X and Y Can Do a Piece of Work in 20 Days and 12 Days Respectively

Embed Size (px)

Citation preview

  • 7/28/2019 X and Y Can Do a Piece of Work in 20 Days and 12 Days Respectively

    1/11

    X and Y can do a piece of work in 20 days and 12 days respectively. X started the work aloneand then after 4 days Y joined him till the completion of the work. How long did the work last?

    X Y

    Speed

    Time 20 12

    distance

    LCM (20,12)=60Total distance = 60Update

    X Y

    Speed

    Time 20 12

    distance 60 60

    Apply STD formula in each column and you get speed of X and Y

    X Y

    Speed 3 5

    Time 20 12

    distance 60 60

    Given: X started the work alone and then after 4 days Y joined him till the completion of thework

  • 7/28/2019 X and Y Can Do a Piece of Work in 20 Days and 12 Days Respectively

    2/11

    Means X worked for four days alone.

    X Y X started

    Speed 3 5 3

    Time 20 12 4

    distance 60 60 34=12

    In 4 days, he covered 12 kms.So remaining work = 60 minus 12 =48.Which was completed by X+Y

    X Y X started X+Y

    Speed 3 5 3 3+5=8

    Time 20 12 4 ??

    distance 60 60 34=12 48

    Run std on last column

    Speed x time = dist8 x time = 48Time =48/ 8 =6 daysFinal table looks like this

    X Y X started X+Y finished

    Speed 3 5 3 3+5=8

    Time 20 12 4 6

    distance 60 60 34=12 48

  • 7/28/2019 X and Y Can Do a Piece of Work in 20 Days and 12 Days Respectively

    3/11

    First question

    P & q can do a job in 15 days &10 days respectively . They began the work together but p leavesafter some days and q finishes the remaining job in 5 days. After how many days did p leave?Take LCM of (15, 10)=30 and fill up the table

    P Q P+q work together Only q

    Speed 2 3 3+2=5 3

    xTime 15 10 ?? 5

    Distance 30 ?? 15

    According to last column, q covered 3x 5= 15 kilmeteres out of total 30 km. Hence the remaining 30 minus 15 = 15 kilometers were covered by P+Q together their combined speed is (3+2)= 5.Run the STD formula on (P+Q) column5 x time = 15Time = 15/5=3Means P+Q worked together for 3 days. And then P left.Final answer: P left after 3 days.

    Second Question

    Singh & ravi can do a job alone in 10 days and 12 days respectively. Singh starts the work & after 6 days ravi also joins to finish the work together. For how manydays ravi actually worked on the job ?

    Same procedure, take LCM of (10,12)=60

    After 6 days, Ravi also joins. That means for the first 6 days, Singh worked alone.Fill up the table.

    Singh Ravi Singh starts Singh+Ravi

    Speed 6 5 6 (6+5)=11

  • 7/28/2019 X and Y Can Do a Piece of Work in 20 Days and 12 Days Respectively

    4/11

    Time 10 12 6 days ??

    Distance 60 36 (60-36)=24

    In the first 6 days, Singh finished 36 kilometers. Hence remaining work= 60 minus 36= 24These 24 kilometers were covered by Singh+Ravi together. (last column)Run the STD on last columnSpeed x time = distance11 x Time =24Time =24/11= approx. 2.18Final answer: Ravi worked for 2.18 days.

    1. Case#1 : Time equations: set of two people working 2. Case# 2: Time Ratios are given

    Case#1 : Time equations: set of two people working

    A & B can do a piece of work in 12 days , B and C in 15 , C & A in 20 days. How long wouldeach take separately to do the same work ?

    In the STD table, when people come and go, we can do addition and subtraction in the SPEED boxes only and now in the Time boxes. Now fill up the table.

    A+B B+C C+A

    SPEED

    TIME 12 15 20

    DISTANCE

    TAKE THE LCM (12,15,20) =60. Based on that we can find individual speeds using STDformula.

    http://mrunal.org/2012/04/aptitude-std-table-two-complex-cases-of.html#2http://mrunal.org/2012/04/aptitude-std-table-two-complex-cases-of.html#2http://mrunal.org/2012/04/aptitude-std-table-two-complex-cases-of.html#510http://mrunal.org/2012/04/aptitude-std-table-two-complex-cases-of.html#510http://mrunal.org/2012/04/aptitude-std-table-two-complex-cases-of.htmlhttp://mrunal.org/2012/04/aptitude-std-table-two-complex-cases-of.htmlhttp://mrunal.org/2012/04/aptitude-std-table-two-complex-cases-of.htmlhttp://mrunal.org/2012/04/aptitude-std-table-two-complex-cases-of.html#510http://mrunal.org/2012/04/aptitude-std-table-two-complex-cases-of.html#2
  • 7/28/2019 X and Y Can Do a Piece of Work in 20 Days and 12 Days Respectively

    5/11

    A+B B+C C+A

    SPEED 5 4 3

    TIME 12 15 20

    DISTANCE 60 60 60

    Assume that these three entities work together

    A+B B+C C+A (A+B)+(B+C)+(C+A)

    SPEED 5 4 3 5+4+3=12

    TIME 12 15 20 ??

