Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Appendix 2
Woodseer Street Track Option Alignment
Cross London Rail Links Limited Mott MacDonald
Woodseer Street Track Alignment Option
Technical Note No. 1D0300-C1V13-00850 March 2005
Cross London Rail Links Limited 1 Butler Place London SW1H 0PT
Woodseer Street
Track Alignment Option
Report No. 1D0300-C1V13-00850
March 2005
Mott MacDonald St Anne House 20-26 Wellesley Road CroydonSurrey CR9 2UL UKTel : 44 (0)20 8774 2000 Fax : 44 (0)20 8681 5706
Cross London Rail Links Limited Mott MacDonald
Woodseer Street Track Alignment Option
Technical Note No. 1D0300-C1V13-00850 March 2005
- i -
Executive Summary
This technical note has been prepared to provide further detail and comparison of the impacts on train operation, track design, maintenance and renewal of the option to site the shaft at Woodseer Street as an alternative to Hanbury Street. This additional technical detail has been prepared following a request to CLRL from the London Borough of Tower Hamlets.
This technical note is intended to support the report; Use of Woodseer Street Site as an alternative to Hanbury Street Shaft, No 1D0300-C1V13-0837 dated 12th November 2004 which compares all aspects of the works at these two potential sites.
When considering the alternative Woodseer Street alignment in terms of operational impact plus track maintenance or renewal, there is no merit whatever in adopting the Woodseer Street alignment. It demonstrates significant disadvantages in terms of operation and increased track maintenance.
With RT60, Grade A rail and rail lubrication installed on the Woodseer Street alignment, it is predicted that rail life on the sharpest curves would be 7 months or less compared with between 12 & 15 years on the Hanbury Street alignment. The Woodseer Street alignment results in more frequent rail replacement necessitating substantially more track possessions over the operating life of Crossrail.
The installation of rail flange lubricators on both tracks to reduce noise and rates of rail & wheel wear would be essential for the Woodseer Street alignment. This equipment introduces significant amounts of grease into the tunnel environment. It is designed to distribute grease along the rail but it also contaminates the track slab. Without regular cleaning this can affect the reliability of signalling equipment and potentially introduce contaminants into the local track drainage system.
The Woodseer Street alignment introduces tight curvature into the Crossrail alignment, a longer railway (54m) and a reduction in speed to 80kph. Based upon these factors the overall journey time between Liverpool Street to Whitechapel stations will increase by between 10 and 15 seconds. The additional journey times quoted are dependant on the speed profile of trains stopping at Whitechapel and Liverpool Street stations.
It is therefore recommended that the original Hanbury Street alignment is retained when considering only operational and track maintenance/renewal impacts.
Cross London Rail Links Limited Mott MacDonald
Woodseer Street Track Alignment Option
Technical Note No. 1D0300-C1V13-00850 March 2005
- i -
List of Contents Page
Executive Summary
1 Introduction 1
2 Purpose of this Technical Note 1
3 Track Specification 1
3.1 General 1
3.2 Woodseer Street 2
3.3 Hanbury Street 2
4 Track Alignment Options 3
4.1 Introduction 3
4.2 Woodseer Street 3
4.3 Hanbury Street 4
5 Comparison of Track Maintenance Requirements 5
5.1 Table of maintenance requirements 5
6 Comparison of Track Renewals 6
6.1 Table of rates of track renewal 6
7 Operational & System Impacts 6
8 Conclusions 8
Appendix A: Drawings A-1
Appendix B: Calculations B-1
Cross London Rail Links Limited Mott MacDonald
Woodseer Street Track Alignment Option
Technical Note No. 1D0300-C1V13-00850 March 2005
- 1 -
1 Introduction
This technical note has been prepared to provide further detail and comparison of the impacts on train operation, track design, maintenance and renewal of the option to site the shaft at Woodseer Street as an alternative to Hanbury Street. The additional technical detail has been prepared following a request to CLRL from the London Borough of Tower Hamlets.
The track alignment design has been influenced by the need to intersect the shaft position at Woodseer Street which has been determined by a previous study (Use of Woodseer Street Site as an alternative to Hanbury Street Shaft, Technical Note No 1D0300-C1V13-0837 dated 12th November 2004).
2 Purpose of this Technical Note
It is intended that this technical note compares only the merits of the track alignment and operational impact for the alternative Woodseer Street shaft position when compared with the existing Hanbury Street shaft track alignment. It will consider the implications of adopting the alternative alignment on train speed, track maintenance and track renewal.
This technical note is intended to support the report; Use of Woodseer Street Site as an alternative to Hanbury Street Shaft, Technical Note No 1D0300-C1V13-0837 dated 12th November 2004 which covers all other aspects of the works at these two potential sites.
3 Track Specification
The Crossrail Project Design Standards – Permanent Way, have been applied to both alignments and reflect the track specification common to the running tunnels throughout the Crossrail central section. The specification also complies with Network Rail Company Specifications for track alignment design and inspection.
Where features differ between the two options these are detailed separately for each alignment.
3.1 General
The Crossrail Project design standards state the following criteria should be applied;
100kph design train speed;
For 100kph line speeds the desirable minimum horizontal curve radius 525m should be specified wherever possible to meet the required passenger comfort requirements and optimise maintenance activities. The absolute minimum radius that will permit a speed of 100kph is 455m;
For 80kph line speed the absolute minimum radius 300m curve is required. This curve radius and restriction in speed may be applied only where physical constraints on the alignment prevent 100kph being achieved economically and is subject to the approval of the Crossrail Chief Executive;
Maximum applied cant shall be 150mm and maximum cant deficiency shall be 110mm;
Cross London Rail Links Limited Mott MacDonald
Woodseer Street Track Alignment Option
Technical Note No. 1D0300-C1V13-00850 March 2005
- 2 -
Maximum gradient, desirable 1 in 40, absolute minimum 1 in 30.
Network rail standards specify the use of RT60 profile rail but 3 different steel types are listed;
Grade A rail steel ; Normal rail steel used throughout the network for rail replacement
Grade B rail steel; No longer used in running lines
High wear resistant (MHT) rail; Network Rail policy only allows use of this type of rail for replacement at existing sites. For use at new locations this must be approved by Network Rail prior to installation.
Throughout the tunnel, section RT60 grade A rail will be specified with appropriate fixings to mitigate noise and vibration where needed. An unballasted track form will be provided throughout the tunnel section of the route. Exact specifications for the design of the track slab form and drainage systems for each section of the tunnel are yet to be developed but the track form will need to incorporate the requirement for derailment containment and noise and vibration mitigation where appropriate.
3.2 Woodseer Street
The track alignment design has been influenced by the need to intersect the shaft position at Woodseer Street which has been determined by previous study (refer Technical Note No 1D0300-C1V13-0837, Section 5.1). To reach the shaft position the alignment is constrained by the piled foundations of several buildings.
This option complies with the Crossrail Project design standards specification except with regard to desirable minimum curvature and speed. The curves specified do however comply with the absolute minimum limits allowable within Crossrail Project design standards for track alignment design but only by application of a speed restriction to 80kph.
The other changes in specification to reflect the more severe curvature of the alignment (see drawings in appendix A) include;
1. Increased number of rail fixings per metre;
2. Installation of rail flange lubricators;
3. Rail profile grinding programme;
4. Increased number of signals due to limited sighting distances.
3.3 Hanbury Street
The track alignment design has been influenced by the need to intersect the shaft position at Hanbury Street which has been determined by previous study (refer Technical Note No 1D0300-C1V13-0837, Section 4.1).
This option complies with the Crossrail Project design standards specification with regard to desirable minimum curvature, whilst maintaining a 100kph line speed.
Cross London Rail Links Limited Mott MacDonald
Woodseer Street Track Alignment Option
Technical Note No. 1D0300-C1V13-00850 March 2005
- 3 -
4 Track Alignment Options
4.1 Introduction
When a train follows a curved path a centrifugal force is exerted outwards. The magnitude of this force is affected by several factors including the speed of the train and the radius of the curve.
The limiting values used to determine that which is acceptable may be defined by either:
Safety considerations; the desire to maintain a reasonable level of passenger comfort; optimise track maintenance activity; Optimise track component life.
Curves are canted (banked) to reduce the lateral forces and improve passenger comfort. To achieve this one rail is raised above the other by a calculated amount. Equilibrium speed is the speed at which the vehicle negotiating the canted curve is balanced. When a vehicle travels round a curve at higher than equilibrium speed the curve can be described as deficient in cant. Providing this is calculated to be within design limits it is acceptable and is described as cant deficiency. Therefore the maximum speed at which a train can traverse a curve is dependant on a combination of radius, cant and cant deficiency.
When designing the track alignment to pass through the two shaft positions the Crossrail Project design standards have been applied. Neither design exceeds these minimum requirements. Therefore both can nominally be considered as compliant to Crossrail design standards, though the Woodseer Street alignment requires a reduced line speed of 80kph, which has not been approved by the Crossrail Chief Executive. This technical note is therefore only concerned with a comparison of the implications on train operations plus track maintenance and renewal activity of each of the proposed alignments.
4.2 Woodseer Street
Figure 1 Woodseer Street track alignment
Cross London Rail Links Limited Mott MacDonald
Woodseer Street Track Alignment Option
Technical Note No. 1D0300-C1V13-00850 March 2005
- 4 -
Describing the alignment from west to east; from a straight at chainage 9220 the line takes a right hand transition onto a 335m radius curve with 120mm of cant & 107mm of cant deficiency. Then at chainage 9482 the curve flattens out to 515m radius, with 85mm of cant & 100mm of cant deficiency. At chainage 9671 the alignment becomes straight for a short distance before curving left again at chainage 9870 onto a left hand, 500m radius curve with 120mm of cant & 95mm of cant deficiency. At chainage 10046 the line returns to a straight as the track approaches the station at Whitechapel. This alignment results in a reduction in speed from 100kph to 80kph for approximately 800m. It should be noted that the westbound alignment through this section has a 320m minimum radius curve with the same restriction in maximum allowable speed. The horizontal alignment differs substantially from that described for Hanbury Street and exceeds the minimum desirable curvature (525m) specified by Crossrail Project design standards and thus dictates the lower speed. It does not exceed the minimum allowable curvature.
This design provides a vertical profile that positions the tracks 4.7m deeper in the proposed shaft than for the Hanbury Street alignment. This is to avoid the suspected piled foundations under Trumans Brewery, McGlashon House and Arthur Deakin House. The vertical alignment therefore changes significantly with a constant 1 in 170 gradient rising from Liverpool Street towards Whitechapel Station. The construction impacts of lowering the alignment are discussed in Technical Note No 1D0300-C1V13-0837.
4.3 Hanbury Street
Figure 2 Hanbury Street track alignment
Describing the alignment from west to east; from a straight at chainage 9030 the line takes a right hand, 595m radius curve with 100mm of cant & 99mm of cant deficiency. Then at chainage 9410 the alignment returns to a straight. At chainage 9712 there is a short 1500m left hand curve to chainage 9800 then another straight as the track approaches the station at Whitechapel. This allows a maximum speed of 100kph through this section of the line. It should be noted that the westbound alignment has a 495m minimum radius curve.
Described in the same direction the vertical alignment follows a 1 in 40 gradient climbing towards Hanbury Street shaft. It then falls slightly towards the station. The vertical and horizontal position of the track at the shaft has been determined by the constraints found on the surface, and to found the shaft wholly within London Clay (refer Technical Note No 1D0300-C1V13-0837).
Cross London Rail Links Limited Mott MacDonald
Woodseer Street Track Alignment Option
Technical Note No. 1D0300-C1V13-00850 March 2005
- 5 -
This design complies with the Crossrail Project design standards design criteria for vertical gradients and horizontal alignment for a line speed of 100kph.
5 Comparison of Track Maintenance Requirements
5.1 Table of maintenance requirements
The following table summarises the key inspection and maintenance differences concerned with a tight radius curve. It does not detail all the inspection or maintenance items common to both alignments.
The frequencies quoted above reflect Network Rail minimum standards for inspection. The frequencies quoted for rail grinding, slab cleaning and rail fixings & pad replacement are based on an estimated rate of deterioration.
The table above assumes the use of RT60, Grade A rail on both the Hanbury Street and Woodseer Street alignment options.
The frequency for monitoring rail side wear is defined in Network Rail standards and is determined by either the predicted or actual rate of wear. The process is the same for either option. Once side wear reaches certain limits the frequency of inspection increases until the rail wear reaches the maximum allowable then it is either replaced or if possible reprofiled.
A programme of rail grinding would be required to maintain rail profile for both alignments. The tight curves on the Woodseer Street alignment would however have a very high rate of wear and grinding may not be a viable solution. If this is the case then replacement of the worn rail is the only alternative.
It should be noted that the Woodseer Street alignment option will require more track fixings to be installed and is 54m longer than the Hanbury Street alignment. This will by definition increase the amount of maintenance activity in terms of minor maintenance work and the amount of infrastructure to be inspected.
Examples of similar track alignment between the Heathrow Express tunnels and airport junction have required significant additional maintenance activity and have caused operational delay due to component failure. On a curve of similar radius to that specified for the Woodseer Street alignment rails are currently being replaced or transposed every 3 to 4 years. This is with a service pattern of 4 trains per hour over 19 hours per day. The proposed Crossrail service is more frequent than the
Routine inspection
Monitorrail
side wear
Railprofile
grinding
Maintainrail flange lubricators
Trackslab
cleaning
Rail Fixings & pad spot replacement
Rail foot inspection
Hanbury Street
Weekly 12 monthly
then 3 monthly
Every 6 – 8 years
No Not required
20 No per year
Every 6 – 8 years
WoodseerStreet
Weekly 3 monthly then
monthly
Every 3 - 4
months
2 per line Monthly
inspection& refill
12monthly
50 No per year
3monthly
Cross London Rail Links Limited Mott MacDonald
Woodseer Street Track Alignment Option
Technical Note No. 1D0300-C1V13-00850 March 2005
- 6 -
Heathrow service with 24 trains per hour and thus it can be reasonably concluded that rail life will be 7 months or less on the 300m curves at Woodseer Street. Whilst it is clear that certain potential maintenance problems can be mitigated at the design stage it will not be possible to remove them completely. Frequency of rail & fixing replacement is clearly increased if the Woodseer Street alignment were to be adopted.
6 Comparison of Track Renewals
6.1 Table of rates of track renewal
The table assumes the use of RT60, Grade A rail on both the Hanbury Street and Woodseer Street alignment options
When determining when a rail must be replaced the limits of wear tolerances are specified within Network Rail standards are to be applied.
Replacement of the worn rail can be achieved in two ways. Rail side wear will only occur on the outside rail on the curve. Therefore when it needs to be replaced this can be achieved initially by transposing the rails on site thus avoiding having to transport new rail into the tunnel. But once the maximum tolerance for side wear is reached again then the only course of action available would be to import new rail to the site and remove the now scrap rails.
7 Operational & System Impacts
Crossrail Project design standards specify a line speed of 100kph for all running lines wherever possible. The Hanbury Street alignment permits a line speed of 100kph. Due to the tight curvature the Woodseer Street design requires an 80kph restriction over approximately 800m of both the east and west bound lines. It is also longer (54m) than the Hanbury Street alignment. Based upon these observations this will increase the overall journey time between Liverpool Street to Whitechapel stations by between 10 and 15 seconds if the Woodseer Street option is accepted. The journey times quoted are dependant on the speed profile of trains stopping at Whitechapel and Liverpool Street stations.
Rail transposing or
replacement
Track fixing replacement
Rail flange lubricator
replacement
Spacing of track fixings
Hanbury Street
Every 6 – 8 years at isolated locations –
remainder every 12 – 15 years
Repadding every 10 - 12 years. Other items every 12 – 15 years
Not required Standard spacing 700mm
WoodseerStreet
300m radius curves every 7 months or less. Other sections as per
Hanbury St
Repadding when rail is replaced
Every 4 – 6 years with heavy
overhaul every 2 - 3 years
Reduce spacing to 610mm on curves
less than 500m radius
Cross London Rail Links Limited Mott MacDonald
Woodseer Street Track Alignment Option
Technical Note No. 1D0300-C1V13-00850 March 2005
- 7 -
If a conventional signalling system is adopted for the Crossrail tunnels then signal sighting could be problematic for the Woodseer Street alignment. This will be assessed during the design stage, but with the tight curvature required it is highly likely that additional signals will be needed to comply with sighting distances for drivers. This could impact on minimum train headways through this section and thus have the potential to restrict the maximum number of trains per hour through this part of the line.
