2 Sizewell C Community Forum | 21st November 2013 | NOT PROTECTIVELY MARKED
Sizewell C Community ForumStephen Walls, Head of Sizewell C Project21 November 2013
3 Sizewell C Community Forum | 21st November 2013 | NOT PROTECTIVELY MARKED
Agenda
• Nuclear New Build Update
• Sizewell C – Post Stage 1 Activity
• Sizewell C – Transport and Accommodation Update
• What Next?
4 Sizewell C Community Forum | 21st November 2013 | NOT PROTECTIVELY MARKED
NNB Update – HPC Agreement and Next Steps
Conditional Commercial Close
October 2013
• Agreement on Commercial terms for HPC
• Confirmation of ongoing support of UK
• Letters of intent with partners
• Agreements in principle with top 4 suppliers
4 Sizewell C Community Forum | 21st November 2013 | NOT PROTECTIVELY MARKED
NNB Update – HPC Agreement and Next Steps
Conditional Commercial Close
October 2013
Conditional Financial Close
• Agreement on Commercial terms for HPC
• Confirmation of ongoing support of UK
• Letters of intent with partners
• Agreements in principle with top 4 suppliers
• Binding agreements on investment terms with CGN, CNNC and Areva, and possible other partners
• Binding agreement with Infrastructure UK on terms for a guarantee of the project’s debt financing
• CfD and Funded Decommissioning Programme full contracts
4 Sizewell C Community Forum | 21st November 2013 | NOT PROTECTIVELY MARKED
NNB Update – HPC Agreement and Next Steps
Conditional Commercial Close
October 2013
Conditional Financial Close
Unconditional Final Investment Decision
• Agreement on Commercial terms for HPC
• Confirmation of ongoing support of UK
• Letters of intent with partners
• Agreements in principle with top 4 suppliers
• Binding agreements on investment terms with CGN, CNNC and Areva, and possible other partners
• Binding agreement with Infrastructure UK on terms for a guarantee of the project’s debt financing
• CfD and Funded Decommissioning Programme full contracts
• Receipt of full State Aid clearance from the European Commission
• Agreement of full debt and equity contracts
5 Sizewell C Community Forum | 21st November 2013 | NOT PROTECTIVELY MARKED
Lower costs for successive power stations – a ‘series benefit’
“This … marks the next generation of nuclear power in Britain, which has an important part to play in contributing to our future energy needs and our longer term security of supply.”
David Cameron, Prime Minister
Project Strike Price
HPC £92.50/MWhHPC* £89.50/MWh
SZC TBC*HPC Strike price if Sizewell C is also built
HPC Agreement – What it means for Sizewell
A kick start for the UK’s new nuclear programme
6 Sizewell C Community Forum | 21st November 2013 | NOT PROTECTIVELY MARKED
Overview of EDF partners on HPC project
Partner of EDF for the past 30 years through
co-investment with on the Taishan EPR and the Daya Bay nuclear power station
Major nuclear corporation, 100% owned by the
Government of the People’s Republic of China
Partner of EDF for thepast 30 years
Leading Chinese nuclear operator and developer,
100% owned by the Government of the People’s
Republic of China
Signifi cant EPR designand construction experience
with EDF through involvement in FLA3
and Taishan
Key supplier of EDF. 83% owned by French
government
57% of the project’s construction value could be spent in the UK, building skillsand expertise which will help the country win a greater share of nuclear
programmes nationally and globally
7 Sizewell C Community Forum | 21st November 2013 | NOT PROTECTIVELY MARKED
NNB – What Next?
Statement of Community Consultation
Stage 1 Consultation
Further Consultation/s
with local people
Application Submission
to the Planning
Inspectorate
Construction OperationDecision by Secretary of
State for Energy and
Climate Change
Sizewell C Hinkley Point C
8 Sizewell C Community Forum | 21st November 2013 | NOT PROTECTIVELY MARKED
Sizewell C Post-Stage 1 Activity
9 Sizewell C Community Forum | 21st November 2013 | NOT PROTECTIVELY MARKED
SZB Outage Survey• Approx. 1,100 additional people working at Sizewell B.
• Some of the outage workforce are not from the area (Non-Home-Based).
• Helps understand impacts of a NHB workforce to the area including businesses.
• Helps understand where NHB workers choose to stay and how they travel to site.
10 Sizewell C Community Forum | 21st November 2013 | NOT PROTECTIVELY MARKED
Groundwater Monitoring
• Borehole drilling in ten locations within and around the SSSI.
• Monitoring will provide us with important information about groundwater conditions.
11 Sizewell C Community Forum | 21st November 2013 | NOT PROTECTIVELY MARKED
Ecology Surveys
• Surveys are being carried out around the Sizewell estate and AONB.
• Bat survey on Sizewell C site.
• Bird surveys along the coast.
• Studies will inform the ecological assessment.
