WATER SUPPLY SYSTEM FOR PUNE CITY PROJECT OVERVIEW
“REVISED DPR”
• DPR & DER submitted on July 12, 2013
• PPTs and Discussions on July 31, September 5
• PMC communicated observations vide Minutes of meeting with SGI & internal meetings
• All Ex. Engineers provided updated info on existing distribution pipes
• Detailed discussions with Ex. Engineers
DPR & DER DELIVERY AND PRESENTATIONS (1/2)
• Revision and modifications based on comments received from Ex. Engineers presented on 29th January 2014
• Final DPR modified and submitted on 18th February 2014.
• Final DER modified and submitted on 24th February 2014.
DPR & DER DELIVERY AND PRESENTATIONS (2/2)
Objectives of study
• Review existing Water Supply System
• Population and Water Demand Projections
• Design of Proposed Water System on 24x7 basis:
Clear Water Transmission, Storage & Distribution
• Preparation of Capital, O & M cost
• Project Financial Analysis and Viability
• Confirmation of sites for Service Reservoirs
• Check suitability of new sites for Service Reservoirs and Pump stations
• Feasibility of the alignments for transmission and Trunk distribution mains
JOINT SITE VISITS
New sites of Service Reservoirs
Sr. No. New Location Earlier location No. of
SRs
1 PARVATI ZONE
1.1 Amenity space in Rohan Kritika
Parvati WTP compound 2
1.2 Police lines SR compound
Sarasbag Kothi 2
2 WARJE ZONE
2.1 Near SNDT HLR Gandhi Bhavan 1
2.2 Fergusson college Pune University 1
2.3 Khairewadi Pune University 3
2.4 Chikhalwadi Ambedkar stadium
Pune Univesrity 2
2.5 Panchavati hill Panchavati Garden 1
New sites of Service Reservoirs
Sr. No. New Location Earlier location No. of
SRs
3 VADGAON ZONE
3.1 Seminary GSR Shivneri-Brahma Amenity space
1
3.2 Near Annad nagar Garden-survey no.46G
Hadpsar Bus Depot 3
3.3 Dorabji Paradise Amenity Space
Part of Cloud Nine 1
3.4 Dorabji Paradise Amenity Space
Nyati Amenity Space 1
3.5 High Bliss Society Amenity Space
Ujjwal Terrace 1
3.6 Near Institute ESR Charwad Wasti 1
New sites of Service Reservoirs
Sr. No. New Location Earlier location No. of
SRs
4 BHAMA-ASKHED ZONE
4.1 Bishops school Wadgaon Sheri PS 2
4.2 Vegetable Market-Plot33 Near 509
Sanjay Park-Rohan Mithila
2
4.3 Gairan in Lohegaon near Haran Tala
Gurudwara Wasti 2
4.4
Palm Garden opposite to Mental Corner(Vishrantwadi zone)
Near Stone Querry 2
SR sites not finalised
Sr. No. Location WS zone No. of
SRs
1 Survey no.7-Behind Raddison Hotel
Kharadi bypass 1
MAJOR ISSUES IN PARVATI
Sr. No. Description Clarification
1 Shifting of ESRs from WTP to Rohan Kritika
Site shifted
2 Utilization of newly laid 900mm MS gravity main
Planned to be used for gravity system from Parvati BPT
3 Shifting of Sarasbag Kothi ESRs to Police lines
Existing SRs and sump proposed to be demolished
4 Transfer of supply to PCWW for area- Sangam bridge to Bund
LLR Zone Is now proposed from Jalmandir GSR to be reconstructed
5 Seminary GSRs to be supplied from Padmavati PS
Parvati PS-BPT-Padmavati- Seminary will result in higher head pumping
MAJOR ISSUES IN VADGAON
Sr. No. Description Clarification
1 Utilization of WW tank as BPT
Now a BPT is proposed near Institute ESR which will supply to Ujjwal Terrace Zone. ( High Bliss ESR) and Venkatesh
Serenity ESR
2 Alignment of Gravity system from New Vadgaon sump-Sudatta Sankul-forest area
After joint site visit, the Alignments are revised
3 Non availability of site for BPT & PS at wonder city-Katraj
Pumping main from Vadgaon, to be extended.
Pumps for Agam Mandir 2 zones to be housed in New RG PS
4 Site for New RG PS shifted to Truck Terminus location
Proposals are modified with location at Santosh Nagar
MAJOR ISSUES IN VADGAON
Sr. No. Description Clarification
5
PMC informed on November 11, 2013 that sites for Charwad vasti & Ujjwal terrace not available
Alternate site for Ujjawal Terrace-Amenity space of High bliss society
confirmed by joint site visit. Alternate location for Charwad vasti
and new BPT is considered at the site adjacent to the existing Institute ESR.
6 Additional SR at Seminary SR site
Shivneri zone divided in to 2, one from ex. Site(Brahma Amenity) and other at
Seminary
MAJOR ISSUES IN CANTONMENT
Sr. No. Description Clarification
1 Revision of Bakri hill zones The capacity of existing GSR is a
constraint. The existing zones retained
2 Utilization of ex.1000mm pumping main For Sicilia
Accepted. The proposal will be modified
3 Utilization of 600mm main from Ram Tekdi-Tukai Tekadi SR
The existing pipeline will be utilized, adequate up to 2032
4 Alternative SR site for part of Cloud nine zone
One higher elevation DMA proposed to be supplied from new ESR in the
premises of Dorabji ESR Lower areas from the existing
location
5
MAJOR ISSUES IN WARJE
Sr. No. Description Clarification
1 Supply to Ideal colony zone from SNDT
The new location for 4 Ml capacity ESR identified by PMC. The design is
revised
2 Confirmation of site for Sutardhara Booster
The new site identified by PMC. The design is revised
3 Revision of Bhosale nagar, Bopodi and Model colony zones
PMC identified 3 new sites, 1 at Khairewadi & 2 at Chikhal wadi.
Designs are revised
4 Supply from Holkar WW Holkar WTP is proposed to Supply Chikhalwadi ESRs i.e. Bopodi Zone
and Khadaki Cantonment Area
5 Supply to Sangam wadi zone Sangam wadi from BA gravity system
MAJOR ISSUES IN WARJE
Sr. No. Description Clarification
6 Utilization of new ESR in Khadki Cant. area
Not proposed to be used in PMC area
7 Transmission main for Baner link Rd ESR
The alignment is now modified along high contour line, as per joint site visit
8 High elevation areas along Law college rd. on SNDT HLR
SNDT HLR zone modified to include this.
9 Alignment of Dukkar khind SR alignment through Forest
The alignment is modified, as per joint site visit
10 Utilization of 864mm diam. pipeline from CC to Pashan
This has been utilized as transmission main, for supply to Pashan &
Panchavati SRs
11 Utilization of 711mm MS pumping main-Pashan to Sus
This will be used in the proposed gravity system from CC BPT to Sus and
other SRs
MAJOR ISSUES IN WARJE
Sr. No. Description Clarification
12 Supply to MAFCO & Asha nagar SRS from HLR, instead of pumping from MLR-sump
Asha nagar SR can not be supplied from SNDT HLR/Existing BPT
A new BPT in SNDT area is proposed to supply MAFCO, Asha nagar and Khaire
Wasti SRs by gravity
13 Reorganization of SNDT HLR and SNDT MLR zones
The zone boundaries are modified and designs are revised.
MAJOR ISSUES IN BHAMA -ASKHED
Sr. No. Description Clarification
1 Shifting of ESRs from Wadgaon sheri PS
Two ESRS at new site-Bishops school-zones 2& 5
2 Khulewadi zone
Earlier Demand worked out based on DP and Metro corridor norms
Discussed revised DP on October 18. The revised 2032 demand 4.60Mld(20.69 mld). This zone is merged in Kharadi zone 3 and
the ESR capacity of the zone is increased to 4.5 ML
3 Thakarsi SRS Capacities & levels shall be as per DPR
MAJOR ISSUES IN BHAMA -ASKHED
Sr. No. Description Clarification
4 Identification of 7 SRs to be tendered
Meeting with PMC. The locations and WS zones finalised
hydraulic levels as per SGI design. If staging height is increased, the network analysis to be revised.
PMC confirmed excluding these 7 SRs from SGI estimates
5 Cost of all SRs included in DPR.
Cost of 11 SRs is not considered by SGI as advised by PMC
10
PMC informed supply of 200 Mld from BA & 22 Mld from Chikhali in 2032 (285 MLD in 2047)
The WS zones from PCWW to BA Kharadi zones 1,2& 3
Kharadi bypass Chandan nagar zones 1& 2
Wadgaon sheri zone 4
WS Zone Location No. of SRs
GL LDL FSL Staging height
Dhanori zone 1 Dhanori-Amenity space
1 588.85m
609.63m
615.63m
21m
Lohgaon Lake zone 1
Dhanori-Amenity space
1 588.13m
610.00m
646.00m
22m
Vadgaon Sheri zone 3
Vadgaon Sheri PS premises
2 566.07m
585.00m
591.00m
19m
Sainath nagar Sainath nagar Amenity space
1 552.68m
568.00m
574.00m
16m
Bhange vasti Bhange vasti-Amenity space
1 556.95m
576.00m
582.00m
19m
Tingare nagar Nyati Amenity space
1 565.47m
581.00m
587.00m
16m
DETAILS OF 7 SERVICE RESERVOIRS
WS Zone Location No. of SRs
GL LDL FSL Staging height
Lohegaon Lake Zone 1
Dhanori-Amenity space
1 588.99m 610.00m 616.00m 21.00m
Munjaba wasti Munjaba Wasti ESR 1 584.04m 603.59m 609.59m 20.00m
Laxmi Nagar/Ram Nagar
Thakarsi Proposed ESR 4
1 574.43m 582.22m 588.22m 8.00m
Navi Khadki Yerwada
K. Bhaurao Patil ESR 1 563.94m 581.00m 587.00m 17.00m
DETAILS OF ADDITIONAL 4 SERVICE RESERVOIRS
COMMON POINTS ON DPR
Sr. No. Description Clarification
1 Transmission main- Min. diam. 450mm
A. Pumping Mains Based on Techno-economic analysis
Water Hammer Velocity-0.60m/sec to 2.5m/sec
A. Gravity Mains
Ensure min. terminal head 3m Velocity-0.60m/sec to 2.5m/sec
Minimum 450mm diam. will reduce
the velocity <0.60m/sec
Designs are modified with 450 mm as minimum diameter.
COMMON POINTS ON DPR
Sr. No. Description Clarification
2 Transmission mains Matreial -steel for all diameters
Design criteria agreed with PMC A. Pumping Mains
Up to 450mm DI Above 450mm-MS
B. Gravity Mains Up to 600mm DI
Above 600mm-MS
PMC Confirmerd the DPR proposals
COMMON POINTS ON DPR
Sr. No. Description Clarification
3 All distribution pipelines in the BDP area to be deleted
This directive from PMC has resulted in modification of designs , drawings &
estimates in 11 WS zones.
Proposals Modified
WS zone Ward Nos.
Sudatta Sankul 127
Institute ESR 130
Charwad vasti 130
Ujjawal Terrace 129
Agam Mandir-E 144
Agam Mandir-P 144
Mahadev Mandir 141
Kedareshwar-P 140,141
WS ZONES WITH BDP
WS zone Ward nos.
