32
By Turaj Amraee Fall 2012 K.N.Toosi University of Technology Planning Criteria Chapter 2

Wide Area Protection of Voltage Stabilitywp.kntu.ac.ir/amraee/chapter2Planningcriteria.pdf · Power systems must be planned, designed, and constructed to operate reliably within thermal,

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

  • By

    Turaj Amraee

    Fall 2012

    K.N.Toosi University of Technology

    Planning Criteria

    Chapter 2

  • Outline

    1- Introduction

    2- System Adequacy and Security

    3- Planning Purposes

    4- Planning Standards

    5- Reliability Assessment

  • Introduction

    Planning could be interpreted as an optimization task

    The planning decision are made as the result of a

    reasonable tradeoff between Technical and Economical

    constraints.

    How to quantify the reliability

    Reliability and Planning

    Reliability begins with Planning

  • System Adequacy and Security

    Adequacy - The ability of the electric systems to supply the aggregate electrical demand and energy requirements of

    their customers at all times, taking into account scheduled and

    reasonably expected unscheduled outages of system elements.

    Security - The ability of the electric systems to withstand sudden disturbances such as electric short circuits or

    unanticipated loss of system elements.

    Reliability of the interconnected bulk electric systems is defined using

    the following two terms:

  • Planning Purposes

    Power systems must be planned, designed, and constructed to operate reliably within thermal, voltage, and stability limits while achieving their major purposes. These purposes are to:

    Deliver Electric Power to Areas of Customer Demand

    Provide Flexibility for Changing System Conditions

    Reduce Installed Generating Capacity

    Allow Economic Exchange of Electric Power Among Systems

  • Planning Standards

    Standards

    NERC WECC IEC

    System Modeling Data Requirements

    System Protection and Control

    System Restoration

    Facility Connection Requirements

    Voltage Support and Reactive Power

    Transfer Capability

    WESTERN ELECTRICITY COORDINATING COUNCIL

    North American Electric Reliability Corporation International Electrotechnical Commission

  • Planning Standards

    S1. The interconnected transmission systems shall be planned, designed, and

    constructed such that with all transmission facilities in service and with normal (pre-

    contingency) operating procedures in effect, the network can deliver generator unit

    output to meet projected customer demands and projected firm (non-recallable

    reserved) transmission services, at all demand levels over the range of forecast

    system demands, under the conditions defined in Category A of Table I (attached).

    Cat. A

    • Normal

    Cat. B

    • N-1

    Cat. C

    • N-2 and higher

    Cat. D

    • Cascading

    NERC Example

  • NERC Planning Criteria

  • NERC Planning Criteria

  • Reliability – An introduction

    Running

    Fault

    Repair

    Planned maintenance

    Temporary maintenance

    Power equipment such as generator, transformers, Trans. Lines, etc., are

    generally considered to be system components. In their service life time,

    they can be in many states:

  • Reliability – failure characteristics

    Characteristics of component failure

    Continuous working time T of a component is a random variable.

    F(t) : failure function of a component,

    R(t) : the probability that a component still operates after a designated time t, and

    is called the reliability function of a component or Reliability

    f ( t ) is the failure probability density function

    0)()( ttTPtF

    0)()( ttTPtR

    )()()(

    1)()(

    tfdt

    tdF

    dt

    tdR

    tRtF

  • Reliability – failure characteristics

    The conditional probability that a component is

    working before the time instant t and develops a

    fault in the unit time Del(t) after the time instant t,

    Failure rate function

    )(1

    lim)( 0 tTttTtPt

    t t

    dt

    tdR

    tRtR

    tft

    )(

    )(

    1

    )(

    )()(

  • Reliability – failure characteristics

    The mean of the random variable T is called a

    component's mean time between failures (MTBF), which is

    another index to evaluate a component's reliability.

    Mean time between failures (MTBF)

    1MTBF

  • Reliability – repair characteristics

    The repair rate can be defined in a form similar to that for the failure rate:

    Mean time to repair (MTTR)

    The mean of a component's repair time TD or the mean time to repair can be written as

    Characteristics of component repair

    )(1

    lim)( 0 tTttTtPt

    t DDt

    1MTTR

  • Reliability – Availability

    The probability PA(t) that a component is in service state is called the availability

    Availability

    )(UPPA

    )(1: DnPAUFOR

    MTTRMTBF

    MTBFA

    MTTRMTBF

    MTTRU

  • Reliability – Evaluation Process

    Define the boundary of the system and list all the components included

    Provide reliability data such as failure rate, repair rate, repair time,

    scheduled maintenance time, etc., for every component.

    Establish reliability models for every component.

    Define the mode of system failure, or define the criterion for normal and faulty systems.

    5. Establish a mathematical model for the system reliability

    assumptions.

