40
Waterdown Road Reconstruction Public Information Centre (PIC) November 27, 2014

Waterdown Road Reconstruction - Burlington · Reconstruction Public Information Centre (PIC) November 27, 2014. Agenda 1. Project Team 2. Project Overview 3. ... Tender January 2015

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Waterdown Road Reconstruction - Burlington · Reconstruction Public Information Centre (PIC) November 27, 2014. Agenda 1. Project Team 2. Project Overview 3. ... Tender January 2015

Waterdown Road Reconstruction

Public Information Centre (PIC)

November 27, 2014

Page 2: Waterdown Road Reconstruction - Burlington · Reconstruction Public Information Centre (PIC) November 27, 2014. Agenda 1. Project Team 2. Project Overview 3. ... Tender January 2015

Agenda

1. Project Team2. Project Overview3. City Works4. Regional Works5. Schedule6. Communications7. Question Period

Page 3: Waterdown Road Reconstruction - Burlington · Reconstruction Public Information Centre (PIC) November 27, 2014. Agenda 1. Project Team 2. Project Overview 3. ... Tender January 2015

1. PROJECT TEAMWaterdown Road Reconstruction

Page 4: Waterdown Road Reconstruction - Burlington · Reconstruction Public Information Centre (PIC) November 27, 2014. Agenda 1. Project Team 2. Project Overview 3. ... Tender January 2015

Project Team

City of Burlington

Councillor Rick Craven, Ward 1Scott Hamilton, Manager of Design & ConstructionBob Jurk, Senior Project ManagerDerek McGaghey, Contract AdministratorAnton Ivanaj, Senior Design TechnicianVito Tolone, Senior Transportation PlannerJody Wellings, Special Business Area Coordinator

Halton Region

Rick Ranalli, Project Manager

Page 5: Waterdown Road Reconstruction - Burlington · Reconstruction Public Information Centre (PIC) November 27, 2014. Agenda 1. Project Team 2. Project Overview 3. ... Tender January 2015

2. PROJECT OVERVIEWWaterdown Road Reconstruction

Page 6: Waterdown Road Reconstruction - Burlington · Reconstruction Public Information Centre (PIC) November 27, 2014. Agenda 1. Project Team 2. Project Overview 3. ... Tender January 2015
Page 7: Waterdown Road Reconstruction - Burlington · Reconstruction Public Information Centre (PIC) November 27, 2014. Agenda 1. Project Team 2. Project Overview 3. ... Tender January 2015

Project Overview

• Environmental study• Building demolitions • Roadway widening:

– Replacement of:• Watermains• Storm sewers• Curbs and sidewalks• Asphalt

Page 8: Waterdown Road Reconstruction - Burlington · Reconstruction Public Information Centre (PIC) November 27, 2014. Agenda 1. Project Team 2. Project Overview 3. ... Tender January 2015

Project Overview

• Roadway widening (continued):– On-road bike lanes

• 3rd party utility relocations• Street lighting improvements• Gateway feature

Page 9: Waterdown Road Reconstruction - Burlington · Reconstruction Public Information Centre (PIC) November 27, 2014. Agenda 1. Project Team 2. Project Overview 3. ... Tender January 2015

3. CITY WORKSWaterdown Road Reconstruction

Page 10: Waterdown Road Reconstruction - Burlington · Reconstruction Public Information Centre (PIC) November 27, 2014. Agenda 1. Project Team 2. Project Overview 3. ... Tender January 2015

Environmental Study

The Purpose of the EA Study was to conduct a Schedule C Class Environmental Assessment to:

– address existing/future capacity deficiencies – consider the effects of all aspects of

environment and systematic evaluation of alternatives

– develop preliminary preferred design(s) of recommended alternative

Page 11: Waterdown Road Reconstruction - Burlington · Reconstruction Public Information Centre (PIC) November 27, 2014. Agenda 1. Project Team 2. Project Overview 3. ... Tender January 2015

Environmental Study

• Environmental Study Report (ESR) published December 2012– Report available on project webpage

• Preferred design selected• Construction to follow

recommendations

Page 12: Waterdown Road Reconstruction - Burlington · Reconstruction Public Information Centre (PIC) November 27, 2014. Agenda 1. Project Team 2. Project Overview 3. ... Tender January 2015

Building Demolitions

• Completed demolition of 4 house structures in August 2014

• RFQ made use of green procurement to recycle materials

Page 13: Waterdown Road Reconstruction - Burlington · Reconstruction Public Information Centre (PIC) November 27, 2014. Agenda 1. Project Team 2. Project Overview 3. ... Tender January 2015

Building DemolitionMurray’s Variety building to be purchased by City and demolished.

