Work Breakdown Structure
Dictionary
US-HiLumi-doc-39
Date: 23-Jun-2018
Page 1 of 16
This document is uncontrolled when printed. The current version is maintained on http://us-hilumi-docdb.fnal.gov
US HL-LHC Accelerator Upgrade Project
WBS DICTIONARY
Approved by:
Giorgio Apollinari, US HL-LHC AUP Project Manager, FNAL
Work Breakdown Structure
Dictionary
US-HiLumi-doc-39
Date: 23-Jun-2018
Page 2 of 16
This document is uncontrolled when printed. The current version is maintained on http://us-hilumi-docdb.fnal.gov
Revision History
Revision Date Section No. Revision Description
14-Mar-2016 All Initial Release
11-Apr-2017 302.2.02 Updated per revisions to BOE US-HiLumi-doc-118
19-Apr-2017 302.2.01 Updated 302.2.01 adding M&S for shipments monitoring
19-Apr-2017 302.2.11 WBS name and scope updated
01-May-2017 302.2.02 Updated per Ruben e-mail
07-May-2017 All General minor updates, clarified L3/L4 LOE is excluded from WBS scope and clarify deliverable is for WBS deliverable (not project)
09-May-2017 302.2.02 Correction of typographical errors (LDC)
10-May-2017 302.2.06 Added fab of shipping fixtures
25-May-2017 302.3.02.03
302.3.02.06
Adjusted RFD cavity testing and re-processing rates to match BOE files
24-Jul-2017 302.2.11 Fixed test requirements reference (US-HiLumi-doc-449)
4-Aug-2017 302.1 Renamed “Project Engineering” to “System Integration Engineering”
15-May-2018 Various Updated to match latest WBS structure
23-Jun-2018 Various Miscellaneous updates for CD-2/3b Directors review
Work Breakdown Structure
Dictionary
US-HiLumi-doc-39
Date: 23-Jun-2018
Page 3 of 16
This document is uncontrolled when printed. The current version is maintained on http://us-hilumi-docdb.fnal.gov
WBS Code WBS Name Control Account
302 High Luminosity LHC Accelerator Upgrade Project No
WBS Description
Scope of Work
Entire project 302 scope. For details, see US-HiLumi-doc-93 “Project Execution Plan”
Scope Assumptions/Exclusions
See Key Assumptions Document US-HiLumi-doc-78
Not in scope:
- Installation and commissioning of deliverables
WBS Deliverables
Inner Triplet Focusing Quadrupoles (Q1 and Q3):
Threshold: 5 Q1 cryo-assemblies and 4 Q3 cryo-assemblies for HL-LHC tunnel installation are accepted
by CERN after testing at HL-LHC nominal temperature and ultimate gradient for the magnets, and
functionality for the Cryoassembly. The Cryo-assemblies will be assembled from Cold Masses built by HL-
LHC AUP and Cryostat kits provided by CERN. Procurement of components for 1 additional Q1/Q3 cold
mases. Objective: assembly of 1 additional Q3 cryo-assembly, accepted by CERN after testing at HL-LHC
nominal temperature and ultimate current for the magnet, and functionality for the Cold Mass. The Cryo-
assembly will be assembled from Cold Masses built by HL-LHC AUP and Cryostat kits provided by
CERN
SRF Crab Cavities:
Threshold: 8 Radio Frequency Dipoles (RFDs) dressed cavities for HL-LHC Crab Cavity System tunnel
installation are accepted by CERN after being tested at HL-LHC nominal temperature, within the nominal
frequency range, and ultimate cavity voltage. The “dressed” cavity is comprised of the bare cavity, the
magnetic shields, the helium containment vessel with tuner interface, and RF ancillaries (H-HOM coupler,
V-HOM coupler, and RF pickup). Procurement of components for 2 additional RFD dressed cavities.
Objective: 2 additional dressed RFD dressed cavities for the HL-LHC Crab Cavity system accepted by
CERN after being tested at HL-LHC nominal temperature, within the nominal frequency range, and
ultimate cavity voltage.
WBS Code WBS Name Control Account
302.1 Project Management Yes
WBS Description
Scope of Work
Provide labor resources for Project Management, Systems Integration Engineering, Project Controls,
Finance, ES&H, Quality, Risk, and Procurement. Most of the labor is in the form of Level-of-Effort and is
based on assigned personnel and estimated effort. It includes the following Level 3 scope:
302.1.01 Project Office Management
- Project Manager, Deputy Project Manager, Systems Integration Engineer, L2 Managers, Systems
Integration Engineer, Lead Project Control staff, Scheduler, and managers for Finance, ES&H, Quality,
Risk, and Procurement.
