Upload
ramon-nadira
View
216
Download
1
Embed Size (px)
Citation preview
Where Do You Draw the Line?Setting Boundaries BetweenGencos, Transcos, and Discos
Setting boundaries between generation, transmission,and/or distribution companies inevitably requiresreaching acceptable compromises among a number oftechnical, commercial, and regulatory considerations.This article proposes such compromises for theboundaries between a Genco and a Transco, a Transcoand a Disco, and a Disco and another Disco.
Ramon Nadira and Carlos A. Dortolina
Ramon Nadira is a Vice Presidentin the Houston office of Stone &
Webster Management Consultants,Inc. He is an Electrical Engineer
with a Master of Science degree inelectrical engineering and applied
physics, and a Ph.D. degree insystems engineering. For over 23
years, Dr. Nadira has providedtechnical consulting services to
electric utilities, independent projectdevelopers, and the financial
community, in domestic as well asinternational assignments in the
electric power sector. He has recentlyparticipated and/or directed
independent technical consultingservices for electricity transmissionand distribution (T&D) companies
in several countries around theworld.
Carlos A. Dortolina is a SeniorConsultant, also in the Houston
office of Stone & Webster. He is anelectrical engineer with a Master of
Science degree in electric powerengineering, and a Master of
Business Administration degree. Hehas specific international expertise in
business, regulatory, and technicalissues related with restructured
power markets, mainly for T&Dcompanies. His experience covers a
wide range of topics includingprivatization and regulation,
strategic planning, tariff design, riskmanagement and demand
forecasting.
I. Introduction
The need to set boundaries—
physical or otherwise—between
generation companies (Gencos),
transmission companies (Trans-
cos), and distribution companies
(Discos) arises in many contexts.
Such is the case, for example,
when vertically integrated utility
companies are unbundled,
whether this unbundling is from
an ownership, functional, legal,
or financial perspective.1
Unbundling from an ownership
perspective is often required
prior to the incorporation of
private capital into the compa-
nies. Financial unbundling (or
‘‘ring fencing’’ as it is sometimes
known) occurs, for example,
when utilities reorganize them-
selves into separate business
units (SBUs). In the U.S., func-
tional unbundling of transmis-
sion is required under Order No.
888 of the Federal Energy Regu-
latory Commission (FERC).2 This
article focuses on the setting of
boundaries for unbundling from
an ownership perspective, since
arguably this is the case that
gives rise to the most challenging
issues.3
32 # 2003, Elsevier Inc., 1040-6190/$ – see front matter doi:/10.1016/j.tej.2003.09.004 The Electricity Journal
In many cases, the boundaries
are legislated—by law or regula-
tory decree—and generally
involve their specification in terms
of voltage levels. Although this
approach is intuitively appealing,
it creates a practical difficulty: the
boundaries would lie inside the
step-up or step-down transformers!
T o get around that difficulty,
this article proposes a set of
basic principles which result in
the definition of more practical
boundaries. The principles, which
are discussed in Section II, take
explicit account of the technical,
commercial, and regulatory con-
siderations involved in the defi-
nition of the boundaries. Sections
III through V discuss, respec-
tively, setting boundaries
between a Genco and a Transco, a
Transco and a Disco, and a Disco
with another Disco. Section VI
presents several relevant interna-
tional experiences, while Section
VII contains some concluding
remarks.
II. Basic Principles forDefining the Boundaries
We propose the following basic
principles for defining the physi-
cal boundaries among the com-
panies (hereafter, a regulated
customer is one which has no
choice but to purchase electricity
from either the incumbent utility
or a commercialization firm,
while an unregulated—or large—
customer is one which has the
option of instead buying its elec-
tricity directly from the wholesale
market)4:
Principle 1: Asset Property
Must Be Correlated with Asset
Function. For example, if a given
asset is used exclusively to dis-
tribute electric power to a regu-
lated end user, then the property
of that asset should be assigned to
the corresponding Disco.