Page 14: Waterdown Road Reconstruction - Burlington · Reconstruction Public Information Centre (PIC) November 27, 2014. Agenda 1. Project Team 2. Project Overview 3. ... Tender January 2015

Road Widening

• Existing 3-lane configuration:– No on-road bike lanes– 1.5m wide sidewalks

• Proposed 5-lane configuration:– On-road bike lanes, both sides– 2.0m wide multi-use sidewalks

• Land required to build approved design

Page 15: Waterdown Road Reconstruction - Burlington · Reconstruction Public Information Centre (PIC) November 27, 2014. Agenda 1. Project Team 2. Project Overview 3. ... Tender January 2015

Existing - North of Fire Station

Page 16: Waterdown Road Reconstruction - Burlington · Reconstruction Public Information Centre (PIC) November 27, 2014. Agenda 1. Project Team 2. Project Overview 3. ... Tender January 2015

Existing – North at CN Bridge

Page 17: Waterdown Road Reconstruction - Burlington · Reconstruction Public Information Centre (PIC) November 27, 2014. Agenda 1. Project Team 2. Project Overview 3. ... Tender January 2015

Proposed – Plains to CN Bridge

Approved Design – Typical Cross Section

EAST WEST

Page 18: Waterdown Road Reconstruction - Burlington · Reconstruction Public Information Centre (PIC) November 27, 2014. Agenda 1. Project Team 2. Project Overview 3. ... Tender January 2015

3rd Party Utility Relocations

Page 19: Waterdown Road Reconstruction - Burlington · Reconstruction Public Information Centre (PIC) November 27, 2014. Agenda 1. Project Team 2. Project Overview 3. ... Tender January 2015

Bell Canada Two (2) existing maintenance hole structures to be rebuilt to accommodate lowering of cable duct structures.

Page 20: Waterdown Road Reconstruction - Burlington · Reconstruction Public Information Centre (PIC) November 27, 2014. Agenda 1. Project Team 2. Project Overview 3. ... Tender January 2015

Burlington HydroEast pole line on Waterdown Road to be relocated further east.

Page 21: Waterdown Road Reconstruction - Burlington · Reconstruction Public Information Centre (PIC) November 27, 2014. Agenda 1. Project Team 2. Project Overview 3. ... Tender January 2015

Burlington HydroBurial of overhead wires on southeast corner - secondary poles only.

Overhead to underground

Remains

Page 22: Waterdown Road Reconstruction - Burlington · Reconstruction Public Information Centre (PIC) November 27, 2014. Agenda 1. Project Team 2. Project Overview 3. ... Tender January 2015

Traffic Signals

• Replacement of existing signals at:– Waterdown Road & Plains Road– Waterdown Road & Masonry Court

• New signal at:– Plains Road & Cooke Boulevard

Page 23: Waterdown Road Reconstruction - Burlington · Reconstruction Public Information Centre (PIC) November 27, 2014. Agenda 1. Project Team 2. Project Overview 3. ... Tender January 2015

Street Lighting

• New street lights on Waterdown Road

• Decorative and traditional

Page 24: Waterdown Road Reconstruction - Burlington · Reconstruction Public Information Centre (PIC) November 27, 2014. Agenda 1. Project Team 2. Project Overview 3. ... Tender January 2015

Gateway Feature

• Streetscaping to include for gateway feature at Plains Road and Waterdown Road intersection

• Combination of hard and soft landscaping

Page 25: Waterdown Road Reconstruction - Burlington · Reconstruction Public Information Centre (PIC) November 27, 2014. Agenda 1. Project Team 2. Project Overview 3. ... Tender January 2015

Gateway Feature

Page 26: Waterdown Road Reconstruction - Burlington · Reconstruction Public Information Centre (PIC) November 27, 2014. Agenda 1. Project Team 2. Project Overview 3. ... Tender January 2015

4. REGIONAL WORKSWaterdown Road Reconstruction

Page 27: Waterdown Road Reconstruction - Burlington · Reconstruction Public Information Centre (PIC) November 27, 2014. Agenda 1. Project Team 2. Project Overview 3. ... Tender January 2015