12 Sizewell C Community Forum | 21st November 2013 | NOT PROTECTIVELY MARKED
Coastal Processes Radar
• Gathering wave information between Minsmere Sluice and Thorpeness, up to 3km from shore.
• Data will be used to understand how the local seabed and shore responds to waves under different weather conditions.
• This will support design work on the sea defences and jetty.
13 Sizewell C Community Forum | 21st November 2013 | NOT PROTECTIVELY MARKED
Design and Engineering
• Preliminary design of access bridges across SSSI.
• Developing sea defence designs.
• Concept design of Jetty (MOLF).
• Investigating ground conditions for possible rail routes.
14 Sizewell C Community Forum | 21st November 2013 | NOT PROTECTIVELY MARKED
Offshore Surveys
• Test drilling to confirm geological conditions for the cooling water tunnels and intake structures.
Eastbridge
DenningtonDenningtonDenningtonDennington
Rendlesham Sudbourne
Snape
LowerHacheston
AldringhamKnodishall
Thorpeness
WalberswickWalberswick
SouthwoldSouthwoldSouthwoldWenhastonCratfield
LaxfieldLaxfield
Badingfield
Peasenhall
SaxteadSaxtead
Earl SohamEarl Soham
FramsdenFramsden
DebenhamDebenham
Cranley
FramlinghamFramlinghamFramlinghamFramlinghamFramlingham
Kelsale
StradbrokeStradbroke
Ufford
Hollesley
GrundisburghWitneshamWitnesham
SwillandSwilland
Hanley
ForwardGreenGreen
RushmereSt Andrew
KesgraveKesgrave
Foxhall
Bucklesham
Wherstead
Cupdock
Hasketon
Clopton
Martlesham
KirtonLevington
Otley
OrfordOrford
IPSWICH
Leiston
Westleton
Theberton
Darsham
Saxmundham
Bredfield
Farnham
Hacheston
Wickham Market
Woodbridge
Melton
Nacton
Yoxford
A12
A12
B1119
A1094
B1069
B1122
A144
A12
A12
A12
A14
A14
Aldeburgh
15
Sizewell C – Transport andAccommodation Update
NOT PROTECTIVELY MARKED
16 Sizewell C Community Forum | 21st November 2013 | NOT PROTECTIVELY MARKED
Developing the Transport and Accommodation StrategyOur aim is to reduce the potential traffic pressure caused by workers and freight travelling to and from the Sizewell C development site.
Socio-economic analysis
Workforce profile
No. of beds required
Campus site detail
Quantity of freight by rail
Residual quantity of freight by road
With development transport model
No. of ‘people’ on road
Quantity of freight by sea
Road improvements
Park and ride site detail
Potential sources of materials
Rail route options
Jetty design
No. of non-home based workers
17 Sizewell C Community Forum | 21st November 2013 | NOT PROTECTIVELY MARKED
Accommodation Strategy
• Single campus: significant efficiency benefit of a single campus.
• Campus management: Concentrated workforce allows creation of a more attractive campus environment which should encourage occupancy levels.
• Workforce management: Operational efficiency.
• Community Safety and Community Cohesion.
• Minimising traffic impact.
18 Sizewell C Community Forum | 21st November 2013 | NOT PROTECTIVELY MARKED
Associated Development Site Assessment Process
Full EIA
Environmental Surveys
(Fieldwork)
Land Issues
Site Selection
Site Investigations
Site Engineering/ Operational
Considerations
Ongoing Consultation
Transport Issues
Socio-Economic Factors
Stage 1 Consultation
ResponsesPlanning
Policy
This is a detailed and iterative process and there is still work to be done
19 Sizewell C Community Forum | 21st November 2013 | NOT PROTECTIVELY MARKED
Indicative Associated Development Site Selection
• Lead Site: The likely, but not definite, location we will present for the associated development at a further consultation stage.
• Reserve Site: To be considered further if the lead site cannot be taken forward.
• Discontinued Site: Not being pursued at this time.
Rendlesham Sudbourne
Snape
LowerHacheston
AldringhamKnodishall
ThorpenessThorpeness
Eastbridge
WalberswickWalberswick
SouthwoldSouthwoldSouthwoldWenhastonCratfield
LaxfieldLaxfield
Peasenhall
DenningtonDenningtonDenningtonDennington
SaxteadSaxtead
Earl SohamEarl Soham
FramsdenFramsden
FramlinghamFramlinghamFramlinghamFramlinghamFramlingham
Kelsale
StradbrokeStradbroke
Ufford
GrundisburghWitnesham
Swilland
Clopton
Otley
A12
A12
B1119
A1094
B1069
B1122
A144
A12
A12
Sizewell PowerStation Complex
DarshamPark & Ride
YoxfordPark & Ride
2 A12/A144Park & Ride
3
1
Westleton
Theberton
Darsham
Saxmundham
Aldeburgh
Bredfield
Farnham
Hacheston
Wickham Market
Melton
Yoxford
Leiston
Associated Development:Park and Ride - North
Option 1:Yoxford Road
Option 2:Darsham
Option 3:A12/A144
20 NOT PROTECTIVELY MARKED
21 Sizewell C Community Forum | 21st November 2013 | NOT PROTECTIVELY MARKED
Park and Ride North Option for Further Consultation
• Lead Site: Darsham (Option 2).
