148
P00001 FIELD INVESTIGATIONS OF UNCONTROLLED HAZARDOUS WASTE SITES FIT PROJECT ' > * • 1 '•. * 1 WORK IN SUPPORT OF EPA ENFORCEMENT CASE: CONTAMINATION OF CURTISS STREET WELL FIELD SOUTHINGTON, CONNECTICUT DRAFT REPORT TDD No. F-l-8007-01A ecology and environment, inc. International Specialists in the Environmental Sciences 3100

WORK IN SUPPORT OF EPA ENFORCEMENT CASE, … · Conduc a preliminart y assessment of all possible source of s contamination of the Curtiss Street wel fieldl . 5. ... for remedial

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

  • P00001

    FIELD INVESTIGATIONS OFUNCONTROLLED HAZARDOUS WASTE SITES

    FIT PROJECT '

    > * •1 '•. * 1 •

    WORK IN SUPPORT OF EPA ENFORCEMENT CASE:

    CONTAMINATION OFCURTISS STREET WELL FIELDSOUTHINGTON, CONNECTICUT

    DRAFT REPORT

    TDD No. F-l-8007-01A

    ecology and environment, inc.International Specialists in the Environmental Sciences

    3100

  • P00002

    F-1-8007-01A

    WORK IN SUPPORT OF EPA ENFORCEMENT CASE:

    CONTAMINATION OF

    CURTISS STREET WELL FIELD

    SOUTHINGTON, CONNECTICUT

    DRAFT REPORT

    Prepared by: Submitted to:

    Paul Exner Merrill S. Hohman (Director)

    Glenn Smart Air and Hazardous Materials Division Margret Han ley U.S. EPA, Region I

    William Norman

    Submitted by: Date Submitted:

    Paul J. Exner, Project Leader October 31, 1980 Ecology and Environment, Inc.

    FIT Team, Region I

  • P00003

    Section Page

    w

    Figures Tables VI

    1. Introduction 1-1

    1.1 Background 1-1

    1.2 Summary and Conclusions 1-4

    1.2.1 Remedial Plans 1-4

    1.2.2 Water Supply Plans 1-7

    1.2.3 SRSNE Housekeeping 1-9 1.2.4 Preliminary Assessment of Possible Contamination Sources

    in the Vicinity of the Curtiss Street Well Field 1-12

    1.2.5 Program to Determine Extent of SRSNE Contribution tp'Well

    Fo'eld Contamination-and. to Monitor Remedial.Plans. .... 1-15 2. Remedial Plans 2-1

    2.1 Introduction 2-1

    2.2 Soil Removal 2-2 2.2.1 Excavation and Backfill 2-3 2.2.2 Disposal of Contaminated Soil 2-5

    2.3 Isolation from Groundwater 2-9

    2.3.1 Capping and Bottom Seal 2-9

    2.3.2 Slurry Walls, Grout Curtains and Sheet Piling 2-13

    2.3.3 Diversion Wells 2-17 2.4 Localized Discharge Wells 2-18 2.5 Pumping Town Well No. 6 2-27

    2.6 Summary 2-28

    2.7 References 2-32

    3. Water Supply Plans 3-1

    3.1 Introduction/Background 3-1 3.2 Development of a New Production Well 3-4 3.3 Utilization of Southington Reservoirs 3-6 3.4 Development of Storage Facilities 3-8 3.5 Purchase Water 3-10

    3.6 On-site Treatment of Production Well No. 6 3-11 . 3.6.1 Aeration 3-13

    3.6.2 Carbon Adsorption 3-17 3.7 Summary 3-22 3.8 References 3-24

    II

  • Page Section CONTENTS P00004

    4. SRSNE Housekeeping 4-1

    4.1 Introduction/Background 4-1

    4.2 General Practices 4-11 4.2.1 Contingency Plan and Emergency Procedures 4-11

    4.2.2 Personnel Training 4-12

    4.2.3 General Inspection Requirements 4-12

    4.2.4 Security 4-13

    4.2.5 Preparedness and Prevention 4-14

    4.3 Process Area Practices 4-15

    4.3.1 Overflow Prevention 4-15

    4.3.2 Distillation Equipment Integrity 4-15

    4.3.3 Outfall Monitoring 4-16

    4.3.4 Process Area Cover 4-17

    4.4 Drum Storage Area Practices 4-18

    4.4.1 Use and Management of Containers 4-18

    4.4.2 Greater Use of Bulk Storage 4-20

    4.4.3 Fire Equipment 4-20

    4.4.4 Drum Storage Area Cover 4-21

    4.5 Bulk Storage Area Practices 4-22

    4.5.1 General Requirements for Tanks 4-22

    4.5.2 Containment Structure 4-23

    4.5.3 Air Pollution Control 4-24

    4.6 Summary 4-24

    4.7 References 4-28

    5. Preliminary Assessment of Possible Contamination Sources in the

    Vicinity of the Curtiss Street Well Field 5-1

    5.1 Introduction 5-J

    5.2 The Caldwell Property 5-2

    5.3 Cianci Property 5̂ 6

    5.4 Potential Industrial Pollution Sources South of Curtiss Street 5~8

    5.4.1 The Industrial Chrome Plating Factory 5-9 5.4.2 The Southington Form Construction Company 5-11

    5.4.3 The Ideal Forge Company 5-12

    5.5 SRSNE Sludge Disposal Sites in the Vicinity of the Curtiss

    Street Well Field 5-13

    5.5.1 The Marek Property, South of Darling Street 5-13

    5.5.2 The Mastrianni Gravel Pit, Flanders Street 5-16" 5.5.3 East Bank of the Quinnipiac River 5-20

    5.6 Summary and Conclusions 5-22

    5.7 References 5-26

    III

  • P00005 Section CONTENTS

    Program to Determine Extent of SRSNE Contribution to Wei?

    Field Contamination and to Monitor Remedial Plans 6-1

    6.1 Introduction 6-2

    6.2 Technical Approach 6-2

    6.2.1 Drawdown Test 6-2

    6.2.2 Computer Model . 6-3

    6.6.3 SRSNE Borings 6-3

    6.2.4 First Ring Off-Site Wells 6-5

    6.2.5 Additional Off-Site Wells 6-6

    6.3 Costs 6-7

    6.4 Summary 6-10

    6.5 Reference 6-11

    IV

  • FIGURES P00006

    Number Page

    2-1

    5-1

    5-2

    Schematic Remedial Plan for 'Contarm'nent PlumeContainment at SRSNE, Southington, CT

    Plot Plan of Curtiss Street Well Field and Surrounding Area

    Analysis of Sludge Found at Flanders Green Apartments Construction Site

    2-21

    5-3

    5-19

  • TABLES P00007

    Number

    1-1 Summary of Remedial Plans and Estimated Costs 1-5

    1-2 Summary of Water Supply Options and Cost for Southington,

    Connecticut 1-8

    1-3 Summary of Housekeeping Practices Available at SRSNE by Area . . . 1-10

    1-4 Cost Estimate For Proposed Hydrogeologic Investigation 1-17

    2-1 Estimated Unit Costs for Surface Sealing Methods and Materials . . 2-11

    3-1 Chemical Analysis of Organic Compounds Found in Southington

    Production Well No. 6 during Warzyn Study 3-12

    3-2 Organic Removal Efficeincies for Pilot Scale Diffused-Air

    Aeration Plants 3-16

    3-3 Summary of Water Supply Options and Costs for Southington,

    Connecticut 3-23

    4-1 Summary of Housekeeping Practices Available at SRSNE by Area • • • 4-26

    6-1 Cost Estimate for Proposed Hydrogeologic Investigation 6-8

  • P00008

    1. INTRODUCTION

    1.1 Background

    On September 15, 1980 Ecology and Environment's (E & E) Field

    Investigation Team (FIT) accepted Technical Direction Document (TDD)

    No. F-1-8007-01A to perform work in support of EPA Enforcement in

    Southington, Connecticut. Briefly, Production Wells Nos. 4 and 6,

    both in the Curtiss Street well field, have been closed due to the

    presence of organic contaminants. Adjacent to this well field and to

    the northwest of the production wells is the site of Solvents

    Recovery Service of New England (SRSNE), a solvent

    recovery/reclamation process plant. SRNSE is suspected of

    contributing to the groundwater pollution mainly through past

    practices of depositing organic material in an open earthen pit which

    overflowed to earthen lagoons on its property. Recent investigations

    have also indicated that there may be other sources of organic

    groundwater contamination in and around the Curtiss Street well

    field. Generally, E & E"s assignment has been divided into five

    tasks which were given priority ranking by EPA at the beginning of

    the project. In descending order of importance, these tasks are:

    1. Prepare a working list of viable remedial plans designed to

    remove, neutralize, or isolate chemical wastes and

    contaminated soil on and/or immediately surrounding SRSNE

    property.

    1 - 1

  • P00009

    2. Prepare a working list of viable plans to assure that an

    adequate supply of drinking water is provided to the

    residents of Southington.

    3. Prepare a working list of on-site measures needed to prevent

    further contamination of groundwater by present on-site

    activities at SRSNE.

    4. Conduct a preliminary assessment of all possible sources of

    contamination of the Curtiss Street well field.

    5. Design a program to determine the extent of chemical waste

    contamination in soil, groundwater, and surface water on

    and/or surrounding SRSNE property. Further, design a

    program to monitor the effectiveness of any implemented

    remedial plan.

    While performing the five tasks, E & E personnel have contacted

    many sources of information in both the private and public sectors.

    When performing Task No. 1, the Region I team drew on the expertise

    and experience of E & E's ad hoc central committee investigating

    remedial options for groundwater contamination. Further, ideas and

    suggestions were solicited from many of the other E & E regional

    offices throughout the U.S.

