11
1| WOO/LUC-75-30.70/0.00 PID 93592 MATCHMAKER EVENT ODOT PROJECT 190108 Michael Stormer, P.E., Project Manager Layth Istefan, P.E., District Construction Engineer Lisa Washington, Northwest Regional Outreach Manager Mike Gramza, P.E., Capital Programs Administrator PID 93592 WOO/LUC-75-30.70/0.00 - ODOT District 2

WOO/LUC-75-30.70/0.00 PID 93592 01 1… · o 47,000 SY of Cement Stabilization o 5,500 FT of Curb o 9,000 FT of Single-Slope Concrete Barrier o 8,400,000 LB Reinforcing Steel. 8 |

  • Upload
    others

  • View
    5

  • Download
    0

Embed Size (px)

Citation preview

Page 1: WOO/LUC-75-30.70/0.00 PID 93592 01 1… · o 47,000 SY of Cement Stabilization o 5,500 FT of Curb o 9,000 FT of Single-Slope Concrete Barrier o 8,400,000 LB Reinforcing Steel. 8 |

1 |

WOO/LUC-75-30.70/0.00

PID 93592MATCHMAKER EVENT

ODOT PROJECT 190108Michael Stormer, P.E., Project Manager

Layth Istefan, P.E., District Construction Engineer

Lisa Washington, Northwest Regional Outreach Manager

Mike Gramza, P.E., Capital Programs Administrator

PID 93592 WOO/LUC-75-30.70/0.00 - ODOT District 2

Page 2: WOO/LUC-75-30.70/0.00 PID 93592 01 1… · o 47,000 SY of Cement Stabilization o 5,500 FT of Curb o 9,000 FT of Single-Slope Concrete Barrier o 8,400,000 LB Reinforcing Steel. 8 |

2 |

WOO/LUC-75-30.70/0.00

PID 93592

PROJECT 180277

KEY PROJECT DATES

• Project Sale - February 21, 2019

• Project Award - March 11, 2019

• Estimated Completion Date - July 31, 2023

PID 93592 WOO/LUC-75-30.70/0.00 - ODOT District 2

Page 3: WOO/LUC-75-30.70/0.00 PID 93592 01 1… · o 47,000 SY of Cement Stabilization o 5,500 FT of Curb o 9,000 FT of Single-Slope Concrete Barrier o 8,400,000 LB Reinforcing Steel. 8 |

3 |

PROJECT OVERVIEW – SOUTH END

PID 93592 WOO/LUC-75-30.70/0.00 - ODOT District 2

Page 4: WOO/LUC-75-30.70/0.00 PID 93592 01 1… · o 47,000 SY of Cement Stabilization o 5,500 FT of Curb o 9,000 FT of Single-Slope Concrete Barrier o 8,400,000 LB Reinforcing Steel. 8 |

4 |

PROJECT OVERVIEW – NORTH END

PID 93592 WOO/LUC-75-30.70/0.00 - ODOT District 2

Page 5: WOO/LUC-75-30.70/0.00 PID 93592 01 1… · o 47,000 SY of Cement Stabilization o 5,500 FT of Curb o 9,000 FT of Single-Slope Concrete Barrier o 8,400,000 LB Reinforcing Steel. 8 |

5 |

MAJOR WORK ON PROJECTo Section 1 – South of Wales Road:

o Widening sub-standard shoulders and replacing deteriorating pavement.

o No change to the existing right-of-way or IR-75 centerline alignment.

o Section 2 – North of Wales Road:

o Correct deficient northbound sight distance and ramp deficiencies at Miami Street and South Avenue.

o Correct horizontal sight distance on IR-75 mainline north of Wales Rd.

o Correct railroad clearance, poor deck conditions and maintenance issues with Maumee River/Norfolk-

Southern Railroad/ South Ave Bridge.

o The above changes will require new road alignments.

o Right-of-way will be required near the South Ave and Miami Street interchanges

PID 93592 WOO/LUC-75-30.70/0.00 - ODOT District 2

Page 6: WOO/LUC-75-30.70/0.00 PID 93592 01 1… · o 47,000 SY of Cement Stabilization o 5,500 FT of Curb o 9,000 FT of Single-Slope Concrete Barrier o 8,400,000 LB Reinforcing Steel. 8 |

