1

WORK PLAN + PROJECT EXPENDITURES

2020

- 20

23

2 2020 – 2023 WORK PLAN + PROJECT EXPENDITURES

3

CONTENTS Work Plan + Project Expenditure Approval Process .......................... 3

2020 – 2023 Work Plan ...................................................................... 4

2019 – 2022 Project Expenditure Variance ........................................ 6

Development Maps ........................................................................... 7

Crossings ........................................................................................ 8

RiverStone ...................................................................................... 9

Watermark ................................................................................... 10

Sherring Business + Industrial park .............................................. 11

Lethbridge Airport ........................................................................ 12

3

WORK PLAN + PROJECT EXPENDITURE APPROVAL PROCESS Lethbridge Land has prepared a work plan for the following four years. This work plan and related project costs will be based upon market demand and market construction costs.

Due to the nature of market fluctuations, there may be some variance in estimated costs from year to year.

Project variances and timing changes will be presented to City Council for approval.

4 2020 – 2023 WORK PLAN + PROJECT EXPENDITURES

2020 – 2023 WORK PLAN + PROJECT EXPENDITURESDevelopment Tasks Scope 2020 2021 2022 2023

CRO

SSIN

GS

Crossings School Site Development (Playground + Sports Fields) Construction

$1,400,000 CIP D-18: $425,000

$1,825,000

Crossings 5* Engineering $125,000

Construction $3,100,000

Crossings North Costing + Pro Forma Development Consulting $500,000

Crossings Landscaping + Wayfinding Signage* Engineering $90,000

Construction $850,000

Roadway Surface Refurbishment* Construction $410,000

Crossings North Site Preparations (Rough Grading + Basement Dump Management) Construction $1,140,000

Crossings 9 + Park* Engineering $320,000

Construction $7,800,000

Crossings 10* Engineering $200,000

Construction $3,900,000

Crossings 11* Engineering $200,000

RIVE

RSTO

NE

RiverStone 18* Engineering $175,000

Construction $4,200,000

RiverStone 19* Engineering $125,000

Construction $2,400,000

WAT

ERM

ARK

Great Bear Blvd Landscaping Construction $250,000

Outline Plan Amendment + Costing and Pro Forma Development Engineering $500,000

Watermark 2* Engineering $200,000

Construction $3,900,000

Watermark 3* Engineering $200,000

5

*Moved out one year from approved 2019-2022 Work Plan.

All forecasted construction is subject to market conditions.

Development Tasks Scope 2020 2021 2022 2023 SH

ERRI

NG

Roadway Overlays Construction $1,990,000

Rail* Engineering $7,000,000

Consulting Services Consulting $1,300,000

Grading Construction $480,000 $2,880,000

Topsoil Removal Construction $4,000,000 $2,000,000

Landscaping Construction $1,380,000

LETH

BRID

GE

AIR

PORT

Waterline Upgrade Construction $1,252,000

Area Structure Plan/Outline Plan Consulting $600,000

Annexation Consulting $150,000

Energy Generation Feasibility Studies Consulting $150,000

TOTAL $ 13,342,000 $ 8,770,000 $ 18,280,000 $ 15,200,000

6 2020 – 2023 WORK PLAN + PROJECT EXPENDITURES

2019 PROJECT EXPENDITURE VARIANCE Development Task Scope Budget Actual Variance Explanation

Crossings Phases 6 + 7 Construction $6,100,000 $4,576,900 $1,523,100 Work is continuing in 2020.

Crossings School Site Development (Playground + Sports Fields)

Engineering $200,000 $55,300 $144,700 Work is continuing in 2020.

Crossings Phase 5 Engineering $125,000 $24,800 $100,200 Work is continuing in 2020.

Crossings Landscaping + Wayfinding Signage Engineering $90,000 $0 $90,000 Work moved to 2020.

Great Bear Boulevard (Roadway) Construction $3,950,000 $3,757,600 $192,4000 Remaining for warranty and maintenance period (2 years).

7

DEVELOPMENT MAPS

DEVELOPMENT MAPS

8 2020 – 2023 WORK PLAN + PROJECT EXPENDITURES

CROSSINGS

9

RIVERSTONE

10 2020 – 2023 WORK PLAN + PROJECT EXPENDITURES

WATERMARK

11

SHERRING BUSINESS + INDUSTRIAL PARK

12 2020 – 2023 WORK PLAN + PROJECT EXPENDITURES

LETHBRIDGE AIRPORT

13

PREPARED BY

LETHBRIDGE LAND

REAL ESTATE & LAND DEVELOPMENT DEPARTMENT CITY OF LETHBRIDGE