A significant operational impact when considered over the longer term will be the requirement for track possessions for track maintenance and rail replacement. It is clear the Woodseer Street option creates additional infrastructure and reduces the life of the rail when compared with the Hanbury Street alignment. The additional maintenance works can be planned within the normal no train periods on the route. However both options will demand the rail to be replaced or transposed due to wear at some time and this work will require operationally disruptive possessions. As has been described earlier the Woodseer Street alignment considerably reduces the life of the rail and therefore as a consequence increases the number of disruptive possessions required for rail replacement over the life of Crossrail.
It should be noted that where excessive rail side wear occurs an increase in wear rates on the wheels of the Crossrail rolling stock will also be evident. This will result in an increase in the frequency of wheel reprofiling and replacement. As with rails this problem is mitigated to a limited degree by the use of rail flange lubricators but it is still a significant issue with trains being out of use more often whilst repairs are carried out.
At locations of high rates of wear to rails and wheels steel “filings” are created. These will mix with the rail flange lubricant creating a paste which can become electrically conductive. This can potentially cause problems with conventional signalling track circuits and introduce stray currents from the traction power supply if not regularly removed.
Cross London Rail Links Limited Mott MacDonald
Woodseer Street Track Alignment Option
Technical Note No. 1D0300-C1V13-00850 March 2005
- 8 -
8 Conclusions
In terms of operation and increased track maintenance/renewal there is no merit whatever in adopting the Woodseer Street alignment as it demonstrates significant disadvantages. The disadvantages for the Woodseer Street alignment are discussed below:
The base case (Hanbury Street) maintains a line speed of 100kph. The Woodseer Street design requires a speed restriction of 80kph over approximately 800m. This will result in an increase in journey times between Liverpool Street & Whitechapel stations of between 10 and 15 seconds. This is dependant on the speed profile of rolling stock accelerating or braking between Liverpool Street and Whitechapel stations;
The rate of rail side wear is predicted to be significantly greater on the Woodseer Street alignment option. With RT60 grade A rail and rail lubrication, it is predicted that rail life would be reduced on the 300m radius curves to 7 months or less. The more frequent rail replacement will substantially increase the number of disruptive track possessions over the operating life of Crossrail.
Rail grinding to maintain the rail profile would be required with a frequency of up to four times that required for the Hanbury Street alignment;
The Woodseer Street option would require wheel flange lubrication equipment to be installed. This will introduce significant amounts of contaminants into the tunnel environment which would demand regular cleaning and maintenance. Without regular cleaning the dirty environment could affect the reliability of signalling equipment and introduce contaminants into the local drainage system;
High lateral forces would be introduced into the rail on a 300m curve which would require higher toe loadings to be accommodated within the track form design;
An increase in the rate of wear on rolling stock wheel sets will result in more frequent reprofiling and replacement. As a consequence stock availability would reduce;
Signal sighting is potentially worse in the alternative Woodseer Street option;
Rail/wheel noise and vibration is significantly increased. This is unlikely to worsen noise levels on the surface but will travel along the tunnels and may be heard in adjacent stations.
The mix of steel “filings” created as a result of the wear on rails & wheels has the potential to cause problems with conventional signalling track circuits and introduce stray currents from the traction power supply if not regularly removed.
It is therefore recommended that the original Hanbury Street alignment is retained.
Cross London Rail Links Limited Mott MacDonald
Woodseer Street Track Alignment Option
Technical Note No. 1D0300-C1V13-00850 March 2005
- A-1 -
Appendix A: Drawings
Alignment – Plan and Profile
Liverpool Street to Whitechapel Station
Eastbound track
1D0100-C1T13-T00-P-00001 Rev A
Alignment – Plan and Profile
Woodseer Street Shaft
Crossrail Alternative Eastbound track
1D0100-C1T13-T00-P-00002 Rev A
Cross London Rail Links Limited Mott MacDonald
Woodseer Street Track Alignment Option
Technical Note No. 1D0300-C1V13-00850 March 2005
- B-1 -
Appendix B: Calculations
Basic calculations for predicted rail life on 300m radius curve at Woodseer Street
The following calculations are derived from information obtained by Crossrail from Heathrow Express (HEX). The data is from a similar radius curve on the HEX branch off the GW main line. HEX state that rail replacement occurs at between 3 & 4 year intervals. This information together with the service levels on HEX have been used to predict the rate of wear on Crossrail with an increased train frequency.
HEX Runs 4tph over 19 hours per day = 76 trains per day Each train is 8 cars or 32 axles
Therefore 32 x 76 = 2432 axles per day
CrossrailRuns 24tph peak times & reduced service off peak
Average 16tph over 19 hours per day = 304 trains per day Each train is 10 cars or 40 axles
Therefore 40 x 304 = 12160 axles per day
If HEX replaces rails every 4 years = 3502080 axles
Crossrail at 12160 axles per day - same level of use after 288 days – 9.6 months
If HEX replaces rails every 3 years = 2626560 axles
Crossrail at 12160 axles per day - same level of use after 216 days – 7.2 months
From these figures it can be assumed Crossrail will replace rails approximately every 7 months
Appendix 3
Crossrail Construction Programme, Programme Impact Without Hanbury Street Shaft as a TBM Launch
Cross London Rail Links Limited Mott MacDonald
Crossrail Construction Programme - Programme Impact without Hanbury Street Shaft as a TBM Launch Site
Technical Note No. No. 1D0300-C1N00-00839/A April 2005
P:\Croydon\MMH\Tunnels\201985\Reports\Technical Notes\839 Programme Impact without Hanbury Shaft as a TBM Launch Site\Revision A - Final Issue\1D0300-C1N00-00839 A.doc
Cross London Rail Links Limited1 Butler PlaceLondonSW1H 0PT
April 2005
Mott MacDonaldSt Anne House20-26 Wellesley RoadCroydonSurreyCR9 2ULUKTel : 44 (0)20 8774 2000Fax : 44 (0)20 8681 5706
Cross London Rail Links Limited Mott MacDonald
Crossrail Construction Programme - Programme Impact without Hanbury Street Shaft as a TBM Launch Site
Technical Note No. No. 1D0300-C1N00-00839/A April 2005
201985/1D0300-C1N00-00839/A3/April 2005
P:\Croydon\MMH\Tunnels\201985\Reports\Technical Notes\839 Programme Impact without Hanbury Shaft as a TBM Launch Site\Revision A - Final Issue\1D0300-C1N00-00839 A.doc
S-1
Executive Summary
This report was prepared by Mott MacDonald for Cross London Rail Links Limited (CLRLL) toreview the programme impact of not using Hanbury Street Shaft as an intermediate tunnelling site (thebase case). The report assesses and compares the programme durations for the introduction of revenueservices for Crossrail Line 1 with and without the use of Hanbury Street Shaft. In the optionsconsidered the revenue service strategy is based upon a staged opening sequence, with the revenueservice that operates services between Paddington and Shenfield considered as the benchmark forfinancial planning. The main depot for Crossrail Line 1 is located at Romford and must be availablefor commissioning, trial running and the commencement of revenue service. As a comparator therevenue service staging has been developed from east to west in each case.
In addition to the base case, which uses Hanbury Street Shaft as an intermediate tunnelling site, twofurther options were considered for the central tunnels drives without using Hanbury Street Shaft:
• Option 1 - Tunnel drive mid-point at Fisher Street Shaft, with the section from Royal Oak toFisher Street constructed using an open face shield in predominantly London Clay groundconditions, and the section from Pudding Mill Lane to Fisher Street constructed using a closedface TBM in predominantly Lambeth Group ground conditions;
• Option 2 - Tunnel drive mid-point at Farringdon Station, with the section from Royal Oak Portalto Farringdon Station and the section from Pudding Mill Lane to Farringdon Station bothconstructed using closed face TBMs (Earth Pressure Balance Machine) due to poorer groundconditions in the Farringdon area.
Adoption of the base case tunnelling strategy reduces the Project’s risk of a delay in the introductionof revenue services (64 months), as a result of tunnelling, by adopting four shorter tunnel drive lengthsbetween Royal Oak and Pudding Mill Lane Portals. Therefore should construction difficulties slow orstop one of the tunnel drives there is potentially more opportunity for one of the other tunnel drives tocompensate. This strategy is also compatible with the revenue service strategy where the easterntunnel section is completed in advance of the western tunnel section, thus reducing delay in thecommencement of the first stage of revenue service.
Option 1 combines three tunnel drive lengths from the base case into one tunnel drive length ofapproximately 8395m, for the section between Pudding Mill Lane Portal and Fisher Street Shaft. Thisresults in a significant imbalance in the construction programme with the section between PuddingMill Lane and Fisher Street being approximately 65% longer than the section between Royal Oak andFisher Street. The resulting revenue service date for Option 1 is 19 months longer than the base case.
Option 2 reduces the tunnel drive length imbalance of Option 1 by using Farringdon Station as thetunnel drive mid point. In doing so, it creates additional constraints as to the tunnelling methodologyand rate due to poorer ground conditions in the Farringdon area. Option 2 also introduces additionalrisks into the project at the Crossrail station at Paddington; the Northern Line Platform Tunnels atTottenham Court Road Station; and the Central Line, in respect of internal project interfaces andinterfaces with third parties such as Network Rail and London Underground Limited. Risks are alsointroduced at the Crossrail station at Farringdon in respect to internal interfaces for decommissioningand removal of the tunnelling machines. The programme risk at Paddington is due to additional worksinvolved in receiving and re-launching the closed face TBM (EPBM) and its associated backup
Cross London Rail Links Limited Mott MacDonald
Crossrail Construction Programme - Programme Impact without Hanbury Street Shaft as a TBM Launch Site
Technical Note No. No. 1D0300-C1N00-00839/A April 2005
201985/1D0300-C1N00-00839/A3/April 2005
P:\Croydon\MMH\Tunnels\201985\Reports\Technical Notes\839 Programme Impact without Hanbury Shaft as a TBM Launch Site\Revision A - Final Issue\1D0300-C1N00-00839 A.doc
S-2
equipment within the station area, compared to the smaller and lighter open face Shield which will beused for the base case and Option 1. This additional work at Paddington will add two months to theconstruction programme. At Tottenham Court Road Station, the eastbound Crossrail tunnel passesabove the existing LUL Northern Line platform tunnels with a clearance of approximately 0.5m. Theuse of the heavier closed face TBM (EPBM) will impose much greater travelling loads on the tunnelsand will require additional structural support to be installed inside the Northern Line platform tunnelsto facilitate the crossing. Between Tottenham Court Road Station and Fisher Street Shaft, bothCrossrail tunnels pass above the existing LUL Central Line tunnels with clearances of less than 0.5m.Again, the use of a heavier closed face TBM (EPBM) will require the installation of structural supportwithin the LUL tunnels. It is probable that the crossings of the Northern Line and Central Line willresult in a closure being required. This could be up to two months for the Northern Line crossing andup to three months for the Central Line crossing. Programme analysis for Option 2 shows that thesedelays will increase the revenue service date by 16 months over the base case.
In addition, completion of the tunnel fit out between Isle of Dogs and Stepney Green will be delayeduntil tunnelling and cleanout is completed between Pudding Mill Lane and Fisher Street andFarringdon (Option 1 and Option 2 respectively).
Without the use of an intermediate tunnelling site at Hanbury Street Shaft, the revenue service datewould be delayed by 19 months for Option 1, and 16 months for Option 2 compared with the basecase. This results in the project programme for Crossrail Line 1 being outside the 6 year timetable forfunding as determined by the Department for Transport (DfT).
It is therefore recommended that the use of Hanbury Street Shaft as an intermediate tunnelling site bemaintained as part of the tunnelling strategy for Crossrail Line 1.
Cross London Rail Links Limited Mott MacDonald
Crossrail Construction Programme - Programme Impact without Hanbury Street Shaft as a TBM Launch Site
Technical Note No. No. 1D0300-C1N00-00839/A April 2005
i201985/1D0300-C1N00-00839/A3
P:\Croydon\MMH\Tunnels\201985\Reports\Technical Notes\839 Programme Impact without Hanbury Shaft as a TBM Launch Site\Revision A - Final Issue\1D0300-C1N00-00839 A.doc
List of Contents
Executive Summary
1 Introduction 1
2 Development of the Crossrail Programme 1
2.1 Classic Crossrail 1
2.2 Crossrail Line 1 1
2.3 Revenue Service Strategy 3
3 Tunnelling Requirements 4
3.1 General 4
3.2 Ground Conditions 4
3.3 TBM Type and Tunnelling Rate 5
4 Review of Tunnelling without Hanbury Street Intermediate Tunnelling Site 7
4.1 Tunnelling Strategy 74.1.1 Option 1- Tunnel Drive Mid-point at Fisher Street Shaft 8
(i) Tunnel Drive Strategy 8(ii) Programme 8
4.1.2 Option 2 - Tunnel Drive Mid-point at Farringdon Station 9(i) Tunnel Drive Strategy 9(ii) Programme 13
5 Review of Tunnelling with Intermediate Tunnelling Site (Base Case) 14
5.1 Tunnelling Strategy 14
5.2 Programme 15
6 Programme Comparison 16
6.1 Option 1 16
6.2 Option 2 17
6.3 Additional Considerations 17
7 Conclusions 19
Appendix A Time Chainage Programmes A-1
Appendix B Review of Intermediate Tunnelling Sites B-1
Cross London Rail Links Limited Mott MacDonald
Crossrail Construction Programme - Programme Impact without Hanbury Street Shaft as a TBM Launch Site
Technical Note No. No. 1D0300-C1N00-00839/A April 2005
1P:\Croydon\MMH\Tunnels\201985\Reports\Technical Notes\839 Programme Impact without Hanbury Shaft as a TBM Launch Site\Revision A - Final Issue\1D0300-C1N00-00839 A.doc/KLD
1 Introduction
This report was prepared by Mott MacDonald for Cross London Rail Links Limited (CLRLL) toreview the effect on the overall Crossrail Construction Programme for Line 1 in the event that theHanbury Street Shaft site was not available for use as an intermediate tunnelling site. The reportcompares the integrated construction programme ICP17, which is the base case and uses HanburyStreet Shaft in conjunction with the adjacent Pedley Street work site as a tunnelling site, to alternativetunnelling strategies where the eastern tunnel drive commences from Pudding Mill Lane (PML) Portaland terminates the drives at Fisher Street Shaft or Farringdon Station without an intermediatetunnelling site; all other tunnelling arrangements remaining the same.
2 Development of the Crossrail Programme
2.1 Classic Crossrail
The original ‘Classic Crossrail’ developed in the 1990s, linked the Great Western lines out ofPaddington to the Great Eastern lines out of Liverpool Street. The central tunnel sections extendedfrom the western portal at Royal Oak to a portal adjacent to the Great Eastern lines at Allen Gardens.The overall length, portal to portal, of the central tunnel alignments was planned to be 9.0km.
It was planned that the construction of the running tunnels would be serviced from the two portals –Royal Oak in the west and Allen Gardens to the east. The Royal Oak Portal would service theconstruction from Paddington to Tottenham Court Road with the balance of the tunnelling beingcarried out from Allen Gardens.
This strategy was adopted for environmental and logistic supply reasons and allowed for rail haulageof the excavated material thus further reducing the impact of the works on the highway network.
The Classic Crossrail construction programme was developed in 1994 and forecast an overall periodfrom commencement of construction to revenue service of approximately 66 months.