302.1.02 BNL Management
- BNL representative
Work Breakdown Structure
Dictionary
US-HiLumi-doc-39
Date: 23-Jun-2018
Page 4 of 16
This document is uncontrolled when printed. The current version is maintained on http://us-hilumi-docdb.fnal.gov
- BNL Project Controls
- Points of Contact for QA and ES&H
302.1.03 LBNL Management
- LBNL representative
- LBNL Project Controls
- Points of Contact for QA and ES&H
Scope Assumptions/Exclusions
Each laboratory provides Project Control Support staff for their respective scope
WBS Deliverables
Documentation required for 413.3b DOE Order. Includes project Documentation required for DOE critical
decision reviews, resource loaded schedule, risk register, configuration control, internal review reports,
monthly performance reports, etc.
WBS Code WBS Name Control Account
302.2 MQXFA Magnets Fabrication No
WBS Description
Scope of Work
Final design and fabrication of MQXF magnets for 1 Q1/Q3 cryo-assembly prototype, 5 production Q1
cryo-assemblies, and 5 production Q3 cryo-assemblies. Each production cryo-assembly contains two
MQXFA magnets.
Scope Assumptions/Exclusions
Testing of MQXFA magnets is not part of the scope of this WBS, but test analysis is included in the scope.
One 4 m prototype magnet (MQXFAP1) and one 4.2 m prototype magnet (MQXFAP2) to be received from
LARP, and to be used for AUP cryo-assembly prototype. This WBS element includes re-work of these
prototype magnets to meet requirements for cryo-assembly prototype.
WBS Deliverables
20 accepted MQXFA magnets, one 4.2 m MQXFAP prototype magnet, and one 4 m MQXFAP prototype
magnet.
WBS Code WBS Name Control Account
302.2.01 Magnet Design, Integration, and Coordination Yes
WBS Description
Scope of Work
Complete the magnet final design, and MQXFA Final Design Report. Integrate products from other WBS
elements into the complete magnet assembly. Coordinate WBS elements regarding MQXFA magnets, for
example: analysis of prototype and production magnet test results and feedback into design or fabrication
process, magnets assembly re-work, etc. Procure accelerometers and shock-sensors for monitoring and
recording shocks during shipments, and perform analysis.
Scope Assumptions/Exclusions
WBS Deliverables
Conceptual Design Report, Final Design Report, and integration documentation.
Work Breakdown Structure
Dictionary
US-HiLumi-doc-39
Date: 23-Jun-2018
Page 5 of 16
This document is uncontrolled when printed. The current version is maintained on http://us-hilumi-docdb.fnal.gov
WBS Code WBS Name Control Account
302.2.02 Strand Procurement Yes
WBS Description
Scope of Work
- Procure, or obtain from LARP inventory, sufficient Nb3Sn strand to manufacture 102 cables. The
Strand Unit Length (UL) is the length of each strand re-spooled onto the cabling machine. The strand
UL (500 m) is longer than the cable UL to accommodate the cable lay and twist.
- Perform Quality Control (QC) verification of supplier’s product. QC verification is manly based on
electromagnetic properties such as critical current (Ic), residual resistance ratio (RRR).
- Mount coil witness samples on reaction barrels and perform tests of electromagnetic properties (Ic and
RRR).
Scope Assumptions/Exclusions
- Strand for 12 cable units is assumed to be available to the project from LARP inventory and is
excluded from the WBS. QC testing for strand in LARP inventory is also excluded from the WBS.
- Each cable has 40 strands.
- Lab performs QC on 50% of pieces.
- 6 witness sample tests are co-reacted with each coil, from which 3 successful sample tests must be
derived.
- A 90% testing yield is assumed for electromagnetic property measurements
WBS Deliverables
40 (strands) × 102 (cables) = 4,080 Accepted Unit Lengths (UL) of strand and related strand QC reports
and witness samples test reports.
WBS Code WBS Name Control Account
302.2.03 Cable Fabrication Yes
WBS Description
Scope of Work
Fabricate 102 Unit Lengths (ULs) of insulated cable. The Cable Fabrication UL is 455m, which is the
length of cable required to fabricate a coil plus length for QC testing samples, braiding, coil winding leads,
and buffer lengths. Each cable uses 40 Nb3Sn strand elements of 500 m long each. The minimum UL of the
delivered cable for coil fabrication is 431 m.
Quality Control activities in this WBS include RRR testing of extracted strands and measurement of post-
braiding insulation thickness by the ten-stack method.
