WELCOME TO BOSTON PPM COMMUNITY
May 2nd, 2018 Presentation will start at 6:00 pm
Please enjoy food, beverage, and networking
AGENDA
From - To Topic
5:30 – 6:00 pm Registration, Refreshments & Networking
6:00 – 6:15 pm Welcome & Introductions
Announcements
Upcoming Meeting Topic Discussion
MS Project Tip
6:15 – 7:15 pm Baselines and Getting Organized.
Presented by John Riopel
Audience Participation / Speaker Q&A
7:15 – 7:30 pm Wrap-up, Networking Sessions, and Final Remarks
2
TOOL TIP OF THE MONTH
Presentation will start at 6:15 pm
Please enjoy food, beverage, and networking
4
WORKING WITH CUSTOM FIELDS AND FORMULAS
“This video provides learning skills for creating custom fields and formulas based on a business scenario.
INTRODUCTIONS AND QUICK HELLO
Leader Mark Wells, MCTS, PMP [email protected]
Leader of Marketing Jan Wells, PMP [email protected]
Board Member Christina Beggs [email protected]
Board Member Jacques Goupil, PMP, MCP, MCTS, V-TSP, CIE
President - PPM Works, Inc.
www.ppmworks.com
Board Member Ed Yee, PMP [email protected]
Board Member
John Riopel, PMP, MCP, MCTS
President - PM Providers
[email protected] www.pm-providers.com
Your name?? 5
1. Name
2. Company
3. What Microsoft Project area are you looking for help with?
MPUG BOSTON MEETING DATES
• MEETINGS ARE SCHEDULED THE FIRST WEDNESDAY OF THE MONTH -
HELD AT CONSTANT CONTACT IN WALTHAM
WEDNESDAY, MAY 2ND
WEDNESDAY, JUNE 6TH
WEDNESDAY, SEPT 5TH
WEDNESDAY, OCT 3RD
WEDNESDAY, NOV 7TH
Location:
1601 Trapelo Road, Waltham, MA
Exit 28 off 1-95 South
Exit 28B off I-95 North
2018
BOSTON PPM COMMUNITY UPCOMING EVENTS
Date Topic Speaker
Wednesday, May 2nd Baselines and Getting Organized John Riopel
Wednesday, June 6th Milestones Professional Gordon Chartier
Wednesday, Sept 5th TBD Phil Perkins
CALL FOR PRESENTERS
WHY:
• SHARE YOUR KNOWLEDGE WITH YOUR PEERS
• RECEIVE PDUS
• GIVE BACK TO YOUR PROJECT COMMUNITY
WHAT:
1. PRESENT YOUR OWN FULL-LENGTH TOPIC (45 MINUTES)
WHEN: THE FOLLOWING SESSIONS ARE AVAILABLE
• WEDNESDAY, SEPTEMBER 5TH
• WEDNESDAY, OCTOBER 3RD
• WEDNESDAY, NOVEMBER 7TH
POTENTIAL MEETING TOPICS
• ??
MS PROJECT TIP
ORGANIZER?
• ALLOWS YOU TO MOVE CUSTOM AND OUT OF THE BOX FUNCTIONS TO OTHER PROJECT
FILES OR TO THE COMPUTER GLOBAL FILE - GLOBAL.MPT
• AUTOMATICALLY ADD NEW VIEWS, TABLES, FILTERS, AND GROUPS TO THE GLOBAL –
ADVANCED OPTIONS
WHAT IS A BASELINE?
• THE PROJECT'S BASELINE IS USED TO MEASURE HOW PERFORMANCE
DEVIATES FROM THE PLAN.
• A PROJECT'S BASELINE IS DEFINED AS THE ORIGINAL SCOPE, COST AND
SCHEDULE.
THERE ARE TWO TYPES IN MICROSOFT PROJECT:
FULL BASELINES
INTERIM BASELINES
WHAT HAPPENS WHEN YOU USE EITHER OPTION?
• FULL BASELINE
• COPIES START, FINISH, WORK, DURATION AND COST TO
• SELECTED FULL BASELINE – BASELINE 0-10
• INTERIM PLAN BASELINE
• COPIES START AND FINISH ONLY TO
• SELECTED START (X) TO FINISH (X), WHERE X IS 1-10 OF THE SAME NUMBER
WHICH TASKS AM I BASELINING?