2.2 Crossrail Line 1
In the current scheme, the western portal is still at Royal Oak to allow connection to the Great Westernsurface lines for continuation to Maidenhead, but the central tunnelled section of Crossrail Line 1extends to a new station at Whitechapel and continues to an eastern portal at Pudding Mill Lane, nearStratford. There the route joins the Great Eastern Lines for continuation to Shenfield on surface lines.The central tunnel section also extends to the southeast from a junction at Stepney Green to a newstation at Isle of Dogs, immediately north of Canary Wharf development, and continues to a portal atVictoria Dock. The overall length, portal to portal, for the central tunnel section is approximately19.5km.
From Victoria Dock Portal, the railway connects with the new Thames Crossing Tunnels forcontinuation to Abbey Wood. The Thames Crossing Tunnels are independent of the Central Tunnelssection and do not influence the tunnelling methodologies and construction programme.
Cross London Rail Links Limited Mott MacDonald
Crossrail Construction Programme - Programme Impact without Hanbury Street Shaft as a TBM Launch Site
Technical Note No. No. 1D0300-C1N00-00839/A April 2005
2P:\Croydon\MMH\Tunnels\201985\Reports\Technical Notes\839 Programme Impact without Hanbury Shaft as a TBM Launch Site\Revision A - Final Issue\1D0300-C1N00-00839 A.doc/KLD
An initial assessment of the programme period, based upon Classic Crossrail constructionmethodology of driving the tunnels from portals at the extremities and taking into account theadditional tunnelled length, showed that the overall programme for the new scheme would beextended to 93 months1. This is 27 months more than the original Classic Crossrail programme.
It was found that the increase in construction duration for the tunnels was disproportionate to the timerequired for station construction resulting in significant delays to the construction programme forcompletion of the station works. Alternative construction strategies were therefore investigated toreduce the programme period, particularly for the tunnel drives.
Construction of the railway tunnels is essentially a linear process, involving in turn the excavation andsupport of the tunnels, clean out and removal of temporary facilities, followed by the installation inseparate operations of the first stage track-bed, the track-form (rails and fixings), walkways, pipe-workand cable brackets and then railway systems. To reduce the programme it was necessary to introduceadditional work fronts into the programme.
Since that initial assessment, the construction programme has been significantly developed. It nowincludes intermediate tunnelling worksites to provide an optimised project wide constructionprogramme and tunnel drive strategy that achieves the requirements of the revenue service strategy(refer to Section 2.3) and also completes construction within a six year timetable as determined by theDepartment for Transport (DfT). The Project’s current (base case) tunnels drive strategy for thecentral section is summarised by the following:
• Royal Oak Portal to Fisher Street Shaft;
• Hanbury Street Shaft to Fisher Street Shaft;
• Hanbury Street Shaft to Whitechapel Station;
• Pudding Mill Lane Portal to Whitechapel Station;
• Isle of Dogs Station to Stepney Green Shaft;
• Limmo Shaft to Isle of Dogs Station; and
• Limmo Shaft to Victoria Dock Portal.
1Refer to Programme Number ICP1 (Report No. 1D0300-C1N00-00013/A). This programme was developed between Royal
Oak Portal (in the west) and Bow Portal (in the east). The portal at Bow has been relocated further east to Pudding Mill
Lane.
Cross London Rail Links Limited Mott MacDonald
Crossrail Construction Programme - Programme Impact without Hanbury Street Shaft as a TBM Launch Site
Technical Note No. No. 1D0300-C1N00-00839/A April 2005
3P:\Croydon\MMH\Tunnels\201985\Reports\Technical Notes\839 Programme Impact without Hanbury Shaft as a TBM Launch Site\Revision A - Final Issue\1D0300-C1N00-00839 A.doc/KLD
2.3 Revenue Service Strategy
The revenue service staging has been developed from east to west. This enables the main depot for therolling stock, located at Romford, to be accessed for commencement of revenue services. Initially therolling stock will be operated from that depot although eventually it will be stabled at various locationsalong the line to avoid unnecessary empty running.
The strategy for bringing Crossrail into Revenue Service has been based upon the following stagedsequence:
Stage 0. Trial running of Crossrail rolling stock, initially on test tracks, then on outer suburban lineswithout passengers, and then introduce Crossrail Rolling Stock into service on theLiverpool Street (surface station) to Shenfield line – working from the new Romford Depotand Stabling Yard;
Stage 1. Commence revenue service from Liverpool Street Station to Isle of Dogs Station (usingPudding Mill Lane Portal to introduce rolling stock into the tunnels from Romford depotand the crossovers at Farringdon and Isle of Dogs to turn trains around);
Stage 2. Extend revenue service to Paddington Station (turning trains around at Westbourne Park);
Stage 3. Introduce a revenue service through Paddington Station to Shenfield services;
Stage 4. Extend revenue services west to Heathrow and Maidenhead;
Stage 5. Extend revenue services east to Abbey Wood.
Cross London Rail Links Limited Mott MacDonald
Crossrail Construction Programme - Programme Impact without Hanbury Street Shaft as a TBM Launch Site
Technical Note No. No. 1D0300-C1N00-00839/A April 2005
4P:\Croydon\MMH\Tunnels\201985\Reports\Technical Notes\839 Programme Impact without Hanbury Shaft as a TBM Launch Site\Revision A - Final Issue\1D0300-C1N00-00839 A.doc/KLD
3 Tunnelling Requirements
3.1 General
For any underground project, the tunnelling methodology and tunnelling rate is predominatelydependant upon the ground conditions to be encountered. The central tunnelled section of CrossrailLine 1 between Royal Oak Portal in the west and Pudding Mill Lane and Victoria Dock Portals in theeast and southeast respectively will be constructed using tunnel boring machines (TBMs) with eitherbolted or expanded precast concrete linings erected within the tunnelling machine. For CrossrailLine 1, the following TBM types have been used for planning:
TBM Type TBM Support Mechanism Typical Ground Condition
Open FaceShield
Open face machine which provides no supportto the face comprising an articulated diggerhoused within a shield. It assumes that thetunnel face has sufficient stand-up timewithout support.
Stable, cohesive material (i.e.London Clay)
Earth PressureBalance (EPB)
Closed face machine which providescontinuous support to the tunnel face bybalancing earth pressure against the thrustpressure of the machine through the control ofexcavated materials from the face.
Water bearing non-cohesive / soft-very soft cohesive material withpermeability ranging between 10-3
to 10-4m/s. (i.e. Lambeth Group,Thanet Sand, Chalk)
Slurry2 Closed face machine which providescontinuous support to the tunnel face bybalancing earth and water pressure in the insitusoil with pressurised bentonite slurry. A largeseparator plant is required at the surface toseparate excavated materials from the slurry,allowing it to be recycled.
Water bearing non-cohesive / soft-very soft cohesive material with ahigher permeability to 10-2m/s.(i.e. Lambeth Group, Thanet Sand,Chalk)
3.2 Ground Conditions
The geology along the central section is varied with thick clay strata (London Clay) found in the west,thinning to the east and southeast. In general, the geology within London typically comprises:
• Superficial Deposits (made ground, alluvium and terrace gravels), overlying;
• London Clay (stiff to hard clay), overlying;
• Lambeth Group (split into five sub sections typically comprising layers of medium to very densesand and stiff to hard clay), overlying;
2The use of a Slurry TBM has been planned for the Thames Crossing Tunnels, located to the east of Victoria Dock Portal,
and is not currently planned for use in the Central Tunnels Section.
Cross London Rail Links Limited Mott MacDonald
Crossrail Construction Programme - Programme Impact without Hanbury Street Shaft as a TBM Launch Site
Technical Note No. No. 1D0300-C1N00-00839/A April 2005
5P:\Croydon\MMH\Tunnels\201985\Reports\Technical Notes\839 Programme Impact without Hanbury Shaft as a TBM Launch Site\Revision A - Final Issue\1D0300-C1N00-00839 A.doc/KLD
• Thanet Sands (very dense fine sand), overlying;
• Chalk (rock ranging in consistency from low to very high density).
Two aquifers exist; the upper and lower. The upper aquifer is usually confined to the SuperficialDeposits, with the London Clay stratum forming an impermeable layer below the aquifer. The loweraquifer is charged from the Chalk and influences both the Thanet Sands and Lambeth Group.
The following tabulates the ground conditions likely to be encountered by the tunnels betweenprincipal scheme components:
Route Section Predominant Ground Condition
Royal Oak Portal to Fisher Street Shaft London Clay
Fisher Street Shaft to Hanbury Street Shaft London Clay & Lambeth Group(With Thanet Sands at tunnel level at Farringdon)
Hanbury Street Shaft to Whitechapel Station London Clay
Whitechapel Station to Stepney Green Shaft Lambeth Group
Stepney Green Shaft to Pudding Mill Lane Portal Lambeth Group
Stepney Green Shaft to Victoria Dock Portal Lambeth Group / Thanet Sand
3.3 TBM Type and Tunnelling Rate
The type of tunnel boring machine (TBM) and tunnelling rate has been developed based upon theground condition, the length of the tunnel drive, and the location of the drive with respect to surfacestructures and their susceptibility to settlement. The following average tunnelling rates have beenadopted for planning purposes for ICP17:
Tunnel Drive TBM Type Planned Average Tunnelling Rate
Royal Oak Portal to FisherStreet Shaft;
Open Face Shield 40m/wk – Royal Oak to Paddington
71m/wk – Paddington to Fisher Street
Hanbury Street Shaft to FisherStreet Shaft;
Earth Pressure Balance 65m/wk
Hanbury Street Shaft toWhitechapel Station;
Open Face Shield 65m/wk
Pudding Mill Lane Portal toWhitechapel Station;
Earth Pressure Balance 77m/wk – PML to Stepney Green
70m/wk – Stepney Green toWhitechapel Station
Cross London Rail Links Limited Mott MacDonald
Crossrail Construction Programme - Programme Impact without Hanbury Street Shaft as a TBM Launch Site
Technical Note No. No. 1D0300-C1N00-00839/A April 2005
6P:\Croydon\MMH\Tunnels\201985\Reports\Technical Notes\839 Programme Impact without Hanbury Shaft as a TBM Launch Site\Revision A - Final Issue\1D0300-C1N00-00839 A.doc/KLD
Tunnel Drive TBM Type Planned Average Tunnelling Rate
Isle of Dogs Station to StepneyGreen Shaft;
Earth Pressure Balance 65m/wk
Limmo Shaft to Isle of DogsStation; and
Earth Pressure Balance 60m/wk
Limmo Shaft to Victoria DockPortal
Earth Pressure Balance 60m/wk
An eight week learning curve has been introduced at the commencement of the drive where typically50% of the advance rate is assumed, except for Royal Oak to Paddington where a tunnelling rate of40m/week has been assumed.
Tunnelling operations will be carried out on a 24 hour, 7 day week basis, allowing for planned andunplanned stoppages; maintenance and replacement of equipment; extension of conveyors and servicerailway; slowing of TBMs through areas of importance through central London; and removal ofobstructing features, where and if necessary. Where possible, tunnelling will be carried outcontinuously to control ground movements.
Cross London Rail Links Limited Mott MacDonald
Crossrail Construction Programme - Programme Impact without Hanbury Street Shaft as a TBM Launch Site
Technical Note No. No. 1D0300-C1N00-00839/A April 2005
7P:\Croydon\MMH\Tunnels\201985\Reports\Technical Notes\839 Programme Impact without Hanbury Shaft as a TBM Launch Site\Revision A - Final Issue\1D0300-C1N00-00839 A.doc/KLD
4 Review of Tunnelling without Hanbury Street IntermediateTunnelling Site
4.1 Tunnelling Strategy
The tunnelling strategy assumes that tunnelling through central London will be carried out from eachof the portals at Royal Oak and Pudding Mill Lane without the need for additional work fronts throughan intermediate tunnelling site at Hanbury Street Shaft.
Two options have been considered:
Option 1 - Tunnel Drive Mid-point at Fisher Street Shaft
Tunnel Drive Ground Conditions
Royal Oak Portal to Fisher Street Shaft; Predominantly London Clay ground conditions
Pudding Mill Lane to Fisher Street Shaft; Predominantly Lambeth Group groundconditions, with tunnel drives into the lowerlevels of London Clay between Hanbury Streetand Whitechapel Station, at immediately to theeast of Fisher Street Shaft
Option 2 - Tunnel Drive Mid-point at Farringdon Station
Tunnel Drive Ground Conditions
Royal Oak Portal to Farringdon Station; Predominantly London Clay, with LambethGroup and Thanet Sand at Farringdon
Pudding Mill Lane to Farringdon Station; Predominantly Lambeth Group groundconditions, with tunnel drives into the lowerlevels of London Clay between Hanbury Streetand Whitechapel Station
The tunnelling strategy and any issues associated with each are outlined in the following sections.
Cross London Rail Links Limited Mott MacDonald
Crossrail Construction Programme - Programme Impact without Hanbury Street Shaft as a TBM Launch Site
Technical Note No. No. 1D0300-C1N00-00839/A April 2005
8P:\Croydon\MMH\Tunnels\201985\Reports\Technical Notes\839 Programme Impact without Hanbury Shaft as a TBM Launch Site\Revision A - Final Issue\1D0300-C1N00-00839 A.doc/KLD
4.1.1 Option 1- Tunnel Drive Mid-point at Fisher Street Shaft
(i) Tunnel Drive Strategy
The following tunnel drive strategy and average tunnelling rate has been adopted for Option 1:
Tunnel Drive TBM Type Planned Average Tunnelling Rate
Royal Oak Portal to FisherStreet Shaft;
Open Face Shield 40m/wk – Royal Oak to Paddington
71m/wk – Paddington to Fisher Street
Pudding Mill Lane to FisherStreet Shaft;
Earth Pressure Balance 77m/wk – PML to Stepney Green
70m/wk – Stepney Green to FisherStreet
Isle of Dogs Station to StepneyGreen Shaft;
Earth Pressure Balance 65m/wk
Limmo Shaft to Isle of DogsStation; and
Earth Pressure Balance 60m/wk
Limmo Shaft to Victoria DockPortal
Earth Pressure Balance 60m/wk
(ii) Programme
The programme was developed using Primavera P3 – an industry standard software programme. Forclarity and ease of understanding a “Time – Chainage Diagram” (TCD) was generated from the P3programme using a software package developed by PCF Ltd. The construction programme ispresented in Appendix A – Time Chainage Report TCDT3HS and summarised below:
Commencement Date June 2007
Complete all tunnel drives for Stage 1 52 months
Complete tunnel fit out for Stage 1 72 months
Commence Revenue Stage 1 83 months
Commence Revenue Stage 2 85 months
Commence Revenue Stage 3 87 months
The construction programmes critical path follows the tunnel drive from Pudding Mill Lane Portal toFisher Street Shaft where the average length of the tunnel drive is approximately 8395m. This is
Cross London Rail Links Limited Mott MacDonald
Crossrail Construction Programme - Programme Impact without Hanbury Street Shaft as a TBM Launch Site
Technical Note No. No. 1D0300-C1N00-00839/A April 2005
9P:\Croydon\MMH\Tunnels\201985\Reports\Technical Notes\839 Programme Impact without Hanbury Shaft as a TBM Launch Site\Revision A - Final Issue\1D0300-C1N00-00839 A.doc/KLD
compared with the average length of the tunnel drive from Royal Oak Portal to Fisher Street Shaft,which is approximately 5102m. This results in a significant imbalance in the construction programmewith the section between Pudding Mill Lane and Fisher Street being approximately 65% longer thanthe section between Royal Oak and Fisher Street. To reduce this imbalance, the programme for tunnelfit out was accelerated by the introduction of two work fronts working from both Fisher Street Shaftand Pudding Mill Lane Portal towards Stepney Green Shaft for tunnel cleanout and installation oftrack bed, walkways and building services for the tunnel section between Pudding Mill Lane andFisher Street. This allows for early commencement of the installation of rail, overhead line equipmentand systems works which will be serviced from Pudding Mill Lane Portal. For the section betweenRoyal Oak and Fisher Street, tunnel fit out will be serviced from the portal at Royal Oak.
Although the tunnel section between Royal Oak Portal and Fisher Street Shaft is completed first,systems testing and trial running cannot commence until after the railway between Pudding Mill LanePortal and Fisher Street Shaft is operational. This is because there is no crossover where the trainsfrom the west can be turned until east of Farringdon Station. This can be accessed when the tunnelfrom the east are complete.
