Weekly Construction Newsletter February 1, 2016elkhorn.ss5.sharpschool.com/UserFiles/Servers/Server_5287940/File... · Foundation work is complete and the footprint has been graded
Text Box
CURRENT NEWS West Side Elementary: Excavation on the classroom
addition had started last week. Footing and foundation wall work is
on going and is scheduled to be completed next week. The steel
structure for the gym vestibule is to be erected later this week.
Roofing at the gym is scheduled for later this week into the
following week. Tibbets Elementary Steel work has been completed
for the gym addition. The precast panel bracing is to be removed
early this week in preparation to grade the gym to elevation. Roof
blocking and roofing are the next activities scheduled later this
week at the gym addition. The kindergarten addition's firewall has
been completed to be followed by steel scheduled for next week.
Jackson Elementary The crew has done a great job this past week
with installing the steel structure and roof deck. After the deck
is complete early this week, exterior framing will begin. High
School Addition Foundation work is complete and the footprint has
been graded to allow for the masons to begin placing CMU block for
the bearing walls. The CMU is scheduled to be completed in the
middle of February. After the bearing walls are completed the steel
structure will be erected.