Konark Indraue 121
Warje Malwadi 110
Ram Nagar 111
Atul Nagar 110
Chandani chowk zone -1 61
WS ZONES WITH BDP
COMMON POINTS ON DPR
Sr. No. Description Clarification
4 Reinstatement of roads
PMC had directed one lane to be considered for reinstatement
The Revised cost of reinstatement worked put in the range of Rs. 700
crores. Therefore original proposal of reinstatement of trench width retained
COMMON POINTS ON DPR
Sr. No. Description Clarification
5 Distribution mains to be deleted on private premises
The proposals are modified
COST ESTIMATES
Sr. No. Description Clarification
1 Pipe rates are with central excise. PMC can avail excise exemption. The rates to be modified ?
Rates retained with central excise
2 Distribution system is proposed with K9 pipes for all diameters. Pl. confirm
PMC Confirmed K9 pipes
3 All sluice valves are of DI Pl. confirm
PMC confirmed DI sluice valves
4 The concrete guiniting is proposed as external protection to MS pipes. Option of 3LPE coating
PMC Confirmed CC guiniting
5 Underground type of FH proposed -One per sq.km in dense areas -One per 4sq.kms in Peripheral areas
PMC Confirmed
Design criteria (1/2)
Sr. No. Parameter Unit Description
1 Design Period 30 Years
Base year/Commissioning Year 2017
Intermediate stage 2032
Ultimate stage 2047
2 Net Domestic water allowance Lpcd 150
3 System Losses
Base year-2012 % 35
Year-2017 % 30
Year-2022 % 20
Year-2032 % 15
Design year-2047 % 15
4 Clear water pumping hours Hours 22
5 Stand by pump capacity % 100
6 Hydraulic Retention Time of sumps min 60
7 Peak factor for distribution 2.50
Sr. No. Parameter Unit Description
8 Pipe Material for Pumping main DI up to 450 mm
MS above
9 Pipe Material for Gravity main DI up to 600 mm
MS above
Minimum Diameter of Transmission Mains mm 450
10 Hydraulic Retention Time of BPTs min 10 (only standard capacities =
= 0.5 ML or 1 ML used)
11 Storage capacity of Service Reservoir 8 hours of daily water demand, i.e.
33%
12 Coefficient of Friction-“C”
Ductile Iron-CM lined 140
Mild Steel-CM lined 140
Cast Iron pipes-New (unlined) 100
Cast iron pipes-Old (unlined) 80
13 Terminal pressure in distribution Network m Normal 12m, but not below 10m
Design criteria (2/2)
Summary of Projections of all Methods
Recommended projected population: as per Metro+Wada policy
Population Projections
Year
A B C
Average
(Arithmetical +
Geometrical
Increase)
Growth Rate Metro+Wada
policy
2017 3,602,449 3,660,631 3,918,763
2022 4,063,195 4,205,832 4,430,320
2032 5,173,269 5,467,581 5,771,754
2042 6,614,462 6,834,477 6,939,529
2047 7,497,376 7,381,235 7,375,348
Population Density- 2012
Population Density- 2017
Population Density- 2022
Population Density- 2032
Population Density- 2042
Population Density- 2047
Water Demand
Year
Net Demand (MLD) System
Losses
Gross Demand (MLD)
PMC
Pune
Canton_
ment
Khadki
Canton_
ment
Total PMC
Pune
Canton_
ment
Khadki
Canton_
ment
Total
2017 712.63 12.53 12.06 737.28 30% 1018.14 17.91 17.22 1053.27
2022 926.97 12.53 12.06 951.56 20% 1158.83 15.66 15.07 1189.56
2032 1231.99 12.53 12.06 1256.58 15% 1449.41 14.75 14.18 1478.34
2042 1431.64 12.53 12.06 1456.23 15% 1684.27 14.75 14.18 1713.20
2047 1596.71 12.53 12.06 1621.30 15% 1877.67 14.75 14.18 1906.60
Existing water supply system
Description Transmission system Details
Parvati WTPs
Mutha Right Bank canal Two pipes of 1200mm & 1600mm diam. for drawing water to Stage 1 WTP of 220 MLD
3030mm diam. MS gravity main, up
to receiving chamber of WTP
Gravity supply to Parvati stage 2 WTP of 315 MLD
Cantonment
WTPs
3030mm diam. MS gravity main, up
to receiving chamber of WTP
Raw water pumping to MBR (in the premises of Parvati water works), and further
gravity supply to Pune Cantonment water works for stage 1 WTP of 240 MLD
Mutha Right Bank canal Supply to stage- 2 WTP of 100 MLD capacity
Warje WTPS Jack well at Khadakwasla dam,
1524mm diameter pumping main
- Supply to Warje stage 1 (9 MLD) WTP by 406mm branch;
- 1524mm pumping main for supply to Warje stage 2 WTP of 180 MLD
Holkar WTPs Jack well at Khadakwasla dam,
1524mm diam. pumping main
1000mm branch pumping main for 45 MLD WTP
Vadgaon WTP
stage 1
3030mm diam. MS gravity main, from
Khadakwasla
- 1524 mm branch gravity main
- Raw water PS
- 1524mm diam. pumping main to stage 1 WTP of 125 MLD.
Chikhali WTP Jack well at Ravet on Pavana river 711mm diam. pumping main to Chikhali WTP
Sources •Khadkwasla Dam - Allocation 16 TMC - 1242 MLD •Pavana River - 30 MLD, through Chikhali WTP
Raw water Transmission
Existing water supply system
Water Treatment Plants
Sr No NAME - LOCATION
CAPACITY in MLD
Existing Under
construction Total
1 Chikhali-(Pavana River) 29 29
2 Holkar 45 45
3
Cantonment Old 260 260
Cantonment New 100 100
Sub Total Cantonment 360 360
4
Parvati Old (line 1) 220 220
Parvati New (line 2) 315 315
Sub Total Parvati 535 535
5 Vadgaon stage 1 125 125
6
Warje Old 9 9
Warje New 186 186
Warje stage 3 200 200
Sub Total Warje 195 200 395
TOTAL 1289 200 1489
Name Sump in ML Pumping destinations
Parvati PH No.1 19.0 Parvati LLR, Parvati MLRs, Parvati HLRS
Parvati PH No.2 12.0 SNDT, Parvati HLRs
Parvati PH No.3 SNDT, Parvati HLRs
Cantonment Old WTP Pump
Station
9.00 Bakri Hill, Wanorie ESR, Wanorie HLRs,
Race course ESR, Thakarsi Hill SRs
Cantonment New WTP PH 4.20 Ram Tekdai, Kharadi ESRs
Warje 180 MLD WTP PH 4.20 Gandhi bhavan GSR, Chandani chowk GSR,
SNDT
Vadgaon 125 MLD WTP PH 4.80 Taljai HLRs, Washout ESR, Institute ESR
Holkar 45 MLD WTP PH 2.0 Vidyanagar sump
Padmavati Pump Station 8.0 Bibvewadi GSRs, Taljai MLR, Seminary GSR
SNDT MLR Pump Station 11.35 SNDT HLR
Vidyanagar Pump Station 1.0 Vidyanagar ESR, Viman nagar ESRs,
Dhanori ESR, Kalwad, Kalas
Rajeev Gandhi Udyan Pump Station 1.60 Kedareshwar GSR, Shreehari ESR
Katraj Pump Station 0.35 Agam Mandir GSR
(minor pump stations & boosters) - various
Existing water supply system
Pump Stations
Clear water transmission
Clear water transmission mains Total Length – 247,989 m
Complicated existing system:
• Transmission and distribution often mixed (e.g. many direct tappings in transmission mains)
• WTP systems often mixed (e.g. mixing between Warje water and Parvati water at SNDT HLR,
mixing between Holkar water and Chikhali water at Vidya Nagar ESR, mixing between Holkar
transmission and Cantonment distribution at 509 chowk, …)
• Only few flowmeters, often not working (e.g. SNDT MLR pump station, Katraj pump station, …)
All these add to the difficulty in management and control of the system (e.g. impossible to assess losses)
Summary of existing Service Reservoirs
WTP SUPPLY AREA
Total Storage
Capacity
(ML)
No. of
existing SRs
No. of
GSRs
No. of
ESRs
PARVATI 98.39 18 15 3
CANTONMENT 95.95 31 14 17
VADGAON 29.93 26 13 13
WARJE 91.60 20 18 2
HOLKAR 8.47 7 0 7
CHIKHALI 4.0 1 0 1
Total of PMC 328.34 103 60 43
Note: out of 103 existing SRs only 83 are currently in operation
Distribution System
Material Diameters in mm Length in km
Asbestos cement 80 to 300 15.465
Cast Iron 75 to 1000 2335.50
RCC 450 7.33
Ductile Iron 50 to 600 189.66
Galvanized Iron 25 to 100 34.39
Mild Steel 100 to 1524 91.35
Prestressed concrete 500 to 1600 6.70
PVC 63 to 250 8.13
Total 2688.525
Material Diameters in mm Length in km
Asbestos cement 80 to 300 15.47
Cast Iron 75 to 1000 2335.50
RCC 450 7.33
Ductile Iron 50 to 600 189.66
Galvanized Iron 25 to 100 34.39
Mild Steel 100 to 1524 91.35
Prestressed concrete 500 to 1600 6.70
PVC 63 to 250 8.13
Total 2688.53
Summary of Existing distribution system
House Service connections
Registered connections
Total Number Domestic Non domestic Stand posts
149,360 134,017
(22,218 metered)
13,993
All metered 1,300
Connections by size
Diameter Metered
domestic
Metered
Non -domestic Stand Posts
15 mm 19,887 844 650
20 mm 1,213 12,211 650
25 mm 681 624
40 mm 169 122
50 mm 128 105
80 mm 73 37
100 mm 34 30
150 mm 22 14
200 mm 4 4
250 mm 5 1
300 mm 2 1
Totals 22,218 13,993 1,300
Problem of not registered Connections Household survey is required as first step for
regularization and metering program
Problems of Metering management Irregular readings
30% are not working
Complaints by users for measurement of air flow
• Intermittent supply-wide variation of supply hours
• Quantity of per capita supply varies substantially, very low in North of Mula-Mutha
River
• Distribution network very old in many areas-high physical losses
• High level of Non Revenue Water
• Inadequate storage capacity
• Reservoirs working as distribution reservoirs, and also feeding other SRs using
distribution mains
• Fast depletion of reservoirs, resulting in high peak factors and small number of
supply hours
Assessment of existing water supply
On Going Projects (1/2)
Component Description
A. Under Construction
Raw water pumping main
Khadakwasla to Parvati
2500mm MS - 11.70 km
Raw water Pump station for New
Warje WTP of 200 MLD
Jack well No.2
Raw water pumps
Raw water pumping main - 1626mm, L = 8.60 km
New Warje WTP - 200 MLD Conventional process Treatment
New Warje clear water pump
station
Sump - 10 ML and PH
On Going Projects (2/2)
Component Description
B. Planned
Raw water pump station for
Parvati
Jack well and PH No.3
Raw water pumps
New water treatment plant at
Parvati-500 MLD
Conventional process Treatment
New Clear water pump station for
500 MLD plant
Sump - 18 ML and PH
Pumps for Pune Cantonment
Raw water pump station for New
Vadgaon WTP
Sump - 8.53 ML
Raw water pumps
Raw water pumping main for for
New Vadgaon WTP
2000mm dia. MS
New Vadgaon WTP-125 mld Conventional process Treatment
New clear water pump station for
Vadgaon
Sump - 11 ML - and PH
Raw water intake and pump
station for Bhama – Askhed
project
Intake well
Jack well and PH
Raw water pumps
Raw water pumping main 1700mm MS - 8.31 km
Water treatment plant -200 MLD
at Alandi road
Conventional process Treatment
MBR
Clear water Transmission system 1600mm diam. gravity main - 16.5 km and feeder mains to ESRs
Water supply sources
Additional supply of 85 MLD (increased up to 285 MLD) is considered from Bhama-Askhed, and remaining from the Khadakwasla system
Proposed water supply system
Source Water Allocation in TMC/y Water Allocation in MLD
Khadakwasla 16 1242
Bhama-Askhed 2.58 200
Pavna 0.30 22
Total 18.88 1464
Water Demand in 2032 19.05 1478
Deficit in 2032 0.18 14
Water Demand in 2047 24.57 1906
Deficit in 2047 6.00 443
THE WTP CAPACITIES AND DEMANDS
Supply
Zone
NO.
