WS Infrastructure Programme
Quarterly WorkshopFree State
Presented by:Mpho Manyama Water Services Infrastructure
Date: 31 – 01 October 2013
Sub-Title here (if needed)PRESENTATION TITLE HERE (if needed)
ContentsA: Expenditure Status 2013/14
1. RBIG 2. MWIG3. ACIP4. NTP
B: Key Challenges
C: Project to be “Fast Track”
D: Projects to be Launched
E: Way forward
A1. RBIG : Expenditure 2013/14 Scheme
Project Cost DWA
Commitment
Budget Allocation
2013/14
BAS Expenditure
31 October 2013
Invoices at Hand
Planned Cash Flow end Oct -
2013
Proposed Budget
Reallocations 2013/14
Reason for Re-allocation/ Movement
Implementation/
Construction Progress
Jagersfontein /Fauresmith BWS Phase 2
148,000,000 24,900,000 17,214,998 1,723,369 18,938,36724,900,000
N/A 67%
Rouxville /Smithfield /Zastron BWS
161,000,000 23,000,000 12,745,036 0 12,745,03623,000,000 N/A
58%
Masilonyana BWS 230,400,000 27,000,000 1,866,779 1,477,271 3,344,050 17,000,000 Slow progress 7%
Tokologo Regional WS
320,000,000 17,820,000 10,456,618 0 10,456,618 13,820,000Slow progress
99%
Setsoto BWS 160,000,000 10,000,000 1,796,773 0 1,796,773 4,000,000Slow progress
14%
Dihlabeng 255,000,000 20,580,000 14,569,839 0 14,569,839 18,580,000Slow progress
99%
Nketoana RWS augmentation
290,000,000 14,000,000 3,890,429 0 3,890,429 12,000,000Slow progress
28%
Sterkfontein Dam Scheme
520,100,000 32,600,000 18,402,864 7,600,000 26,002,864 52,600,000Requires
additional funds 50%
Phumelela 166,000,000 20,000,000 8,917,232 0 8,917,232 23,000,000Requires
additional funds62%
Moqhaka BWS 205,800,000 15,000,000 6,130,404 0 6,130,404 12,000,000Slow progress
10%
Ngwathe Phase 2 300,000,000 5,000,000 0.00 1,450,000 1,450,0007,000,000
Requires additional funds
5%
Nala Bulk Sewer 50,000,000 5,000,000 0.00 0 0.007,000,000 Requires
additional funds0%
Total 2,806,300,000 214,900,000 95,990,976 12,250,640 108,241,616 214,900,000 50%
A1 B: Feasibility studies ”Municipality Projects Estimated Costs Status
Mantsopa LM Bulk water supply R166 m Recommended
Nala LM Wesselsbron Bulk sewer
R86 m Recommended
Mafube LM Namahadi bulk sewer R112 m In final stage(land issue)
Tokologo LM Phase 2 bulk water supply for Boshof and Denesville
R295m In final stage
Tswelopele LM Bulk water supply R56m In final stage
Letsemeng LM Bulk water supply R120 m In final stage
Dihlabeng LM Phase bulk water supply to Fauresburg and Rosendal
R220m In progress
Scheme
Project Cost DWA
Commitment
Budget Allocation
2013/14
BAS Expenditure 31 October
2013
Invoices at Hand
Planned Cash Flow
end Oct -2013
Proposed Budget
Reallocations 2013/14
Reason for Re-allocation/
Movement
Implementation/
Construction Progress
Naledi LM Borehole Development
813,000 813,000 0 0 0 813,000 N/ABP and FA submitted
Dewetsdorp & Wepener Scheme 2
2,000,000 2,000,000 0 0 0 2,000,000 N/ABP and FA submitted
Dewetsdorp Scheme 3
8,000,000 1,046,000 0 0 0 1,046,000 N/ABP and FA submitted
Poding-tse-rolo 2,602,000 2,602,000 1,301,000 0 0 2,602,000 N/ABP and FA submitted
Mohokare LM Refurbishment
1,000,000 1,000,000 500,000 0 0 1,000,000 N/ABP and FA submitted
Jacobsdal/Ratanang WTW
14,000,000 6,500,000 1,000,000 0 0 6,500,000 N/ABP and FA submitted
Luckhoff/Teisesville/Relebohile WTW