    1 - 2

  • P00010

    While developing plans to assure an adequate supply of drinking

    water for Southington, Dan Christy of the Southington Water

    Department provided valuable information. When developing on-site

    measures to prevent further contamination of groundwater by SRSNE, Ed

    Parker and Paul Marin of the Connecticut Department of Environmental

    Protection (DEPJ were particularly helpful in relaying to E & E all

    their experiences while working for many years with the DEP in

    Southington. While conducting the preliminary assessment of all

    possible sources of contamination of the Curtiss Street well field,

    many people and agencies were contacted. Town of Southington

    officials, in particular, Al Adams of the Assessor's Office, lent

    valuable assistance.

    On October 1, 1980, after most of the preliminary investigations

    had been completed, a meeting was held at EPA during which E & E

    presented its findings. At the conclusion of the meeting, the

    direction and scope of subsequent work was established. Basically,

    for remedial planning, E & E's task was to develop a list of possible

    plans, generate cost data associated with implementing each plan, and

    to outline the studies which must be undertaken to evaluate each plan

    before a final decision can be reached. E & E was not required to

    make a recommendation to EPA about the best remedial plan. For SRSNE

    housekeeping practices, a working list of methods was required, but

    the development of cost data for this part of the study was

    considered beyond the scope of E & E's assignment.

    1 - 3

  • P00011

    E & E believes that the tremendous amount of information

    gathered and developed during this study has been assembled here in a

    logical fashion. Each of the five tasks described earlier has been

    assigned an entire chapter of this report. Generally, each chapter

    begins with an introduction, followed by the technical and cost

    information. Finally, a summary section and a list of references are

    included. An overall summary of the report is presented below.

    1.2 Summary and Conclusions

    The summary and conclusions of this report have been divided by

    task.

    1.2.1 Remedial Plans:

    Table 1-1 provided a list of the remedial options with

    associated costs that have been considered viable for

    isolation and removal of chemical wastes and contaminated soil

    on and/or immediately surrounding SRSNE property. E & E

    suggests that each option presented in this report be

    considered as a module. Combining modules, a variety of

    viable remedial plans can be assembled.

    1 - 4

  • '"^ °f *™^ "». -d Estimated Cosu

    installed Cost jthousandj:

    i. Excavation aj Excavation

    & Backfill 132 bj Backfill

    134 2. Disposal of

    aj Landfill Disposal Contaminated Soil

    bj Incineration 2900 160

    3. Isolation from Groundwater

    aj Capping

    bj Bottom Seal 14.5

    cj Slurry Wall

    dj Grout Curtain ej Sheet Pi ling

    fj Diversion Wells

    150

    450

    290

    NE

    4. LocalizedWells

    Discharge aj Discharge/Rechargebj Carbon Treatment

    Wells 38.2

    144 5. Pumping Town

    Well No. 6 N/A

    N/A = Not Applicable NE = NGt Esti-ted for this Study

    P00012

    Maintenance Costs

    N/A

    N/A

    16

    N/A

    N/A

    N/A

    N/A

    N/A

    NE

    NE

    63

    NE

    1 - 5

  • An obvious conclusion that can be drawn at this time

    is that a plan which includes the excavation of the

    lagoons, backfill with clean fill, and disposal of the

    contaminated soil is an expensive alternative

    (transporting contaminated soil to and disposal at a

    secure landfill can cost 2.9 million dollars). However,

    this is the quickest method of removing gross subsurface

    contamination. The plan can be made less expensive

    through the use of a portable rotary kiln incinerator,

    located on-site, to destroy all the organic material in

    the excavated soil. However, the liabilities of such a

    system include a lack of operating data and possible

    objections from local citizens due to potential hazardous air pollution.

    Another plan may be to isolate the contamination

    from the groundwater by constructing barrier walls and

    capping. This alone, however, is only a temporary

    measure due to the inevitable failure of the barriers.

    This plan can be modified through the use of a discharge

    well system designed to draw contaminated water out of

    the ground, treat it, and inject it back into the ground.

    The liability of such a system is that it is basically

    untried. In particular, much more work is needed to

    evaluate carbon adsorption as a potential treatment system.

    1 - 6

  • Another modular option is to pump Production. Well No,

    6 in order to flush the aquifer after isolating the

    source(s) of contamination. Much more study is required

    before this plan can be recommended.

    The general conclusion that can be reached for the

    remedial plans section of this report is that the options

    presented by £ & E make up only a working list.

    Considerably more detailed engineering analysis is

    required before any. plan can be recommended and

    implemented.

    1.2.2 Water Supply Plans:

    Table 1-2 provides a list of the options available to

    insure an adequate supply of safe drinking water for the

    residents of Southington. Considering each option as a

    module, a variety of viable plans can be devised by

    assembling modules. For example, instead of installing a

    new 1000 6PM production well, a 500 6PM well could be

    installed in conjunction with a storage tank for peak

    loads. When considering treatment of Production Well No.

    6, both aeration and carbon treatment can be used in

    conjunction at an overall cost lower than the addition of

    the individual costs.

    1 - 7

    ecology and environment, inc.

  • P00015

    TABLE 1 - 2

    Summary of Water Supply Options and Costs for Southington, Connecticut

    Operating/Maintenance Installed Cost £ Costs (Thousands of

    ITEM (Thousands of dollars) dollars per year)

    1. New Production Well 238 10

    2. Use Reservoirs 957 289

    3. Develop Storage Facilities2 993 NE

    4. Purchase Water 6 315

    5. Aeration Treatment of PW No. 6 285 1103

    6. Carbon Treatment of PW No. 6 237 893

    NE = not estimated for this study

    (1) All costs based on supplying 1.44 MGD except storage facilities

    (2) Based on 2.3 million gallon capacity

    (3) Costs do not include 0 & M for PW No. 6

    1 - 8

  • P00016

    It should be noted that, from E & E's investigation,

    the installation of a new production well is the least

    expensive option. The Town of Southington has already

    reached this conclusion and has had a hydrogeologic survey

    conducted to establish potential well sites.

    Purchasing water is both expensive and risky since

    the lease could be cancelled if and when the source of

    water needs the supply for its own purposes.

    The treatment of the water at the discharge of

    Production Well No. 6 appears both technically and

    economically viable. However, considerably more

    engineering work is required before any recommendation can

    be made.

    1.2.3 SRSNE Housekeeping:

    Table 1-3 lists housekeeping procedures by area for the

    three major sections of the SRSNE facility. Many of the

    proposed methods are generally included as part of the

    recently published regulations to implement RCRA, in

    particular 40 CFR Parts 264 and 265. An asterisk is used

    in Table 1-3 to identify those methods which are covered

    by the regulations. Importantly, the Process Area is now

    1 - 9

  • P00017

    TABLE 1 - 3

    SUMMARY OF HOUSEKEEPING PRACTICES

    AVAILABLE AT SRSNE BY AREA

    Process Area Drum Storage Area Bulk Storage Area

    1. Contingency Plan 1. Contingency Plan (*) 1. Contingency Plan (*)

    2. Personnel Training 2. Personnel Training (*) 2. Personnel Training (*)

    3. General Inspection 3. General Inspection (*) 3. General Inspection (*}

    4. Security 4. Security (*) 4. Security (*)

    5. Preparedness 5. Preparedness (*) 5. Preparedness (*)

    6. Overflow Prevention 6. Container Management (*) 6. Equipment Integrity (*)

    7. Equipment Integrity 7. More Bulk Storage 7. Containment Structure

    8. Outfall Monitoring 8. Fire Equipment 8. Air Pollution Control

    9. Area Cover 9. Area Cover

    * = Covered under existing hazardous waste regulations

    1 - 10

  • P00018

    exempted from the hazardous waste regulations since SRSNE

    is a recycling/reuse operation. New regulations which

    will specifically address solvents recycling industries

    are supposedly imminent. It is E & E's feeling that, as a

    minimum, these new regulations will address the general

    requirements now imposed on the Drum Storage and Bulk

    Storage Areas (See numbers 1 through 5 in Table 1-3).

    However, the time frame between publication of draft

    regulations and the effective date of their implementation

    may be many months. Therefore, any housekeeping practices

    that are to be immediately applied to the Process Area

    must be implemented through a mechanism other than RCRA.

    Beyond regulated housekeeping practices, there are

    methods which are "good engineering practice". Though

    expensive, these practices are extremely effective in

    preventing further groundwater and surface water

    contamination in the Curtiss Street well field]. Examples

    of such practices are the construction of a roof over the

    Process Area, the construction of a pad and roof in the

    Drum Storage Area, and the^construction of a containment

    structure (dike) in the Bulk Storage Area (tank farm).

    1 - 11

  • P00019

    Many of the basic concepts for these practices have been

    extracted from environmental regulations such as 40 CFR

    Part 112 - Oil Pollution Prevention and 40 CFR Part 761

    PCB's.

    Other practices of note are 1) monitoring outfalls

    for organic contaminant levels, 2) reducing the drum

    inventory, 3) installation of quick response fire

    equipment (e.g., deluge system), and, 4) the installation

    of appropriate organic vapor control equipment.

    1.2.4 Preliminary Assessment of Possible Contamination Sources

    In the Vicinity of the Curtiss Street Well Field:

    The information obtained during this assessment

    suggests that several sources of contamination exist in

    the vicinity of the Curtiss Street well field.

    As discussed in previous studies, the contamination

    observed on the Caldwell property appears to emanate from

    a more local source than SRSNE. However, aerial photo

    examination and available site history do not adequately

    confirm the assumption that the source of contamination is

    the Caldwell property.