Scope Assumptions/Exclusions
- Cable production yield is assumed to be 90% (i.e., 1 cable out of 10 will be rejected and scrapped)
- RRR testing samples assumes 5 extracted strand samples required per cable
- The LBNL cabling machine is available for this work
- 4 Unit Lenghts of insulated cable to be received by LARP.
WBS Deliverables
A minimum of 96 Unit Lengths (minimum UL continuous length for delivered cable is 431 m) of accepted
cable and related QC reports. This is the minimum number of cables required to support the fabrication of
96 coils.
WBS Code WBS Name Control Account
Work Breakdown Structure
Dictionary
US-HiLumi-doc-39
Date: 23-Jun-2018
Page 6 of 16
This document is uncontrolled when printed. The current version is maintained on http://us-hilumi-docdb.fnal.gov
302.2.04 Coil Parts, Materials, and Tooling Yes
WBS Description
Scope of Work
1. Procure coil parts (excluding insulated cable) for the fabrication of 96 coils. Major parts include
poles, wedges, end parts, traces, and consumable materials.
2. A total number of 19 coil part sets are assumed to be available from LARP and the balance (77)
are procured with project funds.
3. Procure additional tooling required to increase coil production throughput at both FNAL and BNL
locations. Additional tooling includes 4 reaction fixtures, 2 impregnation fixtures, 10 storage
fixtures and a FNAL second winding mandrel.
4. Procure 3 CMM measurement systems
5. Ship corresponding parts and additional tooling to BNL for coils to be fabricated at the BNL
location as part of 302.2.06 “Coil Fabrication at BNL”.
Scope Assumptions/Exclusions
• 19 coil part sets are available from LARP
• One set of coil production tooling is available from LARP at both FNAL and BNL location
• BNL also requires a second winding mandrel, but it will be procured at BNL as part of 302.2.06
“Coil Fabrication at BNL” because this mandrel is specific to the BNL winding machine.
WBS Deliverables
• Parts for the fabrication of 96 coils (49 sets for FNAL, 47 sets for BNL)
• 1 winding machine mandrel for FNAL
• 4 reaction fixtures (2 for FNAL, 2 for BNL)
• 2 impregnation fixtures (1 for FNAL, 1 for BNL)
• 10 storage fixtures (5 for FNAL, 5 for BNL)
• 3 CMM machines (1 for FNAL, 1 for BNL and 1 for LBNL)
WBS Code WBS Name Control Account
302.2.05 Coil Fabrication at FNAL Yes
WBS Description
Scope of Work
Fabricate 6 pre-series QXFA coils and 43 production QXFA coils at Fermilab. Fabrication steps include
Winding and Curing, Reaction, and Impregnation. Includes shipping of accepted coil to LBNL for magnet
assembly. Detailed description of QXF coil fabrication process provided by US-HiLumi-doc-95.
Scope Assumptions/Exclusions
- One set of coil fabrication tooling is available from LARP, installed and fully functional in Fermilab
Industrial Building 3 (IB3). This includes a winding machine with one mandrel, a curing press, a
reaction oven and an impregnation fixture, an impregnation station (in IB2) and an impregnation
fixture.
- Coil witness sample testing is covered under the scope of WBS 302.2.02 Stand Procurement
- Coil production yield is assumed to be 87.5% (i.e., 1 coil out of 8 will be rejected and scrapped)
WBS Deliverables
A minimum of 43 accepted QXFA coils with their corresponding QC reports.
WBS Code WBS Name Control Account
302.2.06 Coil Fabrication at BNL Yes
WBS Description
Work Breakdown Structure
Dictionary
US-HiLumi-doc-39
Date: 23-Jun-2018
Page 7 of 16
This document is uncontrolled when printed. The current version is maintained on http://us-hilumi-docdb.fnal.gov
Scope of Work
Fabricate 3 pre-series QXFA coils and 44 production QXFA coils at BNL. Fabrication steps include
Winding and Curing, Reaction and Impregnation. Includes shipping of accepted coils to LBNL for magnet
assembly. Also includes winding and curing of one practice coil. Detailed description of QXF coil
fabrication process provided by US-HiLumi-doc-95.
In addition, it includes procurement of additional winding tooling for the BNL winding machine to increase
production throughput. Also included is the fabrication of 4 additional coil shipping fixtures and 3
additional magnet shipping fixtures.
Scope Assumptions/Exclusions
- One set of coil fabrication tooling is available from LARP, installed and fully functional in BNL
Building 902 of the BNL Superconducting Magnet Division. This includes a winding machine with
one mandrel, a curing press, a reaction oven and a reaction fixture, an impregnation station and an
impregnation fixture.
