Delay Event and complete Narrative Report
Event No. : 1, Dated 25-Mar-12.
Reference to Employer instructions received via Letter, ref. Letter 1 dated 25-Mar-12 regarding: Local Authorities Permission.
And our letter ref.1 dated 28-Mar-12 regarding the same subject, attached below the time impact analysis for this Event:
A- Event Justification
This event will delay the project because ,these instructions from the client to hold excavation is after the planned date of Excavation.
B- Existing Scope of work due to Event
Existing Activity Name
Activity Id
Estimated
Duration
Predecessor Id
Predecessor Name
Relationship type
Lag
Authorities Permissions
Letter 1 - 1 20 Letter 1
Local Authorities Permission
FS 0
C- Impacted activities of baseline schedule
Existing Activity Name
Activity Id
Planned Duratio
nPredecess
or IdPredecesso
r NameRelationshi
p type Lag
Excavation Activity SUBz100020 6 Letter 1 -
1Authorities Permissions
FS 0
D- Impact of the Original Schedule After the study of the event impact, and as per attached influence schedule No.(Schedule (1)) , This event delayed the project (0) days as per screenshot below.
Event Screenshot
Delay Event Narrative Report
Event No. : 2 , Dated 20-Mar-12.
Reference to Employer instructions received via Letter , ref. Letter 2 dated 20-Mar-12 regarding : Site Handing Over.
And our letter ref.2 dated 20-Mar-12 regarding the same subject, attached below the time impact analysis for this Event :
E- Event Justification
Reference to the approved project time schedule ,this event will delay the project start from (10-March 2012) to (20-March 2012)
F- Existing Scope of work due to Event
Existing Activity Name
Activity Id
Estimated
Duration
Predecessor Id
Predecessor Name
Relationship type
Lag
Site Delivery Delay Letter 2 - 1 10 Letter 2
Site Handing
Over
FS 0
G- Impacted activities of baseline schedule
Existing Activity Name
Activity Id
Planned Duratio
nPredecess
or IdPredecesso
r NameRelationshi
p type Lag
Mobilization SUBZ100010 25 Letter 2 -
1Site
Delivery Delay
FS 0
H- Impact of the Original Schedule After the study of the event impact, and as per attached influence schedule No.(Schedule (2)) , This event delayed the project (17) days as per screenshot below.
Event Screenshot
Delay Event Narrative Report
Event No. : 3 , Dated 15-Apr-12.
Reference to Consultant instructions received via Material Submittal , ref. Mar-20 dated 15-Apr-12 regarding : Changing Pumps specs by client.
And our letter ref.3 dated 15-Apr-12 regarding the same subject, attached below the time impact analysis for this Event :
I- Event Justification
This event will delay the project because it will take several months to procure these pumps as they will be imported.
J- Existing Scope of work due to Event
Existing Activity Name
Activity Id
Estimated
Duration
Predecessor Id
Predecessor Name
Relationship type
Lag
New Pumps Submittal
MAR-20-1 5 Mar-20
Changing Pumps
specs by client
FS 0
New Pumps Approval MAR-20-2 3 MAR-20-1 New Pumps
SubmittalFS 0
New Pumps Procurement
MAR-20-3 180 MAR-20-2 New Pumps
ApprovalFS 0
K- Impacted activities of baseline schedule
Existing Activity Name
Activity Id
Planned Duratio
nPredecess
or IdPredecesso
r NameRelationshi
p type Lag
INSTALLATION OF WATER & FIRE
PUMPS
0801MW001
117 MAR-20-2
New Pumps Procureme
nt
FS 0
MAR-20-3 180 MAR-20-2
L- Impact of the Original Schedule
After the study of the event impact, and as per attached influence schedule No.(Schedule (3)) , This event delayed the project (0) days as per screenshot below.
Event Screenshot
Delay Event Narrative Report
Event No. : 4 , Dated 12-May-12.
