WEEKLY CONSTRUCTION PROGRESS REPORT
Week of 3/23/20
3/23
Project: Maple Elementary / Middle School Submission Date: 3/27/2020
To: Maple Elementary – Middle School To: Caolo & Bieniek Associates
Building Committee
Tom Brown Bert Gardner
50 Payson Avenue 521 East Street
Easthampton, MA 01027 Chicopee, MA 01020
Construction Representative: Matt Dunn Project Phone: (Cell)
Email Address: Project Fax: Fax #
Project Address: 200 Park Street
Easthampton, MA 01027
Project Activity Summary:
GENERAL
• Started the electrical work necessary to switch-over the school to temporary power.
SITE
• Excavated, installed piping and partially backfilled the storm water detention basin.
• Cut grade adjacent to the basin.
• Backfilled Building B foundation.
• Installed three sewer manholes and pipe connecting them.
• Trenched for Building A south & Building D north & east footings.
• Started to dig for isolated footings in Building B.
BUILDING
• Poured footings and foundation frost walls in Building B. & C.
Attachments: Photos
WEEKLY CONSTRUCTION PROGRESS REPORT
Week of 3/23/20
3/23
BACKFILLING OVER STORM WATER DETENTION BASIN FOOTING TRENCH FOR BUILDING A SW CORNER
CONDUIT FOR TEMPORARY POWER AT PULL BOX BACKFILLING SEWER PIPE RUN
WEEKLY CONSTRUCTION PROGRESS REPORT
Week of 3/23/20
3/23
TYPICAL COLUMN ANCHOR BOLT AND LEVELING PLATE BACFILLING & COMPACTING IN BUILDING B
BUILDING A CONCRETE FOOTING POURED TODAY EXCAVATED & PREPPED FOR BLDG. B ISOLATED FTG.
WEEKLY CONSTRUCTION PROGRESS REPORT
Week of 3/23/20
3/23