78
Yell-Unst Construction Environment Management Plan Construction Environment Management Plan (CEMP) Scottish Hydro Electric Power Distribution plc Assignment Number: A100487-S01 Document Number: A-100487-S01-TECH-002 Xodus Group Xodus House, 50 Huntly Street Aberdeen, UK, AB10 1RS T +44 (0)1224 628300 E [email protected] www.xodusgroup.com

Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

  • Upload
    others

  • View
    6

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Yell-Unst Construction Environment Management Plan

Construction Environment Management Plan (CEMP)

Scottish Hydro Electric Power Distribution plc Assignment Number: A100487-S01 Document Number: A-100487-S01-TECH-002

Xodus Group Xodus House, 50 Huntly Street Aberdeen, UK, AB10 1RS T +44 (0)1224 628300 E [email protected] www.xodusgroup.com

Page 2: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) A100487-S01 Client: Scottish Hydro Electric Power Distribution plc Document Type: Technical Note Document Number: A-100487-S01-TECH-002

R01 23/04/2018 Issued for Review RP EH JH -

Rev Date Description Issued By Checked

By Approved

By Client

Approval

mailys.billet
Typewritten Text
PP
Page 3: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

 

 

 

 

Yell‐Unst Construction Environment Management Plan 

Yell – Unst CEMP 

 

Page 4: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 2 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

 

Contents 

Terminology ........................................................................................................................................... 6 

1.  Introduction ................................................................................................................................ 8 

1.1.  Background ............................................................................................................................................................. 8 

1.2.  Objectives of this Document ................................................................................................................................... 8 

1.3.  Structure of this CEMP ............................................................................................................................................ 8 

1.4.  CEMP Document Management ............................................................................................................................. 10 

1.5.  Update and Amendment to this CEMP ................................................................................................................. 10 

1.6.  Linkages with Other Documents ........................................................................................................................... 11 

Project and vessel related documentation ................................................................................................................... 11 

2.  Project Description .................................................................................................................... 12 

Project overview ........................................................................................................................................................... 12 

Schedule ........................................................................................................................................................................ 16 

3.  Environmental Management Framework ................................................................................. 17 

3.1.  Introduction .......................................................................................................................................................... 17 

3.2.  CEMP Roles and Responsibilities and Chain of Command .................................................................................... 17 

THE Contractor Project Manager .................................................................................................................................. 18 

THE Contractor site manager ........................................................................................................................................ 18 

THE Employer Project Manager .................................................................................................................................... 19 

THE Employer Group SHE Manager .............................................................................................................................. 19 

THE Employer Supervisor for offshore works ............................................................................................................... 19 

THE Employer MARINE Consents Manager .................................................................................................................. 19 

Retained Archaeologist ................................................................................................................................................. 19 

THE Company Fisheries LiaIson Offcier (CFLO) ............................................................................................................. 20 

Fisheries Industry Representative (FIR) ........................................................................................................................ 20 

Marine Mammal Observer (MMO) and Passive acoustic monitor (PAM) Operator..................................................... 20 

THE Contractor Environmetnal Clerk of Works ............................................................................................................. 20 

THE Contractor Environmental Manager ...................................................................................................................... 21 

All other project staff .................................................................................................................................................... 21 

3.3.  CEMP Staff Competence, Training and Awareness ............................................................................................... 21 

Vessel inductions .......................................................................................................................................................... 22 

Page 5: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 3 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

Toolbox talks ................................................................................................................................................................. 22 

Vessel notice boards / awareness materials ................................................................................................................. 23 

3.4.  CEMP Communications and Reporting ................................................................................................................. 23 

Internal communications .............................................................................................................................................. 23 

External communications ............................................................................................................................................. 24 

4.  Environmental Management and Mitigation of Effects on the Seabed, Benthic and Intertidal Ecology ................................................................................................................................................. 27 

4.1.  Introduction .......................................................................................................................................................... 27 

4.2.  Regulatory Requirements & Relevant Policy & Guidance ..................................................................................... 27 

4.3.  Overview of Key Sensitive Receptors Present and Potential Impacts .................................................................. 28 

4.4.  Potential Impacts on Key Sensitive Receptors ...................................................................................................... 31 

4.5.  Management Requirements ................................................................................................................................. 31 

5.  Environmental Management and Mitigation of Effects on Marine Wildlife .............................. 33 

5.1.  Introduction .......................................................................................................................................................... 33 

5.2.  Regulatory Requirements & Relevant Policy & Guidance ..................................................................................... 33 

Marine mammals .......................................................................................................................................................... 33 

Birds .............................................................................................................................................................................. 34 

fish ................................................................................................................................................................................ 34 

Otters ............................................................................................................................................................................ 34 

5.3.  Overview of Key Sensitive Receptors Present and Potential Impacts .................................................................. 35 

Marine mammals .......................................................................................................................................................... 35 

Birds .............................................................................................................................................................................. 35 

Fish ................................................................................................................................................................................ 35 

Otters ............................................................................................................................................................................ 36 

5.4.  Potential Impacts on Key Sensitive Receptors ...................................................................................................... 38 

Marine mammals .......................................................................................................................................................... 38 

Birds .............................................................................................................................................................................. 38 

Fish ................................................................................................................................................................................ 38 

Otters ............................................................................................................................................................................ 39 

5.5.  Management Requirements ................................................................................................................................. 39 

Employer Internal Guidance Documents ...................................................................................................................... 39 

Marine mammals – Marine mammal protection plan (MMPP) ................................................................................... 39 

Marine mammals – Seal Haul OUt sites ........................................................................................................................ 41 

Birds – Marine ............................................................................................................................................................... 41 

Fish ................................................................................................................................................................................ 41 

Otters ............................................................................................................................................................................ 41 

Page 6: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 4 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

Birds – Onshore ............................................................................................................................................................. 42 

LandfallS ‐ General ........................................................................................................................................................ 42 

6.  Environmental Management and Mitigation of Effects on Other Marine Users ....................... 44 

6.1.  Introduction .......................................................................................................................................................... 44 

6.2.  Regulatory Requirements & Relevant Policy & Guidance ..................................................................................... 44 

6.3.  Overview of Key Sensitive Receptors Present and Potential Impacts .................................................................. 45 

6.4.  Potential Impacts on Other Marine Users ............................................................................................................ 45 

Commercial fisheries .................................................................................................................................................... 45 

Shipping and navigation ................................................................................................................................................ 46 

Other sea users ............................................................................................................................................................. 46 

6.5.  Management Requirements ................................................................................................................................. 46 

Commerical fisheries and other sea users .................................................................................................................... 46 

Navigation ..................................................................................................................................................................... 47 

Subsea Infrastructure  ................................................................................................................................................... 47 

7.  Environmental Management and Mitigation of Effects on Marine Archaeology ...................... 49 

7.1.  Introduction .......................................................................................................................................................... 49 

7.2.  Regulatory Requirements & Relevant Policy & Guidance ..................................................................................... 49 

International/ EU legislation and policy ........................................................................................................................ 49 

UK Legislation and Policy .............................................................................................................................................. 49 

Scottish Legislation and Policy ...................................................................................................................................... 50 

Local Planning Policy ..................................................................................................................................................... 50 

Codes of Practice, Professional Guidance and Standards Documents ......................................................................... 50 

7.3.  Overview of key features of archaeological importance in the Project area and potential impacts .................... 51 

7.4.  Management Requirements ................................................................................................................................. 51 

8.  Invasive Non Native Marine Species (INNMS) ........................................................................... 52 

8.1.  Introduction .......................................................................................................................................................... 52 

8.2.  Regulatory Requirements & Relevant Policy & Guidance ..................................................................................... 52 

8.3.  Management Requirements ................................................................................................................................. 53 

9.  Waste Management .................................................................................................................. 53 

9.1.  Introduction .......................................................................................................................................................... 54 

9.2.  Regulatory Requirements & Relevant Policy & Guidance ..................................................................................... 54 

9.3.  Management Requirements ................................................................................................................................. 55 

General.......................................................................................................................................................................... 55 

Waste Reduction ........................................................................................................................................................... 55 

Storage of Waste .......................................................................................................................................................... 55 

Page 7: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 5 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

Hazardous (special) Waste ............................................................................................................................................ 56 

Transporting Waste ...................................................................................................................................................... 56 

10.  Pollution Prevention, Spill Response and Contingency Planning ............................................... 58 

10.1.  Introduction .......................................................................................................................................................... 58 

10.2.  Regulatory Requirements & Relevant Policy & Guidance ..................................................................................... 58 

vessels ‐ The International Convention for the Prevention of Pollution from Ships (MARPOL) ................................... 58 

cable landfall installtion ................................................................................................................................................ 59 

10.3.  Management Requirements ................................................................................................................................. 60 

Pollution prevention measures offsHore ...................................................................................................................... 60 

Emergency Spill Response ............................................................................................................................................ 60 

Monitoring and Record Keeping ................................................................................................................................... 61 

Pollution Prevention Measures onhsore (at cable landfall) .......................................................................................... 61 

11.  Dropped Objects ....................................................................................................................... 62 

12.  Monitoring and Reporting Plan ................................................................................................. 63 

12.1.  Introduction .......................................................................................................................................................... 63 

12.2.  Monitoring During Works ..................................................................................................................................... 63 

Vessel Inspections ......................................................................................................................................................... 63 

Monitoring of Daily Work ............................................................................................................................................. 64 

Audits ............................................................................................................................................................................ 64 

Corrective and Preventive Actions ................................................................................................................................ 65 

12.3.  Reporting During / After Works ............................................................................................................................ 65 

Daily reporting .............................................................................................................................................................. 65 

End of installtion reporting ........................................................................................................................................... 65 

12.4.  Incident Response and Reporting ......................................................................................................................... 65 

13.  References ................................................................................................................................ 69 

  Relevant Marine Policies and Plans ............................................................................ 71 

A.1.  Scottish National Marine Plan ............................................................................................................................... 71 

Fisheries policies ........................................................................................................................................................... 72 

Submarine cables policies ............................................................................................................................................. 73 

A.2.  Shetland Islands Marine Spatial Plan (SIMSP) ....................................................................................................... 75 

Page 8: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 6 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

Terminology  

AfL  Agreement for Lease 

AFS  Anti‐fouling system 

AIS  Automatic Identification System  

BWMP  Ballast Water Management Plan  

CEMP  Construction Environmental Management Plan 

CIfA  Chartered Institute for Archaeologists 

CFLO  Companies Fisheries Liaison Officer 

CLV  Cable Lay Vessel 

CoS  Chamber of Shipping 

DDV  Drop Down Video 

DPR  Daily Project Report 

ECoW  Environmental Clerk of Works 

EMF  Electromagnetic Field 

EPS  European Protected Species 

FIR  Fishing Industry Representative 

FLMAP  Fishing Liaison and Mitigation Action Plan 

FOCI  Feature of Conservation Importance 

GPP  Guidance for Pollution Prevention 

HES  Historic Environment Scotland 

OHL  Over Head Line 

OSPAR  The Convention for the Protection of the Marine Environment of the North East Atlantic 

IMO   International Maritime Organisation 

IUCN  the International Union for the Conservation of Nature 

JNAPC  Joint Nautical Archaeology Policy Committee 

JNCC  Joint Nature Conservation Comittee 

KIS‐ORCA  Kingfisher Information Service Offshore Renewables and Cable Awareness 

LBAP  Local Biodiversity Action Plan  

LNCS  Local Nature Conservation Site 

MARPOL  International Convention for the Prevention of Pollution from Ships / Maritime Pollution 

MCA  Maritime Coastguard Agency 

MGO  Marine Gas Oil 

MHWS  Mean High Water Spring 

MMO   Marine Mammal Observer  

MMPP  Marine Mammal Protection Plan 

MPA  Marine Protection Area 

MS‐LOT  Marine Scotland – Licencing Operations Team 

MSP  Marine Spatial Plan 

NCMPA  Nature Conservation Marine Protection Area 

NMP  National Marine Plan 

PAM  Passive Acoustic Monitoring  

PMF  Primary Marine Feature 

PPE  Personal Protective Equipment  

SAC  Special Area of Conservation 

SAT  Shetland Amenity Trust 

SEPA  Scottish Environment Protection Agency 

Page 9: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 7 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

SHE  Safety, Health & Environment 

SHEPD  Scottish Hydro Electric Power Distribution 

SIMSP  Shetland Islands Marine Spatial Plan 

SNH  Scottish Natural Heritage 

SOPEP  Shipboard Oil Pollution Emergency Plan 

SPA  Special Protection Area 

pSPA  proposed Special Protection Area 

SSE  Scottish and Southern Energy 

SSEN  Scottish and Southern Energy Networks 

SSSI  Site of Special Scientific Interest 

SWCN  Special Waste Consignment Note 

UKBAP  UK Biodiversity Action Plan 

UKHO  UK Hydrographic Office 

UNCLOS  The United Nations Convention of the Law of the Sea 

WEWS  Water Environment and Water Services 

WFD  Waste Framework Directive 

WTN  Waste Transfer Note 

 

Page 10: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 8 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

1. Introduction 

1.1. Background 

1.1.1. This Construction Environment Management Plan (CEMP) is for the replacement of the submarine electricity cables between Yell and Unst (Yell – Unst North and Yell – Unst South (the Project)) by the Scottish Hydro Electric Power Distribution plc (SHEPD, known as the Employer).    

1.1.2. This CEMP outlines the mitigation measures, monitoring and reporting procedures that have been incorporated  into  the design and  installation of  the cable  in order  to prevent or  reduce adverse environmental effects as much as possible.  It covers all potential effects associated with installation of the cable and all works at the landfall occurring below Mean High Water Spring (MHWS).  Given that the cable will be installed across the shore, management of potential impacts on the shore have also been considered.   

1.2. Objectives of this Document  

1.2.1. The  purpose  of  this  CEMP  is  to  provide  the  over‐arching  framework  for  on‐site  environmental management during  the  installation of  the cable.   The works will be undertaken considering  the following: 

Relevant legislation; 

Relevant policies in the Scottish Marine Plan and Shetland Islands Marine Spatial Plan (SIMSP) (see Appendix A); 

SSE policies and procedures; and 

Findings of the assessments undertaken to support the Marine Licence application. 

1.2.2. This CEMP sets out the proposed environmental management framework and procedures that will be followed by the Contractor during the works. It sets out the principles that will be applied by the Contractor  in  formulating  their  own  environmental  management  plans  and  describes  the commitments made by  the Employer  in  respect of environmental management and outlines  the relevant environmental management and mitigation measures that will be practically implemented to prevent significant adverse impacts to environmental interests. 

1.3. Structure of this CEMP 

1.3.1. This CEMP is divided into the following sections: 

Section  Summary of Content 

1  Introduction  Background to and overview of the CEMP scope and structure and  identification  of  other  documents  relevant  to  the environmental management process and the linkage between those documents and the CEMP. 

Sets  out  the  procedures  for  any  updates  to  the  CEMP  and subsequent further approval by the Scottish Ministers. 

Page 11: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 9 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

Section  Summary of Content 

2  Project Description  Provides  an  overview  of  the  Project  and  the  key milestone dates. 

3  Environmental Management Framework  Describes the environmental management framework for the Project.  It  provides  information  on  the  implementation  and communication of the CEMP, including key personnel roles and responsibilities. 

4  Environmental Management and Mitigation of Effects  on  the  Seabed,  Benthic  and  Intertidal Ecology 

Sets out key mitigation and management measures to mitigate or  manage  effects  on  the  seabed,  benthic  and  intertidal ecology. 

5  Environmental Management and Mitigation of Effects Marine Animals 

Sets out key mitigation and management measures to mitigate or manage effects on the marine animals. 

6  Environmental Management and Mitigation of Effects Other Marine Users 

Sets out key mitigation and management measures to mitigate or manage effects on other marine users. 

7  Environmental Management and Mitigation of Effects Marine Archaeology 

Sets out key mitigation and management measures to mitigate or manage effects on marine archaeology. 

8  Invasive Non Native Marine Species  Sets  out  the  measures  to  be  adopted  to  prevent  the introduction of invasive non‐native species. 

9  Pollution  Prevention,  Spill  Response  and Contingency Planning & Reporting 

Sets  out  pollution  prevention  and  contingency  planning measures. 

10  Waste Management   Sets out the waste management framework to be adopted and implemented throughout the Project. 

11  Dropped Objects  Sets  out  the  procedures  to  be  followed  in  the  event  of  a dropped object or accidental deposit being made. 

12  Monitoring and Reporting  Sets out the monitoring and reporting procedures relevant to the CEMP. 

   

Page 12: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 10 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

1.4. CEMP Document Management 

1.4.1. The  CEMP  will  be  a  controlled  document  and  will  be  formally  issued  to  the  Employers  cable installation team and the Contractor.  Live copies of the CEMP will be held at the following locations: 

At the premises of any agent or the Contractor acting on behalf of Employer; 

All site offices dealing with marine operations; 

On board all offshore vessels;  

With  the  Employers  Supervisor  for  Offshore  Works  or  the  Employers  marine  Consents Manager; and  

On  the document management  system where  it will be  filed by  the Employer and made accessible to everyone. 

1.4.2. The Employer will ensure that MS‐LOT are provided with the most up to date copy of the CEMP. 

1.4.3. A register of document versions and issue dates will be maintained by Employer. 

1.5. Update and Amendment to this CEMP 

1.5.1. In  the event  that  there are  changes  to  the proposed  installation methodology  (e.g.  that  require additional  management  or  mitigation  measures  or  changes  to  measures  already  proposed), identification  of  new  environmental  sensitivities,  or  emergence  of  new  guidance  or  legislative requirements etc. it may be necessary to update the CEMP.  

1.5.2. Where updates to the CEMP are required,  it will be the responsibility of the Contractor to notify Employer of the proposed changes, and receive approval for the proposed changes from Employer, at least six weeks prior to the change event occurring.  This is necessary to allow sufficient time for Employer  to  communicate  the  proposed  changes  to  Scottish  Ministers,  amend  the  CEMP accordingly, seek further approval for the necessary amendments or updates, and disseminating the approved changes/amendments to responsible parties.   

1.5.3. All changes to the CEMP will be managed through the change management procedure set out  in Figure 1.1.    

   

   

Page 13: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 11 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

Figure 1.1 CEMP change management procedure 

 

1.6. Linkages with Other Documents 

PROJECT AND VESSEL RELATED DOCUMENTATION 

1.6.1. This CEMP document sets out the proposed overarching environmental management framework to be applied during the Project and forms part of a suite of approved documents that were prepared to inform the Marine Licence application and inform the framework for environmental management of the Project. 

Project Description; 

Environmental Appraisal; 

Fishing Liaison and Mitigation Action Plan, including other legitimate users (FLMAP); 

Decommissioning Plan; 

European Protected Species (EPS) Risk Assessment (to be completed prior to works); and 

JNCC Marine Noise Registry (to be completed prior to works). 