Principle 2: Boundaries Must
Not Create Artificial Barriers to
the Unencumbered Functioning
of the Wholesale Market. For
instance, no barriers should
artificially hinder the ability of
large consumers to directly
interconnect to the transmission
system.
Principle 3: The Commercial
Impact Caused by a Given
Boundary Must Be Minimized.
For example, in the case of the
boundary between Discos, it is
advisable to establish these at
places that minimize—at least
initially—the impact of such
boundaries on the existing com-
mercial processes and systems
(e.g., not altering existing meter
reading routes, and establishing
the boundaries at places where
interchange meters are already
installed).
In addition, a number of con-
siderations—of a technical, com-
mercial, and regulatory nature—
must be explicitly accounted for
when establishing the bound-
aries. These include:
1. Regulatory Jurisdiction.
Unbundling is much more
complicated if there is more than
one regulatory entity with
jurisdiction over the various
assets. This is the case, for
instance, in the U.S., where FERC
has jurisdiction over transmission
while the states have jurisdiction
over local distribution.
2. Ownership of the Assets.
Unbundling can proceed more
quickly and with fewer road-
blocks if at the start of the process
the majority of the assets are
publicly owned (as opposed to
privately owned). This was the
case in many countries that re-
cently restructured their electri-
city sectors (e.g., the U.K. and
Argentina).
3. Operation and Mainte-
nance of the Assets. For example,
in cases where assets that belong
to one company end up in the
territory of another, contractual
arrangements must be entered
into in order to establish the
rights and obligations of the
various parties with respect to:
(1) access, operation, and main-
tenance of these assets, (2) op-
eration under emergency
conditions, etc.;
4. System Expansion. An im-
portant consideration when de-
fining the boundaries has to do
with the ability of the generation
and distribution companies to
expand their systems without
No barriersshould artificiallyhinder the abilityof large consumersto directlyinterconnect tothe transmissionsystem.
November 2003 # 2003, Elsevier Inc., 1040-6190/$–see front matter doi:/10.1016/j.tej.2003.09.004 33
supervision from the regulatory
entity. For example, if the prop-
erty of the boundary substations
is assigned exclusively to the
transmission company, then the
expansion of these substations
will be subject to the scrutiny of
the regulatory entity.5
T he ultimate objective should
be to implement a
reasonable and practical
segmentation of the utility’s
system, based upon sound
technical principles, and that will
ensure a smooth functioning of
the new entities after they are
unbundled. All of these must be
in compliance with applicable
regulations and give due
consideration to the efficient
operation of the system.
In our experience, this issue
needs to be considered with care,
to avoid a number of pitfalls that
would hinder the smooth func-
tioning of the new entities. In
addition, the issue requires a fair
amount of technical expertise
combined with a deep under-
standing of the control/opera-
tional implications of the
commercial arrangements that are
put in place. The latter are dis-
cussed next.
Allocation of the Property of the
Assets. The natural boundary
between a Genco and a Transco
is at (or more precisely within)
the step-up substations. Simi-
larly, the natural boundary
between a Transco and a Disco is
at (within) the step-down sub-
stations. It is generally at these
substations where power is
respectively transferred from the
Genco to the Transco and from
the Transco to the Disco for final
delivery to the customers. By
contrast, the boundaries between
Discos are generally driven by
geographical considerations,
and often cross medium
and/or voltage lines.
As indicated before, any
attempt to draw the line by
splitting the substation facilities
and equipment in terms of voltage
levels is impractical. Further,
doing so exclusively according to
function (i.e., generation, trans-
mission, and distribution) is likely
to fail. The challenge is that
although it would be rather
straightforward to allocate some
of these facilities and equipment
according to their main function
(e.g., measurement transformers
or switches), there is an important
group of equipment that would
be relatively difficult to split. For
example, the high- and medium-
voltage control cabinets generally
share the same physical space
inside the substation control
room. Other examples are the
substation grounding and the
direct current system, which
are shared.
The above notwithstanding,
our recommendation is that
according to Principle 1 above,
and inasmuch as possible, assets
should indeed be assigned
according to their main function.
