Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
Cardiff School of Management
MSc Project Management
Management of Mega and Complex Projects
MPM7007
Exemplar Report ONLY
NOT to be copied, reused, recycled, adapted, cited, referred to under any circumstances – THIS IS STRICTLY NOT ALLOWED
UNIVERSITY’S ACADEMIC REGULATIONS APPLIES ON UNFAIR PRACTICE – PLAGIARISM & YOU HAVE REMINDED OF THIS
1
ORIGINALITY TAKES YOU A LONG WAY & PLAGIARISM KILLS YOUR CAREER – YOU HAVE BEEN REMINDED OF THIS ON
MANY & MANY OCCASIONS INCLUDING DURING LECTURES & SEMINARS
Introduction
With the African continent withholding global natural gas reserves of 7% (Akpata, White and
Bredenhann, 2013 PWC), and the country experiencing economic weaknesses combined with a
virtually complete absence of natural gas networks along with an internally limited gas
consumption, it highlights the substantial exporting capabilities of the continent (Augé, 2010).
The Trans-Saharan Gas Pipeline project (TSGP) has been amongst discussion for a number of
years, with Augé suggesting the project has been discussed since early 2000. The mega-project
is to be the construction of a natural gas pipeline that will connect Africa to Europe through a
pipeline estimated at 4,400 km in length, which will run through Nigeria, Niger and Algeria
connecting to Spain, for European distribution and trade. The project appears to be cost
competitive, as alternative gas transportation methods have been considered, for instance the
comparison of transportation through Liquefied Natural Gas (LNG) which gas wastage through
this method is estimated between 15%-18% amid the process of liquefaction (Mayaki, 2015).
The cost of the overall mega-project is estimated between $10billion and $13.7billion, with
remaining uncertainties regarding the size of the pipeline yet to be finalized. The TSGP project’s
objectives can be seen in greater detail within appendix 1.0, however it is clear to see that the
2
project objectives are closely aligned with African development agencies such as NEPAD and
Africa Power Vision. It can be stated without question that the TSGP mega project will
compromise of a vast and complex business environment interlinked with a variety of powerful
and influential individuals, associations and congress’s. The extensive depth to this mega-
projects macro, meso and micro environment are to prove to be largely complex to manage
effectively, therefore this mega-project will require close micro monitoring within all
departments and throughout each stage of the project.
Figure 1.0 – Trans Saharan Gas Pipeline Overview Source – Sweet Crude Reports, 2014
3
With a number of mega projects being too complex and over ambitious, combined with
long-term execution these projects may be opposed by new technology, public policy and new
legislation (Flyvbjerg and Budzier, 2011). Given the extent of this mega project, traditional
project management practices will not suffice towards the successful completion of this mega-
project, however effective programme management can support in the attempt of a lucrative
outcome. By entering programme management into this mega-project, the organization can
have tighter controls on micro managing individual, smaller projects within the mega-project.
Along with the support of programme managers and leading project manager, the collective
team effort can aid in the prospect of a satisfying delivery.
Complexities surrounding this Mega-project
The complexities surrounding this mega-project are magnified through the collaboration of a
number of key stakeholder organizations primarily the countries involved. Aspects within this
mega-project become largely complex considering the size, time-frame and logistics. The
uncertainties surrounding this mega-project are widely derived from the associated
complexities as the complex nature intensifies the uncertainties within this mega-project. The
high level of complexities and uncertainties within this mega-project could be the reasoning
behind the delayed execution and ultimately make this mega-project extremely difficult to
manage and execute successfully. It is likely that the mega-project will encounter a range of
known and unknown complexities along the way given the extended time scale, these may
come in the form of political and financial complexities as well as complex stakeholder groups.
Key Challenges of the TSGP project
4
Amidst the lengthy time scale and size associated with mega-projects such as the TSGP project,
the mega-project is likely to be confronted by a number of challenges throughout its life span. A
certain challenge faced by the project would be the financing issue, as such a large endeavour
requires a vast amount of funding for it’s successful completion, the TSGP project is estimated
to cost between $10 and $13.7billion, with implementing authorities such as Nigerian National
Petroleum Corporation (NNPC), Sonatrach, Nigeria’s International Committee of Red Cross
(ICRC) and the Economic Community of West African States (ECOWAS) playing a pivotal role.
Within The Energy Information Administration’s (EIA) 2016 report on the analysis of Nigeria’s oil
and gas sector, it states the attributing factors towards the delay of the TSGP project
commencement, affirming that increasing costs, security pipeline concerns, and continuing
political and regulatory uncertainties within Nigeria are collaborating components to the
postponement of this mega-project (Energy Mix Report, 2016). Similarly the Keystone XL
pipeline project, a crude oil gas pipeline which is estimated to transport 83,000 barrels of oil per
day from Canada to American refineries (Artba.org, 2017), has been largely delayed for a
number of years after several permit application refusals by the Presidential Permit and The
State Department whom hold jurisdiction of the approval of this project as it will cross the
United States border (Parfomak et al, 2013).