8,970,295 5,384,000 1,000,000 0 0 5,384,000 N/ABP and FA submitted
Total 37,385,295 19,345,000 3,801,000 0 0 19,345,000
A2. MWIG: Expenditure 2013/14
A3. ACIP : Expenditure 2013/14 Project
Project cost DWA commitment
Budget allocation2012/13 FY
BAS Expenditure 30 October 2013
Invoices in hands
Planned cash flow end November 2013
Proposed budget Re allocations2013/14
Reason for re allocation/movement
Ficksburg sewer upgrade
16,900,000 5,040,000 2,082,338.93 0,00 1,250,000 5,040,000 N/A
Clocolan WWTW 5,800,000 5,800,000 450,000 0,00 1,500,000 3,400,000 Project started
late
Managung WC/DM
22,000,000 6,000,000 2,919,706.91 1,395,374 950,000 8,000,000
Project progressing quicker than scheduled
Ladybrand WTW 1,000,000 1,000,000 1,000,000 0,00 0,001,000,000
N/A
Wepener WWTW
2,250,000 2,250,000 221,020 570,000 650,000 2, 850,000Funds needed to line the pondxs
Morojaneng sewer pump station
5,600,000 600,000 0,000,00
0,00 0.00Non availability
of land
Jacobsdal raw water pipe line
3,000,000 3,000,000 0,000,00
0,00 2,000,000Project started
late
Letsemeng WC/DM
5,000,000- 5,000,000 0,00 0,00 750,000 4,000,000Project started
late
Kroonstad outfall sewer
7,400,000 5,000,000 1,360,000 1,500,000 1,100,000 7,400,000
Project progressing quicker than scheduled
33,690,000 7,583,065,84 3,465,374 (33%) 6,200,000 (52%)
A4: NTP – Expenditure 2013/14 Scheme
Project Cost DWA
Commitment
Budget Allocation
2013/14
BAS Expenditure 31 October
2013
Invoices at Hand
Planned Cash Flow
end Oct -2013
Proposed Budget
Reallocations 2013/14
Reason for Re-allocation/
Movement
Implementation/
Construction Progress
Refurbishment of Gariep Water Treatment Works
5,424,000 2,712,000 1,808,000 0.00 1,808,0002,712,000 N/A
Phase 1 completed
Refurbishment of Clarens Water Supply system
4,400,000 2,200,000 1,466,000 0.00 1,466,000 2,200,000 N/AContractor
phase 2 appointed
Refurbishment of Deneysville WTW
5,424,000 2,712,000 904,000 0.00 904,000 2,712,000 N/AMIG is co-funding
Refurbishment of Fika Patso WTW
10,000,000 5,000,000 1,666,000 0.00 1,666,000 5,000,000 N/AContractor still
to be appointed
Refurbishment of Thaba Nchu rural scheme water supply thruogh WCWDM
6,900,000 6,900,000 4,600,000 0.00 4,600,000 6,900,000 N/AUnder
construction
Total 19,524,000 10,444,000 0.00 10,444,000 19,524,000 N/A
1. RRU Status
1. Implementing Agent : Sedibeng Water2. Consultants : Rubiquant-Letsemane Consortium.3. Contract commencement : 01 April 2012 – 31 March 20154. Allocations 2013 -14 FY: R4,3 million - 1,5 million : schedule 7 (National Transfers Programme)
-2,8 million : RBIG
ExpenditureProgramme Allocation Expenditure Invoice in hands Remaining
RBIG R2 800 000 R1 366 790 R250 000 R1 183 210
TRANSFERS R1 500 000 R1 124 018 R150 000 R225 982
TOTAL R4 300 000 R2 490 809 R400 000 R1 409 192
11
B: Key ChallengesRBIG• (Kopanong) Jagersfontein/Fauresmith Regional Bulk Scheme:Water Treatment WorksEngineer for the Water Treatment Works and Reservoir seconded not well experienced R.E hence delay of project and detail drawings,• Guidance to the contractor is poor,•R.E not on site always so contractors mistakes get realised late,•No proper site instructions,•Contractor struggling to receive construction details.• Documentation on old projects is a challenge.
