12
1 1 XYZ’ Advanced Measurement System Progress Status & Report Professor Paul I. Lin, PE (CA, IN) Dept. of Computer, Electrical, and Information Technology College of Engineering, Technology, and Computer Science Purdue University Fort Wayne Campus Feb. 10, 2017 2 Status of the XYZ AMS Project Tasks completed Task 1. Analyze the XYZ LLC desired Advanced Measurement System (AMS), project hours (20 hr), Jan. 6, 2017 Task 2. Conduct conceptual and preliminary design, project hours (20 hr), Jan. 13, 2017 Tasks in progress Task 3. Conduct detailed AMS system and subsystem design (40 hours) 30% complete

XYZ’ Advanced Measurement System Progress Status & Reportlin/ECET491/SampleProgress... · XYZ’ Advanced Measurement System Progress Status & Report ... Est starting date 12/5/2016,

Embed Size (px)

Citation preview

1

1

XYZ’ Advanced Measurement System

Progress Status & Report

Professor Paul I. Lin, PE (CA, IN)

Dept. of Computer, Electrical, and Information Technology

College of Engineering, Technology, and Computer Science

Purdue University Fort Wayne Campus

Feb. 10, 2017

2

Status of the XYZ AMS Project

Tasks completed• Task 1. Analyze the XYZ LLC desired Advanced

Measurement System (AMS), project hours (20 hr), Jan. 6, 2017

• Task 2. Conduct conceptual and preliminary design, project hours (20 hr), Jan. 13, 2017

Tasks in progress• Task 3. Conduct detailed AMS system and subsystem

design (40 hours)

• 30% complete

2

3

Status of the XYZ AMS Project

Tasks to be started• Task 4: AMS Subsystem Testing and Software

Development, 60 hr; estimate starting date Feb. 12, 2017

• Task 5: AMS System Integration and Testing, 60 hr; estimate starting date March 27, 2017

• Task 6: AMS System Production and Final Testing and Debugging, 20 hr; estimate starting date April 24, 2017

• Task 7: Documentation and Reporting: Final Project Report, 20 hr ; estimate starting date May 18, 2017

4

Status of the XYZ AMS Project (cont.)

Task 1. Analyze the XYZ LLC desired Advanced Measurement System (AMS)

Est starting date 12/5/2016, actual starting date 12/9/2016, completed 1/6/2017, project hours: 20 hours

Deliverables• Analysis Report of Advanced Measurement System,

reviewed and approved, Jan. 6, 2017

• PPT slide and presentation reviewed on Jan. 6, 2017

3

5

Status of the XYZ AMS Project (cont.)

Task 2. Conduct conceptual and preliminary design

a) AMS system architecture design

b) Interface, communication and networking

c) Signal conditioning

d) Data storage and flow

e) Database design

6

Status of the XYZ AMS Project

Task 2. Conduct conceptual and preliminary design (continue..)

Est start date Dec. 14, 2016; actual starting date Jan. 6, 2017; completed date Jan. 13, 2017; total project hours allocated: 20 hours

Deliverables• Conceptual & Preliminary Design Report of Advanced

Measurement System, Jan. 12, 2017

• PPT slide with presentation and review, Jan. 13, 2017

4

7

Status of Tasks

Tasks 3 - Conduct detailed AMS system and subsystem design (40 hours)• In progress, 30% complete

Completed subtasks• NI USB 6501 DIO Device Installation, Testing,

through NI device monitor, Installation and testing report submitted 2017/2/1

• HiPot-to-LabVIEW Interface Circuit using NI USB 6501, interface design and verification report submitted 2017/2/1

8

Task 3 Activity and Accomplishments

NI USB 6501 DIO device, received Jan. 25, 2017

NI USB 6501 Installation, and Testing through NI device monitor

Installation and testing report submitted 2017/2/1

5

9

Task 3 Activity and Accomplishments

HiPot-to-LabVIEW Interface Circuit using NI USB 6501, interface design, simulation and verification report submitted 2017/2/1

An interface circuit for HiPot equipment and NI 6501

R210kΩ

R120kΩ

PLC_VOutput

10V

+5V

2N 2222 or2N 3904

NI 6501 DIO

Pin P0.7Rb 4.7K

Rc 2.2K

Ib

10

Task 3 Activity and Accomplishments

HiPot-to-LabVIEW Interface Circuit using NI USB 6501, interface design, simulation and verification report submitted 2017/2/1

