Overview
• Motivation
• Objective & Challenges
• Major Tasks
• Project Timeline
• Configuration
• Cutover
• Data Cleanup
• Questions?
Motivation
• Motivation:– To have an RPSL compliant database– To take advantage of the enhanced syntax
checking and security– To establish the software platform to support
APNIC’s role as Internet Routing Registry– To have a better operational platform (response
time, enhanced mirroring)– To provide richer APNIC database query
options to the public
Objective & Challenges
• Objective– To implement Whois v3 (based on RIPE
v3 Database) before APNIC-14 in September 2002
• Challenges– User awareness– Impact on Policies and Procedures– Data conversion– Minimum downtime
Major Tasks
Task Group Network Ops.
Soft-ware
Communi-cations
Documen-tation
Host-masters
Training Policy
Identify Users X X X
Familiarisation X X X
Communication X X
Tech. Preparation X X
Software Change X
Migration X
Policy X X X X
Project Timeline
Task Group Mar Apr May Jun July Aug Sep
Identify Users
Policy & Procedures
Familiarisation• Internal testing • Public testing• Training
Communication
Tech. Preparation• System Installation• Business Rule Coding
Software Change• DNS update & Web Interface
Migration
Configuration
APNIChostmasters
APNIC memberhostmasters
near realtime mirroring(NRTM) ~ 2-5 mins delay
masterwhois server
publicwhois servers
whois user (public)
database updateprocessing
whois queriesprocessing
command lineinterface
web browserinterface
whois user (public)
mail/webmail/web
command line
Cutover
• From 9:00-10:00 Brisbane time
• A few problems during cutover– Need fine tuning to handle the high load
• Some hosts gets blocked for intensive queries behavior (spam mining?)
– Web interface replacement needed more time than planned (extra 10 minutes)
Data Cleanup
• Unprotected objects
• inetnum/inet6num status:– ALLOCATED PORTABLE– ALLOCATED NON-PORTABLE– ASSIGNED PORTABLE– ASSIGNED NON-PORTABLE– UNSPECIFIED
Questions?