Complex Business, Organizational and Commercial Environment
The Trans-Saharan Gas Pipeline project will inevitably be either directly or indirectly affected by
the complex environments, in which the project will operate within. The sheer mass of the
5
project and the diversity of the macro, meso and micro environments, surrounding this mega-
project are to prove to be extremely complex given the enormity and depth of all aspects
involved. The successful management of such mega-project will require a highly scrutinized
approach and structured micro monitoring throughout. With complexity being “an inherent and
indispensable part of mega projects” (Kardes et al, 2013), it highlights the multiplicity of a vast
number of contributing factors towards the complex management of mega-projects (Hutter,
2009). With Zidane, johansen and Ekambaram (2012), suggesting that the complexities and
uncertainties are amplified within mega-projects due to their vast size and extended duration.
To begin to understand such a heavily complex and interdisciplinary mega-project, it would
require an in-depth environment assessment. There are a number of approaches to tackle this
tedious task, with Kardes et al (2013) suggesting a categorization of social and technical
complexity to enhance the understanding and improve the management of these complexities.
However, given the enormity of the TSGP project, this approach may appear basic for mega-
projects and could prove to fail in the identification and understanding of the minutiae aspects
involved. Which leads to the suggestions of further segregation and a highly scrutinized
assessment. The TSGP environments can be better managed and understood by assessing the
macro, meso and micro environments, as can be seen from figure 1.1.
6
With this in mind, the figure 1.1 model was used in correspondence with a SWOT and PEST
analysis as can be seen within appendix 1.1 and 1.2. The discovery of the aspects from the
SWOT and PEST analysis can be further segregated into categories within each macro, meso
and micro environment. This will assist in the improvements of a structured approach to
managing these aspects. The TSGP project will inherently experience organizational
complexities, given the vast stakeholders involved, “the intricate interrelationships of elements
within a complex system” (Kauffman et al, 2003), such as the TSGP project which, will
incorporate multiple layers of dependencies. The organizational complexities involved will
affect and influence the approaches taken in the successful management of the mega-project.
It must be considered, whether the parties involved have the capabilities to coordinate and
work collaboratively towards a lucrative outcome. The organizational complexities with the
parties involved may prove to be difficult, as the key stakeholders are from differing countries
and cultures, and each will possess their personal objectives and motives for the mega-project.
The organizational complexities correspond with the structural complexities of the mega-
project, with the structural complexities considering the actual work of the entire project, and
for this mega-project the structural complexities are to be vast given the number of elements
involved. The TSGP project will indefinitely experience a vast number of emergent complexities,
for examples the uncertainties regarding the size of the pipeline, if the decision was made to
construct a wider diameter pipeline, it would conclusively result in higher construction and
Figure 1.1 – Macro, Meso and Micro environment consideration aspects Source – Adapted from Foresight Cards, n.d
7
resource costs for the mega-project. Further more, the late identification of stakeholders,
which may have been missed during the concept phase of the mega-project, would also be
considered as an emergent complexity. These emergent complexities can be overcome through
the detailed and scrutinized upfront planning of the TSGP mega project, during the concept
phase. However, these complexities are given the term emergent, as they are possible to
emerge throughout the extended time frame of a mega-project, and these complexities would
then need to be managed successfully and sent through a strong and structured governance
process, to ensure maximum successful management.
The TSGP project will undoubtedly experience socio-political complexities throughout its
duration, as governing bodies are behind the project it is likely to encounter a range of political
disturbances as well as lacking in transparency, the occurrence of hidden agendas, and as
previously mentioned the differing and conflicting priorities of the parties involved, which may
also incorporate resistance (Harrin, 2014). The commercial complexities of the TSGP project,
are evident with an extensive budget set for the mega-project, contributing to the commercial
complexities of this mega project is the uncertainties regarding the pipeline diameter, as this is
likely to increase costs from $10billion to $13.7billion. However, the budget is appointed on the
basis and the calculations of the project manager within the concept and planning phase of the
TSGP project, with this in mind, if the project/program manager is unsuccessful in the accurate
cost, resource and planning of the overall mega-project, then this will undeniably increase the
commercial complexities.
The legalities complexities of the TSGP project are to be extremely difficult, given the variety of
the collaborative countries, organizations, cultures and individuals involved. The conflicting
priorities again will cause difficulties in ensuring appropriate contractual agreements are put in
place to accommodate to the differing priorities of the parties involved.
The effective execution of the TSGP project will most definitely encounter a range of
complexities within different areas, the implementation of an effective program management
approach will be required for the successful execution of this mega-project. Although, this is
merely not deficient to ensure the successful execution and delivery, the TSGP project will
8
require an extensive level of maturity to champion this endeavor. The Project Management
Maturity Model (PMMM) within figure 1.2, illustrates the maturity process of projects, claiming
in order for a project to reach maximum maturity it must reach level five of continuous
improvement. The TSGP project can be argued to be lacking in maturity, as the inexperience of
performing the mammoth task can halt and create difficulties throughout the project. Although,
it is expected that the collaborative expertise of the TSGP project team will be experienced
within this industry and the project can be benchmarked against similar oil and gas pipeline
projects such as the Ruby pipeline, the Trans-Mediterranean pipeline and the Keystone XL
pipeline. However, going beyond maturity to reach excellence, cannot be achieved without
reaching maximum maturity to achieve excellence Kerzner (2013) argues.