LOCATION
CAPACITY IN MLD WTP CAPACITY DEMAND
Existing
Under
construc
tion
To be
re-
placed
To be
built in
Stage 1
To be
built in
Stage 2
Year
2032
Year
2047
Year
2032
Year
2047
1 Chikhali / Bhama Askhed (Pavana) 29 200 85 200+29 285+29 214.68 306.54
2 Holkar 45 45 45 31.19 33.01
3
Cantonment-stage 1 260
70.8** 357.47 Cantonment stage 2 (**) 100 100 100
Cantonment stage 3 300 300
Sub Total Cantonment 360 300 100 400
4
Parvati stage 1 220 220
456.25 390.73 Parvati stage 2 315 315
Parvati stage 3 500 500 500
Sub Total Parvati 535 535 500 500 500
5
Vadgaon stage 1 125 12 137 137
277.45 356.71 Vadgaon stage 2 125 125 125
Vadgaon stage 3 * 125 125 125
Sub Total Vadgaon 125 262 387 387
6
Warje stage 1 9 9 9
428.49 461.96 Warje stage 2 186 186 186
Warje stage 3 200 200 200
Sub Total Warje 195 200 395 395
TOTAL PMC 1289 200 535 962 385 1656 2041 1478.9 1906.4
Note (*) Vadgaon Stage 3 should be built before 2026
Note (**) Supply to Cantonmnet area shall come from Parvati WTP up to 2032, until Future 300 MLD WTP is
constructed. Bhama Askhed stage 2 is increased up to 285 MLD capacity.
WTP supply zones – 2032
WTP supply zones – 2047
Zone wise distribution of demand (MLD)
CRITERIA FOR UPGRADING /REHABILITATION OF WTPs
• WTPs proposed for Rehabilitation: – Warje 180 Mld WTP
– Cantonment 100 MLd New WTP
– Holkar WTP
• Improved treatment process through monitoring and control of: – Water flow-rate monitoring with recording at WTP inlet and outlet
– Monitoring of turbidity and pH for: 1) raw water, 2) settled water, and 3) treated water
– Control of PAC dosage with dosing pumps for alum/PAC.
– Monitoring of filtration cycle with differential pressure gauges for each filter unit
– Measurement of the backwash water flow and the pressure & velocity air flow
– Upgraded chlorinator equipment for pre and post chlorination served by dedicated motive water booster pumps
– Measurement of chlorine content, both in pre- and in post-chlorination, by specific sensors and with alarms for high or low residual chlorine
Rehabilitation of Existing WTPs (1/2)
• Upgrading of chlorination facilities: – Closure of Chlorine storage area, and provision of gas leakage detection and air extractor connected
with neutralization tower
– Gas leakage detection and air extractor also in the chlorination room
– Safety equipment in a cabinet located outside the room
• Recirculation of Filter backwash water by: – Piping for backwash water collection to settling tank
– Backwash settling tank
– Recirculation pumps & piping to WTP inlet unit
• SCADA for continuous monitoring and recording of WTP operation
Rehabilitation of Existing WTPs (2/2)
Rehabilitation of Existing SRs
RESULTS OF DIAGNOSTIC OF EXISTING RESERVOIRS
TOTAL NUMBER OF SRs CONSIDERED
RESERVOIR CONDITIONS
GOOD FAIR POOR To be
reconstructed To be abandoned
(small size) No works needed Local repairs Extensive Rehab.
103 25 20 16 18 24
SR rehabilitation
Bakari Hill GSR - Ladder
SR rehabilitation
Maharashtra Housing Board ESR 1 - Handrail
SR rehabilitation
Thakarsi ESR 3 - Wall
SR rehabilitation
Maharashtra Housing Board ESR 1 – Top Slab
SR rehabilitation
Parvati Old MLR – Top Slab
SR rehabilitation
Parvati HLR – Top Slab
Reservoirs in Good conditions
SR. No. ZONE NAME SR Name Type of SR
(ESR/GSR)
SR Capacity
Extng. (ML)
1 Parvati – HLR 1 Parvati -HLR1 GSR 4.50
2 Waghjai Existing Waghjai Existing GSR GSR 1.00
3 Atul Nagar Warje Old WTP Pure Water Sump GSR 2.30
4 Karve Nagar Warje WTP GSR (U.C.) GSR 12.00
5 Gandhibhavan Zone 1 Gandhibhavan Old GSR GSR 6.40
6 Gandhibhavan Zone 2 Gandhibhavan New GSR GSR 6.40
7 ChandaniChowk Zone 2 ChandaniChowk New GSR GSR 8.50
8 Baner Hill SUS New GSR GSR 3.50
9 BanerGaon Zone 1 Pancard Club GSR GSR 5.00
10 Ganesh Khind/Aundh Chaturshringi GSR Under
Construction GSR 6.50
11 Hadapsar Industrial Colony Ram Tekdi tendered GSR GSR 6.00
12 Indraprastha Indraprashta ESR ESR 1.25
13 Satavwadi TukaiTekdi New GSR GSR 4.00
14 Bakari Hill Zone 1 Bakari Hill Old GSR GSR 6.00
15 Bakari Hill Zone 2 Bakari Hill New GSR (U.C.) GSR 6.00
16 Kharadi Zone 1 Kharadi ESR Under Construction ESR 2.50
17 Kharadi Zone 2 Kharadi Existing ESR ESR 2.50
18 Shastri Nagar MHB existing ESR 2 (1 ML) ESR 1.00
19 Digambar Nagar Tempo Chowk ESR 1 ESR 1.50
20 Tempo Chowk Tempo Chowk ESR 2 ESR 1.50
21 SundrabaiMarathe SundrabaiMarathe ESR ESR 1.60
22 Taljai HLR- Existing And New Taljai New HLR GSR 6.00
23 Shrihari Shrihari ESR ESR 1.00
24 Kedareshwar Existing Kedareshwar Existing GSR GSR 10.00
25 Seminary Existing Seminary Existing GSR GSR 7.00
Reservoirs in Fair conditions
SR. No. SR Name Type of SR
(ESR/GSR)
SR Capacity
Extng. (ML)
1 Parvati -HLR4 GSR 1.00
2 Parvati -MLR 5 ML GSR 5.00
3 Kumbharwadi GSR GSR 1.25
4 ChandaniChowk Old GSR GSR 8.50
5 SUS Old GSR GSR 4.50
6 Chatushringi Old GSR GSR 4.50
7 Ram Tekdi existing GSR GSR 9.00
8 Chandan Nagar ESR 1 (3.5 ML) ESR 3.50
9 Chandan Nagar ESR 3 (1.5 ML) ESR 1.50
10 Dhanori Existing ESR ESR 1.00
11 B U Bhandari ESR ESR 1.50
12 Viman Nagar existing ESR1 (2.5 ML) ESR 2.50
13 Viman Nagar existing ESR2 (1 ML) ESR 1.00
14 Thakarsi Existing ESR 3 ESR 2.60
15 Institute Existing ESR ESR 1.00
16 Taljai Old HLR GSR 6.26
17 AgamMandir Existing ESR ESR 1.00
18 Dhankavadi GSR GSR 0.75
19 Bibvewadi old GSR GSR 3.40
20 VADGAON WTP ESR * ESR 2.00
Reservoirs in Poor conditions
SR. No. SR Name Type of SR
(ESR/GSR)
SR Capacity
Extng. (ML)
1 Parvati -HLR2 GSR 4.50
2 Parvati -HLR3 GSR 4.50
3 Parvati -MLR 13 ML GSR 13.16
4 SNDT Existing HLR GSR 13.16
5 SNDT MLR GSR 11.35
6 Chatushringi New GSR GSR 8.40
7 Wanori HLR Circular GSR 5.45
8 WANORI ESR SMALL ESR 2.45
9 WANORI MLR RECTANGULAR GSR 4.45
10 Chandan Nagar ESR 2 (2.2 ML) ESR 2.20
11 Vidya Nagar ESR ESR 1.60
12 MHB existing ESR 1 (2 ML) ESR 2.00
13 Taljai MLR 1 GSR 3.40
14 Taljai MLR 2 GSR 3.40
15 Bibvewadi new GSR GSR 3.40
16 CHIKHALI MBR ESR 4.00
Reservoirs to be reconstructed on the same site
Sr No NAME Comments
Capacity
(ML)
1 Swargate Police Line ESR 1 Not in Use
2 Swargate Police Line ESR 2 Not in Use
3 Swargate Police Line Sump Not in Use
4 AHIRE GAON GSR In operation 0.05
5 RAMNAGAR ESR In operation 0.04
6 DUKKARKHIND GSR Not in Use 0.35
7 Pune University GSR Not in Use
8 Mafco GSR 1 Not in Use
9 Mafco GSR 2 Not in Use
10 FC GSR 1 Not in Use
11 FC GSR 2 Not in Use
12 FC GSR 3 Not in Use
13 TUKAI TEKDI OLD 2 In operation 0.10
14 TUKAI TEKDI OLD 1 In operation 0.30
15 JAL MANDIR GSR (Note 1) In operation 17.00
16 Kusmade Wasti ESR (Reconstruct) Not in Use
17 THAKARSI SR 2 In operation 2.50
18 THAKARSI SR 3 In operation 2.50
19 Tarode Wasti GSR 1 (Reconstruct) Not in Use
20 Tarode Wasti GSR 2 (Reconstruct) Not in Use
Reservoirs to be decommissioned
Sr. No. NAME Current WTP Zone CAPACITY (ML)
1 WANORI ESR Cantonment 2.45
2 RACE COURSE ESR Cantonment 1.8
3 UPPER INDIRA NAGAR ESR Parvati 0.45
4 SOMJAI ESR Vadgaon 0.1
5 RAJAS SOCIETY, CIRCULAR Vadgaon 0.1
6 RAJAS SOCIETY, RECTANGULAR Vadgaon 0.15
7 SANTOSH NAGAR GSR Vadgaon 0.25
8 CHARWAD WASTI ESR Vadgaon 0.15
9 MANAS SROVAR ESR Vadgaon 0.1
10 GOKUL NAGAR ESR Vadgaon 0.15
11 KAMBLE WASTI GSR Vadgaon 0.1
12 DALVI WADI ESR Vadgaon 0.1
13 SUTARDARA GSR Warje 0.3
Repairs of reservoirs in fair conditions
TYPICAL PROBLEMS PROPOSED INTERVENTIONS
Local spalling of RCC, with
exposed bars
Repair with cement mortar plaster – protection of tank surfaces
with epoxy based paint
Damaged aeration structures Reconstruct the structure
Local leakages signs on lateral
walls of tank
Injection with special bi-components sealing and replacement of
cracked internal plaster
Helicoidal Stars damaged steps
and parapet
Repairs with cement plaster
Corroded stairs, ladders and
handrails
Replacement stairs/ladders with aluminium alloy
Replacement of hand rails with zinc coated steel
Damaged walkways at bottom of
ESR tanks
Repair with cement plaster
Rehabilitation of reservoirs in poor conditions
TYPICAL PROBLEMS PROPOSED INTERVENTIONS
Extended spalling of concrete,
with severe erosion of bars in
the top slab
Removal and reconstruction of top slabs and, in some cases of the
internal columns
Sagging of SR top slabs As per item above
Several cracks and leakages
signs on the lateral walls
Sealing with injections with special mixes.