- Coil witness sample testing is covered under the scope of WBS 302.2.02 Stand Procurement
- Coil production yield is assumed to be 87.5% (i.e., 1 coil out of 8 will be rejected and scrapped)
WBS Deliverables
A minimum of 41 accepted QXFA coils with their corresponding QC reports; 4 additional coil shipping
fixtures and 3 additional magnet shipping fixtures.
WBS Code WBS Name Control Account
302.2.07 Structure Fabrication and Magnets Assembly Yes
WBS Description
Scope of Work
Re-assemble magnet prototype MQXFA-2b, fabricate pre-series magnets MQXFA-03 and MQXFA-04,
and fabricate 19 MQXFA series production magnets. Scope includes:
- Parts procurement for 21 magnet structures (shell, Yoke, masters, pads, collars, axial support
components, keys, strain gauges and wires)
- 25 magnet assemblies (1 prototype re-assembly, 1 pre-series, 20 series production, and 3 re-
assemblies). Assembly includes install strain gauges on shells, Fabricate Yoke/Shell subassemblies.
Receive, check and prepare coils. Assemble collar packs and coil packs. Insert coil packs, setup
bladders, and perform azimuthal and axial preload, and conduct electrical QC
- Prepare for shipment and ship to magnet assembly to BNL for vertical testing
Scope Assumptions/Exclusions
- Fabrication of magnet prototype MQXFA-2 is off-project (by LARP), only MQXFA-2b re-work is on
project
- One set of magnet fabrication tooling is available from LARP, installed and fully functional in LBNL
Building B77a.
- 15% of the magnets (3 out of 20) are assumed to be re-worked before passing acceptance test. Parts are
assumed to be re-used for this re-work.
- 1 Magnet structure is assumed to be irreversibly damaged, due to shipping and handling, and therefore
assumed lost after vertical test.
WBS Deliverables
- Re-assembled prototype magnet MQXFA-2b, pre-series magnets MQXFA-03 and MQXFA-04, and a
minimum of 19 accepted production MQXFA magnets with their corresponding QC reports
WBS Code WBS Name Control Account
Work Breakdown Structure
Dictionary
US-HiLumi-doc-39
Date: 23-Jun-2018
Page 8 of 16
This document is uncontrolled when printed. The current version is maintained on http://us-hilumi-docdb.fnal.gov
302.4. Q1/Q3 Cryo-assembly Fabrication No
WBS Description
Scope of Work
Final design and fabrication of 11 Q1/Q3 Cold Masses (1 prototype, 1 pre-series, 9 series production)
including final design and fabrication of the Q1/Q3 Cold Mass fabrication tooling. Installation of CERN-
provided Q1/Q3 Cryostat tooling and assembling of Q1/Q3 cryo-assemblies (1 prototype 1 pre-series, 9
series production Q1/Q3 cryo-assemblies) using CERN provided cryostat kits. Includes Vertical testing of
27 magnets: 3 prototypes, 2 pre-series, and 22 series production (19 plus 3 re-worked) and Horizontal
testing and shipping of the 11 Q1/Q3 cryo-assemblies to CERN.
Scope Assumptions/Exclusions
CERN is the Design Authority for the Q1/Q3 Cryostat design. The Q1/Q3 Cryostat tooling procurement is
the responsibility of CERN. The cryostat kit, cryostat tooling, and some cold mass parts are provided by
CERN including initial inspection of these items at CERN and shipping to Fermilab. The complete list of
CERN provided components can be found in “Exchange of components between HL LHC AUP and CERN
for the triplet”, CERN EDMS 1825173.
Q1/Q3 Cryo-assembly installation and commissioning is not in the project scope
WBS Deliverables
1 Q1/Q3 cryo-assembly 1 prototype 1 pre-series, 9 series production Q1/Q3 cryo-assemblies fully tested
and documented.
WBS Code WBS Name Control Account
302.4.01 Magnets Vertical Test Yes
WBS Description
Scope of Work
Test 27 magnets at the BNL vertical test facility: 3 prototypes, 2 pre-series, and 22 series production (19
plus 3 re-worked). Includes test preparation, magnet test, and magnet shipment to LNBL or FNAL.
Includes procurement and fabrication of a second top plate and minor infrastructure upgrades to meet test
production throughput.
Scope Assumptions/Exclusions
- The BNL vertical test facility is assumed to be available from LARP, installed and fully functional in
BNL Building 902 of the BNL Superconducting Magnet Division.
