Bi-Weekly Progress Report Durham Meadows Superfund Project, Durham & Middletown, CT US Army Corps of Engineers Contract No. W912WJ19C0002 September 3, 2021 Work Accomplished to Date: Install Water Service Connection into Foundations Install Internal Plumbing Completed 12” Pipe Installation at Maiden Lane Stream Crossing Work Planned for Next Two Weeks: September 6, 2021 to September 10, 2021 Install Water Services into Foundations Install Plumbing Connections in Houses Restoration of Maiden Lane Stream Crossing September 13, 2021 to September 18, 2021 Install Water Services into Foundations Install Plumbing Connections in Houses Page 1 of 5

Work Planned for Next Two Weeks: September 6, 2021 to

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Work Planned for Next Two Weeks: September 6, 2021 to

Bi-Weekly Progress ReportDurham Meadows Superfund Project, Durham & Middletown, CT

US Army Corps of Engineers Contract No. W912WJ19C0002September 3, 2021

Work Accomplished to Date:• Install Water Service Connection into Foundations• Install Internal Plumbing• Completed 12” Pipe Installation at Maiden Lane Stream Crossing

Work Planned for Next Two Weeks:

September 6, 2021 to September 10, 2021• Install Water Services into Foundations• Install Plumbing Connections in Houses• Restoration of Maiden Lane Stream Crossing

September 13, 2021 to September 18, 2021

• Install Water Services into Foundations• Install Plumbing Connections in Houses

Page 1 of 5

Page 2: Work Planned for Next Two Weeks: September 6, 2021 to

Bi-Weekly Progress ReportDurham Meadows Superfund Project, Durham & Middletown, CT

US Army Corps of Engineers Contract No. W912WJ19C0002September 3, 2021

Figure 1: Water Main Installation Summary Middletown and Durham

Page 2 of 5

Completed Waterline

Remaining Waterline to be installed

Water Line Project(30,202 feet total to install)

Start Date: September 8, 2019

Installed Pressure tested and disinfected

Feet % Feet %

29,610 100 23,584 78

Wells(128 total)

Start Date: TBD

Abandoned Converted to Monitoring Well

Number % Number %

0/125 0 0/3---,-:

Durh,~rn Center ystem

l--

1 ;L--\',_ 1---- \: ~~j I

-. ----•,.

i- H,;,,cu, --"-" ~ ;=-- r

Page 3: Work Planned for Next Two Weeks: September 6, 2021 to

Bi-Weekly Progress ReportDurham Meadows Superfund Project, Durham & Middletown, CT

US Army Corps of Engineers Contract No. W912WJ19C0002September 3, 2021

Figure 2: Full-Service Connection SummaryDurham

Anticipated work limits for next two weeks

Page 3 of 5

Internal Plumbing Complete(119 total in Durham)

Start Date: May 2022

Installed Pressure tested and disinfected

Number % Number %

49 41 49 41

Connections into Foundations(119 total in Durham)

Start Date: May 2022

Installed

Number %

53 45

*---*

Page 4: Work Planned for Next Two Weeks: September 6, 2021 to

Bi-Weekly Progress ReportDurham Meadows Superfund Project, Durham & Middletown, CT

US Army Corps of Engineers Contract No. W912WJ19C0002September 3, 2021

Figure 3: Main Structure SummaryMiddletown and Durham

Page 4 of 5

Altitude Valve VaultStart Date: April 5, 2021

Pre-cast Building Set

Interior Work

Electrical

Instrumentation

Finish Site Work

Testing

Structure On-Line

Cherry Hill Water Storage Tank

Booster Station

Meter Vault

Pressure Relief Valve and Vault

Long Hill Pump Station

Altitude Valve Vault

Booster StationStart Date: April 7, 2021

Pre-cast Building Set

Interior Work

Electrical

Instrumentation

Finish Site Work

Testing

Structure On-Line

Meter BuildingStart Date: TBA

Pre-cast Building Set

Interior Work

Electrical

Instrumentation

Finish Site Work

Testing

Structure On-Line

PRV and VaultStart Date: November 2020

Pre-cast Building Set

Interior Work

Electrical

Instrumentation

Finish Site Work

Testing

Structure On-Line

Water Storage TankStart Date: May 2020

Pre-cast Building Set

Interior Work

Electrical

Instrumentation

Finish Site Work

Testing

Structure On-Line

Long Hill Pump StationStart Date: TBD

VFDs Installed

Hydropneumatic Tanks Removed

Chlorination System Installed

LegendPending

Ongoing

Complete

Page 5: Work Planned for Next Two Weeks: September 6, 2021 to

Bi-Weekly Progress ReportDurham Meadows Superfund Project, Durham & Middletown, CT

US Army Corps of Engineers Contract No. W912WJ19C0002September 3, 2021

Page 5 of 5

Maiden Lane Stream Crossing