4.1.2 Option 2 - Tunnel Drive Mid-point at Farringdon Station
(i) Tunnel Drive Strategy
The following tunnel drive strategy and average tunnelling rate has been adopted for Option 2:
Tunnel Drive TBM Type Planned Average Tunnelling Rate
Royal Oak Portal to FarringdonStation;
Earth Pressure Balance 40m/wk – Royal Oak to Paddington
65m/wk – Paddington to Farringdon
Pudding Mill Lane toFarringdon Station;
Earth Pressure Balance 77m/wk – PML to Stepney Green
70m/wk – Stepney Green to Farringdon
Isle of Dogs Station to StepneyGreen Shaft;
Earth Pressure Balance 65m/wk
Limmo Shaft to Isle of DogsStation; and
Earth Pressure Balance 60m/wk
Limmo Shaft to Victoria DockPortal
Earth Pressure Balance 60m/wk
Option 2 reduces the tunnel drive length imbalance of Option 1 by using Farringdon Station as thetunnel drive mid point and in doing so, creates additional constraints to the selection of tunnellingmethod and progress rate due to poorer ground conditions in the Farringdon area. The additionalconstraints result from the use of a more elaborate and heavier earth pressure balance tunnellingmachine (EPBM) required for Option 2 compared with a less elaborate and lighter open face
Cross London Rail Links Limited Mott MacDonald
Crossrail Construction Programme - Programme Impact without Hanbury Street Shaft as a TBM Launch Site
Technical Note No. No. 1D0300-C1N00-00839/A April 2005
10P:\Croydon\MMH\Tunnels\201985\Reports\Technical Notes\839 Programme Impact without Hanbury Shaft as a TBM Launch Site\Revision A - Final Issue\1D0300-C1N00-00839 A.doc/KLD
tunnelling machine used in the base case and Option 1. The use of an EPBM between Royal Oak andFarringdon imposes additional risk to the programme and project viability at the proposed Crossrailstations at Paddington and Farringdon, and existing LUL infrastructure at Tottenham Court Road(Northern Line Platform Tunnels) and the Central Line at Holborn. The need to use an EPBM and theimpacts from its use are discussed in more detail below.
Ground Conditions
Option 2 changes the tunnelling machine specification and the progress rate as a result of the poorerground conditions east of Fisher Street Shaft and in the Farringdon area. Immediately to the east ofFisher Street Shaft the tunnels bore into the Lambeth Group, staying in that deposit to FarringdonStation. At Farringdon Station itself the invert of the tunnels bore into the underlying Thanet Sands.Refer to Figure 4.1 below.
The levels reported for the top of the Lambeth Group, found at the base of the London Clay, indicatesignificant structural disturbance of the strata in the vicinity of Farringdon since the levels fall fromapproximately 100mATD in the north-west to 82.6mATD in the south-east, which are matched byincreases in the thickness of the London Clay. This is believed to reflect the presence of a number offaults since a similar fall in level is evident for the Chalk-Thanet Sand interface where this has beenproven by drilling.
Figure 4.1: Ground Conditions between Fisher Street & Hanbury Street Shafts
Cross London Rail Links Limited Mott MacDonald
Crossrail Construction Programme - Programme Impact without Hanbury Street Shaft as a TBM Launch Site
Technical Note No. No. 1D0300-C1N00-00839/A April 2005
11P:\Croydon\MMH\Tunnels\201985\Reports\Technical Notes\839 Programme Impact without Hanbury Shaft as a TBM Launch Site\Revision A - Final Issue\1D0300-C1N00-00839 A.doc/KLD
From past historical experience of tunnelling through fault zones in London Clay on the Jubilee LineExtension Project the faulting mentioned is unlikely to be encountered as a single discrete plane ofdisplacement but is likely to be exposed as a series of complex cross cutting and intersecting generallynon-linear fault surfaces with both vertical and lateral displacements. These create blocks within theground which can be adversely arranged and oriented for face stability during tunnelling. Thetunnelling methods adopted for construction need to address this structural variability.
Within the Harwich Formation and the Upper Lambeth Group the vertical and lateral variation inlithologies mean that local trapped aquifers are often found which are not linked to either main aquifer,and the water they contain can be under pressure. These unpredictable bodies of groundwater can bedifficult to locate and give rise to problems during construction.
For these reasons, a closed face earth pressure balance tunnelling machine (EPBM) has been adoptedfor Option 2, with an average advance rate of 65m/week compared with 71m/week used in both ICP17(the base case) and Option 1.
Paddington Station
The construction sequence for interfacing the tunnel drives with the proposed Crossrail station atPaddington assumes the following for all options including the base case:
a) Use the first tunnelling machine reaching Paddington to bore the temporary central tunnel betweenthe two work shafts, which are located at either end of the station. The second tunnelling machinereaching Paddington will be disassembled, lifted-up from western work shaft and re-launched atthe eastern work shaft to continue its operation eastward. The sequence for the operations is listedbelow:
i) First tunnelling machine breaks through the outer diaphragm wall of the western work shaft;slide the machine laterally to centre-line of the station; break through the interim diaphragmwall to commence boring the central temporary tunnel (245m long) to the eastern work shaftand between the already-installed intermediate piles; re-assemble tunnelling machine trainsequentially behind.
ii) Break through the interim diaphragm wall of the eastern work shaft; within the eastern workshaft, slide the tunnelling machine laterally back to the original tunnel alignment; re-assembletunnelling machine train; breakout through the east end diaphragm wall and proceed withbored running tunnel beyond the station. Use the temporary central tunnel for transport ofexcavated material through station back to the construction site at Royal Oak and/or to railhead.
iii) Second tunnelling machine breaks through the diaphragm wall of the western work shaft;dismantle and lift out TBM from this shaft; transport on the surface to the eastern work shaft;lower back onto the correct alignment within the shaft and reassemble machine back-up; breakout from the eastern end diaphragm wall and proceed with second tunnel beyond the station.The central tunnel will be used by both machines for transporting excavated material back toRoyal Oak Portal for onward transport to the designated disposal sites.
Cross London Rail Links Limited Mott MacDonald
Crossrail Construction Programme - Programme Impact without Hanbury Street Shaft as a TBM Launch Site
Technical Note No. No. 1D0300-C1N00-00839/A April 2005
12P:\Croydon\MMH\Tunnels\201985\Reports\Technical Notes\839 Programme Impact without Hanbury Shaft as a TBM Launch Site\Revision A - Final Issue\1D0300-C1N00-00839 A.doc/KLD
b) Construct station box by top-down method (sequence of construction based on casting a slabfollowed by subsequent excavation below that slab). To minimise the impact at street level fromthe handling and transportation of large volumes of excavated material, the bulk of this materialwill be discharged down to rail level for transport underground westward to the Royal Oak site(i.e. in addition to the running tunnel excavated material).
The above sequence is likely to be modified and the programme extended by two months for Option 2for the following reasons:
• Tunnelling machine back up equipment is of longer length for an EPBM, and re-launch of the firstTBM described above will be more difficult due to the greater number of components andcomplexity of operation;
• Construction of the temporary tunnel will take longer using an EPBM due to re-launchrequirements of the machine and slower progress rates in constrained conditions;
• Dismantling and re-assembly of the second TBM will take longer due to the heavier componentsand the need to have a greater portion of the back up equipment assembled for an EPBM. Thislatter requirement would result in the need to construct a larger western work shaft at PaddingtonStation, resulting in additional programme to the station works and greater impact to adjacentlisted structures.
Northern Line at Tottenham Court Road Station
A critical interface is the crossing of the Northern Line platform tunnels at Tottenham Court RoadStation, where the eastbound Crossrail tunnel passes closely above (with approximately 0.5mclearance) the existing cast iron lined platform tunnels. The westbound tunnel passes with clearancesabove 2m. In the base case and Option 1 tunnelling strategies, this crossing is achieved using an openface shield which is considerably lighter in weight than a closed-face TBM, limiting the impact on theexisting tunnels.
Transferring a closed-face TBM over these tunnels will impose much greater loads on the linings andexpose the LUL infrastructure to greater risk of collapse than with the open-face shield. These loadsare mitigated to some extent by advance construction of a sprayed concrete tunnel across the existingtunnels. However, even with this safeguard, there is a high risk that structural assessment of theexisting platform tunnel linings will identify that additional supports are required within the NorthernLine Platform tunnels. Incorporation of such internal structural support would require blockades ofthe Northern Line resulting in significant disruption to LUL operations with a probable closure of theNorthern Line services for a period of up to two months.
Central Line between Tottenham Court Road Station and Fisher Street Shaft
The use of a heavier closed face TBM will impose greater loads on the linings of the Central Linetunnels between Tottenham Court Road Station and Fisher Street Shaft where clearances are less than0.5m. Structural support will be required to maintain the integrity of the existing Central Line tunnellinings. Incorporation of such internal structural support would require blockades of the Central Lineresulting in significant disruption to LUL operations with a probable closure of services for a period ofup to three months.
Cross London Rail Links Limited Mott MacDonald
Crossrail Construction Programme - Programme Impact without Hanbury Street Shaft as a TBM Launch Site
Technical Note No. No. 1D0300-C1N00-00839/A April 2005
13P:\Croydon\MMH\Tunnels\201985\Reports\Technical Notes\839 Programme Impact without Hanbury Shaft as a TBM Launch Site\Revision A - Final Issue\1D0300-C1N00-00839 A.doc/KLD
Interface with Farringdon Station
Removal of TBM components will be required at Farringdon Station. At the end of the drives, thesteel skins of the TBMs would be left in the ground, the machine backup modules and some internalcomponents within the steel skin removed via the tunnels back to the portals, and the cutter headsbroken up and removed via the station access construction shafts. At the western end of FarringdonStation this can be achieved with minimum effect on the overall programme. At the eastern end of thestation there is limited access to the surface and a one month delay in the station programme atplatform level has been allowed for to transfer the cutter head components from the eastern end to thewestern end for subsequent removal to surface.
(ii) Programme
The programme was developed using Primavera P3 – an industry standard software programme. Forclarity and ease of understanding a “Time – Chainage Diagram” (TCD) was generated from the P3programme using a software package developed by PCF Ltd. The construction programme ispresented in Appendix A – Time Chainage Report TCDT4HS and summarised below:
Commencement Date June 2007
Complete all tunnel drives for Stage 1 48 months
Complete tunnel fit out for Stage 1 69 months
Commence Revenue Stage 1 80 months
Commence Revenue Stage 2 83 months
Commence Revenue Stage 3 85 months
The critical path follows the tunnel drive from Pudding Mill Lane Portal to Farringdon Station withthe tunnel drive average length being approximately 6795m. This is compared with the tunnel drivelength from Royal Oak Portal to Farringdon Station which averages approximately 6214m. Toaccelerate the tunnel fit out programme between Pudding Mill Lane Portal and Farringdon Station,tunnel cleanout and the installation of track bed, walkways and building services is planned from bothFarringdon and Pudding Mill Lane to allow early commencement of the installation of rail, overheadline equipment and systems works which will be serviced from Pudding Mill Lane Portal. Tunnel fitout between Royal Oak and Farringdon will be serviced from the portal at Royal Oak.
Although the tunnel section between Royal Oak Portal and Farringdon Station is completed first,systems testing, commissioning and trial running cannot commence until after the railway betweenPudding Mill Lane Portal and Fisher Street Shaft is operational. This is because there is no crossoverwhere trains from the west can be turned until east of Farringdon Station. This can only be accessedwhen the tunnel from the east are complete.
Cross London Rail Links Limited Mott MacDonald
Crossrail Construction Programme - Programme Impact without Hanbury Street Shaft as a TBM Launch Site
Technical Note No. No. 1D0300-C1N00-00839/A April 2005
14P:\Croydon\MMH\Tunnels\201985\Reports\Technical Notes\839 Programme Impact without Hanbury Shaft as a TBM Launch Site\Revision A - Final Issue\1D0300-C1N00-00839 A.doc/KLD
5 Review of Tunnelling with Intermediate Tunnelling Site (BaseCase)
5.1 Tunnelling Strategy
To reduce the project wide construction duration and in particular to minimise delay to theconstruction of stations at Liverpool Street and Farringdon, the programme for Crossrail Line 1 wasreviewed to include an intermediate tunnelling site, so as to separate the route into approximately onethird lengths.
To minimise the construction impact of the project, the location of an intermediate tunnelling site wascombined with other Crossrail infrastructure such as stations or intermediate shafts. The stationlocations were defined by the Project and the emergency intervention access shaft locations weredetermined by the need to satisfy HMRI fire life safety regulations for underground railways, whichrequire emergency access points at about 1.0km centres.
The following were identified as potential TBM launch sites:
• Mile End Park Shaft;
• Stepney Green Shaft;
• Whitechapel Station;
• Hanbury Street Shaft;
• Farringdon Station.
Each of the above potential TBM launch sites were assessed with respect to programme, feasibility ofthe site in terms of tunnelling and logistics, and environmental implications. A review of the potentialTBM launch sites is presented in Appendix B.
The optimum construction programme was achieved by locating the intermediate tunnelling site tocoincide with Hanbury Street Shaft within Spitalfields as it is located at approximately the third pointof the total tunnel length between Royal Oak to Pudding Mill Lane and thereby offering the potentialto balance the TBM drive lengths. By providing a temporary adit from Hanbury Street Shaft to atemporary shaft located within the disused railway lands at Pedley Street, the excavated material fromthe tunnels will be transported to the surface and conveyed to a railhead at Mile End (DevonshireStreet) sidings. The work site at Pedley Street will also be used to locate site offices for tunnellingoperations and for the stockpiling and supply of tunnelling supplies, including tunnel segments. Thissignificantly reduces the impact from lorries around Hanbury Street with the site entrance to thePedley Street work site being from Vallance Road. The use of the Hanbury Street site for the launchof TBMs has been assessed as being an adequate site3 when used in conjunction with the work site atPedley Street.
The tunnel drive strategy and tunnelling rates are those currently adopted by the Project in programmeICP17 and presented in Section 3.3.
3Refer Technical Note No. 1D0300-C1N00-00838 Hanbury Street TBM Assembly.
Cross London Rail Links Limited Mott MacDonald
Crossrail Construction Programme - Programme Impact without Hanbury Street Shaft as a TBM Launch Site
Technical Note No. No. 1D0300-C1N00-00839/A April 2005
15P:\Croydon\MMH\Tunnels\201985\Reports\Technical Notes\839 Programme Impact without Hanbury Shaft as a TBM Launch Site\Revision A - Final Issue\1D0300-C1N00-00839 A.doc/KLD
5.2 Programme
The programme was developed using Primavera P3 – an industry standard software programme. Forclarity and ease of understanding a “Time – Chainage Diagram” (TCD) was generated from the P3programme using a software package developed by PCF Ltd. The construction programme ispresented in Appendix A – Time Chainage Report TCD17 (aka. ICP17) and summarised below:
Commencement Date June 2007
Complete all tunnel drives for Stage 1 37 months
Complete tunnel fit out for Stage 1 53 months
Commence Revenue Stage 1 64 months
Commence Revenue Stage 2 71 months
Commence Revenue Stage 3 71 months
The tunnel drive strategy offers an optimum construction programme with the principal tunnel drivesbeing integral with the station works and thereby minimising periods of inactivity. It also offers aconstruction programme which is compatible with the Project’s revenue service strategy whereStage 1 is operational whilst Stage 2 is being completed.
Cross London Rail Links Limited Mott MacDonald
Crossrail Construction Programme - Programme Impact without Hanbury Street Shaft as a TBM Launch Site
Technical Note No. No. 1D0300-C1N00-00839/A April 2005
16P:\Croydon\MMH\Tunnels\201985\Reports\Technical Notes\839 Programme Impact without Hanbury Shaft as a TBM Launch Site\Revision A - Final Issue\1D0300-C1N00-00839 A.doc/KLD
6 Programme Comparison
Comparisons of the base case (ICP17) with the two alternative tunnelling options are summarisedbelow in Table 6.1 and Table 6.2 for Option 1 and Option 2 respectively.