    DISTANCE 60 60 60 60

    Speed of A+B+C together can be derived using(A+B)+(B+C)+(C+A)

    = 2(A+B+C)=5+4+3=12Hence speed of A+B+C together =12/2=6

    Now STD formulaSpeed x time = distance6 x time = 60Time = 10Meaning if A+B+C work together, they can finish work in 10 days. [although Time of A+B+C,is not asked in the question, but Ive given it only for explanation]

    Now back to the question, weve to f ind individual time. So far our table looks like this-

    A+B B+C C+A A+B+C

    SPEED 5 4 3 6

    TIME 12 15 20 10

  • 7/28/2019 X and Y Can Do a Piece of Work in 20 Days and 12 Days Respectively

    6/11

  • 7/28/2019 X and Y Can Do a Piece of Work in 20 Days and 12 Days Respectively

    7/11

    TIME 12 15 20 10 60 20 30

    DISTANCE 60 60 60 60 60 60 60

    Final answer, time taken by A,B,C if they work individually= 30,20,60

    Run a cross verification to see the answer is correct. Plug the answer values.

    A B C A+B B+C C+A

    Speed 2 3 1 5 4 3

    Time 30 20 60 12 15 20

    Dist 60 60 60 60 60 60

    Yes it satisfies the statements given in the Question.

  • 7/28/2019 X and Y Can Do a Piece of Work in 20 Days and 12 Days Respectively

    8/11

    Case# 2: Time Ratios are given

    http://mrunal.org/2012/04/aptitude-std-table-two-complex-cases-of.htmlhttp://mrunal.org/2012/04/aptitude-std-table-two-complex-cases-of.htmlhttp://www.flipkart.com/search-book?affid=mrunalrugm&wgtid=FK-AF-SB&query=9788183489690http://www.flipkart.com/search-book?affid=mrunalrugm&wgtid=FK-AF-SB&query=9382081029http://www.flipkart.com/search-book?affid=mrunalrugm&wgtid=FK-AF-SB&query=9788183489690http://www.flipkart.com/search-book?affid=mrunalrugm&wgtid=FK-AF-SB&query=9382081029http://mrunal.org/2012/04/aptitude-std-table-two-complex-cases-of.html
  • 7/28/2019 X and Y Can Do a Piece of Work in 20 Days and 12 Days Respectively

    9/11

    A takes twice as much time as B and thrice as much as C to finish a piece of work. They together finish the work in one day. Find the time taken by each of them to finish the work.

    A takes twice as much time as B,meaning if B takes 1 day, A takes 2 daysSo the ratio of time is A:B=2:1Similarly A:C=3:1We can write the same thing as

    B:A=1:2A:C=3:1

    If we want the three terms ratio, we want mid term (A) to be same in both equation.

    In the first eq. A is 2 and in second eq. A is 3. LCM (2,3)=6Multiply something in both equations so that we get 6 in both equation.Meaning, Multiply first eq with (2) and second equation with (3)B:A=3:6A:C=6:2

    Now we can make a three terms ratioB:A:C=3:6:2

    http://www.flipkart.com/search-book?affid=mrunalrugm&wgtid=FK-AF-SB&query=9789381250426http://www.flipkart.com/search-book?affid=mrunalrugm&wgtid=FK-AF-SB&query=9788183481595http://www.flipkart.com/search-book?affid=mrunalrugm&wgtid=FK-AF-SB&query=9789381250426http://www.flipkart.com/search-book?affid=mrunalrugm&wgtid=FK-AF-SB&query=9788183481595
  • 7/28/2019 X and Y Can Do a Piece of Work in 20 Days and 12 Days Respectively

    10/11

    Keep in mind, this is ratio and not absolute number So we fill Time boxes as As time = 6x Bs time = 3xCs Time = 2x

    Run the STD table, fill the data

    A B C A+B+C

    Speed 1 2 3 6

    Time 6x 3x 2x 1 day

    Distance 6x 6x 6x 6x

    LCM of (6x,3x,2x)= 6xFrom the STD fomula, we can get the individual speeds of A,B,C,= 1,2,3Together their speed A+B+C=1+2+3=6For the last columnSpeed x time = distance6 multiplied with 1 =6xHence x= 1

    Put the value of x=1 in the table and you get individual timeA will take 6 days individually, B will take 3 days and C will take 2 days.

    Cross verification (plug the answers we got)

    A B C A+B+C

    Speed 1 2 3 6

    Time 6 3 2 1 day

    Distance 6 6 6 6

    From the table,A takes twice as much time as B and thrice as much as C to finish a piece of work Yes it satisfies the statement given in the question itself.

  • 7/28/2019 X and Y Can Do a Piece of Work in 20 Days and 12 Days Respectively

    11/11