XYZ Training Center: Conversion of an Excel System Database to Internet Based Database SCRUM - AGILE METHODOLOGY JANUARY 2011 Rickie Brannon, Robbie Brown, James "Jim" Douglass, Deborah Obasogie, Elizabeth Tunsrtall

XYZ Training Center - SCRUM - Agile

Embed Size (px)

Citation preview

Page 1: XYZ Training Center - SCRUM - Agile

XYZ Training Center: Conversion of an Excel System Database

to Internet Based Database

SCRUM - AGILE METHODOLOGY

JANUARY 2011

Rickie Brannon, Robbie Brown, James "Jim" Douglass,

Deborah Obasogie, Elizabeth Tunsrtall

Page 2: XYZ Training Center - SCRUM - Agile

Table of Contents

Executive Summary ...................................................................................................................................... 1 Performance Issues .................................................................................................................................. 3 Management and Technical Constraints ................................................................................................. 4

Development Process and Methodology (SDPM) ....................................................................................... 5 Overall Approach to Delivering the Product and Reason for Choice ..................................................... 5 Phases of SDPM Process .......................................................................................................................... 6

Scope ..................................................................................................................................................... 6 Plan/Launch .......................................................................................................................................... 6 Monitor, Control, Close ......................................................................................................................... 7

Degree of Stakeholder Involvement in the SDPM Process ..................................................................... 7 Project Estimates .......................................................................................................................................... 8

Sources of Historical Techniques ............................................................................................................. 8 Estimation Techniques ............................................................................................................................. 9 Estimates of Effort, Cost, Duration .......................................................................................................... 9

Risk Management Strategy ........................................................................................................................ 10 Risk Table ................................................................................................................................................ 12 Discussion of Risks .................................................................................................................................. 12 Risk Mitigation, Monitoring, and Management Plan ........................................................................... 12

Risk Mitigation .................................................................................................................................... 13 Risk Monitoring ................................................................................................................................... 14 Risk Management (contingency plans) ............................................................................................... 15 Risk Mitigation .................................................................................................................................... 15 Risk Monitoring ................................................................................................................................... 16 Risk Management (contingency plans) ............................................................................................... 17 Risk Mitigation .................................................................................................................................... 17 Risk Monitoring ................................................................................................................................... 18 Risk Management (contingency plans) ............................................................................................... 18 Risk Mitigation .................................................................................................................................... 18 Risk Monitoring ................................................................................................................................... 19 Risk Management (contingency plans) ............................................................................................... 19 Risk Mitigation .................................................................................................................................... 19 Risk Monitoring ................................................................................................................................... 20 Risk Management (contingency plans) ............................................................................................... 20

Schedule ..................................................................................................................................................... 22 Project Work Breakdown Structure....................................................................................................... 22 Task Network .......................................................................................................................................... 22 Resource Table ....................................................................................................................................... 23 Responsibility Matrix ............................................................................................................................. 24 Major Milestones and Target Dates ...................................................................................................... 24

Project Resources ....................................................................................................................................... 24 People ..................................................................................................................................................... 24 Hardware and Software Required ......................................................................................................... 25 Special Resources and Tools .................................................................................................................. 25

Page 3: XYZ Training Center - SCRUM - Agile

Project Organization .................................................................................................................................. 25

Team Structure ....................................................................................................................................... 25 Project Organization Type and Reason for Choice ................................................................................ 26 Project Stakeholders .............................................................................................................................. 27

Tracking and Control Mechanisms ............................................................................................................ 28 Quality Assurance and Control .............................................................................................................. 28 Change Management and Control ......................................................................................................... 28

Project Communications ............................................................................................................................ 29 Internal to the Project ............................................................................................................................ 29 External to the Project ........................................................................................................................... 29

Facilities Plan .............................................................................................................................................. 29 Documentation Plan .................................................................................................................................. 30 Test Plan ..................................................................................................................................................... 32 Trial Plans ................................................................................................................................................... 34 Deployment Plans ...................................................................................................................................... 35 Maintenance and Disaster Recovery ......................................................................................................... 37 Open Issues and Pending Decisions ........................................................................................................... 38 Appendix A ................................................................................................................................................. 39 Appendix B.................................................................................................................................................. 40 Appendix C .................................................................................................................................................. 41 Appendix D ................................................................................................................................................. 42 Appendix E .................................................................................................................................................. 43 Appendix F .................................................................................................................................................. 44 Table 1 ........................................................................................................................................................ 45

Page 4: XYZ Training Center - SCRUM - Agile

1

XYZ Training Center: Conversion of an Excel System Database to Internet Based

Database

Executive Summary

What our team has decided to do for XYZ Training Center is to convert their existing

software database (MS Excel) into an automated, sleeker model using new technology. XYZ

needs a system that will allow them to enroll students, yet provide them capabilities to record

and archive the data automatically. XYZ’s requirements are simple, yet straightforward; they are

looking for a system that facilitates them with their entire enrollment process. Such that

information can be provided to potential students, students can be enrolled, generate reports in

the future to understand what type of class students take and how to access future markets.

1

1

Page 5: XYZ Training Center - SCRUM - Agile

2

Project Scope and Objective

Statement of Scope

Although XYZ found substantial costs reduction by adopting open source, risk includes

the absence of a formal open source policy in place and additional costs in man hours to support

system. To address this, open source should be as easy to discover, evaluate, deploy, and support

as the proprietary, licensed alternatives.

In Scope

Tracking, historic information and analysis of student data:

a. System should enroll students and track student enrollments.

b. System should keep and access last two years and going forward history. History

information consists of the student, enrollment and course information listed above.

c. System should supply Marketing with the student information for their purposes.

System should provide the following formatted reports:

a. Course offerings (Course Offerings Report).

b. List of students for each class (Enrollment Report).

c. List of all the classes that a student has taken and is registered currently (Grades and

Student History Reports).

Out of Scope

Student payments, financial/accounting, marketing systems.

Company’s vendors.

3 other student performance reports (to be completed in a separate project).

2

Page 6: XYZ Training Center - SCRUM - Agile

3

Major Functions

XYZ is looking to increase the efficiency and effectiveness of student data by 80% within

one year and to expand customer base by 60% by year end. XYZ wishes to improve the current

method of student data traceability and reduce system redundancy; the newly developed software

will update and retrieve student data from a centralized location. Maintaining a centralized

location will increase data efficiency and effectiveness of the data.