In each case, Stage 3 of the revenue service is considered to the benchmark for financial planning, asthis is the stage when Crossrail Line 1 becomes self funding.
6.1 Option 1
Table 6.1: Option 1 - Programme with Tunnel Drive Mid-point at Fisher Street Shaft
Programme WithoutIntermediate
Tunnelling Site(TCDT3HS)
Programme WithIntermediate
Tunnelling Site(ICP17)
Programme savingusing intermediatetunnelling site at
Hanbury Street Shaft
Commencement Date June 2007 June 2007 0 Months
Complete all tunneldrives for Stage 1
52 Months 37 Months 15 Months
Complete all tunnelfit out for Stage 1
72 Months 53 Months 19 Months
Commence RevenueStage 1
83 Months 64 Months 19 Months
Commence RevenueStage 2
85 Months 71 Months 14 Months
Commence RevenueStage 3
87 Months 71 Months 16 Months
A 19 month or 22% saving in programme is achieved for Stage 1 of the revenue service betweenLiverpool Street and Isle of Dogs Stations by using Hanbury Street Shaft as an intermediate tunnellingsite. This saving is reduced to 16 months or 18% for Stage 3 of the revenue service allowing therailway to operate between Paddington to Isle of Dogs and includes services to Shenfield.
Cross London Rail Links Limited Mott MacDonald
Crossrail Construction Programme - Programme Impact without Hanbury Street Shaft as a TBM Launch Site
Technical Note No. No. 1D0300-C1N00-00839/A April 2005
17P:\Croydon\MMH\Tunnels\201985\Reports\Technical Notes\839 Programme Impact without Hanbury Shaft as a TBM Launch Site\Revision A - Final Issue\1D0300-C1N00-00839 A.doc/KLD
6.2 Option 2
Table 6.2: Option 2 - Programme with Tunnel Drive Mid-point at Farringdon Station
Programme WithoutIntermediate
Tunnelling Site(TCDT4HS)
Programme WithIntermediate
Tunnelling Site(ICP17)
Programme savingusing intermediatetunnelling site at
Hanbury Street Shaft
Commencement Date June 2007 June 2007 0 Months
Complete all tunneldrives for Stage 1
48 Months 37 Months 11 Months
Complete all tunnelfit out for Stage 1
69 Months 53 Months 13 Months
Commence RevenueStage 1
80 Months 64 Months 16 Months
Commence RevenueStage 2
83 Months 71 Months 12 Months
Commence RevenueStage 3
85 Months 71 Months 14 Months
A 16 month or 20% saving in programme is achieved for Stage 1 of the revenue service betweenLiverpool Street and Isle of Dogs Stations by using an intermediate tunnelling within Spitalfields.This saving is reduced to 14 months or 16.5% for Stage 3 of the revenue service allowing the railwayto operate between Paddington to Isle of Dogs and includes services to Shenfield.
6.3 Additional Considerations
The above comparison assesses the impact on construction programme by adopting tunnelling ratesapplicable to the ground conditions and TBM type for each of the tunnel drives and their options.Additional considerations related to logistical issues arise when the tunnel drive length increasesresulting in extra risk to the tunnelling operations. These risks include:
• Interface between the completed tunnel drive from Isle of Dogs Station to Stepney Green Shaftand the continuing tunnelling operations for the drive from Pudding Mill Lane, with respect todecommissioning the TBMs for the completed drive whilst ensuring the incoming tunnellingsupplies, including segments, and the removal of excavated materials for the TBMs headingtowards central London are not interrupted. It is proposed that the TBM skins will be left in situ atthe end of the Isle of Dogs to Stepney Green tunnel drive and that the machine components andback up modules would be dismantled and transported back along the tunnel to the station box atIsle of Dogs. The principal risks are during the initial break through of the TBMs and during thedismantling process which will require the use of heavy lifting equipment, especially for the cutter
Cross London Rail Links Limited Mott MacDonald
Crossrail Construction Programme - Programme Impact without Hanbury Street Shaft as a TBM Launch Site
Technical Note No. No. 1D0300-C1N00-00839/A April 2005
18P:\Croydon\MMH\Tunnels\201985\Reports\Technical Notes\839 Programme Impact without Hanbury Shaft as a TBM Launch Site\Revision A - Final Issue\1D0300-C1N00-00839 A.doc/KLD
head. Whilst the tunnel drive from Isle of Dogs is not critical to the overall constructionprogramme, delays will be incurred during the TBM decommissioning process for Options 1 and 2that are not incurred for the base case.
• Supply of tunnel segments and other tunnelling supplies to TBM will be hindered by theadditional travel time from portal to TBM. This is likely to require additional passing points alongthe tunnel for the segment trains and this may impact on the size of the tunnels at localised pointsto accommodate this. Hand excavation would be required to achieve the tunnel enlargements afterthe TBMs have passed and this will delay the TBMs and increase the construction programme;
• Increased length of conveyor for carrying excavated material from TBM to portal increases therisk of breakdown;
• Increased length for supply of ventilation during tunnelling.
Cross London Rail Links Limited Mott MacDonald
Crossrail Construction Programme - Programme Impact without Hanbury Street Shaft as a TBM Launch Site
Technical Note No. No. 1D0300-C1N00-00839/A April 2005
19P:\Croydon\MMH\Tunnels\201985\Reports\Technical Notes\839 Programme Impact without Hanbury Shaft as a TBM Launch Site\Revision A - Final Issue\1D0300-C1N00-00839 A.doc/KLD
7 Conclusions
This report compares the impacts on the construction programme for the central tunnel section ofCrossrail Line 1 between Royal Oak and Pudding Mill Lane Portals both with and without anintermediate tunnelling site. It is concluded that the incorporation of an intermediate tunnelling sitelocated at Hanbury Street Shaft has significant construction programme benefits.
The use of a tunnelling site comprising the Hanbury Street Shaft and Pedley Street working sites (thebase case) is fundamental to the success of Crossrail Line 1 as it:
• Introduces Stage 1 revenue services, between Liverpool Street and Isle of Dogs Stations, 19months earlier for Option 1, and 16 months earlier for Option 2 than if tunnelling from PuddingMill Lane Portal without the Hanbury Street Shaft site. This represents a programme saving of22% and 20% respectively for the base case;
• Introduces Stage 3 revenue services, between Paddington to Shenfield and to Isle of Dogs, 16months earlier for Option 1, and 14 months earlier for Option 2 than if tunnelling from PuddingMill Lane Portal without the Hanbury Street Shaft site. This represents a programme saving of18% and 16.5% respectively for the base case. Stage 3 of the revenue service is considered thebenchmark for financial planning, as this is the stage when Crossrail Line 1 becomes self funding;
• Completes construction within the six year time frame for funding, as developed by theDepartment for Transport;
• Optimises the project wide construction programme by reducing periods of inactivity betweenstation and railway tunnel construction durations;
• Is compatible with the revenue service strategy where the eastern tunnel section (Stage 1) iscompleted in advance of the western tunnel section (Stage 2), thus reducing delay in thecommencement of the Stage 1 revenue service;
• Reduces the Project’s risk of a delay in the introduction of revenue services, as a result oftunnelling, by adopting four shorter tunnel drive lengths between Royal Oak and Pudding MillLane Portals. Therefore should construction difficulties slow or stop one of the tunnel drives thereis more opportunity for the other tunnel drives to compensate;
• Does not require London Underground Limited to suspend services on the Northern Line andCentral Line to allow installation of internal structural support to facilitate the crossing of EPBTBMs, as required in Option 2;
• Reduces opportunity for programme delay and increased risk from logistical issues that arise whenthe tunnel drive length increases.
It is therefore recommended that the use of Hanbury Street Shaft as an intermediate tunnelling site bemaintained as part of the tunnelling strategy for Crossrail Line 1.
Cross London Rail Links Limited Mott MacDonald
Crossrail Construction Programme - Programme Impact without Hanbury Street Shaft as a TBM Launch Site
Technical Note No. No. 1D0300-C1N00-00839/A April 2005
A-1P:\Croydon\MMH\Tunnels\201985\Reports\Technical Notes\839 Programme Impact without Hanbury Shaft as a TBM Launch Site\Revision A - Final Issue\1D0300-C1N00-00839 A.doc/KLD
Appendix A Time Chainage Programmes
Time Chainage Report TCDT3HS – Tunnelling to Fisher Street Shaft without an intermediatetunnelling site at Hanbury Street Shaft (Option 1)
Time Chainage Report TCDT4HS – Tunnelling to Farringdon Station without an intermediatetunnelling site at Hanbury Street Shaft (Option 2)
Time Chainage Report TCD17 (ICP17) – Tunnelling with an intermediate tunnelling site at HanburyStreet Shaft (Base Case)
J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S
J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S
2005 2006 2007 2008 2009 2010 2011 2012 2013 2014
2005 2006 2007 2008 2009 2010 2011 2012 2013 2014
Crossrail Facilities Buildings & Civil
Crossrail Track & Rail
Exec & Conc to Cut & CoverC&C Diaph Walls
Enabling WorksSettlement Monitoring
Advanced Services Diversions
Exc. & Convc base East box
Exc. & Convc base West box
VentTunnel Addits
Advanced Services Diversions Enabling Works
Settlement Monitoring
CO
MM
UN
ICA
TIO
NS
Enabling Works
Advanced Services Diversions
SIG
NALL
ING
Acc adit & break up
Advanced Services Diversions
Advanced Services DiversionsSCL Excavation Station Tunnels
Advanced Services DiversionsCofferdam
Syst
ems
Test
&Co
mm
issi
onin
g
Services Diversions/Enabling
Construct Goslett Yard BoxAstoria Demo
Goslett Yard Demo
Advanced Services Diversions Sink Shaft Vent Tunnels adits
Services diversions/Enabling
Advanced Services Diversion
DLR StationAccess culvert
Station Fit out
Station Fit out
Shaft Fit out
Site Setupinc Rail Sidings
Enabling Works
MGT
OH
LE
WB
&EB
Plat
form
Stru
ctur
eEnabling Works
FIT
OUT
Enabling Works
MGT
Prep forTBM's
Main Station Structure
Site
Set
up
Syst
ems
Test
&Co
mm
issi
onin
g
ExcAdit
Fareham St - Demo Sink Shaft
Site Set Up
Site Set Up
DLR Viaduct
Prep forTBM's
Construct box
Retained Cut
Site
Setu
p
Exc. & Primary Lining
Phased Demo Dean St
HV&
LV
Site
Setu
p
Enabling Works
Prep for
TBM
's
Site
Setu
p
Station InfillStructure
DLR Puding Mill Station
Spoil Loading Installation
Phased Piling SCL ExcavationStation Tunnels
Construct Piled Box & Tunnel Adits
Secondary concretelining to Station
Sin
kS
haft
Diaph.WallCentral box
Exc.Intervention Passages
Exc. & Conc Station Boxinc base,int and roofslab
Seco
ndar
yco
ncre
telin
ings
toSt
atio
ns
COM
MUN
ICAT
IONS
FIT
OU
T
SCL Excavate Station Tunnels
OHL
E
WB
&EB
Plat
form
Stru
ctur
e
SecondaryLinings
Hanover Sq.demo
Rtg Walls South box
Vent Tunnels
Prep forTBM's
Prep
for
TBM
's
HV&
LV
Seco
ndar
yco
ncre
telin
ing
toSt
atio
n
WB & EBPlatform Structures
Construct Box
Form EastBox SD Walls
Roa
dD
eck
WB & EBPlatformStructure
Sink Shaft
Interface Tunnels
Station Fit out
OH
LEH
V&
LVC
OM
MU
NIC
ATI
ON
S
FIT
OU
T
OH
LE
HV
&LV
OH
LE
FIT
OU
T
Exc. & line interv'n passages
WB & EBPlatform Structure
Prep forTBM's
Secondary concretelinings to StationsSCL Excavation Station Tunnels
HV&
LV
FIT
OU
T
SCL Excavation Station Tunnels
Prep
for
TBM
's
Station Fit out
Construct piled box&tunnel adits
SIG
NA
LLIN
G
Site SetupNew Yard
SIG
NA
LLIN
G
Settlement Monitoring
SIG
NA
LLIN
G
Construct VentShaft & Tmp Aditsto Station Tunnel
Construct BoxMGTExc. & Line Shaft
SIG
NA
LLIN
G
Construct Astoria St Box
SIG
NA
LLIN
G
Enabling Works
Launch Chamber
Construct Davies St Box
Sink Shaft
Deliver, Erect &Commission TBM'sTBM Design, Manufacture & Assembly
Clea
n&
conc
rete
track
bed
-W
BPA
Dto
porta
l
Trac
kwor
kEB
Port
alto
Padd
ingt
on
Trac
kwor
kW
BPo
rtal t
oPa
ddin
gton
Wal
kway
&bu
ildin
gse
rvic
esW
BPA
Dto
Porta
l
New EWS Facility
ConstructPlatform
Foundations x3Construct Platforms x3Site Prep
Install OHLE& Signalling
ConstructRetaining
Wall
Advanced Services Diversions
Backfill
Launch Chamber
Enabling Works
EBTB
M2
tunn
eldr
ive
Padd
ingt
onto
Bond
St.
WB
TBM
1tu
nnel
driv
ePa
ddin
gton
toBo
ndSt
.
Clea
nou
t &co
ncre
tetra
ckbe
dW
B- B
OS- H
yde
Pk
Clea
nou
t &tra
ckbe
dW
BHy
dePk
-PAD
Trac
kwor
kEB
Padd
ingt
onto
Bond
St.
Trac
kwor
kW
BPa
ddin
gton
toBo
ndSt
reet
Wal
kway
&bu
ildin
gse
rvic
esW
BBO
S-Hy
dePk
Wal
kway
&bu
i ldin
gse
rvic
esW
BHy
dePk
-PAD
Prep for
TBM
Prep for
TBMRtg Walls
West box Transfer EB TBM to East End
Arrange TBMin East Box
Advanced Services Diversions Enabling Works Exc. & PrimaryLining
HV
&LVO
HLE
EBTB
M2
tunn
eldr
ive
Bond
St.to
Totte
nham
Ct.R
d
WB
TBM
1tu
nnel
driv
eBo
ndSt
.toTo
ttenh
amCt
.Rd
FIT
OU
T
Clea
nou
t &co
ncre
tetra
ckbe
dW
BTC
Rto
Bond
Str
Trac
kwor
kEB
Bond
Stre
etto
TCR
Trac
kwor
kW
BBo
ndSt
reet
toTC
R
Advanced Services Diversions
Site setup
Com
bine
dSy
stem
Test
&Com
mis
sion
ing
WBP
-FAR
EBTB
M2
driv
eTo
ttenh
amCo
urt R
dto
Fish
erSt
.
WB
TBM1
driv
e Tot
tenh
amCo
urt R
dto
Fish
erSt
.
Clea
nou
t&co
ncre
tetra
ckbe
dW
BFi
sher
Stto
TCR
Trac
kwor
kEB
TCR
toFi
sher
St.s
haft
Trac
kwor
kW
BTC
Rto
Fish
erSt
. sha
ft
Wal
kway
&bu
ildin
gse
rvic
esEB
TCR
toFi
sher
St
Advanced Services Diversions
Advanced Services DiversionsSec Lining
Exc. & Primary LiningVent Tunnels & Adits
COM
MUN
ICAT
IONS
HV&
LVOHL
E
EBTB
Mtu
nnel
driv
eLI
Sto
FAR
Xove
r
WB
TBM
tunn
eldr
ive
LIS
toFA
RXo
ver
SIG
NALL
ING
FIT
OUT
Wal
kway
&bui
ld'g
serv
ices
EBFA
Rto
LIS
EBTB
Mtu
nnel
driv
eFi
sher
Stto
Farri
ngdo
n
WB
TBM
tunn
eldr
ive
Fish
erSt
.toFa
rring
don
Clea
nou
t&co
ncre
tetra
ckbe
dW
BFA
Rto
Fish
erSt
Wal
kway
&bu
ildin
gse
rvic
esW
BFi
sher
Stto
FARR
Crossover Tunnel Crossover lininginvert WB
Settlement Monitoring
COM
MUN
ICAT
IONS
hv&
lv
OHL
E
EBTB
Mtu
nnel
driv
eHa
nbur
ySt
.toW
hite
chap
el
WB
TBM
tunn
eldr
ive
Hanb
ury
St.to
Whi
tech
apel
Clea
n&
track
bed
conc
. -W
BHa
nto
Whi
tech
apel
Wal
kway
&bui
ld'g
serv
ices
EBHa
nto
Whi
tech
apel
COM
MUN
ICAT
IONS
EBTB
MTun
neld
rive
Hanb
ury-
Live
rpoo
lSt.