   

Page 14: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 12 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

2. Project Description 

PROJECT OVERVIEW 

2.1.1. The aim of the Project is to install two replacement 33 kV submarine electricity cable between Yell and Unst (Figure 2.1).  

Page 15: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 13 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

Figure 2.1 Location of cable replacement works 

Page 16: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 14 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

 

2.1.2. The existing Yell to Unst cables are nearing the end of their operational  life. The replacement of these cables is essential to  securing power supplies to Unst. The existing submarine cables will be left in‐situ on the seabed once taken out of service. This section provides an overview of the Project, further details are available in the Project Description. 

2.1.3. The  replacement cable will be connected  into  the onshore distribution grid network via existing infrastructure.  Given that the onshore works are classed as Permitted Development these upgrades do not require planning consent from Shetland Islands Council.  However, the potential impacts from the onshore construction activities have been assessed separately via a Phase 1 habitat survey and desk study.  This will be used to inform the Contractor of any potential environmental issues to be aware of and/or specific working methods to adhere to.  

2.1.4. The replacement cables will be laid along two routes, a north and a south route, between Yell and Unst.  The proposed North cable will be 3.15 km (2.05 km within the marine environment) in length between the two termination points with the OHL, which are located inshore from the MHWS limit.  However,  the  application  length  is 2.5  km  to  allow  for obstacle  avoidance during  cable  lay  and tolerances with the cable lay operations. The proposed South cable will be 3.15 km (2.23 km within the marine environment)  in  length between the two termination points with the Overhead Lines, which are located inshore from the MHWS limit. 

2.1.5. The replacement cables will have an outer diameter of 127 mm and will be installed from a Cable Lay Vessel (CLV). It will be installed within a 200 m corridor (100 m either side of the new cable route within a 500 m survey corridor (250 m either side of the new cable routes) shown in Figure 2.1), to allow  for any unforeseen difficulties  that arise during  installation and  to enable more  scope  for further micro‐routing  during  installation  to  avoid  sensitive  environmental  habitats  or  potential marine archaeology. 

2.1.6. Initially, the proposed submarine cable will be surface laid on the seabed across the length of the route. Due to the strong tidal currents the majority of the proposed cable route will be across rocky seabed with very little overlying sediment. Due to the limited sediment direct cable burial will not be possible.  By initially surface laying the cable this minimises the footprint in these areas; however, cable mobility on the seabed may  increase the  footprint and  impact on the seabed habitat.   The current anticipated installation methods across the routes are summarised in Table 2.1 for the north cable and Table 2.2 for the south cable.  

Table 2.1 Installation methods North cable 

Location along cable route  Cable installation method Length of cable (m) 

Cable protection 

From termination point with existing OHL to 

Yell shoreline 

Cable burial by open‐cut trench 

from termination point with OHL 

through field 

170 

 

Burial 

From Yell shoreline to MLWS  Cable lay  100 

 

Up to 100 m of cast iron pipe 

Page 17: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 15 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

Location along cable route  Cable installation method Length of cable (m) 

Cable protection 

From Yell shoreline across to KP0.5 

Rock filter bags/mattresses 

installed directly on the cable with 

complete coverage 

200 

 

35 rock filter bags/ concrete 

mattresses 

From KP0.5 to Unst shoreline KP2.22 

Rock filter bags/mattresses 

installed directly on the cable at 

50m minimum spaced intervals 

1,650 

 

40 rock filter bags/ concrete 

mattresses 

From MLWS to Unst shoreline  Cable lay  100 

 

Up to 100 m of cast iron pipe 

From Unst shoreline to termination point with 

OHL 

Cable burial by open‐cut trench 

from termination point with OHL 

through field 

930 

 

Burial 

Total (marine cable length)  2,050   

Table 2.2 Installation methods South cable 

Location along cable route  Cable installation method Length of cable (m) 

Cable protection 

From termination point with existing OHL to 

Yell shoreline 

Cable burial by open‐cut trench 

from termination point with OHL 

through field 

240 

 

Burial 

From Yell shoreline to MLWS  Cable lay  100 

 

Up to 100 m of cast iron pipe 

From MLWS on Yell to KP0.5 

Rock filter bags/mattresses 

installed directly on the cable with 

complete coverage 

200 

 

35 rock filter bags/ concrete 

mattresses 

From KP0.5 to MLWS on Unst 

Rock filter bags/mattresses 

installed directly on the cable at 

50m minimum spaced intervals 

1,830 

 

40 rock filter bags/ concrete 

mattresses 

Page 18: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 16 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

Location along cable route  Cable installation method Length of cable (m) 

Cable protection 

From MLWS to Unst shoreline  Cable lay  100 

 

Up to 100 m of cast iron pipe 

From Unst shoreline to termination point with 

OHL 

Cable burial by open‐cut trench 

from termination point with OHL 

through field 

680 

Burial 

Total (marine cable length)  2,230   

 

2.1.7. At the shore end landfall locations, an open cut trench will be used to install and protect the cable inshore from the MLWS tidal limits to above mean high water springs (MHWS). To allow for micro‐routing during cable  installation the  landfall excavation works will take place within 100 m either side of the cable landfall positions shown in Figure 2.1.  On either side where sufficient burial cannot be achieved, cast iron split pipe (up to 100 m at either landfall) will be fitted around the cable for additional protection in the event of exposure. 

2.1.8. For the cable laying activities, a standard small cable lay vessel will be used.  An additional smaller support vessel is likely to be required at each of the shallower shore locations; this is likely to be a multicat / dive support vessel (DSV). A four‐point anchor system for the DSV will be required to be laid out prior  to  commencing works  in  the nearshore  region. An anchor handling  vessel will be required to lay out the anchors, which would be within a radius of 100 m from the DSV. Where there is sensitive habitat close to shore, the anchor pattern would be designed so that  it targets areas where sensitivity is reduced, thereby minimising the potential impact. A guard vessel is also likely to be used during the cable lay operations in order to ensure other vessels remain outside the area of operations, thereby reducing collision risk.  

SCHEDULE 

2.1.9. SHEPD  propose  to  complete  the  submarine  cable  and  onshore  connection works  during  the  period December 2018 – February 2019 or before if the necessary consents have been secured. The planned duration of the proposed cable works are no greater than 30 days, exclusive of weather. A Marine Licence is required for the period of October 2018 to March 2019. The onshore cabling works on both Yell and Unst will be completed prior to the main submarine cable  installation works. The minor modifications required to the existing OHL networks will be carried out during commissioning of the submarine cable to the SHEPD network.  

   

Page 19: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 17 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

3. Environmental Management Framework 

3.1. Introduction 

3.1.1. This section sets out the environmental management framework for the Project, under the following areas: 

CEMP ‐ roles & responsibilities; 

CEMP – staff competency and training; and 

CEMP – communications and reporting. 

3.1.2. Specific environmental management requirements and procedures are then set out in sections 4 to 12 of this CEMP. 

3.2. CEMP Roles and Responsibilities and Chain of Command 

3.2.1. This section sets out the roles and responsibilities of all relevant Project personnel in relation to the delivery of this CEMP.  

3.2.2. All Project personnel have a responsibility to comply with the requirements of the CEMP, however the key roles relevant to the delivery and implementation of the CEMP are: 

The Contractor Project Manager; 

The Contractor Site Manager; 

The Employer Project Manager; 

The  Employer Group SHE Manager; 

The Employer Supervisor for Offshore Works; 

The Employer Marine Consents Manager; 

Retained Archaeologist;  

Company Fisheries Liaison Officer (CFLO);  

Fisheries Industry Representative (FIR);  

Marine Mammal Observer (MMO) and PAM operator; 

The Contractor Environmental Clerk of Works (ECoW); and 

The Contractor Environmental Manager. 

3.2.3. Once a Contractor  for  the Works has been  confirmed,  further  information  relating  to  the  roles, contact details, etc. will be provided. However, the key roles identified are described in the sections below.  

   

Page 20: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 18 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

THE CONTRACTOR PROJECT MANAGER 

3.2.4. Amongst others  is  responsible  for  ensuring  that  the project  is  in  compliance with  any Consent, licence or associated  information and  identifying any breach or potential breach to the Employer Marine Consents Manager.  Specific responsibilities, include: 

Facilitate dissemination of environmental requirements to the Project Team; 

Ensure and be  responsible  for compliance with all permits,  licences and consents, and  to report any deviations or breaches; 

Oversee  the  implementation  and  review  of  environmental  procedures  throughout  the Project; 

Monitor the environmental performance of the Project through maintaining an overview of incidents, inspections and audits; 

Ensure  that  environmental  considerations  form  an  integral  part  of  Design  and Implementation of the Works and include environmental reviews as part of regular Project meetings; 

Review environmental matters with  the Contractor  Environmental Manager on  a  regular basis and as per Project requirements; 

Liaise  with  the  Contractor  Environmental  Manager  on  all  environmental  issues  as appropriate; 

Ensure  that  all  environmental  incidents  are  reported  to  the  Contractor  Environmental Manager according to agreed procedures; and 

Nominate individual Project Team members to support the Employer in public relations and community liaison activities, including local community meetings. 

THE CONTRACTOR SITE MANAGER 

3.2.5. The Contractor Site Manager will be responsible for overseeing the monitoring of environmental and licence  compliance  during works.  The  Contractor  Site Manager  is  experienced  in  ensuring  site operations function  in a manner that  is environmentally compliant, and will be supported by the ECoW.  Specific, responsibilities include: 

Maintaining a full time presence on site; 

Understanding and implementing all environmental procedures ensuring that site operations function in compliance; 

Reporting environmental incidents at the earliest possible time and advising the Contractor Environmental Manager & Project Manager; 

Overseeing site works with a view to reducing the environmental impact of the works and raising  any  environmental  concerns  with  Contractor  Environmental  Manager  &  Project Manager; and 

Ensuring  toolbox  talks are carried out as necessary on  relevant environmental  topics and records maintained. 

 

Page 21: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 19 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

THE EMPLOYER PROJECT MANAGER 

3.2.6. Amongst others  is  responsible  for  ensuring  that  the project  is  in  compliance with  any Consent, licence or associated  information and  identifying any breach or potential breach to the Employer Marine Consents Manager.   

THE EMPLOYER GROUP SHE MANAGER 

3.2.7. The Group SHE Manager shall ensure that: 

Incidents are thoroughly investigated and reported throughout the Company; 

Assistance is provided, when appropriate, during investigations; 

Investigation levels are appropriate to the actual or potential severity of the incident; and 

Incidents are reported in compliance with statutory requirements. 

THE EMPLOYER SUPERVISOR FOR OFFSHORE WORKS 

3.2.8. The Employer Supervisor for Offshore Works shall be responsible for ensuring that the Employers requirement  under  the  contract  with  the  Contractor  are  met.  They  shall  be  responsible  for identifying  and  raising  any  defects  or  breaches  against  the  contract,  licences  or  supporting information. These defects and breaches shall be detailed in the Daily Project Report (DPR). 

THE EMPLOYER MARINE CONSENTS MANAGER 

3.2.9. The Employer Marine Consents Manager shall be responsible for: 

Obtaining Marine Licences, Marine Works Licences and Marine EPS Licences (as appropriate) and any other licences or consents for the works; 

Review and acceptance of Contractor documentation; 

Conducting vessel inspections and pre works briefings where they relate to licence conditions or Consent compliance; and 

Working  alongside  with  the  external  stakeholder  engagement  team  in  developing relationships,  including with Marine  Scotland  and  Crown  Estate  Scotland  (and  any  other relevant stakeholders), to ensure that the project information is communicated as and when appropriate, in order to build consensus around project decision making. 

3.2.10. They shall be in direct communication with the Employer Project Manager and Employer Supervisor for Offshore Works. 

RETAINED ARCHAEOLOGIST  

3.2.11. The  Employer  shall  contract  a  Retained  Archaeologist  as  appropriate  to  provide  archaeological consultancy and to report as appropriate to The Employer and Historic Environment Scotland (the Archaeological Curator).  

3.2.12. The Employer shall advise the Retained Archaeologist of their requirements or responsibilities under this CEMP for the cable laying. 

 

Page 22: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 20 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

THE COMPANY FISHERIES LIAISON OFFCIER (CFLO)  

3.2.13. The primary  responsibilities of  the CFLO are  to establish and maintain effective communications between  The  Employer,  the Contractor  and  legitimate  sea users during  the  Project,  and  ensure compliance with best practice guidelines whilst doing so.   

3.2.14. The primary responsibilities of the CFLO are described in detail in the FLMAP. 

FISHERIES INDUSTRY REPRESENTATIVE (FIR) 

3.2.15. The FIR reports to the CFLO and works in conjunction with The Employer.  

3.2.16. The primary responsibilities of the FIR are also described in the FLMAP. 

MARINE MAMMAL OBSERVER (MMO) AND PASSIVE ACOUSTIC MONITOR (PAM) OPERATOR 

3.2.17. The Marine Mammal Observer (MMO) and Passive Acoustic Monitor (PAM) operator shall be trained and experienced in UK waters and shall implement the requirements set out in any applicable EPS Licence, Marine Mammal Protection Plan (MMPP) or EPS Risk Assessment, along with compliance with any other applicable legislation or guidance such as the JNCC 2017 guidance for seismic survey.  They shall be employed by the Contractor and shall be dedicated to the role on a full time basis.  A minimum of two MMO/PAM operators will be provided for 24 hour works and be operating from a vessel. 

THE CONTRACTOR ENVIRONMETNAL CLERK OF WORKS 

3.2.18. The Contractor Environmental Clerk of Works (ECoW) shall be responsible for: 

Carrying out regular environmental checks keeping records as appropriate as delegated by the Contractor Project Manager; 

Reviewing the success of environmental protection measures; 

Advise and instruct Project Team personnel, when necessary, on the correct implementation of environmental mitigation and protection measures as per those set out within this CEMP; 

Supporting  the  Contractor  Environmental Manager  (and  the wider  Project  Team)  in  the environmental  audits  as  required  and  advise  on  the  implementation  of  environmental mitigation and protection measures; and 

Providing environmental awareness training relevant to environmental compliance detailed within this document which will be given at appropriate times to Project personnel. 

   

Page 23: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 21 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

THE CONTRACTOR ENVIRONMENTAL MANAGER 

3.2.19. The Contractor Environmental Manager will be based at the Contractors site office and be in close contact with the Contractor ECoW, Site Manager & Project Manager.  The Contractor Environmental Manager shall be responsible for: 

Preparation, implementation and undertaking reviews of environmental plans in accordance with Employer and Contractor requirements and procedures and current legislation; 

Maintaining  current  environmental  legislation  register,  reviewing  as  per  relevant  new developments; 

Providing the necessary updates and reports to Project Team and Employer; 

Interfacing with site staff and subcontracted companies on environmental issues; 

Ensuring  the Project specific CEMP  is  implemented, ensuring compliance with procedures and legislation; 

Checking all documents for Duty of Care requirements; 

In conjunction with the Employer,  liaising with government departments,  local authorities and other statutory authorities on environmental matters, as per project needs; 

Reviewing Method Statements against environmental issues;  and 

In the event of an environmental  incident, the Contractor Environmental Manager will be contacted  by  the  onsite  ECoW,  and  will  communicate  incidents  as  per  the  emergency response procedures. 

ALL OTHER PROJECT STAFF 

3.2.20. All other project staff, are responsible for ensuring that they adhere to the following: 

Understand and implement procedures relevant to their role as laid out in the CEMP and the associated documentation including FLMAP; 

Conduct their work with a view to reducing the environmental impact of the Project and to raise  any  environmental  concerns with  their  supervisor  or  the  Contractor  Environmental Manager; and 

Report  all  environmental  incidents  to  their  supervisor  or  the  Contractor  Environmental Manager as soon as possible. 

3.2.21. The Contractor roles outlined above may not be stand alone and one person may fulfil two or more outlined roles. 

3.3. CEMP Staff Competence, Training and Awareness 

3.3.1. The Employer will ensure that a Project organogram is in place and that the roles and responsibilities of all named personnel are clear and that clear project management procedures are in place for all aspects of the Project, including those related to environmental management measures. 

3.3.2. The Employer has a documented process in place to manage the selection and ongoing performance of the Contractor to ensure that the SHE risks associated with the Contractors’ activities are managed effectively. 

Page 24: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 22 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

3.3.3. The  Employer  will  require  that  the  Contractor  has  appropriate  environmental  management procedures in place.  As a minimum, the Contractor is expected to have one full time dedicated site Environmental Clerk of Works  (ECoW), one  Environmental Manager  and  a MMO/PAM operator (working from a vessel with a minimum of two for 24 hour working).  

3.3.4. The Employer (or their appointed representative) will undertake ongoing audit and inspection of The Contractor’s work to check compliance with SHE requirements.  

3.3.5. The Employer will require that all Project personnel attend required  inductions  including, but not necessarily  limited to, matters related to Employer’s environmental rules and policies, Site Rules, Health and  Safety  requirements, arrangements  for First Aid and Emergency Response  (including environmental  pollution  and  emergency  spills),  Environmental Management,  including  Consent compliance requirements and Incident Management.  

3.3.6. Training and awareness specific to this CEMP will be delivered using the following tools: 

Vessel inductions; 

Toolbox talks; and 

Vessel notice boards / awareness materials. 

3.3.7. The Contractor records of training will be maintained and filed by the Contractor and provided to Employer prior to works commencing, then monthly during works (as appropriate).  The records will include the content of the training delivered and record of attendance. 

VESSEL INDUCTIONS 

3.3.8. Vessel  inductions  shall  cover  environment,  consents  and  licence  issues,  highlighting  the  key environmental sensitivities and considerations.  This is to ensure that every Project Team member is aware of their duty and the work related specific needs/hazards.  Vessel Inductions are utilised to raise  awareness  for  personnel  regarding  site/vessel  rules,  emergency  response  procedures  and environmental protection arrangements.  

TOOLBOX TALKS   

3.3.9. A toolbox talk will be held for the all vessel crew as part of the daily (or as required) briefing to be held before starting the operation.  In addition a toolbox talk will be held for any significant abnormal task or change in operation.  These meetings are to address the exact nature of the task and HSE issues specific to the task being performed during a new working day/shift or task change.  A list of attendees will be recorded at each toolbox talk meeting.  Toolbox talks are a combination of briefing followed by a consultation with the workforce to check understanding and invite opinion. 

3.3.10. If an unusual operation  is being performed, a further toolbox talk  is undertaken with the specific staff that will undertake the task.  It will  include a review of the task specific risk assessment and method statement.   This  is an open meeting where opinion  is  invited to ensure that each person understands and agrees with the specific environmental requirements. 

3.3.11. The Contractor shall be responsible for delivery of specific training on the purposes, requirements and procedures of the CEMP and associated documentation, through the toolbox talk. The toolbox talk will be designed to convey key points in a clear and concise manner. For example, on pollution prevention measures it would cover key roles and responsibilities, environmental sensitivities in the vicinity of the Project, and procedures to follow in the event of any spill.  

