Weather Sensitive ERS Training

Presenter: Carl Raish

Weather Sensitive ERS Training Workshop

April 5, 2013

Page 2: Weather Sensitive ERS Training Presenter: Carl Raish Weather Sensitive ERS Training Workshop April 5, 2013

Weather Sensitive ERS Pilot Description

4/5/2013 Weather Sensitive ERS Training2

Pilot purpose: Evaluate the ability of weather-sensitive Loads to provide dispatchable

demand response during summer system conditions; Evaluate the accuracy of Qualified Scheduling Entity (QSE) projections of

demand response capabilities and Load growth; Evaluate deployment impacts on end-use customers (survey); Identify any unforeseen challenges in procuring, deploying and evaluating

the performance of weather-sensitive Loads.

ERCOT will procure a maximum of 30 MW for BH2, BH3 & WEHPilot duration June – September 2013

Page 3: Weather Sensitive ERS Training Presenter: Carl Raish Weather Sensitive ERS Training Workshop April 5, 2013

4/5/2013 Weather Sensitive ERS Training3

Weather Sensitive ERS Pilot Participation

• ERIDS and Offers must be submitted by a QSE qualified to participate in ERS

• Fully executed Weather-Sensitive ERS Pilot Project Supplement to Market Participant Agreement is required

• Minimum offer is 100 kW … subject to proration as limited by Tied Offer MW

• Offers must include projection of the maximum number of sites during Contract Period

• Interval metering is required

• 9 months of historical interval data (when ERID form is submitted) is required for all sites in Loads using default baseline

• No historical data required for control group, but all sites must have interval metering prior to start of Contract Period

• QSE may offer the same capacity into WS ERS, 10M ERS or 30M ERS

• WS ERS will be awarded first

• Capacity may be offered / awarded into 10M ERS or 30M ERS in other time periods.

• If Load participates in WS ERS and another ERS program, no site changes are allowed during the Contract Period

Page 4: Weather Sensitive ERS Training Presenter: Carl Raish Weather Sensitive ERS Training Workshop April 5, 2013

4/5/2013 Weather Sensitive ERS Training4

Weather Sensitive ERS Pilot Participation

• Loads only (no ERS Generators) and Loads must be residential-only or non-residential only

• Load must demonstrate weather sensitivity by meeting minimum accuracy standards posted at the following link:

http://www.ercot.com/mktrules/pilots/wsers/index

•Accuracy is evaluated for specified time periods using Regression Baseline

R2 > 90% and MAPE < 7.5%, orR2 > 95% and MAPE < 10.0%

• Residential Loads on Control Group Baseline are exempt from this requirement … but must have interval metering at start of Contract Period

Page 5: Weather Sensitive ERS Training Presenter: Carl Raish Weather Sensitive ERS Training Workshop April 5, 2013

4/5/2013 Weather Sensitive ERS Training5

Weather Sensitive ERS Pilot Participation

Minimum Accuracy Standards for WS ERS

Resources Meeting Accuarcy Standards for Last Three Contract ERID Processes

Resources

Submitted1Qualify as WS Percent

Feb/May 1185 151 12.7%Oct/Jan 820 106 12.9%Jun/Sep 507 95 18.7%Total 2512 352 14.0%

1Resources Requesting Default Baseline Analysis with Suffi cient Historical Data

Page 6: Weather Sensitive ERS Training Presenter: Carl Raish Weather Sensitive ERS Training Workshop April 5, 2013

4/5/2013 Weather Sensitive ERS Training6

Weather Sensitive ERS Pilot Participation

• Residential WS ERS Loads have two baseline options

• Regression baseline … same as current methodology

• Control Group baseline

• at least 600 sites assigned randomly by ERCOT to control groups

• 2 – 20 groups available

MAPE p90_kw_int_diff p95_kw_int_diff p99_kw_int_diff rsquare

Regression 3.80 0.197 0.255 0.429 94.342

Control 300 2.55 0.110 0.144 0.205 98.554

Per Customer Increase 0.087 0.112 0.224

Sites 1,000 -239.2 -221.8 -143.52,000 -152.3 -110.0 80.03,000 -65.4 1.7 303.54,000 21.5 113.5 527.05,000 108.4 225.3 750.5

10,000 325.4 561.7 1623.415,000 488.1 842.5 2435.1

Page 7: Weather Sensitive ERS Training Presenter: Carl Raish Weather Sensitive ERS Training Workshop April 5, 2013

4/5/2013 Weather Sensitive ERS Training7

Weather Sensitive ERS Pilot Participation

• Non-residential WS ERS Loads have same baseline options as current ERS

• Regression baseline will always be available (since it’s part of qualification)

