67
Document of The World Bank Report No: ICR00003616 IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-45060) ON A CREDIT IN THE AMOUNT OF SDR 98.4 MILLION (US$149 MILLION EQUIVALENT) TO THE PEOPLE’S REPUBLIC OF BANGLADESH FOR A DHAKA WATER SUPPLY AND SANITATION PROJECT December 21, 2016 Global Water Practice (GWADR) Country Department SACBN South Asia Region Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

Document of

The World Bank

Report No: ICR00003616

IMPLEMENTATION COMPLETION AND RESULTS REPORT

(IDA-45060)

ON A

CREDIT

IN THE AMOUNT OF SDR 98.4 MILLION

(US$149 MILLION EQUIVALENT)

TO THE

PEOPLE’S REPUBLIC OF BANGLADESH

FOR A

DHAKA WATER SUPPLY AND SANITATION PROJECT

December 21, 2016

Global Water Practice (GWADR)

Country Department SACBN

South Asia Region

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Page 2: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

ii

CURRENCY EQUIVALENTS

Exchange Rate Effective 10/30/2016

Currency Unit = Bangladesh Taka (BDT)

0.0128 BDT = US$

US$ 1.00 = 78.3 BDT

FISCAL YEAR July to June

Senior Global Practice Director: Guang Zhe Chen

Country Director: Qimiao Fan

Practice Manager: Meike van Ginneken

Project Team Leader: Sudipto Sarkar

ICR Team Leader: Sudipto Sarkar

ICR Lead Author: Susanna Smets with Nishtha Mehta

Page 3: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

iii

ABBREVIATIONS AND ACRONYMS

ADB Asian Development Bank

BoD

CAS

Board of Directors

Country Assistance Strategy

DCC Dhaka City Corporation

DMA Dhaka Metropolitan Area

DPP

DSIP

DWASA

DWSSP

Development Project Proforma

Dhaka Sanitation Improvement Project

Dhaka Water Supply and Sanitation Authority

Dhaka Water Supply and Sanitation Project

EMF Environmental Management Framework

FGD

FM

FSM

FY

Focus Group Discussion

Financial Management

Fecal Sludge Management

Fiscal Year

GFDRR

GoB

Global Facility for Disaster Risk Reduction

Government of Bangladesh

ICR Implementation Completion and Results Report

IDA

IO

IRR

International Development Association

Intermediate Outcome

Internal Rate of Return

ISR Implementation Status and Results Report

IWM

JMP

Institute of Water Modelling

WHO/UNICEF Joint Monitoring Program

LIC Low Income Community

LICSIP Low Income Community Service Improvement Plan

M&E Monitoring and Evaluation

MDGs Millennium Development Goals

MoF

MoLGRDC

MTR

Ministry of Finance

Ministry of Local Government, Rural Development & Cooperatives

Mid-Term Review

NPV

NGO

Net Present Value

Non-Governmental Organization

OP/BP

O&M

PAD

Operational Policy and Bank Procedure

Operations and Maintenance

Project Appraisal Document

PAH Project Affected Households

PDO Project Development Objective

PMU Project Management Unit

Page 4: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

iv

PV

RAP

Present Value

Resettlement Action Plan

RPF

SO

STP

TA

Resettlement Policy Framework

Support Organization

Sewage Treatment Plant

Technical Assistance

WASA Water Supply and Sewerage Authority

WSS

WSP

Water Supply and Sanitation Services

Water and Sanitation Program

WSUP Water and Sanitation for the Urban Poor

Page 5: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

v

BANGLADESH

Dhaka Water Supply and Sanitation Project

CONTENT

Data Sheet

A. Basic Information

B. Key Dates

C. Ratings Summary

D. Sector and Theme Codes

E. Bank Staff

F. Results Framework Analysis

G. Ratings of Project Performance in ISRs

H. Restructuring

I. Disbursement Graph

1. Project Context, Development Objectives and Design ................................................... 1 2. Key Factors Affecting Implementation and Outcomes .................................................. 5

3. Assessment of Outcomes .............................................................................................. 11 4. Assessment of Risk to Development Outcome ............................................................. 17

5. Assessment of Bank and Borrower Performance ......................................................... 18 6. Lessons Learned............................................................................................................ 20

7. Comments on Issues Raised by Borrower/Implementing Agencies/Partners............... 22 Annex 1. Project Costs and Financing .............................................................................. 23

Annex 2. Outputs by Component...................................................................................... 24 Annex 3. Economic and Financial Analysis ..................................................................... 30 Annex 4. Bank Lending and Implementation Support/Supervision Processes ................. 37

Annex 5: Summary of Borrower's ICR and/or Comments on Draft ICR ......................... 39 Annex 6. Comments of Co-Financers and Other Partner Stakeholders ............................ 48

Annex 7. List of Supporting Documents .......................................................................... 49 MAP .................................................................................................................................. 51

Page 6: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

vi

DATA SHEET

A. Basic Information

Country: Bangladesh Project Name:

BD Dhaka Water

Supply and Sanitation

Project

Project ID: P093988 L/C/TF Number(s): IDA-45060

ICR Date: 11/02/2016 ICR Type: Core ICR

Lending Instrument: SIL Borrower: GOVERNMENT OF

BANGLADESH

Original Total

Commitment: XDR 94.80M Disbursed Amount: XDR 50.87M

Revised Amount: XDR 50.97M

Environmental Category: B

Implementing Agencies:

Dhaka Water Supply and Sewerage Authority (DWASA)

Cofinanciers and Other External Partners:

B. Key Dates

Process Date Process Original Date Revised / Actual

Date(s)

Concept Review: 02/01/2005 Effectiveness: 03/17/2009 03/17/2009

Appraisal: 07/21/2008 Restructuring(s): 06/13/2013

11/23/2015

Approval: 12/02/2008 Mid-term Review: 10/31/2012 11/28/2012

Closing: 06/30/2013 06/30/2016

C. Ratings Summary

C.1 Performance Rating by ICR

Outcomes: Moderately Unsatisfactory

Risk to Development Outcome: Substantial

Bank Performance: Moderately Unsatisfactory

Borrower Performance: Moderately Unsatisfactory

C.2 Detailed Ratings of Bank and Borrower Performance (by ICR)

Bank Ratings Borrower Ratings

Quality at Entry: Moderately

Unsatisfactory Government:

Moderately

Unsatisfactory

Page 7: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

vii

Quality of Supervision: Moderately Satisfactory Implementing

Agency/Agencies:

Moderately

Unsatisfactory

Overall Bank

Performance:

Moderately

Unsatisfactory Overall Borrower

Performance:

Moderately

Unsatisfactory

C.3 Quality at Entry and Implementation Performance Indicators

Implementation

Performance Indicators

QAG Assessments

(if any) Rating

Potential Problem Project

at any time (Yes/No): Yes

Quality at Entry

(QEA): None

Problem Project at any

time (Yes/No): Yes

Quality of

Supervision (QSA): None

DO rating before

Closing/Inactive status:

Moderately

Unsatisfactory

D. Sector and Theme Codes

Original Actual

Sector Code (as % of total Bank financing)

Flood protection 51 51

Public administration- Water, sanitation and flood

protection 8 8

Wastewater Collection and Transportation 19 19

Wastewater Treatment and Disposal 19 19

Water supply 3 3

Theme Code (as % of total Bank financing)

City-wide Infrastructure and Service Delivery 50 50

Urban services and housing for the poor 50 50

E. Bank Staff

Positions At ICR At Approval

Vice President: Annette Dixon Isabel Guerrero

Country Director: Qimiao Fan Xian Zhu

Practice

Manager/Manager: Meike van Ginneken Junaid Kamal Ahmad

Project Team Leader: Sudipto Sarkar Fook Chuan Eng

ICR Team Leader: Sudipto Sarkar

ICR Primary Author: Susanna Smets with Nishtha Mehta

Page 8: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

viii

F. Results Framework Analysis

Project Development Objectives (from Project Appraisal Document)

The Project Development Objective (PDO) is to improve the sustainable delivery of stormwater

drainage, wastewater and water services by the Dhaka Water Supply and Sewerage Authority

(DWASA) to the population of Dhaka through: (a) the installation of selected stormwater

pumping stations and the rehabilitation of selected canals to help improve drainage and minimize

urban flooding; (b) the rehabilitation, repair and expansion of priority investments in the city's

sewerage network and treatment plant to help improve the urban environment; and (c) supporting

DWASA's pilot expansion of water and sanitation services into selected Dhaka slums to help

increase services to the urban poor.

Revised Project Development Objectives (as approved by original approving authority) The revised PDO to improve storm water drainage in select catchments in Dhaka and improve

DWASA's planning capacity

(a) PDO Indicator(s)

Indicator Baseline Value

Original Target

Values (from

approval

documents)

Formally

Revised

Target

Values

Actual Value

Achieved at

Completion or

Target Years

Indicator 1 : Direct project beneficiaries (number), of which female (%)

Value

quantitative or

Qualitative)

1500000

4000000

3600000

Date achieved 06/13/2013 06/30/2016 06/30/2016

Comments

(incl. %

achievement)

90% achieved; introduced at restructuring. The number is from the

drainage impact modeling exercise; it is the population of wards that

would see a change in flood depth and duration for a 1 in 10 year event;

the percent of female beneficiaries is 50%.

Indicator 2 : Increase in permanent storm water pumping capacity (m3/d)

Value

quantitative or

Qualitative)

0

40

40

Date achieved 12/08/2008 06/30/2016 06/30/2016

Comments

(incl. %

achievement)

100% achieved; before restructuring this was an IO level indicator, lifted

to PDO level at restructuring. Due to the completion of Rampura (25

m3/s) and Kamalapur (15 m3/s) the indicator is achieved;

Indicator 3 : Increased capacity of rehabilitated drainage canals (m3/s)

Value

quantitative or

Qualitative)

0

250

250

Page 9: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

ix

Date achieved 06/13/2013 06/30/2016 06/30/2016

Comments

(incl. %

achievement)

100% achieved; introduced at restructuring; this indicator is achieved

through the rehabilitation and development of 13 sections of drainage

canals

Indicator 4 : Number of plans prepared and approved by DWASA Board of Directors

Value

quantitative or

Qualitative)

0

4

2

Date achieved 06/13/2013 06/30/2015 06/30/2016

Comments

(incl. %

achievement)

50% achieved; introduced at restructuring; The sewage master plan was

approved on Sep 30, 2014; The drainage master plan on Jun 23, 2016. 2

other plans were prepared, but not approved. These plans were prepared

with BE funds & not attributed to project

Indicator 5 :

Water level and number of days of waterlogging in the eastern part of

Dhaka

Value

quantitative or

Qualitative)

NA

NA

Date achieved 12/12/2008 06/30/2013

Comments

(incl. %

achievement)

Indicator dropped at restructuring in June 2013; DWASA does not have

the systems to monitor this indicator

Indicator 6 : Number of households with access to sewerage services

Value

quantitative or

Qualitative)

50853

57000

Date achieved 12/12/2008 06/30/2013

Comments

(incl. %

achievement)

Indicator dropped at restructuring in June 2013; sewerage investments

were cancelled at restructuring.

Indicator 7 :

Increase in number of people in project area ward slums with access to

safe water

Value

quantitative or

Qualitative)

0

180000

49000

Date achieved 12/12/2008 06/30/2013 06/30/2016

Comments

(incl. %

achievement)

Indicator dropped at restructuring in June 2013; LIC investments were

cancelled. However, the project included some small LIC works, and

49000 LIC residents gained access to safe water supply as a result of

project activities.

Page 10: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

x

Indicator 8 :

Increase in number of people in project area ward slums with access to

improved sanitation

Value

quantitative or

Qualitative)

0

218000

Date achieved 12/12/2008 06/30/2013

Comments

(incl. %

achievement)

Indicator dropped at restructuring in June 2013; LIC investment

component was cancelled

(b) Intermediate Outcome Indicator(s)

Indicator Baseline Value

Original Target

Values (from

approval

documents)

Formally

Revised

Target Values

Actual Value

Achieved at

Completion or

Target Years

Indicator 1 :

A new sewerage master plan for Dhaka city is approved by DWASA's

Board of Directors

Value

(quantitative

or Qualitative)

no

yes

yes

Date achieved 06/13/2013 06/30/2016 06/30/2016

Comments

(incl. %

achievement)

100% achieved; introduced at restructuring; The sewerage master plan

was approved by DWASA's Board of Directors on September 30, 2016

Indicator 2 : Diagnostic study on septage management practices in Dhaka

Value

(quantitative

or Qualitative)

no

yes

yes

Date achieved 06/13/2013 06/30/2016 06/30/2016

Comments

(incl. %

achievement)

100% achieved; introduced at restructuring; a diagnostic study on septage

management was carried out and completed by June 30, 2016;

Indicator 3 : length of storm water canals constructed/rehabilitated (m)

Value

(quantitative

or Qualitative)

0

30000

20885

20885

Date achieved 12/08/2008 06/30/2013 06/30/2016 06/30/2016

Page 11: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

xi

Comments

(incl. %

achievement)

100% achieved

Indicator 4 :

A new drainage master plan for Dhaka city is approved by DWASA's

Board of Directors

Value

(quantitative

or Qualitative)

no

yes

yes

yes

Date achieved 06/13/2013 12/31/2015 06/30/2016 06/30/2016

Comments

(incl. %

achievement)

100% achieved; indicator introduced at restructuring; The drainage master

plan was approved by DWASA's Board of Directors on June 23, 2016

Indicator 5 :

Drainage modeling undertaken of the impact of the project's i) khal

rehabilitation and ii) storm water

Value

(quantitative

or Qualitative)

no

yes

yes

no

Date achieved 06/13/2013 12/31/2015 06/30/2016 06/30/2016

Comments

(incl. %

achievement)

Not achieved; indicator introduced at restructuring; drainage impact

modeling was completed by June 30 2016 with Bank-executed funds.

Rated not achieved as this is not attributable to the project

Indicator 6 : Number of project affected households successfully compensated

Value

(quantitative

or Qualitative)

0

All entitled PAH

fully

compensated

prior to

relocation from

project site

500

441

Date achieved 12/08/2008 06/30/2013 06/30/2016 06/30/2016

Comments

(incl. %

achievement)

100% achieved as this represents all households affected by the project

eligible for compensation (indicator continued)

Indicator 7 : Service Improvement Plan for LICs is prepared

Value

(quantitative

or Qualitative)

no

yes

no

Date achieved 06/13/2013 06/30/2016 06/30/2016

Comments

(incl. %

achievement)

Not achieved; indicator introduced at restructuring; LIC service

improvement plan was developed in close collaboration with DWASA.

This was completed using Bank-executed funds; rated not achieved as not

attributable to the project;

Page 12: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

xii

Indicator 8 :

Annual statutory audits for DWASA demonstrating transparent and

accountable financial management (cumulative)

Value

(quantitative

or Qualitative)

0

No fiduciary

issues with

project funds

4

4

Date achieved 12/08/2008 06/30/2013 06/30/2016 06/30/2016

Comments

(incl. %

achievement)

100% achieved; Annual audits have been submitted regularly; indicator

was continued

Indicator 9 : Water utilities that the project is supporting

Value

(quantitative

or Qualitative)

1

1

1

Date achieved 06/13/2013 06/30/2016 06/30/2016

Comments

(incl. %

achievement)

Core indicator introduced at restructuring

Indicator 10 :

Development of an institutional structure for DWASA’s decentralization

and an action plan for its implementation

Value

(quantitative

or Qualitative)

no

yes

no

Date achieved 06/13/2013 06/30/2016 06/30/2016

Comments

(incl. %

achievement)

Not achieved. Indicator introduced at restructuring; a diagnostic and

options study for DWASA's decentralization was completed with Bank

executed funds; rated not achieved as not attributable to the project.

Indicator 11 :

A new decentralized zonal management structure and action plan for its

implementation are approved by DWASA's Board of Directors

Value

(quantitative

or Qualitative)

no

yes

no

Date achieved 06/13/2013 06/30/2016 06/30/2016

Comments

(incl. %

achievement)

Not Achieved; indicator introduced at restructuring; Plan was completed

with Bank-executed funds, in close coordination with DWASA.