Page 25: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 23 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

3.3.12. Toolbox talks are held on a regular basis, and additionally where required as the Project progresses. Representatives from all parties involved will be expected to participate. During the toolbox talk, all parties are given the opportunity to discuss and hear advice on environmental matters such as waste disposal and handling and storage of hazardous substances. Details of toolbox talks and personnel attending are recorded and maintained on site. 

VESSEL NOTICE BOARDS / AWARENESS MATERIALS 

3.3.13. In addition to induction and talks, the Employer Marine Consents Manager will be responsible for managing the preparation of a series of awareness materials (as appropriate), which may  include training packs, posters, signs and newsletters. For example, posters on specific procedures can be on display on notice boards on the vessels. 

3.4. CEMP Communications and Reporting 

INTERNAL COMMUNICATIONS 

3.4.1. The  following  summarises  the  lines of  communication between  the  key  roles  in  relation  to  the implementation of the CEMP: 

The Contractor Environmental Manager and Contractor ECoW play a key role in the delivery of the CEMP, alongside the Employer Marine Consents Manager and Employer Supervisor for Offshore Works. In fulfilling this role the Employer Marine Consents Manager and Employer Supervisor  for  Offshore  Works  can  establish  direct  contact  with  the  Employer  Project Manager; 

The Employer Marine Consents Manager will report directly to MS‐LOT on compliance with the CEMP; 

The Employer Marine Consents Manager will liaise with MS‐LOT and other stakeholders on environmental matters; and  

The Employer Marine Consents Manager and Employer Supervisor for Offshore Works will maintain  direct  contact  with  and  report  on  the  CEMP  compliance  and  environmental management issues to the Employer Project Manager. 

3.4.2. During the works, daily (or as required) meetings / calls will take place involving the Employer Project Manager, the Contractor representatives, the Employer Marine Consents Manager and the Employer Supervisor for Offshore Works.  Consents and licence compliance and environmental management wil be discussed as necessary.   Any  issues or points  to note will be recorded  in  the Daily Project Report (DPR).  

3.4.3. The Contractor will be required to provide regular written reports to the Employer on  installation activity.     Contractor  reporting will  include  information  on  environmental management  such  as details of environmental  incidents (if any), environmental statistics and records of environmental inspections / audits undertaken and any such other information as may be required for the Employer Marine Consents Manager to complete their reporting responsibilities.  This information will inform the external reporting to MS‐LOT (see below). 

3.4.4. All  Project  personnel  will  be  required  to  report  any  environmental  concerns  or  issues  to  the Contractor Environmental Manager and/or Employer Supervisor for Offshore Works  immediately.  See section 12.4 for incident reporting. 

Page 26: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 24 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

EXTERNAL COMMUNICATIONS 

3.4.5. Table 3.1 summarises the CEMP external reporting requirements, mechanisms and frequencies. 

3.4.6. The relevant returns and notifications as required by the Marine Licence (and set out in Table 3.1) will be collated from information supplied by the Contractor and the Employer Project Team where necessary. 

Table 3.1  CEMP External Communications  

Communication type  Responsible party  Proposed frequency  Relevant stakeholders 

Pre installation reporting requirements 

Proposed date of commencement of installation 

The Employer Marine Consents Manager 

No later than 4 weeks prior to commencement of the works 

MS‐LOT 

Details of the proposed nature and timescale of the cable installation works 

CFLO via Notice to Mariners (NTM) 

No later than 1 week prior to commencement of the works 

All appropriate maritime users 

Details of the proposed nature and timescale of the cable installation works 

CFLO via NTM No later than 10 days prior to commencement of the works 

All appropriate maritime users 

Details of the proposed nature (in particular vessel routes, and working areas) and timescale of the works 

CFLO via NTM Prior to commencement of the works 

Kingfisher Fortnightly Bulletin 

Details of the proposed nature and timescale of the works and details to allow for safe fishing activity in the cable corridor (if appropriate) 

CFLO via NTM Prior to commencement of the works 

Fishermen, their representatives and other relevant marine stakeholders 

Registration of any noisey activities in the JNCC Marine Noise Register 

The Employer Marine Consents Manager 

Prior to submission of the Marine Licence and EPS Licence (if relevant) applications 

JNCC 

During installation reporting requirements 

Details of the proposed nature and timescale of the works and details to allow for safe fishing activity in the cable corridor (if appropriate) 

CFLO via NTM During works (as / if required) 

Fishermen, their representatives and other relevant marine stakeholders 

Change to any of the information on which the Marine Licence is based 

The Employer Marine Consents Manager 

As soon as reasonably practical 

MS‐LOT 

Page 27: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 25 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

Communication type  Responsible party  Proposed frequency  Relevant stakeholders 

Details of any part of the licenced works that has become a danger to navigation or protection of legitimate users of the sea 

The Employer Marine Consents Manager 

As soon as reasonably practical 

Maritime and Coastguard Agency (MCA), Northern Lighthouse Board (NLB) and Kingfisher Information Service Offshore Renewables and Cable Awareness (KIS‐ORCA) 

Environmental or pollution incidents 

The Employer Marine Consents Manager and Supervisor for Offshore Works 

Should one occur within 24 hrs for minor incidents within 30 mins for major incidents 

MS‐LOT, MCA 

Archaeological discovery   Retained Archaeologist 

Following an archaeological discovery 

Historic Environment Scotland (HES) and MS‐LOT 

Post installation reporting requirements 

Notification of completion of the works 

The Employer Marine Consents Manager 

Within one week of completion of the works 

MS‐LOT 

Nature and quantity of all substances and articles deposited below Mean High Water Springs (MHWS) 

The Employer Marine Consents Manager 

Within four weeks of completion of the works 

MS‐LOT 

Copy of Marine Licence and ‘As Laid Plan’ 

The Employer Marine Consents Manager 

Following completion of the works 

The Hydrographic Office 

And notify MS‐LOT of the notification at the time it is made 

Cable route and a 500 m zone either side of it as a hazardous area for anchoring 

The Employer Marine Consents Manager 

Following completion of the works 

Maritime and Coastguard Agency (MCA), UK Hydrographic Office (UKHO), Northern Lighthouse Board (NLB), the Kingfisher Information Service Offshore Renewables and Cable Awareness (KIS‐ORCA) and the UK International Cable Protection Committees 

And notify MS‐LOT of the notification at the time it is made 

Assessment of any risks posed by final subsea cable route, burial depths and untrenched areas where protection measures were used (to ensure that the safety of navigation and other legitimate users of the sea is not compromised) 

The Employer Marine Consents Manager 

Within eight weeks of completion of the works 

MS‐LOT 

Page 28: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 26 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

Communication type  Responsible party  Proposed frequency  Relevant stakeholders 

Marine mammal sightings 

The Contractor to prepare MMO reports for issue to MS‐LOT by the licence holder 

Within 4 weeks of completion of the works 

MS‐LOT, JNCC and SNH 

Close out of noisey activities registered in the JNCC Marine Noise Register 

The Employer Marine Consents Manager 

Following completion of the works 

JNCC 

   

Page 29: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 27 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

4. Environmental Management and Mitigation of Effects on the Seabed, Benthic and Intertidal Ecology 

4.1. Introduction  

4.1.1. This section describes the regulatory and policy framework under which the Employer is required to ensure the protection of the seabed and benthic and  intertidal ecology  in the Project area.   This section then goes on to provide an overview of the key characteristics of, and potential impacts on, the  seabed  and  benthic  and  intertidal  ecology  in  the  Project  area,  and  identifies  a  series  of management and mitigation measures that are required to ensure potential impacts on the seabed and benthic and intertidal ecology are avoided and / or minimised.  

4.2. Regulatory Requirements & Relevant Policy & Guidance 

4.2.1. An integral aspect of the assessment of potential impacts on benthic and intertidal ecology is the identification of habitats and species of conservation importance in the Project area and assessment of potential  impacts on  these.   There are a number of different  statutes and guidance  that are relevant in this regard with respect to benthic and intertidal areas. 

4.2.2. The Habitats (Scotland) Regulations 1994 (as amended) transcribe the requirements of the Habitats Directive in Scotland, on land and in inshore waters (within 12 nm).  The Habitats Directive lists 13 marine habitats and eight marine species in Annexes I and II respectively.  To meet the requirements outlined  in  Article  3  of  the Habitats  Directive,  Special  Areas  of  Conservation  (SACs)  have  been designated  in  UK  offshore  and  Territorial  Waters  to  contribute  to  the  European  network  of important high‐quality  conservation  sites  that will make a  significant  contribution  to  conserving these species and habitats outlined in the Directive.  

4.2.3.  The closest designated SAC to the proposed cable routes between Yell and Unst is the Yell Sound Coast SAC,  24 km south‐east of the Project area.  This site is designated for the protection of otter Lutra lutra and harbour seal Phocoena vitulina, both listed on the Annex II of EU Habitats Directive.  There are no designated benthic features within this site.  

4.2.4. The Marine (Scotland) Act 2010 established powers for Scottish Ministers to designate a suite of 30 Nature Conservation Marine Protected Areas  (NCMPAs), 17 of which are  located within Scottish territorial waters  (out  to 12 nm) and 13  in offshore areas  (12 nm  to 200 nm).     The aim of  the NCMPAs,  is to provide protection for a wide range of  important marine habitats and wildlife and features of geology and geomorphology importance.   The NCMPAs build on, and are designated to complement, the suite of existing network of protected sites that already exist in Scottish Waters including SACs, SPAs and SSSIs.  There is one NCMPA in the immediate vicinity of the Project area, the Fetlar to Haroldswick NCMPA located 1.6 km south. The benthic features designated within this site  include  circalittoral  sand  and  coarse  sediments,  horse  mussel  beds,  kelp  and  seaweed communities on sublittoral sediments, maerl beds, shallow tide‐swept coarse sands with burrowing bivalves, and for the geomorphology of the Scottish shelf seabed (SNH, 2014). 

4.2.5. The Scottish MPA Selection Guidelines  identifies a  list of 41 MPA search features of which 21 are benthic habitats and five are benthic species with low or limited mobility.   

Page 30: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 28 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

4.2.6. Scottish Natural Heritage  (SNH) and  the  Joint Nature Conservation Committee  (JNCC) have been working with Marine Scotland to develop a priority list of marine habitats and species in Scotland's seas, known as Priority Marine Features (PMFs).  The list, which comprises 56 PMFs including eight habitats and species groups, 11  individual habitats and 37 species, was developed to help deliver Marine Scotland's vision for marine nature conservation outlined in the Marine Nature Conservation Strategy, acting as a focused list of marine habitats and species to help target future conservation work  in Scotland.   During 2013, Marine Scotland  ran a consultation on  the  recommended  list of PMFs.  

4.2.7. The UK Biodiversity Action Plan  (UKBAP) was  launched  in 1994 as a means of meeting  the UK’s obligations under the Biodiversity Convention.  UK BAP priority species are those identified as being the most threatened and requiring conservation action under the UK BAP.  As a result of devolution, and new country‐level and  international drivers and  requirements, much of  the work previously carried out by the UK BAP is now focused at a country‐level rather than a UK‐level, and in July 2012 the UK BAP was succeeded by the UK Post‐2010 Biodiversity Framework'.   The UK  list of priority species,  however,  remains  an  important  reference  source  and  has  been  used  to  help  draw  up statutory lists of priorities in Scotland. 

4.2.8. Local Biodiversity Action Plans (LBAPs) are seen as the means by which the UKBAP and the Scottish Biodiversity  Strategy  are  implemented  at  the  local  level.  Targets  set  nationally  for  species  and habitats of conservation concern are translated into actions which are achievable in a local context.  Living Shetland  is  the  Island’s Local Biodiversity Action Plan  (LBAP),  it  identifies  locally  important habitats and  species and highlights and promotes conservation actions.  It also highlights actions from key sectors and promotes action for biodiversity at the community level.  

4.2.9. The Convention for the Protection of the Marine Environment of the North East Atlantic ‐ the OSPAR Convention is the mechanism by which 15 governments of Western Europe work together to protect the marine  environment of  the North  East Atlantic.  In  2003,  the UK  government  committed  to establishing a well‐managed, ecologically coherent network of Marine Protected Areas (known as the OSPAR MPA commitment).   A  list of 54 habitats and species  (including marine and  intertidal habitats) are considered  to be under  threat or  in decline within  the northeast Atlantic has been produced by OSPAR (a number are also Priority Marine Features (PMF)).  A number of these habitats and species have also been identified as PMFs.  

4.2.10. The  Scottish Government  adopted  the National Marine  Plan  in  2015  to provide  an  overarching framework for marine activity in Scottish waters.  The plan is underpinned by a set of general policies which apply across existing and future development and use of the marine environment; policies of particular  reference  to  this  Project  and  impacts  on  seabed  and  intertidal  habitats  and  species include: 

Compliance with legal requirements for protected areas and protected species;  

Not result in significant impact on the national status of Priority Marine Features (PMF); and 

Protect and, where appropriate, enhance the health of the marine environment. 

4.3. Overview of Key Sensitive Receptors Present and Potential Impacts 

4.3.1. An assessment of  the potential  impacts of  the Project on  the seabed, and benthic and  intertidal habitats  and  species within  the  Project  area was  carried  out  in  support  of  the Marine  Licence application.   The assessment was based on data collected from a desk study that used published 

Page 31: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 29 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

data sources including the National Marine Plan interactive (NMPI, 2018) and the Shetland Islands' Marine Spatial Plan (NAFC, 2015), along with results from a previous cable risk assessment survey undertaken  along  the  Yell‐Unst  cable  routes  (ESG, 2015)  and  the  2018  Environmental Appraisal survey at North and South cable landfalls at Yell and Unst (ERM, 2018a, 2018b). The key sensitive receptors will be reviewed and updated following the marine surveys undertaken during May – June 2018.  

4.3.2. The aim of the environmental desk study was to  identify habitats and biotopes present along the proposed cable route.  Key findings from the desk study are summarised is Table 4.1.  

Table 4.2  Broad‐scale habitats present along the proposed cable route  

Section of South 

cable Nature of seabed disturbance  Habitat type 

Intertidal areas at 

Yell and Unst Cable burial in open‐cut trench  Potential Annex I 'vegetated shingle' habitat 

Surface laid cable with cast iron 

protection, where cable burial cannot be 

achieved 

High energy infralittoral rock 

From Yell shoreline 

up to KP0.5 Surface laid cable with complete concrete 

mattresses/rock filter bags coverage High energy infralittoral rock 

From KP0.5 to Unst 

shoreline KP2.22 Surface laid cable with partial protection  High energy infralittoral rock. 

Kelp communities are known to occur along a section of the 

proposed cable routes within the bay to the west of Loch 

Snarravoe on Unst (NAFC Marine Centre, 2015).  Kelp beds 

are designated as Scottish PMFs. 

Nearshore areas  DSV anchoring system  High energy infralittoral rock. 

Potential kelp communities within the bay to the west of 

Loch Snarravoe on Unst. 

 

4.3.3. The nearest conservation site to the proposed Yell ‐ Unst cable routes with benthic features is is the Fetlar  to  Haroldswick  NCMPA  located  1.6  km  south  of  the  Project  area.  The  benthic  features designated within this site are circalittoral sand and coarse sediments, horse mussel beds, kelp and seaweed communities on sublittoral sediments, maerl beds, shallow tide‐swept coarse sands with burrowing bivalves, and geomorphology of the Scottish shelf seabed.   Of these features only kelp beds are potentially present in the immediate vicinity of the proposed cable route, within the bay to the west of Loch Snarravoe on Unst. The distribution of broad‐scale habitats along the proposed routes of the replacement cables are illustrated in Figure 4.1.   

 

 

 

 

 

Page 32: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 30 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

Figure 4.1 ‐ EUSeaMap broad‐scale seabed habitat classification in the vicinity of the Project area (NMPI, 2018) 

 

 

 

Page 33: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 31 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

4.4. Potential Impacts on Key Sensitive Receptors   

4.4.1. The potential  impacts on key sensitive receptors were assessed  in the environmental desk study.  Following  the marine  surveys  to be conducted  in May –  June 2018,  the potential  impact will be reviewed and updated.  

4.4.2. The impact assessment work concluded that, although the proposed route of the replacement cable crosses areas of potential kelp beds listed PMFs and potential Annex I 'vegetated shingle', there are not anticipated to be any significant impacts on these features of conservation importance. 

4.4.3. Due to the strong tidal currents, the majority of the proposed cable route will be across rocky seabed with very little overlying sediments, therefore cable burial will not be possible.  To stabilise the cable where burial cannot be achieved, SHEPD plan to lay either rock filter bags or concrete mattresses on the cable, with complete coverage from Yell shoreline up to KP0.5, and then placed at roughly 50 m intervals from KP0.5 to Unst shoreline along each cable route. This is necessary to prevent the cable from being moved around on the seabed by the strong tidal currents that flow through the area.  The will also minimise potential impacts from direct substratum and habitat removal associated with cable burial activities.  

4.4.4. Although placement of the cable across the potential kelp beds and potential Annex  I  'vegetated shingle' habitat will result in physical disturbance and habitat loss, the total area of impact on the seabed will be very small (0.28 km2).  Potential impacts are therefore not significant.  This is due to the highly localised nature and small scale of the impact, limited to the immediate footprint of the cable  (outer diameter  is 127   mm) and  rock  filter bags/concrete mattresses  (4 m2 per  rock  filter bag/18 m2 per mattress).  

4.5. Management Requirements 

4.5.1. The  following management  requirements  have  been  identified  to  prevent  / minimise  potential impacts on benthic habitats and species:   

The cable will be surface laid through most of the proposed cable route.  This will minimise potential disturbance to these habitats and features;   

Rock filter bags/concrete mattresses will be used to hold the surface laid sections of the cable in position on the seabed.  This is necessary to prevent movement of the cable induced by strong tidal flows through the Yell Sound and subsequent impact of this movement on kelp beds potentially present along the proposed cable route; 

 The cable will be surface laid over the route (except at landfall), and will be held in place by rock filter bags/concrete mattresses with complete coverage from Yell shoreline up to KP0.5 due  to  the  strong  tidal  flows.  From  KP0.5  they  will  be  regularly  spaced  spot  locations (approximately every 50 m) to pin the cable to the seabed. In areas of softer sediment at the landfalls, the cable will be buried. This will limit the area affected by the trenching activities to a corridor of 10 m width.  Trenching will generate some sediment suspension.  However, due to the short distances over which trenching is required (maximum of 32 m of trenching estimated at the South cable route landfall at Unst), the temporary nature of the jet trenching activities and the strong tidal flows through the Yell Sound, any suspended sediment will be rapidly dispersed;   

Page 34: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 32 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

Where smaller multicat / dive support vessels (DSV) are required for operations in shallower waters near the two landfalls, a four‐point anchor system will be required to the laid out on the seabed prior to works commencing in the nearshore area.   The anchors, will be within 100 m from the multicat / DSV, will be installed by an anchor handler.  The position for each of the anchors will be identified to avoid any potential areas of sensitive habitat;     

Once works are complete the anchors will be removed by  the anchor handler  in order  to minimise the risk of anchor drag or additional disturbance to the seabed;    

EMF has been minimised through a three‐core design and double wire armouring of the cable (see section 5); and  

Good practice pollution control measures will be in place to minimise risk of contamination, further details can be found in section 10.    