WB
TBM
Tunn
eldr
iveH
anbu
ry-L
iver
pool
St.
SIG
NALL
ING
FIT
OUT
Trac
kwor
kW
BHa
n.to
Live
rpoo
lSt
MGT Exc. & line shafts
Setup Railhead
E/B Chamber
Form EPBM adit chambers & backshunt
Settlement Monitoring
CO
MM
UN
ICA
TIO
NS
OH
LE
EBTB
Mtu
nnel
driv
eSt
epne
yGr
een
toW
hite
chap
el
WB
TBM
tunn
eldr
ive
Step
ney
Gre
ento
Whi
tech
apel
SIG
NA
LLIN
G
FIT
OU
T
Clea
n&
conc
.trac
kbed
WB
Whi
tech
apel
toSG
Trac
kwor
kW
BSG
toW
hite
chap
el
Wal
kway
&bui
ldin
gse
rvic
esW
BSG
toW
hite
chap
el
Del,Erec& Comm TBM's
EBTB
Mtu
nnel
driv
eLo
wel
lStt
oSt
epne
yG
reen
EBTB
Mtu
nnel
driv
eIO
Dto
Low
ellS
t
Syst
emw
ide
inst
alla
tion
EBIO
D-SG
WB
Cle
anou
t&Tr
ackb
edIO
D-S
G
Trac
kwor
kW
BIO
D-SG
Wal
kway
&Bui
ld'g
serv
ices
WB
IOD-
SG
Sink CaissonCaissionPreparation
Ground TreatmentRunning Tunnels
Mob & Grd TreatmentEnabling Works Sink Escape Shaft
Advanced Services Diversions MGTEnabling Works Sec LiningExc & Line Shaft Tunnels & Adits
Loca
lSys
tem
sTe
stin
gPU
DD-IO
D--W
hite
chap
el-F
ARR
Loca
lSys
tem
sTe
stin
gFA
R-Po
rtal
MGTEnabling Works
EB ChamberExc. & line EB shaft
Exc. & line WB shaftWB Chamber
Stat
icTe
stin
gW
BW
est P
orta
l-FAR
Stat
icTe
stin
gEB
Wes
t Por
tal-F
AR
Stat
icTe
stin
gW
BW
hite
chap
el-F
ARSt
atic
Test
ing
WB
PUDD
-IOD-
Whi
tech
apel
Syst
ems
Test
&Co
mm
issi
onin
g
Tria
lRun
ning
Sta
ge2
Tria
lRun
ning
Sta
ge1
WB
TBM
tunn
eldr
ive
IOD
toLo
wel
lSt
WB
TBM
tunn
eldr
ive
Low
ellS
tto
Step
ney
Gre
en
Sink shaft
Settlement / Ground Monitoring HAS
Advanced Services Diversions
Settlement / Ground Monitoring - west end TCR
Dismantle WBTBM5 at Whitechapel
Settlement / Ground Monitoring PML
WB
Tunn
els
Syst
ems
Inst
alla
tion
PUD
D-E
lean
orSt
EB
TBM
driv
eE
lean
or-M
ileE
ndW
BTB
Mdr
ive
Ele
anor
-Mile
End
WB
Tunn
elcl
ean
out&
Trac
kbed
Elea
nor-M
ileEn
d
WB
Trac
kwor
kin
stal
latio
nEl
eano
r-Mile
End
WB
Wal
kway
&E&M
Serv
ices
Elea
nor-M
ileEn
d
EB
TBM
driv
eM
ileE
nd-S
tepn
eyG
reen
WB
TBM
driv
esM
ileE
nd-S
tep.
Gre
en
Essex Wharf Stage 1 Essex WharfStage 2
Essex WharfStage 3
Essex WharfStage 4 Essex Wharf Stage 5
OH
LE
OH
LE
FIT
OU
T
OH
LE
Fito
ut
Sink Shaft Vent Tunnel adits
PUDD Cut & Cover
City Mills Bridge
Deliver,Erect,Comm.TBM
DLR Embankment 2PUDD Diaph.WallsLaunch chamber
Marshgate LaneMill Lane CB
Procure TBM
PUDD Retained Cut
Construct Box Prep.for TBM's
Form WestBox SD Walls
Site setup
Ventilation Passage
Air Intake/Stair structSite Set up
Construct Box
Settlement/Background Monitoring
Com
bine
dS
yste
mTe
st&
Com
mis
sion
ing
PU
DD
-FA
R
Settlement / Ground Monitoring ELS
Station Fit out
Settlement / Ground Monitoring PAD
Settlement / Ground Monitoring - west end BOS
Settlement / Ground Monitoring LIS
Settlement / Ground Monitoring HES
Settlement / Ground Monitoring WHI
Settlement / Ground Monitoring IOD
OHL
EPo
rtal s
truct
ure
mod
s.
OHL
E/Si
gnal
stru
ct.s
horte
ning
mod
s
Option 1Crossrail Time ChainageTCDT3HSTunnel to Fisher St(not using Hanbury St)
13324Eleanor St Shaft
Mile End Park Shaft
Lowell Stree Vent Shaft
Stepney Green E&WVent Shaft & Turnouts
Central Shaft
10130
10285
10442
9952West Shaft
Hanbury Street Vent Shaft
9500
9532
Pedley StShaft
4716
4888
5060
3654
3820
3986Temp access Shaft East
����
����
��
����
��
����
����
��
����
��
���
����
�
����
��
���
����
�
����
��
Cut & Cover
Open Cut
@ Grade
816
520
210
������������������������������������������������
Roy
alO
akPo
rtal
2225Hyde Park Vent shaft
5825Fisher Street Vent Shaft
���
1578
1245
1410
Pudd
ing
Mill
Lane
14579
Park Lane Vent Shaft 3016
14123
7498
7340
7160
6980
7646
8462
8286
8110
Hertsmere Road Shaft13195
Old
Oak
Com
mon
Dep
ot&
sidi
ngs
Start Bored Tunnel
13575
Isle
ofD
ogs
Stat
ion
Live
rpoo
lSt
reet
Stat
ion
Farri
ngdo
nSt
atio
nPa
ddin
gton
Stat
ion
Start Bored Tunnel
Western Limit of Route
Wes
tbou
rne
Park
Bond
Stre
etSt
atio
n
Totte
nham
Cou
rtR
oad
Stat
ion
Whi
tech
apel
Stat
ion
11405
12276
12340
J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S
J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S
2005 2006 2007 2008 2009 2010 2011 2012 2013 2014
2005 2006 2007 2008 2009 2010 2011 2012 2013 2014
CO
MM
UN
ICA
TIO
NS
Deliver, Erect &Commission TBM's
HV
&LV
OH
LE
TBM Design, Manufacture & Assembly
SIG
NA
LLIN
G
FIT
OU
TClea
n&
conc
rete
track
bed
-W
BPA
Dto
porta
l
Trac
kwor
kEB
Porta
l to
Padd
ingt
on
Trac
kwor
kW
BPo
rtal
toPa
ddin
gton
Wal
kway
&bu
ildin
gse
rvic
esW
BPA
Dto
Porta
l
Crossrail Facilities Buildings & Civil
New EWS Facility
Crossrail Track & Rail
ConstructPlatform
Foundations x3Construct Platforms x3Site Prep
Install OHLE& Signalling
ConstructRetaining
Wall
Advanced Services Diversions
BackfillExec & Conc to Cut & CoverC&C Diaph Walls
Launch Chamber
Enabling Works
Enabling WorksSettlement Monitoring
Site Setupinc Rail Sidings
Site SetupNew Yard
HV
&LV
OH
LE
EBTB
M2
tunn
eldr
ive
Padd
ingt
onto
Bond
St.
WB
TBM
1tu
nnel
driv
ePa
ddin
gton
toBo
ndSt
.
SIG
NA
LLIN
G
FIT
OU
T
Clea
nou
t &co
ncre
tetra
ckbe
dW
B- B
OS- H
yde
Pk
Clea
nou
t &tra
ckbe
dW
BHy
dePk
-PAD
Trac
kwor
kEB
Padd
ingt
onto
Bond
St.
Trac
kwor
kW
BPa
ddin
gton
toBo
ndSt
reet
Wal
kway
&bu
ildin
gse
rvic
esW
BBO
S-Hy
dePk
Wal
kway
&bu
i ldin
gse
rvic
esW
BHy
dePk
-PAD
Advanced Services Diversions
Exc. & Convc base East box
Exc. & Conc Station Boxinc base,int and roofslab
Exc. & Convc base West box
Prep for
TBM
Prep for
TBM
Roa
dD
eck
Rtg Walls South box
Rtg WallsWest box
Enabling Works
Sink Shaft
Site
Setu
p
Add'l time to transferEB EPBM to East End
Add'l time to arrangeEPBM in East Box
Advanced Services Diversions Enabling Works
Settlement Monitoring HP
Exc. & PrimaryLining
VentTunnel Addits
Advanced Services Diversions Exc. & line interv'n passagesEnabling Works
Settlement Monitoring
Exc. & Primary LiningVent Tunnels
CO
MM
UN
ICA
TIO
NS
HV
&LVO
HLE
EBTB
M2
tunn
eldr
ive
Bond
St.to
Totte
nham
Ct.R
d
WB
TBM
1tu
nnel
driv
eBo
ndSt
.toTo
ttenh
amCt
.Rd
SIG
NA
LLIN
GFI
TO
UT
Clea
nou
t &co
ncre
tetra
ckbe
dW
BTC
Rto
Bond
Str
Trac
kwor
kEB
Bond
Stre
etto
TCR
Trac
kwor
kW
BBo
ndSt
reet
toTC
R
Construct VentShaft & Tmp Aditsto Station Tunnel
Advanced Services Diversions
Construct BoxMGT
WB & EBPlatform Structure
Prep forTBM's
Secondary concretelinings to StationsSCL Excavation Station Tunnels
Exc. & Line Shaft
Site setup
Com
bine
dSy
stem
Test
&Com
mis
sion
ing
WBP
-FAR
HV&
LV
OH
LE
EBTB
M2
driv
eTo
ttenh
amCo
urt R
dto
Fish
erSt
.
WB
TBM
1 driv
eTo
ttenh
amCo
urt R
dto
Fish
erSt
.
SIG
NA
LLIN
GFI
TO
UT
Clea
nou
t&co
ncre
tetra
ckbe
dW
BFi
sher
Stto
TCR
Trac
kwor
kEB
TCR
toFi
sher
St.s
haft
Trac
kwor
kW
BTC
Rto
Fish
erSt
. sha
ft
Wal
kway
&bu
ildin
gse
rvic
esEB
TCR
toFi
sher
St
Advanced Services Diversions
Construct Astoria St Box
Phased PilingPhased Demo Dean St
WB & EBPlatformStructure
Prep forTBM's
Seco
ndar
yco
ncre
telin
ings
toSt
atio
ns
SCL ExcavationStation Tunnels
Advanced Services Diversions MGTEnabling WorksSec Lining
Exc. & Primary LiningVent Tunnels & Adits
COM
MUN
ICAT
IONS
HV&
LVOHL
E
EBTB
Mtu
nnel
driv
eLI
Sto
FAR
Xove
r
WB
TBM
tunn
eldr
ive
LIS
toFA
RXo
ver
SIG
NALL
ING
FIT
OUT
Wal
kway
&bui
ld'g
serv
ices
EBFA
Rto
LIS
COM
MUN
ICAT
IONS
HV&
LV
OH
LE
EBTB
Mtu
nnel
driv
eFi
sher
Stto
Farri
ngdo
n
WB
TBM
tunn
eldr
ive
Fish
erSt
.toFa
rring
don
SIG
NA
LLIN
G FIT
OU
T
Clea
nou
t&co
ncre
tetra
ckbe
dW
BFA
Rto
Fish
erSt
Wal
kway
&bu
ildin
gse
rvic
esW
BFi
sher
Stto
FARRAdvanced Services Diversions Construct Piled Box & Tunnel Adits
Crossover Tunnel
WB
&EB
Plat
form
Stru
ctur
e
Crossover lininginvert WB
Prep
for
TBM
'sEnabling Works
Seco
ndar
yco
ncre
telin
ing
toSt
atio
n
Settlement/Grd Monitoring FAR
SCL Excavate Station TunnelsSite
Setu
p
COM
MUN
ICAT
IONS
hv&
lv
OHL
E
EBTB
Mtu
nnel
driv
eHa
nbur
ySt
.toW
hite
chap
el
WB
TBM
tunn
eldr
ive
Hanb
ury
St.to
Whi
tech
apel
SIG
NALL
ING
FIT
OUT
Clea
n&
track
bed
conc
. -W
BHa
nto
Whi
tech
apel
Wal
kway
&bui
ld'g
serv
ices
EBHa
nto
Whi
tech
apel
COM
MUN
ICAT
IONS
HV&
LV
OHL
E
EBTB
MTun
neld
rive
Hanb
ury-
Live
rpoo
lSt.
WB
TBM
Tunn
eldr
iveH
anbu
ry-L
iver
pool
St.
SIG
NALL
ING
FIT
OUT
Trac
kwor
kW
BHa
n.to
Live
rpoo
lSt
Acc adit & break up
MGT Exc. & line shafts
Setup Railhead
E/B Chamber
Enabling Works Form EPBM adit chambers & backshunt
Advanced Services Diversions
WB
&EB
Plat
form
Stru
ctur
e
Prep for
TBM
's
Enabling Works
Seco
ndar
yco
ncre
telin
ing
toSt
atio
n
Settlement Monitoring
SCL Excavation Station Tunnels
Site
Setu
p
CO
MM
UN
ICA
TIO
NS
OH
LE
EBTB
Mtu
nnel
driv
eSt
epne
yGr
een
toW
hite
chap
el
WB
TBM
tunn
eldr
ive
Step
ney
Gre
ento
Whi
tech
apel
SIG
NA
LLIN
G
FIT
OU
T
Clea
n&
conc
.trac
kbed
WB
Whi
tech
apel
toSG
Trac
kwor
kW
BSG
toW
hite
chap
el
Wal
kway
&bui
ldin
gse
rvic
esW
BSG
toW
hite
chap
el
Del,Erec& Comm TBM's
EBTB
Mtu
nnel
driv
eLo
wel
lStt
oSt
epne
yG
reen
EBTB
Mtu
nnel
driv
eIO
Dto
Low
ellS
t
Syst
emw
ide
inst
alla
tion
EBIO
D-SG
WB
Cle
anou
t&Tr
ackb
edIO
D-S
G
Trac
kwor
kW
BIO
D-SG
Wal
kway
&Bui
ld'g
serv
ices
WB
IOD-
SG
Sink CaissonCaissionPreparation
Ground TreatmentRunning TunnelsMGT
Mob & Grd TreatmentEnabling Works Sink Escape Shaft
Advanced Services Diversions
Advanced Services Diversions
MGT
WB & EBPlatform StructuresPrep for
TBM's
Enabling Works
Enabling Works SecondaryLinings
Sec Lining
SCL Excavation Station Tunnels
Exc & Line Shaft Tunnels & Adits
Advanced Services DiversionsCofferdam
Launch Chamber
Main Station Structure Station InfillStructure
Site
Set
up
Loca
lSys
tem
sTe
stin
gPU
DD-IO
D--W
hite
chap
el-F
ARR
Loca
l Sys
tem
sTe
stin
gFA
R-Po
rtal
MGTEnabling Works
EB ChamberExc. & line EB shaft
Exc. & line WB shaftWB Chamber
Stat
icTe
stin
gW
BW
est P
orta
l-FAR
Stat
icTe
stin
gEB
Wes
t Por
tal-F
AR
Stat
icTe
stin
gW
BW
hite
chap
el-F
ARSt
atic
Test
ing
WB
PUDD
-IOD-
Whi
tech
apel
Syst
ems
Test
&Co
mm
issi
onin
gSy
stem
sTe
st&
Com
mis
sion
ing
Syst
ems
Test
&Co
mm
issi
onin
g
Tria
lRun
ning
Sta
ge2
Tria
lRun
ning
Sta
ge1
Sin
kS
haft
WB
TBM
tunn
eldr
ive
IOD
toLo
wel
lSt
WB
TBM
tunn
eldr
ive
Low
ellS
tto
Step
ney
Gre
en
Sink shaft
Settlement / Ground Monitoring HAS
Construct piled box&tunnel adits
Services Diversions/Enabling
Prep
for
TBM
's
Advanced Services Diversions
Diaph.WallCentral box
Hanover Sq.demo
Construct Goslett Yard Box
Dismantle WBTBM5 at Whitechapel
Settlement / Ground Monitoring PML
WB
Tunn
els
Syst
ems
Inst
alla
tion
PUD
D-E
lean
orSt
EB
TBM
driv
eE
lean
or-M
ileE
ndW
BTB
Mdr
ive
Ele
anor
-Mile
End
WB
Tunn
elcl
ean
out&
Trac
kbed
Elea
nor-M
ileEn
d
WB
Trac
kwor
kin
stal
latio
nEl
eano
r-Mile
End
WB
Wal
kway
&E&M
Serv
ices
Elea
nor-M
ileEn
d
EB
TBM
driv
eM
ileE
nd-S
tepn
eyG
reen
WB
TBM
driv
esM
ileE
nd-S
tep.