As with any business plan/project, risk and or obstacles are unforeseen and can be

difficult to plan for until they actually occur. When transitioning from different model/versions

of software, be aware that training may be essential. You have to ensure that the data will be

compatible and during the transitioning phase, employees are still able to be productive and

operate the system with minor supervision. Training is critical and should be taught hands on

even if the customer feels confident in the software. It’s a simple precautionary method to avoid

loss of business. Considering the competition is another thought to consider when evolving into a

more competitive market/industry sector. XYZ will experience larger than normal volumes of

student data, as this new software will allow for wider markets which addresses student needs

and profiles.

Performance Issues

There is a business need to develop an automated student management system for the

following reasons: solutions will meet cost estimates and schedule constraints, the solution will

meet a specified quality benchmark requirement, and to avoid loss or negative effect on

operations as a result of business interruption, unavailable systems. The timeframe for the

schedule is a major obstacle as solutions will have to integrate within the school’s academic year,

3

Page 7: XYZ Training Center - SCRUM - Agile

4

migration of existing data to database and going live from test environment. Current software

expertise of existing staff and migration of skill sets to new environment requires excellent front

– end analysis of knowledge groups to create criterion referenced training modules. Current

business process (legacy process) to lean automated process creates change process which affects

business and organizational environments. School infrastructure will have to be updated to

support software requirements; easing of the enrollment process for students. Students should be

given “suggested courses” during the registration process based on existing profiles and degree

roadmaps improving student’s effectiveness in managing their education; easing of the recruiting

process for advisors when courting new students. Advisors should easily be able to determine

degree roadmaps and provide accurate timely information to prospects.

Management and Technical Constraints

The risk categories that have been identified for this effort include quality, cost,

competitive and operational, scope and environmental. Anything that can negatively affect the

overall completion of the project outside of our means of time and cost is considered a risk (i.e.

running over/under budget, changing the scope mid-project, not having the appropriate man

power, or once the software is developed, the user not being able to effectively execute the

system in order to continue the flow of business). Loss or negative effect on operations as a

result of business interruption, unavailable systems can affect XYZ’s competitive edge. Training

may need to be rolled out to all potential after the initial testing/deployment phase. This can also

help the developers/programmers catch any glitches prior to final run through. If XYZ doesn’t

employee an IT team to keep the organization current with software updates, avoid database

4

Page 8: XYZ Training Center - SCRUM - Agile

5

corruption, or inaccurate data being transmitted between old and new existing systems as well as

a periodic hardware evaluation, it can have a long term effect on XYZ performance. Refer to

Appendix A for more information.

40-50% of high priority features must be included in release 1.0, 70-90% in release 1.1,

95-100% in release 1.3. 90-93% of user acceptance tests must pass for release 1.0, 94-97% for

release 1.1, 98-100% for release 1.3. Budget overrun is up to 10% acceptable with approval by

Customer and Project Sponsor. Release 1.0 is to be available by 5/6, release 1.1 by 6/13, release

1.3 by 6/17. Maximum team size is 4 developers + 2 testers + specific customer resources.

Development Process and Methodology (SDPM)

Overall Approach to Delivering the Product and Reason for Choice

The best method for this type of project would be the SCRUM model (Iterative SDPM).

The goal is known and clear, while the solution is not. There are a number of risks and issues

that could come to the PM when using this methodology, however, solutions can be discovered

as the project progresses. The customer drives deliverables through interaction via project demos

after the completion of each sprint. New features and functions may be identified at that time and

added to the product backlog to be prioritized by the product owner (Effective Software Project

Management, 2010). The customer defines the functions and features that the team prioritizes

into phases and builds a phase at a time. The process allows the customer to change features to

try and solidify solutions throughout various phases. The SCRUM model is best for situations

5

Page 9: XYZ Training Center - SCRUM - Agile

6

where a variety of skills levels are available and everyone is willing and able to share

information and use lessons learned to improve the overall experiences.

Phases of SDPM Process

Scope

An idea is proposed, and then the functionality list is developed and prioritized, sprint

meetings are held regularly, sprints are conducted, then a demo is presented to the customer for

evaluation. The idea portion of the SCRUM model is a description/idea as part of developing the

scope of the project. The functionality list is presented by the product owner which is considered

the product backlog. The sprint meetings are when the team brainstorm for half of the session, to

clear up any questions or concerns anyone may have regarding the backlog. The second half of

the meeting is actually the developing phases. Lastly, after the sprint has been conducted, the

customer updates any changes to functionality that needs to be addressed at the next sprint

session.

Plan/Launch

Because the SCRUM model has been chosen for this project, this allows the team to be

more flexible and customer oriented. XYZ will meet with the project manager, SME, and the

consultants to provide more details to the scope. These key members will meet to discuss the

necessary project deadline, budget, and necessary hardware and software implementation

process. Also, because this approach allows room for changes, how those changes will be

requested and creating either a scope bank or management reverse. Once all are in agreement,

the project manager will assign the proper resources to the project.

6

Page 10: XYZ Training Center - SCRUM - Agile

7

Monitor, Control, Close

Once the project manager has given the project team the deliverables, implementation of

the project will be completed in accordance to the SCRUM model. The conversion of the

student information will be conducted sections. Once each section is completed, a small demo

will be conducted to ensure that particular section is operating according to XYZ agreed to. As

the project progress, the completed sections will be tested with each other to ensure that once the

conversion is completed finished, the software and hardware will be able to handle the volume of

traffic.

Degree of Stakeholder Involvement in the SDPM Process

The stakeholders for this project include the customer, sponsors, subject matter experts

(SMEs) and developers/programmers, and project manager. Sponsors provide overall direction

on the project. Responsibilities include: approve the project charter and plan; secure Subject

Matter Expert resources for the project; confirm the project’s goals and objectives; keep abreast

of major project activities; make decisions on escalated issues; and assist in the resolution of

roadblocks. Subject Matter Expert provides expertise on a specific subject. Responsibilities

include: maintain up-to-date experience and knowledge on the subject matter; and provide

advice on what is critical to the performance of a project task and what is nice-to-know. Project

Manager leads in the planning and development of the project; manages the project to scope.