The remaining assets (e.g., com-
mon-use equipment which
should represent a relative min-
ority) should be assigned to the
Transco (at Genco/Transco or
Transco/Disco substations) or
the Disco (at Genco/Disco sub-
stations).
F urther, in our opinion, from
an operations and mainte-
nance perspective, the allocation
of assets should not unnecessarily
place the companies in a situation
that may be completely unfami-
liar to them. For example, allo-
cating ultra-high-voltage
equipment to the Disco forces it to
have to develop human resources
and expertise (at a significant
cost) in an area very unfamiliar to
the company. On the other hand,
allocating such equipment to the
Transco does not represent a sig-
nificant additional operations and
maintenance (O&M) burden to
that company. That is, the allo-
cation should promote the further
specialization of the companies.
This specialization should lead to
a more efficient functioning of the
electricity industry.
Finally, and based on our own
experience, allocating the maxi-
mum amount of assets to the
companies that are to be priva-
tized is often times a key driver in
the setting of boundaries, on the
belief that:
(i) this will increase the sales
price at privatization time;
The allocation ofassets shouldnot place the
companies in asituation that
may be completelyunfamiliar
to them.
34 # 2003, Elsevier Inc., 1040-6190/$ – see front matter doi:/10.1016/j.tej.2003.09.004 The Electricity Journal
(ii) from a regulatory perspec-
tive, the privates will be more
successful than the government
at making sure that their asset
costs are fully and properly re-
covered;
(iii) this way, the assets will be
better operated and maintained;
and
(iv) in case expansion is re-
quired, private entities are better
able to raise the needed capital.
One should resist the tempta-
tion of following these seemingly
compelling considerations,
which—although apparently
grounded in reality—do not
comply with the principles
enunciated earlier.6
Establishment of Agreements. In
the case of common-use equip-
ment and/or equipment of a
company that is physically
located within the property of
another, it is necessary for the
companies to enter into contrac-
tual agreements to establish the
rights and obligations of each
party with respect to, among
other issues, operations, mainte-
nance, expansion, and access to
this equipment. Another key
aspect is to clearly establish fair
responsibilities for non-compli-
ance with quality of service stan-
dards, especially when monetary
penalties are involved.7
The agreements should contain
non-discriminatory terms and
conditions that are acceptable to
all parties, and should be made
available to the independent sys-
tem operator (or similar entity).
Additionally, if required, some of
these contracts should be subject
to review by the regulatory entity.
System Expansion. An important
consideration when drawing the
line has to do with preserving the
ability of the Gencos and Discos to
expand their systems at will,
without supervision from the
regulatory entity. For example, if
the step-down substations are
completely assigned to the
Transco, then the expansion of
these substations (including the
distribution feeder sections) is
generally subject to regulatory
approval (since transmission is
almost always regulated as a
natural monopoly). This is not
very desirable since it limits the
ability of the distribution com-
pany to expand its system with-
out regulatory supervision.
Besides, the expansion of the
distribution system should be at
the risk of the Disco itself.
Monitoring and Recording of
Power Transfers between Companies.
In line with Principle 3, and as far
as possible, the boundaries
should be set at places that are
already fitted with the appropri-
ate equipment for measuring
power and energy transfers
between companies. Otherwise,
such equipment needs to be
installed. Although this might
seem to be a minor consideration,
it is very important for cash-
strapped utilities that are about to
unbundle.8
Impact on the Operation of the
Wholesale Electricity Market.
Boundaries should not artificially
interfere with—or create barriers
to—the unencumbered operation
of the wholesale electricity mar-
ket. For example, assigning high-
voltage buses to the Disco may
create artificial barriers for large
customers who wish to connect
directly to the Transco, by forcing
them to pay distribution wheeling
rates. This situation should be
avoided.