• ERCOT will also evaluate M810 and MDP and if sufficiently accurate, will be available for QSE selection

• Control group option not available for non-residential Loads

Page 8: Weather Sensitive ERS Training Presenter: Carl Raish Weather Sensitive ERS Training Workshop April 5, 2013

4/5/2013 Weather Sensitive ERS Training8

Modification of Load Population

QSE may update list of sites once per month

• Submit updated offer form prior to 1st of month … can add/remove sites

• Sites added must meet same historical interval data requirement as original sites

• Updated Load must meet minimum accuracy standards and baseline qualifications set by the original Load

• Sites added to Control Group Baseline Load may result in recalculation of number of control groups and control group assignments

• If number of sites falls below 600, Load will revert to default baseline

• Offers should take into consideration that 1 control group will be withheld from EEA event deployments

• Number of sites may increase from original, but not more than the greater of

• 100% of the original number

• (2 MW * max sites specified on offer) / MW capacity of offer

(Effectively number of sites that would be expected to provide 2 MW)

Page 9: Weather Sensitive ERS Training Presenter: Carl Raish Weather Sensitive ERS Training Workshop April 5, 2013

4/5/2013 Weather Sensitive ERS Training9

Group Assignments for Default Baseline Loads

ERCOT may, with QSE approval, split default baseline loads into two deployment groups

• Only one of the two groups will be deployed during a test, tests would alternate between groups

• ERCOT will evaluate if testing one group would provide an accurate estimate of the performance of the entire group

• Initial analysis indicates residential aggregations of 300 kW are likely to qualify

• If sufficiently accurate, ERCOT will randomly assign sites to one of the two groups and notify QSE

• Otherwise, all sites will be assigned to the same group

• If QSE modifies sites in the Load

• Group assignments would be subject to change

• Use of two groups could be disallowed if insufficiently accurate

• Test performance factor will be based on prorated capacity when two groups are in use

Page 10: Weather Sensitive ERS Training Presenter: Carl Raish Weather Sensitive ERS Training Workshop April 5, 2013

4/5/2013 Weather Sensitive ERS Training10

Events and Tests

ERCOT will administer at least one and not more than two tests per month

• Tests will be fleet-wide deployments for the pilot

• Number of tests may be reduced by actual deployment events

• 30-minute ramp

• Tests will typically be long enough to include one full interval

• two of the tests may last for at least one hour

• test duration will not be announced prior to test

ERCOT may deploy Loads up to 8 times for actual EEA deployments

• Subject to deployment in EEA 1 or higher

• Deployment instruction will specifically mention WS ERS

• ERCOT will pre-notify QSE on Control Groups to be with-held from deployment

• 30-minute ramp

• Three-hour time limit on a deployment for an event

Page 11: Weather Sensitive ERS Training Presenter: Carl Raish Weather Sensitive ERS Training Workshop April 5, 2013

4/5/2013 Weather Sensitive ERS Training11

Event / Test Performance

Load-level Interval performance factors calculated same as regular ERS

• (baseline – actual) / (int_frac * obligation) … but not capped at one

• Obligation is directly from offer (or 0.5 * offer if 2 deployment groups used)

• Demand reduction value (baseline – actual) normalized for normal peak weather is used for weighting interval performance factors

• Timeliness of deployment at Load level is assessed for tests/events with two or more full intervals

• If EIPF for first full interval is less than 75% of average EIPF for remaining intervals, a financial penalty is imposed (baseline lowered to reduce event performance factor by 25%)

QSE-level Interval performance factors

• Normalized DR Value and obligations summed across deployed Loads

• Weighted average interval fraction (by DR Value) across deployed Loads

• (DR Value) / (int_frac * obligation)

Page 12: Weather Sensitive ERS Training Presenter: Carl Raish Weather Sensitive ERS Training Workshop April 5, 2013

4/5/2013 Weather Sensitive ERS Training12

Event / Test Performance

Event performance factors (QSE and Load)

• Weighted average of interval performance factors for the event

• Weighted by normalized DR Value and interval fraction

QSE Contract Period Event performance Factor

• Weighted average of interval performance factors for all tests and events during Contract Period

• Weighted by QSE-level normalized DR Value and interval fraction

Page 13: Weather Sensitive ERS Training Presenter: Carl Raish Weather Sensitive ERS Training Workshop April 5, 2013

4/5/2013 Weather Sensitive ERS Training13

Performance Penalties

Financial Performance Penalties will be imposed (no suspensions) for the following:

• If maximum number of sites for a Load during Contract Period is less than 90% of number projected on the offer

• If average normalized DR Value per site for a Load is less than 90% of (Offer MW / projected maximum sites)