Responsibilities include: develop the project plan; identify project deliverables; identify risks and

develop risk management plan; direct the project resources (team members); scope control and

change management; oversee quality assurance of the project management process; maintain all

documentation including the project plan; report and forecast project status; resolve conflicts

7

Page 11: XYZ Training Center - SCRUM - Agile

8

within the project or between cross-functional teams; ensure that the project’s product meets the

store objectives; and communicate project status to stakeholders. Team Member works toward

the deliverables of the project. Responsibilities include: understand the work to be completed;

complete research, data gathering, analysis, and documentation as outlined in the project plan;

inform the project manager of issues, scope changes, and risk and quality concerns; proactively

communicate status; and manage expectations. The customer is the person or department

requesting the project. Responsibilities include: partner with the sponsor or project manager to

create the Project Charter; partner with the project manager to manage the project including the

timeline, work plan, testing, resources, training, and documentation of procedures; work with the

project team to identify the technical approach to be used and the deliverables to be furnished at

the completion of the project; provide a clear definition of the business objective; sign-off on

project deliverables; take ownership of the developed process and software.

Project Estimates

Sources of Historical Techniques

XYZ employees may not be familiar with using Internet based software; however the

many business organizations use Internet based software for their everyday business needs. This

software is very helpful in providing organizations with up dated information. Also, this

software helps eliminate the process of inputting the same information on several different

computers.

8

Page 12: XYZ Training Center - SCRUM - Agile

9

Estimation Techniques

The use of historical data and expert advice is the best approach for this project.

Historical data can be utilize for providing the project team with an updated knowledge of the

prices of parts, services, and the development of the project schedule. Expert advice will be

utilized in conjunction with the development of the project schedule and with informing XYZ

during a scope change requests.

These techniques have been chosen because it allows the project team to remain focus on

the project itself. Also, the experts will serve as an additional support system during any

meetings and throughout the project process.

Estimates of Effort, Cost, Duration

The budget is $750,000 and can be completed anywhere from 18-36 months. The code is

provided by the customer; however, it is a general code which can be provided to several

different vendors at once. A consultant company will help us modify the code to meet XYZ’s

requirements. The cost for consultant fees, software, servers etc are all including in our $750k

budget. The cost for man power, testing, and training is also included in the budget. There will

need to be an excessive amount of hours if the project is split between the 5 team members. The

performance will be done Monday through Friday. Most of the expenses will be the

responsibility of the customer, due to the project being a partial customization/outsourced

initiative. Time, hardware, and cost are variable, as changes is inevitable using a SCRUM model.

There is no prior historical data specific to the exact requirements as been identified with this

effort, however, our PMs are very knowledgeable and experience in software development and

9

Page 13: XYZ Training Center - SCRUM - Agile

10

has generalized costs across the board. Upfront costs (licenses, customization, training, and

implementation) will cost approximately $300,000. The database servers required will cost

approximately $12,000. Microsoft Server 2010 or Linux will cost $7,400. 2 dell web servers

have been priced at $14, 000 (this includes shipment, taxes, and warranty for both servers). The

consultants provided will cost $60,000. The system engineer will cost $50/hour and database

administrator will cost $60/hour, both are variable cost. Also, this project will have a manage

reverse of $100,000.

Risk Management Strategy

XYZ project team identifies risk as the internal and external vulnerabilities associated

with the completion of the scope and deliverables of a project. XYZ seeks to minimize the

impacts of risk through the use of policies, procedures and processes tools which provide the

project team with the guidance to objectively determine risks. The use of tools will guide the

team to analyze, assess and control risks to eliminate, minimize, avoid and or mitigate risks

identified as unacceptable to the successful completion of this project.

The team will populate a preformatted risk register, following ITILv3 practices

(information technology infrastructure library) to provide a comprehensive robust matrix to the

SDPM (software development project management) framework. The matrix will be used as an

on – line dynamic tool which provides a visual and chronological status of all known risks with

read availability to all stakeholders; update responsibility of the aforementioned tool is assigned

to the project manager. The update schedule shall be provided on a weekly basis minimal; unless

10

Page 14: XYZ Training Center - SCRUM - Agile

11

a priority risk is discovered by a stakeholder or project team member whereupon immediate

update is required with data for all known categories of the matrix.

The matrix tool provided below will be the trigger for actions related to the project with

continuous risk management due diligence as the standard.

Risk probability determination is defined through a 100% weighting and scored 1 – 4

with 1 = 0-25% with a dollar impact of $0 - $1600.00, 2 = 26 – 50% with a dollar impact of

$1601 - $400.00, 3 = 51-75% with a dollar impact $4001 - $8000.00 of and 4 = 76 – 100% with

a dollar impact of greater than $8001.00.

The impact values are estimates based on the function of pre response actions and post

response actions.

Proximity denotes the anticipated state the categorized risk event will occur within. The

risk response column falls within two categories threats: avoid, reduce, fallback, transfer, accept

and share and the second category opportunities: enhance, exploit, reject and share. The action

column is functionally aligned with the response column category to state the predetermined

projects teams’ response to mitigate the risk.

The risk Actionee column tracks who has taken on the mitigation task which may be

anyone on the project team and not necessarily the owner of the risk; this is to provide lessons

learned data downstream including providing the project manager with human development

resources data. The final category is the risk status column which provides all stakeholders with

visual information of the state of the risk.

All new risks will be routed to the project manager, with priority level identified in the

routing which will determine the course of action taken by the project manager. A stop light

11

Page 15: XYZ Training Center - SCRUM - Agile

12

priority level system will be used to delineate action levels of consisting of red = immediate,

amber = moderate and green = low to determine impact of the risk on the project. This is a

control measure to ensure concise data is reported to the tool in accordance with the quality

measures agreed upon by the project team. See Appendix A for project’s risk register.

Risk Table

Table 1 lists the indentified risks and their risk level for the project. This information is a

section taken from the project’s risk register in Appendix A.

