Weaverley Housing Coop Design Report.pdf

Embed Size (px)

Citation preview

  • 8/9/2019 Weaverley Housing Coop Design Report.pdf

    1/21

     

    WEAVERLEY HOUSING COOPERATIVE

    WEAVERLEY HOUSING COOPERATIVE

    INFRASTRUCTURE DESIGN PARAMETERS 

    FOR RESIDENTIAL DEVELOPMENT 

    D NDE CIVIL PROJECTS

    CONSULTING ENGINEERS

    Civil &Structural Engineering Consulting 

    P.O Box 6851HarareTel. 04-771484Cel. 0773 282 522

    FEBRUARY 2015

  • 8/9/2019 Weaverley Housing Coop Design Report.pdf

    2/21

    WEAVERLEY COOPERATIVE HOUSING 

    INFRASTRUCTURE DESIGN

    PARAMETERS FOR RESIDENTIAL DEVELOPMENT 

    CONTENTS LIST 

    Page

    1. INTRODUCTION 4 

    1.1 General 4

    1.2 Town Planning 5

    1.2.1 Town Planning Development 5

    1.2.2 Survey & S.G Co-ordinated Plans 5

    2. SITE DESCRIPTION 6 

    2.1 Location 6

    2.2 Topography 6

    2.3 Geology 6

    3. PARAMETERS OF DESIGN 7 

    3.1 Design References 7

    4. CIVIL ENGINEERING SERVICES : RETICULATION 8

    4.1 Local Roads 8

    4.1.1 General 8

    4.1.2 Road Cross Section 8

    4.1.3 Horizontal Alignment 9

    4.1.4 Vertical Alignment 104.2 Local Stormwater Control 11

  • 8/9/2019 Weaverley Housing Coop Design Report.pdf

    3/21

    4.2.1 General 11

    4.2.2 Design 11

    4.2.3 Materials 12

    4.2.4 Ancillary Stormwater Control 12

    4.2.5 Sub Surface Drainage 13

    4.3 Sewer Reticulation 13

    4.3.1 Sewer Reticulation 13

    4.3.2 Sewer Reticulation Design 13

    4.3.3 Computer Analysis 14

    4.3.4 Pipeline Layout and Gradients 15

    4.3.5 Material Specifications 15

    4.4 Water Reticulation 16

    4.4.1 Water Demand 16

    4.4.2 Water Reticulation Designs Development 16

    4.4.3 Design Parameters 16

    4.4.4 Computer Analysis 18

    4.4.5 Pipe Materials Specification 18

  • 8/9/2019 Weaverley Housing Coop Design Report.pdf

    4/21

    1. INTRODUCTION 

    1.1 General 

    Dande Civils was appointed by Waverley Cooperative for the design of their

    infrastructure services for 271 stands for residential purpose. This design report

    forms part of the Consultants’ appointment and covers the strategy for the

    planning, designing and construction of the of the infrastructure services.

    Weaverley cooperative intend to develop the site with the installation of Civil

    reticulation, for the 271 stands , with associated bulk and link infrastructure on

    behalf of Kadoma Municipality.

    The development principles to be adopted by the development team of Town

    Planners, Engineers and Architects is to develop a township with ‘green’ areas,

    adopt green engineering principles and appropriate engineering technologies

    as is practical.

    Engineering Reticulation Services will therefore be as follows; 

    Civil Engineering 

    - Kerbed and surfaced roads

    - Stormwater control primarily in the roads, then channelled to

    open channels as topography dictates

    - Waterborne sewerage reticulation

    - Individual metered water supply to each stand.

    - Fire protection for the development within the water reticulationnetwork.

  • 8/9/2019 Weaverley Housing Coop Design Report.pdf

    5/21

    1.2 Town Planning 

    1.2.1 Town Planning Development 

    The original Town Planning from the own plan developed by the

    Regional Office of the Department of Physical Planning was used. This

    town plan was the layout used for the initial civil design.

    1.2.2 Survey & S.G Coordinated Plans 

    Topographical Survey 

    Detail ‘on site’ topographical survey is required for detailed

    design of,

    •  Sewer reticulation

    •  Roads reticulation

    SG Coordinated Plans & Site Pegging 

    SG Plan 

    •  The SG coordination plan is dependent upon the Town Planning

    •  The coordinated Town Plan was received by Dande Civils for

    detail design in January 2015.

