Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
WORKS AND SERVICES COMMITTEE MEETING HELD ON WEDNESDAY 17 FEBRUARY 2016 AT MEMORIAL HALL SUPPER
ROOM, ESPLANADE, KAIKOURA.
AGENDA
1. Apologies 2. Matters of Importance to be raised as Urgent Business. 3. Reports:
Operations and Maintenance Manager’s Report page 1
Budget Report page 6 4. Footpath Report page 7 5. VDAM Report page 19 6. Minutes Action and Issues List Update
MEETING ACTION REQUIRED BY ACTION Works & Services
Arrange for a representative of NZTA to meet with Council regarding further plans for State Highway 1 through Kaikoura.
Operations Manager
A meeting has been scheduled.
Works & Services
Include a report on incorporating a cycle lane on the footpath on Beach Road in the footpath report.
Operations Manager
Refer footpath report.
7. Urgent Business
OPERATIONS AND MAINTENANCE MANAGER’S REPORT
1.0 WATER SUPPLY 1.1 Urban Water Operations – Kaikoura Urban Supply This facility operated satisfactorily during the reporting month. The second stage of works on the new water main on the end of South Bay Parade, Tui, Moa, Weka and Kaka Roads is commencing in late February. This will be installation of low voltage electrical cabling, streetlighting, water and telecommunication ducts as well as renewal of services on private property and the removal of the overhead reticulation. Approximately 50% of the properties have indicated that they wish to work with Council on renewing services within their properties. Expenditure to date is $117,000 out of a budget of $300,000. Additional minor works on repairs and replacement of old stormwater sumps and roading defects has occurred and been charged appropriately. Many houses on Kotuku Road and South Bay Parade have been identified as requiring an upgrade to their internal water reticulation. An additional authority to complete works inside properties is still being obtained. Significant Work planned for 2016 includes:
The further GNS test on Mackles Bore has been taken. Results will be back in the middle of 2016.
Install flowmeters on Mackles irrigation to comply with new consent conditions. Water Demand Table 1 below shows the water demand for the reporting month measured from the Mackle’s bore while Figure 1 shows the yearly cumulative water demand since 2009.
Water Demand (m3/day)
Min Avg Max Total Demand
July 2014 1629 2166 2681 67,158
August 2014 1791 2271 2989 70,415
September 2014 1686 2546 3374 76,395
October 2014 1686 2252 3582 88,708
November 2014 2246 3259 4670 97,780
December 2014 2403 3444 4556 106,765
January 2015 3169 4327 5296 134,124
February 2015 3325 4353 5185 121,886
March 2015 2808 3500 4493 108,502
April 2015 2398 3119 4321 93,557
May 2015 1691 2519 3088 78,095
June 2015 1997 2470 3217 74,096
July 2015 1917 2450 3033 73,507
August 2015 1779 2412 3783 74,766
September 2015 1565 2335 3040 70,064
October 2015 2291 2880 3783 89,275
November 2015 2383 3297 4454 98,921
December 2015 2797 3898 5050 120,827
January2016 2561 3596 4978 107,894 Table 1: Water Demand for reporting period
Figure 2: Cumulative Water Demand in cubic metres
The water usage for the month and for the year is similar to the previous year.
1.2 Suburban Water Supply The consent allowing irrigation from the Waimangarara Intake has been received from Environment Canterbury. Rain in the catchment on the 3rd of January caused high turbidity levels and a failed E.Coli count which resulted in a boil water notice being issued. 1.3 Kincaid Water Supply Work occurred at the intake to improve infiltration into the gallery. 1.4 Oaro Water Supply A transgression in the reticulation occurred on 12th January. This may have been due to external contamination of the sampling point as there were high numbers of campers in the vicinity. The
0
200000
400000
600000
800000
1000000
1200000
1400000
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
2009-10 2010-11 2011-12 2012-13 2013-14 2014-15 2015-16
riser from the bore is still to be replaced with stainless steel. Water restrictions were not issued as the supply has not shown signs of being overextended. 1.5 Fernleigh Water Supply There were no issues with this system during the reporting month. 1.6 Ocean Ridge Water Supply There were no issues with this system during the reporting month. 1.7 Peketa Water Supply There were no issues with this system during the reporting month. 1.8 East Coast Water Supply The supply has received an invoice of $23,182 for power from Meridian due to a reading of the meter. Previous accounts have been estimates. This is being discussed with Meridian. There were no issues with this system during the reporting month. Minor engineering works have been identified by Food and Health Standards that will improve the security of the supply.
