Upload
annabella-hodges
View
229
Download
6
Tags:
Embed Size (px)
Citation preview
Warnings: This topic we are about to cover may be somewhere deadly serious, but we try not to be!!!If anyone feel bored during this training session, tell us, we will make it faster.
Abstract
To understand the general idea about the reason why IS projects fail
How does a project be successful? ---- Critical Success Factors
IS project failure happens at any fields----3 Case Study Analysis
Solution to improve project management process
.
1
2
3
4
IntroductionWhat is project failure…
The project costs a lot more than estimated. It takes much longer than everyone expected. The product fails to do what it was supposed to. Nobody is happy about it.
So….Who’s fault?
Software System Project manager
Project Outcomes
1994 1996 1998 2000 2002 2004 20090%
10%
20%
30%
40%
50%
60%
16%
27% 26%28%
34%
29%
32%
53%
33%
46%
49%51%
53%
44%
31%
40%
28%
23%
15%
18%
24%
Successed
Challenged
Failed
• Data Source: The Standish Chaos Report, 2009
“Around 2009, the year’s project management statistics show results that in project success rates, with 32% of all projects succeeding which are delivered on time, on budget, with required features and functions. 44% were challenged which are late, over budget, and/or with less than the required features and functions and 24% failed which are cancelled prior to completion or delivered and never used.”
Critical Success Factor
Management of The Implementation Process
Formal methodology and reliable estimates Experienced project manager
Level of Complexity/Risk
Project Size Project Structure Experience with technology
Senior Management Support
Users Involvement
Three constraints
Quality
Cost
Time
Project manager use IS to meet three key elements:
• Identify requirements, • Allocate budget • Keep timing constraints
(Bocij, 2006)
Categories of Project Failure
Correspondence failureCorrespondence failure
Interaction failureInteraction failure
Process failureProcess failure
Expectation failureExpectation failure
Failure to meet the objectives originally
specified for the system
The system is not developed within time and budget
constraints, or the system is never implemented
Poor usage of IS by users (the system itself meets the
technique specification)
‘Inability’ of an information system to meet a specific
stakeholder group’s expectations’
(Lyytinen & Hirschheim, 1987)
Cost overruns
Poor planning and cost
estimation
Poor monitor on time delivering
and poor communication
New technology and poor testing
Poor decision-making, Scope
creep
Time slippage
Technical shortfalls
Forecasted benefits
- Goals not all achieved- Complex Solutions- Lack of Planning- Lack of User Involvement- Lack of Resources- Lack of Commitment- Unrealistic Expectations- Lack of Executive Support- Changing requirements and specifications- Schedule overrun- Budget overrun- Poor leadership and management- Debugging incomplete- Lack of ownership- Too many vested interests
Level of Failure
- Profitability- Poor Estimates- Unproven Tech.- Lack of Res.- Lack of Features- Lack of Usability- Lack of Project
organization- Transparency in IS
Project- Progress Meetings
- Scrapped Before Completion
- Vendor’s Inability to meet requirements
- Client consultation during development stage.
LEVEL ONE(MINOR)
LEVEL TWO(MAJOR)
LEVEL THREE(CRITICAL)
(Bury, 2010)
Background
A lot of transactions within a day, the paper trail was becoming unmanageable.
In 1987 the antiquated paper driven system almost collapsed under the sheer volume of trades resulting from a rising market.
UK development plans to develop an automated transaction settlement system for the London Stock exchange.
Taurus
Develop an automated transaction settlement system for the London Stock Exchange in 1998.
Aim to create a simple system for large investment houses, which account for over 70% of the value of transactions on the London Stock Exchange.
An 6-month time frame demanded by the securities industry for the completion of the Taurus project.
Original budge is slightly above £6million
Inefficient security market in 19th century
Taurus
Content TitleProject Outcome
Ending budget is £800 million, which is over 130 times of original one.
Previous lose reported by financial times on 3th.Nov, 1993 is just 400 million.
The project is completed nearly 12 years, over 11 years delay.
Develop from several stakeholders to over thirty committees connected to the Taurus project all with their own vested interests.
Complexity of Taurus
Structure of project creates a lack of
cohesion and teamwork between interested
parties
Lacks of leadership and
top management
Failure of Taurus
Cause of failure
(Glotz, 1992)
Improvement
Careful selection of the
appropriate package
Strong
leadershipManagement expectations
Project Team
competenceDedicated resources
Critical Success Factor
(Chapman, 2004)
Case study 2: London Ambulance Service
Area covers 620 square miles
Largest Ambulance Service in the world
Around 4,000 staff at over 70 stations
Carries over 5,000 patients every day
Receives 2,000-2,500 calls each day
(Lond.Ambulance)
Gazetteer and mapping software system
Communications interface (RIFS)
Description of CAD
Radio system -MDTs: Mobile Data Terminals in ambulances -AVLS: Automatic Vehicle Locating System
Computer Aided Despatching System
(Fitzgerald & Russo, 2005)
Outcomes of LAS IS Failure
OUTCOMES
The system could not cope with the load placed on it by normal use.