  • 8/9/2019 Weaverley Housing Coop Design Report.pdf

    6/21

    2. SITE DESCRIPTION 

    2.1. Location 

    The proposed housing development is located on portions of Subdivision A of

    Plot 3 of Railway Farm 9 situate in the district of Kadoma and is situated in

    Kadoma.

    2.2 Topography 

    The site generally slopes down towards stand number 3666

    2.3 Geology 

     Attached is a preliminary site assessment of the insitu soils – Appendix 1.

    Material is generally SG5-SG9 material with a few areas with SG3

  • 8/9/2019 Weaverley Housing Coop Design Report.pdf

    7/21

    3. PARAMETERS OF DESIGN 

    3.1 Design References 

    CIVIL

    ZIMBABWE

    Ministry of Local Government & Housing for Water, Sewerage, Road

    & S/W BCHOD : 1981

    - Design Approach to Water and Sewerage Problems Relative to Urban

    (predominantly High Density) and Rural Communities in

    Zimbabwe.

    SOUTH AFRICA

    - Guidelines for the provision of Engineering Services&

     Amenities in residential township Development – South Africa

    (Red Book)

  • 8/9/2019 Weaverley Housing Coop Design Report.pdf

    8/21

    4 CIVIL ENGINEERING SERVICES : RETICULATION 

    4.1. Local Roads 

    4.1.1 General 

    The road reticulation system within the Township is developed on the following

    principles :-

    - To provide all weather access to stands – Class 5a/5b

    - To provide linkage to the distribution roads by vehicle or bus – Class 4

    -  All Class 5 and Class 4 roads to be designed to transport Stormwater within

    the township and to avoid potential Stormwater damage to properties.

    Design speed on the roads is to be limited to 40 km/hr by the use of traffic calming

    measures mini traffic circles or speed bumps. However, and where possible, the design

    stopping / site distance is to be designed for a traffic speed of 60km to ensure additional

    safety within the local streets for pedestrian movement.

     Adjacent all local streets and the bus route, one side only , paved footways are to be

    installed providing all weather pedestrian movement facility.

    Roads geometric and pavement design has been undertaken with criteria from the

    Guidelines for the Provision of Engineering Services in Residential Township issued by the

    National Housing Board SA.

    4.1.2 Road Cross-Sections  

    Class 4 Road- Local bus route 

    18m Road Reserve 

    - Road carriageway offset to allow for Electrical HT Servitude

    - Carriageway 6m wide with 2½ % crossfall

    - Edging support of pre cast concrete mountable kerb on low side and pre cast

    concrete edging on high side

    - 900mm wide footway on low side (Acts with the road as an additional paved

    S/W channel in the event of substantial storm water discharge.

    - Road reserves to be compacted to grades to assist S/W control and stand

    access as detailed on the typical road section detail drawing.

    - Reserves to be top soiled and grass seeded to avoid erosion and

    provide a visually pleasing finish to the reserves.

    - Classification

  • 8/9/2019 Weaverley Housing Coop Design Report.pdf

    9/21

  • 8/9/2019 Weaverley Housing Coop Design Report.pdf

    10/21

    10 

      10m for class 5a to 4

      15m for class 4 to class 3

    4.1.4 Vertical Alignment 

    Road Gradient 

    Class 4 Max gradient 10% Class 5

    Max gradient 12%

    In certain short sections of roads these grades will need to be exceeded to ensure

    stormwater control and avoidance of erosion to reserves, as the dictates of the topography

    and design in minimizing cut/fill requirements.

    Vertical Curves 

    Class 4 : Verified curve length 40 m min

    2% change of grade – no curve required

    Class 5 : Vertical Curve Length 20 m min

    3% change of grade – no curve required

     Access junction between roads -an allowance of up to 5% change of grade with no

    vertical curve can be implemented as a valley between road crossfall and vertical

    alignment of the adjoining road ensuring minimum cut/fill and avoiding potential

    ponding of stormwater discharge from the road junction.

    Pavement Design 

    Road Class 4 : Category UB 0.05≥3 E80s : Class E1

    Road Class 5a/5b : Category UC/UD < 0.2 E80s : Class ER / EO

    Roads to be designed with allowance for const ruction traffic use. 

    General CBR Min 10 (3 < 7 in vlei areas)

    Roads to be granular material with pre mix surfacing

    Footways to be granular material with 60mmblock paving surfacing and

    cement stabilized base.

  • 8/9/2019 Weaverley Housing Coop Design Report.pdf

    11/21

    11 

    Bus bays to be 80mm block paving and cement stabilized base.