2.0 SEWER SYSTEM
Sewage flows (m3/day)
avg Max* Total Flow**
July 2014 857 2500 26,571
August 2014 677 860 20,975
September 2014 668 1233 20,052
October 2014 775 1321 24,025
November 2014 888 1537 26,641
December 2014 986 1266 30,557
January 2015 1029 1318 31,901
February 2015 981 1183 27,478
March 2015 892 1025 27,662
April 2015 945 1284 28,361
May 2015 776 909 24,046
June 2015 764 986 22,934
July 2015 871 1442 26,120
August 2015 784 919 24,307
September 2015 954 2500 28,630
October 2015 738 1116 22,865
November 2015 821 992 24,621
December 2015 953 1240 29,558
January2016 1114 2020 33,418
Table 3 : Sewage generated for reporting period *The asterisk figure represents daily flows during heavy rainfall events. **The double asterisk figure has not been adjusted to reflect inflows from storm-water.
Figure 2: Cumulative Sewerage Discharge from Oxidation Ponds in cubic metres
The lids on the Hawthorne Road pump station are to be rebuilt to improve drainage and the seal to reduce odour. The fan at the Mill Road pump station is to be replaced. The bio-filter at the Gillings Lane pump station has been rebuilt. The odour problems now appear to be solved. A sewer spill occurred as a result of a blockage on the line from Westpac. This lateral needs to be investigated and in all probability replaced. The spill resulted in approximately 300 litres of effluent entering a stormwater sump and ending in Lyell Creek. One of the aerators at the treatment plant has failed as is to be reconditioned.
3.0 STORMWATER The consent for the Kaikoura Urban Area is still being processed by Environment Canterbury. Draft conditions have been proposed.
4.0 PARKS AND RESERVES The parks and reserves were maintained during the reporting month, some areas have been identified as requiring attention.
5.0 BUILDINGS Significant Work planned for 2016 include:
Replacement of existing main lights.
Purchase of scaffolding and fridge.
Unit 11 was vacated and is being refurbished
Unit 7 has requested that major work occur to reduce heat loss. This would include relining walls, insulating and replacing old steel frame windows. This will be reviewed for 2016/17.
0
100000
200000
300000
400000
500000
600000
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
2009-10 2010-11 2011-12 2012-13 2013-14 2014-15 2015-16
6.0 AIRPORT The levelled area has been mown and is still to be grassed.
7.0 SWIMMING POOL The new diesel tank for the pool heating system is now in operation.
8.0 PUBLIC TOILETS There were no issues with the toilets during the reporting month.
9.0 ROADING Significant work planned for 2016:
Kerb and Channel on Margate, Ramsgate and Torquay Streets scheduled to begin in late February.
Minor maintenance works have occurred on roads. HEB Contracting has made significant progress in development of the Contractor’s forward work programme for Kaikoura. At this point they have identified approximately $150,000 of sealed and unsealed carriageway repairs and maintenance. These are being issued to contractors in accordance with the maintenance contract. A meeting was held in Christchurch of the Regional Land Transport Committee. The opportunity was taken to reiterate the preference for work on projects looking at South Island Freight and the State Highway 1 Picton to Christchurch route to be timed so that projects could make the Regional Land Transport Programme. The new process which will lead to the next Regional Land Transport Programme for Canterbury is being led by Environment Canterbury. Kaikoura District will be endeavouring to maximum the projects to improve the roading network within Kaikoura.
10.0 FOOTPATHS Footpath programme and policy has been completed.
11.0 COASTAL As allowed by the Council’s resource consent the Council has taken 5,000 cubic metres of material from South Bay and placed it to provide protection to the Esplanade. A thin layer of topsoil has been placed and will be grassed in due course. Some maintenance on the rock protection at the eastern end has also occurred. As the consent expires in November 2016 no further work is intended until a long-term consent is obtained. Recommendation: That this report be received.
Prepared by Gerry Essenberg, Operations and Maintenance Manager
Authorised by Angela Oosthuizen, Chief Executive Officer
Works and Services Budget Report
47,789
0
20,044
126,724
2,122
0
3,926
106,675
63,949
81,238
0
2,907
81,000
0
758
3,720
63,331
20,322
Roading
Footpaths & Cycleways
Streetlights
Water Services
Sewerage
Stormwater
Refuse & Recycling
Community Facilities
Commercial Activities
Income MTD
Actual Budget
80,296
8,824
8,684
68,087
53,195
8,563
33,770
118,622
26,049
109,667
11,685
6,991
82,295
59,160
11,790
32,694
132,259
7,591
Roading
Footpaths & Cycleways
Streetlights
Water Services
Sewerage
Stormwater
Refuse & Recycling
Community Facilities
Commercial Activities
Expenses MTD
Actual Budget
Footpath Report
This report is for inclusion either as is or as modified to supersede the existing footpath section of the Roading Activity Management Plan.
