US-95 Granite North Safety Improvements 95 Open House - July 31, 2018 The purpose of the meeting is to: Inform the public about the preferred alternative for the project Receive feedback and project input from the public Make property owners aware of property impacts in advance of the right of way acquisition process Welcome to the US-95 Granite North Open House

zgcpj2sylc51eof8mwqh1t6a-wpengine.netdna-ssl.com · 2018. 12. 17. · 95 US-95 Granite North Safety Improvements Open House - July 31, 2018 The project is a part of the US-95 Garwood

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: zgcpj2sylc51eof8mwqh1t6a-wpengine.netdna-ssl.com · 2018. 12. 17. · 95 US-95 Granite North Safety Improvements Open House - July 31, 2018 The project is a part of the US-95 Garwood

US-95 Granite North Safety Improvements95 Open House - July 31, 2018

The purpose of the meeting is to:

• Inform the public about the preferred alternative for the project

• Receive feedback and project input from the public

• Make property owners aware of property impacts in advance of the right of way acquisition process

Welcometo the US-95 Granite North Open House

Page 2: zgcpj2sylc51eof8mwqh1t6a-wpengine.netdna-ssl.com · 2018. 12. 17. · 95 US-95 Granite North Safety Improvements Open House - July 31, 2018 The project is a part of the US-95 Garwood

US-95 Granite North Safety Improvements95 Open House - July 31, 2018

The project is a part of the US-95 Garwood to Sagle Environmental Impact Statement (EIS) approved by the Federal Highway Administration (FHWA) in summer 2010 and is a continuation of the project completed south of Granite Hill.

This project will improve safety and mobility on US-95 near Granite Hill by:

• Constructing continuous frontage roads on both sides of US-95

• Potentially expanding US-95 to two lanes in both directions.

• Realigning the Trails End Road intersection.

The improvements mostly follow the existing alignment of US-95.

Project Details

Page 3: zgcpj2sylc51eof8mwqh1t6a-wpengine.netdna-ssl.com · 2018. 12. 17. · 95 US-95 Granite North Safety Improvements Open House - July 31, 2018 The project is a part of the US-95 Garwood

US-95 Granite North Safety Improvements95 Public Meeting - July 31, 2018

Project Area Map

Bonner/Kootenai County Line

95

95

95

Trails End Rd.

BNSF Railway

Granite Loop Rd.

Homestead Rd.

Northern Sky Rd.

Rock Springs Rd.

End Project

Project Start

Old House Rd.

Mara Meadows Rd.Granite Lake

Page 4: zgcpj2sylc51eof8mwqh1t6a-wpengine.netdna-ssl.com · 2018. 12. 17. · 95 US-95 Granite North Safety Improvements Open House - July 31, 2018 The project is a part of the US-95 Garwood

US-95 Granite North Safety Improvements95 Public Meeting - July 31, 2018

95

95

95

Trails End Rd.

BNSF Railway

Granite Loop Rd.

Homestead Rd.

Mara Meadows Rd.

Rock Springs Rd.

Old House Road

LEGENDProposed US-95 RealignmentProposed Mineral Ridge RoadProposed Vintage 95 RoadProposed ConnectionsProposed Removed Connections

BNSF Railway

Granite Lake

Homestead Rd. will not connect to US-95

Mara Meadows Rd. will not connect to US-95

Preferred Alternative

x

x

x

x

x

x

x

x

x

Old House Rd. will not connect to US-95

Page 5: zgcpj2sylc51eof8mwqh1t6a-wpengine.netdna-ssl.com · 2018. 12. 17. · 95 US-95 Granite North Safety Improvements Open House - July 31, 2018 The project is a part of the US-95 Garwood

US-95 Granite North Safety Improvements95 Open House - July 31, 2018

Typical SectionsUS-95

Mineral Ridge RoadVintage 95 Road

Vintage 95 Road

Page 6: zgcpj2sylc51eof8mwqh1t6a-wpengine.netdna-ssl.com · 2018. 12. 17. · 95 US-95 Granite North Safety Improvements Open House - July 31, 2018 The project is a part of the US-95 Garwood

US-95 Granite North Safety Improvements95 Open House - July 31, 2018

Project Schedule

Please tell us what you think by:

• Filling out a written comment form at tonight’s meeting or mailing a comment form by August 14, 2018

• Submitting a comment through the project webpage at itd.idaho.gov/d1/

• Sending the project team an email at [email protected]

If you are a property owner, ITD would like to set up a meeting with you in the next few weeks to discuss right of way impacts. Please talk to one of the staff members at tonight’s meeting to set an appointment.

2018 2019 2020 2021

J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D

PS&E

Right of Way Process

Preliminary Design

EnvironmentalRe-evaluation

Construction ConstructionFinal Design

EnvironmentalUpdate

we are here

What’s Next