Removal & reconstruction of the plaster in all internal surfaces of
tank
Protective paint epoxy based
Extensive cracking or separation
of plaster in internal surfaces of
tank and on internal columns
As per item above
Corroded stairs, ladders and
hand rails
Replacement stairs/ladders with aluminium alloy
Replacement of hand rails with zinc coated steel
Damaged walkways at bottom of
ESR tanks
Reconstruction of damaged parts of walkways
Formation of water supply zones
Existing Service Reservoirs • Maximum utilisation of the storage capacity • Identification of areas compatible to hydraulic levels • Ensure terminal pressure of 12m • Select water supply zone which maximises the use of trunk distribution mains
Proposed Service reservoirs • Prospective reservoirs are identified after study of limitations of existing service reservoirs, in terms of
location, capacity and hydraulic levels • The list of such locations was prepared and discussed with PMC • The joint site visits have been conducted, for confirming availability and precise site location • The locations jointly agreed are considered for proposals • Final selection by consultants to optimize the zone formation
Other Guidelines • Zone formation based on geographical location, ground elevation and maximum travel • Nalla as zone limit • Major roads as zone limit • Major physical barriers as zone limits, such as River, Canal, Railway line, Expressway etc. • To avoid major undulations
City divided in 141 water supply zones
Pune city water zones summary
Sr. No. Water Supply Zone Water supply in MLD
Water Zones (2032)
DMA (2032)
2032 2047 Nos. Nos.
1 Parvati 212.46 280.36 12 31
2 Pune Cantonment 260.2 357.47 25 58
3 Vadgaon 277.45 356.71 32 85
4 Warje 428.49 461.96 34 98
5 Holkar 31.19 33.01 1 3
6 Bhama-Askhed 214.68 306.56 37 53
Total 1478.93 1906.42 141 328
SR. No. Zone Name
Existing (Count)
Proposed (Count)
Existing Capacity (ML)
Proposed Capacity (ML)
Total Capacity
(ML)
ESR GSR ESR GSR ESR GSR ESR GSR ESR+GSR
1 Parvati - - - 7 9 3 - - - 33.66 33.00 29.50 96.16
2 Warje old - - - 1 1 - - - - - - 2.30 1.00 - - - 3.30
3 Warje New - - - 14 14 6 - - - 99.96 42.50 40.50 182.96
4 Cantonment 6 6 14 1 13.45 36.45 50.00 32.00 131.9
5 Bhama Askhed 12 - - - 28 - - - 17.94 - - - 69.50 - - - 87.44
6 Vadgaon 3 9 15 10 3.00 43.61 39.00 40.00 125.61
7 Holkar - - - - - - 2 - - - - - - - - - 7.00 - - - 7
Total 21 37 83 20 34.39 215.98 242.00 142.00 634.37
SUMMARY OF SERVICE RESERVOIRS PLANNED TO BE USED FOR YEAR 2047
Detailed Summary of Water
Supply Zones & Reservoirs SR. No. Zone Name SR Name
SRs Existing/ Proposed
Type of SR
Demand (2032)
Population (2047)
Demand (2047)
SR Capacity Existing
SR Capacity Proposed
LDL FSL
E/P ESR/GSR MLD MLD ML ML m m
Parvati
1 Parvati -HLR1 Parvati -HLR1 E GSR 9.51 47228 12.99 4.50 622.10 627.28
2 Parvati -HLR 2&3 Parvati -HLR2 E GSR
16.61 93547 27.06 4.50 621.28 627.28
Parvati -HLR3 E GSR 4.50 621.28 627.28
3 Parvati -HLR4 Parvati -HLR4 E GSR 2.90 14946 2.94 1.00 618.00 622.00
4 Parvati -MLRs Zone 2 Parvati -MLR 5 ML E GSR
46.50 237802 63.61 5.00 591.86 597.86
Parvati -MLR 17 ML P GSR 17.00 591.86 598.36
5 Parvati -MLR Zone 1 Parvati -MLR 13 ML E GSR
51.87 250665 66.86 13.16 593.17 598.35
Parvati -MLR 10 ML P GSR 10.00 593.17 599.67
6 Waghjai Existing Waghjai Existing GSR E GSR 3.17 17942 3.17 1.00 619.00 622.00
7 Waghjai Proposed Waghjai Proposed GSR P GSR 5.79 20541 7.09 2.50 620.15 626.15
8 Parvati WTP Rohan Kirtiki ESR 1 P ESR 8.42 43002 10.64 3.50 588.00 594.00
9 P L Deshpande Garden Rohan Kirtiki ESR 2 P ESR 11.60 59289 14.67 4.50 584.00 590.00
10 Saras Baugh
Swargate Police Line Proposed ESR 1
P ESR
17.98 71018 20.90
3.50 590.00 596.10
Swargate Police Line Proposed ESR 2
P ESR 3.50 590.00 596.10
11 Shaniwarwada
Swargate WW ESR 1 P ESR
24.48 117527 33.44
4.00 589.00 595.00
Swargate WW ESR 2 P ESR 4.00 589.00 595.00
Swargate WW ESR 3 P ESR 4.00 589.00 595.00
12 Crescent High School
Crescent High School ESR 1 P ESR
13.63 61696 16.99
3.00 608.50 614.50
Crescent High School ESR 2 P ESR 3.00 608.50 614.50
Detailed Summary of Water
Supply Zones & Reservoirs SR. No. Zone Name SR Name
SRs Existing/ Proposed
Type of SR Demand (2032)
Population (2047)
Demand (2047)
SR Capacity Existing
SR Capacity Proposed
LDL FSL
E/P ESR/GSR MLD MLD ML ML m m
Warje old
13 Ahire Gaon Ahire Gaon ESR (Reconstruct)
P ESR 1.98 12344 2.91 1.00 605.00 611.00
14 Warje Malwadi Warje Old WTP Pure Water Sump
E GSR 2.29 12042 2.87
2.30
624.90 628.00 15 Atul Nagar 5.02 33114 6.30
Warje New
16 Ramnagar Ramnagar ESR (Reconstruct)
P ESR 4.69 28072 5.11 2.00 611.00 617.00
17 Dukkarkhind Dukkarkhind ESR (Reconstruct)
P ESR 5.26 25657 6.60 2.50 616.00 622.50
18 Kumbharwadi Kumbharwadi GSR E GSR 2.71 13861 3.96 1.25 593.30 598.30
19 Karve Nagar Warje WTP GSR (U.C.) E GSR 26.75 141442 36.11 12.00 591.00 597.00
20 Gandhibhavan Zone 1 Gandhibhavan Old GSR E GSR 15.52 83262 19.87 6.40 636.00 641.00
21 Gandhibhavan Zone 2 Gandhibhavan New GSR E GSR 13.16 63651 19.93 6.40 636.00 641.00
22 Chandani Chowk Zone 1 Chandani Chowk Old GSR E GSR 18.53 115819 25.82 8.50 665.00 670.00
23 Chandani Chowk Zone 2 Chandani Chowk New GSR E GSR
42.58 206703 52.53 8.50 657.07 665.07
Chandani Chowk Proposed GSR
P GSR 9.00 657.07 665.07
24 Ideal Colony / MIT College SNDT Proposed HLR P GSR 11.25 60158 13.73 4.50 617.00 623.00
25 Pune University - 4.30 5.88
26 Wakdewadi Khairewasti ESR 1 P ESR
24.23 69346 26.49 4.00 582.00 588.00
Khairewasti ESR 2 P ESR 4.00 582.00 588.00
27 Pashan Lake Pashan Proposed ESR 1 P ESR
13.38 84392 17.63 3.00 600.44 606.44
Pashan Proposed ESR 2 P ESR 3.00 600.44 606.44
28 Sus Sutarwadi SUS Old GSR E GSR 11.92 72843 13.77 4.50 653.00 657.00 29 Baner Hill SUS New GSR E GSR 5.39 49096 10.03 3.50 654.10 660.10 30 Baner Gaon Zone 1 Pancard Club GSR E GSR 8.02 71228 14.65 5.00 598.00 605.50
Detailed Summary of Water
Supply Zones & Reservoirs SR. No. Zone Name SR Name
SRs Existing/ Proposed
Type of SR Demand (2032)
Population (2047)
Demand (2047)
SR Capacity Existing
SR Capacity Proposed
LDL FSL
E/P ESR/GSR MLD MLD ML ML m m
Warje New
31 Baner Gaon Zone 2 Pashan Baner Link Road ESR P ESR 4.95 44670 8.78 3.00 595.20 601.20
32 Balewadi Balewadi Jakat Naka ESR 1 P ESR
8.83 81827 16.46 3.00 590.00 596.00
Balewadi Jakat Naka ESR 2 P ESR 2.50 590.00 596.00
33 Baner West Green Zone Baner ESR P ESR 5.54 42550 10.00 3.50 615.00 621.00
34 Ram Nagar/ Laxman Nagar Sun Horizon ESR P ESR 7.01 55642 12.68 4.50 589.00 595.00
35 Panchavati Panchvati GSR P GSR 3.11 24136 5.71 2.00 641.00 647.00 36 SNDT HLR SNDT Existing HLR E GSR 34.24 133791 38.71 13.16 620.00 625.46 37 SNDT MLR SNDT MLR E GSR 28.85 106308 33.89 11.35 591.33 596.83
38 Bhosale Nagar Pune University GSR (Reconstruct) P GSR 15.20 64620 18.35 6.00 603.00 611.00
39 Gokhale Nagar Mafco Proposed GSR (Reconstruct)
P GSR 12.29 71039 17.85 6.00 610.30 616.80
40 Chatushrungi Temple Asha Nagar ESR P ESR 5.61 28607 6.19 2.00 618.00 625.00
41 BMCC College FC Proposed ESR 1 (Reconstruct) P ESR 4.39 15920 5.12 2.00 595.00 601.00
42 Modern College FC Proposed GSR (Reconstruct) P GSR 32.70 118685 38.17 13.00 586.00 592.50
43 Fergusson College FC ESR 2 P ESR 7.26 36412 9.83 3.50 600.00 606.00
44 Chatushrungi Zone 1 Chatushringi Old GSR E GSR 8.33 37807 12.97 4.50 604.38 608.38
45 Chatushrungi Zone 2 Chatushringi New GSR E GSR 20.33 127449 34.30 8.40 604.38 608.38
46 Ganesh Khind/Aundh Chaturshringi GSR Under Construction
E GSR 12.87 70194 19.14 6.50 601.88 606.88
Detailed Summary of Water
Supply Zones & Reservoirs SR. No. Zone Name SR Name
SRs Existing/ Proposed
Type of SR Demand (2032)
Population (2047)
Demand (2047)
SR Capacity Existing
SR Capacity Proposed
LDL FSL
E/P ESR/GSR MLD MLD ML ML m m
Cantonment
47 Ram Tekdi Ram Tekdi existing GSR E GSR 22.32 71465 27.93 9.00 642.00 646.00
48 Hadapsar Industrial Colony Ram Tekdi tendered GSR E GSR 14.35 58820 18.30 6.00 638.00 646.00
49 Magarpatta - P GSR 10.21 87711 15.89
50 Indraprastha Indraprashta ESR E ESR 2.41 12772 3.76 1.25 592.70 596.70
51 Satavwadi Tukai Tekdi New GSR E GSR 8.26 44513 11.19 4.00 610.70 616.70
52 Gliding Centre Tukai Tekdi ESR (Reconstruct) P ESR 9.85 47610 10.88 3.50 611.00 617.00
53 Akashwani Anand Nagar ESR1 P ESR