Figure 1.2 – Project Management Maturity Model (PMMM) Source – Project Management, Harold Kerzner, 2013
9
Stakeholders Complexities
The TSGP project will inevitably experience stakeholder complexities, due to the enormity of
the mega-project and the vastly geographically dispersed stakeholders involved. The figure 1.3
below, illustrates merely a few key stakeholders for the TSGP project, with the mega-project
being so large in scale and having the influence to impact upon diverse stakeholder groups, the
identification of such stakeholders is a difficult task within itself. The core stakeholders involved
are primarily the acting bodies working collaboratively to achieve the common goal of the
entire mega-project. With the direct stakeholders working directly with the core stakeholders
to achieve the end goal, but perhaps with differing priorities and objectives of the mega-
project. The indirect stakeholders will be affected by the mega-project, its activities and the
deliverables of the mega-project.
10
The vast degree of stakeholders and their influence on the mega-project will be very complex to
manage, and assessing these complex priorities of stakeholders, must be better understood and
managed through a priorities assessment. This will assist in identifying the differing levels of
complexities associated per stakeholder organization or individual, by understanding the exact
priorities to ensure these priorities are met and managed accordingly. This will also coincide
with the degree of stakeholder influence and impact upon the mega-project. The degree of
stakeholder involvement and impact can be better categorized and quantified through
analyzing each stakeholder against an influence and interest grid, this will assist in the
determination of the stakeholders and support in the process of managing these stakeholders
and the process of creating a communication plan.
There will be profound complexities regarding the National Oil Company (NOC), the
international Oil Company (IOC) and the private service companies, these will come in the form
of challenges associated with undertaking a joint venture for the mega-project, or whether it is
decided no joint venture is needed. Although Business Day (2017), claim that the project will be
a Public Private Partnership (PPP) venture, whilst using the Build-Transfer-Operate (BTO)
approach. Also NEPAD’s national coordinator Gloria Akobundu states, that the ICRC, NEPAD and
NNPC will set up a joint committee in the hopes of fast tracking the commencement and
execution of the mega-project and similar African projects to speed up the economic and
infrastructural developments within Africa. The implementation of the mega-project was signed
on a Memorandum of Understanding (MoU) in 2002, between NNPC, Algerian National Oil and
Sonatrach, and in 2009 Nigeria, Niger and Algeria signed a MoU to agree and to develop the
mega-project (Construction Intelligence, 2017).
It is likely that the mega-project will encounter a range of difficulties with conflicting countries,
there may be issues regarding planning permission and cross border issues between the three
countries; Nigeria, Algeria and Niger as well as subsequently Europe. It brings about questions,
whether the countries can collaborate successfully economically, socially and culturally to
facilitate the endeavor. It arises suspicion whether consideration has been given to other routes
that the pipeline could be constructed through, consideration may have been given to identify
what countries could work best together and the weighing up of options to possibly construct
11
an under water pipeline diverting and eliminating other African countries by creating an under
water pipeline from Nigeria around the African coast to Spain. Although, this suggestion is likely
to create further complexities in terms of technical and operational complexities, as well as a
large increase in cost and the possible requirement for further expertise within this field.
The TSGP will indefinitely face competition complexities as gas providers globally compete for
European market custom. There is strong competition from OPEC, Russia and Middle Eastern
countries such as Saudi Arabia, Qatar and Kuwait. These Middle Eastern competitors will
benefit and have lower operational and extraction costs, meaning they are able to produce,
supply and distribute their resources to the European countries at a lower cost, consequently
lowering the demand for African supply and possibly impacting upon the TSGP project activities
and demand. However, this isn’t to say the TSGP project should not commence due to
competition, the African countries need not be leading providers for Europe, but this
competition can be regarded as healthy competition.
Augé (2010) suggests that European dependence on Russia gas supply is likely to increase vastly
in absence of a change in energy policy, with Russia already accounting for 25% of gas supply
for Europe. According to the Russian Energy Minister, the European Union will become
dependent on Russian gas supply of 70% by 2050. Whilst the European Union, are attempting
to diversify their gas supply to alleviate the dependence on Russia. Conversely, Russia’s
Gazprom, whom withhold “the world’s largest natural gas reserves and account for 11% and
66% of the global and national gas output” (Gazprom, 2017), have made significant attempts to
restrict the diversification of the European gas supply, by signing a MoU the NNPC to cooperate
with future oil and gas project within Nigeria (IHS Markit, 2008). This projects the Russian
governments power and influence globally, whilst the country can manipulate substantial
influence regardless of the country’s stagnating oil and gas supply (IHS Markit, 2008).