III. Boundaries betweena Genco and a Transco
Figure 1 shows a simplified
one-line diagram of the typical
way a generation unit connects to
the corresponding bulk trans-
mission system. In general, all of
the equipment connecting the
generation unit to the high-vol-
tage bus, including the circuit
breakers, the step-up transformer,
and all of the auxiliary equipment
(e.g., switches, protections, etc.)
are specifically sized for that
specific generation unit. In other
words, all of this interconnection
equipment serves a ‘‘generation’’
function.
T herefore, we propose that
the boundary between the
generation and the transmission
companies be defined at the
interconnection point between the
The agreementsshould containnon-discriminatoryterms andconditions thatare acceptableto allparties.
November 2003 # 2003, Elsevier Inc., 1040-6190/$–see front matter doi:/10.1016/j.tej.2003.09.004 35
generator (including its corre-
sponding interconnection equip-
ment) and the transmission bus,
as illustrated in Figure 1.
This proposal is in agreement
with all three principles enun-
ciated in Section II. That is:
1. The property of the assets is
correlated with their ultimate
function.
2. No additional barriers to the
unencumbered functioning of the
wholesale market are introduced.
For instance, it is rather unlikely
(and impractical) for a large
customer to want to connect to
the low-voltage side of the step-
up transformer. Furthermore, it is
not technically possible for addi-
tional generators to connect to the
low-voltage side of the step-up
transformer, since, as mentioned
earlier, the interconnection
equipment is generally sized
specifically for the associated
generation units.
3. The proposal has a mini-
mum commercial impact due to
the fact that, in vertically inte-
grated systems, the natural
boundary between generation
and transmission generally oc-
curs at the point where the gen-
erator connects to the high-
voltage transmission bus. Thus,
power exchanges between the
generation and the transmission
companies are generally mea-
sured at that point. Further, in
many instances, the required in-
frastructure for relaying these
measurements to the system op-
erator is already in place (e.g.,
telemetering facilities).
A s mentioned in Section II,
even though the property
of the interconnection equipment
may be the Genco’s, the operation
and maintenance responsibilities
of this equipment may be
assigned to a third party (e.g., a
Transco) via a contractual
arrangement. This may be the
case, for instance, when the gen-
eration facilities are in remote
locations. In that case, it may be
more cost-effective to contract
with a third party the operation
and maintenance of the intercon-
nection equipment, rather than to
have Genco personnel and equip-
ment on site to handle these rela-
tively infrequent tasks.
F inally, it is sometimes the
case that generation units
connect to distribution—rather
than transmission—facilities. In
those cases, the boundary is
established between a Genco and
a Disco. We propose this bound-
ary be established in a similar
manner as shown in Figure 1, that
is, at the interconnection point
between the generator unit
(including its corresponding
interconnection equipment) and
the distribution bus.
IV. Boundaries betweena Transco and a Disco
Figure 2 shows a simplified one-
line diagram of the typical layout
of a boundary substation between
transmission and distribution (i.e.,
a step-down substation). In this
case, it is possible to postulate at
least five boundary alternatives.
