Project Objectives: Continue to establish a
comprehensive trail network by connecting Zim Smith trail to NY Route 9 and beyond
Utilize existing trail alignments Evaluate potential for
pedestrian, bike, and equestrian accommodations
Minimize environmental impacts
Proposed Zim Smith Connection Trail
Project Contact Information Audrey Ball Director of Parks and Recreation Town of Malta One Bayberry Drive Malta, NY 12020 (518) 899‐4411 ext. 303 dirparksrec@malta‐town.org
Kevin King Comptroller
Town of Malta 2540 Route 9
Malta, NY 12020 (518) 899‐2502
comptroller@malta‐town.org
Don Adams Project Manager
Creighton Manning Engineering, LLP 17 Computer Drive West
Albany, NY 12205 (518) 446‐0396
Welcome to the Zim Smith Trail Connect ion Project Public Information Meeting
October 26, 2010 7:00 PM
Location: Town of Malta Recreat ion Center
Existing Trolley Trail
Project Schedule: Fall/Winter 2010:
Preliminary Design Winter/Spring 2011:
Final Design Summer 2011:
Construction Begins Fall 2011:
Construction Completion