Upload
duongdang
View
219
Download
1
Embed Size (px)
Citation preview
2 © 2016 Chevron Corporation
Wheatstone Offshore Platform Hookup and Commissioning
Hookup and commissioning activities continue including the startup of utility systems.
3 © 2016 Chevron Corporation
Commissioning LNG Export System Offshore Umbilicals
The installation of the offshore pipelines connecting the platform to the subsea infrastructure is complete.
4 © 2016 Chevron Corporation
LNG Train 1
All Train 1 process modules required for first LNG have been delivered to the LNG plant site.
5 © 2016 Chevron Corporation
LNG Plant Site
The first Train 2 module has been received at the LNG plant site.
Train 1 Train 2
6 © 2016 Chevron Corporation
LNG Plant Site
The LNG storage tanks are nearing completion with hydrotesting expected to commence soon.