- 15% of the magnets (3 out of 20) are assumed to not pass vertical testing and sent back to LBNL for re-
work and are re-tested before passing acceptance test.
WBS Deliverables
- A total of 27 magnet tests with their corresponding Test Reports
WBS Code WBS Name Control Account
302.4.02 Cold Mass Assemblies Fabrication Yes
WBS Description
Scope of Work
Final design and fabrication of 11 Q1/Q3 Cold Masses (1 prototype, 1 pre-series, 9 series production, 1
re-work) including final design and fabrication of the Q1/Q3 Cold Mass fabrication tooling. Some cold
mass parts are provided by CERN and the scope includes design verification of these components.
Scope Assumptions/Exclusions
Work Breakdown Structure
Dictionary
US-HiLumi-doc-39
Date: 23-Jun-2018
Page 9 of 16
This document is uncontrolled when printed. The current version is maintained on http://us-hilumi-docdb.fnal.gov
Fermilab is the Design Authority for the Cold Mass design. The complete list of CERN provided
components can be found in “Exchange of components between HL LHC AUP and CERN for the
triplet”, CERN EDMS 1825173.
WBS Deliverables
- 11 Q1/Q3 Cold Masses (1 prototype, 1 pre-series, 9 series production) with their corresponding QC
and safety reports
WBS Code WBS Name Control Account
302.4.03 Cryo-assemblies fabrication and shipment Yes
WBS Description
Scope of Work
Assemble 12 Q1/Q3 cryo-assemblies (1 prototype, 1 pre-series, 9 series production, 1 re-work). Each cryo-
assembly has one cold mass assembly inside the CERN-supplied cryostat. Activities include receive a
complete kit of cryostat parts from CERN, assemble the CERN cryostat, insert the cold mass assembly into
the cryostat, and deliver to Horizontal Test Facility for testing. After a successful horizontal test, prepare
the cryo-assembly for shipment and ship to CERN.
Scope Assumptions/Exclusions
- The following items are off project scope:
o Q1/Q3 Cryostats design (CERN is the design authority).
o CERN is responsible for the procurement of kits and tooling for the assembly of the
Q1/Q3 cryostats, including shipment to AUP at Fermilab.
o CERN is responsible for the development of assembly plans and QA/QC plans for the
Q1/Q3 cryostats assembly.
- CERN will provide guidance to support the tooling installation and onsite support to train AUP
personnel during the assembly of the prototype cryo-assembly.
- 10% of the cryo-assemblies (1 out of 10) are assumed to need to be re-worked before they can pass
horizontal acceptance test.
WBS Deliverables
- One Q1/Q3 cryo-assembly prototype and 5 Q1 and 5 Q3 accepted cryo-assemblies shipped to CERN
WBS Code WBS Name Control Account
302.4.04 Cryo-assemblies Horizontal Test Yes
WBS Description
Scope of Work
- Test 12 Q1/Q3 cryo-assemblies at the Fermilab horizontal test stand 4 in Industrial Building 1 (IB1)
(1 prototype, 1 pre-series, 9 series production, 1 re-work). Activities include test preparation, test,
and test report documentation. The scope includes upgrading the test stand to meet the Q1/Q3 cryo-
assembly test requirements (see US-HiLumi-449), but it does not include refurbishment of the test
stand required for reliable cryogenic and electrical operation. The scope also includes development
of the magnetic measurement system to be used at the Fermilab horizontal test stand.
Scope Assumptions/Exclusions
- The IB1 horizontal test stand is assumed to be brought back to reliable cryogenic and electrical
operation off-project.
- Adequate cryogenic services availability from IB1 is assumed to sustain the peak production test
throughput.
- 10% of the cryo-assemblies (1 out of 10) are assumed to not pass horizontal testing and sent back
Work Breakdown Structure
Dictionary
US-HiLumi-doc-39
Date: 23-Jun-2018
Page 10 of 16
This document is uncontrolled when printed. The current version is maintained on http://us-hilumi-docdb.fnal.gov
for re-work and are re-tested before passing acceptance test.
WBS Deliverables
- Test facility upgrades to meet Q1/Q3 cryo-assembly test requirements A total of 12 Q1/Q3 cryo-
assembly tests with their corresponding Test Reports.
WBS Code WBS Name Control Account
302.4.04.01 Cryo-mechanical Horizontal Test Stand Upgrade No
WBS Description
Scope of Work
- Cryogenic and cryo-mechanical upgrades of the existing horizontal test stand in Industrial Building
1 (IB1) to meet the Q1/Q3 cryo-assembly test requirements (see US-HiLumi-449). The scope is
limited to test stand capability upgrades. Zero-magnet test for commissioning the cryo-mechanical
upgrades at the horizontal test stand.