Table 1 describes and contrasts
Figure 1: Proposed Boundary Between a Genco and a Transco
Figure 2: Boundary Alternatives at Step-Down Substations
36 # 2003, Elsevier Inc., 1040-6190/$ – see front matter doi:/10.1016/j.tej.2003.09.004 The Electricity Journal
Table 1: Analysis of Boundary Alternatives at Step-Down Substations (Transco/Disco)
Alternative Description Advantages Potential disadvantages
A The property of
the substation is
completely assigned
to the Transco
� Simplifies the expansion, operation and maintenance
of the substation
� Contrary to Principle 1. Property is not assigned according to function
� Approval and supervision by the regulatory entity is required in order
to modify or expand the distribution portion of the substation
� An agreement is required between the Transco and the Disco to establish
clear responsibilities related to penalty payments arising from interruptions
of the distribution primary circuits. This agreement can potentially lead
to numerous claims
B The boundary is set
immediately after
the medium
voltage bus
� In agreement with Principle 1. Property is assigned according
to function. Note that if large customers connect to the medium
voltage bus, they would be connecting directly to transmission
� The distribution company has control over
modifications/upgrades to the outgoing primary distribution
circuits without any need for approval from the regulatory entity
� In agreement with Principle 3. Meters are generally present at
B to measure the power that flows on each primary distribution
feeder
� THIS IS OUR PREFFERED ALTERNATIVE
� An O&M agreement is probably required for the Transco/Disco to operate
the assets of the Disco/Transco as well as the common-use assets. This
agreement must establish clear responsibilities related to penalty
payments arising from interruptions of the distribution primary circuits,
and can potentially lead to numerous claims
C The boundary is
set just after
the step-down
transformer
� The Disco has control over modifications/upgrades to the
medium voltage bus and the outgoing primary distribution
circuits without any need for approval from the regulatory entity
� In agreement with Principle 3. Meters are generally present at
B to measure the power that flows on each primary distribution
feeder, and therefore, the power that flows from point C on
� Contrary to Principle 2. This boundary may introduce artificial barriers
to the unencumbered functioning of the electricity market, since a
large customer connecting to the medium voltage bus would have to
pay distribution wheeling charges
� An O&M agreement is probably required for the Transco/Disco to operate
the assets of the Disco/Transco as well as the common-use assets.
This agreement must establish clear responsibilities related to penalty
payments arising from interruptions of the distribution primary circuits,
and can potentially lead to numerous claims
Novem
ber2003
#2003,E
lsevier
Inc.,1040-6190/
$–
seefro
nt
matter
do
i:/10.1016/
j.tej.2003.09.00437
Table 1 (Continued )
Alternative Description Advantages Potential disadvantages
D The boundary is
set just before
the step-down
transformer
� The Disco has control over modifications/upgrades to the
step-down transformer, the medium voltage bus, and the
outgoing primary distribution feeders without any need for
approval from the regulatory entity
� Contrary to Principle 2. This boundary may introduce artificial barriers
to the unencumbered functioning of the electricity market, since a large
customer connecting to the medium voltage bus would have to pay
distribution wheeling charges
� Contrary to Principle 3. Additional meters will need to be installed at D
� An O&M agreement is probably required for the Transco/Disco to
operate the assets of the Disco/Transco as well as the common-use assets.
This agreement must establish clear responsibilities related to penalty
payments arising from interruptions of the distribution primary circuits,
and can potentially lead to numerous claims
� The Disco is responsible for the operation and maintenance
of high-voltage equipment
� There is a regulatory risk associated with the possibility that the step-down
transformer would not be recognized as a distribution asset
E The property of
the substation
is completely
assigned to
the Disco
� Simplifies the expansion, operation and maintenance
of the substation
� The Disco has control over modifications/upgrades to the
substation without any need for approval from the
regulatory entity
� Contrary to Principle 1. Property is not assigned according to function
� Contrary to Principle 2. This boundary may introduce artificial barriers
to the unencumbered functioning of the electricity market, since a
large customer connecting to the medium voltage bus would have
to pay distribution wheeling charges
� Contrary to Principle 3. Additional meters will need to be installed at E
� The distribution company is responsible for the operation and maintenance
of high-voltage equipment
� There is a regulatory risk associated with the possibility that the
transformers would not be recognized as distribution assets and therefore
those costs cannot be recovered in the distribution rates.
38#
2003,Elsev
ierIn
c.,1040-6190/$
–see
fron
tm
atterd
oi:/
10.1016/j.tej.2003.09.004
The
Electricity
Journ
al
these five alternatives taking
into account the basic
separation principles enunciated
in Section II.
As shown on Table 1, Alter-
native B is our preferred one.
Note that this alternative results
in substations whose facilities
are of mixed property (some
equipment belongs to the
Transcos and some to the
Discos). This creates
opportunities for the O&M
responsibilities of some of the
equipment to be assigned to the
other party via contractual
arrangements. For example,
when the step-down substations
are in very remote locations, the
Transco may allocate the O&M
responsibilities of its equipment
to the Disco, which must already
have personnel and equipment
in the area to handle its own
O&M responsibilities.
