57
Wyckoff Eagle Harbor Site Public Information Meeting December 10, 2014 Helen Bottcher EPA Project Manager

Wyckoff Eagle Harbor Site - semspub.epa.gov · Wyckoff Eagle Harbor Site Public Information Meeting December 10, 2014 Helen Bottcher EPA Project Manager

Embed Size (px)

Citation preview

Page 1: Wyckoff Eagle Harbor Site - semspub.epa.gov · Wyckoff Eagle Harbor Site Public Information Meeting December 10, 2014 Helen Bottcher EPA Project Manager

Wyckoff Eagle Harbor Site

Public Information Meeting December 10, 2014

Helen BottcherEPA Project Manager

Page 2: Wyckoff Eagle Harbor Site - semspub.epa.gov · Wyckoff Eagle Harbor Site Public Information Meeting December 10, 2014 Helen Bottcher EPA Project Manager

Provide a status update Describe cleanup alternatives under

consideration Answer your questions Hear informal input

No cleanup decision has been made! Formal public comment will be solicited in

Summer 2015 when EPA releases the Proposed Plan

2

Page 3: Wyckoff Eagle Harbor Site - semspub.epa.gov · Wyckoff Eagle Harbor Site Public Information Meeting December 10, 2014 Helen Bottcher EPA Project Manager

Ecology◦ Chung Yee, Barry Rogowski, Sandra Caldwell,

Susannah Edwards, Dawn Hooper Floyd | Snider – Ecology Consultant◦ Kate Snider

CH2M Hill – EPA Contractor◦ Ken Scheffler, Jeff Gentry, George Hicks

EPA◦ Helen Bottcher, Rene Fuentes, Kira Lynch, Peter

Murchie, Beth Sheldrake

3

Page 4: Wyckoff Eagle Harbor Site - semspub.epa.gov · Wyckoff Eagle Harbor Site Public Information Meeting December 10, 2014 Helen Bottcher EPA Project Manager

4

(b) (6)

Page 5: Wyckoff Eagle Harbor Site - semspub.epa.gov · Wyckoff Eagle Harbor Site Public Information Meeting December 10, 2014 Helen Bottcher EPA Project Manager

5

Page 6: Wyckoff Eagle Harbor Site - semspub.epa.gov · Wyckoff Eagle Harbor Site Public Information Meeting December 10, 2014 Helen Bottcher EPA Project Manager
Page 7: Wyckoff Eagle Harbor Site - semspub.epa.gov · Wyckoff Eagle Harbor Site Public Information Meeting December 10, 2014 Helen Bottcher EPA Project Manager

7

Page 8: Wyckoff Eagle Harbor Site - semspub.epa.gov · Wyckoff Eagle Harbor Site Public Information Meeting December 10, 2014 Helen Bottcher EPA Project Manager

• 1984 – EPA orders Wyckoff Company to conduct environmental investigation

• 1987 – Site added to the Superfund List• 1994 – Legal settlement with Pacific Sound

Resources for Superfund liability • Cleanup Decisions

• 1994 – Groundwater ROD (interim)• 1994 – Offshore / Eagle Harbor ROD• 2000 – Soil and Groundwater ROD• 2007 – West Beach ESD

Page 9: Wyckoff Eagle Harbor Site - semspub.epa.gov · Wyckoff Eagle Harbor Site Public Information Meeting December 10, 2014 Helen Bottcher EPA Project Manager

1990: groundwater extraction, treatment begins 1992 – 1994: significant cleanup actions to remove

contaminated soils, repair bulkhead, recycle materials in tanks, treatment equipment

1994: upgrades to groundwater extraction system and treatment plant

1996 – 1997: removal of site structures 2000 – 2001: perimeter sheet pile wall 2002 – 2003: thermal treatment pilot study 2010: replaced groundwater treatment plant 2012 - 2013: new investigation of subsurface

contamination

9

Page 10: Wyckoff Eagle Harbor Site - semspub.epa.gov · Wyckoff Eagle Harbor Site Public Information Meeting December 10, 2014 Helen Bottcher EPA Project Manager

