Upload
yemin
View
212
Download
0
Embed Size (px)
DESCRIPTION
Weather Data
Citation preview
Section 6 – Employer’s Requirements : Part A-Scope of Work 6A-7
Bidding Document for CEAIP – Part 3- Job B Procurement of Plant Single-Stage: Two-Envelope
(d) E’K line should be connected to the proposed Ambathale – Ethulkotte express line
through new SF6 load break switch (remote operated) at K.
(e) Install a new surge arrester set at new Gothatuwa town (E’) and connect KE’ 33kV
line to UG cable line coming from primary substation which is constructed by LECO.
1.2 CLIMATE
The climatic data given are for the standard period for 1961-1990. This data has
to be up dated with the latest available data.
The climate is that of a tropical region and the following meteorological
information is set out for guidance only.
(A) AIR TEMPERATURES
Records are available for the monthly mean daily maximum and minimum
temperatures with offset from average. The averages are taken for the standard
period 30 years and all shown in Table 1.2.1.
Table 1.2.1 – Mean Daily Maximum and Minimum Temperature
Ratmalana Colombo Katunayaka
January Max 29.0 31.1 32.1
Min 22.8 21.7 21.6
February Max 29.9 31.2 32.5 Min 23.0 22.2 21.9
March Max 30.6 31.8 32.7
Min 23.9 23.2 23.1
April Max 30.6 32 32.4
Min 24.8 24.1 24.1
May Max 29.8 31.3 31.4
Min 21.5 25.1 25.1 June Max 28.2 30.5 30.7
Min 21.4 25.2 25.1
(B) RELATIVE HUMIDITY
Records are available giving the following.
(i) Monthly mean maximum and minimum wet bulb temperatures with offsets
from average.
Section 6 – Employer’s Requirements : Part A-Scope of Work 6A-8
Bidding Document for CEAIP – Part 3- Job B Procurement of Plant Single-Stage: Two-Envelope
(ii) Extreme wet bulb temperature in each month.
(iii) Monthly means of the relative humidity obtained from dry and wet bulb
readings with offsets from average.
(iv) Monthly means of the relative humidity obtained from the minimum dry and
maximum wet bulb readings with offsets from average.
The averages are taken for the standard period of 1961-1990 and are
shown in Table 1.2.2 .
Table 1.2.2 - % Relative Humidity
Galle Colombo Katunayaka
January day 76 70 63
night NA 91 84
February day 73 66 65
night NA 90 86
March day 73 67 68
night NA 90 89
April day 76 71 71
night NA 90 89
May day 80 74 76
night NA 88 87
June day 82 73 76
night NA 86 85
July day 82 75 76
night NA 85 85
August day 83 75 74
night NA 84 85
September day 81 75 75
night NA 85 87
October day 81 76 76
night NA 89 90
November day 79 74 73
night NA 90 91 December day 79 71 70
night NA 88 88
(C) BAROMETRIC PRESSURES
Section 6 – Employer’s Requirements : Part A-Scope of Work 6A-9
Bidding Document for CEAIP – Part 3- Job B Procurement of Plant Single-Stage: Two-Envelope
Records are available for monthly means of the air pressure taken at 08.30 and
17.30 hours as mean sea level pressure. The averages are taken for the
standard period of –1961-1990 and varies from 1007.1 mB to 1013.1mB.
(D) RAINFALL
The rainfall figures given in Table 1.2.3 are based on average rainfall.
Table 1.2.3 - Rainfall
Galle Colombo Katunayaka
Jan 85.1 69.3 45.8
Feb 70.5 77.3 79.8
Mar 111.3 141.5 132.9
Apr 206.8 246.5 241.9
May 290.4 360.6 317.6
Jun 188.2 198.4 177.2
Jul 163.2 132.7 99.2
Aug 185.9 139.3 117.6
Sep 255.8 254.9 224.1
Oct 322.7 371.4 389.7
Nov 321.0 314.7 313.7
Dec 176.9 177.8 129.7
(E) WIND
Records available are given as follows.
Table 1.2.4 - 30 Year Averages (1961 - 1990) Wind Speed (m/S)
Galle Colombo
Jan 7.4 11.1
Feb 7.8 9.4
Mar 8.1 8.4
Apr 8.8 8.3
May 13.6 9.8
Jun 16.4 11.3
Jul 15.8 11.5
Aug 16.2 11.2
Sep 15.2 10.4
Section 6 – Employer’s Requirements : Part A-Scope of Work 6A-10
Bidding Document for CEAIP – Part 3- Job B Procurement of Plant Single-Stage: Two-Envelope
Oct 11.9 8.8
Nov 9.3 9.1
Dec 7.7 10.4
(F) STORMS
The frequency of thunder-storms is high, the isokeraunic level being
approximately 60 days per annum on average for the island.
1.3 PLANT & MATERIAL INCLUDING DESIGN SERVICES
Refer Plant & Materials from outside the Employer’s country and Plant &
Materials from within the Employers country in Schedules Nos 1.1, 2.1, 3.1, 4.1
and Schedule Nos 1.2, 2.2, 3.2, 4.2 in Volume 1 of 4, Section 4-Part A of Bidding
Document.
Refer Design services in Schedule Nos. 1.3, 2.3, 3.3, 4.3 in Volume 1 of 4,
Section 4- Part A of Bidding Document.
1.4 CIVIL WORKS, INSTALLATION, TRAINING & OTHER SERVICES
1.4.1 CIVIL WORKS, INSTALLATION & OTHER SERVICES
Refer Civil works in schedule Nos. 1.4, 2.4, 3.4, 4.4 of price schedules in Volume
1 of 4, section 4 Part A.
1.4.1.1 Adherence to the Environmental Mitigation Measures
Bidders are requested to comply with the requirements stated in the Chapter 1 ,
clause 1.42 of Section 6, Part B-Technical Specification and also to the
environmental safeguard measures described in the following documents
attached in the Section 6, Employer’s requirements, Part D-Supplementary
Information.
The said documents prepared in accordance with the governing acts and /or
guidelines, which are particularly relevant to this project may be inspected and a
copy each obtained free of charge from the office of the Project Manager- Clean
Energy and Access Improvement Project, Part 3 –Distribution Substation
Augmentation – Lot B at the following address
Section 6 – Employer’s Requirements : Part A-Scope of Work 6A-11
Bidding Document for CEAIP – Part 3- Job B Procurement of Plant Single-Stage: Two-Envelope
Office of the Project Manager (CEAIP-Part3-lot B)
Ceylon Electricity Board
First Floor,
50,Sir Chittampalam A.Gardiner Mawatha,
Colombo 02,
Sri Lanka.
Telephone: +94 -(0)11-2433117
Facsimile number: + 94 -(0)11 - 2348470
Electronic mail address: [email protected]
Environmental Safeguard - Documents prepared under Environmental Assessment Guide lines of Asian Development Bank (ADB)
Initial Environmental Examination Reports For Clean Energy & Access Improvement project o 33kV Power Lines to Kiribathgoda and Katunayake Primary Sub Stations o 33kV incoming lines to Nawala and Kotikawatta Primary Substations