A s mentioned earlier, it is
key to enter into O&M
agreements that establish clear
and fair responsibilities for non-
compliance with quality of service
standards, especially when
monetary penalties are involved.
This is particularly true of the
step-down substations, since
modern regulatory thinking
imposes penalties for service
disconnections (above a given
threshold) to individual custo-
mers of the Discos.
V. Boundaries betweenDiscos
In practice, boundaries
between Discos have been
drawn to maximize the total
value of the resulting companies,
especially when unbundling is in
anticipation of the incorporation
of private capital. In many
instances, this means balancing
out the resulting electricity
market (i.e., load demand)
to be served by each Disco.
Such balancing is often per-
formed with respect to the
number of customers, load
density, energy sales, and
customer mix (i.e., large vs.
regulated customers)9.
A secondary consideration in
the segmentation is that pre-
scribed by Principle 3, which
states that, as much as possible,
the commercial impact caused by
a given boundary should be
minimized. In practice, this has
generally meant that boundaries
are drawn so as to minimize
changes to the existing regional
structure of the distribution
companies. For example, entire
regions are kept within the same
Disco. As a result, the impact on
the commercial procedures and
systems (e.g., customer data-
bases, meter reading routes,
branch offices, etc.) is minimized.
Further, given that historically
the distribution networks are
generally developed from a
regional perspective, this has the
added advantage of also mini-
mizing the technical impact of
the unbundling, since the net-
works in each region are mostly
independent.
N ote that in the case of
the Disco/Disco
boundaries, Principle 1 is
satisfied by definition, since
such boundaries separate
distribution-only assets. On
the other hand, Principle 2
should not come into play in
this case, since the functioning
of the wholesale market
should not be dependent
upon the way the load demand
is organized.
VI. SelectedInternational Experience
This section describes several
international experiences with
regards to the definition of
boundaries among Gencos,
Transcos, and Discos. As can be
seen from the descriptions below,
there is not a unique and uni-
versally accepted solution for the
establishment of these bound-
aries.
United States. In the U.S., the
definition of the boundaries
between transmission and dis-
tribution (the so called ‘‘bright
line’’) has been a topic of debate
for many years. The need to
properly establish this boundary
is particularly important in the
November 2003 # 2003, Elsevier Inc., 1040-6190/$–see front matter doi:/10.1016/j.tej.2003.09.004 39
U.S, since the regulatory entity at
the federal level (i.e., FERC)
generally has jurisdiction over
interstate electricity trading
(using the bulk transmission
network), while public utility
commissions (at the state level)
have jurisdiction over local
distribution. Interestingly
enough, the same term, bright
line, is used to refer to the
separation between state and
federal jurisdiction.
In Order 888,10 FERC proposed
the following seven indicators to
evaluate when determining—on a
case-by-case basis—whether par-
ticular facilities are transmission
or local distribution:
� Local distribution facilities
are normally in close proximity to
retail customers.
� Local distribution facilities
are primarily radial in character.
� Power flows into local dis-
tribution systems; it rarely, if ever,
flows out.
� When power enters a local
distribution system, it is not
reconsigned or transported on to
some other market.
� Power entering a local dis-
tribution system is consumed in a
comparatively restricted geogra-
phical area.
� Meters are based at the
transmission/local distribution
interface to measure flows
into the local distribution
system.
� Local distribution systems
will be of reduced voltage.’’
Note that the above indicators
are, for the most part, functional/
technical in nature, and that they
provide little specific guidance on
where to exactly set the boun-
dary(ies).
With respect to the boundaries
between Gencos and Transcos,
no specific guidelines for
drawing the lines exist in the
U.S. However, some ‘‘de facto’’
experiences do exist. For
example, private power
generators are generally
responsible for building the
step-up substations that
connect the plant to the bulk
transmission system (or to the
distribution system, if that is the
case). In such situations, the
boundary is generally set at or
near the substation fence.
Further, in this case, the technical
and commercial rights and
obligations of the Genco and
the Transco (or the Disco) are
established in interconnection
agreements, subject to review
by the regulatory entity with
jurisdiction over the matter.