– Environmental surveys, ground investigations and masterplanning due to commence Q1 2014.
– Community engagement.
• Reserve Site: A12/A144 (Option 3).
• Discontinued Site: Yoxford Road (Option 1).
Rendlesham Sudbourne
Snape
LowerHacheston
Knodishall
SaxteadSaxtead
Earl SohamEarl Soham
FramsdenFramsden
DebenhamDebenhamFramlinghamFramlinghamFramlinghamFramlinghamFramlingham
Kelsale
Ufford
Hollesley
GrundisburghWitneshamWitnesham
SwillandSwilland
Hanley
ForwardGreenGreen
RushmereSt Andrew
KesgraveKesgrave
Foxhall
Bucklesham
WhersteadWherstead
CupdockCupdock
Hasketon
Clopton
Martlesham
KirtonLevington
Orford
IPSWICHIPSWICHIPSWICH
B1119
A1094A12
A12
A12
A14
A14
PotashCorner Park & Ride
Wickham MarketPark & Ride
3
1
WoodbridgePark & RideWoodbridgePark & RideWoodbridge
2
Saxmundham
Bredfield
Farnham
Hacheston
Wickham Market
Woodbridge
Melton
Nacton
Associated Development:Park and Ride - South
Option 1:Wickham Market
Option 2:Woodbridge
Option 3:Potash Corner
22 NOT PROTECTIVELY MARKED
23 Sizewell C Community Forum | 21st November 2013 | NOT PROTECTIVELY MARKED
Park and Ride South Option for Further Consultation
• Lead Site: Wickham Market (Option 1).
– Subject to results of the archaeological surveys, ground investigations, environmental surveys, master-planning will commence in Q1 2014.
– Community engagement.
• Primary Reserve Site: Woodbridge (Option 2).
• Secondary Reserve Site: Potash Corner (Option 3).
– Potential to discontinue.
Rendlesham Sudbourne
Snape
LowerHacheston
AldringhamKnodishall
ThorpenessThorpeness
Eastbridge
WalberswickWalberswick
SouthwoldSouthwoldSouthwoldWenhastonCratfield
LaxfieldLaxfield
Badingfield
Peasenhall
DenningtonDenningtonDenningtonDennington
SaxteadSaxtead
Earl SohamEarl Soham
FramsdenFramsden
DebenhamDebenham
Cranley
FramlinghamFramlinghamFramlinghamFramlinghamFramlingham
StradbrokeStradbroke
Ufford
GrundisburghWitneshamWitnesham
SwillandSwilland
RushmereSt Andrew
Hasketon
Clopton
Martlesham
Otley
OrfordOrford
A12
A12
B1119
A1094
B1069
B1122
A144
A12
A12
Sizewell PowerStation Complex
Westleton
Theberton
Darsham
Aldeburgh
Bredfield
Farnham
Hacheston
Wickham Market
Woodbridge
Melton
Yoxford
Leiston
DevelopmentSite CampusDevelopmentSite CampusDevelopment
1
Sizewell GapCampus
2
Leiston EastCampus
3
Associated Development:Campus Accommodation
Option 1:Development Site
Option 2:Sizewell Gap
Option 3:Leiston East
24 NOT PROTECTIVELY MARKED
25 Sizewell C Community Forum | 21st November 2013 | NOT PROTECTIVELY MARKED
Campus Option for Further Consultation
• Lead Site: Development Site (Option 1)
– Ground investigations to commence shortly on part of the site
– Community engagement
– Landscaping and master planning
• Reserve Site: Leiston East (Option 3)
• Discontinued Site: Sizewell Gap (Option 2)
26 Sizewell C Community Forum | 21st November 2013 | NOT PROTECTIVELY MARKED
Associated Development: Rail OptionsOption 1:New Terminal
Option 2:Rail Extension into the Site Blue and Green subject to further assessment
Sizewell C What Next?
27 Sizewell C Community Forum | 21st November 2013 | NOT PROTECTIVELY MARKED
28 Sizewell C Community Forum | 21st November 2013 | NOT PROTECTIVELY MARKED
2014 Headline Activity
Community Engagement Technical StudiesConsultation with communities living near associated development sites.
Ongoing environmental study and assessment, including completion of Wickham Market archaeology
Workshops and consultation with local authorities and DEFRA agencies.
Ongoing engineering design work.
Formal consultation on the detailed preferred proposals for the Sizewell C project to follow later in the year.
Further development of with-development traffic modelling.
29 Sizewell C Community Forum | 21st November 2013 | NOT PROTECTIVELY MARKED
Thank you