The response to emergency calls was several hours; 20-30 people died as a result of ambulances arriving too late.
Ambulance communications failed and ambulances were lost from the system.
OVERLOAD
RESPOND CRASH
Reasons of LAS IS Failure
Project Organisation Information System
The complexity of the system
The frustration of the ambulance crews
Communication and response time problems
Poor project managementInexperience of the developers An over-ambitious project timetable Poor training
CSF Improvement
Good project management: lowest cost should not be deciding factor etcGood project management: lowest cost should not be deciding factor etc
Project management
The project should be pre-test before put into practiceThe project should be pre-test before put into practice
Very relaxed project timetable & Training good, timely, and accurate.
Very relaxed project timetable & Training good, timely, and accurate.
(Ein & Segve, 1978)
CSF Improvement
Develop the system more simpler and easierDevelop the system more simpler and easier
Information system
The new system should be as close as possible to the functioning of the manual system
The new system should be as close as possible to the functioning of the manual system
Upgraded the ambulance fleet &make the crews’ job more comfortable
Upgraded the ambulance fleet &make the crews’ job more comfortable
Case study 3:University Accounting System FailureBackground Introduction
University of Cambridge develop a computerized financial
system, which bugs, and continues to be unstable, slow
and complex in its first six weeks. Until now, CAPSA is still
regarded as unreliable and fail to do what it is expected
to do. The result of investigation proved that CAPSA cause
much pain and inconvenience, which cost lots money,
damage the integrity of the university’s financial
processes and tension the relationship between
academics and administration.
(Rohde, 2001)
Causes of FailureThe reasons of system failure include mainly governance
and management
Project manager changed several
times
Not prepare contingency
plans
Project delay
Overspend
Lack of planning of project
infrastructure
Causes
Roles and responsibilities are not clearly
defined
(Laurie, 2003)
Project management
Risk management
Use of consultant
Clear goal and objectives
CSF Analysis
Critical Success Factors
What we can do about it…Sometimes, easy ways make your project success:
• Think well, know what you really want
• Trust your team, communicate frequently
• Review everything, test everything
• Say goodbye to complexity
References:• Adamu, M. (2005). London Ambulance Service Software Failure. • Bocij, e. a. (2006). Business Information System: Technology, Development
and Management for the E-Business. America: Pearson Education Limited.• Bury, M. (2010). Understanding Information Technology System Project
Failure. Retrieved 2 28, 2012, from https://docs.google.com/viewer?a=v&q=cache:ZUflYANfHZIJ:www.kean.edu/~rmelworm/10/3040-04.s10/submittals/ITSFailure-MB.ppt+Understanding+Information+Technology+System+Project+Failure&hl=en&gl=uk&pid=bl&srcid=ADGEESiyo66tTcaztmPxFKIkfoTorTOSfqbsRgjSV_xRMF0
• Chapman, J. (2004). System failure:Why governments must learn to think differently. Journal of Demos, pp. 47-48.
• Ein, P., & Segve, E. (1978). Organizational context and the success of management information systems. Management Science 24, 1064-1077.
• Fitzgerald, G., & Russo, N. (2005). The turnaround of the London Ambulance Service Computer-Aided Despatch system. European Journal of Information Systems, pp. 244-257.
• Flowers, S. (1996). Software failure:management failure. Chichester: John Wiley and Sons.
• Glotz, S. (1992). A sequential learning analysis of decisions in organizations to escalate investments despite continuing costs or losses. Journal of Applied Behavioural Analysis, pp. 561-574.
• International, T. S. (2001). Standish Chaos Report:Extreme Chaos. The Standish Group International.
• Jeff. (2009). Truth about the Project Failure. Retrieved 2 25, 2012, from http://www.youtube.com/watch?v=-eb7-3W4npM
• Laudon, K., & Laudon, J. (2011). Management Information System: Managing The Digital Firm,12th edition. Canada: Pearson Education Limited.
• Laurie, J. (2003). Why Project Fail?-A University Accounting System Case Study. Newcastle: Northumbria University.
• Lond.Ambulance. (n.d.). CAD Failure LAS.1992. Retrieved 3 9, 2012, from Lond.Ambulance: http://www.lond.ambulance.freeuk.com/cad.html
References:
References:• Lyytinen, K., & Hirschheim, R. (1987). Information Systems Failure: A
Survey and Classification of The Empirical Literature. Oxford: Oxford University Press.
• Rohde, L. (2001). Cambridge may sue Oracle,KPMG for failed system. London: IDG News Service.
• Stair, R. M., Reynolds, G., & Chesney, T. (2008). Fundamentals of business information system. London: Course Technology CENGAGE Learning.
• Stair, R. M., Reynolds, G., & Chesney, T. (2008). Principles of Business Information Systems. London: CENGAGE Learning.
• Wastell. (2011). Managers as designers in the public services: beyond technomagic. Axminster: Triarchy Press.