Regional Works

• Replacement on Waterdown Road:– 155m of 600mm dia. concrete

pressure pipe– 590m of 300mm dia. watermain

• Replacement on Railway Road:– 315m of 150mm dia. watermain

Page 28: Waterdown Road Reconstruction - Burlington · Reconstruction Public Information Centre (PIC) November 27, 2014. Agenda 1. Project Team 2. Project Overview 3. ... Tender January 2015

5. SCHEDULEWaterdown Road Reconstruction

Page 29: Waterdown Road Reconstruction - Burlington · Reconstruction Public Information Centre (PIC) November 27, 2014. Agenda 1. Project Team 2. Project Overview 3. ... Tender January 2015

Schedule

Public Information Centre November 2014Tender January 2015Construction Starts March 2015Road Closure May-October 2015

(Waterdown Road – Masonry to Plains)

Interim Completion November 2015Total Completion May 2016

Page 30: Waterdown Road Reconstruction - Burlington · Reconstruction Public Information Centre (PIC) November 27, 2014. Agenda 1. Project Team 2. Project Overview 3. ... Tender January 2015

Road Closure

• Closure of Waterdown Road from Plains to Masonry (May-October)

• Detour route via Masonry Court and Cooke Boulevard

Page 31: Waterdown Road Reconstruction - Burlington · Reconstruction Public Information Centre (PIC) November 27, 2014. Agenda 1. Project Team 2. Project Overview 3. ... Tender January 2015

LOCAL ACCESS

ONLY

DETOUR ROUTE

Page 32: Waterdown Road Reconstruction - Burlington · Reconstruction Public Information Centre (PIC) November 27, 2014. Agenda 1. Project Team 2. Project Overview 3. ... Tender January 2015

6. COMMUNICATIONSWaterdown Road Reconstruction

Page 33: Waterdown Road Reconstruction - Burlington · Reconstruction Public Information Centre (PIC) November 27, 2014. Agenda 1. Project Team 2. Project Overview 3. ... Tender January 2015

Communications

• Keep up to date on the project by:– Visiting project webpage– Project updates by ad mail– Sign up for email notifications– Contact project team (attached)

Page 34: Waterdown Road Reconstruction - Burlington · Reconstruction Public Information Centre (PIC) November 27, 2014. Agenda 1. Project Team 2. Project Overview 3. ... Tender January 2015

7. QUESTION PERIODWaterdown Road Reconstruction

Page 35: Waterdown Road Reconstruction - Burlington · Reconstruction Public Information Centre (PIC) November 27, 2014. Agenda 1. Project Team 2. Project Overview 3. ... Tender January 2015

Questions

Page 36: Waterdown Road Reconstruction - Burlington · Reconstruction Public Information Centre (PIC) November 27, 2014. Agenda 1. Project Team 2. Project Overview 3. ... Tender January 2015

POST MEETINGWaterdown Road Reconstruction

Page 37: Waterdown Road Reconstruction - Burlington · Reconstruction Public Information Centre (PIC) November 27, 2014. Agenda 1. Project Team 2. Project Overview 3. ... Tender January 2015

Comments

• Take a project information package:– Fill out comments form here or

submit later

• Project team contacts provided in handout

Page 38: Waterdown Road Reconstruction - Burlington · Reconstruction Public Information Centre (PIC) November 27, 2014. Agenda 1. Project Team 2. Project Overview 3. ... Tender January 2015

Project Team Contacts

City of Burlington

Councillor Rick Craven 905-335-7600 Ext. 7587Ward 1 [email protected]

Bob Jurk 905-335-7600 Ext. 7682Senior Project Manager [email protected]

Derek McGaghey 905-335-7600 Ext. 7421Contract Administrator [email protected]

Page 39: Waterdown Road Reconstruction - Burlington · Reconstruction Public Information Centre (PIC) November 27, 2014. Agenda 1. Project Team 2. Project Overview 3. ... Tender January 2015

Project Team Contacts

Halton Region

Rick Ranalli 905-825-6000 Ext. 7619Project Manager [email protected]

Page 40: Waterdown Road Reconstruction - Burlington · Reconstruction Public Information Centre (PIC) November 27, 2014. Agenda 1. Project Team 2. Project Overview 3. ... Tender January 2015

Links

City of Burlingtonhttp://cms.burlington.ca/

Halton Regionhttp://www.halton.ca/

Project Websitehttp://cms.burlington.ca/Page14026.aspx

Councillor Rick Craven, Ward 1http://cms.burlington.ca/Page111.aspx

Plains Road Village Visionhttp://www.aldershotvillage.ca/