1OPERATIONAL ENERGY GROUP INDIA PVT.LTD SITE:M/S IND BARATH
POWER GEN COM 3 X 63 MW ,IPP 250 TPH/110 KSC/540 DEG CCHP WEEKLY
JOB REPORTDate:1-6 March,2015S.NoDateWork Permit
No.AreaEquipmentJob DescriptionPlanned timeTime TakenNo of
PersonsTotal Man hoursSpares usedName of
Persons101-03-1516853CHPPVS-1,BC5,BC1PVS 1 Full jam condition
cleaning work done,PVS 2 lubrication work done,BC5 2 Return &
Carrying rollers changed,BC1 2 return & Ider rollers
changed2236Navaneethan,Vallinayagam,durai202-03-1516854CHPPSV 1PVS
1 Mesh replacement work done,55315Charles,Navaneethan,DuraiJCB
FL,BEML FL,Doser 34 & 35JCB FL full water service & grease
service,BEML FL Doser 34 & 35 pm work greasing of joints
transmission filter changing,transmission oil engine oil
top66212Rajesh,Manickam303-03-154132 & 16855CHPBC1,Coal Bunker
2BC1 Pm work the motor bed & gear box bed plumber block fluid
coupling bolt tightness,DE/NDE bearing grease condition,gear box
& fluid coupling oil level,discharge chute leakage,scraper belt
condition,take off pulley bearing & grease condition all
checked,Coal Bunker 2 chute grill welding
work66424Charles,Vallinayagam,Durai,PramothDoser 34Reverse gear
problem work under progress3326Rajesh,Manickam404-03-1516858 &
16857 &16856CHPBC5 & BC1,PVS1,Crusher 1,Tunnel vibro feeder
1&2BC5 Belt Patch work done;BC1 3 Rollers Replaced & pull
chord checking work & control room pm work done by
instrumentation,PVS 1 pm work the motor casing bolts & jack
bolt tightness checked,bearing housing bolt tightness
checked,bearing grease checked,bearing condition &
clearance,belt guard cover bolts,pedestal spring condition,dischrge
chute leakage checked,all spporting of screens,Crusher 1 pm work
the v-belt pulley,motor & mother base bolts & jack bolt
tightness,plumber block base fasteners,crusher foundation
bolts,coupling condition,bearing housing & grese,liner bolt
tightness,crushing hmmer tooth condition,inlet & discharge
chute leakage,roller & liner adjusting bolts tightness all
checked,Vibro feeder 1& 2 the Motor counter weight angle
condition,sling & spring condition,chute leakage bolt
tightness,spring tension all
checked771177Charles,Vallinayagam,Durai,Ganesh(inst),CL 7Doser
34Doser 34 reverse gear problem gearing assembly bearing heavy wear
and tear work under
progress44312Rajesh,NavaneethaKrishnan,Manickam505-03-1516859 &
4135CHPCoal Bunker unit 1,PVS-2Coal bunker unit 1 1 inch fire line
welding work done,PVS 2 pm work the screen cloth tension &
jamming checked,motor casing bolts & jack bolt tightness
checked,screen mat condition,bearing housing bolt tightness
checked,bearing grese checked,bearing condition &
clearance,belt guard cover bolts,pedestal spring condition,dischrge
chute leakage checked,marsh melloe spring condition,all spporting
of screens,dust sealing cloth fastners
checked66530Charles,Vallinayagam,Durai,Pramoth+1Doser 34Doser 34
reverse gear problem gearing assembly lifting hydra needed so work
stalled other minor checking going
on2224Rajesh,Manickam606-03-154139 & 16866CHPBC5 & BC6BC6
belt patch up work done,BC5 pm work the motor bed & gear box
bed plumber block fluid coupling bolt tightness,DE/NDE bearing
grease condition,gear box & fluid coupling oil level,discharge
chute leakage,scraper belt condition,take off pulley bearing &
grease condition all checked44312Charles,Durai,VallinayagamDoser
34Doser 34 transmission is lifted using hydra nd work under
progress on the mechanical
workshop44312RajeshNavaneethaKrishnan,Manickam