ACTIVITY MANAGEMENT PLAN FOOTPATH SECTION
Asset Description
The purpose of footpaths, cycleways and walkways is to provide a safe, convenient and defined means for the movement of cyclists and pedestrians. Footpaths are constructed alongside roadways and as links between roadways and public spaces. Kaikoura has a growing network of cycle tracks in the rural area for recreation. Community groups manage and fund this network with occasional contributions from the Council. Key issues relating to footpaths include:
Appropriateness of design standards
Urban character and streetscape design
Footpath reinstatement (following excavation/development)
Footpath aesthetics (following replacement/maintenance) Most of the asset is solely funded by rates. The construction of footpaths for safety reasons and the maintenance of cycleways that remove cyclists from the roading network may be able to be subsidised under certain situations. There is approximately 36.76km of formed footpaths, cycleways and walkways in the Kaikoura District, with an approximate area of 65,500m2. The breakdown of the different footpath material used throughout the district is provided in Table 6.5.1. The stone pavilions are structures located in Ocean Ridge.
Type Length (m)
Chip Sealed 11,890
Concrete 9,563
Asphalt 4,244
Concrete Paver 362
Granite Paver 679
Limestone 3230
Metal 6002
Timber 775
Stone Pavilions 15
TOTAL 36,760
Table 6.5.1: Footpath Materials
Type Length (m)
Bridge 93
Cycleway 5,420
Footpath 27,203
Walkway 4,028
Pavilion 15
TOTAL 36,760
Footpaths are constructed to be a minimum of 1.4m in width to provide sufficient passing distance and disabled access. Several sections of footpath are the full width from the kerb and channel back to the boundary and would look better if they were narrowed and the remainder planted in grass with some trees. Parts of the overall roading network have been identified as being required to accommodate both pedestrians and cyclists. These sections of the network are the State Highway sections and roads that are Primary Collectors. Where there are footpaths designed for pedestrians they are informally used by cyclists. This situation generally arises because the cyclist feels safer on the footpath than on the road. In general this situation is neither encouraged nor discouraged however because it is not authorised the cyclist has an awareness that vehicles and pedestrians may affect their path.
Footpath Condition / Performance
The need for footpaths is dependent on the volume of pedestrian traffic. While most of the streets in urban areas have footpaths on both sides, there are some residential areas that only require a footpath on only one side and some urban streets have no footpaths at all. Rural roads seldom have formed footpaths.
There are no formal rules for assessing whether the current number of footpaths adequately serves the needs of each community. Generally the basis for requiring a footpath to be constructed has been established on a case by case basis, considering the specific pedestrian movements in the area and requests by members of the public.
A condition survey of urban footpaths was updated in 2015. This provided a rating assessment from 1 to 5 for each footpath section. The majority of footpaths were considered to be well formed and in an acceptable condition however feedback is showing that the standard for urban should be asphalt, pavers or concrete however metal or limestone is acceptable for walkways and cycleways.
Condition Rating Length (m)
As new 1 9,975
Good condition 2 9,142
Satisfactory condition 3 10,173
Should be in programme for renewal 4 5,835
Overdue for upgrade 5 1,635
TOTAL 36,760
An earlier Kaikoura Walking and Cycling Strategy was completed in February 2009.
Footpath and Cycleway Maintenance Plan
Footpaths require minimal maintenance throughout their useful life, beyond being kept clean. Those footpaths rated 3 require sweeping, pothole repairs and other minor works to restore the condition of the footpath. The granite pavers on West End are in good condition however their appearance has degraded significantly. A special cleaning process is required to remove the grime and then they will need to be sealed. Council manages all footpaths in the district including SH1 (Churchill Street, Beach Road). The Road Maintenance Management Contract includes the requirement to control vegetation including spraying of the footpaths. Other minor footpath maintenance and renewals are carried out under the terms of the contract by the road maintenance contractor. The major safety concern that relates to maintenance is the removal of tripping hazards. On chip sealed and asphalt paths these tripping hazards can develop if potholes appear. This problem typically only arises in the last 50% of the footpath’s life and is repaired by filling the pothole. Emergency/reactive maintenance arises when vehicles cause damage to footpaths creating a safety risk. Cycleways require regular maintenance to prevent encroachment of weeds and also to replace the surface material. The cycleways run parallel to State Highway 1 from Ocean Ridge to the north end of town and maintenance on this is partly subsidisable. To date those footpaths identified as Grade 3 suffer from deferred renewal. Once the work has been completed to sweep and patch them a cost estimated at $20,000 per year should be sufficient to maintain them in a condition until the rate of deterioration, or the requirement for renewal due to other works requires their replacement.