Discussion of Risks

The five highest priority risks will be the focus risks managed by the project team to

ensure the impact of these selected risks will have a minimum impact upon the outcome of the

project. The risks listed below are the highest priority risks to the project:

1. Selection of ISP provider

2. Current hardware infrastructure for relational database

3. Project timeline

4. Scalability

5. Database corruption

The project team has determined the following strategy will allow XYZ to respond and

anticipate the mandated actionable items required to successfully implement the transference of a

legacy spreadsheet system to an on – line relational database management system.

Risk Mitigation, Monitoring, and Management Plan

1. Selection of an ISP provider

12

Page 16: XYZ Training Center - SCRUM - Agile

13

Risk Mitigation

The SME (subject matter expert) assigned to research IPS providers has finalized the

criteria to determine an ISP provider. The findings have determined a linear selection process

will not obtains the desired results and selection should focus on core system requirements

instead. A determining factor is the overall fit of the vendors’ infrastructure to the firms’

business model and current /future customer requirements for services. The database

management system will require the following infrastructure features to achieve and maintain

operational efficiency to the quality measures set forth by the requirements.

1. Overall strategy of the ISP’s network infrastructure must be owned and maintained by the

provider to reduce the following variables contributing to risks.

a. Reliability

b. Scalability

c. Support

2. Scalability of services

a. Availability of guaranteed bandwidth within geographical domain

b. Hardware/Software to support wireless including VPN

c. Security via hardware/software firewall to external/internal threats

d. Must own network infrastructure within geographical service domain

e. Technical support of IPv4 minimum and upcoming IPv6 address structure

3. Support

a. Datacenter support availability to meet a minimum of FIVE NINES (99.999%)

uptime at site level. Stipulation of less than five minutes of system unavailability

13

Page 17: XYZ Training Center - SCRUM - Agile

14

b. per year. It will be so stipulated the ISP will not be liable for acts of GOD,

however measures will be implemented to minimize impact such as off site data

backup storage.

c. Technical staff supports expertise providing critical services (network

administration, traffic analysis, threat detection at all TCP/IP levels, customer

service, intrusion detection and mitigation processes and so on…)

d. Server consolidation via virtualization to optimize server resources via the VMM

(virtual machine model) to facilitate one server many clients.

Finally the overall business environmental/organizational cultures of the ISP and the firm

will be final selection criteria to ensure a homogeneous atmosphere which mirrors the business

vision and mission of XYZ.

Risk Monitoring

During the final selection process of an ISP the following selected SME personnel from

XYZ will tour the facilities of the finalists; senior technical management, network and database

engineers to provide a first – hand look at the state of the facilities under scrutiny to determine

the ability of the vendor to walk the talk. While on – site the SME team shall address the

criterion the vendors were selected on and not have the visit drive the determining criteria. This

methodology will ensure a parity level from which all vendors have the same onus as per RFP’s

and interaction with the service vendors personnel will provide an indication of working

relationships while viewing how customers are currently served.

14

Page 18: XYZ Training Center - SCRUM - Agile

15

A RFP will be the method to evaluate the perspective bidders with the final determining

document comprised of a RFQ sent to finalists and the aforementioned document along with the

responses to the RFP will define the final criteria for selection.

The RFP shall be written to define the technical and management goals required to

provide services to XYZ with a focus on the business needs including requirements of the

requested service. The RFP/RFQ process define the key business and technical partnership

criteria to support the mission, vision including goals where congruence of the aforementioned

criteria is mission critical for a strong business partnership.

Risk Management (contingency plans)

Selected ISP’s from the initial RFP process will receive a RFQ to provide XYZ

procurement team with the detailed technical and managerial costs associated outlined from the

RFP. A contract will be awarded to the vendors chosen with a secondary vendor selected to

facilitate the schedule, if inadvertent circumstances prevent the primary vendor from an ability to

abide with the agreement. In such case the primary vendor is unable to meet the contractual

agreement and/or services are not being met as expected the customer shall receive an effective

corrective action plan with mutually agreed upon measures.

A non – disclosure agreement shall be provided to all participants of the RFP/RFQ

process to ensure confidentiality and integrity of business processes, practices and procedures.

2. Hardware Requirements

Risk Mitigation

The current hardware present in the system is inadequate to deploy a solution meeting the

output required by the POS for this project of a relational database management system.

Page 19: XYZ Training Center - SCRUM - Agile

16

To provide a scalable hardware package that will meet the current and future needs of

XYZ business vision and mission will require a robust server infrastructure capable of scaling to

meet the business needs. The base system minimal requirements will consist of share hosting

with a web server, mail server, a relational database server, a FTP (file transfer protocol) server

connected to third party data storage and a backup server. The XYZ domain will consist of a

primary DNS (domain name server) with a secondary DNS server and a instead of SMS (systems

management server) handling all asset management issues the migration to the use of System

Center Microsoft ® as the dynamic IT management solution leased from the ISP. With the

exponential rate of technological growth including the issues with maintaining asset efficiency

and security, the leasing of the solution is a value added business decision allowing real – time

mitigation of asset and infrastructure integrity.

Risk Monitoring

Asset monitoring will be handled through the software tools of System Center® from

Microsoft to provide the on – line asset management required to monitor the hardware/software

infrastructure environment to provide robust connectivity.

a. Solutions are fully integrated to provide a consistent and comprehensive management

approach.

b. Cross platform integration and interoperability for cross platform environments such

as any open source products.

c. A single process to manage physical and virtual environments utilizing the same

consoles and tools.

16

Page 20: XYZ Training Center - SCRUM - Agile

17

Risk Management (contingency plans)

Asset management will be provided through the software tools of System Center® from

Microsoft to provide the on – line asset management to provide platform solutions which are

knowledge based, can be implemented quickly and provide rapid deployment.

The management of system integrity is based on industry standards ITIL (information

systems infrastructure library) and MOF 4.0 (Microsoft Operations Framework) to provide

proven solutions.

A real – time monitoring system is essential to system resource health with a minimum

of human resource capital required to maintain throughput and integrity. With a service target of

five nines (99.999%) the tools to provide this level of quality of system availability demands the

project team provides a viable solution with a proven track record to achieve the stated target.