Following DWASA's preferred option for decentralized management,

detailed organogram was prepared; not yet approved by BoD

Indicator 12 : DWASA zonal office refurbished and equipped

Value 0 1 6

Page 13: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

xiii

(quantitative

or Qualitative)

Date achieved 06/13/2013 06/30/2016 06/30/2016

Comments

(incl. %

achievement)

Target surpassed; indicator introduced at restructuring; due to fund

reallocation a total of 6 zonal offices have been refurbished and equipped,

compared to the target of one zonal office

Indicator 13 : Length of sewage lines rehabilitated/extended (km)

Value

(quantitative

or Qualitative)

0

30

Date achieved 12/12/2008 06/30/2013

Comments

(incl. %

achievement)

This indicator was dropped at restructuring in June 2013 due to the

cancellation of sewerage investment

Indicator 14 : Volume of solid waste collected along the canals (tons)

Value

(quantitative

or Qualitative)

0

20000

Date achieved 12/12/2008 06/30/2013

Comments

(incl. %

achievement)

Indicator dropped at restructuring in June 2013; DWASA does not have

the monitoring systems or mandate to ensure collection

Indicator 15 :

Increase in population in project area ward slums with access to safe

water

Value

(quantitative

or Qualitative)

0

56000

49000

Date achieved 12/12/2008 06/30/2013 06/30/2016

Comments

(incl. %

achievement)

Indicator dropped at restructuring; some LIC investments were completed.

49000 LIC residents gained access to safe water supply as a result of

project activities.

Indicator 16 :

Increase in population in project area peri-urban unions with access to

safe water

Value

(quantitative

or Qualitative)

0

124000

Date achieved 12/12/2008 06/30/2013

Comments

(incl. %

achievement)

Indicator dropped at restructuring

Indicator 17 : Increase in population in project area ward slums with access to improved

Page 14: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

xiv

G. Ratings of Project Performance in ISRs

No. Date ISR

Archived DO IP

Actual

Disbursements

(USD millions)

1 05/25/2009 Satisfactory Satisfactory 0.75

2 07/29/2009 Satisfactory Satisfactory 0.75

3 11/28/2009 Satisfactory Satisfactory 3.30

4 05/26/2010 Satisfactory Moderately Satisfactory 3.22

5 12/19/2010 Satisfactory Moderately Satisfactory 5.61

6 07/10/2011 Satisfactory Moderately Satisfactory 5.61

7 06/05/2012 Satisfactory Satisfactory 8.42

8 12/31/2012 Unsatisfactory Unsatisfactory 15.49

9 06/22/2013 Unsatisfactory Unsatisfactory 15.49

10 10/09/2013 Unsatisfactory Unsatisfactory 22.04

11 12/14/2013 Unsatisfactory Unsatisfactory 22.04

12 06/22/2014 Moderately Satisfactory Moderately Satisfactory 27.82

13 11/23/2014 Moderately Satisfactory Moderately Satisfactory 40.03

14 06/10/2015 Moderately Satisfactory Moderately Satisfactory 44.76

15 11/17/2015 Moderately

Unsatisfactory

Moderately

Unsatisfactory 58.34

16 02/02/2016 Moderately

Unsatisfactory

Moderately

Unsatisfactory 65.19

17 06/30/2016 Moderately

Unsatisfactory

Moderately

Unsatisfactory 71.39

sanitation

Value

(quantitative

or Qualitative)

0

94000

Date achieved 12/12/2008 06/30/2013

Comments

(incl. %

achievement)

Indicator dropped at restructuring

Indicator 18 :

Increase in population in project area peri-urban unions with access to

improved sanitation

Value

(quantitative

or Qualitative)

0

124000

Date achieved 12/12/2008 06/30/2013

Comments

(incl. %

achievement)

Indicator dropped at restructuring

Page 15: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

xv

H. Restructuring (if any)

Restructuring

Date(s)

Board

Approved

PDO Change

ISR Ratings at

Restructuring

Amount

Disbursed at

Restructuring

in USD

millions

Reason for Restructuring &

Key Changes Made DO IP

06/13/2013 Y U U 15.49

The project was restructured

to scale-down investments

and focus on activities that

could be completed within an

additional 2.5 year period.

The restructuring also

increased project focus on

institutional strengthening

and capacity building

activities

11/23/2015 N MU MU 58.34

A six-month extension was

required to complete crucial

investments (e.g. one of the

pumping stations) and other

ongoing activities

If PDO and/or Key Outcome Targets were formally revised (approved by the original approving

body) enter ratings below:

Outcome Ratings

Against Original PDO/Targets Unsatisfactory

Against Formally Revised PDO/Targets Moderately Unsatisfactory

Overall (weighted) rating Moderately Unsatisfactory

Page 16: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

xvi

I. Disbursement Profile

Page 17: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

1

1. Project Context, Development Objectives and Design

1.1 Context at Appraisal

1. From 2000 to 2008, Bangladesh’s economy grew at 5.8 percent per annum. At the

same time, in 2008, about 40 percent of the population continued to live below US$1.25

per day. While majority of this population was in rural areas, at least 25 percent of the

poor population lived in Bangladesh’s urban areas. Urban poverty was further

exacerbated by rapid urbanization.

2. Between 2000 and 2008, Bangladesh experienced faster urbanization than South

Asia as a whole (World Bank, 2015). In 2008, about 40 million people lived in urban

areas across the country, with about 15 million living in the Dhaka Metropolitan Area

(DMA). While Dhaka was the center for manufacturing, commerce and construction for

the country, the city’s rapid growth also led to considerable infrastructure and

environmental challenges.

3. In 2005, 29 percent of Bangladesh’s urban population had access to piped water

services and 55 percent had access to other improved water sources, while access to

improved sanitation was 58 percent (JMP) 1

. Dhaka was the only city with a water-borne

sewerage system that served about 20 percent of its population. The large majority of

households were not connected to the combined sewer system and either used septic

tanks or had no on-site facility in place at all. As a result, septic tank effluent and black

water discharged directly in the storm water canals and drains. This affected the drainage

systems and led to pollution of water sources and contamination of water supply. In the

absence of adequate planning and enforcement, the canals also became dumping areas for

solid waste. In 2008, only 26 out of Dhaka’s 43 canals (or khals) were functional.

4. In 1996, the Government of Bangladesh adopted the Water Supply and Sewerage

Authority (WASA) Act. Under this Act, Dhaka WASA (DWASA) was assigned the

responsibility of providing water, sewerage and storm water drainage2 services in Dhaka.

As per the Act, DWASA’s management was answerable to a Board of Directors, which

included stakeholders appointed by the GoB. In order to increase DWASA’s autonomy

and improve operations, the GoB also approved various regulations and signed a

Performance Agreement with DWASA. Despite these steps, the increasing population,

increased risk of flooding due to inadequate drainage systems, and limited infrastructure

resulted in critical challenges for DWASA.

5. The Dhaka Water Supply and Sanitation Project (DWSSP) was designed to

address some of the issues confronting DWASA. The Bank had a long history of

supporting water supply and sanitation infrastructure in Dhaka - financing four projects

since the 1960s. Despite a gap after the closure of the Fourth Water Supply and

1 The latest JMP (2015) estimate for Bangladesh shows a slight improvement of 32 percent with piped services, and 55

percent with access to other improved water sources (urban). Urban sanitation access shows 58 percent improved

access, 30 shared access, and 12 unimproved access (no open defecation). 2 Storm water drainage responsibilities are shared with Dhaka City Corporations (DCC). DCC is responsible for

smaller drainage pipes, while DWASA has responsibility for larger canals and some storm water pipes.

Page 18: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

2

Sanitation project in 2002, the Bank was able to prepare DWSSP bringing its experience

and relevant sector knowledge. DWSSP was also well aligned with the Country

Assistance Strategy (CAS) 2006-2009 objectives of improving the governance and

efficiency of infrastructure services, including in the water sector.

1.2 Original Project Development Objectives (PDO) and Key Indicators (as

approved)

6. The PDO was to improve the sustainable delivery of stormwater drainage,

wastewater and water services by the Dhaka Water Supply and Sewerage Authority to the

population of Dhaka through:

a) The installation of selected stormwater pumping stations and the rehabilitation of

selected canals to help improve drainage and minimize urban flooding;

b) The rehabilitation, repair and expansion of priority investments in the city's sewerage

network and treatment plant to help improve the urban environment; and

c) Supporting DWASA's pilot expansion of water and sanitation services into selected

Dhaka slums to help increase services to the urban poor.

7. Progress towards achieving the PDO were monitored through a set of indicators

linked to the PDO:

a) Water level and number of days of water logging in the eastern part of Dhaka;

b) The number of households with access to sewerage services; and

c) Increase in the number of people in project area ward slums with access to safe water

and improved sanitation.

1.3 Revised PDO and Key Indicators, and Reasons/Justification

8. During the project mid-term review (MTR) in December 2012, the ratings for

both the Development Objective and Implementation Progress were assessed as

‘unsatisfactory’. This was mainly due to shortcomings in the design, lack of readiness,

and low capacity of the implementing agency. Thus, the project was restructured in June

2013 with an aim to scale-down the project scope, increase project period by 2.5 years,

complete ongoing works and technical assistance (TA) activities, and enhance DWASA’s

capacity to better plan for future investments in sanitation and drainage

9. The revised PDO was to improve storm water drainage in select catchments in

Dhaka and to improve DWASA's planning capacity. To reflect the above changes and

to mark the Bank’s shift to core sector indicators in July 2009, previous PDO indicators

were dropped and the following were added:

a) Direct project beneficiaries (number), of which female (percentage)

b) Increase in permanent storm water pumping capacity

c) Increased capacity of rehabilitated drainage canals

d) Number of plans prepared and approved by DWASA’s Board of Directors

Page 19: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

3

The intermediate outcome indicators were also revised at restructuring: seven were

dropped, four continued, and 12 new indicators were introduced (See Section F of Data

Sheet).

1.4 Main Beneficiaries

Original target beneficiaries.

10. At appraisal, the target beneficiaries were defined broadly as people of Dhaka city

benefiting from the proposed investments in drainage, wastewater and water supply and

sanitation. Other intended beneficiaries were residents of Dhaka’s low-income

communities where water and sanitation services would be extended.

Revised target beneficiaries

11. After restructuring the target beneficiaries were defined as 4 million people (of

which 50% female) living in the catchment areas of the project’s drainage canals and

stormwater pumping stations. DWASA was seen as intended beneficiary of the project’s

institutional capacity building programs.

1.5 Original Components (as approved)

12. DWSSP had five components, which are summarized below.3

Component 1. Rehabilitation and Strengthening of Existing Sewerage System:

US$63.8m4 (IDA US$52.4m). This component was to support the rehabilitation and

strengthening of the existing sewerage system, including the rehabilitation of

lifting/pumping stations, the rehabilitation and augmentation of the Pagla sewage

treatment plant, the replacement of trunk sewer mains and sewer lines, and expansion of

branches to augment the coverage area of the Pagla sewer basin. Purchase of sewer

cleaning equipment and TA to improve operation and maintenance (O&M) was also

included. This component also included support to develop a sewerage masterplan.

Component 2. Rehabilitation and Strengthening of Stormwater Drainage System:

US$80.3m (IDA US$75.9m). This component was to improve the stormwater drainage

system by installing two pumping stations at Rampura and Kamalapur sites to alleviate

periodic flooding in the central catchment area of Dhaka. The component supported

improving the hydraulic performance of 13 khals (canals) through re-excavation, re-

profiling and protection. In addition, cleaning equipment for drains and TA for O&M

were included. The component also had support for solid waste management along khals

rehabilitated under the project and TA to formulate and implement institutional

arrangements for O&M. It also included the updating of the stormwater drainage master

plan for Dhaka.

Component 3. Support to the implementation of environment and social safeguards:

US$5.2m (IDA US$5.0 m). This component was to support the implementation of

environmental management and social safeguards activities, including Resettlement

3 At appraisal the US$ equivalent of the IDA credit was estimated at US$ 149 million, out of a total estimated project

costs of US$ 165.7m. The amounts are expressed in estimated US$ values at the time of appraisal and time of

restructuring. 4 Theo overall cost for all components includes contingencies – as indicated in the project appraisal document

Page 20: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

4

Action Plans (RAP) for rehabilitation of selected canals and Environmental Management

Framework (EMF) for the project. It also included the provision of laboratory equipment

and chemicals, and TA to DWASA to improve water quality management and

monitoring activities.

Component 4. Support to service provision to Low Income Communities: US$8.7m (IDA

US$8.4m). This component was to support the piloting of several approaches for water

and sanitation service provision to low income communities and the strengthening of

DWASA’s capacity to deliver water and sanitation services to these communities.

Component 5. Project Management, M&E, Consultations and Communications:

US$7.7m (IDA US$7.3m). This component was to support TA for project

implementation, monitoring and evaluation (M&E) and DWASA’s communications

program. Project implementation support included TA for engineering, financial, legal,

environmental and social M&E.

1.6 Revised Components

13. A level-1 restructuring5 took place in June 2013. The revised components are

described below. More details are included in Annex 2.

Component 1: Investment Planning in Sanitation: The original IDA credit was US$ 52.4

m, of which, US$49.3m was canceled. The new IDA amount was US$3.1m. The

component was significantly amended and the name was changed. The revised

component retained the development of Dhaka’s sewerage master plan and the

preparation of engineering designs and bidding documents for priority sewerage

interventions identified in the master plan. A diagnostic study related to fecal sludge

management (FSM) in Dhaka was added to better understand practices and suggest ways

to improve services. Given the significant delays in preparing the sewerage masterplan

and associated bidding documents, implementation was dropped.

Component 2: Rehabilitation and Strengthening of Stormwater Drainage System: The

original IDA credit was US$75.9m, of which US$15.4m was canceled. There are no

major changes under this component. As the actual cost of the activities was less than

originally estimated, part of the IDA credit was cancelled, and a part was allocated for (i)

additional canal rehabilitation (ii) cost-overruns for the stormwater pumping stations; and

(iii) updating of the Drainage Master Plan6.

Component 3: Support to Implementation of Environmental and Social Safeguards: The

original IDA credit was US$5.0m, of which US$2.7m was canceled. The new IDA

amount was US$2.3m. There were no major changes to this component. As the

wastewater treatment and sewerage investments under Component 1 were cancelled, the

overall cost was reduced.

5At the beginning of the project, based on the then applicable exchange rate, the IDA Credit of SDR 94.8 million

equaled US$ 149 million. Due to variation in the SDR to US Dollar exchange rate, at restructuring, SDR 94.8 million

was US$ 141.3 million. Therefore, the project total in June 2013 was US$ 141.3 million. 6 A drainage impact modelling exercise has been included in the restructuring paper and RF, however, the legal

agreement for the restructured project does not mention this study explicitly.

Page 21: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

5

Component 4: Support to Service Improvement Planning to Low Income Communities:

The original IDA credit was US$8.4m, of which US$6.9m was canceled. The new IDA

amount was US$1.5m. This component was significantly amended and the name was

changed. The original design and implementation approach encountered various

challenges (See Section 2.1). Thus, service provision activities in LICs were dropped and

a TA to prepare a Service Improvement Plan for LICs was added. The TA would include:

(i) a review of approaches; (ii) ways to mainstream service provision to LICs; and, (iii)

identifying DWASA’s institutional requirements to better serve LICs.

Component 5: Project Management and Institutional Capacity Building: The original

IDA credit was US$7.4m. There was an addition allocation of US$1.3m under the

component, bringing the IDA credit to US$8.6m. This component was significantly

changed, including its name. TA activities were added to assist DWASA in

decentralizing operations, including: i) developing an institutional structure and

management instruments for decentralization; ii) preparing an action plan for

implementation; (iii) support for equipping and refurbishing zonal offices; and, (iv) staff

training.

1.7 Other significant changes

14. The project had the following significant changes:

a) Level-1 Restructuring: In June 2013, a level 1 restructuring was completed. The

project PDO was revised and the results framework was updated to reflect this

change. The overall scope of the project was reduced as the sewerage and the LIC

components were amended. Institutional strengthening activities were added (See

Section 1.6). In order to complete the revised project scope, 49 percent of the IDA

credit amount was canceled and the project closing date was extended by 2.5 years,

from June 30, 2013 to December 31, 2015.

b) Time Extension: The closing date of the project was extended from December 31,

2015 to June 30, 2016 to allow additional time for completion of critical works.

2. Key Factors Affecting Implementation and Outcomes

2.1 Project Preparation, Design and Quality at Entry

Soundness of background analysis

15. Several lessons learned during previous engagements in Dhaka’s WSS sector

were included. Based on a review of previous sector engagements and overall Bank

support, the need for a long-term engagement with GoB and DWASA to sustain reforms

for improved service delivery was recognized. Learning from the difficulties of the fourth

Dhaka Water Supply and Sanitation Project, closed in 2002, to deliver on its institutional

objectives, the project design took a gradual approach and hence did not have an

institutional focus in its original development objective. Rather it was decided to address

sector and policy risks through a broader instrument, namely the Partnership Framework

and Letter of Sector Policy that were signed in 2007 between GoB and several

development partners. As part of the project design, a Performance Agreement between

DWASA and GoB which complemented the Partnership Framework was reinstituted as a

means to reintroduce performance assessments and implement key elements of the

Page 22: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

6

WASA Act. A drawback of this approach was the non-legally binding nature of the

Partnership Framework for the project, although an annual audit of the performance

Agreement was included as a project covenant.