Footpath and Cycleway Renewal Plan
Following the 2005 footpath upgrades it was not intended to carry out further footpath renewals in the foreseeable future. Now there are significant areas of the chip sealed footpaths rated 4 and 5 which require attention. A renewal programme is generally on an as required basis which occurs when other works occur which will damage the footpath or the rate of deterioration is such that it is more economical to replace the footpath. Whether funding is from loans or depreciation needs to be confirmed. The cost of a new footpath is approximately $240 per metre with little difference whether it is a replacement or new, concrete or asphalt. The cost is based on asphalt footpath constructed in 2015.
Type Length Programme Unsubsidised
Footpath Renewal Programme 7,544m 2016/40 $1,100,000
TOTAL 7,544m 2016/40 $1,100,000
Footpath and Cycleway Upgrade Plan
The following factors are considered when assessing the relative need for additional footpaths:
Whether the street has an existing footpath
Options available for pedestrian traffic
Pedestrian generators
Road hierarchy
Pedestrian safety
Traffic speed (adjoining road)
To cater for the increase in pedestrians, particularly tourists, several improvements and extensions of walking tracks and footpaths are possible around the Kaikoura Township. The following significant extensions to the network are available:
Fyffe Quay / Wakatu Quay - Footpath / Walkway from New Wharf to Fyffe Quay to link the footpaths and walkways extending to Point Keen.
Footpath Killarney Street Annie Boyd to Torquay
Footpath Killarney Street Annie Boyd to Scarborough
Ludstone Road Rorrisons to Grays.
Ludstone Road Kiwi to Davidson north side.
Walkway/Cycleway along Lyell Creek State Highway 1 to Hawthorne and Rorrisons
Walkway/Cycleway along Scarborough Street
Walkway/Cycleway along South Bay Parade from State Highway One to Moa Road
Walkway/Cycleway from the end of the existing footpath where it turns into the racecourse alongside the State Highway to South Bay Parade
Type Length Programme Unsubsidised
Footpath Capital Programme 5,560m 2016/40 $1,200,000
TOTAL 5,560m 2016/40 $1,200,000
In the interests of overall optimisation of asset replacement some renewal and capital works need to be carefully considered prior to being initiated because of other works that need to occur either under or adjacent to the new footpath. The section of footpath outside the new Council building will need to be reconstructed to match in with the final design. Until the design is completed it is unknown what surfacing will be used or the cost to complete these works. The detailed Capital Programme is as follows:
Location Section Type Length Width Surfacing Year Cost Condition Comments
1 Adelphi Terrace East side Footpath 93 1.2 chip seal $20,000 4 Kerb and Channel
2 Bayview Street Churchill to Hastings south side
Footpath 284 1.4 chip seal $60,000 4 Undergrounding
3 Bayview Street Churchill to Fyffe north side
Footpath 285 2.0 chip seal $60,000 4 Undergrounding
4 Beach Road Motel north east side Footpath 774 1.6 metal $120,000 5 Undergrounding
5 Beach Road Old Beach south Footpath 116 1.0 metal $20,000 5 undergrounding and k&c
6 Brighton Esplanade to Torquay south side
Footpath 163 3.1 chip seal 2004 $30,000 4 Undergrounding
7 Chance Haven Churchill to Chance Walkway 113 1.4 metal $30,000 4 Concrete reshape
8 Churchill Street East side Footpath 264 1.7 chip seal $60,000 4 Undergrounding
9 Churchill Street East side Walkway 16 1.1 metal $5,000 5 steps into reserve with above
10 Churchill Street Adelphi north Footpath 82 1.8 chip seal $20,000 4 Undergrounding
11 Churchill Street Hastings to Bayview Footpath 225 1.4 chip seal $40,000 4 Undergrounding
12 Churchill Street Bayview to Davidson Footpath 238 2.8 chip seal $40,000 4 Undergrounding
13 Coastal New World to Middle Creek
Cycleway 2395 1.4 metal 2014 $40,000 4 Acceptable with long term maintenance
14 Deal Street North end Walkway 50 2.0 chip seal $10,000 4 Kerb and Channel on Deal Street
15 Esplanade Torquay to Margate Footpath 325 2.4 chip seal $60,000 4 Water Supply renewal
16 Esplanade Margate to Ramsgate Footpath 225 2.3 chip seal $40,000 4 Undergrounding
17 Fyffe Quay Lower Ward Street east Footpath 203 3.0 chip seal $40,000 4 Undergrouding and Water
18 Hasting Street Churchill west south side Footpath 78 1.3 chip seal 2004 $20,000 4 asphalt
19 Killarney Street Annie Boyd Walkway Walkway 73 1.5 metal $60,000 4 Should be for Disabled
20 Killarney Street Cemetery Access Walkway 227 1.4 metal $40,000 5 Acceptable for walkway?
21 Memorial Gardens South end Walkway 190 2.0 metal $30,000 4 Acceptable for walkway with minor work
22 Memorial Gardens North end Walkway 101 2.0 metal $20,000 4 Acceptable for walkway with minor work
23 Scarborough South side Footpath 230 1.2 metal $10,000 5 Ultimately extend to last house from Toms Track and rebuild ultimate length 1100m, allow for undergrounding
24 State Highway 1 Scarborough south west side
Footpath 67 0.6 metal $40,000 5 Needs power and kern and channel sorted
25 Takahanga Takahanga Walkway Walkway 130 1.5 metal $50,000 5 Asphalt provide ducts under driveways
26 West End Deal west west side Footpath 60 2.9 granite paver $20,000 4 Council building frontage
27 West End State Highway 1 Footpath 18 5.0 asphalt $10,000 4 SH 1 Realignment
28 Whakatu Lane South Bay Parade to Moa Walkway 74 1.4 metal $10,000 3 being replaced concrete?
29 Whalewatch Between bridges Walkway 300 1.0 metal $50,000 4
30 Whalewatch West side by turnaround Walkway 75 1.2 metal $20,000 5
31 Whitby Place Churchill to Whitby Footpath 70 3.3 chip seal $20,000 4 AC Water Main Low Voltage
SUMMARY RENEWALS
Other works required not advised to proceed
3208 $610,000
Can proceed with other works simultaneously
693 $95,000
Below standard but acceptable
3361 $260,000
Ready to proceed 282 $130,000
CAPITAL PROJECTS
C1 Fyffe Quay Avoca to Jimmy Armers Walkway 350 metal $100,000 Resource Consent
C2 Killarney Street Annie Boyd to Torquay Footpath 250 asphalt $140,000 Retaining Wall
C3 Killarney Street Annie Boyd to Scarborough
Footpath 350 asphalt $100,000 Drainage
C4 Ludstone Road Rorrisons to Grays north side
Footpath 130 asphalt $40,000 Undergrounding kerb and channel
C5 Ludstone Road Kiwi to Davidson north side
Footpath 105 asphalt $40,000 Undergrounding kerb and channel
C6 Lyell Creek State Highway 1 to Hawthorne and Rorrisons Rd
Walkway 1500 metal $200,000 Land Ownership
C7 Scarborough Sections Walkway 1100 concrete $200,000 Undergrounding
C8 South Bay Parade Sections Footpath 1500 concrete $300,000 Undergrounding
C9 State Highway 1 South Bay Parade north Footpath 275 metal $50,000
ACTIVITY MANAGEMENT PLAN DISCUSSION
The Council has approved $500,000 for expenditure on capital works on footpaths. Some minor
expenditure has occurred against this account.
As noted in the Activity Management Plan some projects, while desirable, “need to be carefully
considered prior to being initiated because of other works that need to occur either under or adjacent
to the new footpath”.
CAPITAL WORKS
The footpaths graded 4 and 5 in the category “ready to proceed” do not compromise any future works
and there is no impediment to them being constructed in 2015/16.
Recommendation: That the footpaths graded 4 and 5 in the category “ready to proceed” be
completed in 2015/16 at an estimated cost of $130,000.
The footpaths graded 4 and 5 in the category “can proceed with other works simultaneously” do not
compromise any future works if the other works are able to be undertaken in advance or as part of
the project and then there is no impediment to them being constructed in 2015/16.