• ENTIRE PROJECT
• ALL TASKS
• SELECTED TASKS
• MUST SELECT THE TASKS PRIOR TO CHOOSING THE SET BASELINE BUTTON
ON THE PROJECT RIBBON
• ROLL UP BASELINES
• TO ALL SUMMARY TASK - UPDATED BASELINE DATA FOR THE NEW TASKS IS
ROLLED UP TO ALL ASSOCIATED SUMMARY TASKS, NOT JUST THE NEAREST
SUMMARY TASK.
• FROM SUBTASKS INTO SELECTED SUMMARY TASKS - BASELINE DATA IS UPDATED
ONLY FOR THE SELECTED SUMMARY TASK. TYPICALLY, YOU’LL DO THIS SO THAT
ONLY THE NEAREST SUMMARY TASK REFLECTS THE NEW ROLL-UP DATA.
CAN I NAME A BASELINE? • NOT REALLY
• YOU CAN CREATE A MACRO, HOWEVER
THAT DOES SORT OF THAT
• PRIVSELECT CASE STAGEBOX.VALUE
• CASE "CONCEPT"
• GANTTBARSTYLEBASELINE BASELINE:=1, SHOW:=TRUE
• CASE "FEASIBILITY"
• GANTTBARSTYLEBASELINE BASELINE:=2, SHOW:=TRUE
• CASE "INITIATE"
• GANTTBARSTYLEBASELINE BASELINE:=3, SHOW:=TRUE
• CASE "DEVELOPMENT"
• GANTTBARSTYLEBASELINE BASELINE:=4, SHOW:=TRUE
• CASE "DEVELOPMENT INTERIM 1"
• GANTTBARSTYLEBASELINE BASELINE:=5, SHOW:=TRUE
• CASE "DEVELOPMENT INTERIM 2"
• GANTTBARSTYLEBASELINE BASELINE:=6, SHOW:=TRUE
• CASE "QUALIFICATION"
• GANTTBARSTYLEBASELINE BASELINE:=7, SHOW:=TRUE
• CASE "QUALIFICATION INTERIM 1"
• GANTTBARSTYLEBASELINE BASELINE:=8, SHOW:=TRUE
• CASE "QUALIFICATION INTERIM 2"
• GANTTBARSTYLEBASELINE BASELINE:=9, SHOW:=TRUE
• CASE "LAUNCH"
• GANTTBARSTYLEBASELINE BASELINE:=10, SHOW:=TRUE
• CASE "ALL"
• GANTTBARSTYLEBASELINE BASELINE:=1, SHOW:=TRUE
• GANTTBARSTYLEBASELINE BASELINE:=2, SHOW:=TRUE
• GANTTBARSTYLEBASELINE BASELINE:=3, SHOW:=TRUE
• GANTTBARSTYLEBASELINE BASELINE:=4, SHOW:=TRUE
• GANTTBARSTYLEBASELINE BASELINE:=5, SHOW:=TRUE
• GANTTBARSTYLEBASELINE BASELINE:=6, SHOW:=TRUE
• GANTTBARSTYLEBASELINE BASELINE:=7, SHOW:=TRUE
• GANTTBARSTYLEBASELINE BASELINE:=8, SHOW:=TRUE
• GANTTBARSTYLEBASELINE BASELINE:=9, SHOW:=TRUE
• GANTTBARSTYLEBASELINE BASELINE:=10,
SHOW:=TRUE
• END SELECT
• VIEWAPPLY "TRACKING GANTT"
• END SUB
• PRIVATE SUB SAVEBASELINEBUTTON_CLICK()
• SELECT CASE STAGEBOX.VALUE
• CASE "CONCEPT"
• BASELINESAVE INTO:=PJINTOBASELINE
• BASELINESAVE INTO:=PJINTOBASELINE1
• GANTTBARSTYLEBASELINE BASELINE:=1, SHOW:=TRUE
• CASE "FEASIBILITY"
• BASELINESAVE INTO:=PJINTOBASELINE
• BASELINESAVE INTO:=PJINTOBASELINE2
• GANTTBARSTYLEBASELINE BASELINE:=2, SHOW:=TRUE
• CASE "INITIATE"
• BASELINESAVE INTO:=PJINTOBASELINE
