DESCRIPTION
System Integration Test. What : System wide demonstration of the DMAC capabilities we’ve been working on for ca.10 years. Why: Proof of concept that DMAC can be unifying element of IOOS; Essential component of system development. - PowerPoint PPT Presentation
Citation preview
What: System wide demonstration of the DMAC capabilities we’ve been working on for ca.10 years.
Why: Proof of concept that DMAC can be unifying element of IOOS; Essential component of system development.
Who: Project team in place, additional involvement by RAs, DMAC ST, other NOS programs
Outcome: Reports, communications material, software, repeatable procedures
MoS:
Clear notion of the things that work and don’t work in DMAC. Tests like this inform our future development.
1
System Integration Test
DMAC Steering Team Nov 2013
IOOS, and others, have been at this for some time.
• 2002: Sys Dev Plan emphasizes data management as the unifying element of disparate systems
• 2005: First DMAC Plan Published• 2007: IOOS PO begins funding Data
Integration Framework pilot• 2010: DMAC Implementation plan and
funding
DMAC Steering Team Nov 2013
Project Team
11/19/2013 3
Software Development: SOS servers, THREDDS, WMS consulting, workflow/scenario scripting, IOOS Catalog, Clients (Python, Java, Matlab)
Metadata consulting, IOOS Registry
System Engineering, Project Management, Documentation
DMAC Steering Team Nov 2013
High Level Schedule
• Project Planning1 Oct – 15 Jan
• Scenario Identification1 Dec – 15 Jan
• Scenario and Test Preparation16 Jan – 28 Feb
• Testing1 Mar – 31 May
• Analysis and Reporting1 Jun – 31 Jul