Recommendation: That the footpaths graded 4 and 5 in the category “can proceed with other works
simultaneously” be completed in 2015/16 at an estimated cost of $95,000 subject to confirmation
that the additional works can occur or be included.
The footpaths graded 4 and 5 in the category “other works required not advised to proceed” are
compromised by future works. Any investment in these projects will be damaged or be required to be
redone when the associated works are completed. The associated works are of a similar or greater
cost than the footpath work.
Recommendation: That the footpaths graded 4 and 5 in the category “other works required not
advised to proceed” not be completed in 2015/16.
The footpaths graded 4 and 5 in the category “below standard but acceptable” provide access for
specific purposes. They are not suitable for persons with limited mobility or for mobility scooters or
pushchairs.
Recommendation: That the footpaths graded 4 and 5 in the category “below standard but
acceptable” be maintained in a reasonable condition suitable for their intended use.
A new asphalt footpath is proposed from the intersection of South Bay Parade and State Highway 1
past the Trotting Club toilets to link with the existing footpath on State Highway 1 where it turns into
the Trotting Club. This would provide people stopping at the rest area with access to toilet facilities.
The toilets themselves will require an upgrade in the future and eventual connection to the
reticulation.
There will be some requirements for fencing and minor retaining of fill. The opportunity would be
taken in due course to replant and maintain this area
Recommendation: That the footpaths from South Bay Parade to the State Highway 1 footpath be
considered in the next Long Term Plan at an estimated cost of $50,000.
FINANCE
As noted $500,000 was available from loans this financial year through the Annual Plan. If only $250,000 is expended then the loan repayments will be halved. These repayments are from the rates set for 2015/16. The value of repayment not required because only half the loan is used is $21,000. This amount is available to be budgeted and used for maintenance.
MAINTENANCE WORKS
There is approximately 10km of footpaths graded 3 which require maintenance works including
sweeping and patching. There has been significant deferred maintenance on these footpaths. Some
of these footpaths require short sections of footpath and driveways to be replaced. A very rough
estimate of this cost is $30,000.
Recommendation: That the footpaths graded 3 be maintained as required at an estimated cost of
$30,000 in 2016/17 subject to budget.
The paved footpath at the West End requires cleaning and sealing. A very rough estimate of this cost
is $20,000.
Recommendation: That the West End granite pavers be maintained as required at an estimated cost
of $20,000 in 2015/16.
There is approximately 3.4km of footpaths graded 4 and 5 in the category “other works required not
advised to proceed” which require maintenance works including sweeping and patching. There has
been significant deferred maintenance on these footpaths. Some of these footpaths require short
sections of footpath and driveways to be replaced however discretion needs to occur as the value of
this work may eventually be lost. Maintenance work may be to an interim standard that reflects the
remainder of the footpath and its likely date to full replacement. A very rough estimate of this cost is
$30,000.
Recommendation: That the footpaths graded 4 and 5 in the category “other works required not
advised to proceed” be maintained as required at an estimated cost of $30,000 in 2016/17 subject
to budget.
MANAGEMENT ISSUES
The Council has asked for consideration on permitting cyclists to use footpaths and in particular for
those footpaths along State Highway 1. This consideration for dual use is because there is no dedicated
cycleway available. West End has a similar issue.
The Council has discussed and obtained advice from New Zealand Transport Agency on their approach
to dual use footpaths in situations similar to Kaikoura. Elsewhere in New Zealand most dual use
footpaths do not have any vehicle or road crossings or, where these do occur, the footpath or vehicle
traffic is controlled by signage.
With a population of 2,500 Kaikoura does not have a significant number of cyclists. Cycling in and
about Kaikoura is to be encouraged however only a small percentage cycle with the addition of a few
tourists who have probably encountered worse traffic along the State Highway getting to Kaikoura.
Individual Sections
From South to North
South Bay turn off to Scarborough Street (top of the hill). No development with the route on
East side suitable for pedestrians and cyclists – also satisfactory due to no parking demand.
Scarborough to Davidson. Urban area footpaths or access on both sides, alternative routes
are available into the east end of town via Killarney Street – satisfactory situation due to low
parking demand.
Davidson to West End. Constricted by railway, underpass footpath on west side has steps
and footpath on east side constrained by height and just wide enough for one pedestrian –
very difficult to provide a good facility here although the east side can be regarded if services
are lowered to give a good result. On the west side, for the present, cyclists will have to
dismount and negotiate path and steps on foot, or share the road single file with
traffic. New tools such as
“sharrow” road markings
and sharing signs are likely
to become available in about
6 months to help manage
shared space.