16. Capacity strengthening activities under the project aimed to leverage the Policy

Letter, and support long term institutional development activities, using the Performance

Agreement as the major vehicle to assess progress. In addition, the framework provided

opportunities for greater cooperation between development partners, particularly the

Bank and the Asian Development Bank, on institutional strengthening. However, there

were also some gaps in the project design. The background analysis did not address the

lack of readiness of priority investments. In addition, difficulties in implementing the

project in densely populated low-income communities were underestimated, especially

given the fact that DWASA was new to delivering services to LICs at the start of the

project7.

17. The rationale for the Bank’s involvement was to strengthen Dhaka’s WSS sector.

This included: supporting operationalization of the WASA act; facilitating access to WSS

services in line with the National Policy for Safe Water Supply and Sanitation (1998);

and strengthening DWASA’s capacity to provide services to all customers, including LIC

customers.

Assessment of Project Design

18. The Project Appraisal Document (PAD) proposed a phased approach: i)

preparation of masterplans, feasibility studies and further investments; (ii)

implementation of priority drainage and sewerage infrastructure, and iii) a phased

expansion of services in LIC through piloting and replication. The phased approach was a

reasonable strategy, to ensure incremental progress and long-term engagement. However,

the implementation period for the project was set at 4.5 years and the priority investments

were not ready at the time of effectiveness. Even though the results framework

established links from activities to outcomes, the targets were too ambitious. The tight

timeline, complex design, and ambitious targets led to significant implementation

challenges8 (See Section 2.3).

19. Although implementation arrangements were simple, with DWASA as sole

implementing agency, the ambitious design placed a heavy procurement load on the

Project Management Unit (PMU). The implementation agency did not have the capacity

to or the experience to meet the demands of the project. The design also did not address

institutional coordination with Dhaka City Corporations (DCC) and other public

agencies, particularly around drainage and solid waste management.

20. For Component 4 (service provision for LICs), the project design proposed that

DWASA manage the construction, social mobilization and management of services for

LICs through Service Organizations (SOs). DWASA had limited experience in service

provision to LICs and the SOs were not qualified to handle such “hybrid’ contracts

(investments and social mobilization). In addition, some of the LICs selected for

7 At project approval, DWASA only delivered services to LICs through intermediary NGOs. 8 For example by assuming that additional wastewater treatment capacity would be put in place by YR2, stormwater

pumping capacity in place by YR3, and new services operational in LICs by YR2.

Page 23: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

7

interventions were on privately owned land, which affected access and implementation.

The design for sanitation service provision in LICs did not take into account existing

sanitation services. The proposed technical solutions were also not optimal for the

densely populated LICs.

Adequacy of Government Commitment

21. Government commitment was high at the time of project preparation. In 1998, the

GoB put in place the National Policy for Safe Water Supply and sanitation to facilitate

access for all citizens to a basic level of water and sanitation services for all citizens. In

addition, in 2005, the Dhaka Water Supply Policy was formulated, which reiterated

GoB’s commitment to provide water supply services to LICs. At the time of preparation,

GoB indicated its commitment to the reform agenda by signing a Letter of Policy and

Framework Agreement between GoB and Development Partners – which provided a

framework to sustain institutional reforms in the long term and create avenues for

cooperation between development partners. Outside the project, GoB reinstated a five-

year Performance Agreement with DWASA, signed in 2008, which included

performance targets although it did not specify incentives or sanctions.

Risk assessment and mitigation

22. At the time of appraisal, the overall risk rating was “substantial”. Key risks were:

DWASA’s capacity limitations; weakening of GoB’s commitment to implement the

WASA Act; inadequate legislative and institutional oversight for the project; weak

financial management systems; limited capacity to respond to needs of LIC residents;

weak procurement capacity; and limited experience to implement resettlement actions.

23. Most mitigation measures were appropriate, including: extensive financial

management and procurement training; the phasing of khal rehabilitation; intensive

capacity building of DWASA on resettlement; establishing an LIC team in DWASA; TA

support; and agreement on policy actions to sustain development.

24. During implementation, some of the mitigation measures were less effective,

including: The Letter of Sector Policy and Partnership Framework to support institutional

development was non-binding and was not adhered to; GoB-DWASA’s Performance

Agreement was not regularly audited, and there were gaps in maintaining this agreement.

This affected DWASA’s accountability; and an international procurement advisor was

not hired, leading to delays.

25. Some unforeseen risks also led to implementation delays including: the longer

than anticipated time needed to acquire land for the Kamalapur pumping station; and the

shifting of the location of Rampura station.

2.2 Implementation

26. The project became effective on March 14, 2009. In December, 2012, after the

MTR, the implementation progress was rated as unsatisfactory until December 2013.

After restructuring in June 2013, the acceleration of implementation and the refocus of

the project on institutional measures took 12 months to take effect and only in June 2014

the project was rated moderately satisfactory. During the last 7 months, the project was

rated unsatisfactory again for from Nov 2015 to June, 2016. Some reasons for

implementation delays are discussed below:

Page 24: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

8

a) Slow Procurement: DWASA had no prior experience in executing the two-step

procurement process for the pumping stations. As a result, it took over 40 months to

procure the two pumping stations, leading to significant delays. The sewerage

masterplan and engineering designs for priority sewerage works took 24 months to

procure due to a variety of procurement issues. Slow government approvals for

procurement packages also contributed to delays.

b) Complex Project Design: The overall project timeline was tight and the targets were

too ambitious, which affected implementation progress (See Section 2.1).

c) Lack of Capacity: The PMU was understaffed and the capacity to manage contracts,

and financial and procurement issues was low, leading to delays. Building DWASA’s

capacity to implement the project took additional time.

d) Land Acquisition: Land acquisition for both the stormwater pumping stations

required more time that envisaged

e) Restructuring: The project was restructured in June 2013 in a number of key issues

were addressed: (i) the project developed a more strategic planning approach for both

sewerage and drainage; (ii) the project included provisions to prepare a

comprehensive approach for LIC service provision; (iii) technical assistance to assess

DWASA’s organizational set-up and management structure was added; (iv) almost

half of the IDA credit was cancelled; and, (v) the implementation period was

extended by 2.5 years. Subsequently, another level-2 restructuring was processed in

December 2015 to extend the project closing date by 6 months.

f) Exchange Rate Fluctuation: The Dollar to XDR exchange rate fluctuation led to

changes in the overall IDA credit amount,9

which impacted implementation.

Committed activities, such as the IT packages under Component 5, could not be

implemented due to the change in the project amount.

2.3 Monitoring and Evaluation (M&E) Design, Implementation and Utilization

27. M&E design: The M&E design of the original project was comprehensive even

though the targets for some indicators were overambitious. The PDO on water logging

was also not clearly defined. A consulting firm was hired to monitor the project progress

and provide quarterly monitoring reports. After the 2012 restructuring, the results

framework was refined to reflect changes in the PDO (See Section 1.3 and Annex 2) and

to align the project to the Bank’s core sector indicators. The indicators related to the

following were dropped after restructuring: sewerage investments; LIC service provision;

solid waste collection around canals; extent of urban flooding; O&M of drainage and

sewer systems. PDO-level indicators for stormwater drainage and DWASA’s planning

capacity were added.

28. M&E Implementation: Pre-restructuring, the Implementation Status and Results

Reports (ISRs) did not include information on all the indicators. At the MTR, DWASA

provided a comprehensive report assessing project results. This was used to define the

9 XDR 50.9 was US$76.0m at restructuring, and US$70.9m at project closing.

Page 25: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

9

results framework for the restructured project. After restructuring, the ISRs consistently

included progress for each indicator. Through the project period, the PMU’s ability to

monitor the project improved significantly, and it shared detailed quarterly progress

reports with the Bank in a timely manner10

. During the restructuring, DWASA agreed to

implement several TA activities, including: the low-income customer’s service

improvement plan; a decentralized institutional structure and action plan; zonal

management structure and action plan; drainage modeling exercise. After the

restructuring was approved, these activities were not included in the Government’s

revised Development Project Performa (DPP). The task team mobilized Bank-executed

funds for these tasks, however the RF was not formally adjusted and therefore several

indicators are rated as not achieved, as they cannot be attributed to the project.

29. Utilization of M&E. After restructuring, M&E information was used to support

implementation. Consistent monitoring of the RF indicators in the ISRs helped to keep

focus on both infrastructure progress, as well as results of technical activities (including

those financed from Bank-executed funds). This focus helped i) ensure that institutional

activities were seen as an integral project result, ii) keep DWASA’s focus on progress of

civil works, and iii) address problems in a timely manner. In addition, the project

developed a drainage asset database, which will help DWASA in asset management and

guide drainage-related decision making.

2.4 Safeguard and Fiduciary Compliance

30. Environmental and Social Safeguards Compliance. There are no outstanding

environmental or social safeguards issues in the project.

31. Environmental safeguards compliance. The project was appropriately classified

as Category B and triggered OP/BP/ 4.01 (Environmental Assessment). In response, an

Environmental and Social Management Framework was prepared and integrated into the

project. Limited environmental assessments were prepared for sub-projects as per Bank

guidelines. Civil works under the project were all in compliance with local legislations

and Bank policies. Compensation was provided for a case of non-compliance (trees felled

on a work site). An incident of land subsidence also occurred at the Kamlapur pumping

station site, however there were no injuries.

32. Social safeguards compliance. The Bank’s operational policy on involuntary

resettlement (OP/BP/4.12) was triggered and in response DWASA prepared a

Resettlement Policy Framework, and subsequently prepared RAPs to ensure adequate

compensation for project affected households. Even though no private land was acquired

for the project, the two pumping stations affected 221 households and the khal

rehabilitation affected 216 households. These were adequately compensated as per the

RAPs. A complaint regarding the partial demolition of a building on the Khilgaon-

Bashabo canal right-of-way was received. This issue was adequately resolved. DWASA

also carried out a Social Impact Assessment, including extensive stakeholder

10 Although not all indicators reported on were adequately evidenced, for example the increased design capacity of the

rehabilitated khals.

Page 26: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

10

consultations. As a result of the project, DWASA has developed adequate in-house

capacity to address social safeguard issues. Mainly due to the cancellation of the

sewerage investments, the level of spending on environmental and social safeguards was

much lower than originally foreseen (see Annex 1 and Annex 2).

Fiduciary compliance

33. Procurement. Procurement was generally carried out in accordance with agreed

procedures. A Procurement Capacity and Risk Assessment was conducted at appraisal

and a Procurement Risk Mitigation Plan was developed. As per the plan, DWASA would

develop quarterly reports to monitor procurement performance, and contract an

International Procurement Specialist for the PMU. DWASA did provide quarterly M&E

reports after restructuring. An international procurement specialist could not be hired due

to lack of candidates, thus a local expert was contracted.

34. Slow procurement affected project implementation, leading to significant delays

(See Section 2.2). For example, the contract amendment for the variation orders of the

pumping stations, which also required approval from the government, were delayed by

over 12 months. Significant delays occurred in the consultancy procurement for the

sewerage masterplan and engineering designs for priority investment. Due diligence was

required to validate the shortlisting process and other irregularities were encountered that

needed extra time to get resolved. Complaint handling was a major issue and overall

turnout period for advertising, evaluation and award took significant time. The PMU did

not have a technical expert to review complex bids, which necessitated extensive

technical support from the Bank, including the hiring of a drainage consultant using

Bank-executed funds.

35. Financial Management (FM). Financial management was implemented

adequately, and there are no overdue or outstanding audits. However, there was no full

time FM specialist with the PMU, which led to some limitations including maintaining

books of accounts, and timely submission of Interim Unaudited Financial Reports. No

project specific FM was set up and DWASA’s accounts department largely handled

project accounting and disbursements. Since the project designated account was not

managed directly by the PMU, there were delays in reporting project expenditures.

36. External project audit reports, conducted by Foreign Aided Projects Audit

Directorate (FAPAD), were of quality and submitted to the Bank in a timely manner. The

project complied with all fiduciary covenants during implementation. There are some

outstanding issues from various fiscal years. A final opinion by FAPAD on these issues

and the audit report for FY 2015-16 will be provided to the Bank by December 31, 2016.

2.5 Post-completion Operation/Next Phase

37. Transition arrangements: Transition arrangements are summarized below:

a) Technical: newly built pumping stations, rehabilitated khals and drainage cleaning

equipment have been formally handed to the respective divisions/circles within

DWASA for O&M after relevant training was provided.

b) Financial: At this time, there is no clear plan and budget for O&M of newly

constructed assets.

Page 27: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

11

c) Institutional: DWASA is currently carrying out a review of a new organogram and is

looking to set up a new sewerage directorate, however this has not yet been approved

by the DWASA’s board.

38. Future operation. The proposed Dhaka Sanitation Improvement Project (DSIP),

which is a follow-up operation, is currently being prepared. The project aims to improve

sanitation in selected catchments of Dhaka city, improve DWASA capacity to provide

sanitation services and reduce domestic wastewater pollution in and around Dhaka. The

detailed engineering design and tender documents for priority investments prepared

under DWSSP will allow for a faster implementation.

3. Assessment of Outcomes

3.1 Relevance of Objectives, Design and Implementation

Relevance of Objectives: Substantial (before) and Substantial (after restructuring)

39. Before restructuring, the PDO were relevant to the country’s development

objectives and the needs of Dhaka city. The GoB’s Perspective Plan 2012-2020 and the

7th

Five Year Plan articulate the government’s medium and long-term measures to

improve urban development, basic service provision, minimize risks from flooding, and

enhance environmental protection. In addition, the Dhaka Water Supply Policy (2005)

confirmed DWASA’s mandate to extend basic water supply and sanitation services to

slums within its service area. While the project objective was clearly aligned with

government priorities, it did not explicitly address strengthening of DWASA’s

institutional capacity. Thus, the relevance before restructuring is rated as substantial.

After restructuring, the objectives continued to be in-line with government priority to

improve storm water drainage in Dhaka. The project also aimed to improve DWASA’s

planning capacity, which was ultimately expected to improve service delivery in the city.

As the PDO scope was narrowed, the relevance after restructuring is substantial.

40. The project, both before and after restructuring, remained substantially relevant

to the Bank’s priorities and development objectives. The Country Partnership Framework

(2016-2020) has three pillars: i) growth and competiveness, ii) social inclusion and iii)

climate and environment management. The project directly supports objectives under

pillar 1 and 3, namely ‘Delivery of Basic Services in Urban and Rural Areas’, and

‘Improved Water Resource Management for Climate Resilience’. After restructuring, the

project also focused on building DWASA’s capacity, which is aligned with the CPF aim

to strengthen institutions through activities embedded in Bank operations.

Relevance of Design and Implementation: Modest (before) and Substantial (after)

41. Before restructuring, the relevance of the design was modest. The design was

relevant from the following perspectives: (i) The proposed infrastructure investments

focused on improving water and sanitation access for the poor residents, and on

improving necessary services in the city; and (ii) the implementation arrangements were

relevant as the project management responsibility was with DWASA, which also had the

mandate for water, sanitation and stormwater drainage services for Dhaka. However,

There were several shortcomings: i) tight timeline and overambitious targets, ii) weak

Page 28: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

12

institutional coordination mechanism iii) design shortcomings for service delivery to

LICs and inadequate slum selection, and iv) reliance on the non-binding Partnership

Framework for DWASA’s institutional strengthening.

42. After restructuring, the relevance of the design improved to substantial, due to the

following: (i) narrowing of the PDO and a focus on drainage investments that could be

realistically achieved within the project period; (ii) increased focus on DWASA’s

institutional strengthening; (iii) focus on understanding fecal sludge management

practices in Dhaka to comprehensively address sanitation in the long term; (iv) planning

to improve services in LICs; v) defining an action plan and management structure for

DWASA’s decentralization. Implementation arrangements for the restructured project

were appropriate as the mandate for stormwater drainage remained with DWASA. Even

though the overall design of the restructured project was relevant, it also included several

new TA activities, even though DWASA’s capacity to implement ongoing works and

new TA activities was limited.

3.2 Achievement of Project Development Objectives

43. This section assess outcomes against project targets and objectives before and

after project restructuring.

