Procurement Plan-Goods Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
List of Contracts
Component 4: Project Management & System
Monitoring
Norm Duration of Proc Steps
Supply and Installation of Air Quality Equipment in Eleven
Monitoring Stations on LAMATA BRT Corridors including
Training, Laboratory Analysis, Installation of one Control
Centre and one Ambient Control Centre and a back-up
Procurement of IT Stationery/Consumable (4 Lots, to be
procured a lot per quarter)
Design, Supply and Installation of BRT Signal from CMS-
Mile 12-Ikorodu Icluding Design ( Intelligent Transport
Systems) - Phase 1
IT Equipment Purchase Switches and Printers
Implementation of the Recommendation of the Technical
Due Diligence Report on BFS Operations
Component 2:Public Transport and Traffic Management
Procurement of Office Furniture ( Front office desks, Work
stations, Executive swivel chairs, Board room furniture set,
Janitor shelf etc…
NonAsciiFileName0.xls 1 of 754 11/21/2012 1:40 AM
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Procurement Plan-Goods
Total Cost
Fill gray cells only!
NOTE: Line 30 -Procurement of IT
Equipment procurement proces has been
scheduled to commence in October to coicide
with resumption of staff to be recruited for the
construction of Mile 12 to Ikorodu BRT
scheme
Nn
Purchase and installation of Corel Draw and Video editing
software for external relation
Procurement of IT Equipment (Servers Laptops PC's and
UPS
Procurement of IT Stationery/Consumable (4 Lots, to be
procured a lot per quarter)
Procurement of Fire Proof Cabinet
Procurement of Operational Vehicles (One four Wheel and
10 Saloon Cars)
Procurement of Ofice Equipment (2HP Split Air
Conditioners (5, Water Dispenser, Refrigerators)
NonAsciiFileName0.xls 2 of 754 11/21/2012 1:40 AM
Procurement Plan-Goods Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*Package
Number
List of Contracts
1
1
Component 4: Project Management & System
Monitoring
1
1
1
1
Norm Duration of Proc Steps
Supply and Installation of Air Quality Equipment in Eleven
Monitoring Stations on LAMATA BRT Corridors including
Training, Laboratory Analysis, Installation of one Control
Centre and one Ambient Control Centre and a back-up
Procurement of IT Stationery/Consumable (4 Lots, to be
procured a lot per quarter)
Design, Supply and Installation of BRT Signal from CMS-
Mile 12-Ikorodu Icluding Design ( Intelligent Transport
Systems) - Phase 1
IT Equipment Purchase Switches and Printers
Implementation of the Recommendation of the Technical
Due Diligence Report on BFS Operations
Component 2:Public Transport and Traffic Management
Procurement of Office Furniture ( Front office desks, Work
stations, Executive swivel chairs, Board room furniture set,
Janitor shelf etc…
NonAsciiFileName0.xls 3 of 754 11/21/2012 1:40 AM
Procurement Plan-Goods
1
1
1
1
1
Total Cost
Fill gray cells only!
NOTE: Line 30 -Procurement of IT
Equipment procurement proces has been
scheduled to commence in October to coicide
with resumption of staff to be recruited for the
construction of Mile 12 to Ikorodu BRT
scheme
Nn
Purchase and installation of Corel Draw and Video editing
software for external relation
Procurement of IT Equipment (Servers Laptops PC's and
UPS
Procurement of IT Stationery/Consumable (4 Lots, to be
procured a lot per quarter)
Procurement of Fire Proof Cabinet
Procurement of Operational Vehicles (One four Wheel and
10 Saloon Cars)
Procurement of Ofice Equipment (2HP Split Air
Conditioners (5, Water Dispenser, Refrigerators)
NonAsciiFileName0.xls 4 of 754 11/21/2012 1:40 AM
Procurement Plan-Goods Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
List of Contracts
Component 4: Project Management & System
Monitoring
Norm Duration of Proc Steps
Supply and Installation of Air Quality Equipment in Eleven
Monitoring Stations on LAMATA BRT Corridors including
Training, Laboratory Analysis, Installation of one Control
Centre and one Ambient Control Centre and a back-up
Procurement of IT Stationery/Consumable (4 Lots, to be
procured a lot per quarter)
Design, Supply and Installation of BRT Signal from CMS-
Mile 12-Ikorodu Icluding Design ( Intelligent Transport
Systems) - Phase 1
IT Equipment Purchase Switches and Printers
Implementation of the Recommendation of the Technical
Due Diligence Report on BFS Operations
Component 2:Public Transport and Traffic Management
Procurement of Office Furniture ( Front office desks, Work
stations, Executive swivel chairs, Board room furniture set,
Janitor shelf etc…
Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Lot
Number
Lots 1
1
1
Lots 1
Lots 1
Lots 1 -4
BASIC DATA
Component 2:Public Transport and Traffic Management
NonAsciiFileName0.xls 5 of 754 11/21/2012 1:40 AM
Procurement Plan-Goods
Total Cost
Fill gray cells only!
NOTE: Line 30 -Procurement of IT
Equipment procurement proces has been
scheduled to commence in October to coicide
with resumption of staff to be recruited for the
construction of Mile 12 to Ikorodu BRT
scheme
Nn
Purchase and installation of Corel Draw and Video editing
software for external relation
Procurement of IT Equipment (Servers Laptops PC's and
UPS
Procurement of IT Stationery/Consumable (4 Lots, to be
procured a lot per quarter)
Procurement of Fire Proof Cabinet
Procurement of Operational Vehicles (One four Wheel and
10 Saloon Cars)
Procurement of Ofice Equipment (2HP Split Air
Conditioners (5, Water Dispenser, Refrigerators)
Lot 1
Lot 1
Lot 1
Lot 1
1
Nn
NonAsciiFileName0.xls 6 of 754 11/21/2012 1:40 AM
Procurement Plan-Goods Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
List of Contracts
Component 4: Project Management & System
Monitoring
Norm Duration of Proc Steps
Supply and Installation of Air Quality Equipment in Eleven
Monitoring Stations on LAMATA BRT Corridors including
Training, Laboratory Analysis, Installation of one Control
Centre and one Ambient Control Centre and a back-up
Procurement of IT Stationery/Consumable (4 Lots, to be
procured a lot per quarter)
Design, Supply and Installation of BRT Signal from CMS-
Mile 12-Ikorodu Icluding Design ( Intelligent Transport
Systems) - Phase 1
IT Equipment Purchase Switches and Printers
Implementation of the Recommendation of the Technical
Due Diligence Report on BFS Operations
Component 2:Public Transport and Traffic Management
Procurement of Office Furniture ( Front office desks, Work
stations, Executive swivel chairs, Board room furniture set,
Janitor shelf etc…
Procurement Method
ICB
NCB
ICB
NCB
Shopping
Shopping
BASIC DATA
NonAsciiFileName0.xls 7 of 754 11/21/2012 1:40 AM
Procurement Plan-Goods
Total Cost
Fill gray cells only!
NOTE: Line 30 -Procurement of IT
Equipment procurement proces has been
scheduled to commence in October to coicide
with resumption of staff to be recruited for the
construction of Mile 12 to Ikorodu BRT
scheme
Nn
Purchase and installation of Corel Draw and Video editing
software for external relation
Procurement of IT Equipment (Servers Laptops PC's and
UPS
Procurement of IT Stationery/Consumable (4 Lots, to be
procured a lot per quarter)
Procurement of Fire Proof Cabinet
Procurement of Operational Vehicles (One four Wheel and
10 Saloon Cars)
Procurement of Ofice Equipment (2HP Split Air
Conditioners (5, Water Dispenser, Refrigerators)
Shopping
Shopping
Shopping
Shopping
NCB
NonAsciiFileName0.xls 8 of 754 11/21/2012 1:40 AM
Procurement Plan-Goods Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
List of Contracts
Component 4: Project Management & System
Monitoring
Norm Duration of Proc Steps
Supply and Installation of Air Quality Equipment in Eleven
Monitoring Stations on LAMATA BRT Corridors including
Training, Laboratory Analysis, Installation of one Control
Centre and one Ambient Control Centre and a back-up
Procurement of IT Stationery/Consumable (4 Lots, to be
procured a lot per quarter)
Design, Supply and Installation of BRT Signal from CMS-
Mile 12-Ikorodu Icluding Design ( Intelligent Transport
Systems) - Phase 1
IT Equipment Purchase Switches and Printers
Implementation of the Recommendation of the Technical
Due Diligence Report on BFS Operations
Component 2:Public Transport and Traffic Management
Procurement of Office Furniture ( Front office desks, Work
stations, Executive swivel chairs, Board room furniture set,
Janitor shelf etc…
Pre-or Post
Qualification
If Prequalification
add 7-13 wks
Post Qualification
Post Qualification
Post Qualification
Post Qualification
Post Qualification
Post Qualification
BASIC DATA
NonAsciiFileName0.xls 9 of 754 11/21/2012 1:40 AM
Procurement Plan-Goods
Total Cost
Fill gray cells only!
NOTE: Line 30 -Procurement of IT
Equipment procurement proces has been
scheduled to commence in October to coicide
with resumption of staff to be recruited for the
construction of Mile 12 to Ikorodu BRT
scheme
Nn
Purchase and installation of Corel Draw and Video editing
software for external relation
Procurement of IT Equipment (Servers Laptops PC's and
UPS
Procurement of IT Stationery/Consumable (4 Lots, to be
procured a lot per quarter)
Procurement of Fire Proof Cabinet
Procurement of Operational Vehicles (One four Wheel and
10 Saloon Cars)
Procurement of Ofice Equipment (2HP Split Air
Conditioners (5, Water Dispenser, Refrigerators)
Post Qualification
Post Qualification
Post Qualification
Post Qualification
Post Qualification
NonAsciiFileName0.xls 10 of 754 11/21/2012 1:40 AM
Procurement Plan-Goods Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
List of Contracts
Component 4: Project Management & System
Monitoring
Norm Duration of Proc Steps
Supply and Installation of Air Quality Equipment in Eleven
Monitoring Stations on LAMATA BRT Corridors including
Training, Laboratory Analysis, Installation of one Control
Centre and one Ambient Control Centre and a back-up
Procurement of IT Stationery/Consumable (4 Lots, to be
procured a lot per quarter)
Design, Supply and Installation of BRT Signal from CMS-
Mile 12-Ikorodu Icluding Design ( Intelligent Transport
Systems) - Phase 1
IT Equipment Purchase Switches and Printers
Implementation of the Recommendation of the Technical
Due Diligence Report on BFS Operations
Component 2:Public Transport and Traffic Management
Procurement of Office Furniture ( Front office desks, Work
stations, Executive swivel chairs, Board room furniture set,
Janitor shelf etc…
Prior or Post Review
Post Review
Post Review
Prior Review
Post Review
Post Review
Post Review
BASIC DATA
NonAsciiFileName0.xls 11 of 754 11/21/2012 1:40 AM
Procurement Plan-Goods
Total Cost
Fill gray cells only!
NOTE: Line 30 -Procurement of IT
Equipment procurement proces has been
scheduled to commence in October to coicide
with resumption of staff to be recruited for the
construction of Mile 12 to Ikorodu BRT
scheme
Nn
Purchase and installation of Corel Draw and Video editing
software for external relation
Procurement of IT Equipment (Servers Laptops PC's and
UPS
Procurement of IT Stationery/Consumable (4 Lots, to be
procured a lot per quarter)
Procurement of Fire Proof Cabinet
Procurement of Operational Vehicles (One four Wheel and
10 Saloon Cars)
Procurement of Ofice Equipment (2HP Split Air
Conditioners (5, Water Dispenser, Refrigerators)
Post Review
Post Review
Post Review
Post Review
Post Review
NonAsciiFileName0.xls 12 of 754 11/21/2012 1:40 AM
Procurement Plan-Goods Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
List of Contracts
Component 4: Project Management & System
Monitoring
Norm Duration of Proc Steps
Supply and Installation of Air Quality Equipment in Eleven
Monitoring Stations on LAMATA BRT Corridors including
Training, Laboratory Analysis, Installation of one Control
Centre and one Ambient Control Centre and a back-up
Procurement of IT Stationery/Consumable (4 Lots, to be
procured a lot per quarter)
Design, Supply and Installation of BRT Signal from CMS-
Mile 12-Ikorodu Icluding Design ( Intelligent Transport
Systems) - Phase 1
IT Equipment Purchase Switches and Printers
Implementation of the Recommendation of the Technical
Due Diligence Report on BFS Operations
Component 2:Public Transport and Traffic Management
Procurement of Office Furniture ( Front office desks, Work
stations, Executive swivel chairs, Board room furniture set,
Janitor shelf etc…
Plan vs.
Actual
Plan
Actual
Plan
Actual
Plan
Actual
Plan
Plan
Actual
Plan
Actual
Plan
NonAsciiFileName0.xls 13 of 754 11/21/2012 1:40 AM
Procurement Plan-Goods
Total Cost
Fill gray cells only!
NOTE: Line 30 -Procurement of IT
Equipment procurement proces has been
scheduled to commence in October to coicide
with resumption of staff to be recruited for the
construction of Mile 12 to Ikorodu BRT
scheme
Nn
Purchase and installation of Corel Draw and Video editing
software for external relation
Procurement of IT Equipment (Servers Laptops PC's and
UPS
Procurement of IT Stationery/Consumable (4 Lots, to be
procured a lot per quarter)
Procurement of Fire Proof Cabinet
Procurement of Operational Vehicles (One four Wheel and
10 Saloon Cars)
Procurement of Ofice Equipment (2HP Split Air
Conditioners (5, Water Dispenser, Refrigerators)
Actual
Plan
Actual
Plan
Actual
Plan
Actual
Plan
Actual
Plan
Actual
NonAsciiFileName0.xls 14 of 754 11/21/2012 1:40 AM
Procurement Plan-Goods Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
List of Contracts
Component 4: Project Management & System
Monitoring
Norm Duration of Proc Steps
Supply and Installation of Air Quality Equipment in Eleven
Monitoring Stations on LAMATA BRT Corridors including
Training, Laboratory Analysis, Installation of one Control
Centre and one Ambient Control Centre and a back-up
Procurement of IT Stationery/Consumable (4 Lots, to be
procured a lot per quarter)
Design, Supply and Installation of BRT Signal from CMS-
Mile 12-Ikorodu Icluding Design ( Intelligent Transport
Systems) - Phase 1
IT Equipment Purchase Switches and Printers
Implementation of the Recommendation of the Technical
Due Diligence Report on BFS Operations
Component 2:Public Transport and Traffic Management
Procurement of Office Furniture ( Front office desks, Work
stations, Executive swivel chairs, Board room furniture set,
Janitor shelf etc…
Prep & Submission
by Ex Agency
4 - 7 wks
17-Dec-12
N/A
2-May-12
N/A
N/A
N/A
Draft Bid Documents, including specs and
quantities, draft SPN
NonAsciiFileName0.xls 15 of 754 11/21/2012 1:40 AM
Procurement Plan-Goods
Total Cost
Fill gray cells only!
NOTE: Line 30 -Procurement of IT
Equipment procurement proces has been
scheduled to commence in October to coicide
with resumption of staff to be recruited for the
construction of Mile 12 to Ikorodu BRT
scheme
Nn
Purchase and installation of Corel Draw and Video editing
software for external relation
Procurement of IT Equipment (Servers Laptops PC's and
UPS
Procurement of IT Stationery/Consumable (4 Lots, to be
procured a lot per quarter)
Procurement of Fire Proof Cabinet
Procurement of Operational Vehicles (One four Wheel and
10 Saloon Cars)
Procurement of Ofice Equipment (2HP Split Air
Conditioners (5, Water Dispenser, Refrigerators)
N/A
N/A
N/A
N/A
N/A
NonAsciiFileName0.xls 16 of 754 11/21/2012 1:40 AM
Procurement Plan-Goods Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
List of Contracts
Component 4: Project Management & System
Monitoring
Norm Duration of Proc Steps
Supply and Installation of Air Quality Equipment in Eleven
Monitoring Stations on LAMATA BRT Corridors including
Training, Laboratory Analysis, Installation of one Control
Centre and one Ambient Control Centre and a back-up
Procurement of IT Stationery/Consumable (4 Lots, to be
procured a lot per quarter)
Design, Supply and Installation of BRT Signal from CMS-
Mile 12-Ikorodu Icluding Design ( Intelligent Transport
Systems) - Phase 1
IT Equipment Purchase Switches and Printers
Implementation of the Recommendation of the Technical
Due Diligence Report on BFS Operations
Component 2:Public Transport and Traffic Management
Procurement of Office Furniture ( Front office desks, Work
stations, Executive swivel chairs, Board room furniture set,
Janitor shelf etc…
No-objection
Date
1 - 1.5 wks
31-Dec-12
N/A
16-May-12
N/A
N/A
N/A
Draft Bid Documents, including specs and
quantities, draft SPN
NonAsciiFileName0.xls 17 of 754 11/21/2012 1:40 AM
Procurement Plan-Goods
Total Cost
Fill gray cells only!
NOTE: Line 30 -Procurement of IT
Equipment procurement proces has been
scheduled to commence in October to coicide
with resumption of staff to be recruited for the
construction of Mile 12 to Ikorodu BRT
scheme
Nn
Purchase and installation of Corel Draw and Video editing
software for external relation
Procurement of IT Equipment (Servers Laptops PC's and
UPS
Procurement of IT Stationery/Consumable (4 Lots, to be
procured a lot per quarter)
Procurement of Fire Proof Cabinet
Procurement of Operational Vehicles (One four Wheel and
10 Saloon Cars)
Procurement of Ofice Equipment (2HP Split Air
Conditioners (5, Water Dispenser, Refrigerators)
N/A
N/A
N/A
N/A
N/A
NonAsciiFileName0.xls 18 of 754 11/21/2012 1:40 AM
Procurement Plan-Goods Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
List of Contracts
Component 4: Project Management & System
Monitoring
Norm Duration of Proc Steps
Supply and Installation of Air Quality Equipment in Eleven
Monitoring Stations on LAMATA BRT Corridors including
Training, Laboratory Analysis, Installation of one Control
Centre and one Ambient Control Centre and a back-up
Procurement of IT Stationery/Consumable (4 Lots, to be
procured a lot per quarter)
Design, Supply and Installation of BRT Signal from CMS-
Mile 12-Ikorodu Icluding Design ( Intelligent Transport
Systems) - Phase 1
IT Equipment Purchase Switches and Printers
Implementation of the Recommendation of the Technical
Due Diligence Report on BFS Operations
Component 2:Public Transport and Traffic Management
Procurement of Office Furniture ( Front office desks, Work
stations, Executive swivel chairs, Board room furniture set,
Janitor shelf etc…
If Post-Review, No-objection Dates are not needed
Spec Proc Notice
Advert
On-line UNDB
Gateway
Nat Press
1.5 - 2 wks
4-Jan-13
2-Nov-12
20-May-12
29-Feb-12
N/A
N/A
NonAsciiFileName0.xls 19 of 754 11/21/2012 1:40 AM
Procurement Plan-Goods
Total Cost
Fill gray cells only!
NOTE: Line 30 -Procurement of IT
Equipment procurement proces has been
scheduled to commence in October to coicide
with resumption of staff to be recruited for the
construction of Mile 12 to Ikorodu BRT
scheme
Nn
Purchase and installation of Corel Draw and Video editing
software for external relation
Procurement of IT Equipment (Servers Laptops PC's and
UPS
Procurement of IT Stationery/Consumable (4 Lots, to be
procured a lot per quarter)
Procurement of Fire Proof Cabinet
Procurement of Operational Vehicles (One four Wheel and
10 Saloon Cars)
Procurement of Ofice Equipment (2HP Split Air
Conditioners (5, Water Dispenser, Refrigerators)
N/A
N/A
N/A
N/A
29-Feb-12
NonAsciiFileName0.xls 20 of 754 11/21/2012 1:40 AM
Procurement Plan-Goods Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
List of Contracts
Component 4: Project Management & System
Monitoring
Norm Duration of Proc Steps
Supply and Installation of Air Quality Equipment in Eleven
Monitoring Stations on LAMATA BRT Corridors including
Training, Laboratory Analysis, Installation of one Control
Centre and one Ambient Control Centre and a back-up
Procurement of IT Stationery/Consumable (4 Lots, to be
procured a lot per quarter)
Design, Supply and Installation of BRT Signal from CMS-
Mile 12-Ikorodu Icluding Design ( Intelligent Transport
Systems) - Phase 1
IT Equipment Purchase Switches and Printers
Implementation of the Recommendation of the Technical
Due Diligence Report on BFS Operations
Component 2:Public Transport and Traffic Management
Procurement of Office Furniture ( Front office desks, Work
stations, Executive swivel chairs, Board room furniture set,
Janitor shelf etc…
If Post-Review, No-objection Dates are not needed
Bid Invitation Date
6 to
4-Jan-13
2-Nov-12
20-May-12
29-Feb-12
1-Mar-12
1-Mar-12
Bidding Period
NonAsciiFileName0.xls 21 of 754 11/21/2012 1:40 AM
Procurement Plan-Goods
Total Cost
Fill gray cells only!
NOTE: Line 30 -Procurement of IT
Equipment procurement proces has been
scheduled to commence in October to coicide
with resumption of staff to be recruited for the
construction of Mile 12 to Ikorodu BRT
scheme
Nn
Purchase and installation of Corel Draw and Video editing
software for external relation
Procurement of IT Equipment (Servers Laptops PC's and
UPS
Procurement of IT Stationery/Consumable (4 Lots, to be
procured a lot per quarter)
Procurement of Fire Proof Cabinet
Procurement of Operational Vehicles (One four Wheel and
10 Saloon Cars)
Procurement of Ofice Equipment (2HP Split Air
Conditioners (5, Water Dispenser, Refrigerators)
7-Mar-12
8-Oct-12
5-Mar-12
8-Mar-12
29-Feb-12
NonAsciiFileName0.xls 22 of 754 11/21/2012 1:40 AM
Procurement Plan-Goods Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
List of Contracts
Component 4: Project Management & System
Monitoring
Norm Duration of Proc Steps
Supply and Installation of Air Quality Equipment in Eleven
Monitoring Stations on LAMATA BRT Corridors including
Training, Laboratory Analysis, Installation of one Control
Centre and one Ambient Control Centre and a back-up
Procurement of IT Stationery/Consumable (4 Lots, to be
procured a lot per quarter)
Design, Supply and Installation of BRT Signal from CMS-
Mile 12-Ikorodu Icluding Design ( Intelligent Transport
Systems) - Phase 1
IT Equipment Purchase Switches and Printers
Implementation of the Recommendation of the Technical
Due Diligence Report on BFS Operations
Component 2:Public Transport and Traffic Management
Procurement of Office Furniture ( Front office desks, Work
stations, Executive swivel chairs, Board room furniture set,
Janitor shelf etc…
Bid Closing-Opening
12 wks
18-Feb-13
3-Dec-12
19-Jun-12
30-Mar-12
15-Mar-12
15-Mar-12
Bidding Period
NonAsciiFileName0.xls 23 of 754 11/21/2012 1:40 AM
Procurement Plan-Goods
Total Cost
Fill gray cells only!
NOTE: Line 30 -Procurement of IT
Equipment procurement proces has been
scheduled to commence in October to coicide
with resumption of staff to be recruited for the
construction of Mile 12 to Ikorodu BRT
scheme
Nn
Purchase and installation of Corel Draw and Video editing
software for external relation
Procurement of IT Equipment (Servers Laptops PC's and
UPS
Procurement of IT Stationery/Consumable (4 Lots, to be
procured a lot per quarter)
Procurement of Fire Proof Cabinet
Procurement of Operational Vehicles (One four Wheel and
10 Saloon Cars)
Procurement of Ofice Equipment (2HP Split Air
Conditioners (5, Water Dispenser, Refrigerators)
21-Mar-12
22-Oct-12
19-Mar-12
22-Mar-12
30-Mar-12
NonAsciiFileName0.xls 24 of 754 11/21/2012 1:40 AM
Procurement Plan-Goods Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
List of Contracts
Component 4: Project Management & System
Monitoring
Norm Duration of Proc Steps
Supply and Installation of Air Quality Equipment in Eleven
Monitoring Stations on LAMATA BRT Corridors including
Training, Laboratory Analysis, Installation of one Control
Centre and one Ambient Control Centre and a back-up
Procurement of IT Stationery/Consumable (4 Lots, to be
procured a lot per quarter)
Design, Supply and Installation of BRT Signal from CMS-
Mile 12-Ikorodu Icluding Design ( Intelligent Transport
Systems) - Phase 1
IT Equipment Purchase Switches and Printers
Implementation of the Recommendation of the Technical
Due Diligence Report on BFS Operations
Component 2:Public Transport and Traffic Management
Procurement of Office Furniture ( Front office desks, Work
stations, Executive swivel chairs, Board room furniture set,
Janitor shelf etc…
Submission
Bid Eval Rpt
1.5 - 3 wks
4-Mar-13
N/A
7-Jul-12
N/A
N/A
N/A
Bid Evaluation
NonAsciiFileName0.xls 25 of 754 11/21/2012 1:40 AM
Procurement Plan-Goods
Total Cost
Fill gray cells only!