West End to Hawthorne Commercial area. Has parking both sides often by trucks that
protrude beyond the parking bay or park on the footpath damaging the footpath, due to the
narrow road. The alternative route available via the New World to Whale Watch cycleway is
longer, not sealed and requires a detour with a railway crossing. The highway bridge across
the stream is pinch point. Cyclists could use the footpath if there were kerb crossings
provided. There is also a pinch point at the New World shopping complex for southbound
cycling that could be improved by providing kerb crossings and use of the footpath.
“Sharrow” markings could be used or cycle lanes marked on the road. The lack of width
would probably require the parking (probably east side) to be removed. The cyclists can also
use the footpath.
Hawthorne to Mill Road. Has parking on both sides but is not as heavily used by vehicles as
there are no fast food or garage outlets. Again “sharrow” markings could be used or cycle
lanes marked on the road. The lack of width would probably require the parking to be
removed. The cyclists can also use the footpath.
Discussion
The section from West End to Hawthorne Road has the most risk followed by Davidson Terrace to
West End. The other sections of road are working reasonably well with cyclists.
There is an option to have cyclists on the footpaths, cyclists already use the footpaths however they
recognise that they have minimal rights. If this was formalised by recognition of dual usage from
West End to Hawthorne Road this would place the responsibility on the motorist who already have
their attention focused on trying to see past the parked cars and get out safely onto the highway.
The addition of controls on either the cyclist or the motorist is unlikely to have total compliance and
the cyclists when given priority will travel faster on the footpath in the knowledge that they have
right of way.
New Zealand Transport Agency (NZTA) and Council staff do not favour this as the Council would now
be creating a new issue with the responsibility for any accidents on the Council. Formalising footpath
riding by declaring shared path is likely to create more safety issues than it solves. Taking cyclists off
the roads would remove any incentive for NZTA to address the issue and once removed NZTA would
not want the problem back.
Widening the parking so that the vehicles move further towards the centre line and give more room
for cyclists may result in drivers parking further from the kerb. It is preferable to mark the edge line
at 2 metres from the kerb and make more room for sharing side by side in the traffic lane.
For West End to Hawthorne Road we could remove the parking probably on the east side, this may
not be readily accepted by all parties however there would be space for a cycleway on both sides.
This would be a good solution for cycling.
NZTA has over the years taken additional width for widening but it is not contiguous and there is a
designation for a bypass that would take the State Highway traffic from West End to part way
towards Hawthorne Road. However this is not yet a project but would greatly assist the cyclist in the
worst sections of West End to Hawthorne Road.
Davidson Terrace to West End has no obvious solutions and is compromised by everything having to
go under the railway line. Re-grading the footpath on the east side is possible and if it was made
wider would probably be used by cyclists in both directions. There are services that would need to
be lowered.
The crossing of State Highway 1 from Ludstone to West End is not easily addressed. This route is
used to access schools separated by the highway. A route under the State Highway Bridge is feasible
and would generally be used in preference to a road crossing even though it is longer.
The West End sees some cycle traffic. Cyclists take their part as part of the general traffic. If a route
was provided under the State Highway Bridge then this could be extended further down Lyell Creek
to the West End car park which is where the traffic volumes drop off to the east.
Recommendations:
1. That this report be received.
2. That no changes be made to encourage any changes to existing cycle patterns along the
State Highway.
3. That no dual cycleways be provided on Council footpaths.
4. That cyclists be considered in projects associated with the West End and Lyell Creek.
5. That NZTA be requested to address cycle issues as part of the projects identified on the State
Highway.
Prepared by Gerry Essenberg, Operations and Maintenance Manager
Authorised by Angela Oosthuizen, Chief Executive Officer
VDAM REPORT This report has been included as the closing date for submissions is 17 February 2016 which is the date for the Council meeting. A modified draft would be supplied to New Zealand Transport Agency (NZTA) and then confirmed as correct or amended after the Council meeting. VDAM is the review of the “Vehicle Dimension and Mass (VDAM) Rule” for heavy vehicles. The change in rules are aimed at reducing the number of heavy vehicle movements on New Zealand Roads. The full report is available on www.transport.govt.nz/vdam. The main changes being looked at under this rule are as follows:
There is a proposal for allowing more mass on existing axle configurations. These changes are mainly of interest to the heavy haulage industry and while there will be effects on the roads they are in the nature of wear and tear.