Rating: Substantial (before restructuring) and Substantial (after restructuring)

Before restructuring:

PDO 1: Improve the sustainable delivery of stormwater drainage services (Substantial)

44. The project put in place permanent storm water drainage capacity of 40 m3/s

through the full commissioning of Rampura (25 m3/s) and Kamalapur (15 m

3/s) station

(original target 40 m3/s) before the closing date. The project has rehabilitated a total of 13

parts of drainage canals, covering a length of 20.89 km (formally revised target 20.855

km), representing an estimated increase in discharge capacity of 250 m3/s (formally

revised target of 250 m3/s). This objective was intended to be measured through

collection of depths and duration of water logging. However, DWASA did not have a

suitable monitoring systems in place and due to fluctuating year-on-year precipitation,

such empirical data would have to be collected over a long time period. Hence, drainage

impact modeling (See Annex 3) is a good alternative and evidences the widespread

reduction of flood as a result of the project investments in Dhaka. Risks of khal

siltation/clog-up and pump breakdown due to inadequate O&M remain (See section 4).

PDO 2: Improve the sustainable delivery of wastewater services (Negligible)

45. The project aimed to improve the sustainable delivery of wastewater services for

households in Dhaka, specifically those served by Pagla Sewage Treatment Plant (STP;

original PAD target from 50,853 to 57,000 households served, 280 km of sewer

rehabilitated, and Pagla STP capacity increased from 19,500 to 120,000 m3/day). These

improvements could not be realized and were canceled at the time of restructuring.

Page 29: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

13

PDO 3: Improve the sustainable delivery of water services, especially in low-income

areas (Negligible)

46. The project aimed to improve sustainable delivery and access to improved water

and safe sanitation in slum areas, targeting to reach 180,000 (water) and 218,000

(sanitation) people. These were not met, and the investments were canceled at the time of

restructuring.

After restructuring

PDO 1: Improve storm water drainage situation in select catchment of Dhaka

(Substantial)

47. The project resulted in improved storm water drainage in select catchments of

Dhaka. The stormwater pumping capacity target of 40 m3/day was met after the

commissioning of the Kamlapur and Rampura pumping stations. The khal rehabilitation

work for 13 canals was completed and their capacity increased by an estimated 250 m3/s

fulfilling the target (see Table 1). With Bank-executed funds, a drainage impact

modelling exercise was carried out for a one in ten year flood event assuming optimal

O&M. It found that the project investments will reduce the extent, depth and duration of

waterlogging in 24 wards in Dhaka city and would positively impact around 3.6 million

people (See Annex 3), of which 50 percent female. In case of partial pump failure and

siltation of khals, 0.5 million people in Central Dhaka would not fully benefit from this

flood reduction as a result of project investments11

. Nine focus groups discussions were

held in the Rampura catchment area along the rehabilitated Mohakhali canal.

Respondents stated less severe waterlogging during the heavy 2015 monsoon season

when the Rampura pumping station was operational (See section 3.6)12

. As indicated in

section 4, risks of khal siltation and pump breakdown due to inadequate O&M remain.

Table 1. Improve storm water drainage: achievement of indicators.

Indicator Target Achieved Comment

Number of direct project

beneficiaries (million)

4.0 3.6

PDO Indicator

Increase in permanent storm

water capacity

40 m3/s 40 m

3/s PDO Indicator (after

restructuring)

Increased capacity of

rehabilitated drainage canals

250 m3/s 250 m

3/s Intermediate Outcome

Indicator; baseline in 2013

was 60 m3/s

Drainage modelling of impact of

the project’s khal rehabilitation

and stormwater pumping

Yes No (not

attributable)

Intermediate Outcome

Indicator; Completed but not

attributable as this was Bank-

executed

11 IWM, 2016. Flood Modelling of Dhaka City – Impact and Resilience of Storm Water Drainage Investments of

Dhaka Water Supply and Sanitation Project. See also annex 3 for a summary of results. 12 DWASA (2015) Drainage Impact Assessment Exercise – Report on Focus Groups Discussion conducted in two

Catchment Areas of Dhaka. A total of 18 FGD were conducted, however, nine FGDs took place in Kamalapur

catchment area before the station was operational. This qualitative evidence should be seen as complementary to the

obtained results from the drainage impact modelling.

Page 30: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

14

PDO 2: Improve DWASA’s planning capacity (Modest)

48. The restructured project focused on institutional strengthening measures, as well

as planning, feasibility and design studies. A total of four different plans were to be

developed and approved by DWASA’s Board. Table 2 provides an assessment of the

indicators achieved.

Table 2. Improve DWASA’s planning capacity: achievement of indicators

Indicators Target Achieved Comment

No. of plans prepared &

approved by DWASA’s Board

of Directors (BoD)

4 2

PDO Indicator; Out 4 plans, 2

were prepared with Bank-

executed funds, and these plans

are not attributable to the project

A new sewerage masterplan is

approved by DWASA’s BoD

Yes Yes Intermediate Outcome Indicator;;

Approved on September 30, 2014

A new drainage masterplan is

approved by DWASA’s BoD

Yes Yes Intermediate Outcome Indicator;

Approved on June 23, 2016

Diagnostic study on septage

management practices in

Dhaka

Yes Yes Intermediate Outcome Indicator;

Strategy and implementation plan

for non-networked sewer

prepared

A Service Improvement Plan

for LICs is prepared (LICSIP)

Yes No (not

attributable)

Intermediate Outcome Indicator;

completed with Bank executed

funds; thus not attributable to the

project

Development of an

institutional structure for

DWASA’s decentralization

and an action plan for its

implementation

Yes No (not

attributable)

Intermediate Outcome Indicator;

completed with Bank executed

funds; thus not attributable to the

project

A new decentralized zonal

management structure and

action plan for its

implementation are approved

by DWASA’s BoD

Yes No Intermediate Outcome Indicator;

Not attributable to the project, as

this was Bank-executed. New

organizational structure prepared,

but not yet approved by BoD

49. As indicated in Table 2, the LICSIP, the decentralization structure and action plan

and the zonal management structure and action plan are not attributable to the project as

these were executed by the Bank using WSP funds (See section 1.7 and 3.5). Thus, the

PDO outcome is rated Modest.

50. The project also assessed DWASA’s financial aspects. Audited balance sheets for

FY11 – FY15 show that the ratio of current assets over current liabilities is above the

required threshold in the covenant, ranging from 2.05 to 3.13. DWASA’s income

statements show that a positive net income was maintained throughout the period, with

US$ 2 million (BDT 160 million) in FY15.

Page 31: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

15

3.3 Efficiency

Rating: Substantial

51. The economic analysis looked at impacts from flooding that occur with and

without the project investments over the period of 2016-2030 for a one in ten year flood

event (See Annex 3). The ICR analysis takes into account the likely socio-economic

changes in the project area from 2016-2030. Scenarios with various discount rates are

illustrated in Annex 3, using discount factors ranging from 3, 6, 9 and 13 percent. A

discount factor of 6 percent is confirm the latest World Bank Guidance note, while 13

percent was used at appraisal13

.

52. At appraisal, the economic analysis considered the benefits resulting from

avoided damage costs due to reduced flooding and avoided disruption in economic

activities. The Net Present Value (NPV) of project investments was estimated at

US$ 23.1 million at a 13% discount rate.

53. At project closing, a similar economic analysis was carried out, however the

hydraulic and economic model used was more refined as it was developed for a recent

Bank publication14

with support of the Bangladesh Climate Change Resilience Fund.

Using a discount rate of 6 percent, the NPV of project investments was estimated to be

US$ 24.2 million between 2016 and 2030 and the EIRR 12.1 percent (the present value

of the investments and O&M costs was estimated at US$ 53 million; and the present

value of the accumulated avoided damage was estimated at US$ 77.1 million). Avoided

damages can almost equally be attributed to khal rehabilitation and pumping station

investments. The majority (82 percent) of avoided damages occur in Central Dhaka

catchment. Using a discount factor of 13 percent (as used during appraisal), the NPV of

the project investments turns negative to US$ -4.6 million. However, it is to be noted

that the model used to quantify the benefits at project closing was different compared to

appraisal (see Annex 3). Furthermore, externalities due to flood investments cannot be

fully captured in the model.

54. A financial analysis for the khal rehabilitation was not carried out at project

closing since the investments do not generate additional revenues to DWASA. However,

an average unit cost per meter khal rehabilitated under the project was calculated. A unit

cost analysis for the khal rehabilitation was difficult to perform, as benchmarking is

complicated by site-specific conditions like cross-sections and lining requirements. An

average unit costs per meter khal rehabilitated under the project was calculated for

different canal lining types and compared favorably with DWASA’s budget norms15

.

55. Overall, the NPV is positive (at a 6% discount rate), EIRR is high, and unit cost

for khal rehabilitation was lower than DWASA norms, indicating high efficiency of

13 Word Bank Communications February 2016. (Fay, M., et al., 2016) Discounting Cost and Benefits in Economic

Analysis of World Bank Projects. Washington DC. 14

Dasgupta, Susmita; Zaman, Asif; Roy, Subhendu; Huq, Mainul; Jahan, Sarwar; Nishat, Ainun. (2015).

Urban Flooding of Greater Dhaka in a Changing Climate: Building Local Resilience to Disaster Risk.

Directions in Development--Environment and Sustainable Development; Washington, DC: World Bank. 15 Meter unit cost of khal rehab, for varying cross-sections range from US$ 1000-4000/m for RCC U-drains/retaining

walls and US$500-2000/m for Trapezoidal block lining. The values compare favorably with DWASA’s budget norms:

US$4500-5125/m for RCC U drains/retaining walls and US$3200/m for Trapezoidal block lining.

Page 32: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

16

investments. Although it took longer than anticipated to implement the project, the

interventions will lead to long term net benefits due to the impacts on reducing flood

damage. Thus, overall efficiency is rated as Substantial.

3.4 Justification of Overall Outcome Rating

Rating: Moderately Unsatisfactory

56. Before restructuring, the overall outcome rating is Unsatisfactory based on a

Substantial rating for relevance of objectives, a Modest rating for relevance of design

and implementation, a Substantial rating for efficiency, and a Modest rating for

achievement of PDO (efficacy). After restructuring, the overall outcome rating is

Moderately Unsatisfactory based on a Substantial rating for relevance of objectives,

relevance of design and implementation, efficiency, and a Modest rating for

achievement of PDO. Based on a weighted average as per the relevant disbursement

amounts before and after restructuring as indicated in Table 3, the overall Project

Outcome is Moderately Unsatisfactory.

Table 3. Calculation of outcome rating based on weighting

Pre-

restructuring

Post-

restructuring

Overall

Relevance of Objectives Substantial Substantial

Relevance of

Design/Implementation

Modest Substantial

Efficacy (PDO achievement) Modest Modest

Efficiency Substantial Substantial

Disbursement amount US$ 15 m US$ 57 m

US$ 7216

Weighting factor 21 % 79 % 100 %

Outcome rating 2

(Unsatisfactory)

3 (Moderately

Unsatisfactory)

2.8 rounded to 3

(Moderately

Unsatisfactory)

3.5 Overarching Themes, Other Outcomes and Impacts

(a) Poverty Impacts, Gender Aspects, and Social Development

57. Poverty Impacts: It is expected that the project will help improve overall quality

of life for all residents, including the poor, by reducing incidents of flooding and

waterlogging. In addition, project interventions resulted in water supply access for about

49,000 LIC residents. As a result of this work, DWASA’s capacity to provide water

supply services in LICs is also expected to improve.

58. Gender and Social Development Impacts. The project did not report any

specific gender or social development impact, other than stating 50 percent of direct

beneficiaries are female, based on the 2015 Bangladesh country estimates of the World

16 At project closing (June 2016), the XDR exchange rate represented a total of US$ 71.8 (see Annex 1)

Page 33: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

17

Bank. Water committees were established in LICs, to mobilize community contributions

and ensure regular fee collection for DWASA’s. These committees enhance social

capital and are instrumental in tackling issues and conflicts that may arise.

(b) Institutional Change/Strengthening

59. Due to the Bank and other partners’ support, DWASA has developed an

understanding of its obligations to serve LICs. Through this project, DWASA has also

nurtured partnerships with local and international Non-Governmental Organizations

(NGOs) to support interventions in LICs. Connections to LIC customers increased from

615 in 2013 to 3290 by August 2016, serving an estimated number of 545,617 residents.

The project demonstrated feasible water service delivery models. However, without

continued external support to its LIC unit and/or corporate budget prioritization, service

provision in these communities is unlikely to scale up rapidly17

.

60. DWASA is currently carrying out a review of a new organogram and is looking to

set up a new sewerage directorate, however this has not yet been approved by the

DWASA’s board.

3.6 Summary of Findings of Beneficiary Survey and/or Stakeholder Workshops.

61. DWASA commissioned 18 Focus Group Discussions (FGDs) in selected areas of

Dhaka to gather empirical qualitative evidence of impacts of project interventions. All

selected sites were low lying, densely populated areas that were regularly affected by

floods. The participants included petty business owners, homemakers, heads of

households, teachers, and school administrators. Across all FGDs, respondents indicated

that inundation led to negative impacts, including: transportation issues; loss of school

days; loss of livelihood; and increased costs for home and business maintenance. In nine

FGDs conducted along the Mohakhali khal in the Rampura station sites, respondents

reported less severe waterlogging. Many participants also suggested a need for improved

maintenance of canals and sewers, and better coordination between agencies responsible

for waste management, city planning and drainage.

4. Assessment of Risk to Development Outcome

Rating: Substantial

62. The risk to development outcome is rated as Substantial for the following reasons:

a) Pumping station sustainability: Risk to sustainable and optimal operation of the

pumping stations are: (i) Adequacy of human and financial resources for O&M,

including preventive maintenance. In FY13, the O&M budget for the two

pumping stations (with temporary pumping capacity of 12 m3/s) was US$86,000.

DWASA has not yet increased O&M budget forecasts18

for the new assets. (ii)

17 8 of 16 LIC staff are financed by WSUP. Development of LIC services requires resources for customer service

agents for social mobilization and community grants for investments beyond the service connections. These costs are

not yet internalized. 18 A modest estimate of 1 percent of investment costs would require US$ 300,000 O&M budget. DWASA forecasted

Page 34: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

18

O&M training for 20 DWASA staff was organized 18 months ago. The pumps

have recently become operational, and DWASA staff may need additional

training to ensure optimal operations. Moreover, complex repairs may have to be

handled by international experts.

b) Khal sustainability: DWASA procured drainage cleaning equipment under the

project and is also receiving TA on O&M for storm water drains from a Dutch

utility19

. However, average budgets for O&M for all khals for last three FYs was

on US$ 1.9 million annually and for FY17, the budget has been reduced to

US$ 0.9 million. Limited O&M budget and weak coordination with DCC in terms

of solid waste management can affect khal sustainability.

c) Execution of the sewerage and drainage masterplans: Successful

implementation of masterplans requires strong commitment from DWASA’s

Board and management to continue dialogue with relevant public agencies and

development partners. It requires broad support from all stakeholders, including

other agencies and the citizens. At this stage, consensus to implement the

masterplans is building. This is illustrated by the Government’s interest to engage

in a follow-up Bank operation that would use the recommendations of the

masterplans (the Dhaka Sanitation Improvement Project). However, it remains too

early to assess the sustainable use of these plans.

d) Integrated measures for improved drainage situation. In addition to putting in

place sustainable O&M arrangements for all drainage related infrastructure

(pumping stations, khals), sustaining the improved drainage situation requires

complementary investments along up and downstream parts of the drain canals to

stop encroachment and improve the hydraulic capacity of the entire system, and

not just isolated parts of the canals. It is not clear, if the prevention of

encroachment can be sustained in the longer term.

5. Assessment of Bank and Borrower Performance

5.1 Bank Performance

(a) Bank Performance in Ensuring Quality at Entry

Rating: Moderately Unsatisfactory

63. The Bank deployed a team with diverse technical skills to design and appraise the

project over a 3-year preparation period. The relevance of project objectives was

substantial and there was a clear focus on poverty through the LIC-component. A risk

assessment was carried out and mitigation measures were put in place. All relevant

safeguards were adequately addressed during design and appraisal. Fiduciary aspects

were informed by a capacity assessment in procurement and financial management and

relevant training measures and covenants were included to manage risk.

O&M budget for FY17 for two pumping stations is around US$ 150,000 19 This is separate from the Bank-supported project.

Page 35: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

19

64. The quality at entry was negatively affected by the following factors: (i) the

implementation timeline was tight at 4.5 years; (ii) additional work was needed on

bidding documents and feasibility studies for priority investments, which affected overall

project readiness; iii) the LIC component design had to be rethought in accordance with

DWASA’s capacity limitations and prior experience; and, v) additional capacity

strengthening activities were needed to ensure improved project management. Although

the project design deliberately did not include a large institutional component at entry, the

MTR showed that such measures could not be overlooked in order to strengthen

DWASA’s capacity for sustainable service delivery and focus on LICs.