    1 - 12

  • P00020

    The president of Supreme Screw Manufacturing, the

    sole generator of solvent waste to occupy the Caldwell

    property, denies that his company disposed of solvent

    waste on site. In addition, Supreme Screw Manufacturing

    occupied the site for a relatively short period of time

    approximately 15 years ago. It is not clear whether

    Supreme Screw Manufacturing could generate enough waste in

    such a short time of the necessary consistency to persist

    in that location.

    The contamination of the private well on the Cianci

    property indicates that an additional source of

    contamination exists upgradient from SRSNE. The origin of

    this source is presently unknown. Local residents have

    expressed their opinion that SRSNE has deposited waste

    materials on the Cianci property as recently as 1979. The

    management of the Cianci Construction Company, however,

    has declined to comment.

    Potential sources of contamination exist upgradient

    from Production Well No. 4, south of Curtiss Street.

    However, their impact on Well No. 4 is not substantiated

    by the water quality data from previous studies. The very

    high levels of organohalides in observation well TW-2

    suggests that there is probably a substantial source of

    1 - 13

  • contamination in the vicinity of Ideal Forge and/or

    Marek's property, south of Darling Street. Water quality

    data in that area is, however, nonexistent. Ideal Forge

    appears to be a well managed forging operation, and aerial

    photographs do not reveal any surface abnormalities or

    vegetative stress at that location. Marek's property

    should be studied more closely. Available information

    indicates that liquid and/or sludge waste from SRSNE was

    deposited at Marek's property for an undetermined amount

    of time. Surface mining of gravel and fi l l at Marek's has

    changed the appearance of the property, probably

    destroying or removing any surface expression of waste

    disposal. It is also possible that sludge deposited at

    Marek's was removed in part, with the f i l l , and may be

    found at other locations in town.

    The presence of industrial sludge at the Flanders

    Green Apartment Complex has been verified by DEP analysts.

    It is an assumption, however, that this sludge originated

    from SRSNE. Groundwater quality data for the area located

    east of the Quinnipiac is necessary to determine if the

    sludge located at Flanders Green has or will eventually

    affect the Curtis Street well field.

    1 - 14

  • Finally, the disposal of industrial waste on the bank

    of the Quinnipiac south of Lazy Lane during the 1960's has

    been verified in the records of the Connecticut Water

    Resources Commission. In addition, the fill used on the

    flood plain located behind the Mastrianni diner may have

    been contaminated by SRSNE sludge. Water quality data,

    and soil sampling east of the Quinnipiac River between

    Lazy Lane and Curtiss Street will be necessary to

    determine if the wastes have persisted in the flood plain

    environment, and if they are impacting the water quality

    of Production Wells Nos. 4 and 6.

    In conclusion, the information obtained during this

    assessment suggests that several sources of contamination

    exist in the vicinity of the Curtiss Street well field.

    However, further investigation is required to confirm or

    estimate their impact on Production Wells Nos. 4 and 6.

    1.2.5 Program to Determine Extent of SRSNE Contribution to Well

    Field Contamination and to Monitor Remedial Plans:

    E & E has presented a program that will both aid in

    determining the extent of groundwater contamination in the

    Curtiss Street well field north of Production Well No. 6

    and serve as a network of monitoring wells to evaluate the

    1 - 15

    paper ecology and environment,

  • this program are:

    * A drawdown test for Wei] NO. 6

    * Computer model l ing of the aquifer

    * Contamination characterization on SRSNE property

    using ho l low stem augers and split spoon samplers.

    * Establishment of mul t ipoint monitoring wel ls on SRSNE

    property using BAR-CAD samplers.

    # . Contamination characterization in the well f ie ld

    using h o l l o w stem augers and spli t spoon samplers.

    Establishment of a mul t ipo in t monitoring well network

    in the well f ield us ing BAR-CAD samplers.

    S * The cost of the proposed program wi l l be

    ^approximately $76,000. Cost details are outlined in Table 1-4.

    1 - 16

  • P00025

    2. REMEDIAL PLANS

    2.1 Introduction

    As part of the work to be performed under the assigned

    technical directive, E & E was tasked to investigate remedial

    options available to restore the Curtiss Street well field to

    a condition where the groundwater can be used as a source of

    drinking water for the Town of Southington. It is neither

    E & E's task to present detailed remedial plans nor to make

    any recommendations concerning the general concepts presented.

    The purpose of this report is rather to present a variety of

    possible pollution abatement methods in a modular form, giving

    "ball park" cost figures for each. Cost estimates have been

    derived from the best available sources and are meant to be

    used for comparison of various methods. An indepth

    hydrogeologic and engineering study is needed to arrive at

    actual project designs and costs. It should be noted that

    much of the work currently being done in hazardous waste

    remedial action is state-of-the-art. E & E has made an

    attempt to address all available options and to commjfent on

    those which seem to be most viable for use in the Curtiss

    Street wellfield.

    2 - 1

  • P00026

    Hydrologically, groundwater flow through the study area

    comes from both local and regional flow patterns and though

    infiltration of precipitation from the surface, the direction

    of flow being generally west to east at SRSNE's property.

    Since well water quality tests indicate that the highest

    levels of contamination are within the aquifer in the

    immediate vicinity of the old lagoons on SRSNE's property, it

    is reasonable to assume that continued groundwater flow

    through the area will result in a continuing plume of

    contamination off the property into the adjoining well field.

    These basic concepts are the basis of the remedial options

    presented in this section of E & E's report.

    2.2 Soil Removal

    The most direct method of pollution abatement is the

    physical removal of the grossly contaminated soil underlying

    the old lagoons. Test results reported by Warzyn" indicate

    organic contaminant levels as high as 70,000 parts per billion

    (PPB) at a depth of about 15 feet and over 30,000 PPB in the

    bedrock at about 20 feet. Since depth to bedrock appears to

    average about 20 feet, a vast amount of excavation would be

    required to remove the grossly contaminated overburden.

    E & E estimates that approximately one acre of land has been

    2 - 2

  • P00027

    contaminated by the "mounding" and subsequent downward

    movement of contaminants in and around the old lagoons.

    In this section of the report, the various available

    methods for removal, treatment and disposal of contaminated

    soil are presented with ballpark cost figures.

    2.2.1 Excavation and Backfill:

    At 4840 ydp£ per acre and a depth of seven yards, an

    estimated 34,000 cubic yards of material would need to

    be excavated to reach bedrock. Estimates for cost of

    excavation vary for different soil types and removal

    methods, but under normal conditions, costs range from

    $1.16 to $3.47 per cubic yard5. Under the best

    conditions, cost of excavation alone will be

    approximately $40,000. The cost of excavation will at

    least double* when excavation intersects the water

    table, and if dewatering the hole and stabilization of

    the sides of the hole with sheet piling is necessary,

    costs could run as high as $10-15/cu. yd^.

    Once the contaminated soil has been removed,

    suitable fill must be supplied to backfill the hole.

    Other peripheral costs include compaction, grading, and

    2 - 3

  • P00028

    resurfacing of the area, and the less tangible cost of

    disruption of SRSNE business.

    An additional consideration concerning excavation

    of hazardous wastes that must be addressed is the

    exposure of personnel, equipment, and the environment

    to the contaminants. Purchase and use of protective

    equipment, decontamination of equipment, and

    confinement of wastes to the site will all add to the

    cost. Further, for excavation below the water table,

    dewatering discharge must be disposed of properly.

    In order to generate a ball park cost estimate for

    excavation work at SRSNE, the following assumptions

    have been made:

    * Volume of excavated material is 34,000 cu.

    yds.

    * Volume of material below water table is 24,000

    cu. yds.

    * Cost of excavating material above water table

    is $1.16/cu. yd.

    2 - 4

  • P00029

    * Cost of excavating material below water table

    is $5.00/cu. yd. This does not include sheet

    piling, dewatering or any other necessary

    apurtances.

    * Approximate cost of excavation at SRSNE:

    (10,000 cu. yd.) ($1.16/cu.yd) + (24,000 cu.yd)

    ($5.00/cu.yd.) = $131,600.

    * Approximate cost of common borrow for backfill

    is $3.36/cu. yd.1: ($3.36) (40,000 cu. yd.)

    = $134,400.

    * Total excavation cost is: $131,600 + $134,400 =

    $266,000.

    2.2.2 Disposal of contaminated soil:

    Excavated soil must be disposed of in an acceptable

    manner. NumJ/erous methods have been investigated

    including reburial at a secure landfi l l , incineration,

    solidification, and encapsulation.

    2 - 5

    http:5.00/cu.ydhttp:1.16/cu.yd

  • Cost of disposing of wastes in a secure landfill

    range from $140/ton for very hazardous wastes to S85/ton

    for industrial sludges. Transporation cost can be on

    the same order of magnitude as disposal costs. Making

    certain assumptions, the following cost estimate for

    secure landfill disposal of the material excavated from

    SRSNE has been generated:

    * Volume of waste is approximately 34,000 cu.

    yds.

    * Average density of the waste is 1000 Ib/cu. yd.

    * Total weight of material to be dis/carded is:

    (34,000 cu. yd.) (1000 Ib./cu. yd) (1 ton/2000

    Ib) = 17,000 tons.

    * Assuming cost of $170/ton for transportation and

    disposal of industrial sludge, the cost of

    disposal of SRSNE material would be:- (17,000

    tons) $(170/ton) = $2.9 million.

    Additionally, the risks associated with excavation

    and transportation of contaminated soils to licensed a

    landfills includi; exposing equipment operators and the

    2 - 6

  • general public living along the route to hazardous

    waste. A report by the New York State Task Force on

    Hazardous Waste*' found that "excavation and

    transportation which results in reburial in a 'secure1

    landfill will not often warrant the risks."