12
Social Conflict Theory and Conceptual Model of Mega Projects
It can be accepted through the vast stakeholder dynamics of mega-projects alike the TSGP
project, that the project will encounter social conflict amongst stakeholder members. Jia et al
(2011) claims globalization is accountable for the increase in social conflict and that mega
projects motivate social conflict, possibly due to their large influence and impact. Jia et al
(2011) also claims that, “the interaction between a mega project and social conflict influences
politics, economics, environment regulate and other aspects of society”. Figure 1.3 is a
conceptual model of mega projects from a perspective of social conflict theory, created by Jia et
al (2011) in the attempts to increase understanding of the correlation amongst mega projects
and social conflict theory, and how these issues can be addressed.
Figure 1.3 – Conceptual Model of Mega Projects from a Social Conflict Perspective Source – A Study of Mega Project fro a Perspective of Social Conflict Theory, 2011
13
Optimum Bias
All too often within mega –projects there is a culture of over-commit, over-promise and under-
delivery, this continues to be a challenge for mega-projects, and may be an occurrence of the
TSGP project. The under or over estimation of aspects within mega-projects, may be because
the individual making these false statements feel that the project cannot progress on the real
facts, that maybe the project may be rejected if the true facts are stated. Especially within
mega-projects, as everything is vastly enlarged, it can create a sense of distrust and concern for
the successful outcome of the mega-project, it may make individuals and collaborative
organizations relinquish from the mega-project as on paper the mega-project may not at first
instance appear feasible. The key stakeholders of the TSGP project will each be in an attempt to
obtain the best deal and stance from the mega-project, this is likely to occur through the false
or manipulative perspectives of the parties involved. It is difficult to overcome such task, as it is
strenuous to ensure parties are genuine in their statements and actions. Optimum bias and the
misrepresentation in planning can be overcome by adopting the Reference Class Forecasting,
developed by psychologist Daniel Kahneman which, resulted in the winning of the Nobel prize
in economics in 2002. Kahneman and Tversky’s work uncovered the term “the planning fallacy”
which, alike previously mentioned describes the decision making below “underestimated costs,
completion times, and risks of planned actions, whereas they overestimate the benefits of the
same action” (Flyvbjerg, 2007). This method is used to achieve accurate projections on similar
or previous ventures and can prove beneficial and credible for a mega-project alike the TSGP.
Procurement Method
The TSGP project will require a strategically thought out procurement method, to ensure the
effective contractual agreements are input and the appropriate contractual partners are agreed
upon for further commencement of the mega-project. The TSGP project is likely to outsource a
number of resources such as materials, employee expertise and construction tools, this will
require the advertisement and negotiation methods. The mega-project will more than likely
require negotiation amongst suppliers through a bargaining process, the variety of
procurement methods such as open tendering, request for information (RFI), invitation for bids
14
(IFB) and request for quotation (RFQ), are just a few of the procurement methods the TSGP
could adopt. However, it can be suggested that the Two Stage Tendering or Restricted
Tendering may be most beneficial for the TSGP project, as the mega-project will be restricted
on quality suppliers, materials and expertise. Whilst the Two Stage Tendering is usually
associated with projects, which are not restricted by the time limit in securing project contracts
(Sponaugle, 2014), and as, we can understand the lengthy time frame and delay in the TSGP
project there appears leeway and flexibility within the commencement and execution, allowing
for the most effective contractual agreements to be made. The TSGP project will also be in a
position to achieve economies of scale, as they will for example require a large number of the
same materials to construct the pipeline.
Benefit and Value
It may be evident that the initial value and benefit of the TSGP project is unclear at first
instance, given the depth and degree of the entire mega-project along with the profound costly
budget and lengthy time frame. Similarly as previously mentioned within the optimum bias
section, a culture of unclear, over-stated and vague benefit and value of mega projects alike the
TSGP is often stated. On the other hand, the value and benefit can be appreciated from a
consumer perspective, as the TSGP aspires to supply northern African countries, as well as the
European benefit of diversifying their gas suppliers. The value and benefit of the TSGP project
from an organizational perspective may not be evident until way beyond project closure, as
return on investment is lengthy given the overall cost, and this value and benefit can be
transitioned to stakeholders as project benefits tend to materialize over time, for instance the
possibility of an increase in Nigerian GDP as a result of the mega-project. Additionally, figure 1.4
represents where the United Kingdom obtains their gas supply from, with British production
decreasing it highlights the future demand for differing sources of providers. Clearly, expressing
the future benefit and value sought by obtaining Nigeria, Niger and Algerian gas supply and
contractual partnership. The benefits and value of the TSGP project go beyond the supply of
gas, but the value and benefit can be interpreted and achieved through further methods such
15
as realization of enhanced and developed relationships, which in turn can generate further
endeavors between the countries involved.