(b) Quality of Supervision

Rating: Moderately Satisfactory

65. The Bank allocated sufficient budget and staff resources for the project. The task

team undertook regular implementation support missions and prepared detailed Aide

Memoires. Specialist consultants were proactively engaged to support the project. During

the initial project period, there were some weaknesses in M&E reporting (See Section

2.3), which were addressed after the MTR. At MTR stage, the task team candidly

assessed the project, mobilized seasoned utility exerts to assist in an institutional

diagnostics and conducted a close dialogue with the client to address shortcomings.

Based on this, a level-1 restructuring was completed one month before the original

closing date. Some of the activities agreed at the time of the restructuring were not

reflected in the Government’s DPP, for example, the LICSIP and the institutional

decentralization plan. The Bank, however, swiftly mobilized Bank-executed trust funds

for technical assistance to support the institutional reform in close collaboration with

DWASA. (See Section 2.3). The Bank also closely followed the construction of pumping

stations and khal rehabilitation through regular field visits and documentation of progress.

However, adequate transition and O&M arrangements for the newly developed assets

were not put into place.

66. Supervision of fiduciary and safeguard aspects was adequate. Resettlement issues

were dealt with in a pro-active manner. The Bank successfully handled a complaint along

one of the rehabilitated khals by engaging regional safeguard support and in order to

solve the case an external mediator was brought in with Bank support.

(c) Justification of Rating for Overall Bank Performance

Rating: Moderately Unsatisfactory

67. With Moderately Unsatisfactory rating for Quality at Entry, and a Moderately

Satisfactory rating for Quality of Supervision, the overall Bank performance is rated

Moderately Unsatisfactory.

5.2 Borrower Performance

(a) Government Performance

Rating: Moderately Unsatisfactory

68. The Ministry of Local Government Rural Development and Co-operatives

Page 36: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

20

(MoLGRDC) and the Ministry of Finance (MoF), Government of Bangladesh signed a

Partnership Framework in November 2007 with the Bank and other donors committing to

“address long-standing reform issues that have hampered effective operations, sound

financial management and good supply of services…” A Performance Agreement signed

between GoB and DWASA in 2008 was meant to reinstitute monitoring of performance

and the implementation of the provisions in the WASA Act. Although the Framework

was non-binding in nature, the absence of joint annual reviews of policy actions resulted

in limited policy level engagement. GoB and DWASA did not adhere to the annual audits

of the Performance Agreement, included as a covenant in the project, despite frequent

requests to do so in Aide Memoires, nor was the agreement continued after its expiry.

This hindered the assessment of DWASA’s progress towards becoming an autonomous

service delivery institution.

69. Slow government decision, for example, the time taken to approve the contract

variations for the two pumping stations and the revised DPP, had a significant impacts on

project implementation.

(b) Implementing Agency Performance

Rating: Moderately Unsatisfactory

70. DWASA was the sole project implementing agency. DWASA put in substantial

effort to facilitate coordination with stakeholder in transfer of land for the pumping

station and consistently followed up with GoB ministries to ensure the all bureaucratic

processes were followed. DWASA also followed all Bank safeguards policies, helping

resolve resettlement issues effectively.

71. Project progress was affected by DWASA’s limited technical capacity and

chronic understaffing to assess the adequacy and quality of studies, for e.g. the sewerage

and drainage master plan. The PMU was heavily burdened with complex procurement

and extensive handholding from the Bank was needed throughout the project period to

ensure that Bank’s policies were followed. The Bank team suggested increasing PMU

staff and hiring consultants for procurement, contract management, site supervision and

FM. However, this was not completed. Several institutional measures included at

restructuring and reflected in the legal agreements were not included in the revised DPP

and hence could not be financed under the project, affecting achievement of institutional

development objectives.

(c) Justification of Rating for Overall Borrower Performance

Rating: Moderately Unsatisfactory

72. With a Moderately Unsatisfactory rating for Government Performance and a

Moderately Unsatisfactory rating for Implementing Agency Performance, the overall

Borrower performance is rated Moderately Unsatisfactory.

6. Lessons Learned

73. Project Readiness. Realistic timelines, targets and readiness of designs are

necessary for large and complex infrastructure projects. This can help avoid a situation in

which the entire process from identification, feasibility, design, procurement and

construction has be completed within one project cycle. Therefore, to mitigate

Page 37: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

21

unnecessary implementation delays, funds for the preparation of future investments

studies and bidding packages can be allocated within the project. DWSSP demonstrated

this approach successfully. After restructuring, long-term master plans, conceptual design,

feasibility studies, and bidding packages for the next round of priority investment were

delivered. The phasing of large infrastructure investments through various project cycles

will be an effective way to ensure that each project has a large amount of its

infrastructure investments ready at approval (design, bidding and land assignment), while

preparing the detailed documents for the next follow-on stage.

74. Integrated urban planning. While integrated solutions for drainage, sanitation

and solid waste would be ideal, their complexity need to be balanced with the capacity of

the implementing agencies. With increasing emphasis on integrated urban solutions,

future project interventions would need to include some elements of integrated planning,

involving multiple institutions, while at the same time recognizing that implementation

may be less streamlined if many agencies are involved. The project could not address

integrated solutions well, as it positioned itself solely with DWASA and it did not engage

substantially with DCCs that are responsible for solid waste management and khal clean-

up. The sewerage and drainage masterplans emphasize incentives for better coordination,

the need to delineate and rationalize mandates, and can provide a vehicle to gradually

implement such institutional changes, while building capacity of the various entities.

75. Sustainability and institutional measures. Institutional measures along-side

large infrastructure projects cannot be left unaddressed to ensure sustainable services.

Inadequate utility performance is often a symptom of a lack of a proper institutional set-

up. In this case, the project did not address DWASA’s overall financial sustainability to

ensure that adequate financing arrangements were in place for O&M of pumping stations

and regular clean-up of the khals. Institutional measures would need to be accompanied

with monitoring of performance indicators and business incentives, as proposed in

DWASA’s new organizational structure that emphasizes decentralization of services.

76. LIC service delivery. Service delivery to LICs is complex and requires

comprehensive planning, based on an understanding of slum types, existing conditions,

legal aspects, suitable technologies, and different service delivery models. The project

struggled to implement a “pilot and replicate” program for LIC areas due to complexities

in service delivery and the need to go beyond a “blue-print” service delivery model. A

strategic and comprehensive approach is articulated in the LICSIP and forms a solid

foundation for DWASA to expand services to LICs with support from development

partners and NGOs.

77. Complementarity of Bank-executed funds for Technical Assistance. When

project activities include institutional measures, it is essential to ensure that Bank-

executed funds are not used to “substitute” activities that should be executed by the

implementing agency of the project. The Bank can provide complementary Bank-

executed technical assistance, while ensuring that core institutional activities linked to the

project development objective will be implemented the project implementation agency.

78. Procurement. The procurement process needs be identified upfront and reflected

in the overall project work plan. A clear set of criteria should be developed to evaluate

the proposals and assess the strength of the vendors. The procurement process should be

Page 38: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

22

decided based on the nature and complexity of works and should include an assessment

of various technology options. The two-stage bidding process used for the pumping

stations may not have been required if such upfront assessment of technologies had been

carried out. In addition, even though larger packages are desirable to avoid inefficiency,

under this project it was clear that for civil works with local tendering (such as for canal

rehabilitation), smaller packages were better suited to the capacity of local contractors.

7. Comments on Issues Raised by Borrower/Implementing Agencies/Partners

(a) Borrower/implementing agencies

79. Annex 5 provides a summary of the Borrower’s ICR. The report provides a good

overview of the project design and assessment of its implementation. Findings are

generally consistent with this ICR, although there are some discrepancies in data and

ratings for outcome achievement and Bank and Borrower performance. The Borrower’s

evaluative comments highlighted that a long-term engagement combining investments

and TA is a suitable approach to strengthen DWASA’s capacity.

(b) Cofinanciers

NA

(c) Other partners and stakeholders NA

Page 39: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

23

Annex 1. Project Costs and Financing

Dhaka Water Supply and Sanitation Project – Credit Number – 4506-BD

(a) Project Cost by Component (in US$ million equivalent)

Components20

*

Appraisal

Estimate

(US$ m)

(IDA)

Revised

Estimate at

Restructuring

(US$ m) (IDA)

Actual Estimate

(US$ m)

(IDA)21

Percentage

at

Appraisal

(% of IDA)

Percentage

of Revised

(% of IDA)

Component 1: Investment

Planning in Sanitation 63.8 3.1 3.87 6% 102%

Component 2: Rehabilitation and

Strengthening of Storm Water

Drainage System

80.3 60.5 52.28 69% 86%

Component 3: Support to the

Implementation of Environmental

and Social Safeguards

5.2 2.3 1.03 21% 45%

Component 4: Support to Service

Improvement Planning in Low-

Income Communities

8.7 1.5 1.82 22% 121%

Component 5: Project

Management and Institutional

Capacity Building

7.7 8.6 12.69 174% 148%

Total Baseline Cost 165.7 76.0 70.9 48% 93%

Total Contingencies**

Total Project Costs 165.7 76.0 71.8

Front-end fee PPF

Front-end fee IBRD

Total Financing 165.7 76.0 71.8

** Contingencies were included in component estimates. Physical and price

contingencies at appraisal were US$ 19 million, and US$ 6 million after restructuring.

(b) Financing

Source of

Funds

Type of Co-

financing

Appraisal

Estimate

(US$ millions)

Revised

Estimate

(US$ millions)

Actual/latest

Estimate

(US$ millions)

Percentage

at Appraisal

Percentage of

Revised

Borrower 16.70 NA 0.9 5% NA*

IDA 149.0 76.0 70.9 51% 93%

Total 165.7 76.0 71.8 43% 94%

* In the restructuring paper no counterpart funding is included to finance the restructured

project cost. The total use of GoB fund stands at BDT 70.0 million, or US$ 0.9 million.

20 Components 1, 4, and 5 were renamed after restructuring. This information is included in Section 1.2 and 1.3 21 At the beginning of the project, based on the then applicable exchange rate, the IDA credit of XDR 94.8 million was

US$ 149 million. Due to variation in the XDR-US Dollar exchange rate, XDR 94.8 million was US$ 141.3 million at

the time of restructuring. After cancellation and at the time of restructuring (June 2013), the project total was XDR 51

million or US$ 76 million. At project closing (June 2016), XDR 51 million was US$71 million.

Page 40: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

24

Annex 2. Outputs by Component

Component 1: Investment Planning in Sanitation (actual IDA US$ 3.17 m)

(previously: rehabilitation and Strengthening of Existing Sewerage Systems)

Component 1 focused on the rehabilitation, repair and expansion of priority investments

in the city’s sewerage network and treatment plant to help improve the urban

environment. The start of activities under this component was considerably delayed, due

to procurement issues, lengthy GoB approvals, and debate on technical design issues. As

a result, the component was significantly amended at the time of restructuring and the

name was changed to Investment Planning in Sanitation (original IDA US$ 52.4 million

was reduced to US$ 3.1 million). At restructuring, it was determined that investments

could not be completed and were dropped. Instead the focus of shifted to support

DWASA’s planning capacity for wastewater investments.

DWASA prepared a sewerage master plan, which was endorsed by the Board on

September 30, 2014.The plan identifies US$ 1.7 billion worth of investments for Dhaka

city. Based on the priority investments identified in the master plan, DWASA updated

the bidding documents for the eastern trunk sewer and rehabilitation/expansion of Pagla

STP. In addition, a comprehensive package of engineering designs and bidding

documents for wastewater treatment and sewerage investments in Mirpur and Uttara

catchments, as well as an overall diagnostic study on fecal sludge management (FSM)

were prepared.

Table 2.1 below indicates the achievements of indicators that relate to the original and

revised component 1.

Table 2.1 Achievement of indicators relating to component 1

Indicators baseline target achieved Comment

A new sewerage masterplan is

approved by DWASA’s Board of

Directors

no yes yes On September 30, 2014

Diagnostic study on septage

management practices in Dhaka

no yes yes Diagnostic study and plan

for non-network sewer

(FSM) arrangements were

carried out

Number of households with

access to sewer services

51,800 57,000 no Indicator was dropped after

restructuring

Length of sewer lines

rehabilitated/extended (km)

0 280 no Indicator was dropped after

restructuring

Number of sewer blockages

reported (no/km)

0.54 0.25 no Indicator was dropped after

restructuring

Volume of wastewater collected

and treated in Pagla (m3/day)

19,500 120,000 no Indicator was dropped after

restructuring

Component 2- Rehabilitation & Strengthening of Stormwater Drainage (actual IDA

52.3 m)

Component 2 represents the major infrastructure works under this project that aimed at

improving the drainage situation and reduce urban flooding. The component included (i)

construction of Rampura and Kamalapur stormwater pumping stations; (ii) khal

Page 41: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

25

rehabilitation; (iii) storm water drainage cleaning equipment, and (iv) preparation of the

Drainage Master Plan.

Construction of Rampura and Kamalapur stormwater pumping stations

As per Bank guidelines, DWASA started a two‐stage bidding process for the pumping

station contracts. The procurement process took over 40 months. Contracts became

effective 11 months after the Bank’s no objection. Land transfer for Kamalapur station

(from Bangladesh Railways) required various approvals, further delaying physical works

till September 2013. Additional time was also required for approval of contract variation

orders. Rampura pumping station progressed faster and the Completion Certificate was

issued on January 7, 2015. During the warranty period, it was noted that the sluice gates

were not watertight. As a result, these were refurbished, and re-evaluated. Based on

successful testing, an Operational Acceptance Certificate was issued on June 29, 2016.

Most major works for the Kamlapur station were completed by June 2016, and the

Completion Certificate and Certificate of Operational Acceptance were signed on June 26,

2016, and June 30, 2016, respectively. The total permanent capacity of the two pumping

stations is 40 m3/s (25 m

3/s for Rampura and 15 m

3/s for Kamalapur). Both stations were

designed for a one in five year 2 day rainfall event and replace previous temporary

pumping capacity of 12 m3/s. A total of US$ 30.7 million was spent on the pumping

stations.

Canal Rehabilitation

The component included the rehabilitation of selected drainage canals by re‐excavation,

re‐profiling, and protection and improvements of their banks. The objective was to

improve drainage flow and prevent encroachment, using a 2 day rainfall for a one in five

year return period. Some canals were dropped due to complex resettlement issues.

Ultimately, 13 sections with a total 20.89 km in length were rehabilitated, increasing

average design drainage with 250 m3/s drainage capacity (no individual canal values

could be provided) (see Table 2.2). A total of US$ 17.8 million was spent on canal

rehabilitation.

Table 2.2. Details of khal rehabilitation

No. Name of Canal Completed Length

(m)

Avg. new design

discharge (m3/s)

Old design

discharge

(m3/s)

1 Khilgaon-Bashabo Khal Apr 2015 1440 27.72 na

2 Shahjahanpur Khal Jul 2015 477 na na

3 Gerani Khal Jun 2013 4005 65.93 na

4 Shajadpur Khal Dec 2015 1914 38.93 na

5 Kallayanpur Main Khal Jun 2015 720 77.49 na

6 Baunia Khal Jul 2012 1030 99.48 na

7 Digun Khal Mar 2013 3720 180.65 na

8 Mohakali khal Aug 2013 630 55.31 na

9 Abdullahpur Branch Khal Feb 2015 131.2 na na

10 Sutivola Khal Dec 2015 3180 41.40 na

11 Abdullahpur Khal Jun 2016 3000 51.94 na

Page 42: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

26

12 Segunbagicha Khal Jun2016 431 75.29 na

13 Khilgaon-Bashabo (upstream) Dec 2015 212.5 na na

Total 20,890.7

Stormwater Drainage Cleaning Equipment

Various drainage cleaning equipment were procured. The procured drainage equipment

included a mini-excavator, dump truck, tractor, jetting and suction machine, ten O&M

vehicles, and light maintenance equipment. The sub-component financed the installation

of gauges at 3 locations to monitor inundation.

Dhaka Drainage Master Plan

The Dhaka Drainage Master Plan was completed in August 2015. It was approved by the

Board by June 23, 2016 and disseminated to stakeholders. It includes both structural and

nonstructural aspects, although various non-structural issues are described in terms of

options and will need further agreements between relevant public agencies (such as DCC

and DWASA). As per the master plan, US$ 1.99 billion investment is required to

improve drainage across 13 management zones by 2040. To support asset management, a

Storm Water Drainage Management Database was established and staff were trained in

the use of this tool.