    Incineration of exhumed soils can be performed on

    site using a portable rotary kiln. These kilns have

    the capability to dispose of solid, liquid, and gaseous

    wastes. Using EPA figures^, the following cost

    estimate can be derived:

    * Volume of waste is approximately 34,000 cu.

    yds.

    * Average density of the waste is 1,000 Ib./cu.

    yd.

    * Total quantity of waste to be incinerated is:

    (34,000 cu. yd) (1,000 Ib/cu. yd) (1 ton/2,000

    Ib.) * 17,000 tons.

    * Thruput of portable rotary kiln is 16

    tons/day.

    2 - 7

    ecology and environ

  • * Number of days to complete incineration is:

    (17,000 tons) (1 day/16 tons) = 1,062 days. At

    260 operating days per year, it would take 4.1

    years to process excavated material.

    * Assuming the maximum reported installed cost of

    $10,000 per ton per day: (16 ton/day)

    ($10,000/ton/day) = $160,000.

    * Assuming an annual maintenance cost of 10% of

    the installed cost: ($160,000) (0.10) =

    $16,000/year.

    * Total cost of method is installed cost plus

    maintenance cost: $160,000 + ($16,000/yr) (4.1

    yr.) - $225,600.

    Some costs not included in this estimate are for

    operation, disposal of incinerator residue and for

    final disposition of the incinerator after its

    application at SRSNE is completed.

    Other methods of disposal including solidification

    and encapsulation are state-of-the-art engineering

    practices which are both expensive and limited in their

    2 - 8

    ecology and enviro»«»»—•— '

  • P00033

    Application. E & E believes that these methods cannot

    be considered viable options for remedial work at

    SRSNE.

    2.3 Isolation from Groundwater:

    The New York Task Force on Hazardous Waste found that

    on-site containment "may be, at present, the only financially

    and technically practical alternative at many inactive

    sites^." This section of the report will consider several

    methods of containment and address their possible use at

    SRSNE.

    Groundwater recharge to a given area can come from the

    essentially horizontal flow of the regional and local flow

    patterns, from downwater percolating precipitation, and upward

    vertical flow from underlying strata.

    2.3.1 Capping and Bottom Seal:

    The capping of landfills, lagoons, etc. with

    impermeable material has long been used as an effective

    aid in reducing flow of water through contaminated

    soil. An impermeable layer above a disposal site will

    isolate that portion of the waste material which lies

    2 - 9

  • P00034

    above the water table from the leaching action of

    precipitation. Much of the SRSNE property is currently

    paved and, as such, is at least partially impermeable.

    Table 2-1, taken from a report entitled "Manual for

    Remedial Actions at Waste Disposal Sites" by J. R. 8.

    Associates, list comparable costs for various cover

    materials. Other estimates for capping material range

    from $14,0007acre for 6" of clay to $57,5007acre for 30

    mil PVC sheets^ . The function of an impermeable

    cap is to reduce inflow of groundwater to an area of

    known contaminants. It has no effect, however, on those

    contaminants already saturated with groundwater. In

    the case of the SRSNE property, the contaminant plume

    extends into the saturated portion of the aquifier,

    thereby necessitating further containment measures.

    A ballpark cost estimate can be generated for

    capping work at SRSNE by making some general

    assumptions:

    * Approximately one acre must be either newly

    capped or upgraded.

    * The method of capping will cost approximately

    2 - 1 0

  • P00035 TABLE 2 - 1

    ESTIMATED UNIT COSTS FDR SURFACE SEALING METHODS AND MATERIALS

    Cover Material and/or Method of Installation

    Top soil (sandy loam), hauling, spreading and grading (within 20 miles)

    Clay hauling, spreading and compaction

    Sand hauling

    spreading and compaction

    Cement concrete (4 to 6" layer), mixed, spread, compacted on-site

    Bituminous concrete (4 to 6" layer, including base layer)

    Lime or cement, mixed into 5" cover soil

    Bentonite, material only; 2" layer spread and compacted

    Sprayed asphalt membrane (1/4" layer and soil cover), installed

    PVC membrane (20 mil), installed

    Chlorinated PE membrane (20-30 mil), installed

    Elasticized polyolefin membrane, installed

    pHypalon membrane (30 mil), installed

    Neoprene membrane, installed

    Ethylene proplene rubber membrane, installed

    Butyl rubber membrane, installed

    Teflon-coated fiberglass (TFE) membrane (10 mil), installed

    Fly ash and/or sludge, spreading, rolling

    Unit Costs*

    $13/yd.:

    $8.50/yd

    $15/ydJ

    $8,000-10,000 acre

    $3-5/y(T

    $1.50-2.10/yd'i

    $1.40 yd2

    $1.50-2.50/yd/:

    $1.30-2.00/yd^

    $2,40-3.20/yd2

    $2.70-3.60/yd/

    $6.50/yd2

    $5.00/yd2

    $2.70-3.50/yd2

    $2.70-3.80/yd2

    $20/yd2

    $100-1.70/ydJ

    Source of Cost Information

    a New York Trucking Company (1980)

    a New York Trucking Company (1980)

    a New York Trucking Company (1980) Universal Linings, Inc. (1980)

    Tolman et al., 1979

    Tolman et al., 1979

    Tolman et al., 1979

    Lutton et al., 1979

    Lutton et al., 1979

    Lutton et al., 1979

    Lutton et al., 1979

    DuPont Elastomer Chemicals Dept. (1980)

    DuPont Elastomer Chemicals Dept. (1980)

    Lutton et al., 1979

    Lutton et al., 1979

    Lutton et al., 1979

    DuPont Elastomer Chemicals Dept. (1980)

    Tolman et al., 1979

    * NOTE: Different units for Volume (yd3) and surface area (yd2) costs

    Reproduced from JRB Report (Reference 5)

    2 - 11

  • F00036

    $3.00/yd.2.

    * The installed cost will be: (1 acre) (4840 sq.

    yd./acre) ($3.00/sq. yd) = $14,500.

    Wells on the SRSNE property reportedly show an

    upward vertical gradient at certain times of the year

    and exhibit characteristics of flowing artesian wells.

    A similar situation was noted in the Warzyn report at a

    Piezometer nest east of the SRSNE site. Indications

    are that the arkosic bedrock provides input to the

    local groundwater pattern. A bottom seal installed

    beneath the site would reduce the total flow exposed to

    the wastes. Two methods of installing bottom seals are

    currently in use: 1) Excavation and direct

    application, and 2) Injection. As noted previously,

    the cost of excavation is extremely high, poses a

    health hazard and, therefore, is probably not suitable

    to this site. Injection of material is accomplished by

    drilling a series of wells and forcing a grouting or

    slurry material into the wells at high pressure. The

    depth of the seal should be on the order of 4-6 feet

    and should be situated about 5 feet beneath the plume.

    Since tests indicate that the plume at SRSNE extends to

    and into bedrock the use of a bottom seal does not

    2 - 12

  • P00037

    appear to be a viable option. A further constraint

    would be the cost of installation with estimates

    running from $170,000-420,0007acre for a six foot depth

    in an aquifer of 20% void space*0. Since E & E,

    Inc. feels that a bottom seal is not a viable remedial

    option at SRSNE, a detailed cost estimate has not been

    generated.

    2.3.2 Slurry Walls, Grout curtains, and Sheet Piling:

    The majority of the contaminants present at SRSNE have

    been found at or near bedrock or an impervious layer

    and flow as a discrete plume alonglne interface"!

    Since the groundwater flow pattern is the major driving

    force of contaminants off the site, it follows that

    isolating the contaminated soil from the groundwater

    will reduce pollutant concentrations. Various

    impermeable barriers are available to divert

    groundwater flow, including slurry walls, grout

    curtains, and sheet piling. It must be noted that any

    man-made obstruction to groundwater flow is at best a

    delaying action. Though effective for years, leaks can

    be expected to develop.

    The purpose of impermeable barriers is to deflect

    2 - 13

  • flow around an area of high levels of contamination.

    Less contact with the pollutant results in lower

    concentrations in the water. A certain amount of

    geologic and soils data must be generated before the

    barrier is installed. Such variables as flow rates and

    directions, depth to bedrock, nature of soils, and

    constituents of the plume must be defined before

    construction can begin. Care must be taken during

    construction to prevent wastes from migrating off site

    by run-off or other methods.

    Slurry wall construction involves digging a trench

    through or under a slurry of clay, then backfilling and

    mixing the original soil with the slurry. Soil is

    excavated to bedrock or an impervious layer, thus

    forming a continuous wall as an obstruction to

    groundwater flow. By introducing the slurry while

    excavation is in progress, the bentonite acts as

    shoring to support walls and prevent cave-ins, also

    forming a filter cake along the trench walls and

    bottom. When the wall is in place, moisture moves into

    the slurry wall causing the 2:1 expanding lattice of

    the clay to swell and close the pore spaces. One point

    needing further investigation is the effect of organic

    solvents on the structure of the clay. Results of a

    2 - 14

    recycled paper ecoloev ttnA -—

  • study mentioned in the J.R.B. report showed that

    alcohol caused failure of the filter cake. The cost of

    a bentonite slurry trench varies with construction

    methods, distance from contractor, and size of the

    wall. For a 54 foot deep by 3 foot wide trench, costs

    will average $300-500/1inear foot*0.

    Grout curtains are similar to bottom seals in that

    they are injected under pressure into an aquifer to

    seal the interstices. After injection, the grouting

    material sets or gels to form an impermeable barrier.