Reference to Consultant instructions received via Material Submittal , ref. Mar-04 dated 12-May-12 regarding : Late Response Lighting Fixture.
And our letter ref.4 dated 15-May-12 regarding the same subject, attached below the time impact analysis for this Event :
M- Event Justification
Reference to the approved project time schedule this event will delay the project , because the consultant late response with 27 delays days .Response date (12-May 2012) instead of (15-Apr-2012) this will delay the whole process of procurement and executing of these fixtures.
N- Existing Scope of work due to Event
Existing Activity Name
Activity Id
Estimated
Duration
Predecessor Id
Predecessor Name
Relationship type
Lag
Delay of MAR response
MAR 4-1 20 Mar-04
Late Response Lighting Fixture
FS 0
O- Impacted activities of baseline schedule
Existing Activity Name
Activity Id
Planned Duratio
nPredecess
or IdPredecesso
r NameRelationshi
p type Lag
LIGHTING FIXTURES& SWITCHS
ProcurementA2250 47 MAR-4-1
Consultant FS 0
P- Impact of the Original Schedule
After the study of the event impact, and as per attached influence schedule No.(Schedule (4)) , This event delayed the project (0) days as per screenshot below.
Event Screenshot
Delay Event Narrative Report
Event No. : 5 , Dated 01-Feb-13.
Reference to Employer instructions received via Minutes Of Meeting , ref. MOM 13 dated 01-Feb-13 regarding : Utilities availability.
And our letter ref.5 dated 05-Feb-13 regarding the same subject, attached below the time impact analysis for this Event :
Q- Event Justification
Reference to the approved project time schedule this event will delay the project , because any delay in Utilities availability will delay the "Testing & Commissioning" Work Package .Also Utilities availability was planned to start on (21-Mar-2013) not (1-July-2013).
R- Existing Scope of work due to Event
Existing Activity Name
Activity Id
Estimated
Duration
Predecessor Id
Predecessor Name
Relationship type
Lag
Delay of Utilities availability
MOM-13-1
Milestone MOM 13 Utilities
availabilityFS 0
S- Impacted activities of baseline schedule
Existing Activity Name
Activity Id
Planned Duratio
nPredecess
or IdPredecesso
r NameRelationshi
p type Lag
Elevators TESTING AND COMMISSIONING A2450 22 MOM-13-1
Delay of Utilities
availability
FS 0
Finishes Touch up & Commissioning
Site10090 14 MOM-13-1
Delay of Utilities
availability
FS 0
MECHANICAL TESTING AND
COMMISSIONING
Delay of Utilities
availability
FS 0
ELECTRICAL TESTING AND COMMISSIONING
SITE10110 26 MOM-13-1
Delay of Utilities
availability
FS 0
T- Impact of the Original Schedule
After the study of the event impact, and as per attached influence schedule No.(Schedule (5)) , This event delayed the project (71) days as per screenshot below.
Event Primavera Screenshot
Delay Event Narrative Report
Event No. : 6 , Dated 01-Sep-12.
Reference to Employer instructions received via Minutes Of Meeting , ref. MOM 9 dated 01-Sep-12 regarding : Safe Door Delivery.
And our letter ref.6 dated 01-Sep-12 regarding the same subject, attached below the time impact analysis for this Event :
U- Event Justification
Reference to the approved project time schedule this event will delay the project because , Safe Door has a Milestone with fixed date on the baseline schedule. The client delayed this date by (60) days
V- Existing Scope of work due to Event
Existing Activity Name
Activity Id
Estimated
Duration
Predecessor Id
Predecessor Name
Relationship type
Lag
Safe Door Supplying Delay
MOM 9-1 60 MOM 9 Safe Door
DeliveryFS 0
W- Impacted activities of baseline schedule
Existing Activity Name
Activity Id
Planned Duratio
nPredecess
or IdPredecesso
r NameRelationshi
p type Lag
Wall Preparation for Painting
Arch1070 21 MOM 9-1
Safe Door Supplying
Delay
FS 0
X- Impact of the Original Schedule After the study of the event impact, and as per attached influence schedule No.(Schedule (6)) , This event delayed the project (1) days as per screenshot below.