13.76 85694 20.84 3.50 589.00 595.00
Anand Nagar ESR2 P ESR 3.50 589.00 595.00
54 Sadhana Vidyalaya Anand Nagar ESR3 P ESR 9.07 56529 13.75 4.50 585.00 591.00
55 Hadapsar Gaon Hadapsar Bus Depot ESR P ESR 9.40 58541 14.24 4.50 587.00 593.00
56 Bakari Hill Zone 1 Bakari Hill Old GSR E GSR 13.07 62145 15.97 6.00 639.50 644.00
57 Bakari Hill Zone 2 Bakari Hill New GSR (U.C.) E GSR 13.60 64636 16.61 6.00 639.12 643.62
58 Kale Borate Nagar Selen Park ESR P ESR 6.47 28953 7.03 2.50 612.40 618.40
59 Badade Mala Bhujbal Scheme ESR P ESR 7.68 49590 9.70 3.50 615.54 621.54
60 Koregaon Park Cantonment WTP ESR 1 P ESR
16.31 85735 21.22 3.50 583.00 589.00
Cantonment WTP ESR 2 P ESR 3.50 583.00 589.00
Detailed Summary of Water
Supply Zones & Reservoirs SR. No. Zone Name SR Name
SRs Existing/ Proposed
Type of SR
Demand (2032)
Population (2047)
Demand (2047)
SR Capacity Existing
SR Capacity Proposed
LDL FSL
E/P ESR/GSR MLD MLD ML ML m m
Cantonment
61 Jalmandir Cantonment Jalmandir GSR (Reconstruct)
P GSR 60.91 184766 92.67 32.00 575.00 580.55
62 Ghorpadi Wanori HLR Circular E GSR 11.37 77494 13.97 5.45 607.13 612.80
63 Mundhwa Gaon Zone 1 Ghorpadi Sicilia ESR 1 P ESR 7.75 74184 13.59 4.50 580.54 587.04
64 Mundhwa Gaon Zone 2
Ghorpadi Sicilia ESR 2 P ESR
8.66 82864 15.18
2.50 580.54 587.04
Ghorpadi Sicilia ESR 3 P ESR 2.50 580.54 587.04
65 Kharadi Zone 1 Kharadi ESR Under Construction
E ESR 5.74 27022 6.43 2.50 583.63 588.63
66 Kharadi Zone 2 Kharadi Existing ESR E ESR 7.46 29999 7.84 2.50 583.63 588.63
67 Kharadi Zone 3/ Khulewadi Kharadi Proposed ESR P ESR 12.77 50084 13.86 4.50 588.00 594.00
68 Kharadi Bypass Kharadi bypass ESR P ESR 8.18 36853 10.44 3.50 578.00 584.00
69 Wadgaon Sheri Zone 4 Chandan Nagar ESR 1 (3.5 ML)
E ESR 9.71 45425 9.99 3.50 578.00 583.50
70 Chandan Nagar Zone 1 Chandan Nagar ESR 3 (1.5 ML)
E ESR 4.28 18748 4.53 1.50 590.82 595.82
71 Chandan Nagar Zone 2 Chandan Nagar ESR 2 (2.2 ML)
E ESR 6.32 24867 6.69 2.20 584.30 588.80
Detailed Summary of Water
Supply Zones & Reservoirs SR. No. Zone Name SR Name
SRs Existing/ Proposed
Type of SR Demand (2032)
Population (2047)
Demand (2047)
SR Capacity Existing
SR Capacity Proposed
LDL FSL
E/P ESR/GSR MLD MLD ML ML m m
Bhama Askhed
72 Undevelop Area Dhanori Dhanori Undeveloped Area ESR P ESR 4.70 38906 8.72 3.00 631.00 637.00
73 Dhanori Zone 1 Dhanori Proposed ESR 2 P ESR 3.23 21452 4.20 2.00 609.63 615.63
74 Dhanori Zone 2 Dhanori Existing ESR E ESR 2.46 15035 3.20 1.00 605.50 610.50
75 Gokul Nagar Dhanori Proposed ESR 1 P ESR 5.55 33598 6.32 2.50 610.00 616.00
76 Munjaba wasti Munjaba Wasti ESR P ESR 4.58 30279 5.88 2.00 603.59 609.59
77 Lohegaon Lake Zone 1 Dhanori Proposed ESR 3 P ESR 3.16 17455 4.66 2.00 610.00 616.00
78 Lohegaon Lake Zone 2 B U Bhandari ESR E ESR 2.30 28146 3.39 1.50 613.00 618.00
79 Ganesh Nagar - NA NA 1.15 6177 1.15 NA
80 Mhaske Wasti Mhaske Wasti ESR E ESR 0.45 2414 0.45 0.14 578.00 582.00
81 Kusmade Wasti Kusmade Wasti ESR (Reconstruct)
P ESR 2.86 14908 2.95 0.73 570.00 576.00
82 Vishrantwadi Vishrantwadi ESR 1 P ESR
10.26 56784 11.12 2.00 578.00 584.00
Vishrantwadi ESR 2 P ESR 2.00 578.00 584.00
83 Gurudwara Wasti Haran Tala ESR 1 P ESR
5.79 55406 9.93 2.00 616.00 622.00
Haran Tala ESR 2 P ESR 1.50 616.00 622.00
84 Tingre Nagar Tingre Nagar ESR P ESR 3.08 16516 3.08 2.00 581.00 587.00
85 Vidya Nagar Vidya Nagar ESR E ESR 4.04 24057 4.57 1.60 586.37 591.37
86 MHB Zone 1 MHB existing ESR 1 (2 ML) E ESR 5.66 18174 6.20 2.00 586.00 591.00
87 MHB Zone 2 MHB Proposed ESR P ESR 7.81 29066 8.56 3.00 581.00 587.00
88 Shastri Nagar MHB existing ESR 2 (1 ML) E ESR 3.00 12077 3.29 1.00 588.00 593.00
Detailed Summary of Water
Supply Zones & Reservoirs SR. No. Zone Name SR Name
SRs Existing/ Proposed
Type of SR Demand (2032)
Population (2047)
Demand (2047)
SR Capacity Existing
SR Capacity Proposed
LDL FSL
E/P ESR/GSR MLD MLD ML ML m m
Bhama Askhed
89 Wadgaon Sheri Zone 1 Wadgaon Sheri Proposed ESR 1 P ESR 7.31 31357 7.63 2.50 581.00 587.00
90 Wadgaon Sheri Zone 2 Bishop School ESR 1 P ESR 8.53 38717 10.00 3.50 575.00 581.00
91 Wadgaon Sheri Zone 3 Wadgaon Sheri Proposed ESR 2&3
P ESR 7.70 32439 8.08
2.00 587.00 593.00
P ESR 2.00 587.00 593.00
92 Wadgaon Sheri Zone 5 Bishop School ESR 2 P ESR 6.32 34592 7.41 2.50 575.00 581.00
93 Sanjay Park Zone 1 Vegetable Market ESR 1 P ESR 12.76 52472 13.49 4.50 600.00 606.00
94 Sanjay Park Zone 2 Vegetable Market ESR 2 P ESR 12.24 56787 12.93 4.50 600.00 606.00
95 Viman Nagar Zone 1 (2.50 ML) Viman Nagar existing ESR1 (2.5 ML)
E ESR 7.76 30442 7.98 2.50 589.00 592.00
96 Viman Nagar Zone 2 (1.00 ML) Viman Nagar existing ESR2 (1 ML)
E ESR 3.37 8556 3.44 1.00 590.00 594.00
97 Viman Nagar Zone 3 Viman Nagar Proposed ESR P ESR 8.83 26435 9.35 3.00 588.00 594.00
98 Commerzone IT Park Yerwada Thakarsi ESR 1 (Reconstruct 2.5 to 3.5 ML)
P ESR 9.33 29397 10.59 3.50 582.22 588.22
99 Sangamwadi Sangamwadi ESR P ESR 7.70 42212 7.90 3.00 572.00 578.00
100 Laxmi Nagar/Ram Nagar Thakarsi Proposed ESR 4 P ESR 8.94 49690 9.07 3.00 582.22 588.22
101 Navi Khadki Yerwada K. Bhaurao Patil ESR P ESR 3.73 16394 3.85 1.50 581.00 587.00
102 Kashmiri Colony Thakarsi ESR 2 (Reconstruct 2.5 to 4.0 ML)
P ESR 10.98 51724 11.37 4.00 582.00 588.00
103 Kalyani Nagar Thakarsi Existing ESR 3 E ESR 5.91 18732 6.29 2.60 582.00 588.00
104 Digambar Nagar Tempo Chowk ESR 1 E ESR 3.98 19365 5.84 1.50 578.80 582.80
105 Tempo Chowk Tempo Chowk ESR 2 E ESR 3.72 19349 3.84 1.50 578.80 582.80
106 Sundrabai Marathe Sundrabai Marathe ESR E ESR 4.54 20163 5.13 1.60 588.43 592.80
107 Sainath Nagar Sainath Nagar ESR P ESR 5.00 25275 5.76 2.00 568.00 574.00
108 Bhange Wasti Bhange Wasti ESR 1 P ESR
5.95 41037 9.14 2.00 576.00 582.00
Bhange Wasti ESR 2 P ESR 1.00 576.00 582.00
Detailed Summary of Water
Supply Zones & Reservoirs SR. No. Zone Name SR Name
SRs Existing/ Proposed
Type of SR Demand (2032)
Population (2047)
Demand (2047)
SR Capacity Existing
SR Capacity Proposed
LDL FSL
E/P ESR/GSR MLD MLD ML ML m m
Vadgaon
109 IHP IHP ESR1 P ESR
13.13 66335 14.22 2.50 585.00 591.00
IHP ESR2 P ESR 2.50 585.00 591.00 110 Paranjpe Layout Paranjpe Layout ESR P ESR 7.80 38610 10.83 4.00 591.00 597.00
111 Venkatesh Serenity Venkatesh Serenity GSR P GSR 6.74 43967 9.83 3.50 608.50 614.50
112 Ujjawal Terrace High Bliss Society ESR P ESR 6.87 47690 9.43 3.50 622.00 628.00
113 Charwad Vasti Institute Proposed ESR P GSR 4.65 23932 4.85 2.00 627.00 633.00
114 WTP Wash Out Proposed Near Vadgaon WTP Washout GSR
P GSR 7.52 39641 7.87 3.00 598.00 604.00
115 Sudatta Sankul Sudatta Sankul ESR P ESR 4.69 24274 5.02 2.00 604.00 609.00 116 Institute ESR Institute Existing ESR E ESR 2.31 3950 2.69 1.00 638.00 642.00 117 Taljai HLR Proposed Taljai Proposed HLR P GSR 9.17 53451 12.53 4.50 682.00 688.00
118 Taljai HLR- Existing And New
Taljai Old HLR E GSR 28.85 124610 35.31
6.26 686.81 693.56 Taljai New HLR E GSR 6.00 686.81 693.56
119 Taljai MLRs- Existing Taljai MLR 1 E GSR
15.07 84337 20.42 3.40 654.13 657.73
Taljai MLR 2 E GSR 3.40 654.13 657.73
120 Agam Mandir Existing Agam Mandir Existing ESR E ESR 2.15 19349 4.06 1.00 748.39 752.39
121 Agam Mandir Proposed Agam Mandir Proposed ESR P GSR 19.44 102977 25.35 9.00 692.00 698.00
122 Mahadev Mandir Mahadev Mandir GSR P GSR 8.76 48184 10.61 3.50 723.60 728.00
123 Shrihari Shrihari ESR E ESR 1.68 11119 3.00 1.00 668.00 672.50
124 Kedareshwar Existing Kedareshwar Existing GSR E GSR 22.10 132856 29.14 10.00 723.00 728.00
125 Kedareshwar-Proposed Kedareshwar Proposed GSR P GSR 9.67 45426 13.70 5.00 723.00 729.00
126 Kondhwa Road Shivneri Nagar ESR P ESR 7.31 43507 9.30 3.50 675.00 681.00
127 Sai Baba Nagar Steel Yard ESR P ESR 12.33 66379 12.68 4.50 682.16 688.16
Detailed Summary of Water
Supply Zones & Reservoirs SR. No. Zone Name SR Name
SRs Existing/ Proposed
Type of SR Demand (2032)
Population (2047)
Demand (2047)
SR Capacity Existing
SR Capacity Proposed
LDL FSL
E/P ESR/GSR MLD MLD ML ML m m
Vadgaon
128 Upper Indira Nagar Upper Indira Nagar Proposed ESR
P ESR 4.55 28053 5.35 2.00 685.00 691.50
129 Shivneri Nagar Shivneri Nagar GSR P GSR 7.87 32602 8.85 3.00 660.00 667.00
130 Market Yard Seminary Proposed GSR P GSR 10.68 44206 12.00 4.00 675.00 681.00