    Design will be based on the catalogue of designs in the Red Book Section 6

     Appendix 5 to suit the relevant road category and traffic E80 Class as

    designated above and to be based on granular bases in moderate to dry

    region Figure 5A.

    Note: For Class 5b roads E/O compaction of G5 material to obtain a CBR of >60 will be

    used for the road base material to limit the import of G4 / or crusher run base material.

    4.2 Local Storm-water Control  

    4.2.1 General 

     As noted in Section 4.1 the local residential access roads are to be utilized as far as

    possible to transmit localized Storm-water discharge to U/G pipe system or side

    drains.

    The pipe system, side drains or direct discharge from the roads via kerb chute outlets

    will transfer the storm-water discharge into the three existing drainage channels on the

    northern side of the development area of 271 stands.

    Local design storm intensity will be for 1:5 storm discharge with 1: 10 year storm

    surcharge onto the roads.

    The roads and road reserves will also act as the major S/W discharge conduit for

    storms up to 1:50 year intensity.

    4.2.2 Design 

    Storm-water discharge design will be based on the Rational formula : Q =

     AIC m³/sec360

    Intensity will vary to suit the time of concentration (Tc) based on :

    - the return storm intensity

    - Topography

    - Vegetations / Ground coverage

    - Paved areas

  • 8/9/2019 Weaverley Housing Coop Design Report.pdf

    12/21

    12 

    - Channelized Flow

    - Mean annual Rainfall of 900mm / annum

    4.2.3 Materials /Installation 

    - Inlets to U/G pipework will be via kerb inlets or gulley inlets with concrete inlet

    chambers and brick manhole chambers

    - Concrete inlet channels will be used to increase the capacity of the standard

    2m long Kerb inlets with end inlet to the KI to cater for the additional flow.

    - Concrete chute outlets (precast and insitu) will be used on kerbed roads to

    discharge to open drainage systems

    - Pipework will be precast concrete pipes with spigot and socket flexible joints

    equivalent to Class C pipework with Class B bedding – full granular surround andbedding factor 1.8.

    - Cover under roads to be 1m to soffit but with concrete surround, 750 mm to soffit

    will be acceptable provided a minimum of 450 mm cover to the pipe is available

    when the road pavement is being constructed.

    - Open drains will be designed to suit the required flows with concrete or stone lining

    to avoid erosion where required.

    - Manholes are to be brick manholes with full depth benching to ensure

    constant velocity transfer through the manholes. The shape of the manhole is

    dependent upon pipe sizing, number of inlets and turning requirements Covers to

    be cost iron, or cast iron frame with concrete infill in open areas.

    4.2.4 Ancillary Stormwater Contro l 

    To assist Stormwater discharge certain stands will be deemed Stormwater servitudes

    to assist the control of major Stormwater run-off and avoid damage to houses if theywere to be constructed in that location.

    These areas generally occur :

    -  At the bottom of steep roads when the flow ‘cannot’ change direction due to

    velocities or horizontal alignment requirements of the Town Planning Layout

    - Transfer of pipework or open drains to avoid bends and major direction

    changes

    -  Areas that will be damaged with flood discharge

    The open areas will generally be graded to form a central shallow V drain which may or

  • 8/9/2019 Weaverley Housing Coop Design Report.pdf

    13/21

    13 

    may not have the invert lined dependent upon stormwater discharge velocities.

    However, as drain lining can also act as paved walkways I is considered that lining of the

    invert should be undertaken

    4.2.5 Sub Surface Drainage 

    - Due to the topography and the type of soil ground water is not expected in

    many areas. However, areas where ground water may be encountered are :

    - Potential perched water tables at the intersection of the granite sills and

    granite ‘whale backs’

    In these areas single aggregate stone bedding will be used to ensure protection to

    underground pipework and open concrete lined drains and underground fin drains

    will be installed adjacent roads to protect the road pavement.

    4.3 Sewer Reticulation 

    4.3.1 Sewer Capacity 

    The Design Approach to Water and Sewerage Problems Relative to Urban

    (Predominantly High Density) and Rural Communities in Zimbabwe and Guidelines

    for the Provision of Engineering Services and Amenities in Townships Development-

    South Africa identify typical water consumption rates in urban centers as:

    Item  Description  Return to Sewer   Design Guideline 

    1 Medium Income 70% Water Demand +

    15% for S/W ingress.

    850liters/stand/day

    Zimbabwe Guidelines

    4.3.2 Sewer Reticulation Design  

    The designs developed for sewer reticulation are based on data containedabove. Designs have taken into account the following.

