Upload
ethan-gilmore
View
214
Download
0
Tags:
Embed Size (px)
Citation preview
Western RenewableEnergy Zone Project
October 29, 2009
John SavageOregon Public Utility Commission
2
OUTLINE
Background
Current Status
Next Steps
3
Western Governors Association Initiative- Identify and map renewable resource-
rich areas
- Build transmission to ship electricity from renewable zones to load centers.
“Unprecedented challenges face the West in meeting the growing demand for electricity while achieving local and global environmental goals. The WREZ Project will help us tap our vast renewable resources and develop transmission that considers communities, environmental impacts and costs.”
Utah Governor Jon Huntsman
WGA Chairman
WREZ at a Glance
4
Genesis of Project
Offshoot of Western Governors’ Clean and Diversified Energy Initiative (2006) Goal of developing 30,000 megawatts of clean energy
by 2015 Advisory committee identified lack of transmission as
key obstacle and made recommendations for reform September 2007: Western Governors’ Summit on
Transmission and Renewables identified WREZ project as a next step
December 2007: Governors submit proposal to U.S. Department of Energy Secretary Bodman to fund WREZ project
May 28 and 29, 2008: Kick-off meeting in Salt Lake City
5
WREZ Phases
Phase 1 and Phase 2 Identify developable renewable energy zones
Develop renewable resource supply curves for each zone
Develop model to estimate delivered price of power from renewable energy zones to load centers
Develop conceptual transmission plans
Phase 3 and Phase 4 Foster coordinated renewable resource acquisition
Facilitate interstate transmission for renewables
WREZ Phase 1 Report
In June 2009, the Western Governors issued WREZ Phase 1 Report
Report identified 54 renewable resource hubs Sites have high quality and developable resource
Sites have at least 1,500 megawatts of renewable resource capacity within 100 miles
Hubs have the potential to generate: 95,000 megawatts of wind
87,000 megawatts of solar
17,000 megawatts if hydro, geothermal and biomass
6
WREZ ‘Hubs”
7
Major Transmission Proposals and
WREZ Hubs
8
Transmission Planning Request
Case 1. Transmission needed to move power from preferred renewable energy zones to load centers:
▪ 10 year analysis
▪ Meet renewable portfolio standard targets throughout the west
Case 2. Transmission needed to move power from preferred zones to loads: 20 year analysis
▪ 33% Renewable Portfolio Standard Target
▪ 50% reduction in CO² emissions
Case 3. Case 1 with higher renewable resource penetration and 25 to 40 % CO² emission reductions
Case 4. Superhighway Network Overlay
9
WREZ Generation and Transmission Model
WREZ Model is used to estimate the delivered price of power from a hub to a load center Model and data-base made public in June
Excel – based
User can change assumptions
Model being refined to include resource supply curves from all REZs for each load center
10
Next Steps
Western Governor’s Topic B proposal to U.S. Department of Energy asked for funding to complete WREZ Phase 3 and Phase 4
Phase 3 tasks: Procure resource from hubs
Identify zones of interest to multiple utilities
Seek collaboration among those utilities and their PUCs to develop common procurement schedules for projects in preferred zones
Aim is to create a critical mass that would justify new transmission to preferred zones
11
Next Steps (cont’d)
Phase 4 tasks: Facilitate coordinated siting and foster interstate discussions on cost allocation Produce and analyze case studies of transmission
siting
Develop regional response to proposed federal actions related to transmission siting
Organize regional forums on improvements in siting practices
Identify cost allocation options and facilitate a stakeholder process that leads to an interconnection-wide policy on cost allocation
Encourage cost allocation negotiations on specific projects
12