Scope Assumptions/Exclusions
- The IB1 horizontal test stand is assumed to be brought back to reliable cryogenic operation off-
project.
- All equipment required to upgrade and verify the test stand cryo-mechanical capabilities will be
developed at FNAL.
WBS Deliverables
- Test facility cryo-mechanical upgrades to meet Q1/Q3 cryo-assembly test requirements. Completion
of a Zero Magnet Test to verify as many as reasonably achievable cryo-mechanical capabilities in
this configuration.
WBS Code WBS Name Control Account
302.4.04.02 Instrumentation and Mechanical Horizontal Test Stand
Upgrade
No
WBS Description
Scope of Work
- 25 T crane upgrade at test facility to allow lifting of Q1/Q3 cryostat assembly. Development of
magnetic measurement systems for testing cryostat assemblies at Horizontal test stand. Power bus
upgrade to accommodate the Q1/Q3 cryo-assembly test requirements (see US-HiLumi-449).
Miscellaneous instrumentation and mechanical tasks not included in the WBS 302.4.04.01 scope.
Scope Assumptions/Exclusions
- The IB1 horizontal test stand is assumed to be brought back to reliable cryogenic operation off-
project.
- Refurbished Data Acquisition and Quench protection systems, as well as test facility specific
instrumentation will be provided off-project.
- Probe drive and position reading for the rotating coil measurement system will be provided off-
project
WBS Deliverables
- Test facility crane and power bus upgrades to meet the Q1/Q3 cryo-assembly test requirements.
Magnetic measurement systems for the prototype and series cryo-assemblies at room or operating
temperatures.
Work Breakdown Structure
Dictionary
US-HiLumi-doc-39
Date: 23-Jun-2018
Page 11 of 16
This document is uncontrolled when printed. The current version is maintained on http://us-hilumi-docdb.fnal.gov
WBS Code WBS Name Control Account
302.4.04.03 Horizontal Test Stand Operations No
WBS Description
Scope of Work
- Test 12 Q1/Q3 cryo-assemblies (1 prototype, 1 pre-series, 9 series production, 1 re-work) at
horizontal test stand.
Scope Assumptions/Exclusions
- Adequate cryogenic services availability from IB1 is assumed to sustain the peak production test
throughput.
- 10% of the cryo-assemblies (1 out of 10) are assumed to not pass horizontal testing and sent back
for re-work and are re-tested before passing acceptance test.
WBS Deliverables
- A total of 12 Q1/Q3 cryo-assembly tests with their corresponding Test Reports.
WBS Code WBS Name Control Account
302.3 RFD Dressed Crab Cavities Fabrication No
WBS Description
Scope of Work
Design, fabricate, process, test and document Dressed Radio Frequency Dipole (RFD) cavities.
The number of cavities produced will be 2 Prototypes + 2 Pre-Series + 10 Series. Dressed cavities
include the bare cavity, magnetic shields, helium containment vessel, tuner interface components and RF
ancillaries (HOM couplers, RF pickup).
Scope Assumptions/Exclusions
Hardware will be fabricated almost exclusively through procurements with industry. On the other hand,
inspections, chemical processing, heat treatments, cleanroom preparations and qualifications will be
managed at Fermilab and performed primarily at Fermilab and ANL.
Fundamental power couplers for RFD cavities are excluded from the scope and installed at CERN, by
CERN after acceptance and delivery.
String assembly and Cryomodule integration of RFD cavities are also excluded from the scope and
responsibility of CERN.
WBS Deliverables
10 Dressed and qualified RFD cavities fully documented and shipped to CERN.
WBS Code WBS Name Control Account
302.3.01 RFD Cavities Design, Integration, and Coordination Yes
WBS Description
Work Breakdown Structure
Dictionary
US-HiLumi-doc-39
Date: 23-Jun-2018
Page 12 of 16
This document is uncontrolled when printed. The current version is maintained on http://us-hilumi-docdb.fnal.gov
Scope of Work
Develop and finalize the electro-magnetic design, the mechanical design, the interfaces, the fabrication and
qualification strategy of RFD cavities and ancillary components.
Includes L3 management level-of-effort and travel for 302.3.01 (Design, Integration and Coordination) and
302.3.02 (Fabrication and Testing).
Includes oversight and travel for all procurements in the RFD scope.
Includes oversight for all in-house processing and qualification activities in the RFD scope.
Includes control account management tasks, such as planning, meetings, project reviews and other
communications, coordination and oversight, documentation preparation and/or review,
Includes EVMS reporting for 302.3.01 (Design, Integration and Coordination) and 302.3.02 (Fabrication
and Testing).