Page 35: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 33 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

5. Environmental Management  and Mitigation  of  Effects  on Marine Wildlife 

5.1. Introduction 

5.1.1. This section describes the regulatory and policy framework under which the Employer is required to ensure the protection of marine wildlife in the Project area.  This section then goes on to provide an overview of the key sensitive receptors  in the Project area and identifies a series of management and mitigation measures  that  are  required  to  ensure  potential  impacts  on  these  receptors  are avoided and / or minimised.  

5.2. Regulatory Requirements & Relevant Policy & Guidance 

5.2.1. Legal protection is afforded to the different species present in the Project area.  This is summarised below. 

MARINE MAMMALS 

5.2.2. All species of cetacean (whale, dolphin and porpoise) occurring in UK waters are listed in Annex IV (species of community  interest  in need of strict protection) of the Habitats Directive as European Protected Species (EPS) and fully protected in Scottish territorial waters (out to 12 nm) under the Conservation (Natural Habitats, &c.) Regulations 1994 (as amended).  These regulations prohibit the deliberate  killing,  disturbance  or  the  destruction  of  these  species  or  their  habitat.      Bottlenose dolphin and harbour porpoise are also listed on Annex II of the Habitats Directive as species whose conservation requires the designation of Special Areas of Conservation (SACs) as enforced through Schedule 2 of the Habitats Regulations.  EPS species will be present in the Project area; however, there are no existing or proposed protected sites for cetaceans in Shetland.   The nearest sites are:  The Inner Hebrides and the Minches cSAC (north west coast Scotland), which has been designated for  harbour  porpoise;  The Moray  Firth  SAC  (north  east  coast  Scotland) which  is  designated  for bottlenose dolphin; and The possible North East Lewis Nature Conservation Marine Protected Area (NCMPA) (also north west Scotland) which has been proposed for Risso’s dolphin.  Given the distance of these sites from the proposed work areas (more than 200 km) the potential for the activities to impact  individual  animals  from  these  sites  and  for  this  to  affect  the wider  species  populations associated with the sites, is highly unlikely.  

5.2.3. Cetaceans are also listed in Schedule 5 of the Wildlife and Countryside Act 1981 which prohibits their deliberate  killing,  injuring  or  disturbance.  The  Nature  Conservation  (Scotland)  Act  2004 makes amendments to the Wildlife and Countryside Act 1981 in Scottish waters, including the addition of 'reckless' acts to species protection which make it an offence to intentionally or recklessly disturb a cetacean. 

5.2.4. Although not afforded the strict protection of EPS through the Habitats Directive, pinniped species occurring in UK waters are listed in in Annex V (and hence Schedule 3 of the Habitats Regulations) such  that  they are defined as species of community  interest and  taking  in  the wild may  thus be subject to management measures. Two species, grey and harbour seals, are also listed in Annex II as species whose conservation requires the designation of SACs and they are thus featured on Schedule 2 of the Habitats Regulations. 

Page 36: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 34 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

5.2.5. The Marine (Scotland) Act 2010 also makes it an offense to "recklessly or intentionally harass" seals at any designated haul out location in Scotland. 

5.2.6. In addition to the  legislative protection afforded to cetaceans and pinnipeds, species of cetacean occurring regularly in UK waters are designated as UK Biodiversity Action Plan (UKBAP) species, as is the harbour seal.   Seven cetacean and two seal species are  listed on the Scottish Priority Marine Features (PMF) list.  

BIRDS 

5.2.7. All rare, threatened or vulnerable bird species listed in Annex I of the Birds Directive, and all regularly occurring migratory species, are afforded protection through the designation of Special Protection Areas (SPAs).  In 2016, the Scottish Government identified a suite of an additional 15 proposed SPAs (pSPAs) for marine birds.   These pSPAs have been identified specifically for the protection of at sea territories for 45 species of rare and vulnerable seabirds which depend on the marine environment for a large part of their lifecycle.  The proposed cable routes are located within the Blue Mull and Colgrave  Sounds  proposed  SPA  (pSPA).  This  site  has  been  proposed  as  a  protected  site  for  the presence of breeding red‐throated diver (Gavia stellata). 

5.2.8. All wild birds in the UK are also protected under the Wildlife and Countryside Act 1981 (as amended).  Under  this Act  it  is an offence  to  intentionally or  recklessly: kill,  injure,  take, damage,  interfere, disturb or harass wild birds listed on Schedule 1 and 1A. This applies to their nests, eggs and young.     

FISH  

5.2.9. Atlantic salmon, allis and twaite shad, and sea and river lamprey (diadromous migratory species) are listed  on  Annex  II  of  the  Habitats  Directive  and,  as  such,  are  afforded  protection  through  the designation of SACs.  These species are also listed on the International Union for the Conservation of Nature (IUCN) Red List Atlantic salmon.  Atlantic salmon, sea and river lamprey are also listed as PMFs and also on the Convention for the Protection of the Marine Environment in the North East Atlantic (OSPAR) list of marine habitats and species considered to under threat or in decline within the north‐east Atlantic.   

5.2.10. A number of elasmobranchs species (sharks, rays and skates) are also listed as OSPAR species and listed on the IUCN Red List as being vulnerable, except white skate which is listed as endangered and common skate which is listed as critically endangered.  Most species are also UK BAP species. Basking shark, spurdog and common skate are also listed PMFs.  Basking shark is also protected under the Wildlife and Countryside Act 1981.  Herring and sandeel (benthic spawners) are also PMFs.   

OTTERS 

5.2.11. Otters are a European Protected Species  (EPS) and, as  such, are protected against deliberate or reckless harassment, disturbance including while occupying their structure/shelter or rearing/caring for their young.  It is also an offence to obstruct access to a breeding site or resting place or damage or destroy a breeding site or resting place of such an animal, including when the animal is not there. Otters are also  listed  in Annex II as species whose conservation requires the designation of SACs. There is no designated protected site with marine components (with otter as a designted feature) located  in the  immediate vicinity of the replacement cable routes and  landfall  locations. The SAC with otters as a designated  feature  in  closest proximity  is  the   Yell Sound Coast Special Area of Conservation (SAC) (Figure 5.1).   The site, which extends along the coast within the Yell Sound,  is 

Page 37: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 35 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

designated for the presence of harbour seal (Phoca vitulina) and European otter (Lutra lutra), both listed on the Annex II of EU Habitats Directive and is located 24 km soth‐east from the cable routes. 

5.3. Overview of Key Sensitive Receptors Present and Potential Impacts 

5.3.1. Based on the  information that has been collected and assessed  in support of the Marine Licence application the following species maybe present  in the vicinity of the marine cable route corridor and cable landfall works. 

MARINE MAMMALS 

5.3.2. Six species of cetacean occur regularly in waters around Shetland: harbour porpoise; white‐beaked dolphin, minke whale,  Killer whale,  Risso’s  dolphin.   More  rare  sitings  are  striped  dolphin  and humpback whale. Of these the harbour porpoise and white‐beaked dolphin are the most frequently recorded species in the vicinity of the Project area.   Both species are PMFs. Harbour porpoise is also listed on Annex II of the Habitats Directive.  

5.3.3. There is also potential for grey and harbour seals to be present in the Project area.  The proposed cable routes are  located 24 km south‐east (28 km by sea) from the Yell Sound Coast SAC,   where harbor seals seals are a qualifying feature. Thus, they are within forgaing range for harbor seal. There are also a number of designated seal haul out sites  in  the Project area. The majority of sites are located at a reasonable distance from the area of works (closest 2 km north, Westling Seal haul‐out) and vessels associated with the Project will not be present in the waters adjacent to these sites. 

BIRDS 

5.3.4. Waters around Shetland support a number of nationally and internationally important populations of seabird and waterfowl.  As such, a number of SPAs and pSPAs have been designated to protect key species.  The proposed cable routes are located within the Bluemull Sound pSPA,  designated for breeding  red‐throated  diver.  Red  throated  divers  are  considered  to  be  sensitive  to  disturbance during the breeding season. The closest designated SPA to the Project area is the Hermaness, Saxa Vord and Valla field SPA, located approximately 3 km to the north‐east of the Project area.   

5.3.5. There are eight RSPB Reserves in Shetland, the closest of which is Yell (3.4 km south of the Project area) (NMPI, 2018). 

5.3.6. There are also 78 SSSIs in Shetland, including 31 for marine biological features and 36 coastal sites for geological and morphological features (NAFC Marine Centre, 2015).  The closest SSSI is the North Fetlar SSSI,  located 6 km  to the south‐east of the proposed Yell – Unst cable routes.   This site  is designated as SSSI  for  the protection of a number of breeding seabirds and  land birds, grey and harbour seals, and for the presence of Calaminarian grassland and serpentine heath (SNH, 2014). 

5.3.7. There are 49 designated Local Nature Conservation Sites  (LNCS)  in Shetland. The closest LNCS  is located approximately 340 m to the north of the Project area, and is designated for land geodiversity features (NAFC Marine Centre, 2015). 

5.3.8. A small colony of Arctic tern (Sterna paradisaea) is known to breed at Loch Snarravoe, approximately 200 m south‐west of the cable landfall at Unst (ERM, 2018).   

FISH 

Page 38: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 36 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

5.3.9. There  is potential for a number of fish species to be present within the Project area (Aires et al., 2014).  These include species that depend the seabed for spawning (benthic spawners) (herring and sandeel) elasmobranchs (sharks and rays) and diadromous migratory species e.g. Atlantic salmon.  In terms of benthic spawners, although there is potential for sandeel spawning in the Project area, this is only at a low intensity.  The seabed within the working corridor is predominatntly rocky  which is generally unsuitable for sandeels which prefer sandy sediments for spawning.  

5.3.10. Elasmobranchs  (sharks,  rays  and  skates)  use  electroreceptors  to  detect  very  small  changes  in electrical currents.  They have slow growth rates and low reproductive output compared to other fish  species  and  therefore  can  be  slow  to  recover  if  their  populations  are  rapidly  depleted.  Consequently, due to pressures from overfishing many elasmobranchs are listed on the IUCN Red List.  Key elasmobranch species in Shetland waters include skate, spurdog,  spotted ray and basking shark.   

5.3.11. Migratory diadromous fish species are also considered to be electro‐sensitive in that they are able detect  induced voltage gradients.   Atlantic salmon, sea trout and European eel, for example, use magnetic  fields  for orientation and navigation during migration, while  river and  sea  lamprey are thought to use weak low‐frequency electric field to detect prey and predators.  Research by Godfrey et al., 2014 and Guerin et al., 2014 suggests that Atlantic salmon may migrate through waters to the north and east of Orkney in addition to the Pentland Firth. However, it is uncertain whether Atlantic salmon migrate through the Orkney and Shetland waters or if they prefer the Pentland Firth route or use it exclusively (Malcolm et al., 2010). There are no known salmon rivers in the direct vicinity of the Project area (NMPI, 2018). 

5.3.12. There is also potential for noise sensitive fish species, such as cod and herring, to be present in the Project area.  

OTTERS 

5.3.13. Scotland is recognised as a stronghold for the otter in Europe, and is the most significant terrestrial mammal in Shetland. Along with harbour seal, the Yell Sound Coast SAC has been designated for the presence of European otter (L.  lutra). The site supports approximately 80 otters with the highest densities in Britain, thus representing 2.5% of the UK population.  

5.3.14. Three sightings of otter (L. Lutra) have been recorded from a recorded position approximately 760 m to the north of the proposed Yell landfall in 1979, 1991 and 2015 (NBN Atlas, 2018).  A site survey was conducted at Yell and Unst landfalls for the north cable route on 26th January by the Shetland Amenity Trust (ERM, 2018a, 2018b).   At Yell, high  levels of otter activity were recorded along the coast.   However, no holts were recorded within 200 m of the proposed North cable route  (ERM, 2010a) and within 100 m of the South cable route (ERM, 2018b).  At Unst, one otter holt was found on a coastal sandy bank, approximately within 20 m of the South cable landfall location.  Another two active holts were  found on  the  stretch of coastline at Snarra Voe,  the bay where  the cable landfalls are  located, however these were over 100 m from the  landfall sites (ERM, 2018b).   One otter holt was observed 100 m of the proposed North cable route at Unst on a coastal sandy bank (ERM, 2018a). 

5.3.15. A map illustrating all protected sites in and around the Project area is provided in Figure 5.1. 

   

Page 39: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 37 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

Figure 5.1 – Protected sites in and around the Project area 

Page 40: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 38 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

5.4. Potential Impacts on Key Sensitive Receptors   

5.4.1. Potential impacts on key sensitive receptors are summarised below.  Management and mitigation measures for avoiding or minimising these potential impacts are discussed in Section 5.5.   

MARINE MAMMALS 

5.4.2. The main source of potential impact on cetaceans is underwater noise from cable lay and support vessels, cable burial and placement of rock filter bags / concrete mattresses on the seabed.  There is potential for noise sensitive species (e.g. harbour porpoise) to be present in the Project area.   

5.4.3. As with cetaceans, there is potential for seals (while at‐sea) to also be affected by underwater noise generated during cable installation.  However, given that seals are less sensitive to underwater noise than certain cetacean species, potential impacts in terms of disturbance and habitat avoidance are likely to be limited.   

5.4.4. Although impacts on seals at‐sea are limited, grey and harbour seals could be disturbed from their haul due to activities in adjacent waters. As noted above, the Yell landfall is located 24 km from the Yell Sound Coast SAC,   where harbour seals are a qualifying feature.   There are also a number of other designated seal haul out sites located in the vicinity of the Project area, the closest one being the Westling  Seal  haul‐out  2km  north  from  the  Project  are.   Hauled  out  seals  are  sensitive  to disturbance (noise or physical presence of construction vehicles and equipment).  Breeding seals are particularly  sensitive  to disturbance as  this can  lead  to  the abandonment of pups  if  the  level of disturbance is too high.   However, the vessels involved in the installation works will not require to move this far from the Project area and therefore no impacts are predicted.  Measures for avoiding any disturbance to seals within these designated haul out sites are presented in Section 5.5..  

BIRDS 

5.4.5. Potential impacts on seabirds offshore (e.g. disturbance) are limited due to the localised, temporary and short term nature of the cable installation activities (30 days per cable), and the slow speeds of the cable  lay and support vessels. Activities at  the  landfall are not expected  to  impact protected species  in  the  Project  area,  particularly  the  red‐throated  diver  and  the  Artic  tern,  because  the proposed works are planned to occur between October 2018 – March 2019, which is outwith the breeding season for these species (April – mid‐September for red‐throated diver, and May – August for Arctic tern).   

FISH 

5.4.6. Impacts on  fish are  limited.   As noted above,  the Project area  is not considered a key  spawning ground for herring or sandeel.  Therefore, there are no impacts on either species due to a loss of spawning  grounds.      There  is potential  for  localised disturbance of  certain  fish  species  that  are sensitive to noise (e.g. cod and herring) associated with cable installation activities (vessel noise etc.).  However, due to the highly localised, temporary and short term (one week) nature of these activities and  the  extent  of  alternative  available  habitat  for  these  species  (most  of North  Sea),  potential impacts are highly unlikely.    

5.4.7. With regards to potential impacts from electromagnetic fields (EMFs), based on data available from the cable manufacturer for the replacement cable between Yell and Unst, it is predicted that based on  the specific cable design and  if  the cable were continuously operating at maximum  load,  the 

Page 41: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 39 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

electromagnetic field at the external surface of the cable will be 770.0 µT, reducing to 6.8 µT at a distance of 0.5 m from the cable and 1.7 µT at a distance of 1 m from the cable.  When these fields are  compared  to  the  earth’s  natural magnetic  field of  50 µT,  any  potential  EMF  impact will be restricted to the immediate area of the cable only and does not extend any distance from the cable.  Also it is worth noting that in reality, during operation the cable will be loaded well below maximum limits and therefore the actual EMF field less than that predicted above.  It is recognised that burial of a cable (either trenched or with protection such as concrete mattresses or rock placement) is the most effective way  to  reduce EMF  impacts, but based on  the character of  the  seabed along  the proposed route, all of the cable will be surface laid.  In terms of potential impacts on elasmobranchs or electro‐sensitive species that could be present in the immediate footprint of the cable, while there will be EMF emissions  from  the  replacement  cable,  these emissions will  replace  those  from  the existing cable (once the existing cable is taken out of the service) and be limited to the immediate vicinity of  the cable only.   There will be a  short period of  time when both  the  replacement and existing cables could be operational, however even during this time, the spatially limited nature of the emissions that could potentially impact electro sensitive species indicate there are unlikely to be any significant impacts. 

OTTERS 

5.4.8. As noted above, there is potential for otters to be present within the Project are.  Potential impacts on  otters  include  loss  of  habitat  and  disturbance.     Management  and mitigation measures  for avoiding these impacts are presented in Section 5.5 below.  In the event that potential impacts on otters  cannot  be  avoided,  given  that  they  are  listed  on Annex  II  of  the Habitats Directive,  any disturbance will require a European Protected Species (EPS) licence.    

5.5. Management Requirements 

5.5.1. This section provides measures for avoiding and reducing potential impacts on species that may be present in the vicinity of the marine and cable landfall works, below MHWS. 

EMPLOYER INTERNAL GUIDANCE DOCUMENTS 

5.5.2. In recognition of the protected status of the above species, the Employer has developed a number of internal guidance documents and procedures in order to manage their operations, these include: 

Otter Species Protection Plan (TG‐NET‐ENV‐503); 

Bird Species Protection Plan (TG‐NET‐ENV‐505); and 

A Project specific Marine Mammal Protection Plan (MMPP) (see Section 5.5.3). 

MARINE MAMMALS – MARINE MAMMAL PROTECTION PLAN (MMPP) 

5.5.3. The  following measures have been  identified  to  reduce  collision  risk  and disturbance  to marine mammals  (cetaceans and  seals) present  in  the area of  the Project  through  the preparation of a Marine Mammal Protection Plan (MMPP). The potential for disturbance to marine mammals arises from the noise generated by the proposed cable decommissioning activities. The noise source level emitted by the vessels are expected to be similar to those emitted by traditional vessels, 160 – 175 dB re 1μPa (rms) from a small vessel (<50 m length) and 165 – 180 dB re 1μPa (rms) for a medium sized vessel (50‐100 m length).  The USBL is expected to emit at 190 re 1μPa (rms), the multibeam echosounder at 190 to 240 dB re 1μPa (rms) and the side‐scan sonar at 200 to 230 dB re 1 μPa (rms). 