NOTE: Line 30 -Procurement of IT
Equipment procurement proces has been
scheduled to commence in October to coicide
with resumption of staff to be recruited for the
construction of Mile 12 to Ikorodu BRT
scheme
Nn
Purchase and installation of Corel Draw and Video editing
software for external relation
Procurement of IT Equipment (Servers Laptops PC's and
UPS
Procurement of IT Stationery/Consumable (4 Lots, to be
procured a lot per quarter)
Procurement of Fire Proof Cabinet
Procurement of Operational Vehicles (One four Wheel and
10 Saloon Cars)
Procurement of Ofice Equipment (2HP Split Air
Conditioners (5, Water Dispenser, Refrigerators)
N/A
N/A
N/A
N/A
N/A
NonAsciiFileName0.xls 26 of 754 11/21/2012 1:40 AM
Procurement Plan-Goods Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
List of Contracts
Component 4: Project Management & System
Monitoring
Norm Duration of Proc Steps
Supply and Installation of Air Quality Equipment in Eleven
Monitoring Stations on LAMATA BRT Corridors including
Training, Laboratory Analysis, Installation of one Control
Centre and one Ambient Control Centre and a back-up
Procurement of IT Stationery/Consumable (4 Lots, to be
procured a lot per quarter)
Design, Supply and Installation of BRT Signal from CMS-
Mile 12-Ikorodu Icluding Design ( Intelligent Transport
Systems) - Phase 1
IT Equipment Purchase Switches and Printers
Implementation of the Recommendation of the Technical
Due Diligence Report on BFS Operations
Component 2:Public Transport and Traffic Management
Procurement of Office Furniture ( Front office desks, Work
stations, Executive swivel chairs, Board room furniture set,
Janitor shelf etc…
No-objection
Date
1 - 1.5 wks
18-Mar-13
N/A
22-Jul-12
N/A
N/A
N/A
Bid Evaluation
NonAsciiFileName0.xls 27 of 754 11/21/2012 1:40 AM
Procurement Plan-Goods
Total Cost
Fill gray cells only!
NOTE: Line 30 -Procurement of IT
Equipment procurement proces has been
scheduled to commence in October to coicide
with resumption of staff to be recruited for the
construction of Mile 12 to Ikorodu BRT
scheme
Nn
Purchase and installation of Corel Draw and Video editing
software for external relation
Procurement of IT Equipment (Servers Laptops PC's and
UPS
Procurement of IT Stationery/Consumable (4 Lots, to be
procured a lot per quarter)
Procurement of Fire Proof Cabinet
Procurement of Operational Vehicles (One four Wheel and
10 Saloon Cars)
Procurement of Ofice Equipment (2HP Split Air
Conditioners (5, Water Dispenser, Refrigerators)
N/A
N/A
N/A
N/A
N/A
NonAsciiFileName0.xls 28 of 754 11/21/2012 1:40 AM
Procurement Plan-Goods Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
List of Contracts
Component 4: Project Management & System
Monitoring
Norm Duration of Proc Steps
Supply and Installation of Air Quality Equipment in Eleven
Monitoring Stations on LAMATA BRT Corridors including
Training, Laboratory Analysis, Installation of one Control
Centre and one Ambient Control Centre and a back-up
Procurement of IT Stationery/Consumable (4 Lots, to be
procured a lot per quarter)
Design, Supply and Installation of BRT Signal from CMS-
Mile 12-Ikorodu Icluding Design ( Intelligent Transport
Systems) - Phase 1
IT Equipment Purchase Switches and Printers
Implementation of the Recommendation of the Technical
Due Diligence Report on BFS Operations
Component 2:Public Transport and Traffic Management
Procurement of Office Furniture ( Front office desks, Work
stations, Executive swivel chairs, Board room furniture set,
Janitor shelf etc…
Plan vs.
Actual
Plan
Actual
Plan
Actual
Plan
Actual
Plan
Plan
Actual
Plan
Actual
Plan
NonAsciiFileName0.xls 29 of 754 11/21/2012 1:40 AM
Procurement Plan-Goods
Total Cost
Fill gray cells only!
NOTE: Line 30 -Procurement of IT
Equipment procurement proces has been
scheduled to commence in October to coicide
with resumption of staff to be recruited for the
construction of Mile 12 to Ikorodu BRT
scheme
Nn
Purchase and installation of Corel Draw and Video editing
software for external relation
Procurement of IT Equipment (Servers Laptops PC's and
UPS
Procurement of IT Stationery/Consumable (4 Lots, to be
procured a lot per quarter)
Procurement of Fire Proof Cabinet
Procurement of Operational Vehicles (One four Wheel and
10 Saloon Cars)
Procurement of Ofice Equipment (2HP Split Air
Conditioners (5, Water Dispenser, Refrigerators)
Actual
Plan
Actual
Plan
Actual
Plan
Actual
Plan
Actual
Plan
Actual
NonAsciiFileName0.xls 30 of 754 11/21/2012 1:40 AM
Procurement Plan-Goods Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
List of Contracts
Component 4: Project Management & System
Monitoring
Norm Duration of Proc Steps
Supply and Installation of Air Quality Equipment in Eleven
Monitoring Stations on LAMATA BRT Corridors including
Training, Laboratory Analysis, Installation of one Control
Centre and one Ambient Control Centre and a back-up
Procurement of IT Stationery/Consumable (4 Lots, to be
procured a lot per quarter)
Design, Supply and Installation of BRT Signal from CMS-
Mile 12-Ikorodu Icluding Design ( Intelligent Transport
Systems) - Phase 1
IT Equipment Purchase Switches and Printers
Implementation of the Recommendation of the Technical
Due Diligence Report on BFS Operations
Component 2:Public Transport and Traffic Management
Procurement of Office Furniture ( Front office desks, Work
stations, Executive swivel chairs, Board room furniture set,
Janitor shelf etc…
Date
Contract
Award
1 wk
25-Mar-13
24-Dec-12
29-Jul-12
20-Apr-12
22-Mar-12
22-Mar-12
NonAsciiFileName0.xls 31 of 754 11/21/2012 1:40 AM
Procurement Plan-Goods
Total Cost
Fill gray cells only!
NOTE: Line 30 -Procurement of IT
Equipment procurement proces has been
scheduled to commence in October to coicide
with resumption of staff to be recruited for the
construction of Mile 12 to Ikorodu BRT
scheme
Nn
Purchase and installation of Corel Draw and Video editing
software for external relation
Procurement of IT Equipment (Servers Laptops PC's and
UPS
Procurement of IT Stationery/Consumable (4 Lots, to be
procured a lot per quarter)
Procurement of Fire Proof Cabinet
Procurement of Operational Vehicles (One four Wheel and
10 Saloon Cars)
Procurement of Ofice Equipment (2HP Split Air
Conditioners (5, Water Dispenser, Refrigerators)
28-Mar-12
29-Oct-12
26-Mar-12
29-Mar-12
20-Apr-12
NonAsciiFileName0.xls 32 of 754 11/21/2012 1:40 AM
Procurement Plan-Goods Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
List of Contracts
Component 4: Project Management & System
Monitoring
Norm Duration of Proc Steps
Supply and Installation of Air Quality Equipment in Eleven
Monitoring Stations on LAMATA BRT Corridors including
Training, Laboratory Analysis, Installation of one Control
Centre and one Ambient Control Centre and a back-up
Procurement of IT Stationery/Consumable (4 Lots, to be
procured a lot per quarter)
Design, Supply and Installation of BRT Signal from CMS-
Mile 12-Ikorodu Icluding Design ( Intelligent Transport
Systems) - Phase 1
IT Equipment Purchase Switches and Printers
Implementation of the Recommendation of the Technical
Due Diligence Report on BFS Operations
Component 2:Public Transport and Traffic Management
Procurement of Office Furniture ( Front office desks, Work
stations, Executive swivel chairs, Board room furniture set,
Janitor shelf etc…
Date
Contract
Advert
1-Apr-13
31-Dec-12
5-Aug-12
27-Apr-12
N/A
N/A
NonAsciiFileName0.xls 33 of 754 11/21/2012 1:40 AM
Procurement Plan-Goods
Total Cost
Fill gray cells only!
NOTE: Line 30 -Procurement of IT
Equipment procurement proces has been
scheduled to commence in October to coicide
with resumption of staff to be recruited for the
construction of Mile 12 to Ikorodu BRT
scheme
Nn
Purchase and installation of Corel Draw and Video editing
software for external relation
Procurement of IT Equipment (Servers Laptops PC's and
UPS
Procurement of IT Stationery/Consumable (4 Lots, to be
procured a lot per quarter)
Procurement of Fire Proof Cabinet
Procurement of Operational Vehicles (One four Wheel and
10 Saloon Cars)
Procurement of Ofice Equipment (2HP Split Air
Conditioners (5, Water Dispenser, Refrigerators)
N/A
N/A
N/A
N/A
27-Apr-12
NonAsciiFileName0.xls 34 of 754 11/21/2012 1:40 AM
Procurement Plan-Goods Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
List of Contracts
Component 4: Project Management & System
Monitoring
Norm Duration of Proc Steps
Supply and Installation of Air Quality Equipment in Eleven
Monitoring Stations on LAMATA BRT Corridors including
Training, Laboratory Analysis, Installation of one Control
Centre and one Ambient Control Centre and a back-up
Procurement of IT Stationery/Consumable (4 Lots, to be
procured a lot per quarter)
Design, Supply and Installation of BRT Signal from CMS-
Mile 12-Ikorodu Icluding Design ( Intelligent Transport
Systems) - Phase 1
IT Equipment Purchase Switches and Printers
Implementation of the Recommendation of the Technical
Due Diligence Report on BFS Operations
Component 2:Public Transport and Traffic Management
Procurement of Office Furniture ( Front office desks, Work
stations, Executive swivel chairs, Board room furniture set,
Janitor shelf etc…
Date
Contract
Signature
1.5-3 wks
1-Apr-13
31-Dec-12
20-Aug-12
27-Apr-12
29-Mar-12
29-Mar-12
NonAsciiFileName0.xls 35 of 754 11/21/2012 1:40 AM
Procurement Plan-Goods
Total Cost
Fill gray cells only!
NOTE: Line 30 -Procurement of IT
Equipment procurement proces has been
scheduled to commence in October to coicide
with resumption of staff to be recruited for the
construction of Mile 12 to Ikorodu BRT
scheme
Nn
Purchase and installation of Corel Draw and Video editing
software for external relation
Procurement of IT Equipment (Servers Laptops PC's and
UPS
Procurement of IT Stationery/Consumable (4 Lots, to be
procured a lot per quarter)
Procurement of Fire Proof Cabinet
Procurement of Operational Vehicles (One four Wheel and
10 Saloon Cars)
Procurement of Ofice Equipment (2HP Split Air
Conditioners (5, Water Dispenser, Refrigerators)
4-Apr-12
5-Nov-12
2-Apr-12
5-Apr-12
27-Apr-12
NonAsciiFileName0.xls 36 of 754 11/21/2012 1:40 AM
Procurement Plan-Goods Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
List of Contracts
Component 4: Project Management & System
Monitoring
Norm Duration of Proc Steps
Supply and Installation of Air Quality Equipment in Eleven
Monitoring Stations on LAMATA BRT Corridors including
Training, Laboratory Analysis, Installation of one Control
Centre and one Ambient Control Centre and a back-up
Procurement of IT Stationery/Consumable (4 Lots, to be
procured a lot per quarter)
Design, Supply and Installation of BRT Signal from CMS-
Mile 12-Ikorodu Icluding Design ( Intelligent Transport
Systems) - Phase 1
IT Equipment Purchase Switches and Printers
Implementation of the Recommendation of the Technical
Due Diligence Report on BFS Operations
Component 2:Public Transport and Traffic Management
Procurement of Office Furniture ( Front office desks, Work
stations, Executive swivel chairs, Board room furniture set,
Janitor shelf etc…
NonAsciiFileName0.xls 37 of 754 11/21/2012 1:40 AM
Procurement Plan-Goods
Total Cost
Fill gray cells only!
NOTE: Line 30 -Procurement of IT
Equipment procurement proces has been
scheduled to commence in October to coicide
with resumption of staff to be recruited for the
construction of Mile 12 to Ikorodu BRT
scheme
Nn
Purchase and installation of Corel Draw and Video editing
software for external relation
Procurement of IT Equipment (Servers Laptops PC's and
UPS
Procurement of IT Stationery/Consumable (4 Lots, to be
procured a lot per quarter)
Procurement of Fire Proof Cabinet
Procurement of Operational Vehicles (One four Wheel and
10 Saloon Cars)
Procurement of Ofice Equipment (2HP Split Air
Conditioners (5, Water Dispenser, Refrigerators)
NonAsciiFileName0.xls 38 of 754 11/21/2012 1:40 AM
Procurement Plan-Goods Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
List of Contracts
Component 4: Project Management & System
Monitoring
Norm Duration of Proc Steps
Supply and Installation of Air Quality Equipment in Eleven
Monitoring Stations on LAMATA BRT Corridors including
Training, Laboratory Analysis, Installation of one Control
Centre and one Ambient Control Centre and a back-up
Procurement of IT Stationery/Consumable (4 Lots, to be
procured a lot per quarter)
Design, Supply and Installation of BRT Signal from CMS-
Mile 12-Ikorodu Icluding Design ( Intelligent Transport
Systems) - Phase 1
IT Equipment Purchase Switches and Printers
Implementation of the Recommendation of the Technical
Due Diligence Report on BFS Operations
Component 2:Public Transport and Traffic Management
Procurement of Office Furniture ( Front office desks, Work
stations, Executive swivel chairs, Board room furniture set,
Janitor shelf etc…
Contract Implementation
Opening
of
Let of Credit
8-Apr-13
N/A
N/A
N/A
N/A
N/A
NonAsciiFileName0.xls 39 of 754 11/21/2012 1:40 AM
Procurement Plan-Goods
Total Cost
Fill gray cells only!
NOTE: Line 30 -Procurement of IT
Equipment procurement proces has been
scheduled to commence in October to coicide
with resumption of staff to be recruited for the
construction of Mile 12 to Ikorodu BRT
scheme
Nn
Purchase and installation of Corel Draw and Video editing
software for external relation
Procurement of IT Equipment (Servers Laptops PC's and
UPS
Procurement of IT Stationery/Consumable (4 Lots, to be
procured a lot per quarter)
Procurement of Fire Proof Cabinet
Procurement of Operational Vehicles (One four Wheel and
10 Saloon Cars)
Procurement of Ofice Equipment (2HP Split Air
Conditioners (5, Water Dispenser, Refrigerators)
N/A
N/A
N/A
N/A
N/A
NonAsciiFileName0.xls 40 of 754 11/21/2012 1:40 AM
Procurement Plan-Goods Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
List of Contracts
Component 4: Project Management & System
Monitoring
Norm Duration of Proc Steps
Supply and Installation of Air Quality Equipment in Eleven
Monitoring Stations on LAMATA BRT Corridors including
Training, Laboratory Analysis, Installation of one Control
Centre and one Ambient Control Centre and a back-up
Procurement of IT Stationery/Consumable (4 Lots, to be
procured a lot per quarter)
Design, Supply and Installation of BRT Signal from CMS-
Mile 12-Ikorodu Icluding Design ( Intelligent Transport
Systems) - Phase 1
IT Equipment Purchase Switches and Printers
Implementation of the Recommendation of the Technical
Due Diligence Report on BFS Operations
Component 2:Public Transport and Traffic Management
Procurement of Office Furniture ( Front office desks, Work
stations, Executive swivel chairs, Board room furniture set,
Janitor shelf etc…
Contract Implementation
Arrival
of
Goods
28-Sep-13
31-Mar-13
19-Jan-13
25-May-12
5-Apr-12
5-Apr-12
NonAsciiFileName0.xls 41 of 754 11/21/2012 1:40 AM
Procurement Plan-Goods
Total Cost
Fill gray cells only!
NOTE: Line 30 -Procurement of IT
Equipment procurement proces has been
scheduled to commence in October to coicide
with resumption of staff to be recruited for the
construction of Mile 12 to Ikorodu BRT
scheme
Nn
Purchase and installation of Corel Draw and Video editing
software for external relation
Procurement of IT Equipment (Servers Laptops PC's and
UPS
Procurement of IT Stationery/Consumable (4 Lots, to be
procured a lot per quarter)
Procurement of Fire Proof Cabinet
Procurement of Operational Vehicles (One four Wheel and
10 Saloon Cars)
Procurement of Ofice Equipment (2HP Split Air
Conditioners (5, Water Dispenser, Refrigerators)
11-Apr-12
12-Nov-12
9-Apr-12
12-Apr-12
25-May-12
NonAsciiFileName0.xls 42 of 754 11/21/2012 1:40 AM
Procurement Plan-Goods Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
List of Contracts
Component 4: Project Management & System
Monitoring
Norm Duration of Proc Steps
Supply and Installation of Air Quality Equipment in Eleven
Monitoring Stations on LAMATA BRT Corridors including
Training, Laboratory Analysis, Installation of one Control
Centre and one Ambient Control Centre and a back-up
Procurement of IT Stationery/Consumable (4 Lots, to be
procured a lot per quarter)
Design, Supply and Installation of BRT Signal from CMS-
Mile 12-Ikorodu Icluding Design ( Intelligent Transport
Systems) - Phase 1
IT Equipment Purchase Switches and Printers
Implementation of the Recommendation of the Technical
Due Diligence Report on BFS Operations
Component 2:Public Transport and Traffic Management
Procurement of Office Furniture ( Front office desks, Work
stations, Executive swivel chairs, Board room furniture set,
Janitor shelf etc…
Contract Implementation
Inspection
Final
Acceptance
28-Sep-13
31-Mar-13
18-Feb-13
25-May-12
5-Apr-12
5-Apr-12
NonAsciiFileName0.xls 43 of 754 11/21/2012 1:40 AM
Procurement Plan-Goods
Total Cost
Fill gray cells only!
NOTE: Line 30 -Procurement of IT
Equipment procurement proces has been
scheduled to commence in October to coicide
with resumption of staff to be recruited for the
construction of Mile 12 to Ikorodu BRT
scheme
Nn
Purchase and installation of Corel Draw and Video editing
software for external relation
Procurement of IT Equipment (Servers Laptops PC's and
UPS
Procurement of IT Stationery/Consumable (4 Lots, to be
procured a lot per quarter)
Procurement of Fire Proof Cabinet
Procurement of Operational Vehicles (One four Wheel and
10 Saloon Cars)
Procurement of Ofice Equipment (2HP Split Air
Conditioners (5, Water Dispenser, Refrigerators)
11-Apr-12
12-Nov-12
9-Apr-12
12-Apr-12
25-May-12
NonAsciiFileName0.xls 44 of 754 11/21/2012 1:40 AM
Procurement Plan-Works Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
Component 1:(Instititional Development)
List of Contracts
Component 2:Public Transport and Traffic Management
Construction of 8 No Bus Shelters including Platforms
Component 3: Improvement of Lagos State Metropolitan
Road Network
Norm Duration of Proc Steps
Construction of Bus Terminal at Mile 12
Construction of Footbridges at 7 locations along the project
corriddor
Construction of BRT Bus Depot at Ikorodu
Construction of Ikorodu and Agric Bus Terminals
Rehabilitation and Upgrading of Wempco Road Ogba
Construction of 7 No Bus Shelters including Platforms
NonAsciiFileName0.xls 45 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
Total Cost
Fill gray cells only!
NonAsciiFileName0.xls 46 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 47 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 48 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 49 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 50 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 51 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 52 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 53 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 54 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 55 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 56 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 57 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 58 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 59 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 60 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 61 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 62 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 63 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 64 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 65 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 66 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 67 of 754 11/21/2012 1:40 AM
Procurement Plan-Works Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*Package
Number
Component 1:(Instititional Development)
List of Contracts
Component 2:Public Transport and Traffic Management
1
1
2
Construction of 8 No Bus Shelters including Platforms 2
1
1
Component 3: Improvement of Lagos State Metropolitan
Road Network
1
Norm Duration of Proc Steps
Construction of Bus Terminal at Mile 12
Construction of Footbridges at 7 locations along the project
corriddor
Construction of BRT Bus Depot at Ikorodu
Construction of Ikorodu and Agric Bus Terminals
Rehabilitation and Upgrading of Wempco Road Ogba
Construction of 7 No Bus Shelters including Platforms
NonAsciiFileName0.xls 68 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
Total Cost
Fill gray cells only!
NonAsciiFileName0.xls 69 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 70 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 71 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 72 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 73 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 74 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 75 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 76 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 77 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 78 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 79 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 80 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 81 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 82 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 83 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 84 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 85 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 86 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 87 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 88 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 89 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 90 of 754 11/21/2012 1:40 AM
Procurement Plan-Works Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
Component 1:(Instititional Development)
List of Contracts
Component 2:Public Transport and Traffic Management
Construction of 8 No Bus Shelters including Platforms
Component 3: Improvement of Lagos State Metropolitan
Road Network
Norm Duration of Proc Steps
Construction of Bus Terminal at Mile 12
Construction of Footbridges at 7 locations along the project
corriddor
Construction of BRT Bus Depot at Ikorodu
Construction of Ikorodu and Agric Bus Terminals
Rehabilitation and Upgrading of Wempco Road Ogba
Construction of 7 No Bus Shelters including Platforms
Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Lot
Number
1
2
1
2
1
1
1
Basic Data
NonAsciiFileName0.xls 91 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
Total Cost
Fill gray cells only!
NonAsciiFileName0.xls 92 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 93 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 94 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 95 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 96 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 97 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 98 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 99 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 100 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 101 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 102 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 103 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 104 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 105 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 106 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 107 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 108 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 109 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 110 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 111 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 112 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 113 of 754 11/21/2012 1:40 AM
Procurement Plan-Works Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
Component 1:(Instititional Development)
List of Contracts
Component 2:Public Transport and Traffic Management
Construction of 8 No Bus Shelters including Platforms
Component 3: Improvement of Lagos State Metropolitan
Road Network
Norm Duration of Proc Steps
Construction of Bus Terminal at Mile 12
Construction of Footbridges at 7 locations along the project
corriddor
Construction of BRT Bus Depot at Ikorodu
Construction of Ikorodu and Agric Bus Terminals
Rehabilitation and Upgrading of Wempco Road Ogba
Construction of 7 No Bus Shelters including Platforms
Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Lumpsum or
Bill of
Quantities
BOQ
BOQ
BOQ
BOQ
BOQ
BOQ
BOQ
Basic Data
NonAsciiFileName0.xls 114 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
Total Cost
Fill gray cells only!
NonAsciiFileName0.xls 115 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 116 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 117 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 118 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 119 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 120 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 121 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 122 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 123 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 124 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 125 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 126 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 127 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 128 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 129 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 130 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 131 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 132 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 133 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 134 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 135 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 136 of 754 11/21/2012 1:40 AM
Procurement Plan-Works Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
Component 1:(Instititional Development)
List of Contracts
Component 2:Public Transport and Traffic Management
Construction of 8 No Bus Shelters including Platforms
Component 3: Improvement of Lagos State Metropolitan
Road Network
Norm Duration of Proc Steps
Construction of Bus Terminal at Mile 12
Construction of Footbridges at 7 locations along the project
corriddor
Construction of BRT Bus Depot at Ikorodu
Construction of Ikorodu and Agric Bus Terminals
Rehabilitation and Upgrading of Wempco Road Ogba
Construction of 7 No Bus Shelters including Platforms
Procurement
Method
ICB
ICB
ICB
ICB
ICB
ICB
ICB
Basic Data
NonAsciiFileName0.xls 137 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
Total Cost
Fill gray cells only!
NonAsciiFileName0.xls 138 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 139 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 140 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 141 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 142 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 143 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 144 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 145 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 146 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 147 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 148 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 149 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 150 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 151 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 152 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 153 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 154 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 155 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 156 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 157 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 158 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 159 of 754 11/21/2012 1:40 AM
Procurement Plan-Works Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
Component 1:(Instititional Development)
List of Contracts
Component 2:Public Transport and Traffic Management
Construction of 8 No Bus Shelters including Platforms
Component 3: Improvement of Lagos State Metropolitan
Road Network
Norm Duration of Proc Steps
Construction of Bus Terminal at Mile 12
Construction of Footbridges at 7 locations along the project
corriddor
Construction of BRT Bus Depot at Ikorodu
Construction of Ikorodu and Agric Bus Terminals
Rehabilitation and Upgrading of Wempco Road Ogba
Construction of 7 No Bus Shelters including Platforms
Pre-or Post
Qualification
If Prequalification
add 7-13 wks
Post Qualification
Post Qualification
Post Qualification
Post Qualification
Post Qualification
Post Qualification
Post Qualification
Basic Data
NonAsciiFileName0.xls 160 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
Total Cost
Fill gray cells only!