Argentina. Step-down
substations in Argentina are
allocated completely to the
Transco. The rationale is that this
simplifies the allocation of
responsibilities between the
Transco and the Disco, thus
minimizing potential conflicts
between these companies.
The boundary is then at the
point where the primary
distribution feeders connect to
the substation.11
T he rights and responsibil-
ities of the Transco and the
Disco at each of the connection
points are established in
‘‘Interconnection Agreements,’’
which are made available
to the ISO. The agreements
establish in detail: (1) property
boundaries, (2) asset ownership,
(3) O&M responsibilities,
(4) facility access, (5)
information exchange
procedures, (6) expansion
procedures, and (7) safety.
The boundary between Gencos
and Transcos is established
immediately after the step-up
transformer. This notwithstand-
ing, the breaker—but not the
high-voltage bus—at the step-up
substation belongs to the Genco
(see Figure 1), but its actual
operation and maintenance is the
responsibility of the Transco. This
is established in an O&M Agree-
ment entered into by the Transco
and the Genco.
Finally, the main basic princi-
ples adopted for drawing the lines
amongst Discos in Argentina
were the following:
(1) Balance out the resulting
load demand to be served by each
Disco. The balancing was
performed with respect to
number of customers, load
density, energy sales, and
customer mix (i.e., large vs.
regulated customers).
40 # 2003, Elsevier Inc., 1040-6190/$ – see front matter doi:/10.1016/j.tej.2003.09.004 The Electricity Journal
(2) Minimize changes to existing
regional structure. This meant
that, for the most part, regions
were not split into separate
Discos. As a result, the impact
on the commercial procedures
and systems (e.g., customer
databases, bill reading routes,
branch offices, etc.) was
minimized. Moreover,
given that historically the
distribution networks had
been developed from a regional
perspective, the technical
impact was also minimized,
since the networks in each
region were mostly
independent.
Guatemala. In contrast with
the previous case, the boundary
between the Transco and the
Disco in Guatemala is
established immediately
after the medium-voltage bus
(Alternative B in Figure 2). The
rationale was that this enables
the Discos to expand their sys-
tems without having to rely on
the procedures and regulatory
constraints that are applicable
to the Transco (as discussed
earlier). The O&M of the
distribution assets within the
substation may be performed by
the Disco itself, or alternatively,
the Disco may choose to enter
into an agreement with the
Transco for the latter to assume
these O&M responsibilities
for a fee.12
O n the other hand, the
boundaries between
Discos were rather simple
to set, since the decision was
made not to split the distribution
systems of any of the larger
cities into separate Discos.
As a result, and for the most
part, the technical and
commercial difficulties
discussed earlier were
altogether avoided.
Panama. Again in contrast with
the previous case, in Panama the
step-up substations themselves
were allocated completely to the
Gencos. As a result, the boundary
between Gencos and Transcos
was established after the high-
voltage bus in the step-up sub-
stations.13
On the other hand, the
step-down substations were
allocated completely to the
Discos. Further, the transmission
lines that connect to these
step-down substations were
also allocated to the distribution
companies. Therefore, the
boundary between the
transmission and the distribution
companies was generally
established at the point in
which the transmission lines
that tie to the step-down
substations are connected to
the source (i.e., high-voltage
switching) substations, whose
property was completely
allocated to the transmission
company.
A s mentioned earlier, the
above examples illustrate
the fact there is not a unique and
universally accepted solution for
the establishment of the bound-
aries between companies.
VII. Conclusion
Restructuring of the power
industry generally means that
vertically integrated utilities
On the other hand, the boundaries between Discos were rather simple to set.
November 2003 # 2003, Elsevier Inc., 1040-6190/$–see front matter doi:/10.1016/j.tej.2003.09.004 41
must be unbundled from an
ownership, functional, legal,
or financial perspective.
Unbundling always brings the
need to establish physical
boundaries between the newly
formed companies. Doing so is
by no means easy.