1993 -1994: 54 acres of Eagle Harbor capped 1999: West Dock removed 2001: perimeter sheet pile wall 2001 - 2002: extended sediment cap along

west side of site 2008: completed West Beach cap 2013: completed new investigation of

contamination remaining in the beaches

10

Page 11: Wyckoff Eagle Harbor Site - semspub.epa.gov · Wyckoff Eagle Harbor Site Public Information Meeting December 10, 2014 Helen Bottcher EPA Project Manager

11

Page 12: Wyckoff Eagle Harbor Site - semspub.epa.gov · Wyckoff Eagle Harbor Site Public Information Meeting December 10, 2014 Helen Bottcher EPA Project Manager

WA Department of Ecology operates groundwater extraction and treatment plant

Groundwater is pumped from shallow aquifer, treated, discharged to Eagle Harbor

Containment is effective, but running the pump and treat system is expensive ($800,000/yr)

2010: Ecology completed Generational Remedy Evaluation

Current remedy evaluation seeks more permanent and cost effective solution

12

Page 13: Wyckoff Eagle Harbor Site - semspub.epa.gov · Wyckoff Eagle Harbor Site Public Information Meeting December 10, 2014 Helen Bottcher EPA Project Manager

13

Page 14: Wyckoff Eagle Harbor Site - semspub.epa.gov · Wyckoff Eagle Harbor Site Public Information Meeting December 10, 2014 Helen Bottcher EPA Project Manager

14

Page 15: Wyckoff Eagle Harbor Site - semspub.epa.gov · Wyckoff Eagle Harbor Site Public Information Meeting December 10, 2014 Helen Bottcher EPA Project Manager

Wyckoff Point FFS Project Area

Wyckoff Beaches FFS Project Area

Page 16: Wyckoff Eagle Harbor Site - semspub.epa.gov · Wyckoff Eagle Harbor Site Public Information Meeting December 10, 2014 Helen Bottcher EPA Project Manager
Page 17: Wyckoff Eagle Harbor Site - semspub.epa.gov · Wyckoff Eagle Harbor Site Public Information Meeting December 10, 2014 Helen Bottcher EPA Project Manager
Page 18: Wyckoff Eagle Harbor Site - semspub.epa.gov · Wyckoff Eagle Harbor Site Public Information Meeting December 10, 2014 Helen Bottcher EPA Project Manager

NAPL = Non-Aqueous Phase Liquid

18

Page 19: Wyckoff Eagle Harbor Site - semspub.epa.gov · Wyckoff Eagle Harbor Site Public Information Meeting December 10, 2014 Helen Bottcher EPA Project Manager
Page 20: Wyckoff Eagle Harbor Site - semspub.epa.gov · Wyckoff Eagle Harbor Site Public Information Meeting December 10, 2014 Helen Bottcher EPA Project Manager
Page 21: Wyckoff Eagle Harbor Site - semspub.epa.gov · Wyckoff Eagle Harbor Site Public Information Meeting December 10, 2014 Helen Bottcher EPA Project Manager
Page 22: Wyckoff Eagle Harbor Site - semspub.epa.gov · Wyckoff Eagle Harbor Site Public Information Meeting December 10, 2014 Helen Bottcher EPA Project Manager
Page 23: Wyckoff Eagle Harbor Site - semspub.epa.gov · Wyckoff Eagle Harbor Site Public Information Meeting December 10, 2014 Helen Bottcher EPA Project Manager
Page 24: Wyckoff Eagle Harbor Site - semspub.epa.gov · Wyckoff Eagle Harbor Site Public Information Meeting December 10, 2014 Helen Bottcher EPA Project Manager

24

Page 25: Wyckoff Eagle Harbor Site - semspub.epa.gov · Wyckoff Eagle Harbor Site Public Information Meeting December 10, 2014 Helen Bottcher EPA Project Manager

Screened available remedial technologies Bundled technologies in cleanup alternatives◦ All the alternatives rely on more than one

technology Developed conceptual design and rough

duration, cost estimates for each alternative Alternatives compared to one another in Draft

Focused Feasibility Study (FFS) reports

25

Page 26: Wyckoff Eagle Harbor Site - semspub.epa.gov · Wyckoff Eagle Harbor Site Public Information Meeting December 10, 2014 Helen Bottcher EPA Project Manager