6 |

MAJOR WORK ON PROJECTo Construction Specifics

o Building of a more gradual curve of IR-75 between Wales Road and Miami Street.

o The IR-75 mainline spanning the Maumee River/Norfolk Southern Railroad/South Ave will be shifted 55 ft

to the west.

o The Miami St Interchange will utilize a diamond design with standard spacing between ramp intersections

on Miami St.

o The South Avenue entrance ramp to Southbound IR-75 will be rebuilt to current design standards.

o Addition of auxiliary lanes between Wales Rd and Miami St, and between Miami St and South Ave on IR-75

to improve operation.

o Installation of Noise Walls where warranted.

PID 93592 WOO/LUC-75-30.70/0.00 - ODOT District 2

Page 7: WOO/LUC-75-30.70/0.00 PID 93592 01 1… · o 47,000 SY of Cement Stabilization o 5,500 FT of Curb o 9,000 FT of Single-Slope Concrete Barrier o 8,400,000 LB Reinforcing Steel. 8 |

7 |

SUMMARY OF PROJECT MATERIALS

PID 93592 WOO/LUC-75-30.70/0.00 - ODOT District 2

o Option Bid for mainline– Asphalt or Concreteo 53,000 CY of Asphalt Base, 9,000 CY of Asphalt Concrete Surface, 10,000 CY of

Asphalt Concrete Intermediate.

o or

o 203,000 SY of 13.5” Non-reinforced Concrete pavement, Class QC1 W/QA/QC

o 47,000 SY of Cement Stabilization

o 5,500 FT of Curb

o 9,000 FT of Single-Slope Concrete Barrier

o 8,400,000 LB Reinforcing Steel

Page 8: WOO/LUC-75-30.70/0.00 PID 93592 01 1… · o 47,000 SY of Cement Stabilization o 5,500 FT of Curb o 9,000 FT of Single-Slope Concrete Barrier o 8,400,000 LB Reinforcing Steel. 8 |

8 |

SUMMARY OF PROJECT MATERIALS

PID 93592 WOO/LUC-75-30.70/0.00 - ODOT District 2

Misc. Work

o 91,000 SF of MSE Walls

o 108,000 SF of Noise Walls

o Vandal Fence

o 10,500 SF of Sidewalk

o Highway lighting

o Sewer work

o Traffic Signals

Page 9: WOO/LUC-75-30.70/0.00 PID 93592 01 1… · o 47,000 SY of Cement Stabilization o 5,500 FT of Curb o 9,000 FT of Single-Slope Concrete Barrier o 8,400,000 LB Reinforcing Steel. 8 |

9 |

DISADVANTAGED BUSINESS ENTERPRISE (DBE)

PID 93592 WOO/LUC-75-30.70/0.00 - ODOT District 2

DBE Goal – 12%

o Contains the Proposal Note 013-Disadvantaged

Business Enterprise (DBE) Utilization Plan and

Good Faith Efforts updated 04/20/2018

o All bidders shall submit a DBE Utilization Plan at

the time of bid

Page 10: WOO/LUC-75-30.70/0.00 PID 93592 01 1… · o 47,000 SY of Cement Stabilization o 5,500 FT of Curb o 9,000 FT of Single-Slope Concrete Barrier o 8,400,000 LB Reinforcing Steel. 8 |

10 |

DISADVANTAGED BUSINESS ENTERPRISE (DBE)

PID 93592 WOO/LUC-75-30.70/0.00 - ODOT District 2

o The plan should set forth specific information

demonstrating how bidder will achieve DBE Goal

o Identify DBE Certified firms:

http://www.dot.state.oh.us/Divisions/ODI/SDBE/

Pages/DBE-Directory.aspx

Page 11: WOO/LUC-75-30.70/0.00 PID 93592 01 1… · o 47,000 SY of Cement Stabilization o 5,500 FT of Curb o 9,000 FT of Single-Slope Concrete Barrier o 8,400,000 LB Reinforcing Steel. 8 |

11 |

QUESTIONS

Last updated 1/16/2019

PID 93592 WOO/LUC-75-30.70/0.00 - ODOT District 2