Event Primavera Screenshot
Delay Event Narrative Report
Event No. : 7 , Dated 29-Mar-12.
Reference to Consultant instructions received via Request For Information , ref. RFI 3 dated 29-Mar-12 regarding : Under Ground Water Level.
And our letter ref.7 dated 29-Mar-12 regarding the same subject, attached below the time impact analysis for this Event :
Y- Event Justification
The actual condition of the underground water differs from the contractual foundation report therefore the contractor has the right to claim for time and money.
Z- Existing Scope of work due to Event
Existing Activity Name
Activity Id
Estimated
Duration
Predecessor Id
Predecessor Name
Relationship type
Lag
Response from Consultant
RFI No.3-1 10 RFI 3 RFI No.3 SS 0
Dewatering RFI No.3-2 10 RFI No.3-1
Response from
Consultant
FS 0
Soil replacement RFI No.3-3 7 RFI No.3-2 Dewatering FS 0
AA- Impacted activities of baseline schedule
Existing Activity Name
Activity Id
Planned Duratio
nPredecess
or IdPredecesso
r NameRelationshi
p type Lag
COMPACTING WORKS UNDER THE P.C
LAYERSUBZ100030 3 RFI No.3-3
Soil replacemen
t
FS 0
RFI No.3-3 7 RFI No.3-2
BB- Impact of the Original Schedule
After the study of the event impact, and as per attached influence schedule No.(Schedule (7)) , This event delayed the project (0) days as per screenshot below.
Event Primavera Screenshot
Delay Event Narrative Report
Event No. : 8 , Dated 01-Feb-13.
Reference to Consultant instructions received via Request For Information , ref. RFI 6 dated 01-Feb-13 regarding : Clash between Lighting Unit and Diffuser.
And our letter ref.8 dated 05-Feb-13 regarding the same subject, attached below the time impact analysis for this Event :
CC- Event Justification
Reference to the approved project time schedule this event will delay the project because ,the contractor raised the problem before the activity planned start date, however, the consultant late reply (after 8 months) will cause rework for the contractor.
DD- Existing Scope of work due to Event
Existing Activity Name
Activity Id
Estimated
Duration
Predecessor Id
Predecessor Name
Relationship type
Lag
Remove Fixed Lighting Fixture
RFI-6-1 20 RFI 6 RFI-6 SS 0
Modify Cables and conducts
RFI-6-2 20 RFI-6-1
Remove Fixed
Lighting Fixture
FS 0
EE-Impacted activities of baseline schedule
Existing Activity Name
Activity Id
Planned Duratio
nPredecess
or IdPredecesso
r NameRelationshi
p type Lag
LIGHTING FIXTURES& SWITCHS & OUTLETS
0801EL0005 60 RFI-6-2
Modify Cables and conducts
FS 0
FF- Impact of the Original Schedule
After the study of the event impact, and as per attached influence schedule No.(Schedule (8)) , This event delayed the project (44) days as per screenshot below.
Event Primavera Screenshot
Delay Event Narrative Report
Event No. : 9 , Dated 29-Apr-12.
Reference to Consultant instructions received via Shop Drawing reviews , ref. SDF 2 dated 29-Apr-12 regarding : Doors and Windows Shop Drawing.
And our letter ref.9 dated 30-Apr-12 regarding the same subject, attached below the time impact analysis for this Event :
GG- Event Justification
changing the door from local to imported will take longer time to procure which give the right contractor to claim EOT.