26

Mobilizing equipment to the site, obtaining permits, developing health and safety plans

New sheet pile and concrete perimeter wall New Access Road from Eagle Harbor Drive down to the

site Excavation and removal of buried concrete and other

debris Construction of new outfall Final site cap Costs are not insubstantial:◦ Range from $35 to $52 million

Page 27: Wyckoff Eagle Harbor Site - semspub.epa.gov · Wyckoff Eagle Harbor Site Public Information Meeting December 10, 2014 Helen Bottcher EPA Project Manager

No cleanup action will get the upland soil and groundwater so clean that we can allow it to erode into Eagle Harbor

Wall needed to support future use as a park Wall needs to be replaced – this will involve

installation of a second metal wall and concrete bulkhead

2 options on the table: put the new wall inside (land side) of the existing wall, OR build it out onto the beach

27

Page 28: Wyckoff Eagle Harbor Site - semspub.epa.gov · Wyckoff Eagle Harbor Site Public Information Meeting December 10, 2014 Helen Bottcher EPA Project Manager

1. No further action2. Containment (the current remedy)3. Excavation, Thermal Desorption, and In Situ

Chemical Oxidation 4. In-Situ Solidification / Stabilization (ISS)5. Thermal Enhanced Extraction and ISS6. Partial excavation, Thermal Desorption, and

Thermal Enhanced Extraction7. ISS of Core Area + NAPL recovery

28

Page 29: Wyckoff Eagle Harbor Site - semspub.epa.gov · Wyckoff Eagle Harbor Site Public Information Meeting December 10, 2014 Helen Bottcher EPA Project Manager

29

North/East/Periphery Shallow (LNAPL) Areas

Core Area

North Deep (DNAPL) Area

10% RE Footprint

Currently includes the area within the upper aquifer where NAPL is present (TarGOST >10% RE).

Page 30: Wyckoff Eagle Harbor Site - semspub.epa.gov · Wyckoff Eagle Harbor Site Public Information Meeting December 10, 2014 Helen Bottcher EPA Project Manager

Description: Solidification through concrete mixing of virtually all the mobile NAPL.

95% of NAPL would be treated Remaining 5% of NAPL addressed through

natural attenuation and passive groundwater treatment

Cost: $64M to $138M

30

Page 31: Wyckoff Eagle Harbor Site - semspub.epa.gov · Wyckoff Eagle Harbor Site Public Information Meeting December 10, 2014 Helen Bottcher EPA Project Manager

31

Page 32: Wyckoff Eagle Harbor Site - semspub.epa.gov · Wyckoff Eagle Harbor Site Public Information Meeting December 10, 2014 Helen Bottcher EPA Project Manager
Page 33: Wyckoff Eagle Harbor Site - semspub.epa.gov · Wyckoff Eagle Harbor Site Public Information Meeting December 10, 2014 Helen Bottcher EPA Project Manager

33

Page 34: Wyckoff Eagle Harbor Site - semspub.epa.gov · Wyckoff Eagle Harbor Site Public Information Meeting December 10, 2014 Helen Bottcher EPA Project Manager

34

Page 35: Wyckoff Eagle Harbor Site - semspub.epa.gov · Wyckoff Eagle Harbor Site Public Information Meeting December 10, 2014 Helen Bottcher EPA Project Manager

Description: NAPL recovery through an expanded network of groundwater wells, enhanced with heat (steam injection) in the core area, north shallow and east shallow areas. ISS in the north deep area, using jet grout mixing.

Enhanced Aerobic Biodegradation (EAB) in peripheral areas, and to “polish” treated zones

Cost: $104M to $224M

35

Page 36: Wyckoff Eagle Harbor Site - semspub.epa.gov · Wyckoff Eagle Harbor Site Public Information Meeting December 10, 2014 Helen Bottcher EPA Project Manager

36

Page 37: Wyckoff Eagle Harbor Site - semspub.epa.gov · Wyckoff Eagle Harbor Site Public Information Meeting December 10, 2014 Helen Bottcher EPA Project Manager

Phase 1: ISS of an expanded “core” area. NAPL recovery in other areas with EAB. Passive groundwater treatment for residual contamination.

