October 22, 2015
Weekly Bridge Inspection – No change Design – 100% Complete Permits – No Change
◦ UPRR has approved plans; now developing agreement ◦ USCOE and KDWR permit application submitted/under review ◦ Environmental: NEPA “Categorical Exclusion”
R-O-W
◦ Terms for all ROW purchases have been negotiated/agreed upon ◦ Waiting for last Quit Claim Deed to be returned ($310 value)
Utility Relocation – No Change
◦ All utility companies have been contacted/provided plans and preparations being made for relocations (2017)
Funding ◦ USDOT TIGER Grant – Revised Anticipate award announcements late October/mid- November
◦ KDOT – No change In process of developing No Interest Loan Agreement Waiting for Inter-local Agreement to be finalized
◦ Inter-local Agreement – COT indicated waiting until December to review/comment JEDO meeting possibly being scheduled to discuss
◦ Wabaunsee County Agreement: Develop after TIGER Grant determination
Schedule - Revised ◦ Now anticipating a Feb-March 2016 bid letting/May-June 2018
completion ◦ Dependent upon funding availability and type
SCDPW continues to be in “Waiting” Mode
KDOT Financial Advance ◦ Provides Construction Funding in 2016 ◦ Prior to Current Sales Tax Excess Funds Availability ◦ Significantly reduces bonding costs
Sales Tax Extension County Bridge Allotment ◦ $32.5M (includes $10M allotted for Willard Bridge) ◦ Provides reimbursement funds for KDOT Advance
Assistance in Expediting UPRR Agreement ◦ KDOT/Sen. Moran
Goal is a Dec 2015/Jan 2016 Bid ◦ Construction in Jan/Feb 2016 Environmental Restrictions April 1st - August 31st
◦ Completion in Dec 2017