NonAsciiFileName0.xls 161 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 162 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 163 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 164 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 165 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 166 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 167 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 168 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 169 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 170 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 171 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 172 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 173 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 174 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 175 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 176 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 177 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 178 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 179 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 180 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 181 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 182 of 754 11/21/2012 1:40 AM
Procurement Plan-Works Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
Component 1:(Instititional Development)
List of Contracts
Component 2:Public Transport and Traffic Management
Construction of 8 No Bus Shelters including Platforms
Component 3: Improvement of Lagos State Metropolitan
Road Network
Norm Duration of Proc Steps
Construction of Bus Terminal at Mile 12
Construction of Footbridges at 7 locations along the project
corriddor
Construction of BRT Bus Depot at Ikorodu
Construction of Ikorodu and Agric Bus Terminals
Rehabilitation and Upgrading of Wempco Road Ogba
Construction of 7 No Bus Shelters including Platforms
Prior or Post
Review
Prior Review
Post Review
Post Review
Post Review
Prior Review
Prior Review
Prior Review
Basic Data
NonAsciiFileName0.xls 183 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
Total Cost
Fill gray cells only!
NonAsciiFileName0.xls 184 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 185 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 186 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 187 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 188 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 189 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 190 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 191 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 192 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 193 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 194 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 195 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 196 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 197 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 198 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 199 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 200 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 201 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 202 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 203 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 204 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 205 of 754 11/21/2012 1:40 AM
Procurement Plan-Works Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
Component 1:(Instititional Development)
List of Contracts
Component 2:Public Transport and Traffic Management
Construction of 8 No Bus Shelters including Platforms
Component 3: Improvement of Lagos State Metropolitan
Road Network
Norm Duration of Proc Steps
Construction of Bus Terminal at Mile 12
Construction of Footbridges at 7 locations along the project
corriddor
Construction of BRT Bus Depot at Ikorodu
Construction of Ikorodu and Agric Bus Terminals
Rehabilitation and Upgrading of Wempco Road Ogba
Construction of 7 No Bus Shelters including Platforms
Plan
vs.
Actual
Plan
Actual
Plan
Plan
Actual
Plan
Plan
Plan
Actual
Plan
Plan
NonAsciiFileName0.xls 206 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
Total Cost
Fill gray cells only!
NonAsciiFileName0.xls 207 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 208 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 209 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 210 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 211 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 212 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 213 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 214 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 215 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 216 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 217 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 218 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 219 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 220 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 221 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 222 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 223 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 224 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 225 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 226 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 227 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 228 of 754 11/21/2012 1:40 AM
Procurement Plan-Works Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
Component 1:(Instititional Development)
List of Contracts
Component 2:Public Transport and Traffic Management
Construction of 8 No Bus Shelters including Platforms
Component 3: Improvement of Lagos State Metropolitan
Road Network
Norm Duration of Proc Steps
Construction of Bus Terminal at Mile 12
Construction of Footbridges at 7 locations along the project
corriddor
Construction of BRT Bus Depot at Ikorodu
Construction of Ikorodu and Agric Bus Terminals
Rehabilitation and Upgrading of Wempco Road Ogba
Construction of 7 No Bus Shelters including Platforms
Prep &
Submission
by Ex Agency
4 - 7 wks
30-Nov-12
30-Nov-12
30-Nov-12
30-Nov-12
25-Feb-13
25-Feb-13
17-Dec-12
Draft Bid Documents, including specs
and quantities, draft SPN
NonAsciiFileName0.xls 229 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
Total Cost
Fill gray cells only!
NonAsciiFileName0.xls 230 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 231 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 232 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 233 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 234 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 235 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 236 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 237 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 238 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 239 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 240 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 241 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 242 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 243 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 244 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 245 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 246 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 247 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 248 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 249 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 250 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 251 of 754 11/21/2012 1:40 AM
Procurement Plan-Works Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
Component 1:(Instititional Development)
List of Contracts
Component 2:Public Transport and Traffic Management
Construction of 8 No Bus Shelters including Platforms
Component 3: Improvement of Lagos State Metropolitan
Road Network
Norm Duration of Proc Steps
Construction of Bus Terminal at Mile 12
Construction of Footbridges at 7 locations along the project
corriddor
Construction of BRT Bus Depot at Ikorodu
Construction of Ikorodu and Agric Bus Terminals
Rehabilitation and Upgrading of Wempco Road Ogba
Construction of 7 No Bus Shelters including Platforms
No-objection
Date
1 - 1.5 wks
14-Dec-12
14-Dec-12
14-Dec-12
14-Dec-12
11-Mar-13
11-Mar-13
31-Dec-12
Draft Bid Documents, including specs
and quantities, draft SPN
NonAsciiFileName0.xls 252 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
Total Cost
Fill gray cells only!
NonAsciiFileName0.xls 253 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 254 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 255 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 256 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 257 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 258 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 259 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 260 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 261 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 262 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 263 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 264 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 265 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 266 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 267 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 268 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 269 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 270 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 271 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 272 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 273 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 274 of 754 11/21/2012 1:40 AM
Procurement Plan-Works Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
Component 1:(Instititional Development)
List of Contracts
Component 2:Public Transport and Traffic Management
Construction of 8 No Bus Shelters including Platforms
Component 3: Improvement of Lagos State Metropolitan
Road Network
Norm Duration of Proc Steps
Construction of Bus Terminal at Mile 12
Construction of Footbridges at 7 locations along the project
corriddor
Construction of BRT Bus Depot at Ikorodu
Construction of Ikorodu and Agric Bus Terminals
Rehabilitation and Upgrading of Wempco Road Ogba
Construction of 7 No Bus Shelters including Platforms
If Post-Review, No-objection Dates are not needed
Spec Proc Notice
Advert
On-line UNDB
Gateway
Nat Press
1.5 - 2 wks
18-Dec-12
18-Dec-12
18-Dec-12
18-Dec-12
16-Mar-13
15-Mar-13
5-Jan-13
NonAsciiFileName0.xls 275 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
Total Cost
Fill gray cells only!
NonAsciiFileName0.xls 276 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 277 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 278 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 279 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 280 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 281 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 282 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 283 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 284 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 285 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 286 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 287 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 288 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 289 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 290 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 291 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 292 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 293 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 294 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 295 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 296 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 297 of 754 11/21/2012 1:40 AM
Procurement Plan-Works Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
Component 1:(Instititional Development)
List of Contracts
Component 2:Public Transport and Traffic Management
Construction of 8 No Bus Shelters including Platforms
Component 3: Improvement of Lagos State Metropolitan
Road Network
Norm Duration of Proc Steps
Construction of Bus Terminal at Mile 12
Construction of Footbridges at 7 locations along the project
corriddor
Construction of BRT Bus Depot at Ikorodu
Construction of Ikorodu and Agric Bus Terminals
Rehabilitation and Upgrading of Wempco Road Ogba
Construction of 7 No Bus Shelters including Platforms
If Post-Review, No-objection Dates are not needed
Bid Invitation
Date
1.5 - 2 wks
18-Dec-12
18-Dec-12
18-Dec-12
18-Dec-12
16-Mar-13
15-Mar-13
5-Jan-13
Bidding Period
NonAsciiFileName0.xls 298 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
Total Cost
Fill gray cells only!
NonAsciiFileName0.xls 299 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 300 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 301 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 302 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 303 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 304 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 305 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 306 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 307 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 308 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 309 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 310 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 311 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 312 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 313 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 314 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 315 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 316 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 317 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 318 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 319 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 320 of 754 11/21/2012 1:40 AM
Procurement Plan-Works Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
Component 1:(Instititional Development)
List of Contracts
Component 2:Public Transport and Traffic Management
Construction of 8 No Bus Shelters including Platforms
Component 3: Improvement of Lagos State Metropolitan
Road Network
Norm Duration of Proc Steps
Construction of Bus Terminal at Mile 12
Construction of Footbridges at 7 locations along the project
corriddor
Construction of BRT Bus Depot at Ikorodu
Construction of Ikorodu and Agric Bus Terminals
Rehabilitation and Upgrading of Wempco Road Ogba
Construction of 7 No Bus Shelters including Platforms
Bid Closing-
Opening
6 to
31-Jan-13
31-Jan-13
31-Jan-13
31-Jan-13
28-Apr-13
7-May-13
6-Feb-13
Bidding Period
NonAsciiFileName0.xls 321 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
Total Cost
Fill gray cells only!
NonAsciiFileName0.xls 322 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 323 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 324 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 325 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 326 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 327 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 328 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 329 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 330 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 331 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 332 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 333 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 334 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 335 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 336 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 337 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 338 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 339 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 340 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 341 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 342 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 343 of 754 11/21/2012 1:40 AM
Procurement Plan-Works Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
Component 1:(Instititional Development)
List of Contracts
Component 2:Public Transport and Traffic Management
Construction of 8 No Bus Shelters including Platforms
Component 3: Improvement of Lagos State Metropolitan
Road Network
Norm Duration of Proc Steps
Construction of Bus Terminal at Mile 12
Construction of Footbridges at 7 locations along the project
corriddor
Construction of BRT Bus Depot at Ikorodu
Construction of Ikorodu and Agric Bus Terminals
Rehabilitation and Upgrading of Wempco Road Ogba
Construction of 7 No Bus Shelters including Platforms
Submission
Bid Eval Rpt
12 wks
14-Feb-13
14-Feb-13
14-Feb-13
14-Feb-13
12-May-13
21-May-13
20-Feb-13
Bid Evaluation
NonAsciiFileName0.xls 344 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
Total Cost
Fill gray cells only!
NonAsciiFileName0.xls 345 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 346 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 347 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 348 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 349 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 350 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 351 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 352 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 353 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 354 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 355 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 356 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 357 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 358 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 359 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 360 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 361 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 362 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 363 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 364 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 365 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 366 of 754 11/21/2012 1:40 AM
Procurement Plan-Works Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
Component 1:(Instititional Development)
List of Contracts
Component 2:Public Transport and Traffic Management
Construction of 8 No Bus Shelters including Platforms
Component 3: Improvement of Lagos State Metropolitan
Road Network
Norm Duration of Proc Steps
Construction of Bus Terminal at Mile 12
Construction of Footbridges at 7 locations along the project
corriddor
Construction of BRT Bus Depot at Ikorodu
Construction of Ikorodu and Agric Bus Terminals
Rehabilitation and Upgrading of Wempco Road Ogba
Construction of 7 No Bus Shelters including Platforms
No-objection
Date
1.5 - 3 wks
28-Feb-13
28-Feb-13
28-Feb-13
28-Feb-13
26-May-13
4-Jun-13
6-Mar-13
Bid Evaluation
NonAsciiFileName0.xls 367 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
Total Cost
Fill gray cells only!
NonAsciiFileName0.xls 368 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 369 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 370 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 371 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 372 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 373 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 374 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 375 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 376 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 377 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 378 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 379 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 380 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 381 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 382 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 383 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 384 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 385 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 386 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 387 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 388 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 389 of 754 11/21/2012 1:40 AM
Procurement Plan-Works Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
Component 1:(Instititional Development)
List of Contracts
Component 2:Public Transport and Traffic Management
Construction of 8 No Bus Shelters including Platforms
Component 3: Improvement of Lagos State Metropolitan
Road Network
Norm Duration of Proc Steps
Construction of Bus Terminal at Mile 12
Construction of Footbridges at 7 locations along the project
corriddor
Construction of BRT Bus Depot at Ikorodu
Construction of Ikorodu and Agric Bus Terminals
Rehabilitation and Upgrading of Wempco Road Ogba
Construction of 7 No Bus Shelters including Platforms
Plan
vs.
Actual
Plan
Actual
Plan
Plan
Actual
Plan
Plan
Actual
Plan
Actual
Plan
Actual
Plan
NonAsciiFileName0.xls 390 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
Total Cost
Fill gray cells only!
NonAsciiFileName0.xls 391 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 392 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 393 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 394 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 395 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 396 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 397 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 398 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 399 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 400 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 401 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 402 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 403 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 404 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 405 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 406 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 407 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 408 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 409 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 410 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 411 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 412 of 754 11/21/2012 1:40 AM
Procurement Plan-Works Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
Component 1:(Instititional Development)
List of Contracts
Component 2:Public Transport and Traffic Management
Construction of 8 No Bus Shelters including Platforms
Component 3: Improvement of Lagos State Metropolitan
Road Network
Norm Duration of Proc Steps
Construction of Bus Terminal at Mile 12
Construction of Footbridges at 7 locations along the project
corriddor
Construction of BRT Bus Depot at Ikorodu
Construction of Ikorodu and Agric Bus Terminals
Rehabilitation and Upgrading of Wempco Road Ogba
Construction of 7 No Bus Shelters including Platforms
Date
Contract
Award
1 wk
7-Mar-13
7-Mar-13
7-Mar-13
7-Mar-13
2-Jun-13
11-Jun-13
13-Mar-13
NonAsciiFileName0.xls 413 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
Total Cost
Fill gray cells only!
NonAsciiFileName0.xls 414 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 415 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 416 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 417 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 418 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 419 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 420 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 421 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 422 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 423 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 424 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 425 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 426 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 427 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 428 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 429 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 430 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 431 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 432 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 433 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 434 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 435 of 754 11/21/2012 1:40 AM
Procurement Plan-Works Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
Component 1:(Instititional Development)
List of Contracts
Component 2:Public Transport and Traffic Management
Construction of 8 No Bus Shelters including Platforms
Component 3: Improvement of Lagos State Metropolitan
Road Network
Norm Duration of Proc Steps
Construction of Bus Terminal at Mile 12
Construction of Footbridges at 7 locations along the project
corriddor
Construction of BRT Bus Depot at Ikorodu
Construction of Ikorodu and Agric Bus Terminals
Rehabilitation and Upgrading of Wempco Road Ogba
Construction of 7 No Bus Shelters including Platforms
Date
Contract
Advert
14-Mar-13
14-Mar-13
14-Mar-13
14-Mar-13
9-Jun-13
18-Jun-13
20-Mar-13
NonAsciiFileName0.xls 436 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
Total Cost
Fill gray cells only!
NonAsciiFileName0.xls 437 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 438 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 439 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 440 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 441 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 442 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 443 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 444 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 445 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 446 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 447 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 448 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 449 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 450 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 451 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 452 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 453 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 454 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 455 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 456 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 457 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 458 of 754 11/21/2012 1:40 AM
Procurement Plan-Works Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
Component 1:(Instititional Development)
List of Contracts
Component 2:Public Transport and Traffic Management
Construction of 8 No Bus Shelters including Platforms
Component 3: Improvement of Lagos State Metropolitan
Road Network
Norm Duration of Proc Steps
Construction of Bus Terminal at Mile 12
Construction of Footbridges at 7 locations along the project
corriddor
Construction of BRT Bus Depot at Ikorodu
Construction of Ikorodu and Agric Bus Terminals
Rehabilitation and Upgrading of Wempco Road Ogba
Construction of 7 No Bus Shelters including Platforms
Date
Contract
Signature
1.5-3 wks
14-Mar-13
14-Mar-13
14-Mar-13
14-Mar-13
9-Jun-13
18-Jun-13
20-Mar-13
NonAsciiFileName0.xls 459 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
Total Cost
Fill gray cells only!
NonAsciiFileName0.xls 460 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 461 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 462 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 463 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 464 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 465 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 466 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 467 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 468 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 469 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 470 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 471 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 472 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 473 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 474 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 475 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 476 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 477 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 478 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 479 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 480 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 481 of 754 11/21/2012 1:40 AM
Procurement Plan-Works Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
Component 1:(Instititional Development)
List of Contracts
Component 2:Public Transport and Traffic Management
Construction of 8 No Bus Shelters including Platforms
Component 3: Improvement of Lagos State Metropolitan
Road Network
Norm Duration of Proc Steps
Construction of Bus Terminal at Mile 12
Construction of Footbridges at 7 locations along the project
corriddor
Construction of BRT Bus Depot at Ikorodu
Construction of Ikorodu and Agric Bus Terminals
Rehabilitation and Upgrading of Wempco Road Ogba
Construction of 7 No Bus Shelters including Platforms
NonAsciiFileName0.xls 482 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
Total Cost
Fill gray cells only!
NonAsciiFileName0.xls 483 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 484 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 485 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 486 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 487 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 488 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 489 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 490 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 491 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 492 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 493 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 494 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 495 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 496 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 497 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 498 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 499 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 500 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 501 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 502 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 503 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 504 of 754 11/21/2012 1:40 AM
Procurement Plan-Works Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
Component 1:(Instititional Development)
List of Contracts
Component 2:Public Transport and Traffic Management
Construction of 8 No Bus Shelters including Platforms
Component 3: Improvement of Lagos State Metropolitan
Road Network
Norm Duration of Proc Steps
Construction of Bus Terminal at Mile 12
Construction of Footbridges at 7 locations along the project
corriddor
Construction of BRT Bus Depot at Ikorodu
Construction of Ikorodu and Agric Bus Terminals
Rehabilitation and Upgrading of Wempco Road Ogba
Construction of 7 No Bus Shelters including Platforms
Mobilization
Advance
Payment
28-Mar-13
28-Mar-13
28-Mar-13
28-Mar-13
23-Jun-13
2-Jul-13
3-Apr-13
Contract Implementation
NonAsciiFileName0.xls 505 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
Total Cost
Fill gray cells only!
NonAsciiFileName0.xls 506 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 507 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 508 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 509 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 510 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 511 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 512 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 513 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 514 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 515 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 516 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 517 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 518 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 519 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 520 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 521 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 522 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 523 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 524 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 525 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 526 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 527 of 754 11/21/2012 1:40 AM
Procurement Plan-Works Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
Component 1:(Instititional Development)
List of Contracts
Component 2:Public Transport and Traffic Management
Construction of 8 No Bus Shelters including Platforms
Component 3: Improvement of Lagos State Metropolitan
Road Network
Norm Duration of Proc Steps
Construction of Bus Terminal at Mile 12
Construction of Footbridges at 7 locations along the project
corriddor
Construction of BRT Bus Depot at Ikorodu
Construction of Ikorodu and Agric Bus Terminals
Rehabilitation and Upgrading of Wempco Road Ogba
Construction of 7 No Bus Shelters including Platforms
Substantial
Completion
21-Jun-14
21-Jun-14
21-Jun-14
21-Jun-14
14-Apr-15
23-Apr-15
27-Jun-14
Contract Implementation
NonAsciiFileName0.xls 528 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
Total Cost
Fill gray cells only!
NonAsciiFileName0.xls 529 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 530 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 531 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 532 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 533 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 534 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 535 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 536 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 537 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 538 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 539 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 540 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 541 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 542 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 543 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 544 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 545 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 546 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 547 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 548 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 549 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 550 of 754 11/21/2012 1:40 AM
Procurement Plan-Works Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
Component 1:(Instititional Development)
List of Contracts
Component 2:Public Transport and Traffic Management
Construction of 8 No Bus Shelters including Platforms
Component 3: Improvement of Lagos State Metropolitan
Road Network
Norm Duration of Proc Steps
Construction of Bus Terminal at Mile 12
Construction of Footbridges at 7 locations along the project
corriddor
Construction of BRT Bus Depot at Ikorodu
Construction of Ikorodu and Agric Bus Terminals
Rehabilitation and Upgrading of Wempco Road Ogba
Construction of 7 No Bus Shelters including Platforms
Final
Acceptance
19-Sep-14
19-Sep-14
19-Sep-14
19-Sep-14
13-Jun-15
22-Jun-15
25-Sep-14
Contract Implementation
NonAsciiFileName0.xls 551 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
Total Cost
Fill gray cells only!
NonAsciiFileName0.xls 552 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 553 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 554 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 555 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 556 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 557 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 558 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 559 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 560 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 561 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 562 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 563 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 564 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 565 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 566 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 567 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 568 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 569 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 570 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 571 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 572 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 573 of 754 11/21/2012 1:40 AM
Procurement Plan-Works Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
Component 1:(Instititional Development)
List of Contracts
Component 2:Public Transport and Traffic Management
Construction of 8 No Bus Shelters including Platforms
Component 3: Improvement of Lagos State Metropolitan
Road Network
Norm Duration of Proc Steps
Construction of Bus Terminal at Mile 12
Construction of Footbridges at 7 locations along the project
corriddor
Construction of BRT Bus Depot at Ikorodu
Construction of Ikorodu and Agric Bus Terminals
Rehabilitation and Upgrading of Wempco Road Ogba
Construction of 7 No Bus Shelters including Platforms
Source of
Funds
IDA
IDA
IDA
IDA
IDA
AFD
IDA
NonAsciiFileName0.xls 574 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
Total Cost
Fill gray cells only!