• BASELINESAVE INTO:=PJINTOBASELINE3
• GANTTBARSTYLEBASELINE BASELINE:=3, SHOW:=TRUE
• CASE "DEVELOPMENT"
• BASELINESAVE INTO:=PJINTOBASELINE
• BASELINESAVE INTO:=PJINTOBASELINE4
• GANTTBARSTYLEBASELINE BASELINE:=4, SHOW:=TRUE
• CASE "DEVELOPMENT INTERIM 1"
• BASELINESAVE INTO:=PJINTOBASELINE
• BASELINESAVE INTO:=PJINTOBASELINE5
• GANTTBARSTYLEBASELINE BASELINE:=5, SHOW:=TRUE
• CASE "DEVELOPMENT INTERIM 2"
• BASELINESAVE INTO:=PJINTOBASELINE
• BASELINESAVE INTO:=PJINTOBASELINE6
• GANTTBARSTYLEBASELINE BASELINE:=6, SHOW:=TRUE
• CASE "QUALIFICATION"
• BASELINESAVE INTO:=PJINTOBASELINE
• BASELINESAVE INTO:=PJINTOBASELINE7
• GANTTBARSTYLEBASELINE BASELINE:=7, SHOW:=TRUE
• CASE "QUALIFICATION INTERIM 1"
• BASELINESAVE INTO:=PJINTOBASELINE
• BASELINESAVE INTO:=PJINTOBASELINE8
• GANTTBARSTYLEBASELINE BASELINE:=8, SHOW:=TRUE
• CASE "QUALIFICATION INTERIM 2"
• BASELINESAVE INTO:=PJINTOBASELINE
• BASELINESAVE INTO:=PJINTOBASELINE9
• GANTTBARSTYLEBASELINE BASELINE:=9, SHOW:=TRUE
• ATE SUB DISPLAY_CLICK()
• CASE "LAUNCH"
• BASELINESAVE INTO:=PJINTOBASELINE
• BASELINESAVE INTO:=PJINTOBASELINE10
• GANTTBARSTYLEBASELINE BASELINE:=10, SHOW:=TRUE
• END SELECT
• VIEWAPPLY "TRACKING GANTT"
• END SUB
• PRIVATE SUB STAGEBOX_CHANGE()
• END SUB
• PRIVATE SUB USERFORM_INITIALIZE()
• STAGEBOX.ADDITEM ("CONCEPT")
• STAGEBOX.ADDITEM ("FEASIBILITY")
• STAGEBOX.ADDITEM ("INITIATE")
• STAGEBOX.ADDITEM ("DEVELOPMENT")
• STAGEBOX.ADDITEM ("DEVELOPMENT INTERIM 1")
• STAGEBOX.ADDITEM ("DEVELOPMENT INTERIM 2")
• STAGEBOX.ADDITEM ("QUALIFICATION")
• STAGEBOX.ADDITEM ("QUALIFICATION INTERIM 1")
• STAGEBOX.ADDITEM ("QUALIFICATION INTERIM 2")
• STAGEBOX.ADDITEM ("LAUNCH")
• STAGEBOX.ADDITEM ("ALL")
• END SUB
• PRIVATE SUB CANCELBUTTON_CLICK()
• CBFORM.HIDE
• END SUB
LET’S HEAR FROM YOU!
QUESTIONS?
BREAK-OUT SESSIONS & REFRESHMENTS
WHO WE ARE
PM PROVIDERS IS A FULL-SERVICE PROFESSIONAL SERVICES FIRM PROVIDING
PROJECT MANAGEMENT & COLLABORATION SOLUTIONS THAT DELIVER BUSINESS
RESULTS AND
DRIVE TRANSFORMATIONAL CHANGE.
WE DELIVER COMPREHENSIVE CONSULTING SERVICES WHICH ENABLE OUR
CLIENTS TO REALIZE KEY BUSINESS INITIATIVES THROUGH A UNIQUE
COMBINATION OF HIGHLY EFFECTIVE PARTNERING, TARGETED TRAINING, AND
STRATEGIC DEPLOYMENT OF PROJECT MANAGEMENT AND COLLABORATION
TECHNOLOGIES.
21