3. Project Timeline

Risk Mitigation

The project timeline poses a strong risk stemming from the need to have a functioning

on – line business processes in place during the non – peak season for students and before the

non – automated process can be retired. To mitigate this risk the project team has chosen an

iterative SDPM strategy to provide visual selection of prototype models depicting a proposed

solution. The SDPM strategy provides for interaction with the customer to select a solution that

provides the client with the best business value. The project team has decided the best strategy

to mitigate the timeline is to closely monitor the schedule for variances and utilize root cause

failure analysis of each variance to apply the specified action required to correct the variance.

17

Page 21: XYZ Training Center - SCRUM - Agile

18

Risk Monitoring

Daily monitoring of the schedule along with the selected SDPM strategy will provide for

proactive monitoring of the timeline which allows the project manager a quantitative measure of

variances. The closely monitored plan allows for proactive actions to affect the schedule as

trends are encountered.

Risk Management (contingency plans)

To ensure proper management of this risk the team will adhere to daily reporting at EOS

(end of shift) to provide updated information to track the schedule as it unfolds. The resulting

schedule will be measured against the forecast to determine variances (if any) to provide the

opportunity to make corrective action to maintain schedule timeline and deliverable milestones.

4. Scalability

Risk Mitigation

Technical performance of the system will have a major impact on the business system.

The system designers must provide the system with platform independence and performance

response time baseline criteria to allow the IT manager to:

Analyze and determine bottlenecks

Compare the impact of changes

Determine optimum time of low activity to perform system maintenance

Provide feedback to users of platform support issues

18

Page 22: XYZ Training Center - SCRUM - Agile

19

Risk Monitoring

Microsoft System Center® tools will provide the IT manager real – time monitoring of

physical and virtual system response to determine the root cause of any bottleneck issues facing

the system. These bottleneck issues are not limited to:

CPU symptoms’

Disk transfer symptoms’

Memory error symptoms’

Risk Management (contingency plans)

To perform risk management the project has finalized on the following tools to load as

part of the suite of solutions in Microsoft System Center®:

DMV’s (dynamic management views)

Task Manager

System Monitor

SQL Profiler

The use of these tools in conjunction with the DBMS (database management system)

tools will provide the system designers and testers with a robust environment to ensure

throughput along with quality requirements are met during development including test/deploy.

5. Database Corruption

Risk Mitigation

The database type selected for this project is a RDBMS (relational database management

system) as opposed to a flat – file database. The selection of a relational database over the flat –

19

Page 23: XYZ Training Center - SCRUM - Agile

20

file database was to provide robust system response and to provide a wide range of system query

capability through the use of entity relational cardinality.

The project team has defined a database standard model outlined in the requirements and

adherence to this standard will minimize configuration errors and standardized testing creation

without impact to the overall project schedule.

To ensure database integrity the project team has selected to run automated system

backups with a predetermined time frame to be finalized by the business system owner. The time

frame is to be based on the amount of manual data input the system owner is willing to live with.

The project team recommendation is to have automated backups performed by the system every

hour with drive replication performed and offloaded to a different geographical location. The

strategy is to be compliant with the implementation of a disaster recovery plan which suits the

business mission and vision for the firm.

Risk Monitoring

To provide concise data entry to the database the project team recommends the IT

program manager creates a T – SQL DDL (data definition language) trigger to track the

developers as changes are made to ensure proper backup and recovery, database standards are

being adhered and the environments of dev, test and production are maintained.

Risk Management (contingency plans)

A common issue in the transference of legacy system flat – files occurs from the initial

formatting of the flat – file. Comma delimited files (txt) files as opposed to tab delimited files

(excel) must first be converted to deposit into SQL tables. The use of SQL tools server data

transformation services (DTS) or SQL server import services (SSIS) are wizard type tools

20

Page 24: XYZ Training Center - SCRUM - Agile

21

provided by the SQL suite to facilitate file transfer. If the customer prefers to maintain the

spreadsheet format then a linked server connection can be set by the IT manager to provide

updates to the relational database dynamically through the use of a user interface web page.

The project team has created a manager responsible for escalation of all issues falling

outside of the agreed parameters and the escalation manager must provide project database risks

to the attention of the project manager in accordance to the stoplight policy denoting level

identification.

21

Page 25: XYZ Training Center - SCRUM - Agile

22

Schedule

Project Work Breakdown Structure

The SDPM strategy chosen for the XYZ project is an iterative software development

process congruent with the quadrant 2 project where the goals are clear however the solution is

not clear at the present start of the project.

The selected SDPM (software development project management) strategy will make use

of agile methodology using SCRUM as the delivery methodology. The traditional role of project

manager will be denoted as the SCRUM master and each SME will fill the role of project

manager for their perspective feature.

As consistent with this project teams’ strategy a tool to manage the project has been

selected by the project team planning committee. The selection is to use the Agile planning tools

available in Microsoft Visual Studio Team System 2010®. The use of a software planning tool

enables the team to present communication in a manner familiar not only to the team but all of

the stakeholders within the project environment. The stakeholders are very familiar with

spreadsheets and VSTS (visual studio team system) software which has a formatted excel

workbook look to the data entry fields and the reporting.

Appendix B depicts the Scrum WBS and all SDPM phases consisting of scope, plan,

launch, monitor & control and deploy (close).

Task Network

Once the WBS is completed a task network can be drawn, with durations and percentage

of completion assigned to all phases of the project. Appendix C depicts the task network for the

project.

22

Page 26: XYZ Training Center - SCRUM - Agile

23

The task network is important because it will help the project manager to work out the

most efficient sequence of events needed to complete the project. This activity network, is a

graphic representation of the task flow for the project and will be used as a mechanism through

which task sequence and dependencies are input to an automated project scheduling tool. The

concurrent nature of software engineering activities leads to a number of important scheduling

requirements. Because parallel tasks occur asynchronously, the planner must determine inter-task

dependencies to ensure continuous progress toward completion. In addition, the project manager

should be aware of those tasks that lie on the critical path.

Timeline Chart (Gantt Chart)

Appendices D, E and F depicts the project plan.