    Grout curtains are particularly effective in porous or

    fractured rock where other methods of sealing are

    impractical. To install the curtain, a series of

    injection holes are drilled, often in parallel rows,

    whereupon the grout is forced into the pore spaces of

    the aquifer. Two main types of grout are currently

    used: 1) suspension grouts and 2) chemical grouts.

    Suspension Grouts are made up of finely divided

    particulate matter suspended in water. Typical

    suspension grouts are composed of Bentonite or Portland

    cement. Additives such as clays, sands, fly-ash, and

    chemical grouts are often used with Portland cement.

    Chemical grouts are usually composed of silicate or

    lignin based material although organic based grouts of

    2 - 1 5

  • P00040

    urea formaldehyde and acrylamlde are currently being

    used. If permeabilities of less than 10"̂ cm/sec

    are present, grouting is not effective . Grouting

    techniques require very specialized equipment and often

    cost three times as much as slurry trenches .

    Sheet piling is a series of interlocking plates of

    wood, concrete, or most frequently, steel which are

    driven into the ground with a pneumatic or stream

    driven pile driver. Various configurations, widths,

    and lengths are available. The full length of the wall

    is constructed and each plate is advanced, in turn, a

    few feet at a time to ensure a good lock between piles.

    Initially, sheet piling is quite permeable, but as fine

    soil material is washed against the wall it becomes

    relatively impermeable. A 1000 foot long by 20 foot

    deep, 5 gauge galvanized steel sheet would cost an

    estimated $290,OOO5.

    In order to generate ballpark costs, some

    assumptions must be made which are outlined below:

    (1) Slurry wall:

    * Dimensions of wall are 3 feet wide x 20 feet

    deep x 1000 feet long.

    2-16

  • P00041

    * From extrapolation of EPA data, cost of slurry

    wall 3 feet wide and 20 feet deep is $150 per

    linear foot.

    * Cost of wall is: ($150/ft.) (1,000 ft) =

    $150,000.

    (2} Grout curtain:

    * Cost is appriximately three times that of a

    slurry wall or $450,000.

    (3) Sheet piling:

    * Cost for 20 foot deep x 1000 foot long, 5 gauge

    galvanized steel sheet piling is $290,000.

    2.3.3 Diversion Wells:

    Diversion methods, previously mentioned have been by

    passive methods^ An active approach to diversion can be

    achieved in some cases by installing pumping wells

    around the perimeter of a waste disposal site. In

    theory, the wells are pumped to waste causing a

    lowering of the water table by the intersecting cones

    2 - 17

  • P00042

    of depression. The lowered water table prevents

    migration of wastes through the contaminated area. A

    pumping well barrier would probably not be effective in

    Southington for a number of reasons. Existing wells

    show at least a seasonal upward vertical gradient

    indicating groundwater movement into the contaminated

    zone from the arkosic bedrock in addition to the nearly

    horizontal regional flow. Contamination has been shown

    to exist all the way down to and into the bedrock, so

    upward gradients would continue to feed the plume.

    Also, since all of the saturated thickness is

    contaminated, 100% dewatering - an unlikely situation

    would be required to eliminate the plume. Development

    of the wells would entail surging and pumping to remove

    fines from around the casing and annulus, and water

    used in this process would become contaminated by

    existing pollution thus posing a disposal problem.

    Finally, the method itself is simply a delaying action

    since no attempt is made to remove the contaminants

    from the site.

    2.4 Localized Discharge Wells:

    Removal of pollutants from the aquifer by installing

    discharge wells in the vicinity of the contamination is an

    2 - 18

  • P00043

    effective method that might be implemented in Southington. By

    pumping a well at a sufficiently high discharge rate, a

    contaminant plume can theoretically be induced into the radius

    of influence of the well and subsequently be removed from the

    aquifer. The pumped water can be discharged untreated to a

    nearby water body, treated and discharged to a water body, or

    treated and injected back into the aquifer through a recharge

    well. In the Southinqton case, the nature and levels of

    contaminant preclude direct discharge into the environment.

    Treated discharge to a river would entail installation of

    piping to the river.

    The recharge of treated water to the aquifer provides a

    flushing action whereby a continuous flow of water through the

    lagoon area would remove contaminants by leaching. To refine

    the system even further, an impermeable boundary could be

    installed up gradient of the well system to prevent

    uncontaminated water from migrating unjter the, lagoon site and ̂~" " ^ --- '—" - ' --to form somewhat of a "closed system" for waste treatment. j>

    Various methods of well drilling and types of equipment are

    currently available lending to a high degree of flexibility of

    design and cost. Estimates from the J.R.B. report^ indicate

    cost of drilling to be about $2.5/inch/foot of well, $6.5/foot

    of casing (6 inch wells), $1175 per pump (4 inch submersible),

    and $46/linear foot for 8 inch piping. In considering

    2 - 19

  • P00044

    the hydraulics of the system, it should be noted that the

    recharge well must be larger than the discharge well to allow

    for reduced efficiency caused by fine particles and dissolved

    gases clogging the screen and annulus. Figure 2-1 shows a

    system incorporating the above suggestions into a composite

    plan. As the cone of influence expands, it induces the plume

    into the well from which it is pumped into a treatment

    facility and injected back into the aquifer upgradient of the

    old lagoons. Some flow from the upward gradient of the

    bedrock should help purge this as well. A reversal of the

    natural grounwater flow direction should occur initially,

    drawing part of the existing plume back into the treatment

    system.

    Methods of recharging an aquifier, other than by

    injection well, have been investigated. These include lagoons

    and water spreading, both of which have drawbacks in temperate

    climates where the problem of ice accumulation exists.

    Furthermore, rates of recharge are less and extensive

    maintenance is necessary to remove silt and other sediment

    which may accumulate and clog the pore spaces.

    The drawbacks of a discharge/recharge system include:

    1) Frequent monitoring to gauge changing plume

    characteristics,

    2-20

  • LU

    2 - 21

  • P00046

    2) High initial cost,

    3) Discharge water from well development will be

    contaminated and must be safely discarded.

    Of particular importance is the problem of disposing of

    development stages of the well drilling. A surging action is

    initiated in the well to draw fine material through the screen,

    These fines are then "blown" out of the casing with high

    pressure air. If fines are not removed, the abrasion they

    cause would destroy the vanes of the pump. The problem with

    pumping and surging is that under normal development

    procedures, waste water is simply discharged onto the ground.

    At SRSNE some provision will have to be made to prevent such

    wastes from migrating off site.

    A preliminary cost estimate can be prepared using J.R.B.^

    cost figures and certain assumptions:

    * Assume that discharge/recharge system flow rate is 100

    6PM

    * Assume 6" discharge well, 30 feet deep with single

    submersable pump.

    2-22

  • P00047

    * Assume 12" recharge well, 30 feet deep

    * Assume 500 feet of 8" piping required

    * Drilling costs are $2.5/in/ft. of well

    * Casing costs are: $6.5/ft. for 6" casing and $15/ft.

    for 12" casing

    * Piping costs are $46/linear foot for 8" pipe

    * Pump cost is $1,200.

    * Total cost can be generated as follows:

    1) Installed cost of wells $ 2,000.

    2) Installed pump cost 1,200.

    3) Installed piping cost 23,000.

    4) Pump test cost 2,000.

    5) Engineering/Misc. Costs 10,000.

    Total Cost $38,200.

    In conjunction with the installation of the slurry trench

    and wells, a treatment method must be selected and a facility

    2 - 23

  • P00048

    designed. The two methods of removing organic pollutants from

    groundwater which deserve some attention are aeration and

    carbon adsorption. While aeration has been shown to be

    effective in removing highly volatile organics such as

    trichloroethane from groundwater, its effectiveness in

    removing the many compounds detected under the SRSNE property

    has not yet been thoroughly investigated. E & E, Inc. feels

    that it is safe to say that since aeration is still in the

    development stage and, further, since the majority of the

    wastes discarded in the lagoons were low-volatility still

    bottoms, the aeration method could probably not be an effective

    treatment method at SRSNE. The possible use of aeration as a

    treatment method at well #6 and the general use of carbon

    adsorption will be addressed later in this report.

    Though more research will be required on its effectiveness

    under the conditions found in the groundwater at SRSNE,

    activated carbon adsorption appears to be a viable treatment

    method for removal of organic contamination.^ This treatment

    system can be placed in-line between the discharge and recharge

    wells previously discussed. Since it can be predicted that

    this system must be operated for many years before flushing of

    the lagoon area is complete, E & E, Inc. believes that SRSNE

    would probably choose to purchase all equipment and operate it

    through its own staff (Equipment leasing and

    2-24

  • P00049

    operating contracts are presently available through companies

    such as Calgon Corporation^). A question that must be

    answered before a carbon treatment system is installed is; how

    will the spent carbon be handled? There are at least three

    options:

    * Discard spent carbon and purchase fresh material.

    Disposing of hazardous material may pose a formidable

    problem.

    * Construct a carbon regeneration facility on-site. The

    capital cost of such a system is great. The small

    amount of spent carbon generated may not justify the

    expense.

    * Find a regeneration contractor who will make periodic

    pickups and deliveries. This option seems most viable

    for SRSNE. Locating a certified firm may be

    difficult.

    The treatment system will probably consist of two

    pressurized contactors, piping, valving, and instrumentation.

    For winterizing, the entire system must be enclosed. In order

    to generate a cost estimate for a carbon treatment system, the

    following assumptions were made:

    * Design flow rate is 100 GPM

    2 - 25

  • POOOSO

    * Two pressurized downflow contactors with a design

    working pressure of 50 psi are required. Vessels used

    are 10 Ft. diameter and 14 ft high.