Reservior• Contractor has no enough knowledge to construct reservoir,•Contractor spend a lot on plant that they did not need, affecting their cashflow negetivly•Site agent no enough practical experience and ignores instructions from R.E•
B: Key ChallengesRBIG• (Moqhaka) Steynsrus Regional Bulk Scheme:•Changing over from MSW Consulting to Rand Water delayed project by six months,• WSA and Rand Water communication challenges i.e. WSA not in favour of waterboard,•Rand Water has no consistent personnel seconded to the project, this makes project steering committee uneasy,•Expenditure is slow on the project,
(Mohokare) Rouxville Bulk Water Scheme• The area has bucket system that could be a quick win if the bulk project can get additional R60 million to procure pipes,•Contractor had cashflow problems and has delayed the project by 8 months,•Safety on site is very poor even after pointing it out in meetings, this matter continues to be ignored. (An accident on site could shut down the project)•
B: Key ChallengesRBIG• General:•Test results files not available in some instances,•Over pricing of tenders especially for construction of pipes,•Contractors communicating directly with municipal officials , ignoring instructions of the R.E,•Poor invoice administration from municipality side,•WSA’s using MIG funds to pay for RBIG resulting in expenditure delays,•Boreholes schemes as an option against •IA fees – no bench mark(Water Boards)•Non of our WSA are willing to co-funding•Procurement– specifically on new projects(ACIP/RBIG)---commitments•ESKOM– electricity (Masilonyana LM)
B: Key ChallengesACIP• Letsemeng WC/DM and Jacobsdal raw water pipe line:Sedibeng Water only appointed contractors around 20 October 2013 hence no expenditure to date on these project hence re allocation of R2 million to Kroonstad to ensure that all funds are spent by end of FY. Clocolan WWTW:The scope of work had to be revised following the advice from the appointed consultant hence the late commencement of the project (October 2013) Morojaneng sewer pump station:Non availability of land for project implementation and negotiations taking too long hence re allocation of all the funds to other projects for expenditure purposes.MWIGDelay on appointmentsNo reporting, WSA lack of support from Waterboards
C: Project to be “Fast Track”Municipality Projects Costs Reason
Mafube LM Namahadi WWTW R112 m Facilitate Bucket eradication
Masilonyana LM Bulkwater pipeline R86 m Riots on water supply
Mohokare LM Raw water pipeline R66 m Facilitate Bucket eradication
Mantsopa LM Pipeline to connect hospital
R10m Hospital without water. President opening the hospital in November
D: Projects to be LaunchedPROVINCE PROJECT IMPLEMENTING AGENT/
MUNICIPALITY/WATER BOARD
POSSIBLE DATES
FREE STATE
Bethlehem to Paul Roux Scheme
Dihlabeng Local Municipality
08 November 2013
Roux ville WTW and pipeline from WTW to Reservoir
Mohokare Local Municipality
28 March 2014
Jagersfontein Phase1 ( Though the WTW is being upgraded as part of Phase 2)
Kopanong Local Municipality (Operated by Bloemwater)
14 February 2014
Christiana to Hertzogville Bulk water scheme
Tokologo Local Municipality 24 January 2014
Way forward
• Appointed two sub-contractors to avoid further delays
• Made inputs to the WSA to have an experienced RE on site
• Problematic projects- weekly site meetings are scheduled
• Involvement of Regional Head and Premier's coordinating forum to resolve administrative and political challenges