    - The proposed phasing of the development.

    - The availability of materials and cost

    - Contributing figures for sewage based upon water consumption figures

    - Projected population figures

    - Proposed types of housing units

    - Pumping Station requirements

    - Ease of maintenance

  • 8/9/2019 Weaverley Housing Coop Design Report.pdf

    14/21

    14 

    Sewerage reticulation is mid-block where the plan and terrain permits it. The

    sewer lines are located at 1.0 meter from the stand (plot) boundary.

    The minimum pipe size is 110 millimeters in diameter. (O/D UPVC)

    Sewage velocities have been designed to be high enough to transport solids,

    but not so high that scouring of pipes would occur. Minimum velocities for

    design have been achieved at the daily peak, which is not less than 0.6 m/s

    with pipe flow 0.5D.

    Peak flow factors have been limited to 5.25 x dry weather flow which is the

    requirement to meet the blue standard of reticulation design as per Zimbabwe

    regulations.

    Stand connections are to be Y-connections, capped and attached to markers

    to indicate their location. Each connection shall be located at the lower end of

    the stand. If convenient erf connection will be made directly to the sewer line

    M.H.

    The design for connections has been based on 1:60 fall from any point on the

    stand GL. +450mm (min) to give a minimum connection depth to the main

    161mm dia sewer line.

    Manholes have been located at a maximum spacing of 80m for 110mm

    diameter pipes and 90m for pipes of 225mm diameter and above. Manholes

    locations for larger diameter pipes have been designed to accommodate the

    maintenance equipment available to the maintaining authority.

    4.3.3 Computer Analysis  

    The sewer reticulation will be analyzed by Autocad CIVIL 3D software

    package that carries out the pipe line hydraulic calculations for design flow

    and maximum flow. The software out data is listed below:

    •  Longitudinal sections of sewer line annotated automatically with pipe

    specifications, diameter and bedding specifications.

    • Hydraulic information also placed automatically on longitudinal section.

    • Manholes are numbered and sorted in branch order.

    Pipes are numbered and sorted.• Manhole / pipe topology automatically determined

  • 8/9/2019 Weaverley Housing Coop Design Report.pdf

    15/21

    15 

    •  Pipe length calculated and totaled.

    •  Ground and invert levels determined at special chainages such as pipe or

    road crossings.

    •  Manhole invert

    •  Pipe grades

    •  Drop manholes

    •  Pipe earthworks excavation quantities for all branches in the network,

    pipeline layout and gradients

    4.3.4 Pipeline Layout and Gradients 

    The sewers are laid with a minimum cover of 750mm depth between stands and

    900mm Min cover elsewhere.

    Road crossing are to be 1.25m depth to soffit to allow for road construction to be

    undertaken without damage to any installed sewers.

    Diameter (mm)  Gradients 

    Maximum  Minimum 

    160 1:10 1:120

    200 1:16 1:150

    250 1:24 1:200

    315 1:30 1:300

    400 1:40 1:350

    675 1:70 1:600

    Note : 1 in 80 is the minimum grade at the start of a sewer run

    4.3.5 Material Specification  

    The pipeline material to be used is uPVC pipes sewer class 34 with flexible spigot

    and socket joints for all sewer reticulation. Pipework above ground on pipe bridge

    sections will be Mild Steel coated and painted as specified with Viking Johnson

    Coupling Joints to allow for expansion.

    Manholes are to be pre-cast concrete rings 1m dia unless noted on the drawings.

  • 8/9/2019 Weaverley Housing Coop Design Report.pdf

    16/21

    16 

    4.4 Water Reticulation 

    4.4.1 Water Demand 

    Item  Description  Water Demand  Design Guideline 

    1 Medium Income 1000liters/stand/day South African

    Guidelines

    2 Schools - Day 20liters/ pupil/day Zimbabwe Guidelines

    3 Shops 20 liters / Employee Zimbabwe Guidelines

    4 Bars 300 liters / Stand Zimbabwe Guidelines

    5 Offices 20 liters / Employee Zimbabwe Guidelines

    6 Dry services industry 10 000 -15 000 liters

    /Ha

    Zimbabwe Guidelines

    4.4.2 Water Reticulation Designs Developed 

    The designs developed for water reticulation are based on data contained in

    the above documentation.

