269 60 823 334 25 849 065 42 372 155 771 507 100 627 134 944 856 27

Operating profit

before finance charges 9 301 861 (3 252 633) 12 554 493 386 51 363 025 55 601 155 (4 238 129) (8)

Finance Charges

Exchange Differences 6 114 197 318 904 (5 795 294) ( 1 817) (2 260 080) 2 121 260 4 381 340 207

Foreign Loans Interest 1 340 655 1 902 534 561 879 30 13 799 891 13 574 912 ( 224 979) (2)

Other Finance Charges 920 620 466 000 ( 454 620) ( 98) 5 618 227 2 914 101 (2 704 125) (93)

Net Profit/ (Loss) 926 389 (5 940 070) 6 866 459 116 34 204 987 36 990 881 ( 2 785 894) (8)

Page 94: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

66

STATEMENT OF COMPREHENSIVE INCOME BY COMPANY

ZESA HOLDINGS

POWERTEL

COMMUNICATIONS

ZESA

ENTERPRISES ZPC ZETDC

DESCRIPTION

REVENUE

Sale of electricity 0 0 0 18,356,512 360,974,928

Inter-Company electricity sales 0 0 0 170,214,826 0

Interest receivable 1,551 0 613 0 6,374,577

Connection fees 0 0 0 0 3,996,856

Non Core subsidiary Income 483,745 2,369,470 1,337,041 0 0

Miscellaneous income 75,321 60,147 172,021 699,418 3,592,633

Management fee income 16,661,623 0 0 0 0

Inter company Income 823,675 6,578,295 17,621,993 0 0

TOTAL 18,045,915 9,007,912 19,131,669 189,270,756 374,938,994

EXPENDITURE

Payroll costs 3,474,467 1,655,985 3,121,275 19,970,660 54,897,788

Overheads and general exps 2,045,005 3,487,328 1,649,075 9,763,042 32,469,028

Electricity Imports 0 0 0 0 49,719,277

Electricity Purchases Local 0 0 0 0 0

Inter-Company electricity purchases 0 0 0 0 170,214,826

Generation costs 0 0 0 60,025,948 0

Transmission costs 0 0 0 0 1,754,675

Distribution costs 0 0 0 0 14,552,510

Non Core costs 226,167 0 14,056,250 0 0

ZERC Levies 0 0 0 1,885,713 2,703,936

Bad Debts provision 6,664,649 0 0 27,939,931 31,508,451

Depreciation 1,036,547 1,293,546 1,240,542 31,639,760 27,978,797

Management fees 0 450,027 89,321 8,526,716 7,595,559

TOTAL 13,446,835 6,886,885 20,156,463 159,751,770 393,394,846

Operating surplus before finance charges 4,599,080 2,121,027 (1,024,794) 29,518,986 (18,455,852)

Finance charges 713,087 14,238 232,479 9,157,371 6,984,334

Net Profit /(Loss) 3,885,993 2,106,788 (1,257,273) 20,361,615 (25,440,186)

Page 95: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

67

STATEMENT OF FINANCIAL POSITION

NOTES 30 SEPTEMBER 2010 31 DECEMBER 2009

ASSETS

Non Current Assets

Property, Plant and Equipment 8 1,744,830,603 1,781,985,677

Intangibles 9 1,787,436 1,787,863

Investments 3 639,690 790,470

1,747,257,729 1,784,564,010

Current Assets

Inventories 4 94,162,509 77,376,990

Trade and Other Receivables 5 270,291,911 171,190,493

Cash and Cash Equivalents 16,659,599 11,252,208

381,114,019 259,819,692

Total Assets 2,128,371,748 2,044,383,702

EQUITY AND LIABILITIES

Equity and Reserves

Share Capital 0 0

Non Distributable Reserves 1,112,125,509 1,112,125,509

Accumulated Profit /(Loss) (33,330,292) (67,535,279)

1,078,795,217 1,044,590,230

Non Current Liabilities

Long Term Loans 7 31,510,620 40,256,150

Post Employment Benefits 93,518,417 93,518,417

Deferred Taxation 53,186,458 53,186,458

178,215,495 186,961,025

Current Liabilities

Trade and Other Payables 6 472,591,795 423,763,526

Current Portion of Long Term Loans 7 395,062,893 385,063,266

Bank Overdraft 3,706,348 4,005,655

871,361,036 812,832,447

Total Equity And Liabilities 2,128,371,748 2,044,383,702

Page 96: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

68

STATEMENT OF FINANCIAL POSITION BY COMPANY

ZESA

HOLDINGS ZETDC ZPC

ZESA

ENTERPRISES

POWERTEL

COMMUNICATIONS

ASSETS

Non Current Assets 42,756,486 707,018,817 932,001,992 33,855,890 31,624,545

Current Assets

Inventories 40,737 67,518,619 16,629,956 9,402,001 571,196

Trade and Other Receivables 17,157,492 245,319,545 202,930,352 7,455,431 4,173,261

Cash and Cash Equivalents 841,162 12,375,354 2,426,956 501,130 514,997

TOTAL ASSETS 60,795,876 1,032,232,335 1,153,989,255 51,214,452 36,884,000

EQUITY AND LIABILITIES

Equity and Reserves

Share Capital 0 0 0 0 0

Non Distributable Reserves (71,048,602) 313,081,612 750,649,393 28,442,413 23,465,413

Accumulated Profit /(Loss) 3,885,993 (25,440,186) 20,361,615 (1,257,273) 2,050,259

(67,162,609) 287,641,426 771,011,008 27,185,140 25,515,672

Non Current Liabilities

Deferred Tax 205,796 49,230,877 0 0 3,749,785

Post Employment Benefits 93,518,417 0 0 0 0

Current Liabilities

Trade and Other Payables 15,938,658 479,960,432 194,844,717 20,079,819 3,116,919

Current Portion of Loans 17,460,678 215,399,600 164,637,358 3,849,493 4,501,624

Bank Overdraft 834,936 0 2,771,412 100,000 0

TOTAL RESERVES AND LIABILITIES 60,795,876 1,032,232,335 1,153,989,255 51,214,452 36,884,000

Page 97: Zimbabwe - Emergency Power Infrastructure Rehabilitation Project

69

FINANCIAL INDICATORS

Profitability Ratios

Return on Sales

Historical Cost

12.13%

Return on Sales 12.13%

Return on Total Assets 4.83%

Return on Capital Employed 4.09%

Current Ratio

0.44: 1 Acid Test Ratio 0.33: 1

Debtors Collection Period 287 Days

Profitability Ratios

The Return on Sales recorded a positive 12.13%. This shows a favorable rate of return on

sales. However it should be noted that the operating expenditure level is suppressed due to

cash flow constraints.

The Return on Total Assets is a positive 4.83%. This ratio reflects a favorable return on the

use of the group’s assets. However it should be noted that some of the group’s operational

assets are due for replacement.

The Return on Capital Employed is a favorable 4.09%. This ratio shows a fair rate of return

on capital. However the capital is mainly made up of a Non Distributable Reserve which

resulted from dollarization. There is need to enhance the share capital.

Liquidity Ratios

The Group has an unfavourable liquidity position clearly shown by a current ratio of 0.44:1

and an acid test ratio of 0.33:1. The ratios are well below the recommended standard ratios of

2:1 (current ratio), and 1:1 (acid test ratio). The Group’s Debtor’s Collection Period is 287

days. This indicates that whilst making a profit as shown in the above ratios and results, the

cash flow position is strained due to the delay in settling of accounts by customers.