NonAsciiFileName0.xls 575 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 576 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 577 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 578 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 579 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 580 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 581 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 582 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 583 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 584 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 585 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 586 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 587 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 588 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 589 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 590 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 591 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 592 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 593 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 594 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 595 of 754 11/21/2012 1:40 AM
Procurement Plan-Works
NonAsciiFileName0.xls 596 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2 Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)For Contracts under projects approved before the May 2002 Guidelines
Project/Programme: Lagos Urban Transport Project (LUTP)If Post-Review, No-objection Dates are not needed
IDA Credit No.: 3721-0 UNI
Description*Selection
Method
Norm Duration of Proc Steps
Component 1:(Instititional Development)
Training of Staff and Twining programme (To be
Implemented through global Training plan and
Twining arrangement for (January 2012 to Dec
2012)
CQS
QCBS
CQS
CQS
CQS
Component 2:Public Transport and Traffic Management
Consultancy Services for Carrying out the Pre and
Post Study for the Establishment of Transport
Planning Units in Lagos Island, Kosofe and
Ikorodu LGAs in Lagos State
Consultancy Services for Detailed Engineering
Design and Construction Supervision of BRT LITE
Upgrade from Mile 12 to CMS
Consultancy Services for Conceptual Design of
BRT LITE Upgrade from Mile 12 to CMS
Consultancy Services for Engineering Design and
Construction Supervision of BFS Infrastructure
Rehabilitation and Upgrading
Consultancy Services for conducting Technical due
diligence on BFS Buses (Environmental
Enhancement of BFS Operations: Due Diligence
Report) Including Supervision of the
Refurbishment of BFS Buses
NonAsciiFileName0.xls 597 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2 SS
QCBS
CQS
CQS
CQS
CQS
Component 3: Improvement of Lagos State
Metropolitan Road Network
QCBS
QCBS
CQS
CQS
QCBS
Component 4: Project Management & System Monitoring
CQS
CQS
Consultancy for Construction Supervision of Akin
Adesola and Wempco Roads
Consultancy Services for Design Upgrade and
Construction Supervision of BFS Bus Depot
Infrastructure
Consultancy Services for Website Redesign and
Hosting
Consultancy Services for IT Equipment
Maintenance
Consultancy Services for Events and Stakeholders
Management for BRT Services
Consultancy Services for Advertising and
Perception Management for BRT Extension (Mile
12 - Ikorodu)
Consultancy Services for Pavement Management
System Reconfiguration, Training and Data
Collection and Upload
Consultancy Services for the Documentation of the
Communication and Participation Efforts to Raise
Familiarity with BRT on Mile 12 to CMS Route
Consultancy to Conduct Stakeholder engagements
on other LAMATA projects (STMP, Road
rehabilitation/periodic maintenance etc)
Consultancy for Construction Supervision of
Adesina/Omilani/Airways Road Surulere
Consultancy for Construction Supervision of Apata
Lisabi Street Somolu
NonAsciiFileName0.xls 598 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2 CQS
SS
CQS
CQS
S/S
S/S
CQS
CQS
S/S
CQS
CQS
QCBS
Consultancy Services for Supply and installation
and Configuration of HDM4 Software for
LAMATA including Training
Consultancy Services for Provision, Installation
and Implementation of Knowledge Management
Software
Consultancy Services for Supply and installation
and configuratin of internet solution for LAMATA
(Share point)
Consultancy Services for the Provision of 1M
Internet Access
Consultancy Services for Oracle Support Licence
Consultancy Services for IT Equipment
Maintenance
Consultancy Services for EDMS Maintenance
Consultancy Services for Antivirus Support
Consultancy Services for Anti-Spam Support
Consultancy Services for Cloud Storage / Data
Backup
Consultancy Services for Arc GIS & Arc View
Upgrade and Licensing + HP Large format Plotter
Consultancy Services for Institutional, Technical
and Financial AuditNonAsciiFileName0.xls 599 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
CQS
CQS
CQS
CQS
CQS
CQS
CQS
CQS
CQS
CQS
CQS
Consultancy Services for Conducting Resettlement
Policy Framework (RPF) for Akin Adesola &
Wempco Roads
Consultancy Services for Resettlement Action Plan
(RAP) Implementation for Mile 12 to Ikorodu BRT
scheme
Consultancy Services for Procurement Audit for 2
consecutive years
Consultancy Services for Assesment of Needs of
Disadvantaged Group in Accessing Public
Transport Services on Mile 12 to Ikorodu Town
BRT Corridor
Consultancy Services for Carrying out Socio-
Economic Baseline Survey of Transportation from
Mile 12 to Ikorodu
Consultancy Services for Institutional, Technical
and Financial Audit
Consultancy Services for Developing the core
public Transport Network in Kano -Rapid
Development of Shor-time Program Investment
Consultancy Services for Developing the core
public Transport Network in Kano -Rapid
Collection of Traffic and Transport Data
Consultancy Service for Inestigating the impact of
Motocycles and Three Wheelers Growth in Africa -
Case Study of Kano
Consultancy Services for Conducting
Environmental and Social Management Plan
(ESMP) for Akin Adesola and Wempco Roads
NonAsciiFileName0.xls 600 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
NonAsciiFileName0.xls 601 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2 Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
Norm Duration of Proc Steps
Component 1:(Instititional Development)
Training of Staff and Twining programme (To be
Implemented through global Training plan and
Twining arrangement for (January 2012 to Dec
2012)
Component 2:Public Transport and Traffic Management
Consultancy Services for Carrying out the Pre and
Post Study for the Establishment of Transport
Planning Units in Lagos Island, Kosofe and
Ikorodu LGAs in Lagos State
Consultancy Services for Detailed Engineering
Design and Construction Supervision of BRT LITE
Upgrade from Mile 12 to CMS
Consultancy Services for Conceptual Design of
BRT LITE Upgrade from Mile 12 to CMS
Consultancy Services for Engineering Design and
Construction Supervision of BFS Infrastructure
Rehabilitation and Upgrading
Consultancy Services for conducting Technical due
diligence on BFS Buses (Environmental
Enhancement of BFS Operations: Due Diligence
Report) Including Supervision of the
Refurbishment of BFS Buses
For Contracts under projects approved before the May 2002 Guidelines
If Post-Review, No-objection Dates are not needed
Contract
Type
Lumpsum
or
Time-Based
Lump Sum
Lump Sum/
Time Based
Lump Sum
Lump Sum
Lump Sum
Component 2:Public Transport and Traffic Management
NonAsciiFileName0.xls 602 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Component 3: Improvement of Lagos State
Metropolitan Road Network
Component 4: Project Management & System Monitoring
Consultancy for Construction Supervision of Akin
Adesola and Wempco Roads
Consultancy Services for Design Upgrade and
Construction Supervision of BFS Bus Depot
Infrastructure
Consultancy Services for Website Redesign and
Hosting
Consultancy Services for IT Equipment
Maintenance
Consultancy Services for Events and Stakeholders
Management for BRT Services
Consultancy Services for Advertising and
Perception Management for BRT Extension (Mile
12 - Ikorodu)
Consultancy Services for Pavement Management
System Reconfiguration, Training and Data
Collection and Upload
Consultancy Services for the Documentation of the
Communication and Participation Efforts to Raise
Familiarity with BRT on Mile 12 to CMS Route
Consultancy to Conduct Stakeholder engagements
on other LAMATA projects (STMP, Road
rehabilitation/periodic maintenance etc)
Consultancy for Construction Supervision of
Adesina/Omilani/Airways Road Surulere
Consultancy for Construction Supervision of Apata
Lisabi Street Somolu
Lump Sum/
Time Based
Lump Sum
Lump Sum
Lump Sum
Lump Sum
Lump Sum
Time Based
Time Based
Time Based
Time Based
Lump Sum
Lump Sum
Lump Sum
NonAsciiFileName0.xls 603 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Consultancy Services for Supply and installation
and Configuration of HDM4 Software for
LAMATA including Training
Consultancy Services for Provision, Installation
and Implementation of Knowledge Management
Software
Consultancy Services for Supply and installation
and configuratin of internet solution for LAMATA
(Share point)
Consultancy Services for the Provision of 1M
Internet Access
Consultancy Services for Oracle Support Licence
Consultancy Services for IT Equipment
Maintenance
Consultancy Services for EDMS Maintenance
Consultancy Services for Antivirus Support
Consultancy Services for Anti-Spam Support
Consultancy Services for Cloud Storage / Data
Backup
Consultancy Services for Arc GIS & Arc View
Upgrade and Licensing + HP Large format Plotter
Consultancy Services for Institutional, Technical
and Financial Audit
Lump Sum
Lump Sum
Lump Sum
Lump Sum
Lump Sum
Lump Sum
Lump Sum
Lump Sum
Lump Sum
Lump Sum
Lump Sum
Lump Sum
NonAsciiFileName0.xls 604 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Consultancy Services for Conducting Resettlement
Policy Framework (RPF) for Akin Adesola &
Wempco Roads
Consultancy Services for Resettlement Action Plan
(RAP) Implementation for Mile 12 to Ikorodu BRT
scheme
Consultancy Services for Procurement Audit for 2
consecutive years
Consultancy Services for Assesment of Needs of
Disadvantaged Group in Accessing Public
Transport Services on Mile 12 to Ikorodu Town
BRT Corridor
Consultancy Services for Carrying out Socio-
Economic Baseline Survey of Transportation from
Mile 12 to Ikorodu
Consultancy Services for Institutional, Technical
and Financial Audit
Consultancy Services for Developing the core
public Transport Network in Kano -Rapid
Development of Shor-time Program Investment
Consultancy Services for Developing the core
public Transport Network in Kano -Rapid
Collection of Traffic and Transport Data
Consultancy Service for Inestigating the impact of
Motocycles and Three Wheelers Growth in Africa -
Case Study of Kano
Consultancy Services for Conducting
Environmental and Social Management Plan
(ESMP) for Akin Adesola and Wempco Roads
Lump Sum
Lump Sum
Lump Sum
Lump Sum
Lump Sum
Lump Sum
Lump Sum
Lump Sum
Lump Sum
Lump Sum
Lump Sum
NonAsciiFileName0.xls 605 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
NonAsciiFileName0.xls 606 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2 Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
Norm Duration of Proc Steps
Component 1:(Instititional Development)
Training of Staff and Twining programme (To be
Implemented through global Training plan and
Twining arrangement for (January 2012 to Dec
2012)
Component 2:Public Transport and Traffic Management
Consultancy Services for Carrying out the Pre and
Post Study for the Establishment of Transport
Planning Units in Lagos Island, Kosofe and
Ikorodu LGAs in Lagos State
Consultancy Services for Detailed Engineering
Design and Construction Supervision of BRT LITE
Upgrade from Mile 12 to CMS
Consultancy Services for Conceptual Design of
BRT LITE Upgrade from Mile 12 to CMS
Consultancy Services for Engineering Design and
Construction Supervision of BFS Infrastructure
Rehabilitation and Upgrading
Consultancy Services for conducting Technical due
diligence on BFS Buses (Environmental
Enhancement of BFS Operations: Due Diligence
Report) Including Supervision of the
Refurbishment of BFS Buses
For Contracts under projects approved before the May 2002 Guidelines
If Post-Review, No-objection Dates are not needed
Prior/Post
Review
Plan vs.
Actual
Plan
Prior Review Plan
Post Review Plan
Actual
Prior Review Plan
Actual
Post Review Plan
Actual
Post Review Plan
Actual
Post Review Plan
Actual
NonAsciiFileName0.xls 607 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Component 3: Improvement of Lagos State
Metropolitan Road Network
Component 4: Project Management & System Monitoring
Consultancy for Construction Supervision of Akin
Adesola and Wempco Roads
Consultancy Services for Design Upgrade and
Construction Supervision of BFS Bus Depot
Infrastructure
Consultancy Services for Website Redesign and
Hosting
Consultancy Services for IT Equipment
Maintenance
Consultancy Services for Events and Stakeholders
Management for BRT Services
Consultancy Services for Advertising and
Perception Management for BRT Extension (Mile
12 - Ikorodu)
Consultancy Services for Pavement Management
System Reconfiguration, Training and Data
Collection and Upload
Consultancy Services for the Documentation of the
Communication and Participation Efforts to Raise
Familiarity with BRT on Mile 12 to CMS Route
Consultancy to Conduct Stakeholder engagements
on other LAMATA projects (STMP, Road
rehabilitation/periodic maintenance etc)
Consultancy for Construction Supervision of
Adesina/Omilani/Airways Road Surulere
Consultancy for Construction Supervision of Apata
Lisabi Street Somolu
Prior Review Plan
Actual
Prior Review Plan
Actual
Post Review Plan
Post Review Actual
Post Review Plan
Actual
Post Review Plan
Actual
Prior Review Plan
Prior Review
Post Review Plan
Actual
Post Review Plan
Actual
Prior Review Plan
Actual
Post Review Plan
Actual
Post Review Plan
NonAsciiFileName0.xls 608 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Consultancy Services for Supply and installation
and Configuration of HDM4 Software for
LAMATA including Training
Consultancy Services for Provision, Installation
and Implementation of Knowledge Management
Software
Consultancy Services for Supply and installation
and configuratin of internet solution for LAMATA
(Share point)
Consultancy Services for the Provision of 1M
Internet Access
Consultancy Services for Oracle Support Licence
Consultancy Services for IT Equipment
Maintenance
Consultancy Services for EDMS Maintenance
Consultancy Services for Antivirus Support
Consultancy Services for Anti-Spam Support
Consultancy Services for Cloud Storage / Data
Backup
Consultancy Services for Arc GIS & Arc View
Upgrade and Licensing + HP Large format Plotter
Consultancy Services for Institutional, Technical
and Financial Audit
Post Review Actual
Prior Review Plan
Actual
Post Review Plan
Actual
Post Review Plan
Actual
Prior Review Plan
Actual
Prior Review Plan
Actual
Post Review Plan
Actual
Post Review Plan
Actual
Prior Review Plan
Actual
Post Review Plan
Actual
Post Review Plan
Actual
Prior Review Plan
NonAsciiFileName0.xls 609 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Consultancy Services for Conducting Resettlement
Policy Framework (RPF) for Akin Adesola &
Wempco Roads
Consultancy Services for Resettlement Action Plan
(RAP) Implementation for Mile 12 to Ikorodu BRT
scheme
Consultancy Services for Procurement Audit for 2
consecutive years
Consultancy Services for Assesment of Needs of
Disadvantaged Group in Accessing Public
Transport Services on Mile 12 to Ikorodu Town
BRT Corridor
Consultancy Services for Carrying out Socio-
Economic Baseline Survey of Transportation from
Mile 12 to Ikorodu
Consultancy Services for Institutional, Technical
and Financial Audit
Consultancy Services for Developing the core
public Transport Network in Kano -Rapid
Development of Shor-time Program Investment
Consultancy Services for Developing the core
public Transport Network in Kano -Rapid
Collection of Traffic and Transport Data
Consultancy Service for Inestigating the impact of
Motocycles and Three Wheelers Growth in Africa -
Case Study of Kano
Consultancy Services for Conducting
Environmental and Social Management Plan
(ESMP) for Akin Adesola and Wempco Roads
Actual
Post Review Plan
Actual
Post Review Plan
Actual
Post Review Plan
Actual
Post Review Plan
Actual
Post Review Plan
Actual
Post Review Plan
Actual
Post Review Plan
Post Review Actual
Post Review Plan
Post Review Actual
Post Review Plan
Post Review Actual
NonAsciiFileName0.xls 610 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
NonAsciiFileName0.xls 611 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2 Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
Norm Duration of Proc Steps
Component 1:(Instititional Development)
Training of Staff and Twining programme (To be
Implemented through global Training plan and
Twining arrangement for (January 2012 to Dec
2012)
Component 2:Public Transport and Traffic Management
Consultancy Services for Carrying out the Pre and
Post Study for the Establishment of Transport
Planning Units in Lagos Island, Kosofe and
Ikorodu LGAs in Lagos State
Consultancy Services for Detailed Engineering
Design and Construction Supervision of BRT LITE
Upgrade from Mile 12 to CMS
Consultancy Services for Conceptual Design of
BRT LITE Upgrade from Mile 12 to CMS
Consultancy Services for Engineering Design and
Construction Supervision of BFS Infrastructure
Rehabilitation and Upgrading
Consultancy Services for conducting Technical due
diligence on BFS Buses (Environmental
Enhancement of BFS Operations: Due Diligence
Report) Including Supervision of the
Refurbishment of BFS Buses
For Contracts under projects approved before the May 2002 Guidelines
Prep &
Submission
by Ex Ag
3 - 6 wks
15-Mar-12
1-Nov-12
30-Jan-12
18-May-12
15-Nov-12
Preparation
Request for Proposals
NonAsciiFileName0.xls 612 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Component 3: Improvement of Lagos State
Metropolitan Road Network
Component 4: Project Management & System Monitoring
Consultancy for Construction Supervision of Akin
Adesola and Wempco Roads
Consultancy Services for Design Upgrade and
Construction Supervision of BFS Bus Depot
Infrastructure
Consultancy Services for Website Redesign and
Hosting
Consultancy Services for IT Equipment
Maintenance
Consultancy Services for Events and Stakeholders
Management for BRT Services
Consultancy Services for Advertising and
Perception Management for BRT Extension (Mile
12 - Ikorodu)
Consultancy Services for Pavement Management
System Reconfiguration, Training and Data
Collection and Upload
Consultancy Services for the Documentation of the
Communication and Participation Efforts to Raise
Familiarity with BRT on Mile 12 to CMS Route
Consultancy to Conduct Stakeholder engagements
on other LAMATA projects (STMP, Road
rehabilitation/periodic maintenance etc)
Consultancy for Construction Supervision of
Adesina/Omilani/Airways Road Surulere
Consultancy for Construction Supervision of Apata
Lisabi Street Somolu
2-Apr-12
6-Feb-12
8-Nov-11
11-Oct-11
2-Feb-12
2-Feb-12
3-Nov-11
3-Nov-11
6-Sep-12
6-Sep-12
2-Jul-12
2-Feb-12
6-Sep-11
NonAsciiFileName0.xls 613 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Consultancy Services for Supply and installation
and Configuration of HDM4 Software for
LAMATA including Training
Consultancy Services for Provision, Installation
and Implementation of Knowledge Management
Software
Consultancy Services for Supply and installation
and configuratin of internet solution for LAMATA
(Share point)
Consultancy Services for the Provision of 1M
Internet Access
Consultancy Services for Oracle Support Licence
Consultancy Services for IT Equipment
Maintenance
Consultancy Services for EDMS Maintenance
Consultancy Services for Antivirus Support
Consultancy Services for Anti-Spam Support
Consultancy Services for Cloud Storage / Data
Backup
Consultancy Services for Arc GIS & Arc View
Upgrade and Licensing + HP Large format Plotter
Consultancy Services for Institutional, Technical
and Financial Audit
1-Nov-11
13-Apr-12
5-Apr-12
23-Apr-12
20-Aug-12
27-Feb-12
27-Mar-12
23-Apr-12
2-Oct-12
25-Jul-12
25-Jun-12
1-Nov-12
NonAsciiFileName0.xls 614 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Consultancy Services for Conducting Resettlement
Policy Framework (RPF) for Akin Adesola &
Wempco Roads
Consultancy Services for Resettlement Action Plan
(RAP) Implementation for Mile 12 to Ikorodu BRT
scheme
Consultancy Services for Procurement Audit for 2
consecutive years
Consultancy Services for Assesment of Needs of
Disadvantaged Group in Accessing Public
Transport Services on Mile 12 to Ikorodu Town
BRT Corridor
Consultancy Services for Carrying out Socio-
Economic Baseline Survey of Transportation from
Mile 12 to Ikorodu
Consultancy Services for Institutional, Technical
and Financial Audit
Consultancy Services for Developing the core
public Transport Network in Kano -Rapid
Development of Shor-time Program Investment
Consultancy Services for Developing the core
public Transport Network in Kano -Rapid
Collection of Traffic and Transport Data
Consultancy Service for Inestigating the impact of
Motocycles and Three Wheelers Growth in Africa -
Case Study of Kano
Consultancy Services for Conducting
Environmental and Social Management Plan
(ESMP) for Akin Adesola and Wempco Roads
3-Feb-12
2-Feb-12
2-Feb-12
2-Feb-12
9-Apr-12
8-Feb-12
5-Jul-11
5-Jul-11
5-Jul-11
5-Jul-11
5-Jul-11
5-Jul-11
NonAsciiFileName0.xls 615 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
NonAsciiFileName0.xls 616 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2 Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
Norm Duration of Proc Steps
Component 1:(Instititional Development)
Training of Staff and Twining programme (To be
Implemented through global Training plan and
Twining arrangement for (January 2012 to Dec
2012)
Component 2:Public Transport and Traffic Management
Consultancy Services for Carrying out the Pre and
Post Study for the Establishment of Transport
Planning Units in Lagos Island, Kosofe and
Ikorodu LGAs in Lagos State
Consultancy Services for Detailed Engineering
Design and Construction Supervision of BRT LITE
Upgrade from Mile 12 to CMS
Consultancy Services for Conceptual Design of
BRT LITE Upgrade from Mile 12 to CMS
Consultancy Services for Engineering Design and
Construction Supervision of BFS Infrastructure
Rehabilitation and Upgrading
Consultancy Services for conducting Technical due
diligence on BFS Buses (Environmental
Enhancement of BFS Operations: Due Diligence
Report) Including Supervision of the
Refurbishment of BFS Buses
No-objection
Date
1 - 2 wks
22-Mar-12
15-Nov-12
2-Feb-12
25-May-12
29-Nov-12
Preparation
Request for Proposals
NonAsciiFileName0.xls 617 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Component 3: Improvement of Lagos State
Metropolitan Road Network
Component 4: Project Management & System Monitoring
Consultancy for Construction Supervision of Akin
Adesola and Wempco Roads
Consultancy Services for Design Upgrade and
Construction Supervision of BFS Bus Depot
Infrastructure
Consultancy Services for Website Redesign and
Hosting
Consultancy Services for IT Equipment
Maintenance
Consultancy Services for Events and Stakeholders
Management for BRT Services
Consultancy Services for Advertising and
Perception Management for BRT Extension (Mile
12 - Ikorodu)
Consultancy Services for Pavement Management
System Reconfiguration, Training and Data
Collection and Upload
Consultancy Services for the Documentation of the
Communication and Participation Efforts to Raise
Familiarity with BRT on Mile 12 to CMS Route
Consultancy to Conduct Stakeholder engagements
on other LAMATA projects (STMP, Road
rehabilitation/periodic maintenance etc)
Consultancy for Construction Supervision of
Adesina/Omilani/Airways Road Surulere
Consultancy for Construction Supervision of Apata
Lisabi Street Somolu
16-Apr-12
20-Feb-12
16-Nov-11
19-Oct-11
9-Feb-12
9-Feb-12
9-Nov-11
3-Nov-11
14-Sep-12
14-Sep-12
16-Jul-12
9-Feb-12
14-Sep-11
NonAsciiFileName0.xls 618 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Consultancy Services for Supply and installation
and Configuration of HDM4 Software for
LAMATA including Training
Consultancy Services for Provision, Installation
and Implementation of Knowledge Management
Software
Consultancy Services for Supply and installation
and configuratin of internet solution for LAMATA
(Share point)
Consultancy Services for the Provision of 1M
Internet Access
Consultancy Services for Oracle Support Licence
Consultancy Services for IT Equipment
Maintenance
Consultancy Services for EDMS Maintenance
Consultancy Services for Antivirus Support
Consultancy Services for Anti-Spam Support
Consultancy Services for Cloud Storage / Data
Backup
Consultancy Services for Arc GIS & Arc View
Upgrade and Licensing + HP Large format Plotter
Consultancy Services for Institutional, Technical
and Financial Audit
10-Nov-11
27-Apr-12
13-Apr-12
1-May-12
3-Sep-12
12-Mar-12
4-Apr-12
1-May-12
16-Oct-12
2-Aug-12
5-Jul-12
15-Nov-12
NonAsciiFileName0.xls 619 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Consultancy Services for Conducting Resettlement
Policy Framework (RPF) for Akin Adesola &
Wempco Roads
Consultancy Services for Resettlement Action Plan
(RAP) Implementation for Mile 12 to Ikorodu BRT
scheme
Consultancy Services for Procurement Audit for 2
consecutive years
Consultancy Services for Assesment of Needs of
Disadvantaged Group in Accessing Public
Transport Services on Mile 12 to Ikorodu Town
BRT Corridor
Consultancy Services for Carrying out Socio-
Economic Baseline Survey of Transportation from
Mile 12 to Ikorodu
Consultancy Services for Institutional, Technical
and Financial Audit
Consultancy Services for Developing the core
public Transport Network in Kano -Rapid
Development of Shor-time Program Investment
Consultancy Services for Developing the core
public Transport Network in Kano -Rapid
Collection of Traffic and Transport Data
Consultancy Service for Inestigating the impact of
Motocycles and Three Wheelers Growth in Africa -
Case Study of Kano
Consultancy Services for Conducting
Environmental and Social Management Plan
(ESMP) for Akin Adesola and Wempco Roads
10-Feb-12
9-Feb-12
9-Feb-12
9-Feb-12
16-Apr-12
15-Feb-12
13-Jul-11
13-Jul-11
13-Jul-11
13-Jul-11
13-Jul-11
13-Jul-11
NonAsciiFileName0.xls 620 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
NonAsciiFileName0.xls 621 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2 Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
Norm Duration of Proc Steps
Component 1:(Instititional Development)
Training of Staff and Twining programme (To be
Implemented through global Training plan and
Twining arrangement for (January 2012 to Dec
2012)
Component 2:Public Transport and Traffic Management
Consultancy Services for Carrying out the Pre and
Post Study for the Establishment of Transport
Planning Units in Lagos Island, Kosofe and