131 Seminary Existing Seminary Existing GSR E GSR 15.56 80201 18.45 7.00 672.00 676.00
132 Konark Indrayu
Konark Indrayu GSR P GSR 6.04
56025
7.29 2.50 648.00 654.00
Konark Indrayu ESR P ESR 3.05 3.68 1.50 660.00 666.00
133 Dashbhuja Mandir Dhankavadi GSR E GSR 0.86 6820 1.34 0.75 680.80 684.30 134 Bibvewadi Zone 1 Bibvewadi old GSR E GSR 6.85 37691 10.43 3.40 654.13 657.73 135 Bibvewadi Zone 2 Bibvewadi new GSR E GSR 7.26 39896 11.04 3.40 654.13 657.73
136 Dorabji Paradise
Dorabji Paradise ESR 1 P ESR
8.56 64812 13.14
3.00 652.00 658.00
Dorabji Paradise ESR 2 P ESR 1.50 652.00 658.00
137 Cloud Nine Cloud Nine ESR P ESR 5.78 45523 9.23 3.00 635.00 641.00
138 Nyati Enclave Dorabji Paradise ESR 3 P ESR 4.45 29452 6.63 2.50 652.00 658.00
139 Tarode Wasti Tarode Wasti ESR (Reconstruct) P ESR 1.84 9632 2.59 1.00 636.00 642.00
140 Mohamad Wadi Mohamad wadi ESR P ESR 3.86 31717 5.85 2.00 630.00 636.00
Detailed Summary of Water
Supply Zones & Reservoirs
SR. No. Zone Name SR Name SRs
Existing/ Proposed
Type of SR
Demand (2032)
Population (2047)
Demand (2047)
SR Capacity Existing
SR Capacity
Proposed LDL FSL
E/P ESR/GSR MLD MLD ML ML m m
Holkar
141 Bopodi
Chikhalwadi ESR 1 (near Hockey Stadium)
P ESR
17.01 77645 18.83
3.00 585.00 591.00
Chikhalwadi ESR 2 (near Darga) P ESR 3.50 585.00 591.00
Clear Water Transmission System
Basic concepts in bulk transmission plan • Maximum utilisation of the existing facilities (SRs, BPTs, sumps, pumps, and transmission
mains)
• Maximum utilisation of gravity-driven systems and minimization of pumping
• Allocation of water from a WTP to SRs which are best suited in terms of o nearness of location o hydraulic level
• Avoid laying of pipelines through the congested areas
• Avoid to an extent possible, long and complex pipe networks
Clear Water Transmission System - Components
Clear water Pump Stations (No.) Pumping mains (km)
BPT (No.)
Gravity mains (km) @ WTP
Intermediate PS
Existing / Planned
7 (2 planned by other consultants)
2 68.73 1 24.81
Proposed 2 1 68.10 8 71.13
PUMP STATION
BREAK PRESSURE TANK SERVICE
RESERVOIRS
DISTRIBUTION
NETWORK
Parvati Transmission System Clear water pump stations
at Water Treatment Plants:
o Parvati New WTP (planned)
o Parvati Proposed PS (proposed)
Clear water pumping mains
o Existing – 3150 m
o Proposed – 7310 m
Break Pressure Tanks
o BPT near Parvati HLR (proposed)
Clear water gravity mains
o Existing – 0
o Proposed – 5775 m
• Parvati New WTP (planned)
Parvati system- Pump Stations
Proposed pump station no.1
Description Unit Details
Clear water sump
Capacity ML 18.0
Size m 110 x 30 x 6
Full supply level (FSL) RL. m 567.25
Lowest draw level (LDL) RL. m 561.25
Parvati system- Pump Stations
Proposed pump station no.2
Description Unit Details
Clear water sump
capacity ML 9.0
Size m 70x 22
Full supply level (FSL) RL. m 567.15
Lowest draw level (LDL) RL. m 561.25
Parvati system- Pump Stations
Zone wise distribution from Parvati water works
Sr No Description Distribution in MLD
2032 2047
1 Pune Cantonment Water Works 243.79
3 Parvati MLR ws zone-1 51.87 66.86
4 Parvati MLR ws zone-2 46.50 63.61
5 Parvati HLR1 for ws zone-1 9.51 12.99
6 Parvati HLR2 & HLR3 for ws zone-2 16.61 27.06
7 Parvati HLR4 for ws zone-3 2.90 2.94
Subtotal HLRs 29.02 42.99
8 Waghjai Existing 3.17 3.17
9 Waghjai-proposed 5.79 7.09
10 Parvati WTP 8.42 10.64
11 P L Deshpande Garden 11.60 14.67
12 Proposed Parvati BPT
12.1 Sarasbag Kothi 17.98 20.90
12.2 Shaniwarwada 24.48 33.44
12.3 Crescent high school 13.63 16.99
Subtotal-12 56.09 71.33
13 SNDT sump, MLR, and HLRs 110.37
Total 456.25 390.73
Parvati system- Pump Stations / SRs
RESERVOIRS IN PARVATI SUPPLY AREA
Description GSRs ESRs Total
Existing Proposed Existing Proposed Existing Proposed
Num SR 7 3 0 9 7 12
Capacity 33.66 29.50 0 33 33.66 62.5
Zone wise distribution from SNDT SRs / PS / BPT
Sr No Description Distribution in MLD
2032 2047
1 SNDT MLR 33.89
2 SNDT HLR 38.71
3 Ideal Colony / MIT College 13.73
SNDT PS
4 SNDT Proposed BPT
4.1 Gokhale Nagar 17.85
4.2 Chatushrungi Temple 6.19
Total 0.00 109.83
Cantonment Transmission System Clear water pump stations
at Water Treatment Plants:
o Cantonment 100 MLD WTP (existing) Intermediate pump stations:
o Cantonment Proposed PS (proposed)
Clear water pumping mains
o Existing – 31,145 m
o Proposed – 14,320 m
Break Pressure Tanks
o Ram Tekdi BPT (proposed)
Clear water gravity mains
o Existing – 300 m
o Proposed – 16,830 m
• Cantonment 100 MLD WTP (existing)
Cantonment system- Pump Stations
1 CLEAR WATER SUMP
Construction Capacity
(ML) Size
Full Supply Level
FSL
Lowest Draw
Level
LDL
RCC 9.0 85m x 27m 576.23 573.41
• Cantonment Proposed PS (proposed)
Description Unit Details
1Clear water sump
Capacity ML 12.50
Size m 75x30
Full supply level (FSL) RL. m 580.55
Lowest draw level (LDL) RL. m 575.00
Cantonment system- Pump Stations
Zone wise distribution from proposed pump station at Pune Cantonment water
works
Sr No Description Distribution in MLD
2032 2047
1 Wanori HLR for Ghorpadi ws zone 11.37 13.97
2 Proposed ESRs in the PCWW for Koregaon
park ws zone 16.31 21.22
3 Existing GSR-old for Bakari hill zone 1 13.07 15.97
4 Existing GSR-new for Bakari hill zone 2 13.60 16.61
5 Existing Wanori GSR for Pune cantonment
area 14.75 14.75
6 Ghorpadi Sicilia zone 28.77
7 Proposed Jal mandir zone 60.91 92.67
8 Ram Tekadi Existing GSR for Ram Tekdi zone 22.32 27.93
9 Ram Tekadi proposed GSR for Hadapsar
Industrial colony zone 14.35 18.30
10 Proposed Ram Tekadi BPT 77.11 107.28
Total 243.79 357.47
Cantonment system- Pump Stations / SRs
RESERVOIRS IN CANTONMENT SUPPLY AREA
Description GSRs ESRs Total
Existing Proposed Existing Proposed Existing Proposed
Num SR 6 1 6 14 12 15
Capacity 36.45 32 13.45 50 49.90 82
Zone wise distribution from Ram Tekdi BPT
Sr No Description Distribution in MLD
2032 2047
1 Badade Mala 7.68 9.7
2 Kale Borate Nagar 6.47 7.03
3 Gliding Centre / Hadapsar Gaon 9.85 10.88
4 Satavwadi 8.26 11.19
5 Magarpatta 10.21 15.89
6 Hadapsar Gaon 9.4 14.24
7 Sadhana Vidyalaya 9.07 13.75
8 Akashwani 13.76 20.84
9 Indraprastha 2.41 3.76
Total 77.11 107.28
Vadgaon Transmission System (1/2) Clear water pump stations
at Water Treatment Plants:
o Vadgaon old WTP (existing)
o Vadgaon new WTP (planned) Intermediate pump stations:
o Rajeev Gandhi PS (existing)
o Proposed Santosh NagarPS (proposed)
Clear water pumping mains
o Existing – 8,355 m
o Proposed – 18,050 m
Vadgaon Transmission System (2/2) Break Pressure Tanks
o New WTP Clear Water sump (planned)
o Taljai BPT (proposed)
o Institute BPT (proposed)
o Steel Yard BPT (proposed)
o Konark Indrayu BPT (proposed)
Clear water gravity mains
o Existing – 12,640 m
o Proposed – 27,020 m
• Vadgaon old WTP (existing)
Vadgaon system- Pump Stations
1 CLEAR WATER SUMP
Construction Capacity
(ML) Size
Full Supply Level
FSL
Lowest Draw Level
LDL
RCC 4.8 40m x 30m 615.00 611.00
• Vadgaon new WTP (planned)
Description Unit Details Remarks
1Clear water sump and BPT
Capacity ML 6.90
Two compartments of
0.50 for BPT & 6.40 Ml
sump
Size m 50 x 25 -
Full supply level (FSL) RL. m 620.50 -
Lowest draw level (LDL) RL. m 615.00 -
Vadgaon system- Pump Stations
Zone wise distribution from the existing (125 MLD) pump station at Vadgaon
Sr No Description Distribution in MLD
Remarks 2032 2047
1 Existing Institute ESR, Charwad vast GSR
and proposed Institute BPT 20.57 26.80
2 Proposed Santosh nagar pump station 113.47 113.47
Total 134.04 140.27
Details of the Proposed Santosh Nagarpump station
Description Unit Details
1 Clear water sump
Capacity ML 6.00
Size m 40 x 30
Full supply level (FSL) RL. m 661.50
Lowest draw level (LDL) RL. m 656.50
Vadgaon system- Pump Stations
Zone wise distribution from the proposed pump station at Vadgaon
Sr No Description Distribution in MLD
2032 2047
1 Taljai HLRs-Existing 28.85 35.31
2 Taljai HLR -Proposed 9.17 12.53
3 Dhankavadi GSR-Existing for Dashbhuja Mandir zone 0.86 1.34
4 Taljai BPT - -
4.1 Taljai MLRs 15.07 20.42
4.2 Bibvewadi GSRs 14.11 21.47
4.3 Shreehari ESR 1.68 3.0
4.4 Rajiv Gandhi pump station-Existing 40.53 53.45
4.5 Proposed Santosh nagar pump station - 30.98
Subtotal-4 71.39 129.32
Total 110.27 178.50
Zone wise distribution from Rajiv Gandhi Pump Station
