Safe System of Work Activity: Pillar drill Description of work activity: Drilling various sized holes in timber/ plywood/O.S.B Assessment date: Assessor: Responsibilities Site Manager: Peter Scott Supervisor Ben Lowe Number of Ops: 6 Associated Hazards Hazards associated with activity: Serious injury by way of not using correct methods.

 · Web viewBy signing this form you confirm that you have read and understood the method statement outlined and associated risk assessments, and that you agree with the safe working

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1:  · Web viewBy signing this form you confirm that you have read and understood the method statement outlined and associated risk assessments, and that you agree with the safe working

Safe System of WorkActivity: Pillar drillDescription of work activity:

Drilling various sized holes in timber/ plywood/O.S.B

Assessment date:Assessor:

ResponsibilitiesSite Manager: Peter ScottSupervisor Ben LoweNumber of Ops: 6

Associated HazardsHazards associated with activity:

Serious injury by way of not using correct methods.

Site specific Hazards:

Busy work environment, movement of trolleys in factory, excessive noise & dust.

Page 2:  · Web viewBy signing this form you confirm that you have read and understood the method statement outlined and associated risk assessments, and that you agree with the safe working

Work Procedures & Control Measures

1. make sure you are wearing the appropriate PPE before going onTo the factory floor safety boots, safety glasses & hearing protection must be worn at all times.no baggy clothing or gloves are to be Worn whilst operating this machine

Page 3:  · Web viewBy signing this form you confirm that you have read and understood the method statement outlined and associated risk assessments, and that you agree with the safe working

2. make sure the working area is clean & tidy, & thatthere is no waste material on the floor

Page 4:  · Web viewBy signing this form you confirm that you have read and understood the method statement outlined and associated risk assessments, and that you agree with the safe working

3. check the condition of all the start stop buttons & makesure the guards are present & in good condition

4. make sure there is the correct size chuck key with the drill. When changing the drill make sure the drill is switched off before doing so.

Page 5:  · Web viewBy signing this form you confirm that you have read and understood the method statement outlined and associated risk assessments, and that you agree with the safe working

5. depending on what you are drilling always try to set Up the fence and use the stops located on the fence.Use G clamps to hold the fence to the drill bed these should be located on the table at the side of the pillar Drill. If you are drilling something small or oddly shapedDon’t try to drill to many at a time keep them as singlesAnd hold them down properly.

Page 6:  · Web viewBy signing this form you confirm that you have read and understood the method statement outlined and associated risk assessments, and that you agree with the safe working

6. Make sure you leave the working area clean & tidy Put all drill bits & chuck key back on the table or The magnetic holder.

Page 7:  · Web viewBy signing this form you confirm that you have read and understood the method statement outlined and associated risk assessments, and that you agree with the safe working

First Aid Provision:

Welfare Provision:

Schedule of PPE:

Page 8:  · Web viewBy signing this form you confirm that you have read and understood the method statement outlined and associated risk assessments, and that you agree with the safe working

Emergency Procedures:

Completed by: Phone:Signature: Date:

AcknowledgementBy signing this form you confirm that you have read and understood the method

statement outlined and associated risk assessments, and that you agree with the safe working procedures in place

Name Signature Date

Page 9:  · Web viewBy signing this form you confirm that you have read and understood the method statement outlined and associated risk assessments, and that you agree with the safe working