Complexities in Phase by Phase Management
The life cycle of the TSGP project will undoubtedly be lengthy in its time frame, given the
degree of the mega-project itself. The mega-project life cycle can be seen in figure 1.5, and
although the project appears to be in between phase two and three, there remains
uncertainties as to the development of the project due to the source which the life cycle
Figure 1.4 – British Gas Supply Source – British Gas, 2017
16
diagram was obtained and adapted from, it is likely that the project is in a different phase of
execution as the source is likely to be outdated. With this being said, the mega-project is far
behind schedule, with the attributions of security concerns over the pipeline, ongoing
regulatory and political uncertainty in Nigeria and increasing costs, contributing to the delay of
the mega project (Energy Mix Report, 2016). The life cycle diagram can be seen within greater
detail within appendix 1.3. The culture of mega-projects and their interdisciplinary nature
makes them more complex to manage as the reliance on aspects of the work-breakdown
structure completion is required to progress onto further stages of the project life cycle and
work breakdown structure.
Figure 1.5 – Trans-Saharan Gas Pipeline Project Life Cycle Source - http://addisababa.mfa.ir/uploads/Nigeria_-_Algeria_Pipeline_19959.pdf, n.d
17
Supply Chain Management
Figure 1.6, illustrates the gas supply chain for the TSGP project, having identified the upstream,
midstream and downstream aspects of the supply chain. It is believed the upstream
stakeholders and partners will be responsible for the gas exploration and extraction, this is
believed to be the responsibility of NNPC, Sonatrach and Sonidep, as they are experienced and
operate within the oil and gas industry. The midstream stakeholders for this mega-project are
likely to again be NNPC, Sonatrach and Sonidep. With uncertainties regarding who is
responsible for the distribution of the gas refineries once it has arrived at its destination, it is
possible the downstream stakeholders and partners may be the European Union as well as the
Northern African countries.
As can be seen from figure 1.7, the leverage, strategic, non-critical and bottleneck suppliers
have been identified. The TSGP project will require some degree of outsourcing from materials
and resource providers to execute the pipeline. The project will require a distribution channel
to serve the large and varied market customers in terms of personal, industrial and
Figure 1.6 – Trans-Saharan Gas Pipeline Supply Chain Source – Authors own work
18
organizational. The project will need to ensure the appropriate and trustworthy suppliers are
chosen to maximize the likelihood of a successful project outcome, suppliers must ensure
delivery is on time, failure to do so will result in the contractual breach of terms of condition
and may ultimately result in fines and a poor reputation.
Risk
Management
The strategic risk management of mega projects is a critical element towards the successful
management of mega-projects. Risk management appears to be an underdeveloped area
within the mega-project management literature (Irimia-Diéguez, Sanchez-Cazorla and Alfalla-
Luque, 2014), and this area requires further research, development and effective approaches to
manage the risks and uncertainties that are likely to creep up throughout the extended time
frame of a mega-project. In the context of mega-projects, “there are high levels of complexity
Figure 1.7 – The Kraljic Portfolio Purchasing Model, Supplier Identification Source – Purchasing Must Become Supply Management, Peter Kraljic, 1983
19
along various dimensions” (Remington and Pollack, 2007, cited in Sanderson, 2011), which
supports the requirement for an advanced approach to dealing with the complex risks and
uncertainties of a mega-project. Within appendix 1.4, a risk identification register has been
created listing merely a few of the masses of risks and uncertainties associated with such a
large mega-project.
The mega-project will indefinitely encounter a range of complex risks and uncertainties, such
as, the actions of the Movement for the Emancipation of the Niger Delta (MEND), they have
previously vandalized an oil pipeline within the River State in 2009 (African Intelligence, 2010),
and have “explicitly threatened to strike out at the TSGP” (Augè, 2010). There are also high risks
in terms of funding, as the mega-project is a combination of public and private funding, as well
as a the competitor threat from Russia, Middle Eastern countries and non conventional energy.
The pipeline security threat is also a substantial risk, which has as previously mentioned,
contributed to the delay in commencement of the project. Further more, there is political
violence, serious human rights challenges as well as the violence and insecurity persisting
following the capture of the militant group Boko Haram (Human Rights Watch, 2016).
The TSGP project can enhance their mega-project risk management through the categorization
of risks, in an attempt to improve understanding and the overall management and approaches
used to tackle the risks posed. Flyvbjerg & Rottengatter (2003) differentiate between four
categories of risks; cost risk, financial market risk, political risk and demand risk. This can be
argued to be a basic and underdeveloped approach to managing the risks and uncertainties of a
mega-project, as not all risks and uncertainties will fit into these categories appropriately. This
approach in itself can fail in the identification of risks and is merely not a strong and structured
enough approach to managing the risks of mega-projects alike the TSGP requires. However,
Ward and Chapman (2003), propose a broader perspective is required for mega-project
management and the management of uncertainty over risks is needed. This approach must be
more efficient in the identification and management of mega-project risk, as they develop and
emerge continually throughout the extended life time of a mega-project. The proposal of a tight
repeated micro monitoring approach to the risk and uncertainty management of the TSGP
mega project is given.
20
A decision tree has been created and analyzed within appendix 1.5, to illustrate and discuss the
uncertainties surrounding the pipeline diameter and recommendations for the overall decision.