Sr No Description Distribution in MLD
2032 2047
1 Kedareshwar Existing 22.10 29.14
2 Kedareshwar Proposed 9.67 13.70
3 Mahadev Mandir 8.76 10.61
Total 40.53 53.45
Vadgaon system- Pump Stations / SRs
RESERVOIRS IN VADGAON SUPPLY AREA
Description GSRs ESRs Total
Existing Proposed Existing Proposed Existing Proposed
Num SR 9 10 3 15 12 25
Capacity 43.61 40 3 39 46.61 79
Zone wise distribution from Santosh Nagar Pump Station
Sr No Description Distribution in MLD
2032 2047
1 Agam Mandir Existing 2.15 4.06
2 Agam Mandir Proposed 19.44 25.35
3 Konark Indrayu 9.09 10.97
4 Upper Indira Nagar 4.55 5.35
5 Sai Baba Nagar 12.33 12.68
6 Konark Indrayu BPT
6.1 Dorabji Paradise / Nyati Enclave 13.01 19.77
6.2 Cloud Nine 5.78 9.23
6.3 Mohmadwadi 3.86 5.85
6.4 Tarode Wasti 1.84 2.59
7 Steel Yard BPT
7.1 Market Yard 10.68 12.00
7.2 Seminary Existing 15.56 18.45
7.3 Kondhwa Road 7.31 9.30
7.4 Shivneri Nagar 7.87 8.85
Total 113.47 144.45
Warje Transmission System Clear water pump stations
at Water Treatment Plants:
o Warje 180 MLD WTP (existing)
o Warje 200 MLD WTP (under construction) Intermediate pump stations:
o SNDT sump & PH (existing)
Clear water pumping mains
o Existing – 24,775 m
o Proposed – 23,660 m
Break Pressure Tanks
o SNDT BPT (existing)
o SNDT BPT (proposed)
o Old 9 MLD WTP pure water sump (existing)
o Chandani Chowk BPT (proposed)
Clear water gravity mains
o Existing – 11,865 m
o Proposed – 21,500 m
• 180 MLD WTP PH (existing)
Warje system- Pump Stations
1 CLEAR WATER SUMP
Construction Capacity
(ML) Size
Full Supply Level
FSL
Lowest Draw
Level
LDL
RCC 4.2 47m x 23m 574.00 570.00
Salient features of the proposed supplementary pump station
Description Unit Details
1 Clear water sump
Capacity ML 0.40
Size m 20 x 5
Full supply level (FSL) RL. m 574.00
Lowest draw level (LDL) RL. m 570.00
• 180 MLD WTP PH (proposed supplementary)
• 200 MLD WTP PH (under construction)
Warje system- Pump Stations
Salient features of the proposed pump station at Warje water works
Description Unit Details
1Clear water sump
Capacity ML 10.0
Size m 2 sumps of 30m diam.
Full supply level (FSL) RL. m 580.00
Lowest draw level (LDL) RL. m 573.00
Zone wise distribution from the existing sump at old warje WTP
Sr No Description Distribution in MLD
2032 2047
1 Atul nagar zone 5.02 6.30
2 Warje-Malwadi zone 2.29 2.87
3 Ahire Gaon zone 1.98
Total 9.29 9.17
Warje system- Pump Stations
Zone wise distribution from the existing pump station at existing 180 MLD Warje WTP
Sr No Description Distribution in MLD
Remarks 2032 2047
1 Gandhi Bhavanzones 1 and 2 28.68 39.80
2 Chandani chowk zones 1 and 2 61.11 78.35
3 SNDT existing BPT 105.38 77.02 In second stage, the part of
the supply to SNDT will
come from Parvati WTP Total 195.17 195.17
Zone wise distribution from the proposed pump station at 200 MLD Warje WTP
Sr No Description Distribution in MLD
Remarks 2032 2047
1 Proposed Ram nagar ESR 4.69 5.11
2 Ahire gaon ESR 2.91
2 Proposed Karve nagar GSR 26.75 36.11
3 Kumbharwadi GSR and Dukkar Khind ESR 7.97 10.56
3 SNDTHLR, MLR -SUMP 116.47
4 Chandani chowk BPT 68.15 109.71
5 SNDT existing BPT 93.22
Total 224.03 257.62
Warje system- Pump Stations Zone wise distribution from Chandani Chowk BPT
Sr No Description Distribution in MLD
2032 2047
1 Panchavati 3.11 5.71
2 Pashan Lake 13.38 17.63
3 Baner Gaon Zone 1 8.02 14.65
4 Baner Gaon Zone 2 4.95 8.78
5 Baner West 5.54 10.00
6 Balewadi 8.83 16.46
7 Ram Nagar / Laxman Nagar 7.01 12.68
8 Baner Hill 5.39 10.03
9 Sus Sutarwadi 11.92 13.77
Total 68.15 109.71
Zone wise distribution from SNDT Existing BPT
Sr No Description Distribution in MLD
2032 2047
1 Modern College 32.70 38.17
2 BMCC College 4.39 5.12
3 Fergusson College 7.26 9.83
4 Chatushrungi Zone 1 8.33 12.97
5 Chatushrungi Zone 2 20.33 34.30
6 Ganesh Khind / Aundh 12.87 19.14
7 Pune University 4.30 5.88
8 Bhosale Nagar 15.20 18.35
9 Wakdewadi 26.49
Total 105.38 170.25
Warje system- Pump Stations / SRs
RESERVOIRS IN WARJE SUPPLY AREA
Description GSRs ESRs Total
Existing Proposed Existing Proposed Existing Proposed
Num SR 15 6 0 15 15 21
Capacity 102.26 40.50 0 43.50 102.26 84
Zone wise distribution from SNDT SRs / PS / BPT
Sr No Description Distribution in MLD
2032 2047
1 SNDT MLR 28.85
2 SNDT HLR 34.24
3 Ideal Colony / MIT College 11.25
SNDT PS
4 SNDT Proposed BPT
4.1 Gokhale Nagar 12.29
4.2 Chatushrungi Temple 5.61
4.3 Wakdewadi 24.23
Total 116.47 0.00
Holkar Transmission System Clear water pump stations
at Water Treatment Plants:
o Holkar WTP PH (existing)
Clear water pumping mains
o Existing – 1,300 m
o Proposed – 4,755 m
• Holkar WTP PH (existing)
Holkar system- Pump Stations
Description Unit Details Remarks
1 Clear water sump and BPT
Capacity ML 1.20 -
Size m 2 wells of 15m diam. -
Full supply level (FSL) RL. m 550.50 -
Lowest draw level (LDL) RL. m 547.00 -
Zone wise distribution from the Holkar pump station
Sr No Description Distribution in MLD
Remarks 2032 2047
1 Khadki Cantonment Board 14.18 14.18 -
2 Bopodi zone 17.01 18.83 -
Total 31.19 33.01 -
Holkar system- SRs
RESERVOIRS IN HOLKAR SUPPLY AREA
Description GSRs ESRs Total
Existing Proposed Existing Proposed Existing Proposed
Num SR 0 0 0 2 0 2
Capacity 0 0 0 6.5 0 6.5
Bhama Askhed Transmission System
Clear water pump stations
at Water Treatment Plants:
o Bhama Askhed WTP (plan & design by other consultant)
Break Pressure Tanks
o Bhama Askhed MBR (plan & design by other consultant)
Bhama Askhed system- SRs
RESERVOIRS IN BHAMA ASKHED SUPPLY AREA
Description GSRs ESRs Total
Existing Proposed Existing Proposed Existing Proposed
Num SR 0 0 12 28 12 28
Capacity 0 0 17.94 69.50 17.94 69.50
• The storage capacity shall be subdivided in two compartments
• Normal design water depth in GSRs 6,00m
• 5.00m free space to be maintained around GSR
• The reinforcement bar cover in the foundation of minimum 40mm
• Waterstops shall be placed at all the construction joints, either horizontal or vertical
• The top slab shall have minimum rebar cover of at least 30 mm in the lower face
• Impervious plaster layer of 40 mm on internal RCC surfaces in contact with water
• All internal surfaces of the reservoirs shall be covered by an epoxy based paint
• Ventilation openings, every 200 sqm of top slab surface
• The ladders for access to the internal part of the GSRs shall be made with aluminium alloy
Proposed GSR design criteria
• ESR tank normally of circular shape, with a normal water depth of 6 m
• The top slab shall have minimum rebar cover of at least 30 mm in the lower face to ensure
more protection against corrosion of the rebars
• Waterstops at all the construction joints, either horizontal or vertical
• Columns of the supporting structure shall have height generally below 22m
• Stairs for access to the tank shall be preferably built with a conventional staircase resting on a
framework of columns and beams
• Impervious plaster layer of 40 mm, on all the internal RCC surfaces of the tank
• All internal surfaces of the reservoirs shall be covered by an epoxy based paint
• Parapet and handrails protected from corrosion by zinc coating and paint
• Ladders for access to the interior of the tank in aluminium alloy
Proposed ESR design criteria
• Existing distribution network updated in coordination with PMC Engineers
• Existing water supply zones considered for this exercise
• The existing i.e. 2012 water demand used for the analysis
• Peak factor of 1.7 used, considering 24 hours supply
• Results confirm low to very low pressures in many areas
Network modeling of existing distribution system
Parvati system Performance Analysis – 24x7
Pressure
0.00
10.00
30.00
50.00
m
PRESENT DEMAND, PEAK FACTOR = 1.7
Cantonment system Performance Analysis – 24x7
Pressure
0.00
10.00
30.00
50.00
m
PRESENT DEMAND, PEAK FACTOR = 1.7
Vadgaon system Performance Analysis – 24x7
Pressure
0.00
10.00
30.00
50.00
m
PRESENT DEMAND, PEAK FACTOR = 1.7
Warje system Performance Analysis – 24x7
Pressure
0.00
10.00
30.00
50.00
m
PRESENT DEMAND, PEAK FACTOR = 1.7
Holkar system Performance Analysis – 24x7
Pressure
0.00
10.00
30.00
50.00
m
PRESENT DEMAND, PEAK FACTOR = 1.7
Chikhali system Performance Analysis – 24x7
Pressure
0.00
10.00
30.00
50.00
m
PRESENT DEMAND, PEAK FACTOR = 1.7