Phase 2 (only if needed): Thermal enhanced “wet steam” injection and NAPL recovery, continued EAB and passive groundwater treatment.

Cost: $38M to $82M (~ $55M for Phase 1 only)

37

Page 38: Wyckoff Eagle Harbor Site - semspub.epa.gov · Wyckoff Eagle Harbor Site Public Information Meeting December 10, 2014 Helen Bottcher EPA Project Manager

38

Page 39: Wyckoff Eagle Harbor Site - semspub.epa.gov · Wyckoff Eagle Harbor Site Public Information Meeting December 10, 2014 Helen Bottcher EPA Project Manager

Questions about Upland Treatment Options ?

39

Page 40: Wyckoff Eagle Harbor Site - semspub.epa.gov · Wyckoff Eagle Harbor Site Public Information Meeting December 10, 2014 Helen Bottcher EPA Project Manager

40

Alternative 1 – No Action Alternative 2 - Seep Patches and Monitored

Natural Recovery (MNR) Alternative 3 – Thin Inset Caps and MNR Alternative 4 - Vertical Containment with Thin

Caps and MNR Alternative 5 – Dredging with Thick Caps and

MNR

Page 41: Wyckoff Eagle Harbor Site - semspub.epa.gov · Wyckoff Eagle Harbor Site Public Information Meeting December 10, 2014 Helen Bottcher EPA Project Manager

41

Active Remedial Technologies for

Seeps and Potentially Mobile NAPL Zones

(brown areas)

Monitored Natural Recovery (MNR) for Non-Mobile NAPL

Zones (dark green areas)

Existing Phase III Cap

Page 42: Wyckoff Eagle Harbor Site - semspub.epa.gov · Wyckoff Eagle Harbor Site Public Information Meeting December 10, 2014 Helen Bottcher EPA Project Manager

Shallow excavation of active product seeps only Monitored Natural Recovery (MNR) over rest of

beaches Excavate, dewater, and inset cap during low tide ◦ Approximately 15 40 x 40 foot areas◦ 30-inch cap with amended base layer

Dewater, stabilize, landfill or potentially upland dispose of excavated materials

Cost: $8.0M to $17.0M

Page 43: Wyckoff Eagle Harbor Site - semspub.epa.gov · Wyckoff Eagle Harbor Site Public Information Meeting December 10, 2014 Helen Bottcher EPA Project Manager
Page 44: Wyckoff Eagle Harbor Site - semspub.epa.gov · Wyckoff Eagle Harbor Site Public Information Meeting December 10, 2014 Helen Bottcher EPA Project Manager

44

Page 45: Wyckoff Eagle Harbor Site - semspub.epa.gov · Wyckoff Eagle Harbor Site Public Information Meeting December 10, 2014 Helen Bottcher EPA Project Manager

45

AC- and OC-amended caps placed over areas with suspected mobile NAPL and North Shoal Surface Sheen Area

Excavate, dewater, and inset cap during low tide ◦ Approximately 70 40 x 40 foot areas◦ 30-inch composite cap profile ◦ Dewater, stabilize, landfill or potentially upland dispose of

excavated materials Long-term O&M ◦ Up to 50% percent of cap replaced over first 50 years

Cost: $10.2M to $21.8M

Page 46: Wyckoff Eagle Harbor Site - semspub.epa.gov · Wyckoff Eagle Harbor Site Public Information Meeting December 10, 2014 Helen Bottcher EPA Project Manager

46

• Amended caps (cross hatch) placed over suspected mobile NAPL zones (brown) and North Shoal sheening area

• Other mobile NAPL zones shown are deeper and not amenable to capping

New Seep Area Discovered May 2014*

Shallow NAPL Area*

Page 47: Wyckoff Eagle Harbor Site - semspub.epa.gov · Wyckoff Eagle Harbor Site Public Information Meeting December 10, 2014 Helen Bottcher EPA Project Manager

47

Temporary sheet pile enclosures to contain dredging◦ Driven to about 25 feet below beach grade◦ Sediments removed to about 10 feet below beach grade◦ Dredges positioned inside enclosure with standing water column