    * A complete carbon system requires cylinder-operated

    valves, liquid and carbon handling piping,

    instrumentation and totally enclosed building.

    * Bed depth in each contactor is 5 feet, bed area is 78

    ft̂ . Total contact time is 30 minutes in each

    contactor (conservative design).

    * From EPA document; "Estimating Water Treastment

    Costs13" (EPA - 600/2/79-162 b), p. 300, the

    installed cost of a complete two-vessel carbon system

    is approximately $144,000.

    * Operating and mainetnance costs will run about $27,000

    per year. From the previously cited EPA report;

    "Energy requirements are for backwash pumping, for

    pumping of spent carbon to regeneration facilities, and

    for return of regenerated carbon . . . energy for

    supply pumping to contactors is not included. Building

    energy requirements are for heating, lighting,

    ventilating, instrumentation, and other general

    2-26

  • P00051

    building purposes. It was assumed that the contactors

    are completely housed. Maintenance material costs

    reflect estimated annual requirements for general

    supplies, pumps, instrumentation repair, valve

    replacement or repair, and other miscellaneous work

    items."

    * Assume that new carbon is purchased every six months/

    when system is saturated. Also assume that cost of

    disposal of spent carbon is insignificant relative to

    cost of fresh material. Assume 1570 ft3 of carbon is

    purchased every year. At an apparent density of 27

    lb/ft3: (1570 ft.3/yr.) (27 lb./ft.3) = 42,400

    Ib/yr.

    * Assume that the cost of fresh activated carbon is

    85^/lb. The annual cost for carbon is: (42,400

    Ib./yr.) ($0.85/lb.) = $36,000/yr.

    2.5 Pumping Town Well No. 6

    A remedial measure which could be used in conjunction with

    other schemes, is to pump well No. 6 in hopes of accelerating

    the natural purging of the aquifer. Pumping the well will lower

    the water level at the well and increase the gradient of the

    piezomeric surface, thereby increasing flow velocities. The

    Warzyn Report6 estimated transmissivities at 150,000 - 200,000

    2 - 27

  • P00052

    GPD/ft., formational permeabilities of 10'* to 10"̂

    CM/SEC., and groundwater flow velocities of 2.3 to 0.23

    feet/day. For the time it would take groundwater to flow from

    the vicinity of SRSNE to production well No. 6 estimates range

    from 1.4 to 14 years. Pumping of both Well No. 6 and Well No. 4

    could significantly reduce this transit time since pumping well

    No. 4 would eliminate recharge to Well No. 6 from the south,

    causing the cone of influence to shift northerly towards SRSNE.

    Before a more accurate estimate for the number of years can be

    made, more extensive hydrogeologic and soils investigations will

    be needed. The heteorgenous nature of glacial outwash deposits

    makes it difficult to estimate formational permeabilities.

    Furthermore, Well 4 and 6 have not been pumped together. Any

    estimate of the composite effects is speculation.

    It should be noted that pumping Well No. 6 to waste

    involves discharge of polluted water to a river, so that a

    discharge permit will be required. Conecticut D.E.P. was

    contacted in order to determine the extent of the permit

    requirements. Paul Marin stated the two permits would be

    required, both NPDES and state. He also felt that obtaining

    both permits would not be difficult since Southington Production

    Well No. 4 had been previously pumped to waste under similar

    constraints*4.

    2.6 Summary;

    A variety of possible remedial action plans have been

    presented in this report, but the list is by no means limited to

    measures described herein. Recently national coverage of the

    2 - 28

  • P00053

    hazardous waste problem has resulted in increased work in

    research and design of viable clean-up methods. However, the

    implementation of remedial actions is still in its infancy and

    most methods are considered state-of-the-art. Such things as

    barrier walls have been used extensively in the construction

    f what effect organic pollutants

    "vill hav^_j^--tiigT_r_structural JuLê Ê -ty. Treatment of discharge

    for removal or the organics is a new science and research is

    necessary on a site by site basis to design the proper system

    for removal of the site specific pollutants. In-depth

    hydrogeologic work is essential to determine the parameters by

    which a discharge/recharge well system is to be designed or to

    ascertain the economic feasibility of pumping Well No. 6 to

    purge the aquifer.

    Some examples of additional information needed are:

    1) Delineation of the direction and extent of plume

    migration,

    2) Determination of permeabilities, transmissivities, and

    groundwater velocities within the aquifer,

    3) Effects on plume migration if Wells No. 4 and No. 6 are

    2 - 29

  • P00054

    pumped simultaneously,

    4) Effects of upward vertical gradients exhibited near

    SRSNE, and

    5) Extent of offsite dumping of contaminants within the

    aquifer boundaries.

    It would appear that a combination of methods is best

    .fnr_thp Southington site. A-nidjor'toriJiLrdlnl.,1

    is high cost of implementing such

    Frig feasibility study is needed to design the most

    efficient and economical system for the site.

    The costs generated in this section are summarized in Table

    2-2.

    2 - 30

  • P00055

    TABLE 2 - 2

    Summary of Remedial Plans and Estimated Costs for Curtiss Street Well Field

    ITEM

    1. Excavation a) Excavation & Backfill b) Backfill

    Disposal of a) Landfill disposal Contaminated Soil b) Incineration

    Isolation from a) Capping Groundwater b) Bottom Seal

    c) Slurry Wall d) Grout Curtain e) Sheet Pi ling f) Diversion Wells

    Localized a) Discharge/Recharge wells Discharge Wells b) Carbon Treatment

    Pumping Town Well No. 6

    (1) N/A = Not Applicable (2) NE = Not Estimated for this Study

    2 - 31

    Installed Cost (thousands of dollars}

    132 134

    2900 160

    14.5 NE(2) 150 450 290 NE

    38.2 144

    N/A

    Operating/ Maintenance Costs

    (thousands of dol lars per year)

    N/A1

    N/A

    N/A 16

    N/A N/A N/A N/A N/A NE

    NE 63

    NE

  • P00056

    2.7 References

    1. Building Construction Cost Data 1980, Robert Snow Means Company, Inc. Kingston, MA (1979) p. 17-25

    2. Campbell, M. D., J. H. Lehr, Water Well Technology, McGrawHill Book Company, New York, NY (1973) p. 681

    3. Ginsberg, W. R. "Hearings On: Inactive Hazardous Waste Disposal Sites and the Report of the Interagency Task Force on Hazardoud Wastes", State of New York Department of Environmental Conservation (October 1979) p. 97

    4. Love, 0. T. Jr. "Treatment for the Control of Trichloroethylene and Related Industrial Solvents in Drinking Water" U.S. EPA, Cincinnati, Ohio (August 1980)

    5. "Manual for Remedial Actions at Waste Disposal Sites", JRB Associates, Inc, McLean, VA (June 1980)

    6. Preliminary Draft "Hydrogeologic Investigation EPA/JRB Associates, Town of Southington, Connecticut", Warzyn Engineering, Inc., Madison, WI (June 1980)

    7. "Procedures Manual for Groundwater Monitoring at Solid Waste Disposal Facilities", Environmental Protection Agency. EPA/530/SW-611 (August 1977) p. 270

    8. Nebolsine Kohlman Ruggiero Engineers, P. C., "Removal of Organic Contaminants from Drinking Water Supply at Glen Cove, NY", Interim Report on U.S. EPA Agreement No. CR806355-01, Office of Research and Development, MERL, Drinking Water Research Division, Cincinnati, OH (May 1980)

    9. TODD, D. K. Ground Water Hydrology, John Wiley & Sons, Inc., New York, NY (1959) p. 251-272

    10. Tolman, "Guidance Manual for Minimizing Pollution from Waste Disposal Sites", U.S. EPA 600/2-78-142

    2 -32

  • P00057

    11. Crail, J. D., "Dealing With Hazardous Dissolved Organic Compounds in Groundwater, Lagoons or Spills", Calgon Environmental Systems Division, Calgon Corporation, Pittsburg, PA. (1978)

    12. Patterson, J. H., Technical Sales Representative, Activasted Carbon Division, Calgon Corporation, Personal Communication (October 27, 1980)

    13. Gumerman, et. al., "Estimating Water Treatment Costs, Volume 2, Cost Curves Applicable to 1 to 200 mgd Treatment Plants," Culp/Wesner/Culp Consulting Engineers, EPA-600/2-79-162b, (August 1979)

    14. Marin, P., Connecticut Department of Environmental Protection, Personal Communication (October 28, 1980)

    15. Lutton, R.; Regan, G.; Jones, L, "Design and Construction of Covers for Solid Waste Landfills." Cincinnati, OH.: Municipal Environmental Research Laboratory, ORD, EPA-600/2-79-165 (1979)

    2 -33

  • P00058

    3. WATER SUPPLY PLANS

    3.1 Introduction/Background

    The Town of Southington has had a public water system

    since the early 1880's when the Water Company constructed a

    supply from Humiston Brook. Since that time, as demands

    increased and loss of water supplies resulted from

    contamination of various groundwater resources, the town has

    been faced with the immenent problem of augmenting a depleted

    water supply. Under TDD No. F1-8007-01A, E & E, Inc. has been

    tasked to investigate methods that can be implemented to

    replace the supply of water lost due to the closing of

    Production Well No. 6 which has a rated capacity of 1000

    gallons per minute (GPM) or 1.44 million gallons per day

    (MSD).

    Presently the population demands between 3.6 to 3.8 MGD.