Governance
The increasingly popular theme of governance within project management, reflects a broader
perspective and focus diverting away from the historically focused technical and operational
tasks of projects (Sanderson, 2012). The high level of governance is needed within mega-
projects alike the TSGP to ensure appropriate decision making and procedures are carried out
in the best interest and beliefs of the organization. To enable maximum success, governance is
needed at executive level to allow it to flourish throughout the entire mega-project (Rayner and
Reiss, 2013). A strong governance structure is needed to ensure project transparency and
accountability, as the TSGP project may battle against corruption and experience complexities
in the decision-making control mechanism. The failure to adopt and appoint a strong
governance structure into the TSGP project will transpire to lack on control of the overall
project, therefore its criticality and implementation is essential for the successful delivery of
this mega-project.
Cost and Time Management
The management of cost and time for the TSGP is essential, as the project has already been
experiencing huge delays with its commencement. The weighing up of cost efficient decision
has more than likely been conducted already, for example the method of transportation has
been considered to be most cost efficient, rather than to transport the gas by lorry or train as
this method is proposed to be more dangerous (Westenhaus, 2013). It has also been suggested
that 75% of the entire gas which is transported globally is done so by pipelines (Deshpande and
Economides, 2005), which highlights the cost efficiency within this method. Figure 1.8
illustrates the alternative option for natural gas development, which more than likely has been
considered by the TSGP project board. There may be further improvements with capital and
time efficiency, through the adoption of methods such as Just-In-Time (JIT) and Kaizen. It could
also be suggested, to assess alternative options for pipeline and construction materials to
21
ensure maximum efficiency of the mega-project. Capital efficiency may be further achieved
through lean management, which is discussed in more depth within appendix 1.6.
Figure 1.8 – Natural Gas Transport and Development Alternatives Source – Natural Gas utilization in Nigeria: Challenges and Opportunities, 2010
22
Conclusion
In conclusion, we can accept that the TSGP project is a vastly complex mega-project with a
number of risks and uncertainties surrounding it. The mega-project will be a complex task to
undertake successfully, in terms of cost, time, budget and deeper complexities such as security,
human rights challenges, technical complexities and conflicting priorities from a number of
stakeholders. Although, the project faces competition from a number of sources such as Russia
and non-conventional energy, it should not deter the mega-project from commencing, as profit
and benefit of the overall mega-project can be understood as the value and benefit materialize
over time. The mega-project can champion this venture through learning from previous project
like the trans-med gas project, as well as benefitting from a vast degree of expertise within the
industry. The mega-project will require tight monitoring and control throughout all aspect to
ensure the effective risk and uncertainty management, as well as the overall successful delivery
of the mega-project. This report has attempted to cover the main aspects of which the Trans-
Saharan gas pipeline project will encounter, by also giving suggestions where appropriate to
recommend approach and improvements for the successful delivery of the mega-project. The
gaps within analysis of this report have been discussed within appendix 1.6.
Word Count - 5021
23
Appendices
1.0 Trans-Saharan Gas Pipeline project objectivesSource – Africa Power Vision Concept Note & Implementation, from Vision to Action, NEPAD
Project ObjectivesDiversification of export route for marketing Nigerian natural gas
Creation of wealth by opening up economic growth opportunities in the sub-regionBoosting the GDP and improving the living standards of the people within the sub-region
Boosting domestic gas supply within the regionAssisting in the fight against desertification through sustainable and reliable gas supply
24
1.1 Trans-Saharan Gas Pipeline project SWOT analysis Source – Authors own work along with NEPAD
25
1.2 Trans-Saharan Gas Pipeline project PEST Analysis Source – Authors own work
26
1.3 TSGP project Life Cycle Source – Adapted from http://addisababa.mfa.ir/uploads/Nigeria_-_Algeria_Pipeline_19959.pdf
27
1.4 Trans-Saharan gas Pipeline Project Risk Identification
28
1.5 Trans-Saharan Gas Pipeline Project Decision Tree to analyze the uncertainties regarding pipeline diameterSource – Authors own work, figures adapted from The Trans-Saharan Gas Pipeline: An Illusion or a Real Prospect, Benjamin Augé, 2010
This decision tree was created to illustrate and analyze the uncertainties surrounding the
decision to create a 48inch diameter pipeline at a cost of $10billion, which would allow for the
exportation of 20billion cubic meters of gas per annum, with an expected internal rate of return
of 15.5%. The second option is to create a wider 56inch diameter pipeline, at a higher cost of
$13.7billion, which would allow for the exportation of 30billion cubic meters of gas, with an
expected internal rate of return of 25%. Although a more costly venture, the 56inch diameter
pipeline will have the capability to export and transport a higher volume of gas which in turn,
will generate a higher rate of return on the project. It appears the most sensible decision to
make, as following the return on investment, there will be a higher profit margin for future
years to come. Therefore, the suggestion concluding on a decision to create a wider 56inch
diameter pipeline is proposed, which supports cost efficiency, the sustainability and output of
the overall mega-project.Supporting this decision Nguyen and Douglad-Westwood (2013), claim
that “the trend toward the increased adoption of natural gas in the global energy mix is driving
the increase in pipe diameter”.