The equivalent circuit for HiPot equipment and NI 6501

Eth=10V*R2/(R1+R2)=3.3V

Rth=R1|| R2=6.7K

Rth=6.7K

Eth3.3V

+5V

2N 2222 or2N 3904

NI 6501 DIO

Pin P0.7Rb 4.7K

Rc 2.2K

Ib

PLC Output EquivalentCircuit

6

11

Task 3 Activity and Accomplishments

HiPot-to-LabVIEW Interface Circuit using NI USB 6501, interface design, simulation and verification report submitted 2017/2/1

Interface simulation and verification

R210kΩ

R120kΩ

PLC_VOutput

10V

+5V

2N 2222 or2N 3904

NI 6501 DIO

Pin P0.7Rb 4.7K

Ib

XMM1Vc5V

XMM2

Vce measurementXMM3

Vin measurement

Ib measurement

Rc 2.2K

12

Task 3 Activity and Accomplishments

HiPot-to-LabVIEW Interface Circuit using NI USB 6501,

NI Muitisim Interface simulation and verification

7

13

Task 3 Activity and Accomplishments

GPIB-USB Adapter Installation and Testing

Expected NI GPIB-USB-HS adapter

Received POLOGIX GPIB-USB adapter (cost consideration), Jan. 25, 2017; interim setup report submitted Feb. 1 2017.

Download and install PROGLOGX GPIB-USB, completed successful

Connect the PROGLOGX to a HP 3478A DMM• Start LabVIEW, then use LabVIEW => Tools => Measurement &

Automation Explorer to view the connection and port info of PROGLOGX GPIB-USB adapter -- successful

But no able to find a tool to program PROGLOGX with proper GPIB address. To be continue!

14

Task 3 Activity and Accomplishments

LabVIEW Application Modules Testing and Design – for RMS, LCM, and MBTS

Compiled LabVIEW functions, Vis for LabVIEW app

Completed basic building blocks for RMS• 1st version front panel & documentation

8

15

Task 3 Activity and Accomplishments

1st version front panel & documentation Part Number

• Combo Box control

Purpose

• Create a list of strings of part number, the user can cycle through, such as a pull-down menu

• Allowing the user to “Selecting and Entering String” at run time

• Event: Value changed

• *Need to add the number of heater elements to be measured

Where to find it in LabVIEW IDE: View => Control Palette: Modern => String & Path => Combo Box

16

Task 3 Activity and Accomplishments

1st version front panel & documentation Part Number

Performed functions

• Read min, nominal, max resistance values, and number of heater elements to be measured from the “Lot Number: Customer Job CVS file” which was converted from Customer Jobs in a Microsoft Excel Spreadsheet file

• Display Min, Nominal, Max values in their specified indicators

• Initialize a Resistance Value Reading array with the order number from customer job sheet

9

17

Task 3 Activity and Accomplishments

LabVIEW Application Modules Testing and Design – for RMS, LCM, and MBTS

Compiled LabVIEW functions, Vis for LabVIEW app

Completed basic building blocks for RMS• 1st version front panel & documentation

• RMS configuration

GPIB address (default 23) for DMM

Configuration file in CVS; read from hard drive

• LabVIEW – data & control structures Local and Global variables, Shared variables

Numeric, String

Array, Matrix & Cluster

While, For, Case, Flat Sequence

18

Task 3 Activity and Accomplishments

Completed basic building blocks for RMS (cont.)

• LabVIEW – File I/O & String Number Conversions Spreadsheet LabVIEW

CSV file LabVIEW

Read/Write Measurement File

File Path

Resistance min, nominal, max value extraction from configuration file

String Numeric Value conversions

While, For, Case, Flat Sequence

10

19

Task 3 Activity and Accomplishments

Completed basic building blocks for RMS (cont.)

• LabVIEW – File I/O & String, testing cases LabVIEW Heater Element File Reading Example:

Path: C:\Lin-IN-MAC\1-16-2017-DetailedAMSDesign-Taks3\LabVIEW-ReadCVS-File

File Name: HeaterRvalueCSVFile-2017-2-8.txt

20

Task 3 Activity and Accomplishments

Completed basic building blocks for RMS (cont.)

• Instrument I/O Vis and Functions GPIB functions

11

21

LabVIEW Development App Subsystem: SPC and HETR Apps

Figure 1. LDAS: major components, communication and networking Interface Adapters

22

Resistance Measurement Subsystem (RMS)

Figure 2. RMS: major components, communication and networking Interface Adapters

12

23

Leakage Current Measurement Subsystem (LCM)

Figure 3. LCM: major components, communication and networking Interface Adapters

24

Mobile Barcode-Based Tracking Subsystem

Figure 4. MBTS: major components, communication and networking Interface Adapters