    Designs have taken into account the following :-

    Phase 1 

    - 271 Units + associated infrastructure

    - Balanced reticulation with the 271 reticulation of units for

    Phase 1 inclusive of supply line from reservoirs

    - Peak flows @ 1.8 to 3 peak hourly factors

    -  Average Flow + Fire Flow from 1no. Hydrant to be used for final pipe

    sizing.

    4.4.3 Design Parameters  

    Item  Description  Design Guideline 

    1 Water Demand per stand 400m2 stand.

    Medium density – 1000liters per day

    South Africa Guidelines

    2 Peak hourly factor 3 Zimbabwe Guidelines

    3 Minimum Residual pressures at supply points 15m to

    20m

    Maximum Static pressure 60m

    Zimbabwe Guidelines

  • 8/9/2019 Weaverley Housing Coop Design Report.pdf

    17/21

    17 

    4 Design Velocity between 0.5m/s to 2m/s Zimbabwe Guidelines

    5 Cover over pipelines

    Stand connection 450mm

    In gardens 750mm

    Under roads 1250mm

    Zimbabwe Guidelines

    6 Fire Flow

    Low Risk area. One hydrant to Discharge at any one

    time.

    Hydrants at 240m coverage / spacing

    Flow Rate 15liters per second.

    Flow Time 1 hour.

    Minimum Diameter of reticulation with Fire main

    75mm diameter.

     Adjacent to Institutional centers - additional Fire

    Hydrant

    South Africa Guidelines

    Zimbabwe Guidelines

    7 Institu tional Demand 

    Schools – Boarding 80 liters / Boarding pupil

    Schools - Day 20 liters /Day pupil

    Hospitals-200 - 400 liters /Bed

    Primary Healthcare Centre- 10 liters /Out patient

    Hotels 300 – 500 liters /Bed

    Hostels/Rest Camps 200 - 300 liters/ Bed

    Commerce or Administration

    Shops 20 liters / Employee

    Bars 300 liters / Stand

    Zimbabwe Guidelines

    Zimbabwe Guidelines

  • 8/9/2019 Weaverley Housing Coop Design Report.pdf

    18/21

    18 

    Offices 20 liters / Employee

    Industry 

    These will vary considerably according

    to processes used.

    Dry services industry 10 000 -15 000 liters /Ha

    Wet Industrial to be individually

    assessed.

    Zimbabwe Guidelines

    8 Peak Demand Zoned Areas 

    Between min 1.8 max 3.5

    SA Guidelines

    4.4.4 Computer Analysis  

    The water reticulation system is analyzed by Epanet software package

    that carries out a static analysis and a time simulation of the network.

    The software out data is listed below:

    Hydraulic results for each water pipe include:

    • Diameter Chosen (mm)

    Flow (l/s)• Velocity (m/s)

    • Calculated Darcy friction factor

    • Calculated equivalent Hazen Williams friction factor

    • Friction loss in meters per 100 meters

    Hydraulic results for each node include:

    • Energy level (m)

    • Pressure (m)

    4.4.5 Pipe Materials Specifications 

    The pipeline material will be

    •  uPVC pipes Class 9 with spigot and socket joints for all water reticulation

    pipelines

  • 8/9/2019 Weaverley Housing Coop Design Report.pdf

    19/21

    19 

    •  HDPE Type 4 pipes with compression fittings for stand connections.

    •  Joints connections for tees and valve connections to be CI with

    spigot and socket joints. Alternative flange joints to be used where

    directed specifically on valve connections

    •  Valves to be CI to water works quality to SABS 665 , with

    connections to suit uPVC pipework.

    •  Bends to be

    uPVC pressure bends up to 450 .with spigot and socket joints 

    450 / 900 bends or where noted on the pipework schedule to be CI with

     joints to suit spigot and socket uPVC pipework..

    •   All bends, tees etc required thrust block as specified on the drawings.

  • 8/9/2019 Weaverley Housing Coop Design Report.pdf

    20/21

     

    TITLE : WEAVERLEY COOPERATIVE HOUSING DEVELOPMENT

    Project Team : Dande Civils

    Client : Weaverley Cooperative

    Client Project No : ………..

    Status of Report : Final

    Morad Report No : 1

    Date of this Issue : 10 February 2015

    For Dande Civils issuing

    Written & by

    Compiled

    M.Benhura (Bsc) Civil

    Hons

    Initials & Surname Signature Date

    Peer – reviewed

    byM Kaendeza (Pr.Eng)

    Initials & Surname Signature Date

  • 8/9/2019 Weaverley Housing Coop Design Report.pdf

    21/21

     APPENDIX 1: INSITU SOILS