Page 42: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 40 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

The MMPP  incorporates  the  requirements of  the European Protected Species Plan  (EPS Plan) as identified by the EPS Risk Assessment: 

Deployment of qualified and trained MMO(s)/PAM operator(s)1 on a vessel for the duration of the works to monitor for the presence of marine mammals (cetaceans and seals) prior to the commencement of, and during, the works: 

o There will be MMO coverage for the duration of the cable decommissioning activities, with  trained and experienced MMO(s) working  standard 12 hour shifts.   They will have experience of working at sea and will be trained and experience in the operation of PAM (acoustic) equipment; 

o During daylight hours the MMOs will carry out visual observations to monitor for the presence of marine mammals prior  to commencing activities and will  recommend delays in the commencement of activities should any marine mammals be detected within the mitigation zone (see below); and 

o When visibility is poor (i.e. due to fog or during hours of darkness) the PAM system will be operated by a single MMO/PAM operator prior to any cable marine operations commencing. 

Mitigation  zone  – works  only  to  commence  once  all marine mammals  are  clear  of  the mitigation zone.  The following mitigation zones, relating to animals present in the water, will be implemented for the Project: 

o 500 m for cetaceans; 

o 100 m for seals; and 

o Should  any  cetacean/seal  be  detected  within  the  relevant  zones  listed  above, activities will be delayed until their passage (or the transit of the vessel) results in the marine mammals no longer present in the mitigation zone.  In both cases, there will be a 20 minute delay from the time of the last sighting within the mitigation zone to the commencement/recommencement of the activities. 

Reporting: 

o All marine mammal  sightings,  including  seal  sightings, will be documented by  the MMO according to JNCC guidelines. 

The Contractor will provide all Project personnel with marine mammal awareness and good practice training;  

Posters and signs identifying risks and good practice will be provided; 

Pictures of species of concern will be provided;  

The vessels  involved  in  the works are not expected  to regularly exceed 10 knots, a speed threshold above which most lethal and serious injuries to marine mammals are thought to occur; and 

The MMO will have the authority to postpone or stop works  in conditions of  low visibility where marine mammal collision risk is high and the full extent of the safety zone cannot be observed. 

                                                            

1 As daytime working only, only one MMO / PAM operater expected to be required.   

Page 43: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 41 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

 

MARINE MAMMALS – SEAL HAUL OUT SITES 

5.5.4. Although no impacts are expected the Employer will ensure the Contractor is aware of the Scottish Government  advice  and  responsible  behaviour  around  seals http://www.gov.scot/Resource/0045/00452869.pdf.    Scottish  Government  advice  on  issues regarding  seal  haul  outhaul‐outs  states  “New  activities  taking  place  near  seal  haul‐outs, which present no significant disturbance to the seals, or where the disturbance  is  low  level (a few seals) and/or short term  (over a short time period), will normally be acceptable. This may require some monitoring of the seals to avoid the risk of potentially causing a significant proportion of seals on a haul‐out site to leave that site either more than once or repeatedly or, in the worst cases, to abandon it permanently.” 

BIRDS – MARINE  

5.5.5. Due to the location of the Project area within the Bluemull Sound pSPA where there is a potential for 24 hour working, the following measures will be implemented to minimise potential impacts on qualifying features associated with this site:  

Lighting on‐board the cable installation vessel will be kept to the minimum level required to ensure safe operations; and  

Lights will be directed or shielded to prevent upward illumination and minimise disturbance on the protected features of the Bluemull Sound pSPA. 

FISH 

5.5.6. The following measures have been identified regarding elasmobranchs and migratory fish:  

The selection of surface lay as the preferred installation method for the Yell‐Unst cables will minimise the generation of underwater noise by reducing the need for seabed disturbance and reducing duration of installation activities (installation of the subsea cables between Yell and Unst will take 30 days); and 

EMF has been minimised  through a  three‐core design and double wire armouring of  the cable. 

OTTERS 

5.5.7. In the event that potential impacts on otters at the cable landfalls cannot be avoided, given that they are listed on Annex II of the Habitats Directive, any disturbance will require a European Protected Species (EPS) licence. 

5.5.8. As otters are known to be present and / or make use of the cable landfalls and the following details good practice measures in the event of discovery of otters or their resting sites/holts prior to and during landfall construction:  

Preconstruction surveys will be undertaken at least two months prior to works commencing in order to allow time for any  licence applications that may be required.   These should be followed  up with  additional  surveys  immediately  prior  to works  commencing  if  suitable habitat is identified at either of the landfalls; 

Page 44: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 42 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

In the event of a discovery of an otter shelter, a protection zone with a minimum of a 30 m radius will be set up and will be clearly demarcated/fenced off;  

Vegetation will not be cleared from within any protection zones; 

Access to open water habitats, including freshwater sites on / adjacent to the coast, will be safeguarded at all times; 

Impacts to established otter paths and customary routes between areas will be minimised;  

Any lighting required will be directional and directed away from otter habitat; and 

5.5.9. If  breeding  is  suspected where  construction  work  is  already  underway,  on‐site  activity will  be suspended until it can be demonstrated that either (a) breeding is not occurring on site or (b) the cubs are sufficiently old (and therefore mobile) for alternative sites to be used elsewhere.    If  (a), work will be suspended for up to 8‐10 weeks in the area until cubs are mobile.  If this is not possible, a much larger protection zone will be required of between 100 m and 200 m from the otter shelter.  The exact size of this protection zone will be determined by the ECoW  in consultation with SNH.  Where  there  are  imperative  over‐riding  reasons  for  continuing  with  the  work  and  risking disturbance, a licence would be required to be sought from SNH. 

BIRDS – ONSHORE  

5.5.10. The following measures have been identified to ensure the protection of birds at the cable landfalls:  

The proposed works are planned to occur between October 2018 and March 2019, therefore if vegetation clearance is required at the cable landfalls, it will avoid the breeding bird season for the red‐throated diver (March – mid‐September) which is proposed for protection under the Bluemull Sound pSPA;   

In open areas suitable for ground nesting birds, mitigation measures including placement of Hawkeye  bird  scarers,  ticker  tape  or  scarecrows  (e.g.  from  old  Personal  Protective Equipment;  PPE)  and  strimming may  be  used  to  discourage  birds  nesting  (providing  no Schedule 1 or 1A species are present); and 

Although the proposed works are planned to occur outwith the main breeding season for birds  (March  to  September  inclusive),  should  any  birds  be  found  breeding  during construction, a protection  zone will be erected around  the nesting  site and  left until  the young have fledged.  It is an offence to remove or restrict access to any bird’s nest while it is being built or in use.  If a bird nest is to be removed then it must be shown to be disused. 

LANDFALLS ‐ GENERAL 

5.5.11. Preconstruction surveys at the cable landfalls (as appropriate) will be undertaken to confirm if any of these species are present prior to the commencement of works.   

5.5.12. In order to prevent impacts on protected species:  

The Ecological Clerk of Works (ECoW) (appointed by the Contractor) will conduct daily checks of  the  Project  landfalls  during  construction  of  the  onshore  project  elements, which will include inspection for the presence of otters and breeding birds;   

Personnel  will  be made  aware  of  good  practice measures  for  relevant  species  through toolbox talks; 

Page 45: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 43 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

Where  pipes  or  ducts  are  being  used  these  will  be  capped  to  prevent mammals  from accessing and becoming trapped; 

Any excavations left open overnight will be covered or provisioned with mammal ramps to prevent mammals, from falling in and becoming trapped; and   

Works will  take place within a clearly demarcated works area with barriers such as Heras fencing used as appropriate. 

   

Page 46: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 44 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

6. Environmental  Management  and  Mitigation  of  Effects  on  Other Marine Users 

6.1. Introduction  

6.1.1. In recognition of the importance of the management of the Project with regards to other users of the sea, a separate (Fishing) Liaison Mitigation Action Plan has been produced alongside this CEMP and provides further details on the key sensitive receptors in the Project area and identifies a series of management and mitigation measures that are required to ensure potential  impacts on these receptors are avoided and / or minimised.  

6.1.2. For completeness of the CEMP, this section describes the regulatory and policy framework under which  the Employer  is required  to ensure minimise disruption  to, and safeguard access to, other marine users, including fisheries and activities in the Project area and a summary of the key sensitive receptors, potential impacts and management and mitigation measures.   

6.2. Regulatory Requirements & Relevant Policy & Guidance 

6.2.1. The  Scottish  Government  adopted  the  National  Marine  Plan  (NMP)  in  2015  to  provide  an overarching framework for marine activity in Scottish waters.  The plan is underpinned by a set of policies which apply across existing and future development and use of the marine environment.  Under Fisheries Planning Policies, Policy 3  states  ‘where existing  fishing opportunities or activity cannot  be  safeguarded,  a  Fisheries  Management  and  Mitigation  Strategy  (FMMS)  should  be prepared by the proposer of development’. 

6.2.2. The NMP also sets out a number of key objectives and policies relating to subsea cables (further information in Appendix A including:  

Protect submarine cables whilst achieving successful seabed user co‐existence;  

Achieve the highest possible quality and safety standards and reduce risks to all seabed users and the marine environment; and 

Support  the  generation,  distribution  and  optimisation  of  electricity  from  traditional  and renewable sources to Scotland, UK and beyond.  

6.2.3. The Shetland Islands Marine Spatial Plan (SIMSP) provides an overarching policy framework to guide marine development and activity.  The SIMSP is based on Scottish Ministers’ commitment to making marine  management  more  efficient,  inclusive  and  accessible.  Areas  of  constraint  and/or opportunities for development have been identified in order to reduce potential conflicts between marine activities and encourage co‐existence between multiple users. The SIMSP aims at providing an approach to the management of the sea around Shetland; facilitating an integrated and better informed decision‐making process regarding the future distribution of activities and resources; and enabling the long‐term protection and use of the marine environment. The SIMSP has been prepared to align closely with the Scottish National Marine Plan, National Planning Framework 3 and Scottish Planning Policy.   This  is reflected  in the plans guiding principles, aims and objectives all of which underpin  the  overarching  vision  to  ensure  that  the  Shetland  waters  is  a  clean,  healthy,  safe, attractive and productive marine and coastal environment that is rich in biodiversity and managed sustainable to support thriving and resilient local communities 

Page 47: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 45 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

6.2.4. The SIMSP also includes a number of general planning policies (section 4) and a number of sectoral policies which are specifically relevant to particular types of development or activity.  See Appenix C for further detail on relevant policies in the SIMSP. 

6.3. Overview of Key Sensitive Receptors Present and Potential Impacts 

6.3.1. Based  on  the  information  that  has  been  collected  and  assessed  in  support  of  the  FLMAP,  the following marine users have been identified as being present / using the marine environment in the vicinity of the marine cable route corridor and cable landfall works: 

Low vessel traffic is observed crossing the Yell to Unst cable route. The majority of this activity is likely to be from commercial shipping vessels  and tankers transiting to and from Sullom Voe terminal. There are also ferry transits (Toft‐Ulsta) are located in the vicinity Project area (0.5 nm). 

Fishing activity occurs in the vicinity of the cable, with the highest effort in the area attributed to mid water otter trawls. MMO VMS data for all fishing methods shows slightly elevated activity  by  effort  and  value  in  the  immidate  vicinity  of  the  Yell  to  Unst  cable  route. Nonetheless,  these  values  are moderate  compared  to  overall  effort  and  value  of  fishing activity in Shetland waters. 

Surveys suggest chartered angling boast extend towards the inshore regions around the cable route. 

Canoeing/kayaking has possible enchroachment to the west of the cable route, motor crusing has low‐intermediate level of activity across the length of the cable route and sailing activity is observed at low levels in the vicinity of the cable route.  

Scuba diving has a possible interaction as there is a dive site to the west of the cable route. However, the spatial extent of the site is unclear so there is a possibility for an interaction.  

There are wrecks in relatively close proximity to the Project area but they do not overlap with the cable route.  

There is an aquaculture site in the vincity of the Project area and areas surrounding the cable route is a shellfish protected area. 

There is a fully operational Tidal array system deployed in bluemell sound in Shetland, Two turbines have been installed to date. 

6.4. Potential Impacts on Other Marine Users 

6.4.1. Potential impacts on other marine users are summarised below, with further details provided in the FLMAP.  Management and mitigation measures for avoiding or minimising these potential impacts are discussed in Section 5.5.   

COMMERCIAL FISHERIES 

6.4.2. During  installation of the cable there  is potential for temporary exclusion of fisheries from within the Project area.   In accordance with navigational safety requirements, a 500 m safety zone will be implemented  around  the  cable  lay  vessel  and  associated  guard  vessel  for  the  duration  of  the installation works.   Fishing will not be permitted within this safety zone.  However, given that the 

Page 48: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 46 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

cable  installation works are only expected to take one week to complete, the potential  impact of this temporary exclusion on local fisheries will be negligible.   

6.4.3. Once installed, the presence of cables on the seabed presents a potential obstruction, and safety risk, to fisheries, in particular demersal trawls and dredges which catch fish by dragging nets / gear along the seabed.  Where nets / gear get caught or snagged on seabed infrastructure such as cables this can cause damage to the nets and presents a potential safety risk to vessels.  Consequently, the presence of the cable can lead to the long term exclusion of fisheries from the Project area. However, given the primary fishery in the Project area is creeling for crab and lobster, long term exclusion from fishing grounds along the cable is very unlikely as fishermen will still be able to safely lay and retrieve pots in the area where the cable is present.  The fact fishing as not been excluded from along the route of the existing cable is evidence of this.   

SHIPPING AND NAVIGATION 

6.4.4. The main risk to shipping and navigation is increased risk of collision between the cable lay and any support  vessels  and  other  vessels  transiting  the  area.    As  noted  above,  in  accordance  with navigational safety requirements a 500 m safety zone will be implemented around the cable lay and any support vessels for the duration of the cable installation activities.   A number of other measures such as, Notices to Mariners, will also be  implemented (detailed below) to advise other mariners and sea users in the area of the presence of the cable lay vessel and the nature of the works being undertaken.   Given that cable installation activities are expected to be completed within one week, the risk of collision between the cable lay vessel and other vessels is considered to be very low.   

OTHER SEA USERS 

6.4.5. There is a fully operational Tidal array system deployed in bluemell sound, the Crown Estate lease area extends beyond the current site. The current and proposed spatial distribution of the Shetland Tidal Array site overlaps with the Yell‐Unst cable routes. Furthermore, and area identified for tidal development has been indentified in the Yell Sound, this overlaps only with the south cable route. However, it is unlikely that the proposed cable installation activities would have a significant impact on development proposals within the Project area.   

6.4.6. Potential impacts on other sea users are limited to temporary disruption to activities during cable installation due to the presence of the cable lay vessel and associated 500 m safety zone.  Once cable installation  activities  are  complete  (expected  one  week)  it  is  expected  that  activities  such  a recreational sailing and other water sports will be able to recommence and will be unaffected by the presence of the cable.    Impacts on any sand and gravel extraction will also be  limited due to the small scale of the cable infrastructure in relation to the available sand and gravel resource.   

6.5. Management Requirements 

6.5.1. This section provides measures for avoiding and reducing potential impacts on fisheries and other sea users that may be present in the vicinity of the marine and cable landfall works, below MHWS. 

COMMERICAL FISHERIES AND OTHER SEA USERS 

6.5.2. As discussed in Section 3, in accordance with requirements of the Marine Licence, the Employer has prepared a FLMAP for the Project.   

Commented [RP1]: SHEPD can you please confirm this?

Page 49: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 47 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

6.5.3. The FLMAP sets out the primary responsibilities of the Commercial Fisheries Liaison Officer (CFLO) and the Fisheries Industry Representative (FIR).   This includes ensuring effective communications with all legitimate sea users.    

6.5.4. Information will be provided through notice(s) to mariners and/or radio navigational warnings and publication  in  appropriate  bulletins,  prior  to  the  commencement  of  cable  laying  operations.  Notifications will state the nature and timescale of any works carried out in the marine environment relating to the cable installation operations.  In particular the Kingfisher Fortnightly Bulletin will be used to inform the Sea Fish Industry of the vessel routes, timings and locations of each cable laying operation along the licensed route (see the FLMAP for further details). 

6.5.5. The Employer will be responsible for ensuring that the location of the cable is charted by the United Kingdom Hydrographic Office (UKHO) and that surveys are undertaken post  installation to assess whether the cable is safe to trawl over.  

NAVIGATION 

6.5.6. The potential for vessel collisions during works is managed through the following key processes: 

Notification of works; 

Implementation of a safety zone around the area of works; 

Use of guard vessels; 

Engagement with all legitimate sea users;  

Implementation of a code of good practice for all vessels; 

Establishment of cooperation agreements between the Employer and commercial fisheries and other legitimate sea users; and 

Presence of a FIR during installation. 

6.5.7. Further details are available in the FLMAP. 

6.5.8. Other measures regarding navigation include: 

If any proposed cable protection reduces the water depth by greater than 5% this will be agreed with the MCA prior to installation; 

In periods of poor visibility,  restrictions  such as a  temporary cessation of works may be considered to reduce the risk of collisions; 

Vessels will have passage planning procedures, holding positions (e.g. if waiting on weather), traffic  monitoring  (radar,  visual  and  Automatic  Identification  System;  AIS),  means  of communications with third party vessels and emergency response in the event of a vessel approaching on a collision course; and 

The as‐laid coordinates of the cable will be issued to the UKHO and KIS‐ORCA charts.  This will ensure that mariners are aware of the location of the cable.  

 

SUBSEA INFRASTRUCTURE  

6.5.9. In  order  to  avoid  damage  to  pre‐existing  subsea  infrastructure,  a  detailed  pre  construction geophysical survey will be undertaken which will identify all pre existing infrastructure in the vicinity 

Commented [RP2]: SHEPD – do we need to acknowledge the renewables site lay down area that was discussed at the kick-off meeting on 19/04/18?

Page 50: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 48 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

of  the  works  and  will  be  used  to  inform  project  design  and  vessel mooring  patterns  (where appropriate).  

6.5.10. The only existing subsea assets in the vicinity of the works, are existing submarine electricity cables owned by the Employer this cable will be crossed following industry best practice. 

   

Commented [RP3]: NMPi only show one cable, SIMSP show three. SHEPD to confirm if there a consensus on how many there are between Yell and Unst? And that the Employer is the owner of them.

Page 51: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 49 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

7. Environmental Management  and Mitigation  of  Effects  on Marine Archaeology 

7.1. Introduction  

7.1.1. No features of archaeological interest were identified along the cable route corridor.  An additional survey is to be undertaken during May‐June in 2018 (as advised by SNH) which will be reviewed for features of archaeological interest. Thus, there is still potential for the Project to uncover previously unknown  features.    Therefore  archaeological management  and mitigation measures  have  been considered.  

