Upload
denzel-hollen
View
215
Download
0
Embed Size (px)
Citation preview
www.argans.co.uk
SMOS L2 Ocean Salinity Commissioning Plan, 07/05/2009
Level 2 Ocean Salinity Processor
Commissioning Plan
7 May 2009
ARGANSACRI-ST
ICM-CSICLOCEAN-IPSL
IFREMER
www.argans.co.uk
SMOS L2 Ocean Salinity Commissioning Plan, 07/05/2009
First look
Southern Pacific Ocean orbits over region far from land: 120°W and 150°W, 30°S and the equator
www.argans.co.uk
SMOS L2 Ocean Salinity Commissioning Plan, 07/05/2009
• Compare L1c brightness temperatures (BT) with L2 direct models, including ground-truth geophysical parameters (wind speed, SST, SSS)– far from land, relatively homogeneous & well
monitored ocean region– scatter plots of L1c and L2OS_fwd TBs by grid
point (+ distance to ground track) & snapshot
• If biases > ± 1K OS cannot be retrieved without correction
First look
www.argans.co.uk
SMOS L2 Ocean Salinity Commissioning Plan, 07/05/2009
Long term• compare L1c BT with L2 direct models • verify T3, radiometric accuracy• error autocorrelation • Acard/sea-ice detection• verify retrieved parameters with climatology• optical data matching• tuning direct models• examine distance to coast thresholds effects
www.argans.co.uk
SMOS L2 Ocean Salinity Commissioning Plan, 07/05/2009
Priority 1• Goal: comparison of L1c brightness
temperatures with L2 OS direct models using ECMWF forcing– open ocean: ascending and descending orbits over
well monitored homogeneous salinity regions– plot average, stdev, of differences in FOV
referential (cos dir geometry)– plot average, stdev, of differences per grid point
www.argans.co.uk
SMOS L2 Ocean Salinity Commissioning Plan, 07/05/2009
Priority 1• Goal: verification of T3– comparison of L1c T3 with L2 direct models– open ocean with relatively homogeneous SSS
• Goal: radiometric accuracy wrt FOV mean TB & autocorrelation of the error
– plot radiometric accuracy with FOV trend removed– compare autocorrelation of the temperature
residuals TB(L1c) - TB(L2OS) to the WEF
www.argans.co.uk
SMOS L2 Ocean Salinity Commissioning Plan, 07/05/2009
Priority 2• Goal: comparison of L1c brightness
temperatures with L2 OS direct models using retrieved parameters or ECMWF forcing– plot average, std, skewness, kurtosis of
differences in FOV (cos dir geometry)– plot Tx and Ty as function of incidence angle
(pointing)– histograms of the differences in TBs, dividing
measurements into AF-FOV and EAF-FOV classes
www.argans.co.uk
SMOS L2 Ocean Salinity Commissioning Plan, 07/05/2009
Priority 2• Goal: verification of the radiometric noise
– plot Var(Tbmodel-Tbmeasured_DP) / Var(Tbmodel-Tbmeasured_FP) in FOV
– plot Var(Tbmodel-Tbmeasured) wrt distance to boresight
• Goal: Acard/sea-ice detection– look at compatibility between retrieved Acard and
known values of dielectric constants
www.argans.co.uk
SMOS L2 Ocean Salinity Commissioning Plan, 07/05/2009
Priority 3 & 4 goals• comparison of L1c brightness temperatures
with L2 OS direct models• verification of retrieved parameters based on
climatology (FP and DP) and other classes• optical data matching• tuning direct models• distance to coast thresholds effects
www.argans.co.uk
SMOS L2 Ocean Salinity Commissioning Plan, 07/05/2009
High coverage test sites
• North Atlantic• SW tropical Pacific• South of Tasmania• Equatorial
• Tarfaya model region• Amazon Plume• Gulf of Biscay• Mediterranean Sea
Test sites: 70-80% availability (time):
Southern Pacific Ocean (first look)100% availability before KP1; 60-70% afterwards
www.argans.co.uk
SMOS L2 Ocean Salinity Commissioning Plan, 07/05/2009
Operational Monitoring Facility sites• TAO-PIRATA & moored buoys (16), ±1 degree,
filter data using L2 OS global quality indicators, extract average, std for every intersecting orbit:– ECMWF Sea_Surface_Temperature,
Significant_Wave_Height, Wind_Zonal_Lowest_Level, Wind_Meridonal_Lowest_Level
– L2 OS SSS from forward models 1, 2 & 3– MIR_BWSD1C BT_VALUE
www.argans.co.uk
SMOS L2 Ocean Salinity Commissioning Plan, 07/05/2009
Schedule• First look:
– ESL collocation at ESAC 2-3 weeks after launch (KP0/first image), for first look image analysis
• Priority 1:– preliminary dual & full pol report for KP1
(estimate of L1c accuracy)– radiometric accuracy assessment & analysis of
dual versus full for KP2 & SVRT release decision– report comparing dual & full pol for KP3
www.argans.co.uk
SMOS L2 Ocean Salinity Commissioning Plan, 07/05/2009
Schedule• Priority 2:
– if good progress with priority 1:• preliminary dual pol report for KP1
– otherwise• preliminary dual pol report for KP2
– report comparing dual & full pol for KP3
• Priority 3 & 4 (only if priority 1 & 2 successful):– report for KP3
www.argans.co.uk
SMOS L2 Ocean Salinity Commissioning Plan, 07/05/2009
Questions• What is the role of each KP?• When will first calibrated data be available for
our Southern Pacific site?• For calibration frequency analysis, will we get
the complete data set used to generate the L1c products?
• What metric will be used to determine calibration frequency?