Table 2.3 Achievement of indicators relating to component 2

Indicators baseline target achieved Comment

Number of direct beneficiaries, of

which female 50 percent (million)

no 4.0 3.6 Based on calculation

noted in annex 3

Increase in permanent storm water

drainage capacity (m3/s)

0 40 40 after restructuring,

this was a PDO-level

indicator

Increased capacity of rehabilitated

drainage canals (m3/s)

0 250 250 No comparison

between discharge

before and after

rehabilitation could

be found

Length of storm water drainage canals

developed (km)

0 20.80 20.89 Fully achieved.

A new drainage master plan is

approved by DWASA’s BoD

no yes yes Fully achieved

Drainage modelling undertaken of the

impacts of i) khal rehabilitation and ii)

storm water station

no yes No (not

attributable)

Completed but not

attributable to the

project, financed with

GFDRR funds

Water level and number of days of

waterlogging in eastern part of Dhaka

na na No Indicator was

dropped after

restructuring

Volume of solid waste collected along

the canals (t)

0 20,000 No Indicator was

dropped after

restructuring

Page 43: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

27

Component 3 Implementation of Environmental and Social Safeguards (actual IDA

US$ 1.02)

Environmental support

The environmental and safeguards program was defined in the PAD. The initial plan was

quite ambitious. It included: (i) the establishment of an environment unit (Circle) in

DWASA to support safeguards implementation in subprojects; and (ii) capacity

strengthening of the DWASA Central Lab. However, at restructuring, the project scope

was reduced, and these activities were dropped.

The following outputs and were achieved:

Implementation of the Environmental Management Framework was fully

implemented, including: (i) use of limited environmental assessments for the

preparation of the Environmental Management Plan in 12 sub‐projects; ii)

Environmental Impact Assessment for three of the larger projects; iii) testing of

excavated materials (in canals) for potentially harmful substances (they were

found to be free of toxic materials in significant concentrations)

Capacity Building on Environmental Management: the project was able to

improve the analytical and environmental management capacity of the DWASA

Central lab, through: i) procurement of laboratory equipment22

and chemicals, ii)

provision of vehicle and motorbike for sample collection, iii) providing training

for staff in use of newly procured equipment, Quality Assurance and Quality

Control (QAQC) in chemical analysis, and Standard Operating Procedures (SOP),

iv) water quality assessment for Dhaka watershed, and v) international training.

All equipment was installed properly in DWASA Central Lab. DWASA lab staff stated

that not all reagents were procured, and thus some of the equipment is not yet in use.

DWASA lab staff are now able to take samples and analyze these as per agreed QAQC

and SOPs. Sampling frequency (around 250-300/month) is still restrained due to

available budget. The water quality assessment for Dhaka watershed produced water

quality maps for three quarters of a hydrological cycle. These maps can be used by

DWASA to plan for flood events.

Safeguard Support

During project preparation, DWASA undertook a Social Impact Assessment (SIA),

including extensive community/stakeholder consultations for each canal and for the storm

water drainage pumping stations. Resettlement Plans were prepared and implemented in

close coordination with the Bank team. The project built PMU capacity to handle

complex resettlement issues. These lessons were reflected in the revision of the

Resettlement Policy Framework. Complex khal rehabilitations were dropped23

, to

22 A full listing of equipment has been provided in the ISRs. 23 In one of the khals eviction took place of an unknown number of people. A tracer study was expedited by DWASA.

However due to the risk that these studies are incomplete, this khal was dropped. A total of seven khals were dropped

due to complex resettlement issues

Page 44: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

28

minimize the number of PAHs. A total of 216 households were compensated along the

khals and 225 households received compensation (US$ 0.3 million). Table 2.4 indicates

the achievements under this component.

Table 2.4 Achievement of indicators relating to component 3

Indicators baseline target achieved Comment

Number of project affected

households successfully

compensated

no 500 441 This represents all

households that were

eligible for compensation

Component 4 Support Service Improvement Planning in Low-Income Communities

(actual IDA US$ 1.82 million)

The original component was expected to support pilot sub-projects in various low-income

communities (LIC) and focused on strengthening DWASA’s capacity to provide services

to LICs. At restructuring, the scope of the component was considerably reduced. The

restructured component focused on improving DWASA’s capacity to serve LIC residents.

The project financed three deep tube wells in six LICs and supported small value works

to connect LIC customers. As a result, about 49,000 people in six LICs gained access to

legal water supply (see Table 2.5). Table 2.6 indicates the achievements under this

component.

Table 2.5. Access to water supply in LICs by the project

No. LICs Persons Households Total

Connections

1 Duaripara 10,770 2,692 101

2 Mollar Basti 11,960 3,148 123

3 Kallayanpur 11,357 2,840 180

4 Kalshi 8,976 2,244 118

5 Beguntila 3,954 988 60

6 City colony 1,991 556 70

Total 49,008 12,468 652

Table 2.6. Achievement of indicators relating to component 4

Indicators Baseline Target Achieved Comment

Service Improvement Plan for

LICs is prepared

No Yes No (not

attributable)

Completed but not

attributable to the project,

financed with WSP funds

Increase in number of people in

project area ward slums with

access to safe water

0 180,000 NA This indicator was

dropped at restructuring;

nevertheless achievements

were made

Increase in number of people in

project area ward slums with

access to improved sanitation

0 218,000 NA This indicator was

dropped at restructuring

Page 45: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

29

Component 5 Project Management & Institutional Capacity Building (actual IDA

US$ 12.7m)

At restructuring this component focused on institutional strengthening to position

DWASA as a stronger service delivery institution. An institutional assessment suggested

that decentralization would allow DWASA to deliver effective and efficient services.

Through Bank-executed resources, Water and Sanitation Program (WSP) facilitated the

execution of a diagnostic study and an option study to investigate appropriate

decentralized organizational structures, aimed to improve incentives for effective zonal

management. An implementation plan for its preferred decentralized organizational

arrangement was delivered, including a new organogram for DWASA, outline of job

descriptions for key positions, and revised salary structure. DWASA’s management and

Board is currently considering the proposal.24

Under this component, the repair, refurbishment and equipment for six zonal offices and

the existing training center was also executed.

Table 2.7 Achievement of indicators relating to component 5

Indicators baseline Target Achieved Comment

Annual statuary audits for

DWASA demonstrating

transparent and accountable

financial management

1 4 4 Indicator before

restructuring defined

qualitatively “no fiduciary

issues with project funds”,

which is achieved

Development of an institutional

structure for DWASA

decentralization and an action

plan for its implementation

no yes No (Not

attributable)

Completed but not

attributable as financed

with Bank executed funds

(WSP)

A new decentralized zonal

management structure and an

action plan for its

implementation are approved by

DWASA’s BoD

no yes No Proposed organigram was

developed with Bank

executed funds; proposal

not approved by DWASA

Board

DWASA Zonal Offices

refurbished and equipped

0 1 6 Total of 6 zonal offices

have been refurbished and

equipped

24 See also Castalia (2015) Options Report of the Organizational Structure of DWASA. Three options were proposed

with increasing degree of autonomy at zonal level. DWASA’s preferred option was the “Integrated Zonal

Management”. This implies that each zone is organized under an administrative unit, headed by a Zonal Manager. This

model strives to improve collaboration between technical and commercial teams, minimize costs and optimize

efficiency through increased accountability at zonal level.

Page 46: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

30

Annex 3. Economic and Financial Analysis

The project planned for investments in i) storm water drainage infrastructure, including

storm water pumping stations and canal rehabilitation, ii) sewerage investments, and iii)

water supply and sanitation investments in LICs. After restructuring the investments were

narrowed to drainage improvement. The economic analysis at appraisal stated that project

benefits would accrue from avoided damages to infrastructure, avoided disruption in

economic activities, and avoided environmental degradation and their associated costs to

the society. Using a damages impact model available at that time, it was estimated that

the NPV of incremental benefits was US$ 23.1 million at a 13 percent discount rate for a

one in five year flood event. The IRR of the project at appraisal was estimated at 17.2

percent. It was estimated that a total investment of US$ 80 million would be required for

the drainage investments, including recurrent O&M costs.

This ICR economic analysis uses in principle the same avoided damages methodology,

however has benefitted from the development of recent hydraulic and economic damage

models with support of Global Facility for Disaster Risk Reduction for a series of

recently published World Bank reports on climate change and the impact of urban

flooding in Dhaka25

. The ICR analysis uses the actual costs for the drainage investments,

accounting for US$ 47 million and reasonable estimates for recurrent O&M expenditures

and includes state-of-the-art i) hydraulic modelling to estimate the impact of the project

investments on urban flooding, and ii) analyses of avoided damages and the estimation of

economic benefits26

. Other differences than the hydraulic and economic models used at

appraisal and at ICR are i) the return period used (at appraisal one in five year, at ICR

one in ten years), ii) discount factor (at appraisal 13 percent, at ICR 6 percent), and iii)

the lifespan of NPV calculations (at appraisal 30 years, at ICR fifteen years). A

sensitivity analysis has been carried out that uses discount factors of 3, 9 and 13 percent,

the latter being used at appraisal27

.

Flood modelling

The objective of the study is to simulate the impact of project investments, particularly on

changes in flood depth and duration across the project area. In addition, the study also

aimed to simulate different O&M scenarios, demonstrating the need to maintain well-

functioning drainage infrastructures and institutions. The location of project investments,

including for the pumping stations and the 13 canals, is indicated in Figure 3.2. The

25 Dasgupta, Susmita; Zaman, Asif; Roy, Subhendu; Huq, Mainul; Jahan, Sarwar; Nishat, Ainun. 2015. Urban

Flooding of Greater Dhaka in a Changing Climate: Building Local Resilience to Disaster Risk. Directions in

Development--Environment and Sustainable Development;.Washington, DC: World Bank and World Bank (2015b).

Climate and disaster resilience of greater Dhaka area: a micro level analysis. Bangladesh development series; paper no.

32. Washington, D.C. World Bank Group. 26 These are IWM (2016) Flood Modeling of Dhaka City – Part 2 Impact and Resilience of Storm Water Drainage

Investments of Dhaka Water Supply and Sanitation Project (DWSSP); and Roy, S. (forthcoming) The Impact of Storm

Water Drainage Investments by DWASA in Greater Dhaka Area – Estimation of Potential Damages Component and

Economic Analysis. 27 Discount rate of 6 percent is the current recommended practice as per the World Bank (2016) Discounting Costs and

Benefits in Economic Analysis of World Bank projects. The discount period used is conservatively estimated at 15

years, while benefits may extend beyond this period but are not expected to contribute considerably due to the time

value of money.

Page 47: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

31

modeling was done for a ten year flood event, applying a hydraulic inundation model

with existing drainage infrastructure and baseline conditions of 2010 for imperviousness

of surfaces and land-fill/topographic conditions. In addition, scenarios were simulated

with different O&M levels (e.g. siltation of canals due to lack of maintenance, fall-out of

1 or 2 pumps at monsoon peak).

Data for the improved khals cross sections and pumping station regime were collected

from DWASA and used to update the hydrodynamic model for the “with project”

scenario. Other boundary conditions are external water levels, inter-zonal flows and

wastewater flows. The modelling used the latest drainage models for four catchment

zones: i) Central Dhaka, ii) Kallyanpur, iii) Goranchatbari, and iv) eastern Dhaka. Results

for flood depth and duration comparing the “without” project” and the “with project”

scenario for each of different zones are summarized in Table 3.1.

Table 3.1. Summary of impact of project investments on flood depth and duration Catchment

zone

Flood depth Flood duration Comment

Central Dhaka Significant reductions in

flood extent and depth in

ward 24, 31, 32 and 75

Large to modest reduction

in average flood duration

in ward 21, 23, 24, 25, 26,

30, 31, 32, 33, 35, 37, 54,

55, 75, 76, 84, 85 (up to

25 hrs)

Includes two pumping

stations and three khals

rehabilitated

Overall flood depth

increase slightly in ward

22 and 5528

Kallyanpur Mixed reduction/increase

in flood depth in ward 10,

13, 16, 4329

No significant changes in

average flood duration

One khal was rehabilitated

Goranchatbari Slight decrease in

medium flood depth in

ward 15

Slight decrease of average

flood duration in ward 4,

5 and 15

Four khals were

rehabilitated

Eastern Dhaka No significant change in

flood extent and depth

No significant change in

average flood duration

Five khals were

rehabilitated

The extent by which the khal rehabilitation helped to mitigate urban flooding in other

catchment areas is minor, mostly because: i) khals have only been improved partially (not

the whole system), and ii) the influence of the improvement is localized to the

rehabilitated area as the drainage system is controlled by downstream levels.

Nevertheless, the canal rehabilitation produced other benefits, such as the protection from

encroachment, aesthetic enhancement, and improvement of waste water flow in off-peak

season.

Economic modelling

The economic modeling exercise estimates the reduction in monetary damages due to

project interventions by comparing the “without project” and “with project” scenario

results using 2016 socio-economic conditions. The monetary damage is estimated by

28 This is due to high initial water level at Hatirjheel retention area (not the case in the “without project” scenario) 29 In ward 10 and 43 (downstream of improved Kallyanpur canal) the area with low and medium flood depth is

decreasing, while area with high flood depth has increased. In ward 13 and 16 the reverse situation is found (upstream

of the improved canal section).

Page 48: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

32

examining the direct and indirect impacts of flooding.

Flooding can affect buildings and property and lead disruption of livelihoods. The longer

duration of the flood can exacerbate the damage. While impacts like damage to property

and loss of income from flooding can be more easily quantified, it is often difficult to

assign monetary values to the socio-economic, environmental, and health impacts of

flooding. Wherever possible, the analysis tried to impute monetary values for these

intangible damages.

The analysis compared the economic impacts with and without project interventions from

a one in ten year flood event over a fifteen year period (2016-2030)30

. Changes in the

valuation of damage between 2016 and 2030 are estimated using a 6 percent growth in

GDP, the average rate over the past decade. To assess the damage in real terms, all

economic data are based on 2016 prices and thus ignores any inflation that can occur by

2030. The analysis also takes into account the likely socioeconomic changes in the

project area during a 15 year period, which includes considerable uncertainties given

Dhaka’s rapid development. To determine the expected total damage between 2016 and

2030, the cumulative damage between 2016 and 2030 is based on random assignment of

1-year to 10-year storms during each year.

Flood damage is split into two categories: direct damage and indirect damage - if time is

a primary factor for the estimates.

Direct Damage: This economic loss is primarily concerned with the damage to physical

capital from water submersion, and the depth of flooding is the primary determinant of

such damage. However, the degree of damage can also increase with the duration of

flooding of a given depth. The most common examples of damage to private resources

are buildings and property. Other losses include damage suffered by owners of transport

vehicles, and telecommunication and electric infrastructure. Publicly owned

infrastructure like roads, railways, water and sewerage facilities, etc. can be damaged.

Indirect Damage: The main determinant of such damage is the duration of the flooding

above a certain depth that can lead to disruption of normal activity over a period of time.

While majority of the loss in this category will occur during the flooding, some of the

losses can continue even after water recedes. The most significant component of this loss

arises from the loss of income due to the inability of people, businesses, and industries to

carry out their normal economic activity. The loss of resources covered under direct

damage can also prolong the total or partial loss of earning capacity even after flood

water recedes. Indirect damage can also occur from impacts on transport and

communications infrastructure. Indirect damage also arises from additional health care

costs and reduced income from higher morbidity (See Table 3.2).

30 While the economic lifespan of the investments are longer, the projection beyond fifteen year will add additional

uncertainty in the assumptions, and due to the time value of money will not contribute greatly to the overall damage

estimates.

Page 49: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

33

Figure 3.1. Drainage investments done under the project

Page 50: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

34

Table 3.2. Assessment of damages across sectors Sector Direct Damage Indirect damage

Residential Building, Property Loss of Income

Commercial Building, Property Loss of Income

Industrial Building, Machinery, Inventory Loss of Income

Health Infrastructure, Mortality Treatment costs, Morbidity

Roads Infrastructure Travel Dislocation

Transport Damage to vehicles Loss of Income

Railways Infrastructure Travel Dislocation

Avoided damage estimates and affected beneficiaries

The accumulative damage for the period 2016-2030 for the different catchment areas is

indicated in Table 3.3. The largest damage reduction occurs in avoided income loss31

,

followed by residential property and buildings. The cumulative damage reduction from

project implementation is around US$ 77.1 million.