7.1.2. This  section  also  describes  the  regulatory  and  policy  framework  under  which  the  Employer  is required to protect archaeological assets in the Project area.   

7.2. Regulatory Requirements & Relevant Policy & Guidance 

7.2.1. Legislation, policy and guidance relevant to the protection of the marine historic and archaeological environment is summarised below. 

INTERNATIONAL/ EU LEGISLATION AND POLICY 

The United Nations Convention of the Law of the Sea (UNCLOS); 

Annex  to  the UNESCO Convention on  the Protection of  the Underwater Cultural Heritage 2001; and 

The European Convention on the Protection of the Archaeological Heritage (revised), known as the Valletta Convention.  

UK LEGISLATION AND POLICY 

The Merchant Shipping Act 1995;  

The Protection of Wrecks Act 1973 (Section 1 of the Protection of Wrecks Act was repealed in  Scotland  on  the  1st November  2013  and  the  8 wrecks  around  the  coast  of  Scotland designated under  this  section of  the Act are now protected by Historic Marine Protected Areas (HMPAs) as defined in the Marine (Scotland) Act 2010); 

The Protection of Military Remains Act 1986 has the principal concern to protect the sanctity of vessels and aircraft that are military maritime graves. Any aircraft  lost while  in military service is automatically protected under this Act; and 

The UK Marine Policy Statement (2011) states heritage assets should be conserved through marine  planning  in  a manner  appropriate  and  proportionate  to  their  significance. Many heritage  assets  with  archaeological  interest  are  not  currently  designated  as  scheduled monuments or protected wreck sites but are demonstrably of equivalent significance.  

   

Page 52: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 50 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

SCOTTISH LEGISLATION AND POLICY 

The Marine (Scotland) Act 2010.  This requires licensing activities in the marine environment to consider potential impacts on the marine environment including features of archaeological or historic interest and defines marine historic assets (Section 73);  

The Historic Environment Scotland Policy Statement 2016;  

Scottish Planning Policy (SPP) 2014;  

The Scottish Government’s Planning Advice Note  (PAN 2/2011) Planning and Archaeology 2011; and 

The Scottish Government’s Planning Scotland’s Seas: Scotland’s National Marine Plan (March 2015).  

LOCAL PLANNING POLICY  

The  Shetland  Islands  Marine  Spatial  Plan  2015  (SIMSP)  includes  policies  which  aim  to preserve and protect marine archaeological and historical features. They are as follows; 

o Policy MSP HIS1: Historic Marine Protected Areas; 

o Policy MSP HIS2: Safeguarding Nationally Important Heritage Assets; and 

o Policy MSP HIS3: Safeguarding Locally Important Heritage Assets 

CODES OF PRACTICE, PROFESSIONAL GUIDANCE AND STANDARDS DOCUMENTS 

The Chartered  Institute  for Archaeologists  (CIfA) Codes, Standards and Guidance  (various) http://www.archaeologists.net/codes/cifa; 

The  Crown  Estate.  (2010.)  Model  clauses  for  Archaeological  Written  Schemes  of Investigation: Offshore Renewables Projects. Wessex Archaeology Ltd (Ref 73340.05) for The Crown Estate; 

English Heritage. (2012). Ships and Boats: Prehistory to Present.  Designation Selection Guide. Swindon: English Heritage; 

Gribble,  J.  &  Leather,  S.  for  EMU  Ltd.  (2011).  Offshore  Geotechnical  Investigations  and Historic Environment Analysis: Guidance for the Renewable Energy Sector. Commissioned by COWRIE Ltd (project reference GEOARCH‐09); 

The  Joint  Nautical  Archaeology  Policy  Committee  and  Crown  Estate.  (2006).  Maritime Cultural Heritage & Seabed Development: JNAPC Code of Practice for Seabed Development. York: CBA; 

Plets, R., Dix,  J., & Bates,  R.  (2013). Marine Geophysics Data Acquisition, Processing  and Interpretation: Guidance Notes. Swindon: English Heritage Publishing; 

Wessex  Archaeology.  (2014).  Protocols  for  Archaeological  Discoveries  (PAD) http://www.wessexarch.co.uk/protocols‐archaeological‐discoveries‐pad . Salisbury: Wessex Archaeology; 

Wessex  Archaeology.  (2006). On  the  Importance  of  Shipwrecks:  Final  Report  Volume  1. Salisbury: Wessex Archaeology; 

Wessex Archaeology.  (2011a). Assessing Boats and Ships 1860‐1913 Archaeological Desk‐Based Assessment. Salisbury: Wessex Archaeology; and 

Page 53: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 51 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

Wessex Archaeology.  (2011b). Assessing Boats and Ships 1914‐1938 Archaeological Desk‐Based Assessment. Salisbury: Wessex Archaeology. 

7.3. Overview of key features of archaeological importance in the Project area and potential impacts  

7.3.1. There are no known features of archeological importance e.g. ship wrecks or aircraft wrecks located in the Project area.   Therefore there will be no impacts on these features.   

7.3.2. Within  any  location  there  is  always  the  potential  for  the  presence  of  unknown  features  of archaeological importance.  However, based on the results from the marine survey and the highly dynamic nature of the marine environment along the route of the replacement cable, the potential for unknown remains  to be present  in  the Project area  is  low.   The potential  for any  impacts on unknown archaeological remains is therefore also considered to be low to negligible.  A survey is to be undertaken during May‐June in 2018 (as advised by SNH) which will be reviewed for features of archaeological interest.    

7.4. Management Requirements 

7.4.1. Although potential impacts on both known and unknown archaeological remains are considered to be negligible to nonexistent, there is still a requirement to identify specific measures that can be put in place to safeguard against any potential impacts on archaeological remains (known or unknown) in the area.   

Mitigation by design:  

o The potential for significant impacts on marine cultural heritage has been reduced to negligible‐low during the development and design of the Project by conducting a desk based assessment, geophysical and Drop Down Video (DDV) surveys to identify any marine historic environment assets;  

o A pre installation survey will be conducted to inform final cable routing and vessel anchoring areas which will seek to avoid any anthropogenic seabed features; and 

o Rock filter bags or concrete mattresses will be used to hold the cable  in position.  This will significantly reduce any cable movement and potential scour or disturbance of unknown archaeological remains over the lifetime of the Project.   

Mitigation during installation:  

o The  Employer  Supervisor  for Offshore Works will  be  the  initial  point  of  contact regarding archaeological interests; and 

o Potential impacts on unknown heritage will be managed through implementation of a  reporting protocol  for  the discovery of previously unknown marine  cultural material  during  development  e.g.  the  reporting  protocol  produced  by  Wessex Archaeology (2014) for the Crown Estate (http://www.wessexarch.co.uk/protocols‐archaeological‐discoveries‐pad). 

Mitigation during operation: 

o The reporting protocol will be kept in place in case anything of interest is observed during  inspection  surveys.  If  any  cultural  heritage  sites  are  reported  during inspection  surveys,  it  is  recommended  that  they  are  investigated  by  a  qualified marine archaeologist to determine their cultural heritage importance. 

Page 54: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 52 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

 

8. Invasive Non Native Marine Species (INNMS) 

8.1. Introduction 

8.1.1. It  is  common  practice  for  offshore  construction  projects  around  the UK  to manage  the  risk  of introduction of non‐native marine species.  As such all vessels involved in works will be required to meet  relevant  legislative  requirements  and  best  standard  practices  with  regards  to  ballasting activities (if any ballasting is required) and vessel biofouling management. 

8.2. Regulatory Requirements & Relevant Policy & Guidance 

8.2.1. To prevent the risk of spread of non‐native species through discharging of ballast water, all works will be carried out in accordance with The International Convention for the Control and Management of  Ships'  Ballast  Water  and  Sediments  (BWM),  adopted  2004  and  entered  into  force  on  8th September 2017.   

8.2.2. The BWM Convention requires all ships to conduct ballast water exchange (BWE) to a set standard (“D‐1’) or to meet a ballast water performance standard (‘D2’) (dependent on build date and ballast water capacity2). 

Standard D‐1 requires that all ships undertaking BWE should, whenever possible, conduct BWE at  least 200 nautical miles (nm) from the nearest land and  in water at least 200 m  in depth.  If  neither  of  these  scenarios  is  possible  then  a  vessel may  exchange  in  an  area designated by the port state. 

Standard D‐2 requires that new or retrofitted ballast water treatment systems be employed in order to minimise numbers of viable organisms remaining within the ballast tank before discharge. These treatment systems significantly reduce the likelihood of non‐native species being introduced by inefficient exchange practices or in the event of an untreated near shore discharge. 

8.2.3. The  International Maritime Organisation (IMO) also aims to control and manage ships' biofouling through the implementation of the Guidelines for the control and management of ships' biofouling to minimize  the  transfer of  invasive aquatic species  (Biofouling Guidelines  IMO 2011)  (resolution MEPC. 207 (62)). The Biofouling Guidelines are not ratified by member states, and there is currently no  requirement  for  hull  cleaning  for  vessel movement  between  ports  in  the  EU,  however  the guidelines are intended to provide a globally consistent approach to the management of biofouling. The Biofouling Guidelines  state  that a  ship  should  implement biofouling management practices, including the use of anti‐fouling systems and other operational management practices to reduce the 

                                                            

2 Ships constructed before 2009 with a ballast capacity of between 1,500 and 5,000 m3 must at least meet the ballast water performance 

standard, and ships with a capacity <1,500 or > 5,000 m3 must meet the BWE standards or the performance standards until 2016, after which time it shall at least meet the performance standard. Ships constructed in or after 2009 (capacity of < 5,000 m3) must meet the performance standard. Ships constructed between 2009 and 2012, capacity of 5,000 m3 or more shall meet D‐1 or D‐2 until 2016 and at least the performance standard after 2016. Ships constructed in or after 2012 (capacity of 5,000 m3 or more) shall meet the ballast water performance standard. 

Page 55: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 53 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

development of biofouling. The  intent of such practices  is to keep the ship's submerged surfaces, and internal seawater cooling systems as free of biofouling as practical. 

8.2.4. In addition, in 2014 SNH commissioned the production of guidance for producing site and operation based plans for preventing the introduction of non‐native species (Payne et al., 20143). 

8.2.5. Although not directly applicable to the introduction of non‐native marine species, related legislation is the Merchant Shipping (Anti‐fouling systems) Regulations 2009 which prohibit the use of harmful organotin compounds in antifouling paints used on ships.  Vessels of 400 GRT and above, and every ship which is certified to carry 15 or more persons should have an International Anti‐fouling System Certificate to ensure the antifouling paint complies with the regulations. 

8.3. Management Requirements 

8.3.1. In adopting management measures to prevent the introduction of INNMS, The Employer will: 

Ballast water management: 

o Ensure  all  vessels  contracted  to  undertake works will  be  contractually  obliged  to adhere  to  relevant  BWM  measures  as  outlined  above,  where  relevant  and  be surveyed and issued with an International Ballast Water Management Certificate. 

o Ballast Water Management Plans (BWMP) will be provided by contracted vessels in accordance with Regulation B‐1 of the Convention, alongside Ballast Water Record Books as described by BWM Regulation B‐2.  

Biofouling / Antifouling: 

o The Employer will request that all vessels consider  the requirements of Resolution MEPC.207(62) Guidelines  for  the Control  and Management of  Ships  Biofouling  to Minimise  the  Transfer  of  Invasive  Aquatic  Species,  including  for  example  the implementation  of  a  biofouling  management  plan,  and  records  of  biofouling management practices kept in a biofouling record book.  

o Ensure  all  vessels  (as  appropriate)  have  an  International  Anti‐fouling  System Certificate. 

o All vessels will be required to undertake pre use and post use checks, including the presence for marine growth.  All equipment (ploughs, ROVs etc.) will be required to be free from marine growth prior to mobilisation. 

9. Waste Management 

                                                            

3 Payne, R.D., Cook, E.J. and Macleod, A. (2014). Marine Biosecurity Planning – Guidance for producing site and operation‐based plans 

for preventing the introduction of non‐native species. Report by SRSL Ltd. in conjunction with Robin Payne to the Firth of Clyde Forum and Scottish Natural Heritage 39 pp.  Further background information on this guidance document can be found in the report entitled “Cook, E.J., Payne, R.D. and Macleod, A. (2014). Marine Biosecurity Planning – Identification of best practice: A Literature Review. Report by SRSL Ltd. in conjunction with Robin Payne to the Firth of Clyde Forum and Scottish Natural Heritage Commissioned Report No. 748 ‐ 45 pp. 

Page 56: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 54 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

9.1. Introduction 

9.1.1. The principal wastes generated  from  the works will  include packaging, general waste and waste water.  Hazardous wastes are possible in the form of used oils and chemicals. 

9.1.2. Under  the Duty of Care as a waste producer,  the  failure  to manage wastes generated  from  the Project,  such  as  failure  to  segregate  recyclates,  also  results  in  a  breach  of waste management legislation in addition to potential environmental impact. 

9.1.3. There are legislative requiremetns (see below) that stipulate specific requirements with regards to waste management for every ship (certified to carry 15 persons or more), and vessel (of 400 GRT and above).  Not all vessels involved in the proposed works will be over 400 GRT.  Vessels under 400 GRT, are not subject to the legislative requirements around ship waste.  However these vessls will be operated by a responsible compentant contractor. 

9.2. Regulatory Requirements & Relevant Policy & Guidance 

9.2.1. In terms of waste generated offshore, the International Convention for the Prevention of Pollution from Ships (MARPOL 73/78) Annex IV (sewage) and Annex V (garbage) is the main legislative driver. Under the Convention, the North Sea is designated as a Special Area where the disposal of any waste (except food waste) offshore is prohibited. The Convention is transposed into UK legislation by the Merchant Shipping (Prevention of Pollution by Sewage and Garbage from Ships) Regulations 2008, which places a number of obligations on vessels in terms of managing waste. 

9.2.2. The key driver for waste management legislation in the UK, when onshore disposal is required, is the Waste Framework Directive (WFD). The Directive is transposed into Scottish legislation by the Waste (Scotland) Regulations 2012; Waste Management  Licensing  (Scotland) Regulations 2011 and  the Environmental Protection (Duty of Care) (Scotland) Regulations 2014. These regulations require all businesses and organisations that produce waste to take all reasonable measures to prevent waste, and to apply the waste hierarchy when managing waste. 

9.2.3. A key requirement is that the waste producer is responsible for ensuring that their waste is collected by an appropriately licensed waste carrier and managed at a suitably licensed facility. Section 34 of the Environmental Protection Act 1990 (as amended) sets out a number of duties with respect to the  management  of  waste.  The  Waste  (Scotland)  Regulations  2012  amended  Section  34  to implement a number of actions in the Scottish Government’s Zero Waste Plan (2010). The Duty of Care: A Code of Practice (Scottish Government, 2012) explains these duties which apply to anyone who produces, keeps, imports or manages controlled waste in Scotland. 

9.2.4. In accordance with MARPOL (73/78) Annex V (as amended) every ship (certified to carry 15 persons or more), and vessel (of 400 gross tonnage and above) involved in the Project will have a Garbage Management  Plan.  The  plan will  include  procedures  for  the  collection,  storage,  processing  and disposal of all waste, and will designate an individual responsible for implementing the plan. Waste types and volumes generated by the works will be recorded  in a garbage record book. Once  the waste is brought onshore it will be managed in accordance with the duty of care legislation (Section 9.1.2).  Information  from  the  garbage  record book will be used  to  complete  the  relevant Waste Transfer Notes. 

9.2.5. The  Special Waste  (Scotland) Regulations 1996  set out  the  requirements  for  the preparation of Special  Waste  Consignment  Notes  for  the  handling  and  carriage  of  special  waste  (including 

Page 57: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 55 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

hazardous waste) as defined within the regulations. The regulations provide the requirements for the removal of ships’ waste to reception facilities and also the avoidance of mixing waste streams. 

9.3. Management Requirements 

GENERAL 

The only materials to be deposited to the seabed will be those detailed in the Marine Licence.   

All vessels engaged in the works will be equipped with waste storage facilities according to IMO International Convention for the Prevention of Pollution from Ships (MARPOL) standard vessels certified to carry 15 persons or more or of 400 GRT and above will have the following in place: 

o Waste management plan; and 

o Garbage record book. 

No waste will be disposed of over the side of the vessel and all produced waste will be stored on board. 

All waste  products  and  rubbish  will  be  removed  from  the  vessel  and  disposed  of  by  a registered waste disposal company. 

Any debris or waste materials arising during the course of the works will be removed from the vessel and disposed of by a registered waste disposal company. 

WASTE REDUCTION 

9.3.1. The waste hierarchy of Prevention, Re‐use, Recycle and Disposal will be adopted on the Project. The following measures will align  the Project waste management with  the hierarchy and  reduce  the amount of waste produced during construction:  

The appropriate volume of materials will be ordered; 

Excess materials will be returned to the supplier if possible;  

Re‐usable materials will be identified on site and removed for storage and re‐sale; 

Recyclable materials will be removed from site for processing in licenced facilities; 

There will be clearly located and defined storage areas for materials; and 

General  information  on waste will  be  provided  in  site  inductions  and  toolbox  talks with feedback welcomed. 

STORAGE OF WASTE   

9.3.2. The following methods have been identified in relation to storage of waste:  

Storage will be provided at suitable points for all waste streams including hazardous waste, liquid wastes and discarded smoking materials; 

Waste will be segregated as far as practically possible;  

Page 58: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 56 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

Waste will be  stored  in  secure covered containers which will be clearly  labelled with  the waste they hold e.g. wood, metal, plastics etc.; 

Liquid wastes will be stored in appropriately (portable or permanent) bunded facilities that hold the capacity of the container;  

Any hazardous waste will be  stored  in  separate  containers  (further details on hazardous waste are provided below); 

Any odorous wastes will be temporarily stored in suitable containers and where possible, at a distance from any nearby sensitive receptors; 

All places of work will be kept clean and tidy. Waste will not be allowed to accumulate. All surplus material and waste is to be removed in a timely manner; 

Storage areas / containers will be monitored and action taken if waste is piled too high; and 

Burning of waste is prohibited.  

HAZARDOUS (SPECIAL) WASTE 

9.3.3. “Hazardous waste” –any waste which  contains properties  that might make  it harmful  to human health or the environment.  In Scotland, hazardous waste is referred to as Special waste. 

9.3.4. Special waste could arise from the following sources: 

Maintenance of plant and machinery; 

Oily water waste;  

Oil filters;  

Oily rags; 

Oil absorbent pads etc.; 

Contaminated Marine Gas Oil (MGO); 

Hydraulic oil; and  

Environmental  spill  recovery  (small amounts only;  larger volumes  taken away directly  for disposal). 