    6. Select an algorithm to calculate the system reliability

    Reliability Calculation

  • Reliability – Evaluation Process

    Generation: Transmission is ignored Composite: Generation+Transmission Distribution: Gen+Trans. Are ignored

    •Generation: Two or three states model •Transmission Line, Transformer: Two or three states model •Load: Load Duration Curve

    Here HLI is considered

    Gen Load

  • Reliability – Generation Model

    1- State Probability Model: The system loses capacity c with a certain probability when the

    generating unit to stop due to random failures. Therefore, the capacity or the X is considered to be a random variable in power system. The unit model is the probability table of a generator unit's capacity state.

    Probability model The dual-state model assumes that a unit only has two states:

    operation and failure (repair).

    Example- Dual State Generation Model

    0

    1)(

    i

    i

    ixFOR

    cxFORxXP

    cx

    cxFOR

    x

    xXP

    i

    i

    i

    i

    1

    0

    00

    )(

    Individual state probability cumulative state probability

  • Reliability – Generation Model

    2- State Frequency Model:

    Suppose p(i) = P(X = xi) is the individual probability of ith state

    (capacity), fi is the ith state frequency and fij is the transition

    frequency from state i to state j.

    Example- Dual State Generation Model

    )1( FORppf ijiji

    ijii

    )(FORppf jijji

    jiij

    ki

    ixfxXFxF )()()(

    Individual state frequency cumulative state frequency

  • Reliability – Example

    Example- Dual State Generation Model

    Capacity Outage Probability Table

  • Reliability – Example

    Example- Dual State 2-Units Generation Model

    For multi-generator unit model COPT is constructed using

    recursive algorithm

    the table is revised as units are added one after another until the last one and the capacity

    model for the whole generating system is formed.

  • Reliability – Load Model

    From 1 and 2

    Primary load data Normally primary load data include:

    1. The maximum monthly load or weekly load in a year.

    As a percentage of the maximum load in a year(52 weeks)

    2. The maximum load in each day in a week.

    As a percentage of the maximum load in a week(7 days)

    It is assumed that it is valid for all the seasons

    3. The load in 24 hours in a typical day in each season.

    As a percentage of the maximum load in every hour(24 hours)

    For each season a typical different load curve is assumed

    Maximum load for the 365 days

    in a year

    From 1,2 and 3 Maximum load for the 8760 hrs

    in a year

  • Reliability – Load Model

    Load outage capacity table

    Tha aim is to replace the load curve with a load outage capacity

    j

    ij

    iT

    tLP )(

    ijt

    T

    The pause time of Li inside T

    The examination period: 365 days or 8760 hrs

    The load level Li is the negative of operation capacity

  • Reliability – Load Model

  • Generating System Reliability Evaluation

    The system margin state probability and frequency table is formed by

    convolution of the parallel calculation formula applied to the generator

    outage table and the load capacity table

    Generating unit's cumulative P and F: aiaia NiXFXP ,...,1,0)(),(

    bibib NiXFXP ,...,1,0)(),( Load cumulative P and F:

    Margin state cumulative probability

    )]()([)()( 10

    jbjbikN

    j

    akc XPXPXXPXPb

    )]}()([)(

    )]()([)({)(

    1

    1

    0

    jbjbika

    jbjbik

    N

    j

    akc

    XFXFXXP

    XPXPXXFXFb

    Margin state cumulative frequency

  • Reliability Indices

    The power generation system reliability indices are usually a measure of power

    supply reduction to customers (load point) as a result of faults developed in the

    power generating unit

    1. Loss of load probability (LOLP),

    LOLP is defined as the probability of the effective system capacity not meeting

    the load demand, which can be written as

    )( RXPLOLP

    X: system outage capacity

    R=C-L: system reserve capacity

    C: system effective capacity

    L: Maximum load

  • Reliability Indices

    The expected number of days or number of hours in the

    period investigated when the maximum load exceeds

    the system effective capacity:

    2. Loss of Load Expectation (LOLE)

    Based on load model:

    T is 8760 hours or 365 days

    TLOLPLOLE * hrs/year or day/year

  • Reliability Indices

    EENS is the expectation of the energy loss caused to

    customers by insufficient power supply:

    3.Expected energy not served (EENS)

    yearMWhpMEENS kM

    k

    k

    /8760*0

    Mk=Cj-Li: system margin capacity

  • Reliability Indices

    If the cost to customers is affected by the frequency of power interruption over a certain period instance to customers e.g. chemical industry or metallurgical then the indices of power interruption duration is needed.

    4. Frequency and duration (F& D)

    The cumulative system interruption frequency and duration

    yeartimesRXFF /)( hoursRXF

    RXPD

    )(

    )(

  • Reliability Indices

    The SM index is the ratio of energy loss due to power

    interruption as a result of insufficient system

    generation over the annual maximum load

    5. System-minutes (SM)

    utesL

    EENSSM

    p

    min

    Lp the annual maximum load

  • Exercise 1.

    Write a computer program to obtain the results of

    Examples 2.2 and 2.3 of the reference # 1.

  • End

    ؟