Resource Table

Resource Name Type

SCRUM Master Work

Database Architect Work

IT Manager PM – Test Work

IT Manager PM – Development Work

IT Manager PM – Programming Work

Project Sponsor – Business Analyst Work

Customer 1 – Business Analyst Work

Customer 2 – Business Analyst Work

ISP Provider Work

Web Servers Material

Computers Material

Kuali Software Material

Database Software (PostgreSQL 8.4) Material

Database Server Material

23

Page 27: XYZ Training Center - SCRUM - Agile

24

Responsibility Matrix

Work Resource Responsible

Planning SCRUM Master

Requirements SCRUM Master/IT Project Manager

Analysis IT Project Manager

Development IT PM – DEV /Database Architect

System Design IT PM – DEV/TEST/PROG/Database Architect

System Integration IT PM – TEST/PROG/Database Architect

System Test IT PM – TEST/ Database Architect

System Demonstration SCRUM Master

System Deployment IT PM – DEV/TEST/PROG

Documentation IT PM – DEV/TEST/PROG/Database Architect

Project close and post implementation review SCRUM Master/ IT PM –

DEV/TEST/PROG/Database Architect

Major Milestones and Target Dates

Requirements 02/21/2011

Iteration Backlog 05/16/2011

Product Release Backlog 06/13/2011

Test Functionality 06/15/2011

Demonstrate Functionality 06/17/2011

Project Resources

People

Team Chemistry is the vital ingredient for this project to remain on task, on/under budget,

and completed at the projected deadline. For this to be accomplished, the project team

responsible will have to be highly skilled and technically educated in their respective roles and

responsibilities. Strong leadership is the cement that will ensure this house is built properly. The

project manager chosen will be one that posses highly above average communication skills. This

is important when working with co-workers that are highly skilled. Since experts only listen to

themselves a project consultant will also be hired. To oversee the infrastructure and

implementation of XYZ a database administrator and system engineer will also be hired.

24

Page 28: XYZ Training Center - SCRUM - Agile

25

Hardware and Software Required

Since technology is changing at the blink of an eye, it has been determined that using

open source software is best. This type of software will allow for XYZ to make changes after

the project has been completed. The software will be obtained from Kuali Company. They were

chosen because they have a respectful reputation with several other top colleges and universities.

XYZ will also need to choose an Internet Service Provider. All computers will have to be

updated to have the necessary system requirements for the software. Web servers will utilize as

information backup system to data storage (1 primary and 1 secondary).

Special Resources and Tools

After successful implementation of the data conversion, XYZ will need to train their

employees on how to properly use and manage thru the software system. Also, a written

instructions and/or a web demonstration will have to be provide for current and future students

on how to enroll for classes with the new software.

Project Organization

Team Structure

The project team DNA only focus will be on the completion of upgrading the system for

XYZ. The project team will consist of a project manager, Subject Matter Expert (SME),

consultants, 2 software developers/programmers, 4 testers, 1 system engineer, and 1 database

administrator. The project manager will have complete authority and responsibility for the

successful completion of this project. The software system developers/programmers are

responsible for ensuring proper data migration from excel based system to the preferred internet

based Kuali software. They will also oversee the data migration, they will make sure all

25

Page 29: XYZ Training Center - SCRUM - Agile

26

information is 100% transferred and any new information can be properly entered and saved with

the new software. They will also have to write the source code for the data migration. The SME

will be providing the expert knowledge in software data migration. He/she will oversee that

software information is being converted with the highest level of quality. The testers are the

quality control personnel. After each section of source code is written and implemented, the

testers will conduct real-time testing to determine how the software and hardware handle the

required volume of traffic. Also, they will make sure that each section is having an appropriate

conversation and proper teamwork with all the other sections. The system engineer is

responsible for the hardware and infrastructure of XYZ. Once the ISP has been chosen, the

system engineer will test the wireless connection throughout the building and LAN. The

database administrator will oversee the software developers/programmers. He/she will monitor

their progress to ensure everything is on schedule. The consultants are merely the ghost of the

project. They offer no true responsibilities toward the project only to provide the project

manager will adequate project updates. During meetings with the customer and sponsor, the

consultants will provide as an extra supporting voice for the project manager.

Project Organization Type and Reason for Choice

Due to the constricted time frame of this project, the project team will be project

organizational. The employees selected will be those are highly qualified from within the

organization and will be completely focused on the project. This project type was selected

because it gives the best opportunity for project completion at the requested due date. Also, with

the customer still uncertain on areas of the project, this form puts us in the best position to adapt

to any changes quickly.

26

Page 30: XYZ Training Center - SCRUM - Agile

27

Project Stakeholders

The primary stakeholder is XYZ Training Center; other stakeholders are project manager,

Subject Matter Expert, and the project team as well as Kuali Company. Other stakeholders are

the student’s of XYZ Training Center.

27

Page 31: XYZ Training Center - SCRUM - Agile

28

Tracking and Control Mechanisms

Quality Assurance and Control

No project can be fully completed if the quality is not at the highest level of standards.

As stated earlier, the testers will be responsible maintaining the above average industry standards

of quality. After software phase is completed, quality testing will be conducted before the next

phase starts. A detailed description of all testing procedures can be reviewed in the testing

documentation. Once the completed project is finished, an overall quality testing will be

conducted and a demo will be done for XYZ Training Center. Upon approval from XYZ, one

final quality testing will be done before the official project due date.

Change Management and Control

It is understandable the change is inevitable. Procedures will be implemented for both the

project team and the customer in regards to requesting any changes toward the project (with the

understanding that any changes may/may not affect the overall progress of the project).

Whenever the customer deems the need to change the scope of the project, a formal written

request will be given to the project manager. The project manager will review the request and

analyze the risks that could (this will be discuss with the project team). Once the risks are

determined, the project manager will explain the risk to the customer before asking the customer

to sign off on the requested changes. Whenever the project team notices a change that needs to

be made with the project, he/she is required to provide fully detailed documentation of the

change, how will it benefit the project, and the risks associated with the change. Those changes

will be given to the project manager, who will discuss them with the customer for final approval.

28

Page 32: XYZ Training Center - SCRUM - Agile

29

Once any/all approvals properly documented and signed, the project manager will issue the

copies of the documentation to the customer and upper management for record keeping.

Project Communications

Internal to the Project

Effective and efficient open communication plays a vital role toward the success of this

project. To prevent any unknown variables from putting an unnecessary halt to the progression

of the project, weekly project status meetings will be required. During said meetings, all project

input and area of responsibility on the project. Even though the team members will have weekly

reports, the project manager will be encouraged to periodically monitor the project and make

suggestions whenever needed (without hindering the progress of the project).