9.3.5. All special waste will be segregated by type and from other waste streams.  

9.3.6. All special waste oil will be stored in a bunded facility until such times that it is collected. 

9.3.7. Used filters, rags and absorbents will be stowed in the special waste container in drums or waste oil bags.  

TRANSPORTING WASTE 

9.3.8. There is a duty of care on the waste producer to make sure that waste is appropriately disposed of. The following measures have been identified to comply with the duty of care:  

All waste leaving the Project will be accompanied by a Waste Transfer Note (WTN) for non‐hazardous waste or a Special Waste Consignment Note (SWCN) for hazardous waste.  A copy of which will be retained for 2 (WTN) or 3 years (SWCN); and 

Page 59: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 57 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

Waste contractors will be checked ahead of the works to ensure they have valid licences. 

   

Page 60: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 58 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

10. Pollution Prevention, Spill Response and Contingency Planning 

10.1. Introduction 

10.1.1. Potential  sources of offshore  pollution  associated with  the  vessels  and  assocaited works  are  as follows: 

Oil; 

Noxious liquid substances4; 

Harmful substances carried by sea in packaged form; 

Sewage; 

Waste from ships; 

Air pollution from ships ; and 

Invasive non‐native species. 

10.1.2. Specific practices relevant to the management of waste (including sewage) and invasive non‐native species are considered  in previous sections of this CEMP, and therefore this section of the CEMP focuses on wider pollution prevention and spill response and contingency planning. 

10.1.3. Reporting procedures (for any incident including a spill) are covered in section 12.4. 

10.2. Regulatory Requirements & Relevant Policy & Guidance 

VESSELS ‐ THE INTERNATIONAL CONVENTION FOR THE PREVENTION OF POLLUTION FROM SHIPS (MARPOL)  

10.2.1. The  International  Convention  for  the  Prevention  of  Pollution  from  Ships  (MARPOL)  is  the main international convention covering prevention of pollution of the marine environment by ships from operational or accidental causes.  All work will be carried out in accordance with these regulations.  The Convention includes regulations aimed at preventing and minimising pollution from ships and currently includes six technical Annexes: 

Annex I Regulations for the Prevention of Pollution by Oil (entered into force 2 October 1983) ‐ Covers prevention of pollution by oil from operational measures as well as from accidental discharges and requires all ships of 400 GRT5 and above to have an approved Shipboard Oil Pollution Emergency Plan (SOPEP) on board.  

Annex  II  Regulations  for  the  Control  of  Pollution  by  Noxious  Liquid  Substances  in  Bulk  (entered  into  force 2 October 1983)  ‐ Details  the discharge  criteria and measures  for  the control of pollution by noxious liquid substances carried in bulk; some 250 substances were evaluated and included in the list appended to the Convention; the discharge of their residues 

                                                            

4  Although  no  such  substances  are  expected  from  the  proposed  works  reference  to  noxious  substances  has  been  included  for 

completeness. 5 And all oil tankers of 150 GRT and above.  Regulation 17 of MARPOL Annex II makes similar stipulations that all ships 150 GRT and 

above carrying noxious liquid substances in bulk carry an approved SOPEP for noxious liquid substances. 

Page 61: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 59 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

is allowed only to reception facilities until certain concentrations and conditions (which vary with the category of substances) are complied with.    In any case, no discharge of residues containing noxious substances is permitted within 12 nautical miles of the nearest land.    

Annex  III Prevention of Pollution by Harmful Substances Carried by Sea  in Packaged Form (entered  into force 1 July 1992) ‐ Contains general requirements for the  issuing of detailed standards  on  packing,  marking,  labelling,  documentation,  stowage,  quantity  limitations, exceptions and notifications.  For the purpose of this Annex, “harmful substances” are those substances which are identified as marine pollutants in the International Maritime Dangerous Goods Code (IMDG Code) or which meet the criteria in the Appendix of Annex III. 

Annex  IV Prevention of Pollution by Sewage from Ships   (entered  into force 27 September 2003)  ‐ Contains requirements to control pollution of  the sea by sewage;  the discharge of sewage into the sea is prohibited, except when the ship has in operation an approved sewage treatment plant or when the ship is discharging comminuted and disinfected sewage using an approved  system  at  a distance of more  than  three nautical miles  from  the  nearest  land; sewage which is not comminuted or disinfected has to be discharged at a distance of more than 12 nautical miles from the nearest land. 

Annex V Prevention of Pollution by Garbage  from Ships  (entered  into  force 31 December 1988) ‐ Deals with the different types of garbage and specifies the distances from land and the manner in which they may be disposed of. The Annex designates Special Areas (including the North  Sea) where  the disposal of any garbage  is prohibited except  food wastes. The dumping of plastics at sea is also prohibited by this Annex. 

Annex VI Prevention of  Air Pollution from Ships (entered into force 19 May 2005) ‐ Sets limits on sulphur oxide and nitrogen oxide emissions from ship exhausts and prohibits deliberate emissions  of  ozone  depleting  substances;  designated  emission  control  areas  set  more stringent standards for SOx, NOx and particulate matter.  A chapter adopted in 2011 covers mandatory  technical  and  operational  energy  efficiency  measures  aimed  at  reducing greenhouse gas emissions from ships. 

CABLE LANDFALL INSTALLTION 

10.2.2. As the Project boundary ends at MHWS, in addition to the vessel related legislation detailed above the following legislation is also relevant to the works, in particular in relation to cable landfall works: 

The Water Environment (Controlled Activities) (Scotland) Regulations 2011 (CAR); 

The Water Environment and Water Services (WEWS) (Scotland) Act 2003; and 

The Pollution Prevention and Control (Scotland) Regulations 2012 (PPC 2012). 

10.2.3. The Water Framework Directive (WFD) came  into force  in December 2003 and  is  implemented  in Scotland  through  the Water Environment and Water Services  (Scotland) Act 2003. This provides Ministers with  the powers  to make regulations  to control activities which could affect  the water environment. The Scottish Environment Protection Agency’s (SEPA’s) powers under CAR are defined as for the purpose of ‘protecting the water environment’ and include authorising activities including abstractions, impoundments, building and engineering works, and activities liable to cause Pollution. Activities likely to cause pollution to the water environment require authorisation under CAR. A key objective of this Directive is the achievement of ‘good ecological status’ (as a minimum) of all natural waterbodies. 

Page 62: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 60 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

10.2.4. In  addition  to  these  regulations,  there  are  a  number  of  guidance  documents  and  best  practice guidelines related to prevention of pollution in the water environment, including: 

The  recently  updated  UK  guidance  for  pollution  prevention  (GPP)  available  at: http://www.netregs.org.uk/environmental‐topics/pollution‐prevention‐guidelines‐ppgs‐and‐replacement‐series/guidance‐for‐pollution‐prevention‐gpps‐full‐list/.    Including  GPP5 Works or Maintenance in or Near Water. 

Land  Use  Planning  System  SEPA  Guidance  Note  17.  Marine  development  and  marine aquaculture planning guidance; 

CIRIA (Construction Industry Research and Information Association) Report C532, Control of water, pollution from construction sites: Guidance for consultants and contractors; and 

CIRIA Report C584D, Coastal and marine environmental site guide (C584D). 

10.3. Management Requirements 

10.3.1. The Contractor will be  responsible  for ensuring all measures  set out within  the Annex’s detailed above are adhered to and appropriate management plans relating to each of the items above are produced and adhered to throughout the works.  

10.3.2. There are legislative requirements (Section 9.3) that stipulate specific requirements with regards to every ship (certified to carry 15 persons or more), and vessel (of 400 GRT and above).  Not all vessels involved in the proposed works will be over 400 GRT.  Vessels under 400 GRT, are not subject to the legislative requirements around ship waste.  However these vessls will be operated by a responsible compentant contractor. 

POLLUTION PREVENTION MEASURES OFFSHORE 

10.3.3. Emissions  shall  be  reduced  by  ensuring  efficient  operation  and maintenance  of  all  equipment wherever possible.  Specific energy and fuel efficiency projects should be introduced to reduce air emissions.   Natural resources such as  fossil  fuels shall be used as efficiently as possible.   Targets should be set to continually reduce CO2 emissions generated from all equipment. 

EMERGENCY SPILL RESPONSE  

10.3.4. All vessels 450 GRT and above require an approved SOPEP i.e. procedures and descriptions of actions to be taken  in the event of an oil pollution incident.   The SOPEP shall contain all  information and operational  instructions as required by the “Guidelines for the development of the Shipboard Oil Pollution Emergency Plan” as developed by the Organization (IMO). The appendices contain names, telephone, telex numbers, etc., of all contacts referenced in the SOPEP, as well as other reference material. 

10.3.5. The following measures have been identified regarding emergency spills:  

Work will stop immediately and the source of the spill will be addressed where possible;  

Follow vessel SOPEP procedure and emergency spill response; 

Isolate the source of the spill / leak if safe to do so; 

Sources of ignition will be eliminated – in case of spilled substance being flammable;  

Page 63: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 61 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

The spill will be contained as far as practicable using appropriate spill equipment;  

All spills will be reported to the appropriate authorities where applicable;  

The Project Team will be provided with emergency spill response training;  

Spill kits will be made available at fuel storage and refuelling locations and in individual plant vehicles and vessels; and 

Spill kits will be replaced after use. 

10.3.6. The  collected  contaminant  from  a  spill will be  treated as hazardous  (Special) waste  and will be disposed of appropriately. 

MONITORING AND RECORD KEEPING 

10.3.7. The  COSHH  record  for  any  chemicals  stored  on  the  Project  will  be  kept  and  updated  by  the Contractor along with  the data  sheet  for any COSHH Material, chemical or substance. Operating instructions have to be prepared (under the use of current Material Safety Data Sheets (MSDS)).  For all used hazardous substances a register has to be maintained. 

10.3.8. Records will be kept of all visual fuel and oil checks of plant and fuel and oil storage containers by the Contractor.  

10.3.9. Records will be kept by the Contractor of all spills and actions taken will be noted.  Lessons learned will be communicated as appropriate (see also section 12).  

POLLUTION PREVENTION MEASURES ONHSORE (AT CABLE LANDFALL) 

10.3.10. The Contractor will be required to undertake cable landfall works in line with standard industry best practice and the general environmental management plans provided by the Employer: 

Biosecurity; 

Waste management; 

Working in or near water; 

Unexpected contaminated land; 

Working in sensitive habitats; and 

Oil storage and refuelling.   

Page 64: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 62 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

11. Dropped Objects 

11.1.1. It will be a condition of the Marine Licence that any debris (or waste) arising during the course of the Project are  removed  from  the  site of  the works  if practicably  feasible and safe  to do so,  for disposal at an approved location. 

11.1.2. Should  debris  not  be  able  to  be  removed  immediately  and  it  be  considered  to  be  a  danger  to navigation or risk to any other legitimate user of the sea, notification should be provided to Marine Scotland and a mitigation plan proposed for approval by Marine Scotland. 

11.1.3. The mitigation plan must include consideration of removal or alteration to the debris. 

11.1.4. Separate provisions apply  for  the accidental  loss of pollutants.   These procedures are  set out  in Section 10 of this CEMP.   

Page 65: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 63 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

12. Monitoring and Reporting Plan 

12.1. Introduction 

12.1.1. Monitoring and reporting of activities during the Project  is required  in order to ensure works are carried  out  as  per  legislation,  consent    and  licence  conditions  and  in  line  with  the  Employer requirements.  This section describes the monitoring (including auditing) and reporting activities that will be performed during the execution of the Project.   These requirements are additional to the external communications requirements detailed in Section 3.  

12.2. Monitoring During Works 

VESSEL INSPECTIONS 

12.2.1. All  vessels  utilised  on  the  Project  shall  be  fully  complaint  with  the  ISM  Code  and  flag  state requirements.   Where  ISM Code does not apply to a vessel utilised due to vessel size, the vessel operator shall ensure that the vessel has a suitably integrated Safety Management System in use on board the vessel. 

12.2.2. Table 12.1 outlines a number of environmental documents / certificates the vessels will be expected to provide  in order  to comply with  the environmental aspects of  the  initial vessel audit and / or ongoing audits throughout the Project work.  Documentation will be required to be provided to the Employer  (where  specified) ahead of operations and prior  to HAZID  in order  that any necessary amendments  can  be made  in  advance  of works  commencing.    Pre works  vessel  checks will  be undertaken by the Employer, to ensure all appropriate documentation is on board the vessel. 

Table 12.1 Vessel Audit – Environmental Compliance Checklist 

Aspect  Document  Action  Responsibility for Provision 

Marine  Licence  and related documentation 

Marine Licence  Copy  of  Marine  Licence  to  be  on board vessel throughout works 

Vessel 

EPS Licence  Copy of EPS  Licence  to be on board vessel throughout works 

Vessel 

CEMP  (incorporating  the MMPP) 

Copy of CEMP to be on board vessel throughout works 

Vessel 

FLMAP  Copy of FLMAP to be on board vessel throughout works 

Vessel 

MMO Records  Evidence required at vessel audit  Vessel 

Water Protection  Shipboard  Marine  Pollution Emergency Plan (SOPEP) 

Plan  to  be  presented  prior  to  the HAZID,  and  on  board  vessel throughout works 

Vessel 

Ensure  that  materials  are secured on deck 

Evidence required at vessel audit  Vessel 

Wastes  are  required  to  be contained  on  board  vessels 

Evidence required at vessel audit  Vessel 

Page 66: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 64 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

Aspect  Document  Action  Responsibility for Provision 

for  appropriate  disposal  on return to port 

Oily Discharges  Oil  Pollution  Prevention Certificate 

Certificate  to  be  presented  prior  to the  HAZID,  and  on  board  vessel throughout works 

Vessel 

Oil Record Book  Record  book  to  be  on  board  vessel throughout works 

Vessel 

Ballast  Water Management  (if applicable) 

International  Ballast  Water Management Certificate 

Certificate  to  be  presented  prior  to the  HAZID,  and  on  board  vessel throughout works 

Vessel 

Ballast  Water  Management Plan 

Plan  to  be  presented  prior  to  the HAZID,  and  on  board  vessel throughout works 

Vessel 

Ballast Water Record Book  Record  book  to  be  on  board  vessel throughout works 

Vessel 

Biofouling Management 

International  Anti‐Fouling System Certificate 

Certificate  to  be  presented  prior  to the  HAZID,  and  on  board  vessel throughout works 

Vessel 

Biofouling Management Plan  Plan  to  be  presented  prior  to  the HAZID,  and  on  board  vessel throughout works 

Vessel 

Biofouling Record Book  Record  book  to  be  on  board  vessel throughout works 

Vessel 

Waste Management  Waste Management Plan  Plan  to  be  presented  prior  to  the HAZID,  and  on  board  vessel throughout works 

Vessel 

Garbage Record Book  Record  book  to  be  on  board  vessel throughout works 

Vessel 

Controlled  Waste  Transfer Note  /  Special  Waste Consignment Note 

Notes to be on board vessel at vessel audit and throughout works 

Vessel 

MONITORING OF DAILY WORK 

12.2.3. Daily checks will be carried out by the Employer Supervisor for Offshore Works.  Any actions resulting from these inspections will be reported at team meetings. 

AUDITS 

12.2.4. The Employer Project Manager will arrange a schedule of audits for both the vessel and work sites as appropriate during the delivery of the Project.  The audits will include evaluation of compliance with environmental legislation, good practice and with any Project and the Employer requirements. 

12.2.5. Following completion of each audit, a report will be prepared, and distributed to the Project Team and the Employer personnel as appropriate.  This will identify any corrective measures that need to be undertaken, which will be entered into the Audit Close Out Schedule.  This will contain details on who is responsible for implementing each action and the associated timescales. 

Page 67: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 65 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

CORRECTIVE AND PREVENTIVE ACTIONS 

12.2.6. All  corrective  actions  identified  as  a  result  of  any  audit  or  inspection  generated  either  by  the Contractor or by the Employer will be entered into the Corrective Actions Tracker.  This will detail: 

The date of the audit; 

The origin of the audit finding (e.g. weekly inspection); 

The audit finding; 

The corrective action required; 

Responsibility for the corrective action; and 

Date of close‐out of the corrective action. 

12.3. Reporting During / After Works 

DAILY REPORTING 

12.3.1. In addition to  incident reporting, environmental related matters will be reported to the Employer Supervisor for Offshore Works in the Daily Project Report (DPR) prepared by the Contractor. 

END OF INSTALLTION REPORTING 

12.3.2. The Contractor will be responsible for the preparation of all reports required at the end of the works, including, but not necessarily limited to the following: 

As laid report; 

Charting; 

RPL report;  

Lessons learned report; and 

MMO report. 

12.3.3. The above will be used to compile the end of works report required by Marine Scotland. 

12.4. Incident Response and Reporting 

12.4.1. All incident reporting and investigation will be undertaken in line with the Employer requirements as detailed in MS‐SHE‐010 Incident Reporting Management and Investigation Standard and REF‐PS‐SHE‐COM‐015 Reporting of SHE  Incidents.   The requirements are detailed  in Figure 12.1 and this should be the first reference in the event of an incident or near miss. 

 

Refer to Figure 12.1 for response requirements  

Reporting required within 30 minutes 0800 107 3207 

Page 68: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 66 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

12.4.2. Incident response will be based on the Stop, Control, and Notify principle.  Works will be stopped and where possible the source of any pollution will be addressed.   Appropriate measures will be taken to contain the pollutant.  

12.4.3. After an  incident any  lessons  learnt  from the  incident will be communicated to all of the Project Team  and  appropriate  action will  be  taken  elsewhere  on  the  Project  if  necessary.   All  relevant method statements, sections of the CEMP, toolbox talks etc. will be updated and all Project Team members informed of the changes.  

12.4.4. Audits  will  be  conducted  at  regular  intervals  with  corrective  and  preventative  actions  being monitored in an Audit Close‐out Schedule.   

12.4.5. The Project Team will be briefed on the system for reporting incidents and near misses as a part of their Site Induction. 

12.4.6. Any  complaints  received  from  the  public  or  regulatory  authorities will  also be  recorded on  the environmental incidents and near misses register. 

12.4.7. In general, all significant environmental or pollution incidents will be initially managed according to the Employer process outlined above, but also according  to  the Contractor emergency  response procedures, including the Shipboard Marine Pollution Emergency Plan (SOPEP).   

Page 69: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 67 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

Figure 12.1 Reporting of SHE Incidents  

 

Page 70: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 68 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

 

 

Page 71: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 69 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

13. References 

13.1.1. Aires, C., Gonz lez‐Irusta, J.M., Watret, R.  (2014).  Scottish Marine and Freshwater Science Report, Vol  5  No  10,  Updating  Fisheries  Sensitivity  Maps  in  British  Waters'  found  at: http://www.scotland.gov.uk/Publications/2014/12/3334  with  further  details  at http://www.scotland.gov.uk/Topics/marine/science/MSInteractive/Themes/fish‐fisheries/fsm. 

13.1.2. ESG  (2015).   SSE  Cable  Burial  Assessment  Surveys.   Hydrographic,  Geophysical  and  Intrusive Surveys.  Report No. L5248‐15.  