Ikorodu LGAs in Lagos State
Consultancy Services for Detailed Engineering
Design and Construction Supervision of BRT LITE
Upgrade from Mile 12 to CMS
Consultancy Services for Conceptual Design of
BRT LITE Upgrade from Mile 12 to CMS
Consultancy Services for Engineering Design and
Construction Supervision of BFS Infrastructure
Rehabilitation and Upgrading
Consultancy Services for conducting Technical due
diligence on BFS Buses (Environmental
Enhancement of BFS Operations: Due Diligence
Report) Including Supervision of the
Refurbishment of BFS Buses
On-line UNDB
Gateway
Nat Press
1 - 1.5 wks
5-Apr-12
19-Nov-12
3-Feb-12
29-May-12
06-Dec-12
Request for EOI
(where required)
NonAsciiFileName0.xls 622 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Component 3: Improvement of Lagos State
Metropolitan Road Network
Component 4: Project Management & System Monitoring
Consultancy for Construction Supervision of Akin
Adesola and Wempco Roads
Consultancy Services for Design Upgrade and
Construction Supervision of BFS Bus Depot
Infrastructure
Consultancy Services for Website Redesign and
Hosting
Consultancy Services for IT Equipment
Maintenance
Consultancy Services for Events and Stakeholders
Management for BRT Services
Consultancy Services for Advertising and
Perception Management for BRT Extension (Mile
12 - Ikorodu)
Consultancy Services for Pavement Management
System Reconfiguration, Training and Data
Collection and Upload
Consultancy Services for the Documentation of the
Communication and Participation Efforts to Raise
Familiarity with BRT on Mile 12 to CMS Route
Consultancy to Conduct Stakeholder engagements
on other LAMATA projects (STMP, Road
rehabilitation/periodic maintenance etc)
Consultancy for Construction Supervision of
Adesina/Omilani/Airways Road Surulere
Consultancy for Construction Supervision of Apata
Lisabi Street Somolu
N/A
27-Feb-12
18-Nov-11
21-Oct-11
13-Feb-12
13-Feb-12
11-Nov-11
8-Nov-11
18-Sep-12
18-Sep-12
20-Jul-12
13-Feb-12
16-Sep-11
NonAsciiFileName0.xls 623 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Consultancy Services for Supply and installation
and Configuration of HDM4 Software for
LAMATA including Training
Consultancy Services for Provision, Installation
and Implementation of Knowledge Management
Software
Consultancy Services for Supply and installation
and configuratin of internet solution for LAMATA
(Share point)
Consultancy Services for the Provision of 1M
Internet Access
Consultancy Services for Oracle Support Licence
Consultancy Services for IT Equipment
Maintenance
Consultancy Services for EDMS Maintenance
Consultancy Services for Antivirus Support
Consultancy Services for Anti-Spam Support
Consultancy Services for Cloud Storage / Data
Backup
Consultancy Services for Arc GIS & Arc View
Upgrade and Licensing + HP Large format Plotter
Consultancy Services for Institutional, Technical
and Financial Audit
15-Nov-11
N/A
17-Apr-12
3-May-12
N/A
N/A
6-Apr-12
3-May-12
N/A
6-Aug-12
9-Jul-12
22-Nov-12
NonAsciiFileName0.xls 624 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Consultancy Services for Conducting Resettlement
Policy Framework (RPF) for Akin Adesola &
Wempco Roads
Consultancy Services for Resettlement Action Plan
(RAP) Implementation for Mile 12 to Ikorodu BRT
scheme
Consultancy Services for Procurement Audit for 2
consecutive years
Consultancy Services for Assesment of Needs of
Disadvantaged Group in Accessing Public
Transport Services on Mile 12 to Ikorodu Town
BRT Corridor
Consultancy Services for Carrying out Socio-
Economic Baseline Survey of Transportation from
Mile 12 to Ikorodu
Consultancy Services for Institutional, Technical
and Financial Audit
Consultancy Services for Developing the core
public Transport Network in Kano -Rapid
Development of Shor-time Program Investment
Consultancy Services for Developing the core
public Transport Network in Kano -Rapid
Collection of Traffic and Transport Data
Consultancy Service for Inestigating the impact of
Motocycles and Three Wheelers Growth in Africa -
Case Study of Kano
Consultancy Services for Conducting
Environmental and Social Management Plan
(ESMP) for Akin Adesola and Wempco Roads
13-Feb-12
13-Feb-12
13-Feb-12
13-Feb-12
20-Apr-12
19-Feb-12
15-Jul-11
15-Jul-11
15-Jul-11
15-Jul-11
15-Jul-11
15-Jul-11
NonAsciiFileName0.xls 625 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
NonAsciiFileName0.xls 626 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2 Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
Norm Duration of Proc Steps
Component 1:(Instititional Development)
Training of Staff and Twining programme (To be
Implemented through global Training plan and
Twining arrangement for (January 2012 to Dec
2012)
Component 2:Public Transport and Traffic Management
Consultancy Services for Carrying out the Pre and
Post Study for the Establishment of Transport
Planning Units in Lagos Island, Kosofe and
Ikorodu LGAs in Lagos State
Consultancy Services for Detailed Engineering
Design and Construction Supervision of BRT LITE
Upgrade from Mile 12 to CMS
Consultancy Services for Conceptual Design of
BRT LITE Upgrade from Mile 12 to CMS
Consultancy Services for Engineering Design and
Construction Supervision of BFS Infrastructure
Rehabilitation and Upgrading
Consultancy Services for conducting Technical due
diligence on BFS Buses (Environmental
Enhancement of BFS Operations: Due Diligence
Report) Including Supervision of the
Refurbishment of BFS Buses
Lead-time
before shortlist
2 wks
19-Apr-12
3-Dec-12
17-Feb-12
12-Jun-12
20-Dec-12
Request for EOI
(where required)
NonAsciiFileName0.xls 627 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Component 3: Improvement of Lagos State
Metropolitan Road Network
Component 4: Project Management & System Monitoring
Consultancy for Construction Supervision of Akin
Adesola and Wempco Roads
Consultancy Services for Design Upgrade and
Construction Supervision of BFS Bus Depot
Infrastructure
Consultancy Services for Website Redesign and
Hosting
Consultancy Services for IT Equipment
Maintenance
Consultancy Services for Events and Stakeholders
Management for BRT Services
Consultancy Services for Advertising and
Perception Management for BRT Extension (Mile
12 - Ikorodu)
Consultancy Services for Pavement Management
System Reconfiguration, Training and Data
Collection and Upload
Consultancy Services for the Documentation of the
Communication and Participation Efforts to Raise
Familiarity with BRT on Mile 12 to CMS Route
Consultancy to Conduct Stakeholder engagements
on other LAMATA projects (STMP, Road
rehabilitation/periodic maintenance etc)
Consultancy for Construction Supervision of
Adesina/Omilani/Airways Road Surulere
Consultancy for Construction Supervision of Apata
Lisabi Street Somolu
N/A
12-Mar-12
2-Dec-11
4-Nov-11
27-Feb-12
27-Feb-12
25-Nov-11
23-Nov-11
2-Oct-12
2-Oct-12
3-Aug-12
27-Feb-12
30-Sep-11
NonAsciiFileName0.xls 628 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Consultancy Services for Supply and installation
and Configuration of HDM4 Software for
LAMATA including Training
Consultancy Services for Provision, Installation
and Implementation of Knowledge Management
Software
Consultancy Services for Supply and installation
and configuratin of internet solution for LAMATA
(Share point)
Consultancy Services for the Provision of 1M
Internet Access
Consultancy Services for Oracle Support Licence
Consultancy Services for IT Equipment
Maintenance
Consultancy Services for EDMS Maintenance
Consultancy Services for Antivirus Support
Consultancy Services for Anti-Spam Support
Consultancy Services for Cloud Storage / Data
Backup
Consultancy Services for Arc GIS & Arc View
Upgrade and Licensing + HP Large format Plotter
Consultancy Services for Institutional, Technical
and Financial Audit
29-Nov-11
N/A
1-May-12
17-May-12
N/A
N/A
20-Apr-12
17-May-12
N/A
20-Aug-12
23-Jul-12
6-Dec-12
NonAsciiFileName0.xls 629 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Consultancy Services for Conducting Resettlement
Policy Framework (RPF) for Akin Adesola &
Wempco Roads
Consultancy Services for Resettlement Action Plan
(RAP) Implementation for Mile 12 to Ikorodu BRT
scheme
Consultancy Services for Procurement Audit for 2
consecutive years
Consultancy Services for Assesment of Needs of
Disadvantaged Group in Accessing Public
Transport Services on Mile 12 to Ikorodu Town
BRT Corridor
Consultancy Services for Carrying out Socio-
Economic Baseline Survey of Transportation from
Mile 12 to Ikorodu
Consultancy Services for Institutional, Technical
and Financial Audit
Consultancy Services for Developing the core
public Transport Network in Kano -Rapid
Development of Shor-time Program Investment
Consultancy Services for Developing the core
public Transport Network in Kano -Rapid
Collection of Traffic and Transport Data
Consultancy Service for Inestigating the impact of
Motocycles and Three Wheelers Growth in Africa -
Case Study of Kano
Consultancy Services for Conducting
Environmental and Social Management Plan
(ESMP) for Akin Adesola and Wempco Roads
27-Feb-12
27-Feb-12
27-Feb-12
27-Feb-12
4-May-12
4-Mar-12
29-Jul-11
1-Aug-11
29-Jul-11
1-Aug-11
29-Jul-11
1-Aug-11
NonAsciiFileName0.xls 630 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
NonAsciiFileName0.xls 631 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2 Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
Norm Duration of Proc Steps
Component 1:(Instititional Development)
Training of Staff and Twining programme (To be
Implemented through global Training plan and
Twining arrangement for (January 2012 to Dec
2012)
Component 2:Public Transport and Traffic Management
Consultancy Services for Carrying out the Pre and
Post Study for the Establishment of Transport
Planning Units in Lagos Island, Kosofe and
Ikorodu LGAs in Lagos State
Consultancy Services for Detailed Engineering
Design and Construction Supervision of BRT LITE
Upgrade from Mile 12 to CMS
Consultancy Services for Conceptual Design of
BRT LITE Upgrade from Mile 12 to CMS
Consultancy Services for Engineering Design and
Construction Supervision of BFS Infrastructure
Rehabilitation and Upgrading
Consultancy Services for conducting Technical due
diligence on BFS Buses (Environmental
Enhancement of BFS Operations: Due Diligence
Report) Including Supervision of the
Refurbishment of BFS Buses
Submission
Date
N/A
17-Dec-12
N/A
N/A
N/A
Short
List
NonAsciiFileName0.xls 632 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Component 3: Improvement of Lagos State
Metropolitan Road Network
Component 4: Project Management & System Monitoring
Consultancy for Construction Supervision of Akin
Adesola and Wempco Roads
Consultancy Services for Design Upgrade and
Construction Supervision of BFS Bus Depot
Infrastructure
Consultancy Services for Website Redesign and
Hosting
Consultancy Services for IT Equipment
Maintenance
Consultancy Services for Events and Stakeholders
Management for BRT Services
Consultancy Services for Advertising and
Perception Management for BRT Extension (Mile
12 - Ikorodu)
Consultancy Services for Pavement Management
System Reconfiguration, Training and Data
Collection and Upload
Consultancy Services for the Documentation of the
Communication and Participation Efforts to Raise
Familiarity with BRT on Mile 12 to CMS Route
Consultancy to Conduct Stakeholder engagements
on other LAMATA projects (STMP, Road
rehabilitation/periodic maintenance etc)
Consultancy for Construction Supervision of
Adesina/Omilani/Airways Road Surulere
Consultancy for Construction Supervision of Apata
Lisabi Street Somolu
N/A
26-Mar-12
N/A
N/A
N/A
N/A
30-Jan-12
N/A
N/A
17-Aug-12
N/A
N/A
NonAsciiFileName0.xls 633 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Consultancy Services for Supply and installation
and Configuration of HDM4 Software for
LAMATA including Training
Consultancy Services for Provision, Installation
and Implementation of Knowledge Management
Software
Consultancy Services for Supply and installation
and configuratin of internet solution for LAMATA
(Share point)
Consultancy Services for the Provision of 1M
Internet Access
Consultancy Services for Oracle Support Licence
Consultancy Services for IT Equipment
Maintenance
Consultancy Services for EDMS Maintenance
Consultancy Services for Antivirus Support
Consultancy Services for Anti-Spam Support
Consultancy Services for Cloud Storage / Data
Backup
Consultancy Services for Arc GIS & Arc View
Upgrade and Licensing + HP Large format Plotter
Consultancy Services for Institutional, Technical
and Financial Audit
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
20-Dec-12
NonAsciiFileName0.xls 634 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Consultancy Services for Conducting Resettlement
Policy Framework (RPF) for Akin Adesola &
Wempco Roads
Consultancy Services for Resettlement Action Plan
(RAP) Implementation for Mile 12 to Ikorodu BRT
scheme
Consultancy Services for Procurement Audit for 2
consecutive years
Consultancy Services for Assesment of Needs of
Disadvantaged Group in Accessing Public
Transport Services on Mile 12 to Ikorodu Town
BRT Corridor
Consultancy Services for Carrying out Socio-
Economic Baseline Survey of Transportation from
Mile 12 to Ikorodu
Consultancy Services for Institutional, Technical
and Financial Audit
Consultancy Services for Developing the core
public Transport Network in Kano -Rapid
Development of Shor-time Program Investment
Consultancy Services for Developing the core
public Transport Network in Kano -Rapid
Collection of Traffic and Transport Data
Consultancy Service for Inestigating the impact of
Motocycles and Three Wheelers Growth in Africa -
Case Study of Kano
Consultancy Services for Conducting
Environmental and Social Management Plan
(ESMP) for Akin Adesola and Wempco Roads
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
NonAsciiFileName0.xls 635 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
NonAsciiFileName0.xls 636 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2 Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
Norm Duration of Proc Steps
Component 1:(Instititional Development)
Training of Staff and Twining programme (To be
Implemented through global Training plan and
Twining arrangement for (January 2012 to Dec
2012)
Component 2:Public Transport and Traffic Management
Consultancy Services for Carrying out the Pre and
Post Study for the Establishment of Transport
Planning Units in Lagos Island, Kosofe and
Ikorodu LGAs in Lagos State
Consultancy Services for Detailed Engineering
Design and Construction Supervision of BRT LITE
Upgrade from Mile 12 to CMS
Consultancy Services for Conceptual Design of
BRT LITE Upgrade from Mile 12 to CMS
Consultancy Services for Engineering Design and
Construction Supervision of BFS Infrastructure
Rehabilitation and Upgrading
Consultancy Services for conducting Technical due
diligence on BFS Buses (Environmental
Enhancement of BFS Operations: Due Diligence
Report) Including Supervision of the
Refurbishment of BFS Buses
No-objection
Date
Plan vs.
Actual
1 - 2 wks Plan
Plan
N/A Plan
Actual
31-Dec-12 Plan
Actual
N/A Plan
Actual
N/A Plan
Actual
N/A Plan
Actual
Short
List
NonAsciiFileName0.xls 637 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Component 3: Improvement of Lagos State
Metropolitan Road Network
Component 4: Project Management & System Monitoring
Consultancy for Construction Supervision of Akin
Adesola and Wempco Roads
Consultancy Services for Design Upgrade and
Construction Supervision of BFS Bus Depot
Infrastructure
Consultancy Services for Website Redesign and
Hosting
Consultancy Services for IT Equipment
Maintenance
Consultancy Services for Events and Stakeholders
Management for BRT Services
Consultancy Services for Advertising and
Perception Management for BRT Extension (Mile
12 - Ikorodu)
Consultancy Services for Pavement Management
System Reconfiguration, Training and Data
Collection and Upload
Consultancy Services for the Documentation of the
Communication and Participation Efforts to Raise
Familiarity with BRT on Mile 12 to CMS Route
Consultancy to Conduct Stakeholder engagements
on other LAMATA projects (STMP, Road
rehabilitation/periodic maintenance etc)
Consultancy for Construction Supervision of
Adesina/Omilani/Airways Road Surulere
Consultancy for Construction Supervision of Apata
Lisabi Street Somolu
N/A Plan
Actual
9-Apr-12 Plan
Actual
N/A Plan
N/A Actual
N/A Plan
Actual
N/A Plan
Actual
6-Feb-12 Plan
N/A Plan
Actual
N/A Plan
Actual
31-Aug-12 Plan
Actual
N/A Plan
Actual
N/A Plan
NonAsciiFileName0.xls 638 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Consultancy Services for Supply and installation
and Configuration of HDM4 Software for
LAMATA including Training
Consultancy Services for Provision, Installation
and Implementation of Knowledge Management
Software
Consultancy Services for Supply and installation
and configuratin of internet solution for LAMATA
(Share point)
Consultancy Services for the Provision of 1M
Internet Access
Consultancy Services for Oracle Support Licence
Consultancy Services for IT Equipment
Maintenance
Consultancy Services for EDMS Maintenance
Consultancy Services for Antivirus Support
Consultancy Services for Anti-Spam Support
Consultancy Services for Cloud Storage / Data
Backup
Consultancy Services for Arc GIS & Arc View
Upgrade and Licensing + HP Large format Plotter
Consultancy Services for Institutional, Technical
and Financial Audit
N/A Actual
N/A Plan
Actual
N/A Plan
Actual
N/A Plan
Actual
N/A Plan
Actual
N/A Plan
Actual
N/A Plan
Actual
N/A Plan
Actual
N/A Plan
Actual
N/A Plan
Actual
N/A Plan
Actual
3-Jan-13 Plan
NonAsciiFileName0.xls 639 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Consultancy Services for Conducting Resettlement
Policy Framework (RPF) for Akin Adesola &
Wempco Roads
Consultancy Services for Resettlement Action Plan
(RAP) Implementation for Mile 12 to Ikorodu BRT
scheme
Consultancy Services for Procurement Audit for 2
consecutive years
Consultancy Services for Assesment of Needs of
Disadvantaged Group in Accessing Public
Transport Services on Mile 12 to Ikorodu Town
BRT Corridor
Consultancy Services for Carrying out Socio-
Economic Baseline Survey of Transportation from
Mile 12 to Ikorodu
Consultancy Services for Institutional, Technical
and Financial Audit
Consultancy Services for Developing the core
public Transport Network in Kano -Rapid
Development of Shor-time Program Investment
Consultancy Services for Developing the core
public Transport Network in Kano -Rapid
Collection of Traffic and Transport Data
Consultancy Service for Inestigating the impact of
Motocycles and Three Wheelers Growth in Africa -
Case Study of Kano
Consultancy Services for Conducting
Environmental and Social Management Plan
(ESMP) for Akin Adesola and Wempco Roads
Actual
N/A Plan
Actual
N/A Plan
Actual
N/A Plan
Actual
N/A Plan
Actual
N/A Plan
Actual
N/A Plan
Actual
N/A Plan
N/A Actual
N/A Plan
N/A Actual
N/A Plan
N/A Actual
NonAsciiFileName0.xls 640 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
NonAsciiFileName0.xls 641 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2 Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
Norm Duration of Proc Steps
Component 1:(Instititional Development)
Training of Staff and Twining programme (To be
Implemented through global Training plan and
Twining arrangement for (January 2012 to Dec
2012)
Component 2:Public Transport and Traffic Management
Consultancy Services for Carrying out the Pre and
Post Study for the Establishment of Transport
Planning Units in Lagos Island, Kosofe and
Ikorodu LGAs in Lagos State
Consultancy Services for Detailed Engineering
Design and Construction Supervision of BRT LITE
Upgrade from Mile 12 to CMS
Consultancy Services for Conceptual Design of
BRT LITE Upgrade from Mile 12 to CMS
Consultancy Services for Engineering Design and
Construction Supervision of BFS Infrastructure
Rehabilitation and Upgrading
Consultancy Services for conducting Technical due
diligence on BFS Buses (Environmental
Enhancement of BFS Operations: Due Diligence
Report) Including Supervision of the
Refurbishment of BFS Buses
Invitation
Date
4 to
3-May-12
4-Jan-13
2-Mar-12
26-Jun-12
3-Jan-13
Consultant
Proposals
NonAsciiFileName0.xls 642 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Component 3: Improvement of Lagos State
Metropolitan Road Network
Component 4: Project Management & System Monitoring
Consultancy for Construction Supervision of Akin
Adesola and Wempco Roads
Consultancy Services for Design Upgrade and
Construction Supervision of BFS Bus Depot
Infrastructure
Consultancy Services for Website Redesign and
Hosting
Consultancy Services for IT Equipment
Maintenance
Consultancy Services for Events and Stakeholders
Management for BRT Services
Consultancy Services for Advertising and
Perception Management for BRT Extension (Mile
12 - Ikorodu)
Consultancy Services for Pavement Management
System Reconfiguration, Training and Data
Collection and Upload
Consultancy Services for the Documentation of the
Communication and Participation Efforts to Raise
Familiarity with BRT on Mile 12 to CMS Route
Consultancy to Conduct Stakeholder engagements
on other LAMATA projects (STMP, Road
rehabilitation/periodic maintenance etc)
Consultancy for Construction Supervision of
Adesina/Omilani/Airways Road Surulere
Consultancy for Construction Supervision of Apata
Lisabi Street Somolu
20-Apr-12
16-Apr-12
16-Dec-11
23-No-11
12-Mar-12
12-Mar-12
13-Feb-12
16-Oct-12
16-Oct-12
4-Sep-12
12-Mar-12
23-Jan-12
NonAsciiFileName0.xls 643 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Consultancy Services for Supply and installation
and Configuration of HDM4 Software for
LAMATA including Training
Consultancy Services for Provision, Installation
and Implementation of Knowledge Management
Software
Consultancy Services for Supply and installation
and configuratin of internet solution for LAMATA
(Share point)
Consultancy Services for the Provision of 1M
Internet Access
Consultancy Services for Oracle Support Licence
Consultancy Services for IT Equipment
Maintenance
Consultancy Services for EDMS Maintenance
Consultancy Services for Antivirus Support
Consultancy Services for Anti-Spam Support
Consultancy Services for Cloud Storage / Data
Backup
Consultancy Services for Arc GIS & Arc View
Upgrade and Licensing + HP Large format Plotter
Consultancy Services for Institutional, Technical
and Financial Audit
23-Jan-12
29-Apr-12
15-May-12
31-May-12
5-Sep-12
15-Mar-12
4-May-12
31-May-12
19-Oct-12
3-Sep-12
6-Aug-12
10-Jan-13
NonAsciiFileName0.xls 644 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Consultancy Services for Conducting Resettlement
Policy Framework (RPF) for Akin Adesola &
Wempco Roads
Consultancy Services for Resettlement Action Plan
(RAP) Implementation for Mile 12 to Ikorodu BRT
scheme
Consultancy Services for Procurement Audit for 2
consecutive years
Consultancy Services for Assesment of Needs of
Disadvantaged Group in Accessing Public
Transport Services on Mile 12 to Ikorodu Town
BRT Corridor
Consultancy Services for Carrying out Socio-
Economic Baseline Survey of Transportation from
Mile 12 to Ikorodu
Consultancy Services for Institutional, Technical
and Financial Audit
Consultancy Services for Developing the core
public Transport Network in Kano -Rapid
Development of Shor-time Program Investment
Consultancy Services for Developing the core
public Transport Network in Kano -Rapid
Collection of Traffic and Transport Data
Consultancy Service for Inestigating the impact of
Motocycles and Three Wheelers Growth in Africa -
Case Study of Kano
Consultancy Services for Conducting
Environmental and Social Management Plan
(ESMP) for Akin Adesola and Wempco Roads
12-Mar-12
12-Mar-12
12-Mar-12
12-Mar-12
18-May-12
18-Mar-12
16-Sep-11
19-Sep-11
16-Sep-11
19-Sep-11
16-Sep-11
19-Sep-11
NonAsciiFileName0.xls 645 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
NonAsciiFileName0.xls 646 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2 Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
Norm Duration of Proc Steps
Component 1:(Instititional Development)
Training of Staff and Twining programme (To be
Implemented through global Training plan and
Twining arrangement for (January 2012 to Dec
2012)
Component 2:Public Transport and Traffic Management
Consultancy Services for Carrying out the Pre and
Post Study for the Establishment of Transport
Planning Units in Lagos Island, Kosofe and
Ikorodu LGAs in Lagos State
Consultancy Services for Detailed Engineering
Design and Construction Supervision of BRT LITE
Upgrade from Mile 12 to CMS
Consultancy Services for Conceptual Design of
BRT LITE Upgrade from Mile 12 to CMS
Consultancy Services for Engineering Design and
Construction Supervision of BFS Infrastructure
Rehabilitation and Upgrading
Consultancy Services for conducting Technical due
diligence on BFS Buses (Environmental
Enhancement of BFS Operations: Due Diligence
Report) Including Supervision of the
Refurbishment of BFS Buses
Submission/
Opening
Date
12 wks
2-Jun-12
3-Feb-13
1-Apr-12
26-Jul-12
2-Feb-13
Consultant
Proposals
NonAsciiFileName0.xls 647 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Component 3: Improvement of Lagos State
Metropolitan Road Network
Component 4: Project Management & System Monitoring
Consultancy for Construction Supervision of Akin
Adesola and Wempco Roads
Consultancy Services for Design Upgrade and
Construction Supervision of BFS Bus Depot
Infrastructure
Consultancy Services for Website Redesign and
Hosting
Consultancy Services for IT Equipment
Maintenance
Consultancy Services for Events and Stakeholders
Management for BRT Services
Consultancy Services for Advertising and
Perception Management for BRT Extension (Mile
12 - Ikorodu)
Consultancy Services for Pavement Management
System Reconfiguration, Training and Data
Collection and Upload
Consultancy Services for the Documentation of the
Communication and Participation Efforts to Raise
Familiarity with BRT on Mile 12 to CMS Route
Consultancy to Conduct Stakeholder engagements
on other LAMATA projects (STMP, Road
rehabilitation/periodic maintenance etc)
Consultancy for Construction Supervision of
Adesina/Omilani/Airways Road Surulere
Consultancy for Construction Supervision of Apata
Lisabi Street Somolu
21-May-12
15-May-12
15-Jan-12
29-Dec-11
11-Apr-12
11-Apr-12
12-Mar-12
15-Nov-12
15-Nov-12
4-Oct-12
9-Apr-12
21-Feb-12
NonAsciiFileName0.xls 648 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Consultancy Services for Supply and installation
and Configuration of HDM4 Software for
LAMATA including Training
Consultancy Services for Provision, Installation
and Implementation of Knowledge Management
Software
Consultancy Services for Supply and installation
and configuratin of internet solution for LAMATA
(Share point)
Consultancy Services for the Provision of 1M
Internet Access
Consultancy Services for Oracle Support Licence
Consultancy Services for IT Equipment
Maintenance
Consultancy Services for EDMS Maintenance
Consultancy Services for Antivirus Support
Consultancy Services for Anti-Spam Support