External to the Project

The customer’s presence may be requested during the weekly project team meetings. It

will be asked of the customer that during the meetings to only listens to the status that the project

team and address any concerns with the project manager in private. Those concerns will be

handled either with the project manager and those employees overseeing that particular portion

and discussed in the next meeting.

Facilities Plan

The purpose of this section is to provide an overview of both physical and environmental

requirements to house the database servers. The database servers have power requirements

regarding voltage, power redundancy, and surge protection. These requirements are already in

place in the existing data centers to be used in this implementation.

29

Page 33: XYZ Training Center - SCRUM - Agile

30

The servers will be required to have access to the corporate network. This will be

attained by connectivity to core network switches and routing tables on network routers.

There are also additional requirements related to the physical security of the servers.

Like any other information technology piece of equipment, these server are required to be placed

in a secure location only attainable by those individuals requiring access to the actual hardware.

This section does not consider software authentication and security. The existing data centers

meet the physical security requirements in terms of reader access and security cameras.

The final requirement for the facilities plan is related to the environmental requirements

of the database servers. Climate control is already in place in the existing data centers. The

addition of the database servers will not have an impact on the overall climate in the data centers.

The existing AC units and humidity control is sufficient for this deployment.

Documentation Plan

Documentation provides appropriate communication about all system changes. Graphic

User Interface (GUI), infrastructure and technology changes are unavoidable. The

Documentation plan keeps track of these changes and is critical in maintaining the business value

that the system is intended to generate.

Kuali documentation will be revised and supplemented for GIU's implementation to

include customizations for GIU, including changes to accommodate GIU's business practices.

Documentation will be provided for creation, content, network configuration, and hosting

services which provide options for buying dedicated servers, high availability configurations,

extended back-ups of database and files and ability to maintain hot back-ups. However, if

hosting package does not deliver as expected, documentation will be essential when finding a

30

Page 34: XYZ Training Center - SCRUM - Agile

31

better solution to meet our business needs and ensuring that GIU will continue to perform up to

expectations no matter what browser is used. In addition to content management, documentation

of network infrastructure, software, support functions and supplier agreements will be vital if a

new supplier is required.

Functional and technical documentation, downloadable digital user guides will also be

provided by Kuali to assist in utilizing and maintaining system after implementation.

Configuration management documentation is needed to identify the initial base lining of work,

logging and analysis of change requests, change control board procedures, tracking of changes in

progress, and procedures for notifying concerned parties when baselines are established and

changed. A change management documentation process should also be introduced to monitor

changes that will impact project’s schedule, cost, objective, and customer satisfaction.

A process improvement documentation process will be established based on lessons

learned, customer’s satisfaction level and whether the project provided XYZ with the anticipated

benefits. The focus is to learn from the experience in order to improve performance on future

projects. The documenting of budgeted vs. actual in both costs and schedule will also help with

XYZ evaluate these variances.

Missing, shortage of and excessive document jeopardize the project’s success; lengthen

project timeline and results in higher costs. Focus on value added processes such as change and

configuration management, GUI documentation and process improvement to gain the most value

from the document.

31

Page 35: XYZ Training Center - SCRUM - Agile

32

Test Plan

The test plan documents test strategy taken by the project team to ensure that our product

developed is of high quality in relation to what the customer has requested. It defines the scope,

approach to be taken, and the schedule of testing as well as identifies the test items for the entire

testing process and the personnel responsible for the different activities of testing. The tools and

staff that will be performing the testing should also be briefly introduced here.

It is important to complete the plan early in the project and manage it carefully to ensure

on time, within budget project delivery and to communicate test results. To increase its utility in

achieving the goals of the project, the test team will meet once every two weeks to evaluate

progress to date and to identify error trends and problems as early as possible. Measures and

metrics information will be by the test team during all testing phases. This information will be

provided on a biweekly basis to the test manager, project team and sponsor.

The test strategy consists of a series of different tests that will fully exercise the system.

The primary purpose of these tests is to uncover the systems limitations and measure its full

capabilities. The System tests will focus on the behavior of the system. User scenarios will be

executed against the system as well as screen mapping and error message testing. Overall, the

system tests will test the integrated system and verify that it meets the requirements defined in

the requirements document. Performance test will be conducted to ensure that the system’s

response time meet the user expectations and does not exceed the specified performance criteria.

During these tests, response times will be measured under heavy stress and/or volume. Security

tests will determine how secure the system is. The tests will verify that unauthorized user access

to confidential data is prevented. A suite of automated tests will be developed to test the basic

32

Page 36: XYZ Training Center - SCRUM - Agile

33

functionality of the system and perform regression testing on areas of the systems that

previously had critical/major defects. The tool will also assist us by executing user scenarios

thereby emulating several users. We will subject the system to high input conditions and a high

volume of data during the peak times. The system will be stress tested using twice (5000 users)

the number of expected users. Recovery tests will force the system to fail in a various ways and

verify the recovery is properly performed. It is vitally important that all data is recovered after a

system failure and no corruption of the data occurred. Once the system is ready for

implementation, the customer will perform User Acceptance Testing. The purpose of these tests

is to confirm that the system is developed according to the specified user requirements and is

ready for operational use (Software Quality Assurance Tester, n.d.).

Automated testing is an enhancement to manual testing and such tools have difficulty

recognizing some custom controls features within the application. Therefore, it is unreasonable

to expect that 100% of the tests on the project can be automated. Because of this, manual testing

will be performed.

While every attempt is made to focus on testing, realize that testing does not stand alone.

It is intimately dependent on the development activity and therefore draws heavily on the

development practices. An increased portion of the testing will be on the developer, before it

reaches a formal team of testers.

33

Page 37: XYZ Training Center - SCRUM - Agile

34

Trial Plans

The trial plan for this database project is imply to get the users affected by all aspects of

the new design familiar with it and comfortable working with the new platform. In this trial

plan, end users of the database will be required to learn the appropriate tactics for accessing the

data required. This will include teaching where the data is kept, how it is accessed, how it is

updated, and what to do if there are problems.

