    Leading SON Solutions

    OSS Based xACP

    3G RF Automatic Optimization: Project Proposal

    Feb 2012

  • 7/29/2019 xACP OSS Based Standard

    2/7

    Optimi Corporation | 2010 | OPTIMI CONFIDENTIAL2

    Scope:Utilization of Optimi OSS Based xACP solution in a city/area of

    CUSTOMER network to demonstrate the performance gains achievable

    using automated cell level RF parameter optimization

    Objectives:

    1. Obtain performance improvement based on agreed objectives

    2. Demonstrate the tool operation

    Phases:

    Verification of tool adapters (configuration and performance

    management data) and output files Automatic RF Optimization (including NL optimization)

    Report generation and trial goal evaluation

    Project Scope

  • 7/29/2019 xACP OSS Based Standard

    3/7

    Optimi Corporation | 2010 | OPTIMI CONFIDENTIAL3

    OSSData

    RF and Network

    Configuration

    (AZ, Tilts..)

    Maps:

    Elevation /

    Clutter

    Antenna

    Patterns

    OSS Based xACP

    NSN 3G

    Huawei 3G

    Ericsson 3G

    Data Requirements:

    o Physical and Network Configuration data

    o Raster Maps (elevation, clutter)

    o Antennas

    o OSS Data

    o xACP fully synchronized with configuration in OSS

    o xACP models calibrated with Performance Counters

    - RF Changes

    - NL Plan- SC Plan

    Optimization Architecture

  • 7/29/2019 xACP OSS Based Standard

    4/7

    Optimi Corporation | 2010 | OPTIMI CONFIDENTIAL4

    Data requirements:

    OSS Based xACP RF physical information

    o Lat/long

    o Cell ID

    o Antenna type

    o Antenna height

    o Antenna azimutho Antenna mechanical tilt

    o Antenna electrical tilt

    Antenna radiation patterns

    Raster mapso Clutter

    o Elevation

    OSS datao Raw configuration (CM) data (in vendor standard format).

    o Raw performance (PM) data (in vendor standard format).

    o Call trace data (Ericsson GPEH/WNCS; Huawei IOS, etc) [Optional]

    Interfaces for OSS data:

    Vendor standard interfaces [Details to be concluded once we know vendor on trial area]

    Data Requirements & Interfaces

  • 7/29/2019 xACP OSS Based Standard

    5/7

    Optimi Corporation | 2010 | OPTIMI CONFIDENTIAL5

    Daily operations/Tasks

    CUSTOMER should provide the required inputs (physical information, rastermaps, OSS data, etc)

    Optimi engineer(s) will be in charge of building the project and running the RF

    optimization

    Optimi will provide the optimized RF optimization settings

    Optimi will provide the optimized NB list optimization list After CUSTOMER engineers review and approval, optimized RF design should be

    loaded into the network

    Deliverables

    RF Optimization

    NL Optimization

    Final Report: Optimi will provide a final report with final project summary and

    results

    Project Tasks & Deliverables

  • 7/29/2019 xACP OSS Based Standard

    6/7

    Optimi Corporation | 2010 | OPTIMI CONFIDENTIAL6

    Based on network OSS KPIs. Possible KPIs (5% improvement)

    Quality

    Improve % DCR due to missing neighbors

    Improve % calls in 3-way or 4-way soft handover

    Capacity

    Reduce Congestion/Blocking

    Reduce iRAT rate (%)

    Procedure (5 working days before the optimization) versus

    (5 working days after the optimization)

    In case of specific events/failures happening in thenetwork during the benchmarking phase: Those

    faulty days/cells will be identified and agreed

    between both parties (maybe agree to exclude them

    from evaluation).

    Success Criteria

  • 7/29/2019 xACP OSS Based Standard

    7/7

    Leading SON Solutions

    www.optimi.com