There are proposed changes to the permitting of heavy vehicles which are aimed at streamlining administration.
Also they are considering increasing the height from 4.25 to 4.30 and the width from 2.5 to 2.55 metres. This will allow changes in the composition of the truck and bus fleet and enable use of some European models that are not presently allowed on New Zealand roads.
They also look at the effects on infrastructure and have noted some items of infrastructure such as the Kaikoura Tunnels and the Lyttleton Road Tunnel as being affected.
The intention is to make a submission and a draft has been proposed as follows: SUBMISSION
The rule changes are well intentioned and will save the New Zealand economy significantly over time, particularly as it has been identified in the “The South Island Freight Study” that there will be a significant increase in heavy vehicles over the next 30 years. The effects are such that while the changes are good for New Zealand as a whole the effects on the Kaikoura District are negative. Even with the existing rules the effect of heavy vehicles will increasingly impact Kaikoura. None of the additional over dimension buses and trucks will be able to use State Highway one from Kaikoura to Cheviot northbound legally due to the road tunnels, one tunnel is posted as 4.25m. Whether they can use the route southbound depends on the combination of increase width and height. Because the tunnels are arches it is the extreme top corners that will hit the edge of the tunnels. The tunnels need to be comprehensively measured and tolerances agreed with the industry. They should be open cut.
Fig 1 Kaikoura Raramai Tunnel North Bound More vehicles will be diverted along the Inland Road should they wish to travel the freight or tourist route from Christchurch to Picton. This route has never been designed to take the heavy vehicles presently using this as an alternative to State Highway 1. The increase in width reduces the already minimum clearance along many sections of the State Highway in Kaikoura District. The highway through Kaikoura District has other users beside heavy vehicles including tourists, cyclists and local traffic. All these users will be detrimentally affected by the increase in vehicle width. The urban section is already heavily compromised by large vehicles. Heavy trucks regularly park on the footpath and the damage is to the ratepayer’s cost. If they park on the carriageway they are often parked inside the travel lane. When trucks park opposite each other, heavy vehicles cross the centreline. There are such major concerns about the insufficient width in the State Highway through the town of Kaikoura to accommodate parking, cyclists and heavy vehicles that with the projected increase in freight is frightening to the other road users and the locals who view the close calls on a regular basis.
Fig 2 State Highway 1 Kaikoura, outside BP Service Station, one vehicle parked on footpath, one vehicle parked 200mm into travel lane As heavy vehicles travel to meet with ferry crossings there are peak periods when motorists are second class road users dictated to by the number of heavy vehicles in their immediate vicinity to how they must travel. Part of the One Network Roads outcomes was looking at travel reliability. Heavy vehicle accidents can close the highway for half a day at any time of the year. Guardrails may reduce the severity of accidents but is not an answer to the issues on the Kaikoura section of State Highway 1. NZTA has not undertaken any projects in Kaikoura District that have improved the State Highway for all road users for a significant period. While it is now undertaking some investigations towards completing some reports it has not committed to any projects. We are aware that there are separate projects being “The South Island Freight Study” and a “Study of the State Highway 1 Picton to Christchurch Route”. State Highway 1 outside of the Kaikoura District has had many projects that have improved sections of road that were better than most of the highway in our District prior to commencement of the project. The roads in Kaikoura District may be expensive to get to a state
suitable for their existing use and their proposed future use but this is the least user friendly section of State Highway 1 in the South Island and works are overdue. Until there is a firm commitment to providing a route for all users in both the urban and rural parts of the State Highway, Kaikoura District Council believes that it is inappropriate to allow any of the new over dimension vehicles to operate within Kaikoura District. An additional rule that excludes these vehicles from Kaikoura District is appropriate. The limitations on these vehicles should remain in place until the following projects have been implemented or agreed otherwise with Kaikoura District Council:
State Highway 1 achieves a continuous width with passing bays and pull of bays at regular intervals for tourists, cyclists, heavy vehicles and slow vehicles.
State Highway 1 is redesigned through Kaikoura with a new bypass from the existing railway bridge for 500metres north as designated with suitable width for parking, cyclists and heavy vehicles.
The Inland Road is reclassified as a State Highway. Recommendation: That the “Submission” be endorsed and forwarded to New Zealand Transport Agency.
Prepared by Gerry Essenberg, Operations and Maintenance Manager
Authorised by Angela Oosthuizen, Chief Executive Officer