Gre
en
Interface Tunnels
Construct Davies St Box
ExcAdit
Construct Dean St BoxFareham St - Demo
Astoria DemoGoslett Yard Demo Sink Shaft
Sink Shaft
Construct Box
Essex Wharf Stage 1 Essex WharfStage 2
Essex WharfStage 3
Essex WharfStage 4 Essex Wharf Stage 5
OH
LE
OH
LE
FIT
OU
T
OH
LE
Fito
ut
Advanced Services Diversions Sink ShaftSite Set Up Vent Tunnels adits
Services diversions/Enabling Sink ShaftSite Set Up Vent Tunnel adits
Advanced Services Diversion
PUDD Cut & Cover
City Mills Bridge
Deliver,Erect,Comm.TBM
DLR Embankment 2
DLR Puding Mill StationDLR Station
Access culvertDLR Viaduct
PUDD Diaph.WallsLaunch chamber
Marshgate LaneMill Lane CB
Procure TBM
PUDD Retained Cut
Spoil Loading Installation
Construct Box Prep.for TBM's
Form EastBox SD Walls
Form WestBox SD Walls
Exc.Intervention PassagesPrep forTBM's
Site setup
Ventilation Passage
Air Intake/Stair structConstruct boxSite Set up
Construct Box
Retained Cut
Settlement/Background Monitoring
Com
bine
dS
yste
mTe
st&
Com
mis
sion
ing
PU
DD
-FA
R
Settlement / Ground Monitoring ELS
Station Fit out
Station Fit out
Station Fit out
Station Fit out
Station Fit out
Station Fit out
Settlement / Ground Monitoring HES
OHL
EPo
rtal s
truct
ure
mod
s.
OHL
E/Si
gnal
stru
ct.s
horte
ning
mod
s
Shaft Fit out
Dismantle & remove WB TBM1 at FAR via Fisher St.
Remove WB TBM3 at FAR via HANB shaft or PML
Add'
ltim
eto
alig
nEP
BMAd
d'lt
ime
toal
ign
EPBM
LUL
Cent
ralL
ine
clos
ure
forp
rote
ctiv
ew
orks
LUL NL closurefor Protection works
Add'l time to dismantle WB TBM 7
Settlement/Grd Monitoring PAD
Settlement/Grd Monitoring BOS
Settlement/Grd Monitoring TCR
Option 2 Crossrail Time Chainage TCDT4HSTunnel to Farringdon (not using Hanbury St)
13324Eleanor St Shaft
Mile End Park Shaft
Lowell Stree Vent Shaft
Stepney Green E&WVent Shaft & Turnouts
Central Shaft
10130
10285
10442
9952West Shaft
Hanbury Street Vent Shaft
9500
9532
Pedley StShaft
4716
4888
5060
3654
3820
3986Temp access Shaft East
����
����
��
����
��
����
����
��
����
��
���
����
�
����
��
���
����
�
����
��
Cut & Cover
Open Cut
@ Grade
816
520
210
������������������������������������������������
Roy
alO
akPo
rtal
2225Hyde Park Vent shaft
5825Fisher Street Vent Shaft
���
1578
1245
1410
Pudd
ing
Mill
Lane
14579
Park Lane Vent Shaft 3016
14123
7498
7340
7160
6980
7646
8462
8286
8110
Hertsmere Road Shaft13195
Old
Oak
Com
mon
Dep
ot&
sidi
ngs
Start Bored Tunnel
13575
Isle
ofD
ogs
Stat
ion
Live
rpoo
lSt
reet
Stat
ion
Farri
ngdo
nSt
atio
nPa
ddin
gton
Stat
ion
Start Bored Tunnel
Western Limit of Route
Wes
tbou
rne
Park
Bond
Stre
etSt
atio
n
Totte
nham
Cou
rtR
oad
Stat
ion
Whi
tech
apel
Stat
ion
11405
12276
12340
J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
2005 2006 2007 2008 2009 2010 2011 2012 2013
2005 2006 2007 2008 2009 2010 2011 2012 2013
EBTB
M2
tunn
eldr
ive
Padd
ingt
onto
Bond
St.
WB
TBM
1tu
nnel
driv
ePa
ddin
gton
toBo
ndSt
.
OH
LE
SIG
NA
LLIN
G
FIT
OU
T
Clea
nou
t &co
ncre
tetra
ckbe
dW
B- B
OS- H
yde
Pk
Clea
nou
t &tra
ckbe
dW
BHy
dePk
-PAD
Trac
kwor
kEB
Padd
ingt
onto
Bond
St.
Trac
kwor
kW
BPa
ddin
gton
toBo
ndSt
reet
Wal
kway
&bu
ildin
gse
rvic
esW
BBO
S-Hy
dePk
HV
&LV
Wal
kway
&bu
ildin
gse
rvic
esW
BHy
dePk
-PAD
Advanced Services Diversions
Exc. & Convc base East box
Exc. & Conc Station Boxinc base,int and roofslab
Exc. & Convc base West box
Prep for
TBM
Prep for
TBM
Roa
dD
eck
Rtg Walls South box
Rtg WallsWest box
Enabling Works
Sink Shaft
Site
Setu
p
Transfer EB TBM to East End
Arrange TBMin East Box
Advanced Services Diversions Enabling Works
Settlement Monitoring
Exc. & PrimaryLining
Site SetupNew Yard
Advanced Services Diversions Exc. & line interv'n passagesEnabling Works
Settlement Monitoring
Exc. & Primary LiningVent Tunnels
Site Setupinc Rail Sidings
CO
MM
UN
ICA
TIO
NS
HV
&LVO
HLE
SIG
NA
LLIN
GFI
TO
UT
Trac
kwor
kEB
Bond
Stre
etto
TCR
Trac
kwor
kW
BBo
ndSt
reet
toTC
R
Settlement Monitoring
Construct VentShaft & Tmp Aditsto Station Tunnel
Advanced Services Diversions
Construct BoxMGT
WB & EBPlatform Structure
Prep forTBM's
Secondary concretelinings to Stations
Enabling Works
NATM Excavation Station Tunnels
Exc. & Line Shaft
Site setup
Com
bine
dSy
stem
Test
&Com
mis
sion
ing
WBP
-FAR
R
HV&
LV
OH
LE
Enabling Works
SIG
NA
LLIN
G
FIT
OU
T
Clea
nou
t&co
ncre
tetra
ckbe
dW
BFi
sher
Stto
TCR
Trac
kwor
kEB
TCR
toFi
sher
St.s
haft
Trac
kwor
kW
BTC
Rto
Fish
erSt
. sha
ft
Wa l
kway
&bu
ildin
gse
rvic
esEB
TCR
toFi
sher
St
Advanced Services Diversions
Launch Chamber
Construct Astoria St Box
Phased PilingPhased Demo Dean St
WB & EBPlatformStructure
Prep forTBM's
Seco
ndar
yco
ncre
telin
ings
toSt
atio
ns
NATM ExcavationStation Tunnels
Advanced Services Diversions MGTEnabling WorksSec Lining
C&C Diaph Walls
Exc. & Primary LiningVent Tunnels & Adits
COM
MUN
ICAT
IONS
HV&
LVOHL
E
SIG
NALL
ING
FIT
OUT
Exec & Conc to Cut & Cover
Wal
kway
&bui
ld'g
serv
ices
EBFA
Rto
LIS
COM
MUN
ICAT
IONS
HV&
LV
OH
LE
EBTB
Mtu
nnel
driv
eFa
rring
don
toFi
sher
St
WB
TBM
tunn
eldr
iveFa
rring
don
toFi
sher
St.
SIG
NA
LLIN
G FIT
OU
T
Clea
nou
t&co
ncre
tetra
ckbe
dW
BFA
Rto
Fish
erSt
Wal
kway
&bu
ildin
gse
rvic
esW
BFi
sher
Stto
FARRAdvanced Services Diversions
Backfill
Construct Piled Box & Tunnel Adits
Crossover Tunnel
WB
&EB
Plat
form
Stru
ctur
e
Crossover lininginvert WB
Prep
for
TBM
'sEnabling Works
Seco
ndar
yco
ncre
telin
ing
toSt
atio
n
Settlement Monitoring
NATM Excavate Station TunnelsSite
Setu
p
COM
MUN
ICAT
IONS
Advanced Services Diversions
hv&
lv
OHL
E
WB
TBM
tunn
eldr
iveHa
nbur
y St.t
oW
hite
chap
el
SIG
NALL
ING
FIT
OUT
Clea
n&
track
bed
conc
. -W
BHa
nto
Whi
tech
apel
Wal
kway
&bui
ld'g
serv
ices
EBHa
nto
Whi
tech
apel
ConstructRetaining
Wall
COM
MUN
ICAT
IONS
HV&
LV
OHL
E
EBTB
MTunn
eldr
iveHa
nbur
y-Liv
erpo
olSt
.
WB
TBM
Tunn
eldr
iveHa
nbur
y-Live
rpoo
lSt.
SIG
NALL
ING
FIT
OUT
Install OHLE& Signalling
Trac
kwor
kW
BHa
n.to
Live
rpoo
lSt
Acc adit & break up
MGT Exc. & line shafts
Setup Railhead
Deleiver Erect& commission TBM
E/B Chamber
Site Prep
Enabling Works Form EPBM adit chambers & backshunt
Advanced Services DiversionsW
B&
EBPl
atfo
rmSt
ruct
ure
Prep for
TBM
's
Enabling WorksSecondary concrete
lining to Station
Construct Platforms x3
Settlement Monitoring
NATM Excavation Station Tunnels
Site
Setu
p
CO
MM
UN
ICA
TIO
NS
OH
LE
EBTB
Mtu
nnel
driv
eSt
epne
yGr
een
toW
hite
chap
el
ConstructPlatform
Foundations x3
SIG
NA
LLIN
G
FIT
OU
T
Clea
n&
conc
.trac
kbed
WB
Whi
tech
apel
toSG
Trac
kwor
kW
BSG
toW
hite
chap
el
Wal
kway
&bui
ldin
gse
rvic
esEB
SGto
Whi
tech
apel
Wal
kway
&bui
ldin
gse
rvic
esW
BSG
toW
hite
chap
el
Del,Erec& Comm TBM's
Crossrail Track & Rail
EBTB
Mtu
nnel
driv
eIO
Dto
Low
ellS
t
Syst
emwi
dein
stal
latio
nEB
IOD-
SG
WB
Cle
anou
t &Tr
ackb
edIO
D-S
G
Trac
kwor
kW
BIO
D-SG
Wal
kway
&Bui
ld'g
serv
ices
WB
IOD-
SG
Sink CaissonCaissionPreparation
New EWS Facility
Ground TreatmentRunning TunnelsMGT
Mob & Grd TreatmentEnabling Works Sink Escape Shaft
Advanced Services Diversions
Advanced Services Diversions
Crossrail Facilities Buildings & Civil
MGT
WB & EBPlatform StructuresPrep for
TBM's
Enabling Works
Enabling Works SecondaryLinings
Sec Lining
Wal
kway
&bu
ildin
gse
rvic
esW
BPA
Dto
Porta
l
NATM Excavation Station Tunnels
Exc & Line Shaft Tunnels & Adits
Advanced Services DiversionsCofferdam
Launch Chamber
Main Station Structure
Enab
ling
Wor
ks
Station InfillStructure
Site
Set
up
Loca
lSys
tem
sTe
stin
gPU
DD-IO
D--W
hite
chap
el-F
ARR
Loca
l Sys
tem
sTe
stin
gFA
RR-P
o rta
l
MGT
Trac
kwor
kW
BPo
rtal t
oPa
ddin
gton
Enabling Works
EB ChamberExc. & line EB shaft
Exc. & line WB shaftWB Chamber
Stat
icTe
stin
gW
BW
est P
orta
l-FAR
RSt
atic
Test
ing
EBW
est P
orta
l-FAR
R
Trac
kwor
kEB
Port
alto
Padd
ingt
on
Stat
icTe
stin
gW
BW
hite
chap
el-F
ARR
Stat
icTe
stin
gW
BPU
DD-IO
D-W
hite
chap
el
Syst
ems
Test
&Co
mm
issi
onin
gSy
stem
sTe
st&
Com
mis
sion
ing
Syst
ems
Test
&Co
mm
issi
onin
g
Tria
lRun
ning
Sta
ge2
Tria
lRun
ning
Sta
ge1
Clea
n&
conc
rete
track
bed
-W
BPA
Dto
porta
l
Sin
kS
haft
WB
TBM
tunn
eldr
ive
IOD
toLo
wel
lSt
Sink shaft
Settlement / Ground Monitoring HAS
Construct piled box&tunnel adits
Services Diversions/Enabling
Prep
for
TBM
's
Advanced Services Diversions
Diaph.WallCentral box
Hanover Sq.demo
Construct Goslett Yard Box
Settlement / Ground Monitoring - west end TCR
Dismantle WBTBM5 at Whitechapel
Settlement / Ground Monitoring PML
WB
Tunn
els
Syst
ems
Inst
alla
tion
PUD
D-E
lean
orSt
WB
TBM
driv
eEl
eano
r-M
ileEn
d
WB
Tunn
elcl
ean
out&
Trac
kbed
Elea
nor-M
ileEn
d
WB
Trac
kwor
kin
stal
latio
nEl
eano
r-Mile
End
FIT
OU
T
WB
Wal
kway
&E&M
Serv
ices
Elea
nor-M
ileEn
d
Interface Tunnels
Construct Davies St Box
ExcAdit
Fareham St - Demo
Astoria DemoGoslett Yard Demo Sink Shaft
Sink Shaft
Construct Box
Essex Wharf Stage 1
SIG
NA
LLIN
G
Essex WharfStage 2
Essex WharfStage 3
Essex WharfStage 4 Essex Wharf Stage 5
OH
LE
OH
LE
FIT
OU
T
OH
LE
Fito
ut
Advanced Services Diversions Sink ShaftSite Set Up Vent Tunnels adits
Services diversions/Enabling Sink ShaftSite Set Up Vent Tunnel adits
Advanced Services Diversion
PUDD Cut & Cover
City Mills Bridge
Deliver,Erect,Comm.TBM
DLR Embankment 2
DLR Puding Mill StationDLR Station
Access culvertDLR Viaduct
PUDD Diaph.Walls
TBM Design, Manufacture & Assembly
Marshgate Lane
Mill Lane CB
Procure TBM
PUDD Retained Cut
Spoil Loading Installation
Construct Box Prep.for TBM's
OH
LE
Form EastBox SD Walls
Form WestBox SD Walls
Exc.Intervention PassagesPrep forTBM's
Site setup
Ventilation Passage
Air Intake/Stair struct
HV
&LV
Construct boxSite Set up
Construct Box
Retained Cut
Settlement/Background Monitoring
Com
bine
dS
yste
mTe
st&
Com
mis
sion
ing
PU
DD
-FA
RR
Settlement / Ground Monitoring ELS
Station Fit out
Station Fit out
Station Fit out
Station Fit out
Station Fit out
Settlement / Ground Monitoring PAD
CO
MM
UN
ICA
TIO
NS
Settlement / Ground Monitoring - west end BOS
Settlement / Ground Monitoring LIS
Settlement / Ground Monitoring HES
Settlement / Ground Monitoring WHI
Settlement / Ground Monitoring IOD
Crossrail Time ChainageTCD17 P3 Revision ICP17
13324Eleanor St Shaft
Mile End Park Shaft
Lowell Stree Vent Shaft
Stepney Green E&WVent Shaft & Turnouts
Central Shaft
10130
10285
10442
9952West Shaft
Hanbury Street Vent Shaft
9500
9532
Pedley StShaft
4716
4888
5060
3654
3820
3986Temp access Shaft East
����
����
��
����
��
����
����
��
����
��
���
����
�
����
��
���
����
�
����
��
Cut & Cover
Open Cut
@ Grade
816
520
210
Roy
alO
akPo
rtal
������������������������������������������������
2225Hyde Park Vent shaft
5825Fisher Street Vent Shaft
���
1578
1245
1410
Park Lane Vent Shaft 3016
Pudd
ing
Mill
Lane
7498
7340
7160
6980
14579
14123
7646
8462
8286
8110
Hertsmere Road Shaft13195
Old
Oak
Com
mon
Dep
ot&
sidi
ngs
Start Bored Tunnel
13575
Isle
ofD
ogs
Stat
ion
Live
rpoo
lSt
reet
Stat
ion
Farri
ngdo
nSt
atio
nPa
ddin
gton
Stat
ion
Start Bored Tunnel
Western Limit of Route
Wes
tbou
rne
Park
Stat
ion
Bond
Stre
etSt
atio
n
Totte
nham
Cou
rtR
oad
Stat
ion
Whi
tech
apel
Stat
ion
11405
12276
12340
Cross London Rail Links Limited Mott MacDonald
Crossrail Construction Programme - Programme Impact without Hanbury Street Shaft as a TBM Launch Site
Technical Note No. No. 1D0300-C1N00-00839/A April 2005
B-1P:\Croydon\MMH\Tunnels\201985\Reports\Technical Notes\839 Programme Impact without Hanbury Shaft as a TBM Launch Site\Revision A - Final Issue\1D0300-C1N00-00839 A.doc/KLD
Appendix B Review of Intermediate Tunnelling Sites
B.1 Criteria for TBM Launch Sites
Selection of potential TBM launch sites was based upon the following criteria:
• Programme;
• Feasibility of the site in terms of tunnelling and logistics; and
• Impact on the surrounding environment.