T his article advances a
number of proposals for
the establishment of physical
boundaries between unbundled
companies. Based on our experi-
ence, these proposals should be
followed as closely as possible.
That is, the decision-maker
should avoid the temptation of
following the seemingly compel-
ling considerations (that contra-
dict the principles enunciated
here) that will inevitably arise
during the segmentation
process.&
Endnotes:
1. In many countries that haverecently restructured their electricitysectors, legislation mandates thelegal separation—or segmentation,as it is often called—of verticallyintegrated companies into theirvarious functions: generation,transmission, distribution, andcommercialization. Further, thislegislation prescribes the inabilityof participants in the electricityindustry of simultaneouslyengaging into selected pairs ofactivities, such as generation andtransmission, or transmission anddistribution.
2. Federal Energy RegulatoryCommission, Promoting WholesaleCompetition Through Open AccessNon-Discriminatory TransmissionServices by Public Utilities, andRecovery of Stranded Costs byPublic Utilities and TransmittingUtilities, Order No. 888, issuedApril 24, 1996.
3. Unbundling a vertically integratedutility from an ownership perspectiveis, to say the least, complicated.A number of issues must beaddressed, such as the allocation ofthe physical assets. This is where ourproposal comes into play, since bydefining a practical boundary, theassets on one side of the boundarybelong to one company, and theassets on the other side belong tothe other.
4. Together with the separationof activities, recent electricity
legislation in many countriesprescribes the establishment of aWholesale Electricity Market (WEM).Further, legislation only allows‘‘large’’ customers to participate inthe WEM, such that these customershave the option to purchase theirown requirements directly fromthe market. Small customers mustpurchase their electricity fromtheir local distribution companies,or in some countries, fromspecialized commercializationentities. It is often the case thatcustomer size is measured interms of peak demand (i.e., peakMW load).
5. For the most part, transmissionand distribution are activities stillsubject to regulation. The differenceis that, in many countries, theregulatory style is evolving fromone of regulating inputs to one ofregulating outputs. In the case ofdistribution companies, what thismeans is that regulators measureperformance in terms of a set of
output indicators, such as frequencyand duration of customers outages.Discos are then free to manipulatetheir inputs (such as systemexpansion) without regulatoryintervention.
6. We say this from experience.
7. Key to the output regulation men-tioned above, is the establishment ofpenalties for non-compliance with theminimum acceptable performancestandards. In some countries, suchpenalties have been rather stiff. Forexample, as a result of the outage eventin 1999 at the Azopardo Substation ofEdesur in Argentina, that companywas fined several tens of millions ofU.S. dollars.
8. Again, this is from experience.
9. In practice this has meant thatthe distribution systems of thelargest city in the country is split inhalf, so that one half is allocated toone Disco and the other half toanother Disco. This is done tomaximize the proceeds from theprivatization, and for the regulatorsto be able to establish regulation bycomparison. A notable exception isGuatemala, where the distributionsystem of the capital city wasprivatized as a single unit.
10. Supra note 2.
11. This is in National Law No.24,065, issued Jan. 16, 1992, and inseveral regulatory orders issued bythe Ente Nacional Regulador de laElectricidad (National ElectricityRegulator of Argentina), (ENRE),including decree 1398/1992, issuedAug. 11, 1992, and decree 0186/1995,issued July 27, 1995.
12. This is in the General ElectricityLaw of Guatemala, Decree No. 93-96,issued Nov. 21, 1996, and the regula-tions of this law, issued by the Comi-sion Nacional de Energıa Electrica deGuatemala (National ElectricityCommission of Guatemala),Agreement No. 256-97.
13. See the Electricity Law, issued Feb.6, 1997. Rules issued June 19, 1998, andthe regulatory decree issued by theEnte Regulador de los Servicios Pub-licos (Public Services Regulatory Entityof Panama), issued Feb. 26, 1998.
42 # 2003, Elsevier Inc., 1040-6190/$ – see front matter doi:/10.1016/j.tej.2003.09.004 The Electricity Journal