The number of beneficiaries is the total (2016) population living in the wards where

project interventions are expected to have an impact (See Table 3.4). The total number of

people benefiting from project interventions is estimated to be around 3.6 million32

.

Table 3.4. Estimated number of population (in million) affected by project investments Central

Dhaka

Kallyanpur Goranchatbari Eastern

Dhaka

Total

Total population in

catchment

3.73 3.04 5.16 5.27 17.2

Population positively

impacted

1.37 0.97 1.22 0.01 3.6

Population negatively

impacted33

0.29 - - - 0.3

31 Income losses for Dhaka residents are estimated based on per capita GDP data as it reflects per capita income of

residents. The income loss computation is based on the number of people affected by flood multiplied by the lost work

days among them. The income loss also includes the loss suffered by migrant workers coming daily to Dhaka. 32 In the worst case maintenance scenario (2 pump failure, 30% siltation), five wards in Central Dhaka (w30, w31, w32,

w38, w75) will experience significant negative impact, with around 0.5 million people experiencing less than optimal

flood reduction due to the project investments 33 0.3 million people will experience an increase in flooding due to changes in the fixed water level at Hatirjheel

retention pond ( beyond the influence of the project)

Page 51: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

35

Table 3.3. Accumulated Damage in Catchments for 2016-2030 (discount factor 6 percent)

Cost Benefit Analysis and Ratios

The analysis also looked at the separate impacts of the two pumping stations, and the khal

rehabilitation, and showed that the pumping stations would account for US$ 42.3 million,

and the khal rehabilitation for avoided damages of US$ 34.8 million (Table 3.5).The

economic return from the project is based on the avoided damages from the project and

the initial investment costs and annual O&M costs under the project for 2016-2030. A

total investment of $48.5 million was used for the complete project ($30.7 million for

installation of two new pumps and $17.8 million for rehabilitation of the canals). Based

on past experience, the O&M costs for the two pumping stations were estimated at

US$ 0.15 million annually and for the khals at US$ 0.31 million. The ratios are presented

in Table 3.5. Table 3.5. Results of Cost Benefit Analysis with discount factor of 6 percent

PV of

Investment

and O&M

(US$ m)

PV of

Avoided

Damages

(US$ m)

Net Present

Value

(US$ m)

Return on

Investment

Economic

Internal

Rate of

Return

Total Project 53.0 77.1 24.2 1.46 12.1%

Pump Installation 32.2 42.3 10.2 1.32 9.9%

Canal Rehabilitation 20.8 34.8 14.0 1.67 15.7%

Central Dhaka Kallyanpur Goranchatbari Eastern Dhaka

without with avoided Without with avoided without with avoided without with avoided

Residential

Building 43.4 32.0 11.4 33.1 29.8 3.3 9.5 9.3 0.2 820.6 820.5 0.1

Residential

Property 57.9 44.7 13.2 35.9 32.6 3.4 12.3 12.0 0.3 806.5 806.5 0.1

Commerce 9.4 5.6 3.8 3.1 2.9 0.2 2.1 2.1 0.1 219.6 219.6 0.0

Industry 24.1 17.8 6.3 8.3 7.8 0.5 5.6 5.4 0.1 602.5 602.5 0.0

Income

Loss 47.6 33.9 13.7 29.3 27.2 2.1 6.1 5.6 0.4 1480.2 1479.9 0.2

Health 29.3 23.0 6.3 8.8 8.3 0.5 10.9 10.8 0.2 51.5 51.5 0.0

Roads 7.5 3.2 4.4 6.7 6.3 0.3 2.4 2.3 0.1 332.4 332.4 0.0

Railways 1.3 0.7 0.5 0.8 0.7 0.1 0.1 0.1 0.0 33.1 33.1 0.0

Transport 13.0 9.1 3.9 17.7 16.6 1.1 9.0 8.7 0.3 1736.9 1736.8 0.0

Total 233.5 170.0 63.4 143.8 132.2 11.6 58.0 56.3 1.6 6083.5 6083.0 0.5

Page 52: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

36

The total project has a high ROI of 1.46 with a positive NPV of $ 24.2 million. The EIRR

is 12.1 percent. Both investments (pump installation and canal rehabilitation) show

positive returns. The damage estimates reveal that for a one in 10 year flood, project-

related damage savings from 2016-2030 exceed the investment made in the project. The

EIRR of 12.1 percent reveals significant returns from the investment.

Sensitivity analysis for different discount factors

Table 3.6 summarizes the ratios, using different discount factors of 3, 9 and 13 percent

(the latter was used at appraisal). As can be seen, the EIRR slightly decreases from 12.1

percent for a discount factor of 6 percent, to 10.9 percent with a higher discount factor of

9 percent and the project continues to deliver net economic benefits.

Table 3.6 Ratios for situation with different discount factors

Discount

factor

PV of

Investment

and O&M

(US$ m)

PV of Avoided

Damages

(US$ m)

Net Present

Value

(US$ m)

Return on

Investment

Economic

Internal Rate

of Return

3% 54.0 98.5 44.5 1.82 13.3%

6% 53.0 77.1 24.2 1.46 12.1%

9% 52.2 61.4 9.2 1.18 10.9%

13% 51.5 46.8 -4.6 0.91 9.4%

Only at a much higher discount factors of 13 percent, used at appraisal, the net economic

benefits turn negative (NPV of minus 4.6 million) and the EIRR drops to 9.4 percent

(below the discount rate used of 13 percent).

Page 53: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

37

Annex 4. Bank Lending and Implementation Support/Supervision Processes

(a) Task Team members

Names Title Unit Responsibility/

Specialty

Lending

Supervision/ICR

Sudipto Sarkar Lead Water Supply and Sanitation

Specialist GWADR TTL

Josses Mugabi Senior Water Supply and Sanitation

Specialist GWADR TTL

Martin Gambrill Lead Water Supply and Sanitation

Specialist GWASS TTL

Fook Chuan Eng Lead Water Supply and Sanitation

Specialist GWADR TTL

Arif Ahamed Senior Water Supply and Sanitation

Specialist GWADR Co-TTL

Nishtha Mehta Water and Sanitation Specialist GWADR Team Member

Burhanuddin Ahmed Consultant GED06

Sheikh Naveed Uddin

Ahmed Consultant

SASHN -

HIS

Md. Akhtaruzzaman Sr Institutional Dev. Spec. GWASS

Soma Ghosh Moulik Lead Water and Sanitation

Specialist GWADR Team Member

Shideh Hadian Senior Infrastructure Economist GWADR Team Member

Arvind Prasad Mantha Financial Management Specialist GGODR FM

Ishtiak Siddiqi Senior Procurement Specialst GGODR Procurement

Marghoob Bin Hussein Senior Procurement Specialist GGODR Procurement

Zafrul Islam Lead Procurement Specialist GGODR Procurement

Muhammed Riadul Islam Procurement Analyst CMEAS Procurement

Dr. M. Khaliquzzaman Local Consultant ST GEN06 Environmental

Safeguards

Tarak Sarker Program Assistant SACBD Team Member

Abu Ahmed Mansoor Kabir Program Assistant GWASS Team Member

Md Abul Fayez Khan Program Assistant EDS12 Team Member

Lilian MacArthur Program Assistant GSURR Team Member

Abdul Motaleb Sr Water & Sanitation Spec. GWASS Team Member

Fabio Pittaluga Senior Social Development Spec GSURR Social Safeguards

Prakash Raghunath Sanglikar Local Consultant ST GWA06 Technical

Consultant

Shyamal Sarkar Consultant GWA06 Technical

Consultant

Chau-Ching Shen Senior Finance Officer WFALN Finance

Kishor Uprety Senior Counsel LEGAM Lawyer

Page 54: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

38

(b) Staff Time and Cost

Stage of Project Cycle

Staff Time and Cost (Bank Budget Only)

No. of staff weeks USD Thousands (including

travel and consultant costs)

Lending

FY05 8.86 3.51

FY06 56.62 109.22

FY07 62.33 198.03

FY08 103.87 403.19

Total: 231.68 713.95

Supervision/ICR

FY05 0.00

FY06 -0.33

FY07 0.00

FY08 0.00

FY09 48.85 162.24

FY10 31.91 115.24

FY11 28.65 130.91

FY12 42.46 205.91

FY13 52.32 233.10

FY14 39.45 172.28

FY15 59.14 252.47

FY16 37.39 239.56

Total: 340.17 1,511.38

Page 55: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

39

Annex 5: Summary of Borrower's ICR and/or Comments on Draft ICR

1.1 Context at appraisal

Dhaka is the primary urban center in Bangladesh. Dhaka’s population is estimated at

around 12 million, comprising about one third of Bangladesh’s urban population. It is by

far the largest urban center in Bangladesh. In contrast, the second largest city in

Bangladesh, Chittagong, has a population of about four million. The preeminence of

Dhaka as the overwhelmingly largest urban center in Bangladesh is both a source of

concern and opportunity. The city provides livelihood options for millions of migrants

that come from rural areas in search of better opportunities to improve their living

standards. Dhaka is growing rapidly. Between 2000 and 2005, the city grew at an average

rate of 4.4% per year. It is estimated to be one of the fastest growing mega city in the

world.

WSS service provision unable to meet demand growth. Much of the growth in the city

has been from migration of the rural population. Other contributing factors include

natural growth of population and expansion of new areas to the existing city limits.

Dhaka attracts private sector investments in manufacturing, commerce and construction

due to availability of labor pool and better quality of supporting infrastructure services.

Extensive investment in the past in urban infrastructure in Dhaka further influenced the

growth of industrial and commercial activities. However, the extraordinary growth in

Dhaka’s population puts pressure on utility service providers to meet the needs of its

population.

DWASA is the sole authority for water and sewerage service provision. Dhaka Water

Supply and Sewerage Authority (DWASA) manages about 3462 kilometers of water

distribution network and 916 kilometers of sewerage networks. DWASA is responsible

for about 350,772 water and about 59,366 sewerage connections. It is estimated that only

about 20% of the Dhaka City Corporation (DCC) area is covered by the sewerage

network (DWASA, Annual Report 2014-15).

DWASA lacks autonomy in practice. In practice DWASA’s autonomy is significantly

constrained. While the WASA Act (1996) provides for a multi-stakeholder Board of

Directors structure, the GOB retains the sole responsibility for the appointment of the

Board. There are no established rules or procedures for the appointment of the Board of

Directors providing for the systematic input of other stakeholders in this process. The Act

provides for GOB approval and involvement when the GOB provides financing or

guarantees to DWASA - which is the case in DWASA operations, particularly in

infrastructure development activities. Recently, implementing rules and regulations of the

WASA Act (1996) have been approved. Of the five Rules and Regulations, two have

been published in the National Gazette while three are pending final GOB approval. This

is expected to increase the functional autonomy of DWASA.

DWASA is responsible to provide WSS service to slums. The Dhaka Water Supply

Policy (2005) confirms DWASA’s mandate to extend basic water supply and sanitation

services to slums within its service area, to provide legal connections, and to introduce

formal billing and collections. Through this guideline, the GOB commits to 100% water

supply coverage to the urban poor of all slums. Nevertheless, DWASA faces an

Page 56: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

40

enormous implementation challenge to ensure that all sections of the society, including

the urban poor, can access water and sanitation services.

DWASA is unable to provide adequate sewerage services. Dhaka’s sewerage system has

deteriorated particularly due to the damage caused by the 2004 floods, which devastated

the functioning of the sewerage network of the city. The primary, secondary and tertiary

lines are partly or fully damaged, and the damage to the trunk sewer main to the Pagla

Sewerage Treatment Plant (PSTP) from the 2004 floods has contributed to the 50%

reduction in capacity utilization of the plant. Additionally, new treatment plants would

need to be constructed to expand the sewerage coverage for newly occupied areas

throughout the city.

Deteriorated sewerage systems adversely affect water quality. The pressure on Dhaka’s

sewerage system has sewerage system exacerbates the poor and deteriorating condition of

the water quality of the surrounding water bodies. Indiscriminate dumping of industrial

effluents, solid wastes and untreated sewage into the Buriganga, Balu, Turag and

Shitalakhya rivers continue to strain an already overburdened sewerage network and

treatment capacity. Though several agencies - Department of Environment, Institute of

Water Modeling (IWM) and Water Resources Planning Organization (WARPO) -

regularly monitor raw water quality, the lack of enforcement of acts, policies and

guidelines have aggravated the pollution in these water bodies. Water quality parameters

of Dissolved Oxygen (DO), Biological Oxygen Demand (BOD), and Chemical Oxygen

Demand (COD) exceed the permissible limits, particularly during the dry season between

January and April, making water unusable for any domestic purposes and for treatment

by the Saidabad Water Treatment Plant. The GOB has taken the initiative for surface

water management on a priority basis.

DWASA has also been given the mandate for major storm water drainage. The

responsibility for storm water drainage in Dhaka was transferred from the Dhaka City

Corporation (DCC) to DWASA in 1989 through an LGD circular and subsequently

included in the WASA Act (1996). Under this arrangement, the operations and

maintenance of 43 Khals (canals) and two associated drainage pumping stations

(Kalyanpur and Dholaikhal) came under the responsibility of DWASA. This comprises

about 350 km of the city’s storm water drainage system, which covers about 38% of the

DCC area, to drain out the flood water through natural canals into the adjoining rivers. It

should be noted that there are no separate provision for DWASA to be remunerated for

the cost of storm water drainage operations.

Inadequate storm water drainage poses significant costs to the city. Currently only 26

khals (canals) out of the former 43 canals are recognizable in Dhaka city, as the

remaining khals have been partially filled in. Illegal encroachment and its associated

problems such as maintenance difficulties and khal clogging is a significant issue in

major khals. Moreover, the functioning of the storm sewer system is hindered by

sedimentation in the storm water inlets caused by road carpeting materials and

construction materials. Improper maintenance of the inlets of storm sewers aggravates the

scale of the problem. These problems have resulted in continued frequent water logging

in the city during the monsoon seasons. During the 2004 floods, it was estimated that

approximately US$6.3 million of losses per day were sustained by businesses and

residents during the 30 days when the city was incapacitated by flooding.

Page 57: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

41

Solid Waste Management in Dhaka. While DWASA is partly responsible for the storm

water drainage systems in Dhaka, solid waste management in Dhaka remains the

responsibility of the Dhaka City Corporation (DCC). Inefficient solid waste management

in Dhaka adversely affects DWASA’s operations of the storm water drainage,

particularly in slum areas where solid and other wastes are frequently thrown into the

canals.

1.2 Rationale for Bank involvement

The Primacy of Dhaka City and Dhaka’s Investment Needs. Dhaka is the preeminent

urban center of Bangladesh supporting the livelihood of about 12 million people. It has

historically attracted and is presently attracting large numbers of migrant workers from

the rural areas of Bangladesh. This trend has contributed largely to Dhaka being

estimated as one of the fastest growing megacity in the world. The recent population

growth of about 4.4% per year is projected to continue, with the population projected to

increase to about 21.6 million by 2025. Dhaka is the main commercial hub of Bangladesh

and contributes more than 20% of Bangladesh’s GDP (estimated at about US$61 billion

in current terms in 2006). The investment needs to provide services to Dhaka’s

population are significant.

1.3 Implementation Strategy

The project sponsored interventions were expected to bring about public health and

environmental benefits, by improving delivery and quality of DWASA services

1.4 Project Development Objective (PDO) and Key Indicators:

The Original Project Development Objective was to “improve the sustainable delivery of

storm water drainage, waste water and water services by DWASA to the population of

Dhaka City through: (i) the installation of selected storm water pumping station and the

rehabilitation of selected canals to help improve drainage and minimize urban flooding;

(ii) the rehabilitation , repair and expansion of priority investments in the city’s sewerage

network and treatment plant to help improve the urban environment; (iii) supporting

DWASA’s pilot expansion of water and sanitation services into selected Dhaka slums to

help increase services to the urban poor”. The key outcome indicators of the development

objectives are the following:

(i) Water level and number of days of water logging in the eastern part of Dhaka

(ii) Number of households with access to sewerage services

(iii) Increase in number of people in project area ward slums with access

1.5 Revised PDO

The project was restructured mid-June 2013 and the PDO also changed. The original

project was declared effective on March 17, 2009 but implementation suffered due to

slow disbursement. It was only 10.5 percent in four years, the closing date of the project

being on 30 June 2013. The project suffered the consequences of delays resulting from

issues related to its initial readiness and design (at appraisal, no detailed engineering

designs were ready, the consultancy assignments to prepare the detailed interventions had

not been procured, the LIC component had not been clearly conceived), start up delays

and problems with the procurement of key consultancies and civil works. Significant

delays occurred regarding (i) procurement of the sewage master plan consultancy, which

Page 58: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

42

included identification, detailed design, preparation of bidding documents for priority

sewerage and wastewater treatment works (ii) the adoption of a complicated two-stage

bidding process for the two large storm water pumping stations, (iii) procurement of

consultancy services to prepare the drainage master plan, and (iv) the initial design of the

LIC component. As a result following changes (restructure) in the project components

were made: (i) reducing the scope of activities under the sewerage and the LIC

component (component 1 and 4), (ii) incorporating additional DWASA institutional

strengthening activities into the project management component, (iii) cancelling

US$65.34 million of the original IDA credit, (iv) extending the closing date and (v)

amending the PDO and results framework to correspond with the revised project scope

and extended project implementation period.