To support the TBM drives any of the sites would need to be of such a size that they handleconsistently the removal of up to 2,800m3 of excavated material per day (equivalent to 200 lorry loadseach way) and the supply of the tunnel linings and other necessary materials, about 30 lorry loads perday. Ideally the site should be of such a size that would allow the stock-piling of up to 48 hoursproduction of both excavated material and tunnel linings to cater for disruptions in the supply chainsupporting the operation.
Given the volumes of excavated materials involved ideally the TBM launch site should be relativelyclose to rail infrastructure to enable this material to be hauled to the disposal site by rail.
B.2 Mile End Park
Site Location
The tunnelling worksite would coincide with the intervention, ventilation and evacuation shaft locatedat the southeast corner of the Mile End Park, where Burdett Road intersects the railway viaduct.
Construction Programme
The tunnel drive is constrained by the construction of the turnouts at Stepney Green Shaft. Thecurrent philosophy is that the turnouts are constructed prior to the railway tunnels being constructed.As a result, the TBMs cannot be received at Stepney Green before about Month 28 (September 2009).
Worksite
A tunnelling worksite located immediately adjacent to the shaft is considered unfeasible due to thecurrent expansion of sports facilities, which includes new football pitches and sports complex.Therefore, the tunnelling worksite would need to be sited northwards and further into the park, with adedicated link between the tunnelling worksite and the shaft for launching TBMs.
Excavated materials will be transported to the stockpile area at the northern end of Mile End Park forloading on to the railway at Mile End (Devonshire Street) sidings. The site is a considerable distancefrom the stockpile area. The excavated materials could be transported to the stockpiling site by eithera conveyor through the park, a tunnelled adit connecting the tunnelling shaft with a temporary shaft atthe stockpile area, or by lorry either directly to the stockpile area or direct to the landfill site.
Tunnelling supplies, including segments, will be transported to site by lorry.
Cross London Rail Links Limited Mott MacDonald
Crossrail Construction Programme - Programme Impact without Hanbury Street Shaft as a TBM Launch Site
Technical Note No. No. 1D0300-C1N00-00839/A April 2005
B-2P:\Croydon\MMH\Tunnels\201985\Reports\Technical Notes\839 Programme Impact without Hanbury Shaft as a TBM Launch Site\Revision A - Final Issue\1D0300-C1N00-00839 A.doc/KLD
Environmental Implications
Locating the tunnelling worksite within Mile End Park would place a significant demand on the parkand in particular the Mile End Park Sports Facility as construction sites would be required at bothends, with the tunnelling worksite and shaft at the southern end and the stockpile area at the northern.Closure of the Mile End Park Sports Facility main entrance and car parking area is required whentransporting TBMs from the tunnelling worksite, where they will be erected, to the shaft for launch ofthe TBMs. Transporting TBM generated excavated materials between the tunnelling worksite (at thesouthern end of the park) and the area for stockpiling (to the north) would be disruptive eitherenvironmentally from a surface mounted conveyor or from an increase in construction duration for atunnelled adit or from the significant burden on the local road network from the addition of 230 lorriesper day both ways required to support tunnelling operations.
B.3 Stepney Green
Site Location
The tunnelling worksite would coincide with the intervention, ventilation and evacuation shaft locatedwithin Stepney Green, adjacent to the road junction of Garden Street and Stepney Green.
Construction Programme
The tunnel drive is constrained by the construction of the turnouts at Stepney Green Shaft to launchthe TBMs. Launch of the TBMs prior to completion of the primary lining for the turnouts may allowthe tunnelling machines to commence at an earlier stage, but the launch date would be constrained bythe new station at Whitechapel and the availability of the station platform tunnels to receive TBMs.Early release of the TBMs would significantly impact on the construction logistics for completing theturnouts at Stepney Green with both shaft construction and tunnelling operations being carried outsimultaneously. The construction methods of the turnouts are already constrained by the westboundcavern being located within poor ground.
Worksite
The worksite required for Stepney Green Shaft will occupy an area of open space that includes a sportsfacility and the western paddocks of Stepping Stones Farm. To facilitate a tunnelling worksite, theworking site will require expansion into the grassed playing field (Stepney Green), immediately westof the current sports facility, to facilitate mixed excavated material stockpile areas, sufficient tolocated and hold 48 hours capacity.
Excavated materials would be transported by lorry either directly to the disposal site or to the MileEnd Park stockpile for onward loading to the railhead at Mile End (Devonshire Street) sidings. Theuse of a surface mounted conveyor is considered unfeasible with no unobstructed direct corridorbetween Stepney Green and Mile End Park available, thereby limiting the conveyor route to followthat of the road network requiring the conveyor to change direction numerous times over shortdistances. A long tunnelled adit connecting Stepney Green Shaft with a temporary shaft at thenorthern end of Mile End Park is considered undesirable due to its long length and connectionarrangement with the turnout caverns, which are at different levels. An obstruction free route for atemporary adit has not been developed, but will need to account for piled foundations (Royal London
Cross London Rail Links Limited Mott MacDonald
Crossrail Construction Programme - Programme Impact without Hanbury Street Shaft as a TBM Launch Site
Technical Note No. No. 1D0300-C1N00-00839/A April 2005
B-3P:\Croydon\MMH\Tunnels\201985\Reports\Technical Notes\839 Programme Impact without Hanbury Shaft as a TBM Launch Site\Revision A - Final Issue\1D0300-C1N00-00839 A.doc/KLD
Hospital – Mile End and Queen Mary University of London), sewers, and LUL tunnels (Hammersmith& City and District Line). Tunnelling supplies, including segments, will be delivered to site by lorry.
Environmental Implications
Stepney Green Shaft site lies in a busy residential area and the main streets, including Mile End Road,Stepney Green and Commercial Road, are already heavily trafficked. The introduction of a tunnellingsite would significantly increase traffic congestion with up to 230 lorry loads being required to supporttunnelling operations in each direction. This is in addition to the numbers of lorries required forconstruction of the shaft itself.
B.4 Whitechapel
Site Location
The tunnelling site would coincide with the proposed new Crossrail station at Whitechapel.
Construction Programme
Tunnelling operations would be constrained by the availability of the station platform tunnels. TheTBMs would not be launched until the primary lining of the platform tunnels is complete. The stationprogramme is likely to be extended as a result of tunnelling with station fit out being constrained byremoval of excavated materials from the railway tunnels and the delivery of tunnel segments andsupplies by the surrounding road network. The arrangement of the station will need to change to allowthe TBMs to be lowered and positioned within the station ready for launch.
Worksite
The worksite around the proposed new Whitechapel Station is heavily constrained with commercialand residential premises, the existing LUL railway lines and associated LUL Whitechapel Station,Swanlea School and busy roads. There are limited worksites available for construction of the newstation. The principal station worksites for Crossrail are the District Line worksite (bus stand andturning area on Durward Street); the Durward Street worksite (sports centre car park, Essex Wharf,substation and part of Swanlea School grounds); and the Sainsbury’s Car Park worksite (car park atthe junction of Whitechapel Road and Cambridge Heath Road). To facilitate tunnelling operations,the working site area needs to be increased. This has not been developed in detail, though an initialassessment would be to use the Pedley Street tunnelling site and transport materials via VallanceRoad.
Excavated materials for the station construction will be transported directly to the landfill site by road.Excavated materials from tunnelling operations would be transported to the Pedley Street site by eitherlorry, conveyor or tunnelled adit. From the Pedley Street worksite, excavated materials would betransported by conveyor to Mile End Park for stockpiling and onward loading to the railhead at MileEnd (Devonshire Street) sidings.
Tunnelling supplies, including segments, will be transported to site by lorry.
Cross London Rail Links Limited Mott MacDonald
Crossrail Construction Programme - Programme Impact without Hanbury Street Shaft as a TBM Launch Site
Technical Note No. No. 1D0300-C1N00-00839/A April 2005
B-4P:\Croydon\MMH\Tunnels\201985\Reports\Technical Notes\839 Programme Impact without Hanbury Shaft as a TBM Launch Site\Revision A - Final Issue\1D0300-C1N00-00839 A.doc/KLD
Environmental Implications
Combining the tunnelling operations with the station works will increase disruption to the surroundingenvironment through an increase in construction programme, additional lorries accessing the site andadditional facilities for tunnelling and equipment to support tunnelling operations.
B.5 Hanbury Street Shaft (Base Case)
Site Location
The TBM launch site would coincide with the intervention and ventilation shaft located at 68 to 102Hanbury Street, Spitalfields and known as Hanbury Street Shaft. The principal tunnelling work site islocated within Network Rail owned lands between the Great Eastern railway and Pedley Street.Access to the site is from Vallance Road.
Construction Programme
Spitalfields has the advantage of being located at approximately the third point of the total tunnellength from Royal Oak to Pudding Mill Lane, offering the potential for balancing the TBM drivelengths and thus achieving the optimum programme reduction.
Worksite
The TBMs will be launched from Hanbury Street Shaft, with the principal tunnelling work site beinglocated at the Pedley Street worksite. A temporary tunnel and shaft (located within the Pedley Streetworksite) will connect the two work sites.
Excavated materials will be removed from the railway tunnels and brought to the surface at the PedleyStreet site, and then conveyed to Mile End Park for stockpiling and onward loading to the railhead atMile End (Devonshire Street) sidings.
Tunnelling supplies, including segments, will be transported to the Pedley Street site by lorry.
All materials for the construction of the Hanbury Street Shaft, including the removal of excavatedmaterials, will be transported by lorry.
Environmental Implications
A shaft at Hanbury Street is required to satisfy fire, life and safety standards for the railway betweenthe proposed new Liverpool Street and Whitechapel Stations. The construction of the shaft willimpact on the environment through visual intrusion, demolition works, increased traffic, alternativepedestrian routes, dust generation, noise and vibration.
The need for Hanbury Street Shaft to launch TBMs requires facilities for transporting the TBMs tosite; TBM erection; craning TBM and back up modules into position; and TBM testing andcommissioning. The environmental impacts normally associated with a tunnelling site are mitigatedby the use of a working site at Pedley Street with all TBM generated excavated material beingtransported to the Pedley Street work site through a temporary tunnel where it will be conveyed to therailhead at Mile End (Devonshire Street) sidings. All tunnelling supplies and segments will be
Cross London Rail Links Limited Mott MacDonald
Crossrail Construction Programme - Programme Impact without Hanbury Street Shaft as a TBM Launch Site
Technical Note No. No. 1D0300-C1N00-00839/A April 2005
B-5P:\Croydon\MMH\Tunnels\201985\Reports\Technical Notes\839 Programme Impact without Hanbury Shaft as a TBM Launch Site\Revision A - Final Issue\1D0300-C1N00-00839 A.doc/KLD
transported by lorry using Vallance Road (B108) and stored at the Pedley Street work site and thenintroduced into the tunnel system via the Pedley Street construction shaft. Use of the Pedley Streetwork site, including the temporary tunnel and shaft, minimises the tunnelling works at surface atHanbury Street Shaft.
B.6 Farringdon
Site Location
The tunnelling site would coincide with the proposed new Crossrail station at Farringdon.
Construction Programme
The use of Farringdon Station as a tunnelling site would require a significant change in the tunneldrive strategy for the central tunnels. As Farringdon Station and Fisher Street Shaft are close to eachother, the TBMs would be driven eastwards from Farringdon to Whitechapel Station, removed,transported back to Farringdon by lorry and re-launched for the short drive westwards to Fisher StreetShaft. The other tunnel drives would be from Royal Oak to Fisher Street and from Pudding Mill Laneto Whitechapel, as per the base case. There are a number of constraints including the interface ofconstructing Farringdon Station whilst tunnelling is carried out, the interface with constructing thecrossover located between Farringdon and Liverpool Street Stations and the availability of the stationplatform tunnels at Liverpool Street and Whitechapel for receipt of the tunnelling machines.
Worksite
The sites available for constructing Farringdon Station are very limited. Introducing a tunnelling sitewithin this area is considered to be unfeasible with all available space being used as working sites forconstructing the station. All materials into and out of the site would be by road. It is considered thatthe use of rail is unfeasible as the existing sidings lie in a cutting with difficult access and connect onlyto London Underground Ltd. lines. Their use would be limited to engineering hours between 12:30amand 4am, and would be dependant upon the availability of LUL works trains in the numbers required.
Environmental Implications
The principal environmental implications are the increased working site area required to supporttunnelling operations which is likely to require demolition to create this space, increased lorrymovements with excavated materials and incoming materials for both station and tunnel constructionbeing transported by road, and an increased construction duration.
B.7 Review of Intermediate Tunnelling Sites – Conclusions
Being located at approximately the third point of the total tunnel length from Royal Oak to PuddingMill Lane (B.5), an intermediate tunnelling site located at Hanbury Street offers the potential tobalance the TBM drive lengths and reduce periods of inactivity between station and railway tunnelconstruction to provide a six year programme that achieves the revenue service dates required by theProject.