Consultancy Services for Cloud Storage / Data
Backup
Consultancy Services for Arc GIS & Arc View
Upgrade and Licensing + HP Large format Plotter
Consultancy Services for Institutional, Technical
and Financial Audit
27-May-12
12-Jun-12
28-Jun-12
3-Oct-12
12-Apr-12
1-Jun-12
28-Jun-12
2-Nov-12
1-Oct-12
3-Sep-12
8-Feb-13
NonAsciiFileName0.xls 649 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Consultancy Services for Conducting Resettlement
Policy Framework (RPF) for Akin Adesola &
Wempco Roads
Consultancy Services for Resettlement Action Plan
(RAP) Implementation for Mile 12 to Ikorodu BRT
scheme
Consultancy Services for Procurement Audit for 2
consecutive years
Consultancy Services for Assesment of Needs of
Disadvantaged Group in Accessing Public
Transport Services on Mile 12 to Ikorodu Town
BRT Corridor
Consultancy Services for Carrying out Socio-
Economic Baseline Survey of Transportation from
Mile 12 to Ikorodu
Consultancy Services for Institutional, Technical
and Financial Audit
Consultancy Services for Developing the core
public Transport Network in Kano -Rapid
Development of Shor-time Program Investment
Consultancy Services for Developing the core
public Transport Network in Kano -Rapid
Collection of Traffic and Transport Data
Consultancy Service for Inestigating the impact of
Motocycles and Three Wheelers Growth in Africa -
Case Study of Kano
Consultancy Services for Conducting
Environmental and Social Management Plan
(ESMP) for Akin Adesola and Wempco Roads
9-Apr-12
9-Apr-12
9-Apr-12
9-Apr-12
17-Jun-12
17-Apr-12
16-Oct-11
21-Oct-11
16-Oct-11
21-Oct-11
16-Oct-11
21-Oct-11
NonAsciiFileName0.xls 650 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
NonAsciiFileName0.xls 651 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2 Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
Norm Duration of Proc Steps
Component 1:(Instititional Development)
Training of Staff and Twining programme (To be
Implemented through global Training plan and
Twining arrangement for (January 2012 to Dec
2012)
Component 2:Public Transport and Traffic Management
Consultancy Services for Carrying out the Pre and
Post Study for the Establishment of Transport
Planning Units in Lagos Island, Kosofe and
Ikorodu LGAs in Lagos State
Consultancy Services for Detailed Engineering
Design and Construction Supervision of BRT LITE
Upgrade from Mile 12 to CMS
Consultancy Services for Conceptual Design of
BRT LITE Upgrade from Mile 12 to CMS
Consultancy Services for Engineering Design and
Construction Supervision of BFS Infrastructure
Rehabilitation and Upgrading
Consultancy Services for conducting Technical due
diligence on BFS Buses (Environmental
Enhancement of BFS Operations: Due Diligence
Report) Including Supervision of the
Refurbishment of BFS Buses
Submission
Evaluation
Report (T)
2 - 3 wks
N/A
17-Feb-13
N/A
N/A
N/A
Proposal Evaluation and Negotiation for Projects after May 2002
Technical (T) & Financial (F) and Negotions (N)
NonAsciiFileName0.xls 652 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Component 3: Improvement of Lagos State
Metropolitan Road Network
Component 4: Project Management & System Monitoring
Consultancy for Construction Supervision of Akin
Adesola and Wempco Roads
Consultancy Services for Design Upgrade and
Construction Supervision of BFS Bus Depot
Infrastructure
Consultancy Services for Website Redesign and
Hosting
Consultancy Services for IT Equipment
Maintenance
Consultancy Services for Events and Stakeholders
Management for BRT Services
Consultancy Services for Advertising and
Perception Management for BRT Extension (Mile
12 - Ikorodu)
Consultancy Services for Pavement Management
System Reconfiguration, Training and Data
Collection and Upload
Consultancy Services for the Documentation of the
Communication and Participation Efforts to Raise
Familiarity with BRT on Mile 12 to CMS Route
Consultancy to Conduct Stakeholder engagements
on other LAMATA projects (STMP, Road
rehabilitation/periodic maintenance etc)
Consultancy for Construction Supervision of
Adesina/Omilani/Airways Road Surulere
Consultancy for Construction Supervision of Apata
Lisabi Street Somolu
N/A
29-May-12
N/A
N/A
N/A
N/A
30-Sep-11
N/A
N/A
18-Oct-12
N/A
N/A
NonAsciiFileName0.xls 653 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Consultancy Services for Supply and installation
and Configuration of HDM4 Software for
LAMATA including Training
Consultancy Services for Provision, Installation
and Implementation of Knowledge Management
Software
Consultancy Services for Supply and installation
and configuratin of internet solution for LAMATA
(Share point)
Consultancy Services for the Provision of 1M
Internet Access
Consultancy Services for Oracle Support Licence
Consultancy Services for IT Equipment
Maintenance
Consultancy Services for EDMS Maintenance
Consultancy Services for Antivirus Support
Consultancy Services for Anti-Spam Support
Consultancy Services for Cloud Storage / Data
Backup
Consultancy Services for Arc GIS & Arc View
Upgrade and Licensing + HP Large format Plotter
Consultancy Services for Institutional, Technical
and Financial Audit
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
22-Feb-13
NonAsciiFileName0.xls 654 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Consultancy Services for Conducting Resettlement
Policy Framework (RPF) for Akin Adesola &
Wempco Roads
Consultancy Services for Resettlement Action Plan
(RAP) Implementation for Mile 12 to Ikorodu BRT
scheme
Consultancy Services for Procurement Audit for 2
consecutive years
Consultancy Services for Assesment of Needs of
Disadvantaged Group in Accessing Public
Transport Services on Mile 12 to Ikorodu Town
BRT Corridor
Consultancy Services for Carrying out Socio-
Economic Baseline Survey of Transportation from
Mile 12 to Ikorodu
Consultancy Services for Institutional, Technical
and Financial Audit
Consultancy Services for Developing the core
public Transport Network in Kano -Rapid
Development of Shor-time Program Investment
Consultancy Services for Developing the core
public Transport Network in Kano -Rapid
Collection of Traffic and Transport Data
Consultancy Service for Inestigating the impact of
Motocycles and Three Wheelers Growth in Africa -
Case Study of Kano
Consultancy Services for Conducting
Environmental and Social Management Plan
(ESMP) for Akin Adesola and Wempco Roads
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
NonAsciiFileName0.xls 655 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
NonAsciiFileName0.xls 656 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2 Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
Norm Duration of Proc Steps
Component 1:(Instititional Development)
Training of Staff and Twining programme (To be
Implemented through global Training plan and
Twining arrangement for (January 2012 to Dec
2012)
Component 2:Public Transport and Traffic Management
Consultancy Services for Carrying out the Pre and
Post Study for the Establishment of Transport
Planning Units in Lagos Island, Kosofe and
Ikorodu LGAs in Lagos State
Consultancy Services for Detailed Engineering
Design and Construction Supervision of BRT LITE
Upgrade from Mile 12 to CMS
Consultancy Services for Conceptual Design of
BRT LITE Upgrade from Mile 12 to CMS
Consultancy Services for Engineering Design and
Construction Supervision of BFS Infrastructure
Rehabilitation and Upgrading
Consultancy Services for conducting Technical due
diligence on BFS Buses (Environmental
Enhancement of BFS Operations: Due Diligence
Report) Including Supervision of the
Refurbishment of BFS Buses
No-objection
Evaluation
Report (T)
0.5 - 2 wks
N/A
3-Mar-13
N/A
N/A
N/A
Proposal Evaluation and Negotiation for Projects after May 2002
Technical (T) & Financial (F) and Negotions (N)
NonAsciiFileName0.xls 657 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Component 3: Improvement of Lagos State
Metropolitan Road Network
Component 4: Project Management & System Monitoring
Consultancy for Construction Supervision of Akin
Adesola and Wempco Roads
Consultancy Services for Design Upgrade and
Construction Supervision of BFS Bus Depot
Infrastructure
Consultancy Services for Website Redesign and
Hosting
Consultancy Services for IT Equipment
Maintenance
Consultancy Services for Events and Stakeholders
Management for BRT Services
Consultancy Services for Advertising and
Perception Management for BRT Extension (Mile
12 - Ikorodu)
Consultancy Services for Pavement Management
System Reconfiguration, Training and Data
Collection and Upload
Consultancy Services for the Documentation of the
Communication and Participation Efforts to Raise
Familiarity with BRT on Mile 12 to CMS Route
Consultancy to Conduct Stakeholder engagements
on other LAMATA projects (STMP, Road
rehabilitation/periodic maintenance etc)
Consultancy for Construction Supervision of
Adesina/Omilani/Airways Road Surulere
Consultancy for Construction Supervision of Apata
Lisabi Street Somolu
N/A
12-Jun-12
N/A
N/A
N/A
N/A
14-Oct-11
N/A
N/A
1-Nov-12
N/A
N/A
NonAsciiFileName0.xls 658 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Consultancy Services for Supply and installation
and Configuration of HDM4 Software for
LAMATA including Training
Consultancy Services for Provision, Installation
and Implementation of Knowledge Management
Software
Consultancy Services for Supply and installation
and configuratin of internet solution for LAMATA
(Share point)
Consultancy Services for the Provision of 1M
Internet Access
Consultancy Services for Oracle Support Licence
Consultancy Services for IT Equipment
Maintenance
Consultancy Services for EDMS Maintenance
Consultancy Services for Antivirus Support
Consultancy Services for Anti-Spam Support
Consultancy Services for Cloud Storage / Data
Backup
Consultancy Services for Arc GIS & Arc View
Upgrade and Licensing + HP Large format Plotter
Consultancy Services for Institutional, Technical
and Financial Audit
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
8-Mar-13
NonAsciiFileName0.xls 659 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Consultancy Services for Conducting Resettlement
Policy Framework (RPF) for Akin Adesola &
Wempco Roads
Consultancy Services for Resettlement Action Plan
(RAP) Implementation for Mile 12 to Ikorodu BRT
scheme
Consultancy Services for Procurement Audit for 2
consecutive years
Consultancy Services for Assesment of Needs of
Disadvantaged Group in Accessing Public
Transport Services on Mile 12 to Ikorodu Town
BRT Corridor
Consultancy Services for Carrying out Socio-
Economic Baseline Survey of Transportation from
Mile 12 to Ikorodu
Consultancy Services for Institutional, Technical
and Financial Audit
Consultancy Services for Developing the core
public Transport Network in Kano -Rapid
Development of Shor-time Program Investment
Consultancy Services for Developing the core
public Transport Network in Kano -Rapid
Collection of Traffic and Transport Data
Consultancy Service for Inestigating the impact of
Motocycles and Three Wheelers Growth in Africa -
Case Study of Kano
Consultancy Services for Conducting
Environmental and Social Management Plan
(ESMP) for Akin Adesola and Wempco Roads
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
NonAsciiFileName0.xls 660 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
NonAsciiFileName0.xls 661 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2 Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
Norm Duration of Proc Steps
Component 1:(Instititional Development)
Training of Staff and Twining programme (To be
Implemented through global Training plan and
Twining arrangement for (January 2012 to Dec
2012)
Component 2:Public Transport and Traffic Management
Consultancy Services for Carrying out the Pre and
Post Study for the Establishment of Transport
Planning Units in Lagos Island, Kosofe and
Ikorodu LGAs in Lagos State
Consultancy Services for Detailed Engineering
Design and Construction Supervision of BRT LITE
Upgrade from Mile 12 to CMS
Consultancy Services for Conceptual Design of
BRT LITE Upgrade from Mile 12 to CMS
Consultancy Services for Engineering Design and
Construction Supervision of BFS Infrastructure
Rehabilitation and Upgrading
Consultancy Services for conducting Technical due
diligence on BFS Buses (Environmental
Enhancement of BFS Operations: Due Diligence
Report) Including Supervision of the
Refurbishment of BFS Buses
Opening Financial
Proposals
2 wks
N/A
17-Feb-13
N/A
N/A
N/A
Proposal Evaluation and Negotiation for Projects after May 2002
Technical (T) & Financial (F) and Negotions (N)
NonAsciiFileName0.xls 662 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Component 3: Improvement of Lagos State
Metropolitan Road Network
Component 4: Project Management & System Monitoring
Consultancy for Construction Supervision of Akin
Adesola and Wempco Roads
Consultancy Services for Design Upgrade and
Construction Supervision of BFS Bus Depot
Infrastructure
Consultancy Services for Website Redesign and
Hosting
Consultancy Services for IT Equipment
Maintenance
Consultancy Services for Events and Stakeholders
Management for BRT Services
Consultancy Services for Advertising and
Perception Management for BRT Extension (Mile
12 - Ikorodu)
Consultancy Services for Pavement Management
System Reconfiguration, Training and Data
Collection and Upload
Consultancy Services for the Documentation of the
Communication and Participation Efforts to Raise
Familiarity with BRT on Mile 12 to CMS Route
Consultancy to Conduct Stakeholder engagements
on other LAMATA projects (STMP, Road
rehabilitation/periodic maintenance etc)
Consultancy for Construction Supervision of
Adesina/Omilani/Airways Road Surulere
Consultancy for Construction Supervision of Apata
Lisabi Street Somolu
N/A
19-Jun-12
N/A
N/A
N/A
N/A
21-Oct-11
N/A
N/A
18-Oct-12
N/A
N/A
NonAsciiFileName0.xls 663 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Consultancy Services for Supply and installation
and Configuration of HDM4 Software for
LAMATA including Training
Consultancy Services for Provision, Installation
and Implementation of Knowledge Management
Software
Consultancy Services for Supply and installation
and configuratin of internet solution for LAMATA
(Share point)
Consultancy Services for the Provision of 1M
Internet Access
Consultancy Services for Oracle Support Licence
Consultancy Services for IT Equipment
Maintenance
Consultancy Services for EDMS Maintenance
Consultancy Services for Antivirus Support
Consultancy Services for Anti-Spam Support
Consultancy Services for Cloud Storage / Data
Backup
Consultancy Services for Arc GIS & Arc View
Upgrade and Licensing + HP Large format Plotter
Consultancy Services for Institutional, Technical
and Financial Audit
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
15-Mar-13
NonAsciiFileName0.xls 664 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Consultancy Services for Conducting Resettlement
Policy Framework (RPF) for Akin Adesola &
Wempco Roads
Consultancy Services for Resettlement Action Plan
(RAP) Implementation for Mile 12 to Ikorodu BRT
scheme
Consultancy Services for Procurement Audit for 2
consecutive years
Consultancy Services for Assesment of Needs of
Disadvantaged Group in Accessing Public
Transport Services on Mile 12 to Ikorodu Town
BRT Corridor
Consultancy Services for Carrying out Socio-
Economic Baseline Survey of Transportation from
Mile 12 to Ikorodu
Consultancy Services for Institutional, Technical
and Financial Audit
Consultancy Services for Developing the core
public Transport Network in Kano -Rapid
Development of Shor-time Program Investment
Consultancy Services for Developing the core
public Transport Network in Kano -Rapid
Collection of Traffic and Transport Data
Consultancy Service for Inestigating the impact of
Motocycles and Three Wheelers Growth in Africa -
Case Study of Kano
Consultancy Services for Conducting
Environmental and Social Management Plan
(ESMP) for Akin Adesola and Wempco Roads
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
NonAsciiFileName0.xls 665 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
NonAsciiFileName0.xls 666 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2 Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
Norm Duration of Proc Steps
Component 1:(Instititional Development)
Training of Staff and Twining programme (To be
Implemented through global Training plan and
Twining arrangement for (January 2012 to Dec
2012)
Component 2:Public Transport and Traffic Management
Consultancy Services for Carrying out the Pre and
Post Study for the Establishment of Transport
Planning Units in Lagos Island, Kosofe and
Ikorodu LGAs in Lagos State
Consultancy Services for Detailed Engineering
Design and Construction Supervision of BRT LITE
Upgrade from Mile 12 to CMS
Consultancy Services for Conceptual Design of
BRT LITE Upgrade from Mile 12 to CMS
Consultancy Services for Engineering Design and
Construction Supervision of BFS Infrastructure
Rehabilitation and Upgrading
Consultancy Services for conducting Technical due
diligence on BFS Buses (Environmental
Enhancement of BFS Operations: Due Diligence
Report) Including Supervision of the
Refurbishment of BFS Buses
Preparation
Eval Report
(T) (F)
1 - 2 wks
9-Jun-12
24-Feb-13
8-Apr-12
12-Aug-12
9-Feb-13
Proposal Evaluation and Negotiation for Projects after May 2002
Technical (T) & Financial (F) and Negotions (N)
NonAsciiFileName0.xls 667 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Component 3: Improvement of Lagos State
Metropolitan Road Network
Component 4: Project Management & System Monitoring
Consultancy for Construction Supervision of Akin
Adesola and Wempco Roads
Consultancy Services for Design Upgrade and
Construction Supervision of BFS Bus Depot
Infrastructure
Consultancy Services for Website Redesign and
Hosting
Consultancy Services for IT Equipment
Maintenance
Consultancy Services for Events and Stakeholders
Management for BRT Services
Consultancy Services for Advertising and
Perception Management for BRT Extension (Mile
12 - Ikorodu)
Consultancy Services for Pavement Management
System Reconfiguration, Training and Data
Collection and Upload
Consultancy Services for the Documentation of the
Communication and Participation Efforts to Raise
Familiarity with BRT on Mile 12 to CMS Route
Consultancy to Conduct Stakeholder engagements
on other LAMATA projects (STMP, Road
rehabilitation/periodic maintenance etc)
Consultancy for Construction Supervision of
Adesina/Omilani/Airways Road Surulere
Consultancy for Construction Supervision of Apata
Lisabi Street Somolu
4-Jun-12
26-Jun-12
22-Jan-12
6-Jan-12
18-Apr-12
18-Apr-12
28-Oct-11
22-Nov-12
22-Nov-12
25-Oct-12
16-Apr-12
28-Feb-12
NonAsciiFileName0.xls 668 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Consultancy Services for Supply and installation
and Configuration of HDM4 Software for
LAMATA including Training
Consultancy Services for Provision, Installation
and Implementation of Knowledge Management
Software
Consultancy Services for Supply and installation
and configuratin of internet solution for LAMATA
(Share point)
Consultancy Services for the Provision of 1M
Internet Access
Consultancy Services for Oracle Support Licence
Consultancy Services for IT Equipment
Maintenance
Consultancy Services for EDMS Maintenance
Consultancy Services for Antivirus Support
Consultancy Services for Anti-Spam Support
Consultancy Services for Cloud Storage / Data
Backup
Consultancy Services for Arc GIS & Arc View
Upgrade and Licensing + HP Large format Plotter
Consultancy Services for Institutional, Technical
and Financial Audit
3-Jun-12
19-Jun-12
5-Jul-12
10-Oct-12
19-Apr-12
8-Jun-12
5-Jul-12
9-Nov-12
8-Oct-12
10-Sep-12
22-Mar-13
NonAsciiFileName0.xls 669 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Consultancy Services for Conducting Resettlement
Policy Framework (RPF) for Akin Adesola &
Wempco Roads
Consultancy Services for Resettlement Action Plan
(RAP) Implementation for Mile 12 to Ikorodu BRT
scheme
Consultancy Services for Procurement Audit for 2
consecutive years
Consultancy Services for Assesment of Needs of
Disadvantaged Group in Accessing Public
Transport Services on Mile 12 to Ikorodu Town
BRT Corridor
Consultancy Services for Carrying out Socio-
Economic Baseline Survey of Transportation from
Mile 12 to Ikorodu
Consultancy Services for Institutional, Technical
and Financial Audit
Consultancy Services for Developing the core
public Transport Network in Kano -Rapid
Development of Shor-time Program Investment
Consultancy Services for Developing the core
public Transport Network in Kano -Rapid
Collection of Traffic and Transport Data
Consultancy Service for Inestigating the impact of
Motocycles and Three Wheelers Growth in Africa -
Case Study of Kano
Consultancy Services for Conducting
Environmental and Social Management Plan
(ESMP) for Akin Adesola and Wempco Roads
16-Apr-12
16-Apr-12
16-Apr-12
16-Apr-12
24-Jun-12
24-Apr-12
6-Nov-11
30-Nov-11
6-Nov-11
30-Nov-11
6-Nov-11
30-Nov-11
NonAsciiFileName0.xls 670 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
NonAsciiFileName0.xls 671 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2 Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
Norm Duration of Proc Steps
Component 1:(Instititional Development)
Training of Staff and Twining programme (To be
Implemented through global Training plan and
Twining arrangement for (January 2012 to Dec
2012)
Component 2:Public Transport and Traffic Management
Consultancy Services for Carrying out the Pre and
Post Study for the Establishment of Transport
Planning Units in Lagos Island, Kosofe and
Ikorodu LGAs in Lagos State
Consultancy Services for Detailed Engineering
Design and Construction Supervision of BRT LITE
Upgrade from Mile 12 to CMS
Consultancy Services for Conceptual Design of
BRT LITE Upgrade from Mile 12 to CMS
Consultancy Services for Engineering Design and
Construction Supervision of BFS Infrastructure
Rehabilitation and Upgrading
Consultancy Services for conducting Technical due
diligence on BFS Buses (Environmental
Enhancement of BFS Operations: Due Diligence
Report) Including Supervision of the
Refurbishment of BFS Buses
Negotiations (N)
2 wks
16-Jun-12
3-Mar-13
15-Apr-12
19-Aug-12
16-Feb-13
Proposal Evaluation and Negotiation for Projects after May 2002
Technical (T) & Financial (F) and Negotions (N)
NonAsciiFileName0.xls 672 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Component 3: Improvement of Lagos State
Metropolitan Road Network
Component 4: Project Management & System Monitoring
Consultancy for Construction Supervision of Akin
Adesola and Wempco Roads
Consultancy Services for Design Upgrade and
Construction Supervision of BFS Bus Depot
Infrastructure
Consultancy Services for Website Redesign and
Hosting
Consultancy Services for IT Equipment
Maintenance
Consultancy Services for Events and Stakeholders
Management for BRT Services
Consultancy Services for Advertising and
Perception Management for BRT Extension (Mile
12 - Ikorodu)
Consultancy Services for Pavement Management
System Reconfiguration, Training and Data
Collection and Upload
Consultancy Services for the Documentation of the
Communication and Participation Efforts to Raise
Familiarity with BRT on Mile 12 to CMS Route
Consultancy to Conduct Stakeholder engagements
on other LAMATA projects (STMP, Road
rehabilitation/periodic maintenance etc)
Consultancy for Construction Supervision of
Adesina/Omilani/Airways Road Surulere
Consultancy for Construction Supervision of Apata
Lisabi Street Somolu
18-Jun-12
10-Jul-12
31-Jan-12
25-Apr-12
25-Apr-12
4-Nov-11
29-Nov-12
29-Nov-12
1-Nov-12
23-Apr-12
6-Mar-12
NonAsciiFileName0.xls 673 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Consultancy Services for Supply and installation
and Configuration of HDM4 Software for
LAMATA including Training
Consultancy Services for Provision, Installation
and Implementation of Knowledge Management
Software
Consultancy Services for Supply and installation
and configuratin of internet solution for LAMATA
(Share point)
Consultancy Services for the Provision of 1M
Internet Access
Consultancy Services for Oracle Support Licence
Consultancy Services for IT Equipment
Maintenance
Consultancy Services for EDMS Maintenance
Consultancy Services for Antivirus Support
Consultancy Services for Anti-Spam Support
Consultancy Services for Cloud Storage / Data
Backup
Consultancy Services for Arc GIS & Arc View
Upgrade and Licensing + HP Large format Plotter
Consultancy Services for Institutional, Technical
and Financial Audit
10-Jun-12
26-Jun-12
12-Jul-12
17-Oct-12
26-Apr-12
15-Jun-12
12-Jul-12
16-Nov-12
15-Oct-12
17-Sep-12
5-Apr-13
NonAsciiFileName0.xls 674 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Consultancy Services for Conducting Resettlement
Policy Framework (RPF) for Akin Adesola &
Wempco Roads
Consultancy Services for Resettlement Action Plan
(RAP) Implementation for Mile 12 to Ikorodu BRT
scheme
Consultancy Services for Procurement Audit for 2
consecutive years
Consultancy Services for Assesment of Needs of
Disadvantaged Group in Accessing Public
Transport Services on Mile 12 to Ikorodu Town
BRT Corridor
Consultancy Services for Carrying out Socio-
Economic Baseline Survey of Transportation from
Mile 12 to Ikorodu
Consultancy Services for Institutional, Technical
and Financial Audit
Consultancy Services for Developing the core
public Transport Network in Kano -Rapid
Development of Shor-time Program Investment
Consultancy Services for Developing the core
public Transport Network in Kano -Rapid
Collection of Traffic and Transport Data
Consultancy Service for Inestigating the impact of
Motocycles and Three Wheelers Growth in Africa -
Case Study of Kano
Consultancy Services for Conducting
Environmental and Social Management Plan
(ESMP) for Akin Adesola and Wempco Roads
23-Apr-12
23-Apr-12
23-Apr-12
23-Apr-12
1-Jul-12
1-May-12
16-Feb-12
16-Feb-12
16-Feb-12
NonAsciiFileName0.xls 675 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
NonAsciiFileName0.xls 676 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2 Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
Norm Duration of Proc Steps
Component 1:(Instititional Development)
Training of Staff and Twining programme (To be
Implemented through global Training plan and
Twining arrangement for (January 2012 to Dec
2012)
Component 2:Public Transport and Traffic Management
Consultancy Services for Carrying out the Pre and
Post Study for the Establishment of Transport
Planning Units in Lagos Island, Kosofe and
Ikorodu LGAs in Lagos State
Consultancy Services for Detailed Engineering
Design and Construction Supervision of BRT LITE
Upgrade from Mile 12 to CMS
Consultancy Services for Conceptual Design of
BRT LITE Upgrade from Mile 12 to CMS
Consultancy Services for Engineering Design and
Construction Supervision of BFS Infrastructure
Rehabilitation and Upgrading
Consultancy Services for conducting Technical due
diligence on BFS Buses (Environmental
Enhancement of BFS Operations: Due Diligence
Report) Including Supervision of the
Refurbishment of BFS Buses
Plan vs.