29
1.6 Gaps in Analysis
Change & Agile Management
Effective change management will be required to facilitate the vast changes that are likely to
occur throughout the extended time frame of the TSGP project. The adopting and creation of
an agile organization can support in the resistance to change, and assist in overcoming of
obstacles along the way towards a successful project outcome. The less resistant to change an
organization is, the sooner the project and organization are able to progress and adapt
accordingly to the changes when they occur. It is personally believed that, an organization,
which practices effective change management and is an agile organization, conquers in the
journey towards maximum project maturity. Which as previously mentioned, is required to
reach maximum success and is seen as a stepping stone towards project excellence.
Lean Management
Closely corresponding with the above, and continuous improvement is lean management, the
requirement for the adoption of lean management is to systematically achieve incremental
changes to further champion and improve the overall efficiency and quality of the project. The
TSGP will require the adoption of lean management to maximize their efficiency within all areas
of the mega-project not limited to cost and time, but efficiency saving can be achieved within
all areas. The aim is to reach maximum efficiency within project management to ensure
excellence is achieved through the mega-projects activities and operations.
Project Management Office
The TSGP will require a strong project management office to manage, facilitate and support the
project and program managers within their activities. The project management office can
support with the overall governance, and it will enhance the organization and management of
30
the overall mega-project, given it vast size. Along with the governance structure, the PMO will
work collaboratively to ensure the mega-project maintains the highest possible standard and
quality of its operations. This can be seen as a risk mitigation procedure as it ensures best
practices and seeks for further efficiency and tighter controls on monitoring, which is what this
mega project requires.
Sustainability
The overall project may appear sustainable for the future supply to the European Union,
diversifying the EU gas suppliers. However, it brings about question on how sustainable the
resource of gas reserves are, it is unknown the amount of gas reserves which are left in the
world, which is worrying, and further supports alternative solution such as non conventional
energy. The mega-project can achieve further sustainability through, delivering more with less
this being closely aligned with efficiency as previously mentioned.
Lessons Learnt
The TSGP project can learn from similar venture undertaken previously such as, the Trans-
Mediterranean Natural Gas Pipeline constructed in 1983, it’s use is to transport natural gas
from Algeria to Italy via Tunisia and Sicily. This mega-project is very similar to the TSGP, as the
project would have encountered similar complexities, uncertainties and risks, such as, the
conflicting priorities of a vast number of individuals, organizations, countries and governments
involved. Although there is a vast difference in project years, the TSGP project may be able to
complete the workload faster given advanced technologies and expertise. The TSGP can learn
from such projects and how they were able to overcome certain obstacles, and possibly
implement methods and approaches to champion these drawbacks.
31
Suggestion
It can be suggested for TSGP project to successfully manage and operate their activities
effectively, that the incorporation of program management is used, with program managers
being responsible for each program, and further a risk officer can be appointed for each
program, to work closely with the program manager to ensure the effective risk and uncertainty
management is done throughout the mega-project. As a high level of micro monitoring will be
required to ensure the successful management and delivery of the overall mega-project is
achieved.
32
References
Africa Power Vision Concept Note & Implementation plan - from Vision to Action. (2015). NEPAD Transforming Africa.
Alex Vines, S. (2017). Africa's oil and gas potential: Boom or hype?. [online] CNN. Available at: http://edition.cnn.com/2014/09/18/business/africa-oil-gas-potential-boom-hype/ [Accessed 24 Apr. 2017].
Artba.org. (2017). Long-Delayed Keystone XL Pipeline Project Granted Construction Permit | ARTBA Newsline. [online] Available at: http://www.artba.org/newsline/2017/03/24/long-delayed-keystone-xl-pipeline-project-granted-construction-permit/ [Accessed 25 Apr. 2017].
Benjamin Augè (2010). The Trans-Saharan Gas Pipeline: An Illusion of a Real Prospect?.
Britishgas.co.uk. (2017). Where does UK gas come from?. [online] Available at: https://www.britishgas.co.uk/the-source/our-world-of-energy/energys-grand-journey/where-does-uk-gas-come-from [Accessed 6 Jun. 2017].
BusinessDay : News you can trust. (2017). ICRC partners NEPAD on Trans-Saharan Gas Pipeline project - BusinessDay : News you can trust. [online] Available at: https://www.businessdayonline.com/icrc-partners-nepad-trans-saharan-gas-pipeline-project/ [Accessed 5 Jun. 2017].
Construction Intelligence Center. (2017). NNPC- Trans-Saharan Gas Pipeline. [online] Available at: https://www.construction-ic.com/HomePage/Projects?returnUrl=%2FProjects%2FOverview%2F103994 [Accessed 5 Jun. 2017].
Deshpande, A. and Economides, M. (2005). An Alternative Transport for Natural Gas Instead of LNG. University of Houston.
Energy News | Oil and Gas News - Energy Mix Report. (2017). Trans Saharan Gas Pipeline project stalled on costs, insecurity. [online] Available at: http://energymixreport.com/trans-saharan-gas-pipeline-project-stalled-on-costs-insecurity/ [Accessed 25 Apr. 2017].