HH- Existing Scope of work due to Event
Existing Activity Name
Activity Id
Estimated
Duration
Predecessor Id
Predecessor Name
Relationship type
Lag
New Door Submittal SDF 2-1 5 SDF 2 SDF 2 SS 0
New Door Approval SDF 2-2 3 SDF 2-1 New Door
SubmittalDoor Procurement SDF 2-
3 280 SDF 2-2 New Door Approval
II- Impacted activities of baseline schedule
Existing Activity Name
Activity Id
Planned Duratio
nPredecess
or IdPredecesso
r NameRelationshi
p type Lag
WOODEN DOORS INSTALLING
ARCH1150 14 SDF 2-3
Door Procureme
nt
FS 0
SDF 2-3 280 SDF 2-2
JJ- Impact of the Original Schedule After the study of the event impact, and as per attached influence schedule No.(Schedule (9)) , This event delayed the project (66) days as per screenshot below.
Event Primavera Screenshot
Delay Event Narrative Report
Event No. : 10 , Dated 20-Jan-13.
Reference to Employer instructions received via Site Work Instruction , ref. SWI 1 dated 20-Jan-13 regarding : Change Marble Fixation.
And our letter ref.10 dated 20-Jan-13 regarding the same subject, attached below the time impact analysis for this Event :
KK- Event Justification
Reference to the approved project time schedule this event will delay the project because ,the client instructed the contractor to change the installation method after starting the activity. This instruction will hold the work until submitting new method statement, procure the material and remove the fixed marble
LL- Existing Scope of work due to Event
Existing Activity Name
Activity Id
Estimated
Duration
Predecessor Id
Predecessor Name
Relationship type
Lag
Demolish all fixed marble
SWI1_1 3 SWI 1 SWI 1 SS 0
Submit New Method Statement for
mechanical FixationSWI 1_2 3 SWI1_1
Demolish all fixed marble
SS 0
Approved Method Statement For
Mechanical FixationSWI1_
3 3 SWI1_2
Submit New
Method Statement
for mechanical
Fixation
FS 0
Material Procurement order for new
materialSWI1_
4 7 SWI1_3
Approved Method
Statement For
Mechanical Fixation
FS 0
MM- Impacted activities of baseline schedule
Existing Activity Name
Activity Id
Planned Duratio
nPredecess
or IdPredecesso
r NameRelationshi
p type Lag
MARBLE WORKS VIP SEC. WALL'S CLADDING
&FLOORING
Arch1110 20 SWI1_4
Material Procurement order for
new material
FS 0
SWI1_3 3 SWI1_2
NN- Impact of the Original Schedule After the study of the event impact, and as per attached influence schedule No.(Schedule (10)) , This event delayed the project (26) days as per screenshot below.
Event Primavera Screenshot
Delay Event Narrative Report
Event No. : 11 , Dated 15-Mar-13.
Reference to Employer instructions received via Site Work Instruction , ref. SWI 2 dated 15-Mar-13 regarding : Change Painting Color Code.
And our letter ref.11 dated 19-Mar-13 regarding the same subject, attached below the time impact analysis for this Event :
OO- Event Justification
Reference to the approved project time schedule this event will delay the project because , the client requested to change the color code on "15-Mar-2013" and the contactor painting material procurement finish date "20-Oct-2012" , So the contactor has right to claim about the time needed for new material procurement.
PP-Existing Scope of work due to Event
Existing Activity Name
Activity Id
Estimated
Duration
Predecessor Id
Predecessor Name
Relationship type
Lag
Submit new material for approved
SWI 2_1 3 SWI 2 SWI 2 SS 0
Approved New Material
SWI 2_2 3 SWI 2_1
Submit new material for approved
SS 0
Material Procurement SWI2 _3 15 SWI 2_2
Approved New
Material
FS 0
QQ- Impacted activities of baseline schedule
Existing Activity Name
Activity Id
Planned Duratio
nPredecess
or IdPredecesso
r NameRelationshi
p type Lag
Painting Site delivery date A2290 15 SWI2 _3
Material Procureme
nt
FS 0
SWI2 _3 15 SWI 2_2
RR- Impact of the Original Schedule After the study of the event impact, and as per attached influence schedule No.(Schedule (11)) , This event delayed the project (266) days as per screenshot below.
Event Screenshot