For this trial plan, each department should designate a user to be the primary point of

contact for that department. These users will learn the basics of the new database system in

terms of what has been mentioned above and in terms of simple queries.

The trail plan should include software users, engineers required to maintain the database

servers, and DB administrators.

34

Page 38: XYZ Training Center - SCRUM - Agile

35

Deployment Plans

The Deployment Plan defines how software will be implemented into a production

environment. It includes the deployment strategy, training requirements and operational

readiness checks followed by the project team. A detailed schedule of events for the installation

is prepared. Responsibility is assigned for each activity. The activities included in this schedule

will be used to refine the project schedule. Tables will be prepared documenting the software

units to be installed, data structure files to be created, start-up files to be installed, user accounts

and security assignments, and configuration file changes to be made on each client and server

node (Toolbox, n.d.). User training is required as part of the deployment and is conducted by

Kuali.

The deployment of the new system is a substantial milestone in the delivery of the

project. Successful deployment is one with minimal disruptions to the production processes. To

increase its utility in achieving this goal of the project, strategy includes both pilot and

production deployments. In addition to helping you to evaluate the compatibility and stability of

new system, the pilot will be used for performance planning and capacity testing, training users

and support staff, testing new security policies and documenting deployment or administration

procedures.

According to TechRepublic (n.d.), the pilot will consist of rolling out the new system to a

select group of users at XYZ. The focus is to have enough users involved to give you an accurate

assessment of how the full deployment will tell when the time comes. Users participating in the

pilot also need to be knowledgeable enough that they can communicate errors or problems to you

in a meaningful way. The next step is to do some training on the new system. Create and

35

Page 39: XYZ Training Center - SCRUM - Agile

36

distribute documentation or a quick reference guide for the users. This documentation will be

designed to walk the users through various procedures. The documentation should be written in

as easy to follow of a manner as possible, and include lots of screenshots. One of the best ways

to reduce the number of "how do I" calls is to provide users with good training and good

documentation.

Provide the users with the name and phone number of a contact person whose job it will

be to dispatch help for issues related to the new system. Since some of the program participants

will invariably call the help desk anyway, it is important to inform the helpdesk staff that calls

related to the new system should be forwarded to the designated point of contact of whom has a

good working knowledge of the system that is being deployed.

The environment will mimic the production environment, network servers, operating

systems on high-end PCs, administrative policies. We will configure the test servers by restoring

backups of the production servers to them. This ensures that the pilot is an exact match of the

production servers. The new system is installed and running correctly.

The next phase will be handled by the application developer and the database

administrator. They need to ensure the web site and the database is fully integrated with the

open source system. All user training should be done, roles understood, outstanding issues

resolved, plan communicated to primary stakeholders and a roll out plan completed, before the

deployment is complete. There will be check points during each phase to ensure the installment

of all components. This should be reflected in a schedule.

The process of the deployment will be exactly like that of the pilot with the exception of

the audience, it opens the all of XYZ and installation will proceed according to the roll out plan.

36

Page 40: XYZ Training Center - SCRUM - Agile

37

The end of deployment marks the beginning of application support which would address the On-

going Support Plan. Application support and application alerting and monitoring procedures in

the vent of application outages will be covered in separate documents.

Because software projects have a tendency to be delivered late and over budget, training

and documentation are skipped. This is a common pitfall during deployment and a risk to the

project. Lack of employee training and poor documentation tracking will result in significantly

higher maintenance and support costs for the system.

Although XYZ found substantial costs reduction by adopting open source, risk includes

the absence of a formal open source policy in place and additional costs in man hours to support

system. To address this, open source should be as easy to discover, evaluate, deploy, and support

as the proprietary, licensed alternatives.

Maintenance and Disaster Recovery

In order to ensure the new database platform is being maintained and is accessible at all

times, this section will address the maintenance plan and disaster recovery tasks associated with

this deployment.

Server maintenance will be completed by the software and hardware engineers

responsible for the database servers. Maintenance will include security patching and OS

patching as required by the manufacturer. Overall the servers should be self-reliant and require

little maintenance. However, issues are bound to arise and the responsible individuals listed

above will be responsible for all software and hardware issues.

The other issue of maintenance is the amount of data on the servers and the amount of

data required to be kept. Each database server will keep data for 14 days. After this threshold is

37

Page 41: XYZ Training Center - SCRUM - Agile

38

reached, any data older than 14 days will be sent to a data warehouse and will no longer be

retrievable on the servers. If end users require data in the data warehouse, the DB administrators

will be required to retrieve this data.

The database servers will house an exorbitant amount of data. If a server goes down or

loses network connectivity, end user will still need to pull expected data. To ensure this

capability, two database servers will be deployed at separate data centers. The servers will run in

an active/active state meaning both servers are capable of executing queries. When data is

updated, the data will be updated on the primary database server and then synched to the

secondary server. This will ensure that if one server or data center is down, accurate data will

still be attainable by end users.

The data on these database servers will also be backed up each day. This will enable data

to be accurate even in the case where either server or both data centers go offline. The backup

file will be accessible on the primary database servers once the servers and/or data centers are

available.

Open Issues and Pending Decisions

To have the technical and administrative staff maintain and support customized modules

may be intensive on-going and long term costs. Watch and monitor costs and schedule carefully.

Move forward with having a formal OSS policy in place.

38

Page 42: XYZ Training Center - SCRUM - Agile

39

Appendix A

Risk Register

39

Page 43: XYZ Training Center - SCRUM - Agile

40

Appendix B

Scrum WBS

40

Page 44: XYZ Training Center - SCRUM - Agile

41

Appendix C

Task Network

41

Page 45: XYZ Training Center - SCRUM - Agile

42

Appendix D

Gantt Chart – Planning, Requirements, Iterations

42

Page 46: XYZ Training Center - SCRUM - Agile

43

Appendix E

Gantt Chart – Product Release Backlog, Test Functionality, Demo Functionality

43

Page 47: XYZ Training Center - SCRUM - Agile

44

Appendix F

Gantt Chart Product Release Backlog, Test Functionality, Demo Functionality continued

44

Page 48: XYZ Training Center - SCRUM - Agile

45

Table 1

Indentified Risks Risk Level

45