Scope Assumptions/Exclusions
EM design of cavity ant HOM dampers: AUP
Mechanical design of cavity: AUP-CERN joint effort
Specification Drawings of all prototype hardware: AUP (or CERN where possible)
Specification Drawings of all series hardware: CERN (external dependencies)
WBS Deliverables
Conceptual Design Report, Preliminary Design Report, Final Design Report. Functional Requirements,
Technical Specifications, Acceptance Criteria, Interface Control Documents and any documentation
necessary for each project stage.
WBS Code WBS Name Control Account
302.3.02 RFD Cavities Fabrication and Testing Yes
WBS Description
Scope of Work
Includes in-house discrete work effort and procurements in industry and at other laboratories, to fabricate,
process, test and document Dressed Radio Frequency Dipole (RFD) cavities and ancillary devices.
The number of cavities produced will be 2 Prototypes + 2 Pre-Series + 10 Series. Dressed cavities include
the bare cavity, magnetic shields, helium containment vessel, tuner interface components and RF ancillaries
(HOM couplers, RF pickup).
Scope Assumptions
Hardware will be fabricated almost exclusively through procurements with industry (managed by
Fermilab).
Inspections, chemical processing, heat treatments, cleanroom preparations and qualifications will be
managed performed primarily at Fermilab and ANL, with other collaborating labs as back-up.
Exclusions
L3 management level-of effort and EVMS reporting effort for this Control Account are included in
302.3.01
WBS Deliverables
10 Dressed and qualified RFD cavities fully documented and shipped to CERN.
EVMS reporting for control account 302.3.02
Work Breakdown Structure
Dictionary
US-HiLumi-doc-39
Date: 23-Jun-2018
Page 13 of 16
This document is uncontrolled when printed. The current version is maintained on http://us-hilumi-docdb.fnal.gov
WBS Code WBS Name Control Account
302.3.02.01 Procurement of Services No
WBS Description
Scope of Work
Procure services from other laboratories and institutions to carry out design, integration and coordination
activities in support of the RFD scope.
Services from SLAC, ODU and BNL are anticipated to continue throughout the life of the project.
Responsibilities of different teams are identified in a separate document.
Scope Assumptions
Resources at other laboratories and institutions will be made available on a yearly basis to achieve
deliverables as agreed on statement-of-work documents which are prepared each FY.
Exclusions
L4 Management LOE is excluded from the WBS scope and included in WBS 302.3.01
WBS Deliverables
Obtain support from other laboratories for the design, integration and coordination activities, throughout
the lifetime of the project as agreed in the SOW documents
WBS Code WBS Name Control Account
302.3.02.02 Materials and Bare Cavity Procurement No
WBS Description
Scope of Work
Procurement of raw materials for 12 bare cavities (2 Pre-Series + 10 Series).
Procurement of 14 bare cavities (2 Prototypes + 2 Pre-Series + 10 Series)
Raw materials include:
- Bulk RRR Niobium sheets, tubes and rods
- Niobium-Titanium alloy plates
- 316LN Stainless Steel plates
- Nb-SST braze joints for cavity extremities
Perform incoming inspection of all material and provide to Cern samples and documentation as needed.
Serialize all material for traceability. Ship materials to bare cavity suppliers.
Procurement of Bare Cavities in industry includes:
- Development of fabrication drawings
- Fabrication of tooling for forming, machining and electron-beam welding
- Fabrication of all cavity components, final trim-tuning and electron-beam welding
- Fabrication documentation, final QC reports
- Packaging and shipping to Fermilab
Incoming Inspections for bare cavities include:
- Visual inspections
- Dimensional inspections
- RF survey
- Leak check
Scope Assumptions
Work Breakdown Structure
Dictionary
US-HiLumi-doc-39
Date: 23-Jun-2018
Page 14 of 16
This document is uncontrolled when printed. The current version is maintained on http://us-hilumi-docdb.fnal.gov
Incoming inspection (visual & dimensional) performed by Fermilab TD Quality Control. Staff to be
available as necessary to perform all inspections in a timely manner.
Ultrasonic inspections requested by CERN for raw materials will be performed in industry.
Additional qualification of raw materials if requested by Cern will be carried out at Cern with shipping
responsibility of AUP.
Exclusions
Raw materials for 2 Prototypes is already available from LARP and excluded from the scope.
