April to June 2017 Details are subject to change. Current as at 17 May 2017. SOUTHERN UPPER CAR PARK TRANSIT HUB SCARBOROUGH SQUARE NORTHERN LOWER CAR PARK Works continue until August 2017. Paving commences mid-May 2017 (Sandbar to Cold Rock). Road reopens early July 2017. Minor traffic shift (contraflow) on roundabout late May 2017. Relocation of clock tower in June 2017. Includes new entry to lower carpark near Manning Street. Work area moves further north from early June 2017. 1 2 3 4 1 2 3 4 T: 1800 639 726 W: visitscarborough.com.au WORKS PROGRAM 13 SCARBOROUGH BEACH POOL Works continue until early 2018 13

WORKS PROGRAM - Seashells Hospitality Group · 2017-06-02 · WORKS PROGRAM 7 NORTHERN ESPLANADE SHOPFRONTS Road, paving and landscaping works. Road closure in place until November

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: WORKS PROGRAM - Seashells Hospitality Group · 2017-06-02 · WORKS PROGRAM 7 NORTHERN ESPLANADE SHOPFRONTS Road, paving and landscaping works. Road closure in place until November

April to June 2017Details are subject to change.Current as at 17 May 2017.

SOUTHERN UPPER CAR PARK

TRANSIT HUB

SCARBOROUGH SQUARE

NORTHERN LOWER CAR PARK

Works continue until August 2017.

Paving commences mid-May 2017 (Sandbar to Cold Rock). Road reopens early July 2017.

Minor traffic shift (contraflow) on roundabout late May 2017. Relocation of clock tower in June 2017.

Includes new entry to lower carpark near Manning Street. Work area moves further north from early June 2017.

1

2

3

4

1

2

3

4

T: 1800 639 726 W: visitscarborough.com.au

WORKS PROGRAM

13

SCARBOROUGH BEACH POOL

Works continue until early 2018

13

Page 2: WORKS PROGRAM - Seashells Hospitality Group · 2017-06-02 · WORKS PROGRAM 7 NORTHERN ESPLANADE SHOPFRONTS Road, paving and landscaping works. Road closure in place until November

UPPER SOUTHERN CARPARK THE ESPLANADE SHOPFRONTS

THE ESPLANADE SHOPFRONTS LOWER SOUTHERN CAR PARK

INTERGENERATIONAL PLAZA SCARBOROUGH BEACH POOL

NORTHERN LOWER CAR PARK

Includes new beach access. Works ongoing until October 2017.

Road closure

Works move to northern section. Carpark access via new entry.

Commence foundation works for skate park.

Works continue until early 2018Paving works Sandbar - Coles. New traffic arrangement until September 2017.

Paving works Cold Rock - Matisse.New traffic arrangement.

1 5

6 8

7 13

4

4

July to August 2017

56

7

WORKS PROGRAM

1 8

Works ongoing until August 2017. Open for access to residential buildings, no parking during this time.

T: 1800 639 726 W: visitscarborough.com.au

Details are subject to change.Current as at 17 May 2017.

13

Page 3: WORKS PROGRAM - Seashells Hospitality Group · 2017-06-02 · WORKS PROGRAM 7 NORTHERN ESPLANADE SHOPFRONTS Road, paving and landscaping works. Road closure in place until November

September 2017

WORKS PROGRAM

Details are subject to change.Current as at 17 May 2017.

Landscaping and road upgrades.Temporary road diversion in place.

7

6

8

9

5

T: 1800 639 726 W: visitscarborough.com.au

Road closure

13

THE ESPLANADE SHOPFRONTS

THE ESPLANADE SHOPFRONTS

INTERGENERATIONAL PLAZA THE ESPLANADE SOUTH

LOWER SOUTHERN CAR PARK

Paving works Sandbar - Coles. New traffic arrangement until September.

Paving works Cold Rock - MatisseNew traffic arrangement.

Works for skate park, basketball court and climbing wall continue.

Includes new beach access. Works ongoing until October 2017.

5

6

7 9

8 SCARBOROUGH BEACH POOL

Works continue until early 2018

13

Page 4: WORKS PROGRAM - Seashells Hospitality Group · 2017-06-02 · WORKS PROGRAM 7 NORTHERN ESPLANADE SHOPFRONTS Road, paving and landscaping works. Road closure in place until November

WORKS PROGRAM

7

NORTHERN ESPLANADE SHOPFRONTS

Road, paving and landscaping works. Road closure in place until November 2017.

10

9

PLAYGROUND

Commence playground installation and landscaping.

11

11

T: 1800 639 726 W: visitscarborough.com.au

810

13

Landscaping and road upgrades.Temporary road diversion in place until December 2017.

INTERGENERATIONAL PLAZA THE ESPLANADE SOUTH

LOWER SOUTHERN CAR PARK

Works for skate park, basketball court and climbing wall continue.

Includes new beach access. Works ongoing until October 2017.

7 9

8 SCARBOROUGH BEACH POOL

Works continue until early 2018

13

September to November 2017Details are subject to change.Current as at 17 May 2017.

Page 5: WORKS PROGRAM - Seashells Hospitality Group · 2017-06-02 · WORKS PROGRAM 7 NORTHERN ESPLANADE SHOPFRONTS Road, paving and landscaping works. Road closure in place until November

December 2017

WORKS PROGRAM

Details are subject to change.Current as at 17 May 2017.

7

11

9

1

T: 1800 639 726 W: visitscarborough.com.au

13

SOUTHERN CAR PARK

INTERGENERATIONAL PLAZA

THE ESPLANADE SOUTH

PLAYGROUND

Lower carpark and beach access open. Upper carpark southern end closed until February 2018.

Works for skate park, basketball court and climbing wall continue.

Works continue on playground installation and landscaping.

1

2

9

11

SCARBOROUGH BEACH POOL

Works continue until early 2018

13

Landscaping and road upgrades.Temporary road diversion in place until December 2017.

Page 6: WORKS PROGRAM - Seashells Hospitality Group · 2017-06-02 · WORKS PROGRAM 7 NORTHERN ESPLANADE SHOPFRONTS Road, paving and landscaping works. Road closure in place until November

December 2017 to early 2018

WORKS PROGRAM

Details are subject to change.Current as at 17 May 2017.

1

7

11

12

T: 1800 639 726 W: visitscarborough.com.au

13

SOUTHERN CAR PARK

INTERGENERATIONAL PLAZA

PLAYGROUND

NORTHERN UPPER CAR PARK

Lower carpark and beach access open. Upper carpark southern end closed until February 2018.

Works for skate park, basketball court and climbing wall continue.

Upgrade works.

1

2

9

12

SCARBOROUGH BEACH POOL

Works continue until early 2018

13

Works continue on playground installation and landscaping.