• If one of the above conditions is true the baseline is reduced to result in the Load’s event performance factor to be equal to the square of the original event performance factor

• If both of the above conditions are true the baseline is reduced to result in the Load’s event performance factor to be equal to the cube of the original event performance factor

• However, the penalties are waived if:

• The DR Value provided by the Load is greater than or equal to 90% of the offered MW, or

• The ERS Load’s obligation is exhausted during the Contract Period

Page 14: Weather Sensitive ERS Training Presenter: Carl Raish Weather Sensitive ERS Training Workshop April 5, 2013

ERS Submission Form Changes

4/5/2013 Weather Sensitive ERS Training14

QSE Name

QSE DUNs Number

Company submitting form (if different than QSE)

Submittal Type

QSE Authorized Representative

Printed Name:

Signature:

Title: Phone Number: Cell Phone Number: E-mail Address: QSE Primary Contact 1Printed Name: Title: Phone Number: Cell Phone Number: E-mail Address:

Qualified Scheduling Entity (QSE) InformationThis portion of the ID page must be filled out.

Submittal Type Options:• Preliminary Review• Procurement ERID• 10M Procurement Offer• 30M Procurement Offer • WS Procurement Offer• 10M Reinstatement ERID• 10M Reinstatement Offer• 30M Reinstatement Offer• 10M Substitution • 30M Substitution• WS Site Update

Page 15: Weather Sensitive ERS Training Presenter: Carl Raish Weather Sensitive ERS Training Workshop April 5, 2013

ERS Submission Form Changes

4/5/2013 Weather Sensitive ERS Training15

Hours for 10 Minute ERS & 30 Minute ERS Pilot

Business Hours 1 (BH1) are the Hours Ending 0900 through 1300, Monday thru Friday, except ERCOT holidays.

Business Hours 2 (BH2) are the Hours Ending 1400 through 1600, Monday thru Friday, except ERCOT holidays.

Business Hours 3 (BH3) are the Hours Ending 1700 through 2000, Monday thru Friday, except ERCOT holidays.

Non-Business Hours (NBH) are all other hours.

Hours for Weather Sensitive ERS Pilot

Business Hours 2 (BH2) are the Hours Ending 1400 through 1600, Monday thru Friday, except ERCOT holidays.

Business Hours 3 (BH3) are the Hours Ending 1700 through 2000, Monday thru Friday, except ERCOT holidays.

WeekEnd Holidays (WEH) are the Hours Ending 1400-2000, Saturday, Sundays & Holidays

New tab added, Contract Hours

Page 16: Weather Sensitive ERS Training Presenter: Carl Raish Weather Sensitive ERS Training Workshop April 5, 2013

ERS Submission Form Changes

4/5/2013 Weather Sensitive ERS Training16

Several changes to this section of the ERS Submission Form:

1.Cell B2 – added Weather Sensitive Load as an option

2.Cell C2 – Projected # of Sites for Weather Sensitive ERS

3.Baseline – WS Control Group added as an option

4.ERS Time Period – WeekEnd Holidays added for Weather Sensitive

1 2

3 4

Page 17: Weather Sensitive ERS Training Presenter: Carl Raish Weather Sensitive ERS Training Workshop April 5, 2013

Major Program Differences

4/5/2013 Weather Sensitive ERS Training17

Program Characteristics 

10 Minute ERS 30 Minute ERS Weather Sensitive ERS

Status Production Pilot Pilot

Ramp Rate 10 Minutes 30 Minutes 30 Minutes

How Paid Paid As Bid Clearing Price Clearing Price

Deployed EEA Level 2 or higher EEA Level 1 or higher EEA Level 1 or higher

Deployments Durations

8 hours max per CP, remain deployed until recall

Max 8 cum hours, up to 4 events

Max 3 hours per event,up to 8 events

ERS Generators Yes No No 

Opt-In Renewal Yes No No

Self Provision Yes Yes No

Number of TestsMust have passed a test in the

last 365 daysAt least 1, max of 4 per

Contract PeriodAt least 1, max of 2 per

month (event offset)

Testing / EventEvent – XML & All QSE Hotline

Test - XML & call on OPXXML & All QSE Hotline

CallXML & All QSE Hotline Call

No XML during WEH 

Suspensions Availability & Load Test Failures No Suspensions No Suspensions

*Suspended Resources can offer in WS ERS / ERS 30 without serving suspension but must successfully complete the reinstatement process.

Page 18: Weather Sensitive ERS Training Presenter: Carl Raish Weather Sensitive ERS Training Workshop April 5, 2013

Questions

4/5/2013 Weather Sensitive ERS Training18