© 2016 Chevron Corporation Wheatstone Project Update January 29, 2016

Wheatstone Project Update - Chevron.com LNG Export System ... The first Train 2 module has been received at the LNG plant site. ... Wheatstone Project Update, January 29, 2016

Embed Size (px)

Citation preview

© 2016 Chevron Corporation

Wheatstone Project Update

January 29, 2016

2 © 2016 Chevron Corporation

Wheatstone Offshore Platform Hookup and Commissioning

Hookup and commissioning activities continue including the startup of utility systems.

3 © 2016 Chevron Corporation

Commissioning LNG Export System Offshore Umbilicals

The installation of the offshore pipelines connecting the platform to the subsea infrastructure is complete.

4 © 2016 Chevron Corporation

LNG Train 1

All Train 1 process modules required for first LNG have been delivered to the LNG plant site.

5 © 2016 Chevron Corporation

LNG Plant Site

The first Train 2 module has been received at the LNG plant site.

Train 1 Train 2

6 © 2016 Chevron Corporation

LNG Plant Site

The LNG storage tanks are nearing completion with hydrotesting expected to commence soon.

7 © 2016 Chevron Corporation

LNG Loading Facility

The LNG and condensate export loading arms have been installed on the product-loading jetty.