L4 Management LOE is excluded from the WBS scope and included in WBS 302.3.01
WBS Deliverables
14 inspected and documented bare cavities (2 Prototypes + 2 Pre-Series + 10 Series). Manufacturing
reports, certifications, final inspection reports in form of electronic travelers.
WBS Code WBS Name Control Account
302.3.02.03 Bare Cavity Qualification No
WBS Description
Scope of Work
Define preparation recipe for RFD cavities (details of chemical processing, heat treatments, high pressure
rinsing, clean room assembly).
Develop all facility and infrastructure modifications to accommodate bare RFD cavities processing and
testing.
Process, prepare and test at cryogenic temperature 14 bare cavities (2 Prototypes + 2 Pre-Series + 10
Series).
Scope Assumptions/Exclusions
- L4 Management LOE is excluded from the WBS scope and included in WBS 302.3.01
- 50% of cavities is assumed to re-process and re-test once (e.g. 10 cavities = 15 cycles)
- Buffered chemical polishing, high pressure rinsing, and cleanroom assembly for testing are performed
at the SCPF at Argonne National Lab.
- Hydrogen degasification and low temperature baking is performed in MP9 at Fermilab.
- Cavity SRF performance is measured in the IB1 Vertical Test Area.
- ANL SCPF facility and staff as well as at FNAL MP9 are available as necessary to process and re-
process the bare cavities.
- Cryogenics at the VTA are available as necessary to test the bare cavities.
WBS Deliverables
14 bare cavities, processed and tested and delivered to WBS 302.3.02.04.
Processing and testing traveler documentation.
WBS Code WBS Name Control Account
302.3.02.04 Dressed Cavity Procurement No
WBS Description
Work Breakdown Structure
Dictionary
US-HiLumi-doc-39
Date: 23-Jun-2018
Page 15 of 16
This document is uncontrolled when printed. The current version is maintained on http://us-hilumi-docdb.fnal.gov
Scope of Work
Procurement of magnetic shields in industry, procurement of helium tanks in industry (including raw
materials, machining, assembly, and welding around bare cavities).
Procurement of RF ancillaries at JLab (including raw materials, fabrication drawings, manufacturing,
chemical processing, documentation, shipment)
Final inspections of dressed cavities performed at Fermilab (visual, dimensional, frequency, vacuum).
Scope Assumptions/Exclusions
Fabrication of dressed cavities will be carried out as a series of procurements. Inspection, measurements,
cleaning and preparations will be performed at Fermilab.
L4 Management LOE is excluded from the WBS scope and included in WBS 302.3.01
Work carried out in industry. Magnetic shields and bare cavities are shipped to supplier of helium vessels
for integration and welding.
Tuner interface components procured and installed as part of helium vessel procurement.
Pressure testing of helium vessels performed at supplier per CERN requirement.
WBS Deliverables
14 dressed RFD Cavities (2 Prototypes + 2 Pre-Series + 10 Series) delivered to WBS 302.3.02.05.
Manufacturing records and final inspection documentation in the form of electronic travelers.
14 RF Ancillaries sets, ready for installation on dressed cavities.
Each set is comprised of:
- 1 vertical HOM
- 1 horizontal HOM
- 1 RF pick-up
WBS Code WBS Name Control Account
302.3.02.05 Dressed Cavity Qualification No
WBS Description
Scope of Work
Develop all facility and infrastructure modifications to accommodate dressed RFD cavities processing and
testing.
Process, prepare and test at cryogenic temperature a maximum of 14 bare cavities (2 Prototypes + 2 Pre-
Series + 10 Series).
Deliver to Cern 10 cavities that meet acceptance criteria (8 for tunnel installation + 2 spares).
Scope Assumptions/Exclusions
- L4 Management LOE is excluded from the WBS scope and included in WBS 302.3.01
- Buffered chemical polishing, high pressure rinsing, and cleanroom assembly for testing are performed
at the SCPF at Argonne National Lab.
- 50% of cavities is assumed to re-process and re-test once (e.g. 10 cavities = 15 cycles)
- Low temperature baking is performed in MP9 at Fermilab.
- Cavity SRF performance is measured in the IB1 Vertical Test Area.
- ANL SCPF facility and staff as well as at FNAL MP9 are available as necessary to process and re-
process the bare cavities.
- Cryogenics at the VTA are available as necessary to test the bare cavities.
WBS Deliverables
- Delivery of 10 fully qualified RFD cavities to CERN (8 for tunnel installation + 2 spares).
Work Breakdown Structure
Dictionary
US-HiLumi-doc-39
Date: 23-Jun-2018
Page 16 of 16
This document is uncontrolled when printed. The current version is maintained on http://us-hilumi-docdb.fnal.gov