Actual
Plan
Plan
Plan
Actual
Plan
Actual
Plan
Actual
Plan
Actual
Plan
Actual
NonAsciiFileName0.xls 677 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Component 3: Improvement of Lagos State
Metropolitan Road Network
Component 4: Project Management & System Monitoring
Consultancy for Construction Supervision of Akin
Adesola and Wempco Roads
Consultancy Services for Design Upgrade and
Construction Supervision of BFS Bus Depot
Infrastructure
Consultancy Services for Website Redesign and
Hosting
Consultancy Services for IT Equipment
Maintenance
Consultancy Services for Events and Stakeholders
Management for BRT Services
Consultancy Services for Advertising and
Perception Management for BRT Extension (Mile
12 - Ikorodu)
Consultancy Services for Pavement Management
System Reconfiguration, Training and Data
Collection and Upload
Consultancy Services for the Documentation of the
Communication and Participation Efforts to Raise
Familiarity with BRT on Mile 12 to CMS Route
Consultancy to Conduct Stakeholder engagements
on other LAMATA projects (STMP, Road
rehabilitation/periodic maintenance etc)
Consultancy for Construction Supervision of
Adesina/Omilani/Airways Road Surulere
Consultancy for Construction Supervision of Apata
Lisabi Street Somolu
Plan
Actual
Plan
Actual
Plan
Actual
Plan
Actual
Plan
Actual
Plan
Plan
Actual
Plan
Actual
Plan
Actual
Plan
Actual
Plan
NonAsciiFileName0.xls 678 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Consultancy Services for Supply and installation
and Configuration of HDM4 Software for
LAMATA including Training
Consultancy Services for Provision, Installation
and Implementation of Knowledge Management
Software
Consultancy Services for Supply and installation
and configuratin of internet solution for LAMATA
(Share point)
Consultancy Services for the Provision of 1M
Internet Access
Consultancy Services for Oracle Support Licence
Consultancy Services for IT Equipment
Maintenance
Consultancy Services for EDMS Maintenance
Consultancy Services for Antivirus Support
Consultancy Services for Anti-Spam Support
Consultancy Services for Cloud Storage / Data
Backup
Consultancy Services for Arc GIS & Arc View
Upgrade and Licensing + HP Large format Plotter
Consultancy Services for Institutional, Technical
and Financial Audit
Actual
Plan
Actual
Plan
Actual
Plan
Actual
Plan
Actual
Plan
Actual
Plan
Actual
Plan
Actual
Plan
Actual
Plan
Actual
Plan
Actual
Plan
NonAsciiFileName0.xls 679 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Consultancy Services for Conducting Resettlement
Policy Framework (RPF) for Akin Adesola &
Wempco Roads
Consultancy Services for Resettlement Action Plan
(RAP) Implementation for Mile 12 to Ikorodu BRT
scheme
Consultancy Services for Procurement Audit for 2
consecutive years
Consultancy Services for Assesment of Needs of
Disadvantaged Group in Accessing Public
Transport Services on Mile 12 to Ikorodu Town
BRT Corridor
Consultancy Services for Carrying out Socio-
Economic Baseline Survey of Transportation from
Mile 12 to Ikorodu
Consultancy Services for Institutional, Technical
and Financial Audit
Consultancy Services for Developing the core
public Transport Network in Kano -Rapid
Development of Shor-time Program Investment
Consultancy Services for Developing the core
public Transport Network in Kano -Rapid
Collection of Traffic and Transport Data
Consultancy Service for Inestigating the impact of
Motocycles and Three Wheelers Growth in Africa -
Case Study of Kano
Consultancy Services for Conducting
Environmental and Social Management Plan
(ESMP) for Akin Adesola and Wempco Roads
Actual
Plan
Actual
Plan
Actual
Plan
Actual
Plan
Actual
Plan
Actual
Plan
Actual
Plan
Actual
Plan
Actual
Plan
Actual
NonAsciiFileName0.xls 680 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
NonAsciiFileName0.xls 681 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2 Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
Norm Duration of Proc Steps
Component 1:(Instititional Development)
Training of Staff and Twining programme (To be
Implemented through global Training plan and
Twining arrangement for (January 2012 to Dec
2012)
Component 2:Public Transport and Traffic Management
Consultancy Services for Carrying out the Pre and
Post Study for the Establishment of Transport
Planning Units in Lagos Island, Kosofe and
Ikorodu LGAs in Lagos State
Consultancy Services for Detailed Engineering
Design and Construction Supervision of BRT LITE
Upgrade from Mile 12 to CMS
Consultancy Services for Conceptual Design of
BRT LITE Upgrade from Mile 12 to CMS
Consultancy Services for Engineering Design and
Construction Supervision of BFS Infrastructure
Rehabilitation and Upgrading
Consultancy Services for conducting Technical due
diligence on BFS Buses (Environmental
Enhancement of BFS Operations: Due Diligence
Report) Including Supervision of the
Refurbishment of BFS Buses
Submission Date
1 - 2 wks
N/A
17-Mar-13
N/A
N/A
N/A
Draft Contract
NonAsciiFileName0.xls 682 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Component 3: Improvement of Lagos State
Metropolitan Road Network
Component 4: Project Management & System Monitoring
Consultancy for Construction Supervision of Akin
Adesola and Wempco Roads
Consultancy Services for Design Upgrade and
Construction Supervision of BFS Bus Depot
Infrastructure
Consultancy Services for Website Redesign and
Hosting
Consultancy Services for IT Equipment
Maintenance
Consultancy Services for Events and Stakeholders
Management for BRT Services
Consultancy Services for Advertising and
Perception Management for BRT Extension (Mile
12 - Ikorodu)
Consultancy Services for Pavement Management
System Reconfiguration, Training and Data
Collection and Upload
Consultancy Services for the Documentation of the
Communication and Participation Efforts to Raise
Familiarity with BRT on Mile 12 to CMS Route
Consultancy to Conduct Stakeholder engagements
on other LAMATA projects (STMP, Road
rehabilitation/periodic maintenance etc)
Consultancy for Construction Supervision of
Adesina/Omilani/Airways Road Surulere
Consultancy for Construction Supervision of Apata
Lisabi Street Somolu
2-Jul-12
24-Jul-12
N/A
N/A
N/A
11-Nov-11
N/A
N/A
15-Nov-12
N/A
N/A
NonAsciiFileName0.xls 683 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Consultancy Services for Supply and installation
and Configuration of HDM4 Software for
LAMATA including Training
Consultancy Services for Provision, Installation
and Implementation of Knowledge Management
Software
Consultancy Services for Supply and installation
and configuratin of internet solution for LAMATA
(Share point)
Consultancy Services for the Provision of 1M
Internet Access
Consultancy Services for Oracle Support Licence
Consultancy Services for IT Equipment
Maintenance
Consultancy Services for EDMS Maintenance
Consultancy Services for Antivirus Support
Consultancy Services for Anti-Spam Support
Consultancy Services for Cloud Storage / Data
Backup
Consultancy Services for Arc GIS & Arc View
Upgrade and Licensing + HP Large format Plotter
Consultancy Services for Institutional, Technical
and Financial Audit
17-Jun-12
N/A
N/A
24-Oct-12
3-May-12
N/A
N/A
23-Nov-12
N/A
N/A
19-Apr-13
NonAsciiFileName0.xls 684 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Consultancy Services for Conducting Resettlement
Policy Framework (RPF) for Akin Adesola &
Wempco Roads
Consultancy Services for Resettlement Action Plan
(RAP) Implementation for Mile 12 to Ikorodu BRT
scheme
Consultancy Services for Procurement Audit for 2
consecutive years
Consultancy Services for Assesment of Needs of
Disadvantaged Group in Accessing Public
Transport Services on Mile 12 to Ikorodu Town
BRT Corridor
Consultancy Services for Carrying out Socio-
Economic Baseline Survey of Transportation from
Mile 12 to Ikorodu
Consultancy Services for Institutional, Technical
and Financial Audit
Consultancy Services for Developing the core
public Transport Network in Kano -Rapid
Development of Shor-time Program Investment
Consultancy Services for Developing the core
public Transport Network in Kano -Rapid
Collection of Traffic and Transport Data
Consultancy Service for Inestigating the impact of
Motocycles and Three Wheelers Growth in Africa -
Case Study of Kano
Consultancy Services for Conducting
Environmental and Social Management Plan
(ESMP) for Akin Adesola and Wempco Roads
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
NonAsciiFileName0.xls 685 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
NonAsciiFileName0.xls 686 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2 Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
Norm Duration of Proc Steps
Component 1:(Instititional Development)
Training of Staff and Twining programme (To be
Implemented through global Training plan and
Twining arrangement for (January 2012 to Dec
2012)
Component 2:Public Transport and Traffic Management
Consultancy Services for Carrying out the Pre and
Post Study for the Establishment of Transport
Planning Units in Lagos Island, Kosofe and
Ikorodu LGAs in Lagos State
Consultancy Services for Detailed Engineering
Design and Construction Supervision of BRT LITE
Upgrade from Mile 12 to CMS
Consultancy Services for Conceptual Design of
BRT LITE Upgrade from Mile 12 to CMS
Consultancy Services for Engineering Design and
Construction Supervision of BFS Infrastructure
Rehabilitation and Upgrading
Consultancy Services for conducting Technical due
diligence on BFS Buses (Environmental
Enhancement of BFS Operations: Due Diligence
Report) Including Supervision of the
Refurbishment of BFS Buses
No-objection Date
1 - 2 wks
N/A
29-Mar-13
N/A
N/A
N/A
Draft Contract
NonAsciiFileName0.xls 687 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Component 3: Improvement of Lagos State
Metropolitan Road Network
Component 4: Project Management & System Monitoring
Consultancy for Construction Supervision of Akin
Adesola and Wempco Roads
Consultancy Services for Design Upgrade and
Construction Supervision of BFS Bus Depot
Infrastructure
Consultancy Services for Website Redesign and
Hosting
Consultancy Services for IT Equipment
Maintenance
Consultancy Services for Events and Stakeholders
Management for BRT Services
Consultancy Services for Advertising and
Perception Management for BRT Extension (Mile
12 - Ikorodu)
Consultancy Services for Pavement Management
System Reconfiguration, Training and Data
Collection and Upload
Consultancy Services for the Documentation of the
Communication and Participation Efforts to Raise
Familiarity with BRT on Mile 12 to CMS Route
Consultancy to Conduct Stakeholder engagements
on other LAMATA projects (STMP, Road
rehabilitation/periodic maintenance etc)
Consultancy for Construction Supervision of
Adesina/Omilani/Airways Road Surulere
Consultancy for Construction Supervision of Apata
Lisabi Street Somolu
16-Jul-12
7-Aug-12
N/A
N/A
N/A
18-Nov-11
N/A
N/A
27-Nov-12
N/A
N/A
NonAsciiFileName0.xls 688 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Consultancy Services for Supply and installation
and Configuration of HDM4 Software for
LAMATA including Training
Consultancy Services for Provision, Installation
and Implementation of Knowledge Management
Software
Consultancy Services for Supply and installation
and configuratin of internet solution for LAMATA
(Share point)
Consultancy Services for the Provision of 1M
Internet Access
Consultancy Services for Oracle Support Licence
Consultancy Services for IT Equipment
Maintenance
Consultancy Services for EDMS Maintenance
Consultancy Services for Antivirus Support
Consultancy Services for Anti-Spam Support
Consultancy Services for Cloud Storage / Data
Backup
Consultancy Services for Arc GIS & Arc View
Upgrade and Licensing + HP Large format Plotter
Consultancy Services for Institutional, Technical
and Financial Audit
27-Jun-12
N/A
N/A
3-Nov-12
13-May-12
N/A
N/A
3-Dec-12
N/A
N/A
3-May-13
NonAsciiFileName0.xls 689 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Consultancy Services for Conducting Resettlement
Policy Framework (RPF) for Akin Adesola &
Wempco Roads
Consultancy Services for Resettlement Action Plan
(RAP) Implementation for Mile 12 to Ikorodu BRT
scheme
Consultancy Services for Procurement Audit for 2
consecutive years
Consultancy Services for Assesment of Needs of
Disadvantaged Group in Accessing Public
Transport Services on Mile 12 to Ikorodu Town
BRT Corridor
Consultancy Services for Carrying out Socio-
Economic Baseline Survey of Transportation from
Mile 12 to Ikorodu
Consultancy Services for Institutional, Technical
and Financial Audit
Consultancy Services for Developing the core
public Transport Network in Kano -Rapid
Development of Shor-time Program Investment
Consultancy Services for Developing the core
public Transport Network in Kano -Rapid
Collection of Traffic and Transport Data
Consultancy Service for Inestigating the impact of
Motocycles and Three Wheelers Growth in Africa -
Case Study of Kano
Consultancy Services for Conducting
Environmental and Social Management Plan
(ESMP) for Akin Adesola and Wempco Roads
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
NonAsciiFileName0.xls 690 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
NonAsciiFileName0.xls 691 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2 Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
Norm Duration of Proc Steps
Component 1:(Instititional Development)
Training of Staff and Twining programme (To be
Implemented through global Training plan and
Twining arrangement for (January 2012 to Dec
2012)
Component 2:Public Transport and Traffic Management
Consultancy Services for Carrying out the Pre and
Post Study for the Establishment of Transport
Planning Units in Lagos Island, Kosofe and
Ikorodu LGAs in Lagos State
Consultancy Services for Detailed Engineering
Design and Construction Supervision of BRT LITE
Upgrade from Mile 12 to CMS
Consultancy Services for Conceptual Design of
BRT LITE Upgrade from Mile 12 to CMS
Consultancy Services for Engineering Design and
Construction Supervision of BFS Infrastructure
Rehabilitation and Upgrading
Consultancy Services for conducting Technical due
diligence on BFS Buses (Environmental
Enhancement of BFS Operations: Due Diligence
Report) Including Supervision of the
Refurbishment of BFS Buses
Contract Award
1 wk
24-Jun-12
5-Apr-13
23-Apr-12
27-Aug-12
24-Feb-13
NonAsciiFileName0.xls 692 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Component 3: Improvement of Lagos State
Metropolitan Road Network
Component 4: Project Management & System Monitoring
Consultancy for Construction Supervision of Akin
Adesola and Wempco Roads
Consultancy Services for Design Upgrade and
Construction Supervision of BFS Bus Depot
Infrastructure
Consultancy Services for Website Redesign and
Hosting
Consultancy Services for IT Equipment
Maintenance
Consultancy Services for Events and Stakeholders
Management for BRT Services
Consultancy Services for Advertising and
Perception Management for BRT Extension (Mile
12 - Ikorodu)
Consultancy Services for Pavement Management
System Reconfiguration, Training and Data
Collection and Upload
Consultancy Services for the Documentation of the
Communication and Participation Efforts to Raise
Familiarity with BRT on Mile 12 to CMS Route
Consultancy to Conduct Stakeholder engagements
on other LAMATA projects (STMP, Road
rehabilitation/periodic maintenance etc)
Consultancy for Construction Supervision of
Adesina/Omilani/Airways Road Surulere
Consultancy for Construction Supervision of Apata
Lisabi Street Somolu
26-Jun-12
14-Aug-12
8-Feb-12
3-May-12
3-May-12
25-Nov-11
7-Dec-12
7-Dec-12
4-Dec-12
30-Apr-12
13-Mar-12
NonAsciiFileName0.xls 693 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Consultancy Services for Supply and installation
and Configuration of HDM4 Software for
LAMATA including Training
Consultancy Services for Provision, Installation
and Implementation of Knowledge Management
Software
Consultancy Services for Supply and installation
and configuratin of internet solution for LAMATA
(Share point)
Consultancy Services for the Provision of 1M
Internet Access
Consultancy Services for Oracle Support Licence
Consultancy Services for IT Equipment
Maintenance
Consultancy Services for EDMS Maintenance
Consultancy Services for Antivirus Support
Consultancy Services for Anti-Spam Support
Consultancy Services for Cloud Storage / Data
Backup
Consultancy Services for Arc GIS & Arc View
Upgrade and Licensing + HP Large format Plotter
Consultancy Services for Institutional, Technical
and Financial Audit
2-Jul-12
3-Jul-12
19-Jul-12
8-Nov-12
18-May-12
22-Jun-12
19-Jul-12
8-Dec-12
22-Oct-12
24-Sep-12
10-May-13
NonAsciiFileName0.xls 694 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Consultancy Services for Conducting Resettlement
Policy Framework (RPF) for Akin Adesola &
Wempco Roads
Consultancy Services for Resettlement Action Plan
(RAP) Implementation for Mile 12 to Ikorodu BRT
scheme
Consultancy Services for Procurement Audit for 2
consecutive years
Consultancy Services for Assesment of Needs of
Disadvantaged Group in Accessing Public
Transport Services on Mile 12 to Ikorodu Town
BRT Corridor
Consultancy Services for Carrying out Socio-
Economic Baseline Survey of Transportation from
Mile 12 to Ikorodu
Consultancy Services for Institutional, Technical
and Financial Audit
Consultancy Services for Developing the core
public Transport Network in Kano -Rapid
Development of Shor-time Program Investment
Consultancy Services for Developing the core
public Transport Network in Kano -Rapid
Collection of Traffic and Transport Data
Consultancy Service for Inestigating the impact of
Motocycles and Three Wheelers Growth in Africa -
Case Study of Kano
Consultancy Services for Conducting
Environmental and Social Management Plan
(ESMP) for Akin Adesola and Wempco Roads
30-Apr-12
30-Apr-12
30-Apr-12
30-Apr-12
9-Jul-12
9-May-12
23-Feb-12
23-Feb-12
23-Feb-12
NonAsciiFileName0.xls 695 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
NonAsciiFileName0.xls 696 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2 Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
Norm Duration of Proc Steps
Component 1:(Instititional Development)
Training of Staff and Twining programme (To be
Implemented through global Training plan and
Twining arrangement for (January 2012 to Dec
2012)
Component 2:Public Transport and Traffic Management
Consultancy Services for Carrying out the Pre and
Post Study for the Establishment of Transport
Planning Units in Lagos Island, Kosofe and
Ikorodu LGAs in Lagos State
Consultancy Services for Detailed Engineering
Design and Construction Supervision of BRT LITE
Upgrade from Mile 12 to CMS
Consultancy Services for Conceptual Design of
BRT LITE Upgrade from Mile 12 to CMS
Consultancy Services for Engineering Design and
Construction Supervision of BFS Infrastructure
Rehabilitation and Upgrading
Consultancy Services for conducting Technical due
diligence on BFS Buses (Environmental
Enhancement of BFS Operations: Due Diligence
Report) Including Supervision of the
Refurbishment of BFS Buses
Date
Contract
Advert
N/A
19-Apr-13
N/A
N/A
N/A
NonAsciiFileName0.xls 697 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Component 3: Improvement of Lagos State
Metropolitan Road Network
Component 4: Project Management & System Monitoring
Consultancy for Construction Supervision of Akin
Adesola and Wempco Roads
Consultancy Services for Design Upgrade and
Construction Supervision of BFS Bus Depot
Infrastructure
Consultancy Services for Website Redesign and
Hosting
Consultancy Services for IT Equipment
Maintenance
Consultancy Services for Events and Stakeholders
Management for BRT Services
Consultancy Services for Advertising and
Perception Management for BRT Extension (Mile
12 - Ikorodu)
Consultancy Services for Pavement Management
System Reconfiguration, Training and Data
Collection and Upload
Consultancy Services for the Documentation of the
Communication and Participation Efforts to Raise
Familiarity with BRT on Mile 12 to CMS Route
Consultancy to Conduct Stakeholder engagements
on other LAMATA projects (STMP, Road
rehabilitation/periodic maintenance etc)
Consultancy for Construction Supervision of
Adesina/Omilani/Airways Road Surulere
Consultancy for Construction Supervision of Apata
Lisabi Street Somolu
N/A
21-Aug-12
N/A
N/A
N/A
2-Dec-11
N/A
N/A
18-Dec-12
N/A
N/A
NonAsciiFileName0.xls 698 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Consultancy Services for Supply and installation
and Configuration of HDM4 Software for
LAMATA including Training
Consultancy Services for Provision, Installation
and Implementation of Knowledge Management
Software
Consultancy Services for Supply and installation
and configuratin of internet solution for LAMATA
(Share point)
Consultancy Services for the Provision of 1M
Internet Access
Consultancy Services for Oracle Support Licence
Consultancy Services for IT Equipment
Maintenance
Consultancy Services for EDMS Maintenance
Consultancy Services for Antivirus Support
Consultancy Services for Anti-Spam Support
Consultancy Services for Cloud Storage / Data
Backup
Consultancy Services for Arc GIS & Arc View
Upgrade and Licensing + HP Large format Plotter
Consultancy Services for Institutional, Technical
and Financial Audit
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
17-May-13
NonAsciiFileName0.xls 699 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Consultancy Services for Conducting Resettlement
Policy Framework (RPF) for Akin Adesola &
Wempco Roads
Consultancy Services for Resettlement Action Plan
(RAP) Implementation for Mile 12 to Ikorodu BRT
scheme
Consultancy Services for Procurement Audit for 2
consecutive years
Consultancy Services for Assesment of Needs of
Disadvantaged Group in Accessing Public
Transport Services on Mile 12 to Ikorodu Town
BRT Corridor
Consultancy Services for Carrying out Socio-
Economic Baseline Survey of Transportation from
Mile 12 to Ikorodu
Consultancy Services for Institutional, Technical
and Financial Audit
Consultancy Services for Developing the core
public Transport Network in Kano -Rapid
Development of Shor-time Program Investment
Consultancy Services for Developing the core
public Transport Network in Kano -Rapid
Collection of Traffic and Transport Data
Consultancy Service for Inestigating the impact of
Motocycles and Three Wheelers Growth in Africa -
Case Study of Kano
Consultancy Services for Conducting
Environmental and Social Management Plan
(ESMP) for Akin Adesola and Wempco Roads
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
NonAsciiFileName0.xls 700 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
NonAsciiFileName0.xls 701 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2 Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
Norm Duration of Proc Steps
Component 1:(Instititional Development)
Training of Staff and Twining programme (To be
Implemented through global Training plan and
Twining arrangement for (January 2012 to Dec
2012)
Component 2:Public Transport and Traffic Management
Consultancy Services for Carrying out the Pre and
Post Study for the Establishment of Transport
Planning Units in Lagos Island, Kosofe and
Ikorodu LGAs in Lagos State
Consultancy Services for Detailed Engineering
Design and Construction Supervision of BRT LITE
Upgrade from Mile 12 to CMS
Consultancy Services for Conceptual Design of
BRT LITE Upgrade from Mile 12 to CMS
Consultancy Services for Engineering Design and
Construction Supervision of BFS Infrastructure
Rehabilitation and Upgrading
Consultancy Services for conducting Technical due
diligence on BFS Buses (Environmental
Enhancement of BFS Operations: Due Diligence
Report) Including Supervision of the
Refurbishment of BFS Buses
Contract
Signature
1 - 3 wks
1-Jul-12
12-Apr-13
30-Apr-12
3-Sep-12
3-Mar-13
NonAsciiFileName0.xls 702 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Component 3: Improvement of Lagos State
Metropolitan Road Network
Component 4: Project Management & System Monitoring
Consultancy for Construction Supervision of Akin
Adesola and Wempco Roads
Consultancy Services for Design Upgrade and
Construction Supervision of BFS Bus Depot
Infrastructure
Consultancy Services for Website Redesign and
Hosting
Consultancy Services for IT Equipment
Maintenance
Consultancy Services for Events and Stakeholders
Management for BRT Services
Consultancy Services for Advertising and
Perception Management for BRT Extension (Mile
12 - Ikorodu)
Consultancy Services for Pavement Management
System Reconfiguration, Training and Data
Collection and Upload
Consultancy Services for the Documentation of the
Communication and Participation Efforts to Raise
Familiarity with BRT on Mile 12 to CMS Route
Consultancy to Conduct Stakeholder engagements
on other LAMATA projects (STMP, Road
rehabilitation/periodic maintenance etc)
Consultancy for Construction Supervision of
Adesina/Omilani/Airways Road Surulere
Consultancy for Construction Supervision of Apata
Lisabi Street Somolu
3-Jul-12
21-Aug-12
15-Feb-12
10-May-12
10-May-12
2-Dec-11
14-Dec-12
14-Dec-12
11-Dec-12
7-May-12
20-Mar-12
NonAsciiFileName0.xls 703 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Consultancy Services for Supply and installation
and Configuration of HDM4 Software for
LAMATA including Training
Consultancy Services for Provision, Installation
and Implementation of Knowledge Management
Software
Consultancy Services for Supply and installation
and configuratin of internet solution for LAMATA
(Share point)
Consultancy Services for the Provision of 1M
Internet Access
Consultancy Services for Oracle Support Licence
Consultancy Services for IT Equipment
Maintenance
Consultancy Services for EDMS Maintenance
Consultancy Services for Antivirus Support
Consultancy Services for Anti-Spam Support
Consultancy Services for Cloud Storage / Data
Backup
Consultancy Services for Arc GIS & Arc View
Upgrade and Licensing + HP Large format Plotter
Consultancy Services for Institutional, Technical
and Financial Audit
9-Jul-12
10-Jul-12
26-Jul-12
15-Nov-12
25-May-12
29-Jun-12
26-Jul-12
15-Dec-12
29-Oct-12
1-Oct-12
17-May-13
NonAsciiFileName0.xls 704 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Consultancy Services for Conducting Resettlement
Policy Framework (RPF) for Akin Adesola &
Wempco Roads
Consultancy Services for Resettlement Action Plan
(RAP) Implementation for Mile 12 to Ikorodu BRT
scheme
Consultancy Services for Procurement Audit for 2
consecutive years
Consultancy Services for Assesment of Needs of
Disadvantaged Group in Accessing Public
Transport Services on Mile 12 to Ikorodu Town
BRT Corridor
Consultancy Services for Carrying out Socio-
Economic Baseline Survey of Transportation from
Mile 12 to Ikorodu
Consultancy Services for Institutional, Technical
and Financial Audit
Consultancy Services for Developing the core
public Transport Network in Kano -Rapid
Development of Shor-time Program Investment
Consultancy Services for Developing the core
public Transport Network in Kano -Rapid
Collection of Traffic and Transport Data
Consultancy Service for Inestigating the impact of
Motocycles and Three Wheelers Growth in Africa -
Case Study of Kano
Consultancy Services for Conducting
Environmental and Social Management Plan
(ESMP) for Akin Adesola and Wempco Roads
7-May-12
7-May-12
7-May-12
7-May-12
16-Jul-12
16-May-12
1-Mar-12
1-Mar-12
1-Mar-12
NonAsciiFileName0.xls 705 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
NonAsciiFileName0.xls 706 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2 Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
Norm Duration of Proc Steps
Component 1:(Instititional Development)
Training of Staff and Twining programme (To be
Implemented through global Training plan and
Twining arrangement for (January 2012 to Dec
2012)
Component 2:Public Transport and Traffic Management
Consultancy Services for Carrying out the Pre and
Post Study for the Establishment of Transport
Planning Units in Lagos Island, Kosofe and
Ikorodu LGAs in Lagos State
Consultancy Services for Detailed Engineering
Design and Construction Supervision of BRT LITE
Upgrade from Mile 12 to CMS
Consultancy Services for Conceptual Design of
BRT LITE Upgrade from Mile 12 to CMS
Consultancy Services for Engineering Design and
Construction Supervision of BFS Infrastructure
Rehabilitation and Upgrading
Consultancy Services for conducting Technical due
diligence on BFS Buses (Environmental
Enhancement of BFS Operations: Due Diligence
Report) Including Supervision of the
Refurbishment of BFS Buses
Plan vs.