The revised PDO was stated as “to improve storm water drainage in Dhaka and to

improve DWASA’s capacity for investment planning and operations”. To reflect the

above changes in the PDO the results framework and its indicators were also adjusted as

mentioned below.

(i) Number of direct project beneficiaries and percentage of female population;

(ii) Increase in permanent storm water pumping capacity

(iii) A new drainage master plan for Dhaka city is approved by DWASA’s Board of

Directors;

(iv) A new sewerage master plan for Dhaka city is approved by DWASA’s Board of

Directors;

(v) A new decentralized zonal management structure and action plan for the

implementation are approved by DWASA’s Board of Directors.

1.6 Main Beneficiaries

The primary target group was the local communities and in particular the poor and

vulnerable groups in the eastern part of Dhaka city. Total beneficiaries of two pump

houses and 13 rehabilitated canals are estimated at 3.6 million. This estimate is based on

the assumption of the catchment area of these infrastructure estimated at 105.28 km2

with

a density of population of 34,700/km2.

1.7 Status of Implementation Performance

The project has made good progress on all components.

Achievements and Progress update

(i) Component 1: Achievement and progress made by the close of implementation

period include (i) Dhaka Waste Water Management Master Plan has been approved

by DWASA’s Board; (ii) the priority sewerage and Sewerage Treatment Plant (STP)

designs identified in the Master Plan have been completed, and the corresponding

bidding documents were finalized;(iii) detailed engineering designs and bidding

documents for sewerage investments in the Uttara and Mirpur catchments were also

completed.

(ii) Component 2: The drainage master plan has been completed, finalized and

disseminated to key stakeholders. The final master plan was approved by DWASA’s

Page 59: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

43

Board by project closing. The canal rehabilitation works have been completed; the

Rampura pumping station has been completed and commissioned. The contractor

has carried out the required refurbishment of all the sluice gates which were

subsequently tested by technical experts from the Bangladesh University of

Engineering Technology (BUET). There was no barrier to issue Operational

Acceptance Certificate (OAC) by DWASA for Rampura pump station.

The delay in completion of the Kamalapur pumping station has led to the risk of

project closure with unfinished works. The delays in works implementation was due

to delays in import of pipe jacking instruments, slow progress in works

implementation with limited labor force, breakdown of major jacking equipment as

well as required repair. However, the contractor successfully installed four discharge

pipe sections underneath a busy road through pipe jacking method and completed all

ancillary works by project closure.

(iii)Component 3: Support to the Implementation of Environment and Social

Safeguards:

Environmental Safeguards: Work on all the sub‐projects (i.e.13 canals and two

pumping stations) have been completed. The implementation of Environmental

Management Plan (EMP) in the sub‐projects did reasonably well. Some violations

were observed in the implementation of EHS provisions such as non‐universal use

of PPE by the workers, missing safety signs and barriers, and piling up of

construction debris.

Social Safeguards: Social safeguard issues under DWSSP were concerned with the

impacts resulted from displacement of people during recovery, re‐excavation and

other improvements implemented on 9 drainage canals. During preparation of

DWSSP, DWASA carried out Social Impact Assessment (SIA), including extensive

community/stakeholder consultations for the individual canals. In view of the

potential impacts as found in the SIA, DWASA prepared a Resettlement Policy

Framework (RPF) in April 2006 in accord with the principles and guidelines

provided in the Bank’s OP 4.12 on Involuntary Resettlement. The RPF, which was

cleared by the Bank, provided the necessary bases to prepare Resettlement Action

Plans (RAPs) for individual and/or batches of canals that were selected for

improvement. There was no need for private land acquisition. But the improvements

on the 9 canals, as a whole, affected 187 persons/households, of which 67 were

encroachers who owned land adjacent to the canals. Impacts on the encroachers were

negligible and, according to the RPF they were ineligible for any resettlement

assistance.

(iv) Component 4: Support to Service Provision to Low Income Communities (LIC).

The original design of this component and the implementation approach envisaged

presented practical challenges which necessitated a reevaluation and change in scope.

The required planning and design to address these challenges demanded more time

and as a result service provision activities to LICs were dropped from the

restructured project and the associated cost, estimated at US$ 6.47 million, was

canceled from the IDA Credit. The name of this component was changed to Support

to Service Improvement Planning in Low‐Income Communities (Original

Page 60: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

44

component name: Support to Service Provision to Low Income Communities;

original IDA US$ 8.4 million; cancellation US$ 6.47 million; new IDA total US$ 1.5

million). The down‐sized component included preparations of a Service

Improvement Plan for LICs. However, the study to prepare a Service Improvement

Plan for low‐income customers has been completed using Water and Sanitation

Program (WSP) funds. DWASA also continued to strengthen its existing

Nongovernment Organization (NGO) partnerships to serve the poor through

implementation of small value works in selected LICs. As a result of these

partnerships, approximately 12,500 households across six LIC areas have access to

legal water supply provided by DWASA through the project. Works for installation

of deep tube wells at selected LIC locations to supplement water supply to these

communities was also completed by project closure including completion of pump

house, installation of electric sub‐station, electricity connection and delivery line

installation.

(v) Component 5: Project Management, Monitoring and Evaluation (M&E),

Consultations and Communications. A study to prepare an organizational

restructuring plan was undertaken using WSP funds and was completed. The repair

and refurbishment work for three zonal offices and the existing training center

completed and renovation work for three additional zonal offices was also completed.

DWASA completed preparations of the design and bid documents for a modern

training center. DWASA has completed procurement of computers and database

licenses. Unfortunately, the contracts of other key items to improve the utility’s

information and communication technology infrastructure namely servers and

storage systems as well as video‐conferencing services could not be fulfilled due to

lack of project funds. These contracts were cancelled before the project closing date.

1.8 Key Challenges

The major difficulty encountered in the implementation of the canal excavation was to

make part of these canals free from encroachers, and removal of excavated solid waste,

political conflict and resultant law and order situation. Delay of handing over of land by

the Bangladesh Railway for the construction of Kamalapur Pump house also hampered

the progress of the project implementation.

2 Key Factors Affecting Implementation and Outcomes

2.1 Project Preparation, Design and Quality at Entry

Use of Lessons in Project Design. The main lesson incorporated is the introduction of

decentralized service delivery approach, including community demand driven approach

with partial capital cost recovery and 100 percent O&M financing by the users that

unveiled the major shift from adopting a supply driven mode to a more demand driven

and decentralized service delivery approach.

Focus on Institutional Changes. The project objectives – especially after restructuring -

focused on the institutional strengthening that was needed to implement the project. The

project components represented a balance of institutional support, capacity building and

infrastructure development.

Government Commitment and Risks: GOB’s commitment and ownership to the

Page 61: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

45

reform agenda remained firm throughout project implementation. The project design had

identified all the possible risks, which were “High”. Despite all measures proposed, the

actual implementation experienced problems and risks.

2.2 Implementation

Implementation was moderately satisfactory throughout the course of the project. The

PAD physical targets were not only fully achieved at the extended closing date of June

2016 and good progress was made on all components.

2.3 Monitoring & Evaluation

The project was successful in institutionalizing the mechanism of information processing

and data analysis on MIS system developed by DWSSP. M&E capacity has been

developed during the project within DWASA.

2.4 Safeguard & Fiduciary Compliance

Social Safeguards: No lands were acquired involuntarily. Social safeguard issues under

DWSSP were concerned with the impacts resulted from displacement of people during

recovery, re‐excavation and other improvements implemented on the drainage canals.

During preparation of DWSSP, DWASA carried out Social Impact Assessment (SIA),

including extensive community/stakeholder consultations for the individual canals. In

view of the potential impacts as found in the SIA, DWASA prepared a Resettlement

Policy Framework (RPF) in April 2006 which provided the necessary bases to prepare

Resettlement Action Plans (RAPs) for individual and/or batches of canals that were

selected for improvement.

Environmental Safeguards: The implementation of Environmental Management Plan

(EMP) in the sub‐projects were done reasonably well. Some violations were observed in

the implementation of EHS provisions such as non‐universal use of PPE by the workers,

missing safety signs and barriers, and piling up of construction debris.

2.5 Fiduciary Management: Fiduciary compliance was satisfactory throughout

implementation. Fund flow and expenditures monitoring were adequate. Financial

management reports were prepared in a timely manner throughout project

implementation.

2.6 Procurement: Procurement was carried out in accordance with the agreed procedures.

Delays in decision making took plays due capacity constraints of the PMU officials.

2.7 Post-completion Operation/Next Phase

The post completion operation is adequately addressed: Project design was adequate in

ensuring sustainability on all fronts: technical, financial and institutional. All the

infrastructure assets (pumping stations, canals, LIC water connections) have been

completed and commissioned and are being operated and maintained by DWASA.

Project’s sustainability prospects are good: Overall performance of DWASA in managing

the drainage, water and sanitation facilities has been excellent. The capacities created

under the project will continue to be available for the sector. GOB has now got a

commitment of World Bank to develop a new project for continued support.

Page 62: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

46

3.1 Relevance of Objectives, Design and Implementation

The project objectives remain highly relevant to current Government priorities. The

sector development framework aimed for total urban sanitation services throughout

Bangladesh by 2015. The Bangladesh Millennium Development Goals (MDGs) envisage

100% coverage for access to safe drinking water in urban areas by 2015, and 86% access

to improved sanitation in urban areas by 2010. The scale and timeframe of the sector

development framework targets are slightly more ambitious than the MDGs. These

various sector targets

Represent a huge challenge to the Government of Bangladesh (GOB). In addition, the

GOB targets to provide access to higher quality piped water supply to 70% of urban areas

by 2010 and 90% by 2015. These targets now are included in Sustainable Development

Goals (SDGs).

3.2 Achievement of Project Development Objectives the revised Project Development

Objective (PDO) was “to improve storm water drainage in Dhaka city and to improve

DWASA’s capacity for investment planning and operations”.

The project has achieved this PDO as all the result indicators recorded good

achievements. Key important result indicator of 20,885 m of storm water canals

constructed/rehabilitated has been fully achieved by re-excavating 13 canals. The

indicator target to increase discharge capacity of the rehabilitated 13 canals to 250m3/s

has been achieved. The indicator target to achieve 40 m3/s permanent storm water

drainage capacity has been fully achieved. The indicator target of a sewerage master plan

and drainage master plan approved by the Board have been fully achieved.

3.3 Achievement of Project Impact

The initial impact of the Kamalapur pump house in the catchment area was not visible to

the intended beneficiaries as it was not operational when beneficiaries were interviewed

in October 2015. In fact the incidence of water logging during the last monsoon got

worse due to heavy rainfall and the results of the beneficiary interviews can provide a

good baseline data for any drainage development impact analysis in future. Data on the

depth and duration of water logging in Kamalapur is consistent with the above statement.

Rampura catchment area presented a different picture as the operations of the Rampura

pump house continued throughout the monsoon and completion of the Mohakhali canal

rehabilitation activities resulted in positive impacts by reducing duration, depth and

extent of water logging in the catchment area. Loss of school days, loss of livelihoods

and traffic congestion were also reduced quite substantially.

4.1 Lessons learnt

(i) PMU staff should not only have commitment but they should have good

management skills, fully knowledgeable and be computer literate. If possible they

should be given training in areas which affects the progress of project

implementation.

(ii) Loan should be made effective only when the initial readiness of the Executing

Agency is fully complied with.

Page 63: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

47

(iii)The procurement process, including all the required steps and timeline, should have

been identified and needs to be considered in the total project work plan.

(iv) For small civil works such as canal rehabilitation, large packaging in case of local

tendering is not optimal and desirable. It has been observed that limited number of

capable local contractors is available to undertake large works in canals.

(v) Procurement packages of civil works should be considerably larger to avoid

engagement of insolvent and inefficient vendors.

(vi) Proposal evaluation should be thoroughly reviewed with set criteria to get a good

understanding of the strength of vendor to carry out the assignment.

(vii) PMU should have its own accounting section to improve financial management.

PMU should also have dedicated M&E section/focal point.

(viii) Procurement process needs to be decided based on the nature of works in

particular considering the complexity of the works involved, including veracity of

alternative technologies.

(ix) Communities should be made aware and involve in the maintenance work of canals

for sustainability of investment through engagement of NGOs.

(x) Communities should be regularly briefed about the project output and the expected

impact

(xi) PMU Coordination with Zonal Offices is a pre-requisite for expanding service

delivery to LICs since zonal offices are responsible for final delivery of services.

(xii) Understanding of existing legislative provisions in service provision is key e.g.

on‐site sanitation is not DWASA’s mandate which is also not covered under WASA

Act

4.2 Looking forward

Since the project has achieved its goals, Government ensure to consolidate on the gains

by formulating a follow on project proposal which targets to sanitation sector

improvement issues.

Page 64: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

48

Annex 6. Comments of Co-Financers and Other Partner Stakeholders

Not Applicable

Page 65: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

49

Annex 7. List of Supporting Documents

Project Appraisal Document for Bangladesh: Dhaka Water Supply and Sanitation Project,

dated October 31, 2008 (Report No: 44935-BD

Restructuring Paper for Bangladesh: Dhaka Water Supply and Sanitation Project, dated

June 13, 2013 (Report No: 78117-BD)

Aide Memoires, Implementation Status Reports

Project Progress Reports by Dhaka Water Supply and Sanitation Project – PMU

Borrower’s Evaluation Report, dated November 2016

IWM (2016) Flood Modeling of Dhaka City – Part 2 Impact and Resilience of Storm

Water Drainage Investments of Dhaka Water Supply and Sanitation Project (DWSSP)

Roy, S. (2016) The Impact of Storm Water Drainage Investments by DWASA in Greater

Dhaka Area – Estimation of Potential Damages Component and Economic Analysis

Dasgupta, Susmita; Zaman, Asif; Roy, Subhendu; Huq, Mainul; Jahan, Sarwar; Nishat,

Ainun. (2015). Urban Flooding of Greater Dhaka in a Changing Climate : Building

Local Resilience to Disaster Risk. Directions in Development--Environment and

Sustainable Development; Washington, DC: World Bank.

DWASA (2014) Sewerage Master Plan for Dhaka City

DWASA (2015) Low Income Customers Improvement Plan

DWASA (2015) Drainage Impact Assessment Exercise - Report on Focus Groups

Discussion conducted in Two Catchment Areas of Dhaka

DWASA (2016) Storm Water Drainage Master Plan for Dhaka City

Castalia (2015) Diagnostic Report of the organizational Structure of DWASA; and

Options Report of the Organizational Structure of DWASA

World Bank (2016) Strengthening Poor-Inclusive Urban Water Supply and Sanitation

Service Quality Information Systems in Bangladesh (P131951)

World Bank (2016) Country Partnership Framework for Bangladesh for the period FY16-

FY20. Report No. 103723-BD

World Bank (2015) Systematic Country Diagnostics for Bangladesh. More and better

Jobs to Accelerate Shared Growth and End Extreme Poverty

World Bank (2015b). Climate and disaster resilience of greater Dhaka area: a micro level

analysis. Bangladesh development series; paper no. 32. Washington, D.C. World Bank

Group.

World Bank (2011) Country Assistance Strategy for Bangladesh 2011-2014.

World Bank (2006) Country Assistance Strategy for Bangladesh 2006-2009. Report No.

35193

World Bank (2006) Bangladesh Country Assistance Strategy (2001-2005) Completion

Page 66: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

50

Review. Independent Evaluation Group. Report No. 89106

Government of Bangladesh (2011) Perspective Plan 2010-2021 Making Vision 2021 a

Reality. Economic planning Commission

Government of Bangladesh (2015) The Seventh Five Year Plan FY16-FY20.

Accelerating Growth, Empowering Citizens. Economic Planning Commission

Page 67: World Bank Documentdocuments.worldbank.org/curated/en/319831484319690176/... · 2016-12-21 · document of the world bank report no: icr00003616 implementation completion and results

51

MAP