Finland Futures Research Centre (FFRC) (2003). Organisational Complexity. [online] Finland. Available at: https://www.utu.fi/fi/yksikot/ffrc/julkaisut/tutu-julkaisut/Documents/Tutu_2003-6.pdf [Accessed 4 May 2017].
Flyvbjerg, B. (2007). Curbing Optimism Bias and Strategic Misrepresentation in Planning: Reference Class Forecasting in Practice. European Planning Studies, 16(1), pp.3-21.
Flyvbjerg, B. and Rothengatter, W. (2003). Megaprojects and Risk. An Anatomy of Ambition. Anthropologica, 46(1), p.99.
33
Foresight Cards. (n.d.). Macro, Meso and Micro environment. [online] Available at: https://foresightcards.com/background-information/macro-meso-and-micro-environment/ [Accessed 3 May 2017].
Gazprom.com. (2017). About Gazprom. [online] Available at: http://www.gazprom.com/about/ [Accessed 5 Jun. 2017].
Harrin, E. (2014). 3 Types of Complexity. [online] Projectmanagement.com. Available at: https://www.projectmanagement.com/blog-post/7405/3-Types-of-Complexity?blogName=The-Money-Files&posting=7405 [Accessed 31 May 2017].
Human Rights Watch. (2016). Nigeria - Events of 2015. [online] Available at: https://www.hrw.org/world-report/2016/country-chapters/nigeria [Accessed 6 Jun. 2017].
Ihs.com. (2008). Europe and Russia Compete over Trans-Sahara Pipeline as Nigeria Considers its Gas Options. [online] Available at: https://www.ihs.com/country-industry-forecasting.html?ID=106596343 [Accessed 5 Jun. 2017].
Irimia-Dieguez, A., Sanchez-Cazorla, A. and Alfalla-Luque, R. (2014). Risk Management in Megaprojects. Social and Behavioral Sciences, pp.407-416.
Jia, G., Yang, F., Wang, G., Hong, B. and You, R. (2011). A Study of Mega Project from a Perspective of Social Conflict Theory. International Journal of Project Management, [online] 29(7), pp.817-827. Available at: http://www.sciencedirect.com.ezproxy.cardiffmet.ac.uk/science/article/pii/S0263786311000524 [Accessed 5 Jun. 2017].
Kerzner, H. (2013). Project management. 11th ed. Hoboken: Wiley.
Kraljic, P. (1983). Purchasing Must Become Supply Management. [online] Harvard Business Review. Available at: https://hbr.org/1983/09/purchasing-must-become-supply-management [Accessed 5 Jun. 2017].
Nguyen, T. and Douglas-Westwood, A. (2013). World Demand for Onshore Pipeline Construction to Grow from 2013 to 2017. OGF, 2(3).
Nigeria- Algeria Pipeline. (n.d.). 1st ed. [ebook] Available at: http://addisababa.mfa.ir/uploads/Nigeria_-_Algeria_Pipeline_19959.pdf [Accessed 5 Jun. 2017].
Odumugbo, C. (2010). Natural Gas Utilisation in Nigeria: Challenges and Opportunities. Journal of Natural Gas Sciences and Engineering, 2, pp.310-316.
Ofgem.gov.uk. (2017). EU legislation. [online] Available at: https://www.ofgem.gov.uk/gas/wholesale-market/european-market/eu-legislation [Accessed 1 Jun. 2017].
34
PricewaterhouseCoopers (2013). From promise to performance, Africa oil & gas review. [online] Available at: http://file:///H:/My%20Documents/Downloads/pwc-africa-oil-and-gas-review.pdf [Accessed 24 Apr. 2017].
Rayner, P. and Reiss, G. (2012). Portfolio and Programme Management Demystified : Managing Multiple Projects Successfully (2nd Edition). 1st ed. Taylor and Francis.
Remington, K., Pollack, J., 2007. Tools for Complex Projects. Gower, Aldershot.
Sanderson, J. (2012). Risk, uncertainty and governance in megaprojects: A critical discussion of alternative explanations. International Journal of Project Management, 30(4), pp.432-443.
Sponaugle, B. (2014). Six Procurement Methods: Obtaining Quality Goods and Services. [online] Blog.udemy.com. Available at: https://blog.udemy.com/procurement-methods/ [Accessed 5 Jun. 2017].
SweetCrudeReports. (2014). Nigeria mobilises $700m for Trans-Sahara gas project. [online] Available at: http://sweetcrudereports.com/2014/01/29/nigeria-mobilises-700m-for-trans-sahara-gas-project/ [Accessed 1 May 2017].
Ward, S. and Chapman, C. (2003). Transforming project risk management into project uncertainty management. International Journal of Project Management, 21(2), pp.97-105.
Westenhaus, B. (2013). Trucks, Trains, or Pipelines – The Best Way to Transport Petroleum | OilPrice.com. [online] OilPrice.com. Available at: http://oilprice.com/Energy/Energy-General/Trucks-Trains-or-Pipelines-The-Best-Way-to-Transport-Petroleum.html [Accessed 6 Jun. 2017].
35
36