Backfilled with capping materials◦ OC-amended lift placed at base of dredge prism◦ Gravelly sand backfill placed to beach surface

Dewater/stabilize, and landfill or potentially upland dispose of dredged materials

Long-term monitoring but no repair/replacement envisioned Cost: $32.0M to $68.5M

Page 48: Wyckoff Eagle Harbor Site - semspub.epa.gov · Wyckoff Eagle Harbor Site Public Information Meeting December 10, 2014 Helen Bottcher EPA Project Manager

48

• Temporary sheet pile enclosures (gray lines) placed around suspect mobile NAPL zones

• East Beach removal may be completed from land

• North Shoal areas to be refined in design

Page 49: Wyckoff Eagle Harbor Site - semspub.epa.gov · Wyckoff Eagle Harbor Site Public Information Meeting December 10, 2014 Helen Bottcher EPA Project Manager

Questions about Treatment Options for the Beaches ?

49

Page 50: Wyckoff Eagle Harbor Site - semspub.epa.gov · Wyckoff Eagle Harbor Site Public Information Meeting December 10, 2014 Helen Bottcher EPA Project Manager

50

Long-Term Effectiveness and Permanence

Reduction of TMV

Balancing Criteria

Short-term Effectiveness

Implementability

Cost

Threshold Criteria

Protection of HH and Environment

Compliance with ARARs

Pass Pass

Rating

Rating

Rating

Rating

Rating

Page 51: Wyckoff Eagle Harbor Site - semspub.epa.gov · Wyckoff Eagle Harbor Site Public Information Meeting December 10, 2014 Helen Bottcher EPA Project Manager

51

Threshold criteria evaluated using:◦ Pass (yes) ◦ Fail (no)

Alternatives that failed threshold criteria not carried forward for balancing criteria evaluation

Page 52: Wyckoff Eagle Harbor Site - semspub.epa.gov · Wyckoff Eagle Harbor Site Public Information Meeting December 10, 2014 Helen Bottcher EPA Project Manager

Primary Balancing Criteria◦ 3. Long-term effectiveness and permanence◦ 4. Reduction of toxicity, mobility or volume through

treatment◦ 5. Short-term effectiveness◦ 6. Implementability◦ 7. Cost

Balancing criteria evaluated:◦ Narratively◦ Rating provided using the following:

52

Page 53: Wyckoff Eagle Harbor Site - semspub.epa.gov · Wyckoff Eagle Harbor Site Public Information Meeting December 10, 2014 Helen Bottcher EPA Project Manager

Modifying criteria◦ 8. State/Support agency acceptance◦ 9. Community acceptance

These criteria are assessed formally after the public comment period on the Proposed Plan.

53

Page 54: Wyckoff Eagle Harbor Site - semspub.epa.gov · Wyckoff Eagle Harbor Site Public Information Meeting December 10, 2014 Helen Bottcher EPA Project Manager

EPA National Remedy Review Board Choose preferred alternative for both areas Determine how best to combine the remedies

for the two areas Publish the final FFS Reports Develop the Proposed Plan

54

Page 55: Wyckoff Eagle Harbor Site - semspub.epa.gov · Wyckoff Eagle Harbor Site Public Information Meeting December 10, 2014 Helen Bottcher EPA Project Manager

55

Phasing and Sequencing◦ Which first: offshore or upland?

Which wall replacement design? Opportunities for efficiencies or cost savings◦ Possible disposal of beach sediment in the upland portion of

the site Will develop recommended sequence, duration

estimates for Proposed Plan

Page 56: Wyckoff Eagle Harbor Site - semspub.epa.gov · Wyckoff Eagle Harbor Site Public Information Meeting December 10, 2014 Helen Bottcher EPA Project Manager

Proposed Plan available for public review and comment - Summer 2015◦ Notice in newspaper◦ Formal public meeting(s)◦ Opportunity for verbal and written comment

Final FFS document will be made available at the same time

Join our Mail List Record of Decision Winter 2015

56

Page 57: Wyckoff Eagle Harbor Site - semspub.epa.gov · Wyckoff Eagle Harbor Site Public Information Meeting December 10, 2014 Helen Bottcher EPA Project Manager

Thank you for coming! Questions?

57