    During peak usage hours, the demand is 6.2 MGD. . Currently

    the town is supplied water from three different sources. A

    discussion of these sources follows:

    (a) Groundwater Sources: The ground water supply

    consisted of six gravel packed wells until the shut-down

    3 - 1

  • P00059

    of Production Wells Nos. 4, 5, and 6 due to the discovery of

    unacceptable levels of chemical contaminants. Two new wells,

    Numbers 7 and 8, were recently completed in the southeastern

    section of town and are expected to yield 1000 6PM each. Well

    No. 8 is expected to be in production by October 1980. Wells

    No. 1, 2, and 3 currently supply 550 gallons per minute.

    Total daily yeild from groundwater supplies is 5.3 MGD.

    (b) Existing Surface Supplies: Southington's surface

    supply consists of three reservoirs located in the southwest

    section of town. The reservoirs have a combined storage

    capacity of 157.7 million gallons (MG). The safe yield of

    these sources, defined as the maximum dependable draft that

    can be made continuously on a water supply during an extended

    drought, has been estimated to be 1.0 MGD. During this past

    summer (June-September 1980), the reservoirs were used for

    water supply due to the inadequacy of the existing wells to

    supply enough water during drought conditions. The use of

    these reservoirs was curtailed at the end of September 1980.

    (c) Lease of Well From City of New Britain: Presently

    the Town of Southington is augmenting their water supply with

    water leased from a New Britain Water Department well which is

    located with-in Southington town boundaries. The lease

    agreement calls for a one year period of usage with two,

    3 - 2

  • F00060

    six month extensions. The first extension has already been

    exercised. The cost of the lease is $1,000 per month.

    An initial cost of $6,000 was expended for piping to connect

    to the existing Southington water supply.

    Current potential yield from all three sources is 6.2

    MGD. This assures full utilization of all sources, an

    infeasible condition due to fluctuations in groundwater and

    surface water capacities caused by variables such as climatic

    changes and aquifer recharge characteristics. Further,

    provisions for population increases are not taken into

    account.

    Future water demand is based upon anticipated domestic

    and non-domestic demands. Southington has experienced a

    faster growth rate between 1940 and 1970 than the State of

    Connecticut, Hartford County, and any of the adjoining towns.

    Attractive, developable, residential land, and the proximity

    of the town to Hartford and New Haven are two reasons why the

    area has experienced rapid growth. According to a report by

    Camp, Dresser, and McKee* of February 24, 1977, the town

    will reach a saturation population of 68,000 in the year 2000.

    This means that the present water system capacity will not

    be adequate to supply domestic and non-domestic needs. Total

    estimated use for the entire town in the year 2000 is

    3 - 3

  • F00061

    summarized as follows.

    Use Consumption (mgd)

    Domestic 4.17

    Non-domestic 1.74

    Unaccounted for 1.05

    (Leakage, Fire Fighting etc.)

    Total Average Day 6.96

    Total Maximum Day 11.83

    Total Peak Hour 18.79

    One will note that projected demands for the year 2000

    are above the current supply capacity of the water system.

    Therefore, new water resources will have to be developed to

    meet the needs of the town. In the following sections of this

    report E & E, Inc. presents some of the possible measures

    that can be, and/or are being undertaken to meet future

    demands.

    3.2 Development of a New Production Well

    Geraghty and Miller recently completed a groundwater

    3 - 4

  • P00062

    availability assessment for the town resulting in the

    discovery of 20 sites that are favorable for drilling

    production wells. To date two new production Wells, Nos. 7

    and 8, have been developed in the southeastern section of

    town. Both wells are scheduled to be put on-line in October,

    19802.

    Based upon the recent construction of Wells Nos. 7 and 8,

    cost estimates can be projected to cover further development

    of groundwater resources. The following costs do not take

    into account the initial cost of hydrogeologic studies.

    Previous expenditures for such studies have been in the

    vicinity of $200,000. Development costs for a 1000 GPM well

    to replace No. 6 are as follows:

    * Costs for two, 1000 GPM wells in Southington:

    1) Pumps and Building construction $ 260,000

    2) Acquisition of Land 80,000

    3) Pipeline to present water system 50,000

    4) Cost of Drilling Wells 45,000

    (Labor, Materials, etc.)

    5) Final hydrogeologic testing and

    exploration 40,000

    Total $ 475,000

    3 - 5

  • P00063

    * Cost of one, 1000 GPM production well to replace No. 6

    is approximately $238,000.

    * A ballpark estimate for operating and maintenance cost

    is $10,000/year3.

    According to Daniel Christy, Superintendent of

    Southington's Water Works Department, further development of

    groundwater resources seems to be the most economical approach

    to solving Southington's water problems^. Since the most

    expensive part of development (hydrogeologic studies) have

    been completed, all that remains is to place wells in the most

    desirable locations.

    3.3 Utilization of Southington Reservoirs

    The general quality of Southington's reservoir supply is

    within recommended Federal and State limits. However during

    spring and fall overturn of the lakes (due to changes in the

    density of surface and bottom water), color, odor, and

    turbidity exceed or approach the limits. If the reservoirs

    are to be used as a permanent water supply, water treatment

    would be required to conform with the Federal Safe Drinking

    Water Act and the State of Connecticut Public Health Code

    regulations "Standards for Quality of Drinking Water" (Section

    19-13-B102). Construction of a treatment plant would have to

    3 - 6

  • P00064

    to be completed by December 31, 1980 in order to conform to

    these regulations. According to the Camp, Dresser and McKee

    report of 1977 the following treatment processes would

    probably be required:

    * Coagulation and Flocculation for a period of 20 to 30

    minutes

    * Intermediate sedimentation, followed by filtration using

    dual media filters.

    * Chemical treatment using

    1) Alum, ferric sulfates or polymers for coagulation

    2) Lime or caustic soda for pH adjustment

    3) Chlorine for disinfection

    4) Potassium permanganate for manganese removal

    5) Activated carbon for taste and odor control

    Based on 1977 estimates, the construction, annual

    operation and maintenance costs, and the acquisition of

    3 - 7

  • P00065

    surrounding watershed land for the protection of the

    reservoirs would be as follows:

    * The installed cost of a 1.6 MGD treatment plant is

    $1,063,000. Prorated for 1.44 MGD (loss of Production

    Well No. 6), the cost is $957,000.

    * Operating and maintenance cost for the 1.6 MGD plant and

    watershed are $321,000. Prorated for 1.44 MGD, the cost

    is $289,000.

    Dan Christy stated that the town would rather not pursue

    the usage of reservoir water because of the obvious large

    capital expenditure. Compared with the costs of groundwater

    development, it is more economical for the town to continue

    developing groundwater resources.

    3.4 Development of Storage Facilities

    In order to alleviate peak demands on the water system

    during certain hours, one alternative that has been suggested

    is the use of some sort of storage facility from which water

    can be pumped during high demand hours and into which water

    can be replenished during low demand periods. Currently the

    town uses Reservoir No. 1 (2.5 mg capacity), along with the

    3 - 8

  • P00066

    Mill Street standpipes (2.2 mg capacity) as storage areas.

    Total volume of storage is 4.7 mg. Realistically, the total

    active volume of the Mill Street standpipes is only about 1.0

    mg due to inadequate pressures developed in areas adjacent to

    the standpipes and near the extremities of the distribution

    system, when the water level reaches mid-depth in the tanks.

    Since Reservoir No. 1 has been isolated (as of the end of

    August 1980) from the water distribution system, the Mill

    Street standpipes serve as the only storage facilities in the

    town.

    Presently the total volume of storage required to satisfy

    hourly fluctuations is 3.1 mg. Projection to the year 2000

    produces a need for 3.9 mg. Therefore, without the use of

    Reservoir No. 1 as a storage facility, the town has

    insufficient storage.

    In order to realize the use of Reservoir No. 1 as a

    storage facility, a one million dollar treatment plant would

    have to be built, operated and maintained as discussed

    previously. The cost of construction for a storage facility

    with the recommended capacity of 2.3 mg is $993,000. This is

    based on a 1977 estimate by Camp, Dresser, and McKee for a

    prestressed concrete storage tank, or a steel standpipe.

    3 - 9

  • F00067

    If additional groundwater resources prove to be

    available, it is more economical for the town to proceed with

    such development than to construct treatment facilities to

    utilize the existing reservoir for storage or to construct new

    storage facilities.

    3.5 Purchase Water

    To supplement their depleted water supply due to the

    shut-down of Wells Nos. 4, 5 and 6, the town is currently

    purchasing water from the City of New Britain which owns a

    well on Southington town property. Conditions of the lease

    call for a one year rental with two, six month extensions.

    Another possible source of rental water is from the City

    of New Haven, which owns a well field in the Town of Cheshire,

    just south of Southington. However, these wells have also

    started to show traces of solvent contamination, so their

    future usage is not assured.

    Costs for purchasing water can be generated as follows:

    * Assume lease arrangement investigated by Southington

    Water Department will provide for amount of water lost

    due to closing of Production Well No. 6.

    3 - 10

  • F00068

    * Capital cost of piping to connect to water system is

    $6,000.

    * Cost of treatment is not included.

    * Cost of water is similar to arrangements made by Town of

    Bedford, Massachusetts which has three contracts to buy

    water at $530/million gallons, $600/million gallons and

    $700/million gallons4. Assume average value of

    $600/million gallons:

    (1.44 MGD) ($600/M6) = $864/day = $25,920/mo = $315,400/year

    3.6 On-site Treatment of Production Well No. 6:

    One method that can be employed to restore the supply of

    drinking water lost due to groundwater contamination of the

    Curtis Street well field is on-site treatment of the dicharge

    from Production Well No. 6. The two techniques that are now

    being most thoroughly investigated for organic removal are

    aeration and adsorption. This section of E & E, Inc.'s report

    outlines current opinion on the effectiveness of these

    techniques.

