What is Goliath up to and how
can David benefit from it?
ReGenerate
Introduction
• Utility WRA
• Scalability
• Reduce cost
ReGenerate
Typical Project
80 MW 40 x 2.0 MW Turbines 3 x 60m masts 1 x 80 m masts
ReGenerate
So you’ve got your data…
•60 m mast: $20-40k installed/tower •80 m mast : $80-100k installed/tower •Routine maintenance: $5-10k/year/tower •Corrective maintenance: $5-10k/year/tower •Communication: $1k/year/tower •60 m decommission: $ 5-10k •80 m decommission: $10-30k
Total tower costs over 5 years: ~$425k Cost per MW=$5.3k
You can go cheaper, but you have to be lucky or good.
ReGenerate
…but what it is worth?
• Data processing • $1-2k/tower/year
• Assessments • Informative
• Verification
• 1 / year?
• $5-30k per
• Total for project: ~$130k
• Cost/MW: $ 1.6k
Don’t collect it, if you can’t maintain and analyze it!
ReGenerate
It can be scaled down effectively…
• 80 MW: $555k • 4 masts • 5 years • 5 studies
• 20 MW: $139k • 2 masts • 2 years • 1 study
• 5 MW: $35k • 1 mast • 1 year • 1 study
0
100
200
300
400
500
600
0 50 100
Tho
usa
nd
$
Namplate MW
WRA BUDGET
Total
Data
Analysis
Must spend every penny wisely.
ReGenerate
…but it rarely is.
• Lacking expertise
• Need solid planning
• No clear goals
• Scope creep
• No budget for ongoing costs
• Bad or no advice
• Penny wise and pound foolish
It is better to do a small thing well than a big thing poorly.
ReGenerate
How low can you go?
0
5
10
15
20
25
30
35
40
0 1 2 3 4 5 6
Tho
usa
nd
$
Nameplate MW
WRA BUDGET
Total
Data
Analysis
ReGenerate
When the party is over…
•60 m mast: $20-40k installed/tower •80 m mast : $80-100k installed/tower •Routine maintenance: $5-10k/year/tower •Corrective maintenance: $5-10k/year/tower •Communication: $1k/year/tower •60 m decommission: $ 5-10k •80 m decommission: $10-30k
Total tower costs over 5 years: ~$425k Cost per MW=$5.3k
You can go cheaper, but you have to be lucky or good.
ReGenerate
…somebody has to clean up
•Two options •Carefully decommission and stored •Cut it down •Difference is ~$5k
•How many 10 m masts can you get from a 60 m tower? •20 m? •30 m? •What modifications are necessary?
ReGenerate
Challenges remain
•Late to the party •Installers want to hold towers •Installation •Shipping •Economies of scale •Gov’t funds buying used equipment? •Need cooperation from manufacturer
ReGenerate
Is desperate too strong?
ReGenerate
Sensors are consistent
Part Quantity (per kit)
#40C anemometer or similar (used Part) 1
#200p wind vane or similar (used part) 1
1.53m or similar boom (used Part) 2
25' 2C Sensor Cable (used) 1
25' 3C Sensor Cable (used) 1
Ideal SS 6X500 Clamp (new) 2
Number 5 15 100 200
Unit Cost $300 $200 $75 $70
Total $1,500 $3,000 $7,500 $14,000
Delivery ASAP ASAP End of 2013 End of 2014
ReGenerate
Summary
• “Optics” are fantastic
• Needs proof of concept
• Many unanswered questions
ReGenerate
Questions?
Chris Nuckols
Phone: (712) 577-1825
Thank You
ReGenerate
Optimize early and often
Best times to optimize?
• Define project area
• Major milestones
• “Final” layout
• Now
Because optimization is so cheap compared to the potential value, ROI is always high.
ReGenerate
weaknesses
• Just a tool
• Only as good as data
• Butterfly effect
• Potential for overestimation
• Perfect can be the enemy of good
ReGenerate
Work in progress
• $/MWh
• Calculation vs. rule of thumb
• Early and often
• ROI
• Requires expertise
ReGenerate
What’s it worth?
• Improve project
• Lower Uncertainty
• Financing
• Comfort
• Is it worth it?