Actual
Plan
Plan
Plan
Actual
Plan
Actual
Plan
Actual
Plan
Actual
Plan
Actual
NonAsciiFileName0.xls 707 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Component 3: Improvement of Lagos State
Metropolitan Road Network
Component 4: Project Management & System Monitoring
Consultancy for Construction Supervision of Akin
Adesola and Wempco Roads
Consultancy Services for Design Upgrade and
Construction Supervision of BFS Bus Depot
Infrastructure
Consultancy Services for Website Redesign and
Hosting
Consultancy Services for IT Equipment
Maintenance
Consultancy Services for Events and Stakeholders
Management for BRT Services
Consultancy Services for Advertising and
Perception Management for BRT Extension (Mile
12 - Ikorodu)
Consultancy Services for Pavement Management
System Reconfiguration, Training and Data
Collection and Upload
Consultancy Services for the Documentation of the
Communication and Participation Efforts to Raise
Familiarity with BRT on Mile 12 to CMS Route
Consultancy to Conduct Stakeholder engagements
on other LAMATA projects (STMP, Road
rehabilitation/periodic maintenance etc)
Consultancy for Construction Supervision of
Adesina/Omilani/Airways Road Surulere
Consultancy for Construction Supervision of Apata
Lisabi Street Somolu
Plan
Actual
Plan
Actual
Plan
Actual
Plan
Actual
Plan
Actual
Plan
Plan
Actual
Plan
Actual
Plan
Actual
Plan
Actual
Plan
NonAsciiFileName0.xls 708 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Consultancy Services for Supply and installation
and Configuration of HDM4 Software for
LAMATA including Training
Consultancy Services for Provision, Installation
and Implementation of Knowledge Management
Software
Consultancy Services for Supply and installation
and configuratin of internet solution for LAMATA
(Share point)
Consultancy Services for the Provision of 1M
Internet Access
Consultancy Services for Oracle Support Licence
Consultancy Services for IT Equipment
Maintenance
Consultancy Services for EDMS Maintenance
Consultancy Services for Antivirus Support
Consultancy Services for Anti-Spam Support
Consultancy Services for Cloud Storage / Data
Backup
Consultancy Services for Arc GIS & Arc View
Upgrade and Licensing + HP Large format Plotter
Consultancy Services for Institutional, Technical
and Financial Audit
Actual
Plan
Actual
Plan
Actual
Plan
Actual
Plan
Actual
Plan
Actual
Plan
Actual
Plan
Actual
Plan
Actual
Plan
Actual
Plan
Actual
Plan
NonAsciiFileName0.xls 709 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Consultancy Services for Conducting Resettlement
Policy Framework (RPF) for Akin Adesola &
Wempco Roads
Consultancy Services for Resettlement Action Plan
(RAP) Implementation for Mile 12 to Ikorodu BRT
scheme
Consultancy Services for Procurement Audit for 2
consecutive years
Consultancy Services for Assesment of Needs of
Disadvantaged Group in Accessing Public
Transport Services on Mile 12 to Ikorodu Town
BRT Corridor
Consultancy Services for Carrying out Socio-
Economic Baseline Survey of Transportation from
Mile 12 to Ikorodu
Consultancy Services for Institutional, Technical
and Financial Audit
Consultancy Services for Developing the core
public Transport Network in Kano -Rapid
Development of Shor-time Program Investment
Consultancy Services for Developing the core
public Transport Network in Kano -Rapid
Collection of Traffic and Transport Data
Consultancy Service for Inestigating the impact of
Motocycles and Three Wheelers Growth in Africa -
Case Study of Kano
Consultancy Services for Conducting
Environmental and Social Management Plan
(ESMP) for Akin Adesola and Wempco Roads
Actual
Plan
Actual
Plan
Actual
Plan
Actual
Plan
Actual
Plan
Actual
Plan
Actual
Plan
Actual
Plan
Actual
Plan
Actual
NonAsciiFileName0.xls 710 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
NonAsciiFileName0.xls 711 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2 Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
Norm Duration of Proc Steps
Component 1:(Instititional Development)
Training of Staff and Twining programme (To be
Implemented through global Training plan and
Twining arrangement for (January 2012 to Dec
2012)
Component 2:Public Transport and Traffic Management
Consultancy Services for Carrying out the Pre and
Post Study for the Establishment of Transport
Planning Units in Lagos Island, Kosofe and
Ikorodu LGAs in Lagos State
Consultancy Services for Detailed Engineering
Design and Construction Supervision of BRT LITE
Upgrade from Mile 12 to CMS
Consultancy Services for Conceptual Design of
BRT LITE Upgrade from Mile 12 to CMS
Consultancy Services for Engineering Design and
Construction Supervision of BFS Infrastructure
Rehabilitation and Upgrading
Consultancy Services for conducting Technical due
diligence on BFS Buses (Environmental
Enhancement of BFS Operations: Due Diligence
Report) Including Supervision of the
Refurbishment of BFS Buses
Mobilization
Advance
Payment
15-Jul-12
26-Apr-13
14-May-12
17-Sep-12
17-Mar-13
Contract Implementation
NonAsciiFileName0.xls 712 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Component 3: Improvement of Lagos State
Metropolitan Road Network
Component 4: Project Management & System Monitoring
Consultancy for Construction Supervision of Akin
Adesola and Wempco Roads
Consultancy Services for Design Upgrade and
Construction Supervision of BFS Bus Depot
Infrastructure
Consultancy Services for Website Redesign and
Hosting
Consultancy Services for IT Equipment
Maintenance
Consultancy Services for Events and Stakeholders
Management for BRT Services
Consultancy Services for Advertising and
Perception Management for BRT Extension (Mile
12 - Ikorodu)
Consultancy Services for Pavement Management
System Reconfiguration, Training and Data
Collection and Upload
Consultancy Services for the Documentation of the
Communication and Participation Efforts to Raise
Familiarity with BRT on Mile 12 to CMS Route
Consultancy to Conduct Stakeholder engagements
on other LAMATA projects (STMP, Road
rehabilitation/periodic maintenance etc)
Consultancy for Construction Supervision of
Adesina/Omilani/Airways Road Surulere
Consultancy for Construction Supervision of Apata
Lisabi Street Somolu
17-Jul-12
4-Sep-12
29-Feb-12
24-May-12
24-May-12
16-Dec-11
28-Dec-12
28-Dec-12
25-Dec-12
21-May-12
3-Apr-12
NonAsciiFileName0.xls 713 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Consultancy Services for Supply and installation
and Configuration of HDM4 Software for
LAMATA including Training
Consultancy Services for Provision, Installation
and Implementation of Knowledge Management
Software
Consultancy Services for Supply and installation
and configuratin of internet solution for LAMATA
(Share point)
Consultancy Services for the Provision of 1M
Internet Access
Consultancy Services for Oracle Support Licence
Consultancy Services for IT Equipment
Maintenance
Consultancy Services for EDMS Maintenance
Consultancy Services for Antivirus Support
Consultancy Services for Anti-Spam Support
Consultancy Services for Cloud Storage / Data
Backup
Consultancy Services for Arc GIS & Arc View
Upgrade and Licensing + HP Large format Plotter
Consultancy Services for Institutional, Technical
and Financial Audit
23-Jul-12
24-Jul-12
9-Aug-12
29-Nov-12
8-Jun-12
13-Jul-12
9-Aug-12
29-Dec-12
12-Nov-12
15-Oct-12
31-May-13
NonAsciiFileName0.xls 714 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Consultancy Services for Conducting Resettlement
Policy Framework (RPF) for Akin Adesola &
Wempco Roads
Consultancy Services for Resettlement Action Plan
(RAP) Implementation for Mile 12 to Ikorodu BRT
scheme
Consultancy Services for Procurement Audit for 2
consecutive years
Consultancy Services for Assesment of Needs of
Disadvantaged Group in Accessing Public
Transport Services on Mile 12 to Ikorodu Town
BRT Corridor
Consultancy Services for Carrying out Socio-
Economic Baseline Survey of Transportation from
Mile 12 to Ikorodu
Consultancy Services for Institutional, Technical
and Financial Audit
Consultancy Services for Developing the core
public Transport Network in Kano -Rapid
Development of Shor-time Program Investment
Consultancy Services for Developing the core
public Transport Network in Kano -Rapid
Collection of Traffic and Transport Data
Consultancy Service for Inestigating the impact of
Motocycles and Three Wheelers Growth in Africa -
Case Study of Kano
Consultancy Services for Conducting
Environmental and Social Management Plan
(ESMP) for Akin Adesola and Wempco Roads
21-May-12
21-May-12
21-May-12
21-May-12
30-Jul-12
30-May-12
15-Mar-12
15-Mar-12
15-Mar-12
NonAsciiFileName0.xls 715 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
NonAsciiFileName0.xls 716 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2 Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
Norm Duration of Proc Steps
Component 1:(Instititional Development)
Training of Staff and Twining programme (To be
Implemented through global Training plan and
Twining arrangement for (January 2012 to Dec
2012)
Component 2:Public Transport and Traffic Management
Consultancy Services for Carrying out the Pre and
Post Study for the Establishment of Transport
Planning Units in Lagos Island, Kosofe and
Ikorodu LGAs in Lagos State
Consultancy Services for Detailed Engineering
Design and Construction Supervision of BRT LITE
Upgrade from Mile 12 to CMS
Consultancy Services for Conceptual Design of
BRT LITE Upgrade from Mile 12 to CMS
Consultancy Services for Engineering Design and
Construction Supervision of BFS Infrastructure
Rehabilitation and Upgrading
Consultancy Services for conducting Technical due
diligence on BFS Buses (Environmental
Enhancement of BFS Operations: Due Diligence
Report) Including Supervision of the
Refurbishment of BFS Buses
Draft
Report
13-Oct-12
23-Sep-13
12-Aug-12
14-Feb-13
15-Jun-13
Contract Implementation
NonAsciiFileName0.xls 717 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Component 3: Improvement of Lagos State
Metropolitan Road Network
Component 4: Project Management & System Monitoring
Consultancy for Construction Supervision of Akin
Adesola and Wempco Roads
Consultancy Services for Design Upgrade and
Construction Supervision of BFS Bus Depot
Infrastructure
Consultancy Services for Website Redesign and
Hosting
Consultancy Services for IT Equipment
Maintenance
Consultancy Services for Events and Stakeholders
Management for BRT Services
Consultancy Services for Advertising and
Perception Management for BRT Extension (Mile
12 - Ikorodu)
Consultancy Services for Pavement Management
System Reconfiguration, Training and Data
Collection and Upload
Consultancy Services for the Documentation of the
Communication and Participation Efforts to Raise
Familiarity with BRT on Mile 12 to CMS Route
Consultancy to Conduct Stakeholder engagements
on other LAMATA projects (STMP, Road
rehabilitation/periodic maintenance etc)
Consultancy for Construction Supervision of
Adesina/Omilani/Airways Road Surulere
Consultancy for Construction Supervision of Apata
Lisabi Street Somolu
15-Oct-12
1-Jul-13
25-Dec-12
22-Aug-12
20-Mar-13
11-Oct-12
24-Oct-13
24-Oct-13
21-Oct-13
17-Mar-13
28-Jan-13
NonAsciiFileName0.xls 718 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Consultancy Services for Supply and installation
and Configuration of HDM4 Software for
LAMATA including Training
Consultancy Services for Provision, Installation
and Implementation of Knowledge Management
Software
Consultancy Services for Supply and installation
and configuratin of internet solution for LAMATA
(Share point)
Consultancy Services for the Provision of 1M
Internet Access
Consultancy Services for Oracle Support Licence
Consultancy Services for IT Equipment
Maintenance
Consultancy Services for EDMS Maintenance
Consultancy Services for Antivirus Support
Consultancy Services for Anti-Spam Support
Consultancy Services for Cloud Storage / Data
Backup
Consultancy Services for Arc GIS & Arc View
Upgrade and Licensing + HP Large format Plotter
Consultancy Services for Institutional, Technical
and Financial Audit
19-May-13
20-May-13
5-Jun-13
25-Sep-13
4-Apr-13
11-Sep-12
8-Oct-12
25-Oct-13
11-Jan-13
14-Dec-12
27-Mar-14
NonAsciiFileName0.xls 719 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Consultancy Services for Conducting Resettlement
Policy Framework (RPF) for Akin Adesola &
Wempco Roads
Consultancy Services for Resettlement Action Plan
(RAP) Implementation for Mile 12 to Ikorodu BRT
scheme
Consultancy Services for Procurement Audit for 2
consecutive years
Consultancy Services for Assesment of Needs of
Disadvantaged Group in Accessing Public
Transport Services on Mile 12 to Ikorodu Town
BRT Corridor
Consultancy Services for Carrying out Socio-
Economic Baseline Survey of Transportation from
Mile 12 to Ikorodu
Consultancy Services for Institutional, Technical
and Financial Audit
Consultancy Services for Developing the core
public Transport Network in Kano -Rapid
Development of Shor-time Program Investment
Consultancy Services for Developing the core
public Transport Network in Kano -Rapid
Collection of Traffic and Transport Data
Consultancy Service for Inestigating the impact of
Motocycles and Three Wheelers Growth in Africa -
Case Study of Kano
Consultancy Services for Conducting
Environmental and Social Management Plan
(ESMP) for Akin Adesola and Wempco Roads
2-Dec-13
17-Mar-13
17-Mar-13
17-Mar-13
27-Dec-12
27-Oct-12
14-Apr-12
14-Apr-12
14-Apr-12
NonAsciiFileName0.xls 720 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
NonAsciiFileName0.xls 721 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2 Country/Organisation:Nigeria Lagos Metropolitan Area Transport Authority (LAMATA)
Project/Programme: Lagos Urban Transport Project (LUTP)
IDA Credit No.: 3721-0 UNI
Description*
Norm Duration of Proc Steps
Component 1:(Instititional Development)
Training of Staff and Twining programme (To be
Implemented through global Training plan and
Twining arrangement for (January 2012 to Dec
2012)
Component 2:Public Transport and Traffic Management
Consultancy Services for Carrying out the Pre and
Post Study for the Establishment of Transport
Planning Units in Lagos Island, Kosofe and
Ikorodu LGAs in Lagos State
Consultancy Services for Detailed Engineering
Design and Construction Supervision of BRT LITE
Upgrade from Mile 12 to CMS
Consultancy Services for Conceptual Design of
BRT LITE Upgrade from Mile 12 to CMS
Consultancy Services for Engineering Design and
Construction Supervision of BFS Infrastructure
Rehabilitation and Upgrading
Consultancy Services for conducting Technical due
diligence on BFS Buses (Environmental
Enhancement of BFS Operations: Due Diligence
Report) Including Supervision of the
Refurbishment of BFS Buses
Final
Report
10-Jul-13
23-Oct-13
9-May-13
16-Mar-13
15-Jul-13
Contract Implementation
NonAsciiFileName0.xls 722 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Component 3: Improvement of Lagos State
Metropolitan Road Network
Component 4: Project Management & System Monitoring
Consultancy for Construction Supervision of Akin
Adesola and Wempco Roads
Consultancy Services for Design Upgrade and
Construction Supervision of BFS Bus Depot
Infrastructure
Consultancy Services for Website Redesign and
Hosting
Consultancy Services for IT Equipment
Maintenance
Consultancy Services for Events and Stakeholders
Management for BRT Services
Consultancy Services for Advertising and
Perception Management for BRT Extension (Mile
12 - Ikorodu)
Consultancy Services for Pavement Management
System Reconfiguration, Training and Data
Collection and Upload
Consultancy Services for the Documentation of the
Communication and Participation Efforts to Raise
Familiarity with BRT on Mile 12 to CMS Route
Consultancy to Conduct Stakeholder engagements
on other LAMATA projects (STMP, Road
rehabilitation/periodic maintenance etc)
Consultancy for Construction Supervision of
Adesina/Omilani/Airways Road Surulere
Consultancy for Construction Supervision of Apata
Lisabi Street Somolu
14-Nov-12
30-Aug-13
24-Feb-13
21-Sep-12
20-May-13
10-Dec-12
24-Dec-13
24-Dec-13
20-Dec-13
16-May-13
29-Mar-13
NonAsciiFileName0.xls 723 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Consultancy Services for Supply and installation
and Configuration of HDM4 Software for
LAMATA including Training
Consultancy Services for Provision, Installation
and Implementation of Knowledge Management
Software
Consultancy Services for Supply and installation
and configuratin of internet solution for LAMATA
(Share point)
Consultancy Services for the Provision of 1M
Internet Access
Consultancy Services for Oracle Support Licence
Consultancy Services for IT Equipment
Maintenance
Consultancy Services for EDMS Maintenance
Consultancy Services for Antivirus Support
Consultancy Services for Anti-Spam Support
Consultancy Services for Cloud Storage / Data
Backup
Consultancy Services for Arc GIS & Arc View
Upgrade and Licensing + HP Large format Plotter
Consultancy Services for Institutional, Technical
and Financial Audit
18-Jul-13
19-Jul-13
4-Aug-13
24-Nov-13
3-Jun-13
11-Oct-12
7-Nov-12
24-Dec-13
10-Feb-13
13-Jan-13
26-May-14
NonAsciiFileName0.xls 724 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
Consultancy Services for Conducting Resettlement
Policy Framework (RPF) for Akin Adesola &
Wempco Roads
Consultancy Services for Resettlement Action Plan
(RAP) Implementation for Mile 12 to Ikorodu BRT
scheme
Consultancy Services for Procurement Audit for 2
consecutive years
Consultancy Services for Assesment of Needs of
Disadvantaged Group in Accessing Public
Transport Services on Mile 12 to Ikorodu Town
BRT Corridor
Consultancy Services for Carrying out Socio-
Economic Baseline Survey of Transportation from
Mile 12 to Ikorodu
Consultancy Services for Institutional, Technical
and Financial Audit
Consultancy Services for Developing the core
public Transport Network in Kano -Rapid
Development of Shor-time Program Investment
Consultancy Services for Developing the core
public Transport Network in Kano -Rapid
Collection of Traffic and Transport Data
Consultancy Service for Inestigating the impact of
Motocycles and Three Wheelers Growth in Africa -
Case Study of Kano
Consultancy Services for Conducting
Environmental and Social Management Plan
(ESMP) for Akin Adesola and Wempco Roads
31-Jan-14
17-May-13
17-May-13
17-May-13
26-Jan-13
26-Nov-12
14-May-12
14-May-12
14-May-12
NonAsciiFileName0.xls 725 of 754 11/21/2012 1:40 AM
Procurement Plan-Consultants 2
NonAsciiFileName0.xls 726 of 754 11/21/2012 1:40 AM
Procurement Plan-Approvals-Consultants 2
Initial Approval Update
Dates of Bank Approval of Procurement Plan
For Consultants 2
NonAsciiFileName0.xls 727 of 754 11/21/2012 1:40 AM
Item Description
Component 1:(Instititional Development)
1
2
3
4
5
6
7
8
9
10
Component 3: Improvement of Lagos State Metropolitan Road
Network11
12
13
14
Component 4: Project Management & System Monitoring
15
16
17
18 Consultancy Services for Anti-Spam Support
Consultancy Services for Conceptual Design of BRT LITE Upgrade
from Mile 12 to CMS
Consultancy Services for Detailed Engineering Design and
Construction Supervision of BRT LITE Upgrade from Mile 12 to CMS
Consultancy Services for Events and Stakeholders Management for
BRT Services
Consultancy Services for Advertising and Perception Management for
BRT Extension (Mile 12 - Ikorodu)
Consultancy Services for the Documentation of the Communication and
Participation Efforts to Raise Familiarity with BRT on Mile 12 to CMS
Consultancy to Conduct Stakeholder engagements on other LAMATA
projects (STMP, Road rehabilitation/periodic maintenance etc)
Consultancy Services for Carrying out the Pre and Post Study for the
Establishment of Transport Planning Units in Lagos Island, Kosofe and
Consultancy Services for Engineering Design and Construction
Supervision of BFS Infrastructure Rehabilitation and Upgrading
Consultancy Services for conducting Technical due diligence on BFS
Buses
Consultancy Services for Design Upgrade and Construction
Supervision of BFS Bus Depot Infrastructure
Consultancy Services for IT Equipment Maintenance
Consultancy for Construction Supervision of Akin Adesola and
Wempco Roads
Consultancy for Construction Supervision of Adesina/Omilani/Airways
Road Surulere
Consultancy Services for Cloud Storage / Data Backup
Consultancy for Construction Supervision of Apata Lisabi Street
Somolu
Consultancy Services for Pavement Management System
Reconfiguration, Training and Data Collection
Consultancy Services for Website Redesign and Hosting
19
20
22
23
24
25
25
25
26
27
28
29
30
31
32
Consultancy Services for Assesment of Needs of Disadvantaged Group
in Accessing Public Transport Services on Mile 12 to Ikorodu Town
Consultancy Services for Anti-Spam Support
Consultancy Services for Antivirus Support
Consultancy Services for Provision, Installation and Implementation of
Knowledge Management Software
Consultancy Services for Supply and installation and configuratin of
internet solution for LAMATA (Share point)
Consultancy Services for EDMS Maintenance
Consultancy Services for Institutional, Technical and Financial Audit
Consultancy Services for Procurement Audit for 2 consecutive years
Consultancy Services for Resettlement Action Plan (RAP)
Implementation for Mile 12 to Ikorodu BRT scheme
Consultancy Services for Conducting Environmental and Social
Management Framework (ESMF) for Akin Adesola and Wempco
Consultancy Services for Carrying out Socio-Economic Baseline
Survey of Transportation from Mile 12 to Ikorodu
Consultancy Services for Conducting Resettlement Policy Framwork
(RPF) for Akin Adesola & Wempco Roads
Arc GIS & Arc View Upgrade and Licensing + HP Large format
plotter
Consultancy Services for the Provision of 1M Internet Access
Oracle Support Licence
HDM4 Purchase, installation and training
Item
Description
Component 1:(Instititional Development)
1
Component 2:Public Transport and Traffic Management
2
3
4
5
6 Construction of 8 No Bus Shelters including Platforms
7
8
9
Component 3: Improvement of Lagos State Metropolitan Road Network
10
11
12
13
Post Review
Prior Review
PeriodicMaintenance Work on Apata Lisabi Street, Somolu
Construction of 7 No Bus Shelters including Platforms
Construction of BRT Bus Depot at Ikorodu
Construction of BRT infrastructure from Ajegunle to Majidun Bridge – (Rural
Area Roadworks, Bridges, TSM And Street Light, Chainage 14+350 to 18+333-
Rural Section)
Construction of BRT infrastructure from Majidun Bridge to Ikorodu
Roundabout – (Urban Area Roadworks, Bridges, TSM and Street Light -
Chainage 18+333 to 22+390-Urban Section 2)
Construction of LAMATA Corporate Headquarter Building
Construction of BRT infrastructure from Mile 12 to Ajegunle – (Urban Area
Roadworks, Bridges, TSM and Street Light) - Chainage 9+075 TO 14+350)
Construction of Bus Terminal at Mile 12
Construction of Ikorodu and Agric Bus Terminals
Rehabilitation and Upgrading of Akin Adesola Road
Rehabilitation and Upgrading of Wempco Road Ogba
Priodic Maintenance Work on Adesina/Omilani/Airways Roads
Item Description
Component 2:Public Transport and Traffic Management
1
3
Component 4: Project Management & System Monitoring
4
5
6
7
8
9
12
13
14
Supply and Installation of BRT Signal Control (Intelligent
Transport Systems -Mile 12 - CMS)
Procurement of Office Furniture ( Front office desks, Work
stations, Executive swivel chairs, Board room furniture set,
Janitor shelf etc…
IT Equipment Purchase Switches, Server, UPS, PC's, Laptops,
pritners and Other Spare Parts
Procurement of IT Stationery/Consumable (4 Lots, to be
procured a lot per quarter)
Purchase and installation of Corel Draw and Video editing
software for external relation
Procurement of Ofice Equipment (2HP Slit Air conditioners (5,
Water Dispenser, Refrigerators)
Procurement of Operational Vehicles
Implementation of the Recommendation of the Technical Due
Diligence Report on BFS Operations
Supply and Installation of Air Quality Equipment in Eleven
Monitoring Stations on LAMATA BRT Corridors including
Training, Laboratory Analysis, Installation of one Control Centre
and one Ambient Control Centre and a back-up
Procurement of Fire Proof Cabinet
Procurement of IT Equipment (Multi-function Colour Printer,
Black and White Lase Jet Printer-Auto Duplexing, Wndow