    3 -11

  • P0006S

    Table 3-1 outlines the analytical results generated during a

    study of the contamination problem by Warzyn Engineering

    Company5. In general, the chemicals found in Production Well

    No. 6 are widely used solvents in industries and households.

    EPA is currently reviewing most of these compounds for possible

    inclusion in the National Interim Primary Drinking Water

    Regulations. The single compound found in Well No. 6, not

    included, is 1, 1 Dichloroethane.

    TABLE 3 - 1

    Chemical Analysis of Organic Compounds Found in Southington

    Production Well No. 6 during Warzyn Study5

    Concentration of Chemical in PW No. 6

    Chemical by Analytical Lab (ppb)

    ERCO EPA

    1.1 Dichloroethane 8.3 7.6 4

    1.2 Dichloroethane 0.1 0.1 ND

    1,1,1 Trichloroethane 63 53 30

    Trichloroethylene 0.5 0.5 1

    Tetrachloroethylene 0.1 0.1 ND

    3-12

  • P00070

    3.6.1 Aeration:

    Aeriation is a treatment method that has recently been

    receiving considerable attention. Briefly, the process

    consists of routing the contaminated well water

    countercurrent to diffused air in an enclosed column.

    The well water is pumped through the column in a

    downflow configuration with the column being typically

    designed for a storage capacity of more than ten

    minutes. Air from a blower is introduced to the bottom

    of the column through a diffuser system at an air to

    water ratio ranging typically from 4:1 to 30:1.

    A major consideration in evaluating aeration for

    Production Well No. 6 is that there are no full-scale

    aeration plants for well water organic contaminant

    removal in operation. Therefore, the application in

    Southington would be research oriented.

    In fact, EPA is now considering the installation of

    a full-scale aeration plant on Southington Production

    Well No. 4. To date, the program has not progressed

    beyond the funding phase and preliminary engineering has

    not been conducted^. Much of the research on aeration

    has been conducted by EPA's Municipal Environmental

    3-13

  • P00071

    Research Laboratory, Drinking Water Research Division

    (USEPA-DWRD) using pilot scale equipment. Also, a

    consulting firm, NKRE, has evaluated the method on a

    pilot scale at a well site on Long Island, New York.

    Looking at 1, 1, 1 Trichloroethane, the major

    contaminant in Production Well No. 6, NKRE observed a 66

    to 85 percent reduction in concentrations (influent

    concentrations of 3 to 7 ppb) with air-to-water ratios

    ranging from 5:1 to 30:1. The diffused-air aerator used

    by the UEPA-DWRD at its pilot facility in New Jersey has

    consistently shown approximately 90 percent removal of

    1, 1, 1-trichloroethane ( in f luen t concentration range of

    170 to 280 ppb) at a 4:1 air-to-water ratio. Similar

    results were obtained for other organic compounds.

    Table 3-2 is a summary of those results^. It appears

    that diffused aeration can be a successful means of

    lowering the concentration of the applicable

    contaminants in the drinking water from Production Wel l

    No. 6. The major liability of the method is the lack of

    full-scale plant data.

    3-14

  • FOGG?; Some cost data has been generated in a study for

    which a final report has not been published'7. These

    costs are presented below:

    * Capital costs based on a 1 MGD plant

    1) /Aeration Storage Tank $ 45,000

    2) Air Compressors 62,000

    3) Air Piping 37,000

    4) Control Bu i ld ing 32,000

    5) Electrical and Instrumentation 12,000

    6) Miscellaneous 10,000

    Total $198,000

    * Capital cost prorated for a 1.44 MGD plant (1000

    GPM Production Wel l No. 6) is:

    ($198,000) (1.44) = $285,000

    * Annual operating and maintenance cost for a 1 MGD

    plant, based on an energy cost of $0.09/kwh are:

    1) Energy $ 44,000

    2) Maintenance 3,500

    3) Operation 20,000

    4) Quality Control 9,000

    Total $ 76,500

    * Annual 0 & M costs prorated for a 1.44 MGD plant

    are: ($76,500J (1.44) = $110,200

    3 - 1 5

  • P00073

    TABLE 3 - 2

    Organic Removal Efficiencies for Pilot Scale Diffused-Air Aeration Plants 6

    Highest Removal Efficiency for Chemical Each Study (%)

    USEPA-DWRD Pilot NKRE Pilot Plant in N.J. Plant on L.I.

    1,2 Dichloroethane NS NS

    1,1,1 Trichloroethane >90(170-280)* 66-85(3-7)

    Trichloroethylene >80(3.3) 69-90(132-313)

    Tetrachloroethylene 95 75-95

    * Values in parenthesis represent influent contaminant concentration in ppb.

    NS - not studied

    3 - 16

  • P00074

    3.6.2 Carbon Adsorption:

    These are two major adsorption systems receiving

    attention. One system employs very specific and very

    expensive exchange resins such as those developed by

    Rohm and Haas. These resins have proven to be very

    effective for the chemicals identified in the drinking

    water from Production Well No.6. However, the cost of

    the resin is too high to justify its application when

    compared to the other adsorption system, activated

    carbon. Also, it seems that specific resins are

    effective for specific chemicals, but no one resin is

    good for all chemcials.

    Basically, a carbon adsorption treatment system for

    this application would consist of more than one granular

    activated carbon bed piped into the discharge from

    Production Well No. 6. More engineering work will be

    required to select from the various alternatives

    available such as 1) downflow or upflow through the

    carbon bed, 2) series or parallel operation, 3) pressure

    or gravity operation in downflow contactors, 4) packed

    or expanded bed in upflow contactors, and 5) materials

    of contruction and configuration of carbon vessel (sj.

    For well water application, a typical installation would

    3 - 17

  • P00075

    consist of two lined steel tanks, each with a packed

    carbon bed, operated in series in the downflow mode.

    An example of an activated carbon system now in

    service at a town production well is the treatment

    system on Woodbury, Connecticut Well No. 2̂ . The well

    operates at 125 GPM and is contaminated with about 140

    ppb 1, 1, 1, trichloroethane and lesser amounts of

    trichloroethylene and tetrachloroethylene. The basis of

    the treatment system is three converted softening units.

    Generally, two units operate in series while the third,

    as a standby, is put on line when a spent carbon bed is

    being changed. Each tank contains 60 cubic feet of

    activated carbon and the total retention time of two

    tanks in series is 7.5 minutes. Though little data has

    been generated to date due to mechanical problems, Mr.

    Kevin Moran of the General Waterworks of the Northeast

    Region stated that nearly complete removel of organics /•̂ 5

    was accomplished during proper operation. Calgon Carbon

    Service, which supplies the activated carbon, estimates

    that the life of a bed is from six months to one year.

    Most studies show that nearly 100 percent removal

    of the organic compounds in question can be effected

    with the proper design of an activated carbon system^.

    3-18

  • P00076

    However, some very important factors that must be

    evaluated before a treatment system can be installed

    are:

    * Length of service to breakthrough or contaminant

    loading for the components in question on activated

    carbon.

    * The desired or legally required effluent

    concentrations and thus the retention time.

    * Water characteristics, in particular, suspended

    solids content. (May require pre-filters)

    * The disposal method for spent carbon.

    There are two major financing routes that can be

    followed when installing an activated carbon treatment

    system on Production Well No. 6. First, a turnkey

    system can be leased from a service company such as

    Calgon Corporation. As part of the contract, the

    service company will design, build, operate, and

    maintain the treatment plant including disposal and/or

    regeneration of spent carbon. A representative of

    Calgon Corporation stated that the cost of such a system

    3 - 19

  • P00077

    would be about $500 per million gallons treated^.

    Since Production Well No. 6 is 1.44 MGD, the cost would

    be about $21,600 per month or about $236,000 per year.

    In order to generate a cost estimate for the

    purchase of a carbon system, the following assumptions

    were made:

    * Design flow rate is 1,000 GPM (1.44 MGD)

    * Treatment system consists of two pressurized

    downflow contactors with a design working pressure

    of 50 psi. Vessels are 12 feet in diameter. Total

    contact area is 113 ft.2.

    * Required detention time in carbon bed is 20

    minutes. Therefore, total bed length is: (1000 GPM)

    (1 ft.3/7.48 gal.) (20 min.) (1/113 ft.2) = 24

    ft. Each vessel will have 12 feet of bed.

    * Total bed volume is 2712ft.3.

    * From EPA document; "Estimating Water Treatment

    Costs" (EPA-600/2-79-162b), p. 302,3 the

    installed cost of a complete two-vessel carbon

    3 - 2 0

    http:ft.3/7.48

  • P00078

    system similar to that described above is

    $237,000.

    * Operating and maintenance costs, exclusive of

    carbon replacement/regeneration, is about $27,000

    per year. The major cost is for building heating,

    lighting, ventilating, instrumentation and other

    general building requirements.

    * Assume that new carbon is purchased when system is

    saturated (most conservative approach). Also

    assume that the cost of disposal of spent carbon is

    insignificant relative to the cost of fresh

    material. Assume that total volume of carbon is

    replaced each year, (2712 ft3). At an apparent

    density of 27 lb/ft3:

    (2712 ft3/yr.) (27 lb/ft.3) = 73,200 Ib/yr.

    * Assume that the cost of fresh activated carbon is

    85

  • P00073

    3.7 Summary:

    Table 3-3 is a summary of the water supply options and

    associated costs. The most cost-effective alternative that the

    Town of Southington can pursue to alleviate water supply

    problems appears to be groundwater resource development. In

    conversation with Dan Christy, he stated that the town is

    leaning away from reservoir usage due to the high cost involved

    with building a treatment plant. He places more confidence in

    the development of new well fields, since the recent

    hydrogeologic studies have point