13.1.3. ERM  (2018a).  Scottish  Island Cables, Shore Ends.  Environmental Appraisal Report.  Yell  ‐ Unst 1, Shetland. Final version.  April 2018. 

13.1.4. ERM  (2018b).  Scottish  Island Cables, Shore Ends.  Environmental Appraisal Report.  Yell  ‐ Unst 2, Shetland.  Final version.  April 2018. 

13.1.5. Guerin,  A.J.,  Jackson,  A.C.,  Bowyer,  P.A.  and  Youngson,  A.F.    (2014).   Hydrodynamic models  to understand salmon migration in Scotland.  The Crown Estate, 116 pages. ISBN: 978‐1‐906410‐52‐0.  

13.1.6. Godfrey, J. D., Stewart, D. C., Middlemas, S. J., & Armstrong, J. D.  (2014).  Depth use and migratory behaviour of homing Atlantic salmon (Salmo salar) in Scottish coastal waters. ICES Journal of Marine Science, 72(2), 568‐575. 

13.1.7. IMO.  (2011).  2011 Guidelines for the Control and Management of Ships' Biofouling to Minimise the Transfer of Invasive Aquatic Species. 

13.1.8. JNCC.  (2017).  JNCC guidelines for minimising the risk of injury to marine mammals from geophysical surveys. Published, April 2017.  

13.1.9. NBN  Atlas  (2018).    National  Biodiversity  Network.    Available  at https://records.nbnatlas.org/explore/your‐area [Accessed 16/03/2018]. 

13.1.10. NAFC Marine Centre (2015).  The Shetland  Islands' Marine Spatial Plan.  Fourth Edition.  Strategic Environmental  Assessment.   Environmental  Report.   Available  at: http://www.nafc.uhi.ac.uk/research/marine‐spatial‐planning/shetland‐islands‐marine‐spatial‐plan‐simsp/ [Accessed 3/04/2018]. 

13.1.11. NMPI  (2018).   The  Scottish  Government  National  Marine  Plan  Interactive  available  at http://www.gov.scot/Topics/marine/seamanagement/nmpihome [Accessed 02/04/2018]. 

13.1.12. Malcolm, I. A., Godfrey, J., & Youngson, A. F. (2010). Review of migratory routes and behaviour of Atlantic salmon, sea trout and European eel in Scotland’s coastal environment: implications for the development of marine renewables. Scottish Marine and Freshwater Science, 1(14), 1‐72. 

13.1.13. OSPAR (2008). Case Reports for the OSPAR List of threatened and/or declining species and habitats. OSPAR  Commission.  Available  online  at http://qsr2010.ospar.org/media/assessments/p00358_case_reports_species_and_habitats_2008.pdf [Accessed on 14/12/2017]. 

13.1.14. Payne,  R.D.,  Cook,  E.J.  and Macleod,  A.    (2014).   Marine  Biosecurity  Planning  –  Guidance  for producing  site and operation‐based plans  for preventing  the  introduction of non‐native  species. Report by SRSL Ltd. in conjunction with Robin Payne to the Firth of Clyde Forum and Scottish Natural Heritage 39 pp.  

Page 72: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 70 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

13.1.15. Scottish  Government  (2010).    Scottish  Government’s  Zero  Waste  Plan.    Available  at: http://www.gov.scot/Publications/2010/06/08092645/0 [Accessed 14/12/2017]. 

13.1.16. Scottish Government.    (2012).   The Duty of Care: A Code of Practice.   Published by  the Scottish Government, October 2012.  ISBN: 978‐1‐78256‐138‐5 (web only). 

13.1.17. SNH (Scottish Natural Heritage) (2014).  Recommended list of Priority Marine Features in Scotland’s seas.    Available  at:  http://www.snh.gov.uk/protecting‐scotlands‐nature/safeguarding‐biodiversity/priority‐marine‐features/priority‐marine‐features/  [Accessed 10/10/2017]. 

13.1.18. UKBAP  (2011).    UK  Biodiversity  Action  Plan.    Available  at:  http://jncc.defra.gov.uk/page‐5155 [Accessed 11/10/2017]. 

13.1.19. Wessex  Archaeology  (2014).    Protocols  for  Archaeological  Discoveries.    Available  at: http://www.wessexarch.co.uk/protocols‐archaeological‐discoveries‐pad [Accessed 14/12/2017]. 

 

   

Page 73: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 71 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

Relevant Marine Policies and Plans 

A.1. Scottish National Marine Plan 

The  Scottish Government  adopted  the National Marine Plan  (NMP)  in early 2015  to provide an overarching  framework  for marine activity  in Scottish waters, with an aim  to enable  sustainable development  and  the  use  of  the marine  area  in  a way  that  protects  and  enhances  the marine environment whilst promoting both existing and emerging industries.  This is underpinned by a core set of general policies which apply across existing and future development and use of the marine environment.  The general planning policies of particular relevance to the works include: 

General planning ‐ There is a presumption in favour of sustainable development and use of the marine environment when consistent with the policies and objectives of the Plan; 

Economic benefit  ‐ Sustainable development and use which provides economic benefit  to Scottish communities is encouraged when consistent with the objectives and policies of this Plan; 

Co‐existence  ‐  Proposals which  enable  coexistence with  other  development  sectors  and activities within the Scottish marine area are encouraged  in planning and decision making processes, when consistent with policies and objectives of this Plan; 

Climate change ‐ Marine planners and decision makers must act in the way best calculated to mitigate, and adapt to, climate change;  

Natural heritage ‐ Development and use of the marine environment must: 

o Comply with legal requirements for protected areas and protected species; 

o Not result in significant impact on the national status of PMF; and 

o Protect and, where appropriate, enhance the health of the marine area. 

Noise: Development and use  in  the marine environment  should avoid  significant adverse effects of manmade noise and vibration, especially on species sensitive to such effects; 

Engagement: Early and effective engagement should be undertaken with the general public and interested stakeholders to facilitate planning and consenting processes; and 

Cumulative  impacts: Cumulative  impacts affecting  the ecosystem of  the Marine Plan area should be addressed in decision‐making and Plan implementation. 

The Employer has taken all the above policies into consideration when developing the cable route and assessing the potential environmental and socio‐economic  impacts. Sectoral policies are also outlined  in the Plan where a particular  industry brings with  it  issues beyond those set out  in the general  policies.    For  the  Project,  the  policies  covering  fisheries  and  submarine  cables  are  of particular  relevance;  these are detailed below, along with comment on  the degree  to which  the Project is aligned with such objectives and policies. 

   

Page 74: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 72 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

FISHERIES POLICIES  

Taking  account  of  the  EU’s  Common  Fisheries  Policy, Habitats  and  Birds Directives  and Marine Strategy  Framework  Directive,  the  works  have  been  planned  to  ensure  that  existing  fishing opportunities  and  activities  are  safeguarded  wherever  possible  and  that  the  proposed  cable installation activities protect local fish stocks and sustain healthy fisheries. This has been achieved by the Employer engaging early with the fishing community to discuss the proposals, minimising the duration of cable installation and by minimising conflicts with the fisheries sector and the impact on fish stocks through a thorough assessment of the potential impacts. 

Scottish National Marine Plan – Sea Fisheries Marine Planning Policies 

Marine planning policies

FISHERIES 1: Taking account of the EU's Common Fisheries Policy, Habitats Directive, Birds Directive and Marine Strategy Framework Directive, marine planners and decision makers should aim to ensure:

Existing fishing opportunities and activities are safeguarded wherever possible.

An ecosystem-based approach to the management of fishing which ensures sustainable and resilient fish stocks and avoids damage to fragile habitats.

Protection for vulnerable stocks (in particular for juvenile and spawning stocks through continuation of sea area closures where appropriate).

Improved protection of the seabed and historical and archaeological remains requiring protection through effective identification of high-risk areas and management measures to mitigate the impacts of fishing, where appropriate.

That other sectors take into account the need to protect fish stocks and sustain healthy fisheries for both economic and conservation reasons.

Delivery of Scotland's international commitments in fisheries, including the ban on discards.

Mechanisms for managing conflicts between fishermen and/or between the fishing sector and other users of the marine environment.

FISHERIES 2: The following key factors should be taken into account when deciding on uses of the marine environment and the potential impact on fishing:

The cultural and economic importance of fishing, in particular to vulnerable coastal communities.

The potential impact (positive and negative) of marine developments on the sustainability of fish and shellfish stocks and resultant fishing opportunities in any given area.

The environmental impact on fishing grounds (such as nursery, spawning areas), commercially fished species, habitats and species more generally.

The potential effect of displacement on: fish stocks; the wider environment; use of fuel; socio-economic costs to fishers and their communities and other marine users.

FISHERIES 3: Where existing fishing opportunities or activity cannot be safeguarded, a Fisheries Management and Mitigation Strategy should be prepared by the proposer of development or use, involving full engagement with local fishing interests (and other interests as appropriate) in the development of the

Page 75: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 73 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

Strategy. All efforts should be made to agree the Strategy with those interests. Those interests should also undertake to engage with the proposer and provide transparent and accurate information and data to help complete the Strategy. The Strategy should be drawn up as part of the discharge of conditions of permissions granted.

The content of the Strategy should be relevant to the particular circumstances and could include:

An assessment of the potential impact of the development or use on the affected fishery or fisheries, both in socio-economic terms and in terms of environmental sustainability.

A recognition that the disruption to existing fishing opportunities/activity should be minimised as far as possible.

Reasonable measures to mitigate any constraints which the proposed development or use may place on existing or proposed fishing activity.

Reasonable measures to mitigate any potential impacts on sustainability of fish stocks (e.g. impacts on spawning grounds or areas of fish or shellfish abundance) and any socio-economic impacts.

Where it does not prove possible to agree the Strategy with all interests, the reasons for any divergence of views between the parties should be fully explained in the Strategy and dissenting views should be given a platform within the Strategy to make their case.

FISHERIES 4: Ports and harbours should seek to engage with fishing and other relevant stakeholders at an early stage to discuss any changes in infrastructure that may affect them. Any port or harbour developments should take account of the needs of the dependent fishing fleets with a view to avoiding commercial harm where possible. Where a port or harbour has reached a minimum level of infrastructure required to support a viable fishing fleet, there should be a presumption in favour of maintaining this infrastructure, provided there is an ongoing requirement for it to remain in place and that it continues to be fit for purpose.

FISHERIES 5: Inshore Fisheries Groups (IFGs) should work with all local stakeholders with an interest to agree joint fisheries management measures. These measures should inform and reflect the objectives of regional marine plans. <applies to inshore waters>

Regional Policy: Regional marine plans should consider:

Whether they require to undertake further work on any data gaps in relation to fishing activity within their region.

The potential socio-economic impacts for the local fishing industry (and parts of the industry using their area) of any proposed activity or conservation measure.

How to include local Inshore Fisheries Groups as a key part of their planning process.

The potential consequences and impacts for other marine regions; and for offshore regions of their approach to planning for fisheries.

Taking account of ongoing local initiatives, such as Clyde 2020, which may be relevant to their work. <applies to inshore waters>

SUBMARINE CABLES POLICIES  

With  respect  to submarine cables,  the NMP sets out a number of key objectives. Those  that are relevant to the works include:  

Page 76: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 74 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

Protect submarine cables whilst achieving successful seabed user co‐existence;  

Achieve the highest possible quality and safety standards and reduce risks to all seabed users and the marine environment; and 

Support  the  generation,  distribution  and  optimisation  of  electricity  from  traditional  and renewable sources to Scotland, UK and beyond.  

Key marine policies underpinning work carried out as part of this Project include:  

Stakeholder engagement – this should be undertaken before routes are selected and agreed;  

Cable developers are required to provide evidence that they have taken a joined‐up approach to development and activity to minimise impacts on the environment and other sea users;  

Cables  should be  suitability  routed  to provide  sufficient  requirement  for  installation  and protection;  

Cables should be buried to maximise protection where there are safety or seabed stability risks  and  to  reduce  conflict  with  other  marine  users  and  to  protect  the  assets  and infrastructure;  

Where burial is demonstrated to be not feasible, cables may be suitability protected through recognised and approved measures (such as rock placement, concrete mattresses or cable armouring) where practicable and cost‐effective and as risk assessments direct; and  

When selecting  locations  for cable  landfalls consideration should be given to flooding and coastal protection and align with policies in Scottish Planning Policy and Local Development Plans.  

Scottish National Marine Plan – Submarine Cables Marine Planning Policies 

Marine planning policies

CABLES 1: Cable and network owners should engage with decision makers at the early planning stage to notify of any intention to lay, repair or replace cables before routes are selected and agreed. When making proposals, cable and network owners and marine users should evidence that they have taken a joined-up approach to development and activity to minimise impacts, where possible, on the marine historic and natural environment, the assets, infrastructures and other users. Appropriate and proportionate environmental consideration and risk assessments should be provided which may include cable protection measures and mitigation plans.

Any deposit, removal or dredging carried out for the purpose of executing emergency inspection or repair works to any cable is exempt[151] from the marine licensing regime with approval by Scottish Ministers. However, cable replacement requires a marine licence. Marine Licensing Guidance should be followed when considering any cable development and activity.

CABLES 2: The following factors will be taken into account on a case by case basis when reaching decisions regarding submarine cable development and activities:

Cables should be suitably routed to provide sufficient requirements for installation and cable protection.

New cables should implement methods to minimise impacts on the environment, seabed and other users, where operationally possible and in accordance with relevant industry practice.

Page 77: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 75 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

Cables should be buried to maximise protection where there are safety or seabed stability risks and to reduce conflict with other marine users and to protect the assets and infrastructure.

Where burial is demonstrated not to be feasible, cables may be suitably protected through recognised and approved measures (such as rock or mattress placement or cable armouring) where practicable and cost-effective and as risk assessments direct.

Consideration of the need to reinstate the seabed, undertake post-lay surveys and monitoring and carry out remedial action where required.

CABLES 3: A risk-based approach should be applied by network owners and decision makers to the removal of redundant submarine cables, with consideration given to cables being left in situ where this would minimise impacts on the marine historic and natural environment and other users.

CABLES 4: When selecting locations for land-fall of power and telecommunications equipment and cabling, developers and decision makers should consider the policies pertaining to flooding and coastal protection in Chapter 4, and align with those in Scottish Planning Policy and Local Development Plans.

Regional policy: Regional marine plans should consider identifying suitable areas for land fall of submarine cables and integrate with spatial priorities for submarine cables within Local Development Plans. <applies to inshore waters>

A.2. Shetland Islands Marine Spatial Plan (SIMSP) 

The Shetland  Islands Marine Spatial Plan (SIMSP) provides an overarching policy framework to guide marine development  and  activity.  This  SIMSP  is  based  on  Scottish  Ministers’  commitment  to  making  marine management more efficient, inclusive and accessible. Areas of constraint and/or opportunities for development have been identified in order to reduce potential conflicts between marine activities and encourage co‐existence between multiple  users.  The  SIMSP  aims  at providing  an  approach  to  the management of  the  sea  around Shetland;  facilitating  an  integrated  and  better  informed  decision‐making  process  regarding  the  future distribution  of  activities  and  resources;  and  enabling  the  long‐term  protection  and  use  of  the  marine environment. 

Section 4 of the SIMSP sets out the legislative requirements that need to be considered for any development proposal. This  section covers marine and works  licences, planning permission, controlled activity  regulation (CAR)  authorisation,  seabed  agreement  for  lease,  electricity  regulations,  EIA,  cumulative  impacts  and consultation with stakeholders. 

Section 5 of the SIMSP sets out a number of general policies that ensure that the SIMSP is contributing to the high‐level government targets that are supporting a clean and safe, healthy and diverse, and productive marine environment. Those that are most relevant to this Project include: underwater noise, navigational safety, cables and pipelines, climate change, coastal defence and  flood protection, protected species, nature conservation designations, marine recreation and invasive non‐native species.  

There are a number of sectoral policies which are specifically relevant to particular types of development or activity. Of direct relevance to this Project are Specific policy requirements relevant to the decommissioning of subsea cables. 

SIMSP Chapter 5: Policy framework 

Policy MSP WAT1: Water Ecology 

Page 78: Yell-Unst Construction Environment Management …news.ssen.co.uk › media › 248706 › Part-7-Yell-Unst-CEMP.pdfYell-Unst Construction Environment Management Plan t Management Plan

Construction Environment Management Plan (CEMP) 

Page 76 of 76 

© Scottish and Southern Electricity Networks 

Uncontrolled if Printed 

Development shall not cause any water body to deteriorate the ecological statys nor prevent the achievement of  established  objectives  set  out  in  the  Scotland  River  Basin Management  Plan  and Orkney  and  Shetland Management Plan. 

Development  adjacent  to  a  water  body must  be  accompanied  by  sufficient  information  to  enable  a  full assessment of the likely effects including cumulative effects. 

Policy MSP INNS1: Reducing the Spread of Invasive Non‐Native Species 

Applications for marine‐related developments should demonstrate that the potential risks of spreading INNS have been adequately considered in their proposal, particularly when moving equipment, boats or live stock (e.g.  fish and shellfish)  from one water body to another or  introducing structures suitable  for settlement of INNS. 

Development  proposals  in  ares  where  INNS  are  known  to  exist  must  include  mitigation  measures  or  a contingency plan approved by  the  local authority  that  seeks  to minimise  the  risk of  spreading  the  INNS or identified ways to eradicate the organisms and set up a scheme to prevent reintroduction. 

Policy MSP NOISE 1: Minimising levels of noise including underwater noise 

Applications for marine‐related developments should, where directed by the local authority: a) Submit a noise  impact assessment or supporting  information to described the duration, type and  level of noise expected to be generated at all stages of the development (construction, operation, decommissioning); and b) include mitigation measures to minimise the adverse impacts associated with the duration and level of noise activity. Development must also  take  into consideration  the potential cumulative effects of noise within  the marine area. Developers  should consider whether  the  level of  surface or underwater noise has  the potential  to affect a marine  species where  this  includes  a  European  Protected  Species  (EPS)  note  that  an  EPS  licence may  be required.  Policy MSP LITT1: Waste Minimisation 

All  applications  for marine‐related  developments  should, where  directed  by  the  local  authority,  submit  a waste/litter minimisation  and management  plan  to  ensure  the  safe  disposal  of waste material  and  debris associated with the construction, operation and decommissioning stages of the development in a format to the satisfaction of the consenting authority or regulator. Disposal of marine waste/litter at sea is prohibited. 

Policy MSP SHIP1: Safeguarding Navigation Channels and Port Areas 

Development proposals that would have an adverse impact on the efficient and safe movement or navigation of shipping to and from ports, harbours, marinas and anchorages or the long‐term operational capacity  of a ferry operation will be refused.  

Policy MSP SHIP2: Marine Environmental High Risk Areas (MEHRAs) Developments should consider the presence and status of Marine Environmental High Risk Areas (MEHRAs).