• Water distribution system analysed for each zone with WATER GEMS software
• A water supply zone is divided in to two or more DMAs, to minimize the pressure
variation
• The Pressure Reducing Valves (PRVs) are proposed to restrict the terminal
pressures
• Pipes of GI,AC, RCC, PSC, PVC replaced with MS and DI pipes
• Old CI pipes replaced with suitable DI pipes
Distribution System
Summary Of Existing and Proposed Pipes in Distribution System
Sr. No. ZONE NAME
SUMMARY OF PIPE LENGTH IN METRES
EXISTING PIPES TOTAL
EXISTING PROPOSE
D SERVICE
LINES TOTAL
PROPOSED
TOTAL EXISTING + PROPOSED
RETAINED REPLACE
D
1 Parvati Zone 298,594
45,641 344,235
127,534
28,353
155,887 454,481
2 Warje Old Zones
26,118
1,728
27,846
3,890
5,423
9,313 35,431
3 Warje New WTP Zones 666,936
53,205 720,141
378,959
41,630
420,589 1,087,525
4 Cantonment Zones 405,623
45,613 451,236
242,565
104,252
346,817 752,440
5 Bhama Askhed Zones 342,557
28,129 370,686
163,181
91,916
255,097 597,654
6 Vadgaon Zones 560,808
38,881 599,689
305,044
116,288
421,332 982,140
7 Holkar Zones
25,224
5,041
30,265
8,331
1,034
9,365 34,589
Total
2,325,860
218,238
2,544,098
1,229,504
388,896
1,618,400 3,944,260
Data from House Unit Property Registration
Considered Housing typologies
Estimate of consumer meters
ARV Slab No. of Properties
<1000 61,547
1001 to 3000 205,801
3001 to 5000 180,614
5001 to 10,000 151,479
>10,000 68,920
Total No. 668,361
Typology Number of flats/units
in the building
Size and number of the meter
connection
1 1 no. 1 x 15 mm
2 2 to 6 no. 1 x 15 mm
3 7 to 12 no.2 x 15 mm or no. 1 x 20 mm
4 13 to 24 no.2 x 20 mm or no. 1 x 25 mm
5 25 to 52 no.1 x 40 mm
6 52 to 96 no. 1 x 50 mm
7 >96 no. 2 x 40 mm
Estimate of consumer meters
ARV Slab No. of
Properties
Type1
Individ
houses
Type 2
2 to 6
units
Type 3
7 to 12
units
Type 4
13 to 24
units
Type 5
25 to 52
units
Type 6
52 to 96
units
Type 7
>96
units
<1000 61,547 10%
61,547
1001 to 3000 205,801 20% 25% 30% 25%
41,160 12,863 6,860 2,858
3001 to 5000 180,614 30% 40% 30%
13546 8027 3010 1693
5001 to 10,000 151,479 10% 30% 40% 20%
3787 5049 3366 947
>10,000 68,920 10% 10% 20% 20% 20% 10%
1723 766 574 538 280 69
Totals 668,361 102,707 31,919 20,704 9,810 3,179 280 69
Unreg. Slum units 33,000
Total Resid. Cnx 135,707 31,919 20,704 9,810 3,179 280 69
Assumed Housing Typology for ARV slabs
Estimate of consumer meters
Numerical results for Connections by size
Connection
Diameter
Domestic
Connections Commercial
Industrial/
Institutional
Total at year
2012
Total at year
2017
(coef. 1.315)
15 mm 171,089 2,110 173,199 220,500
20 mm 34,376 26,864 61,240 78,000
25 mm 7,848 994 8,842 11,300
40 mm 3,317 156 3,473 4,440
50 mm 280 37 95 412 500
80 mm - 30 37 67 100
100 mm 30 34 64 90
150 mm 14 22 36 50
200 mm 4 4 8 10
250 mm 1 5 6 7
300 mm - 3 3 3
Totals 216,910 30,240 200 247,350 315,000
Consumer Meters
Mech. Turbine type
Multi Jet
< 50 mm dia.
Woltmann
≥ 50 mm dia.
Ultrasonic Electromagnetic
Consumer Water Meters
House Connection
Distribution
Line
Ferrule Water
Meter
Air Valve (if required)
Consumer
Ball Valve
* Recommended
Recommended type of Water Meter
AMR System
Advantages of AMR System
• Reduce meter reading Cost & Time due to lesser human resources
• Safety & Privacy issues avoided due to wireless data collection
• Enhanced monitoring of system integrity
• Water Audit in the DMA possible
• More efficient and accurate billing
• Improved Cash Flow
• Improved Customer Service
• Help in detecting anomalies in water consumption
Data Collection
WALK BY MODE
DRIVE BY MODE
Data Transmission & Analysis
Billing
Salient features considered WTPs
• Measurement of Parameters such as turbidity, pH, residual chlorine at strategic locations
• Measurement of differential pressure across the filters
Pump houses - Existing
• Measurement of sump level and tripping all the pumps in case of very low level
• Measurement of flow from the rising main
• Communication for acquiring electrical parameters such as voltage, current, power, power factor for each pump
• Start/stop of pumps from the operator stations and status display of pumps
SCADA
Pump houses - New
• Measurement of sump level and tripping all the pumps in case of very low level in the sump and high water level in the SR / BPT
• Measurement of flow and pressure for individual pumps and display on the operator station of the current operating point and the best efficiency point.
• Communication for acquiring electrical parameters such as voltage, current, power, power factor for each pump
• Start/stop of pumps from the operator stations and status display of pumps
• Computation of pump efficiency on line
• Measurement of vibration at strategic locations, pump trip at high vibration/temperature levels
SCADA
Reservoirs
• Measurement of inlet and outlet flow
• Measurement of level and conversion into volume resident in reservoirs
• Possible reservoir leakage diagnostic from the above
• Motorized valves at inlets and outlets to isolate reservoirs and control wherever needed
DMAs
• Measurement of flow at strategic locations
• Measurement of pressure at strategic locations
SCADA
Instrument
Description of water supply system component
Rehabilitatio
n of WTPs Pump station
Transmission
and
Distribution
systems
Service
Reservoirs
Distribution
System
Electro magnetic flow meter √ √ √
Ultrasonic level transmitters √ √
Residual chlorine transmitters √
pH transmitters √
Turbidity transmitters √
Differentialpressure transmitters √
Controllers √ √ √ √ √
Pressure transmitters √ √ √
Vibration system √
SCADA
Cost Summary of Water Supply System components
Particulars Cost in INR
Land Acquisition 406,165,150
Clear water Transmission mains 4,308,430,020
Clear water Pump Stations 1,389,525,091
Proposed Service Reservoirs 2,931,026,213
Distribution system 17,465,011,566
Rehabilitation of existing service reservoir’s 237,264,296
SCADA 31,803,804
Consumer survey 55,459,672
Rehabilitation of existing water treatment plants 56,588,925
Pilot DMA project 161,247,509
Total 27,042,522,246
Overall Project Cost Analysis
Consumer meters
12%
Bulk Flow meter 1%
Cost of pipes and specials for
Transmission System 14%
Cost of pipes and specials for
Distribution System 26%
Valves 2%
Consumer awareness &
consumer Survey 2%
Instrumentation & Control
2%
Change of House Connections
6%
IT & Billing works 1% Pump House works
16%
Land Acquisition cost 4%
Other Works 14%
Clear water Transmission mains
WTP Zone Cost in INR
Parvati zone 793,849,457
Pune Cantonment zone 897,534,647
Vadgaon zone 1,255,268,234
Warje zone 1,272,531,598
Holkar zone 89,246,083
Bhama –Askhed zone NA
Total 4,308,430,020
Clear water pump stations
WTP Zone Cost in INR
Parvati zone 308,510,793
Pune Cantonment zone 297,468,614
Vadgaon zone 382,327,060
Warje zone 386,602,479
Holkar zone 14,616,145
Total 1,389,525,091
Proposed Service reservoirs
WTP Zone Cost in INR
Parvati zone 482,901,888
Pune Cantonment zone 601,120,828
Vadgaon zone 738,992,527
Warje zone 630,348,110
Holkar zone 60,902,855
Bhama–Askhed zone 416,760,005
Total 2,931,026,213
Distribution system
WTP Zone Cost in INR
Parvati zone 2,380,607,250
Pune Cantonment zone 3,465,464,160
Vadgaon zone 3,997,822,481
Warje zone 4,534,000,090
Holkar zone 122,916,449
Bhama–Askhed zone 2,964,201,136
Total 17,465,011,566
Distribution System Cost Analysis
Consumer meters 19% Bulk Flow meter
1%
Cost of pipes and specials
41%
Valves 2%
Consumer awareness
3%
Instrumentation & Control
2%
Change of House Connections
11%
IT & Billing works 2%
Road reinstatement works
7% Other Works
12%
Gross Project Cost Sr No DESCRIPTION OF COMPONENT COST IN INR
A Land Acquisition 406,165,150
B Physical infrastructure components
1 Rehabilitation of existing water treatment plants 56,588,925
2 Clear water pump stations 1,389,525,091
3 Clear water transmission System 4,308,430,020
4 Rehabilitation of existing Service reservoirs 237,264,296
5 Service reservoirs 2,931,026,213
6 Distribution system 17,465,011,566
7 Pilot DMA works 161,247,509
8 SCADA 31,803,804
9 Consumer survey 55,459,672
Sub Total-B 26,580,897,424
Total cost of water supply components (A+B) 26,987,062,574
C Shifting of utilities 53,161,795
D Statutory compliances 5,000,000
Total Net cost 27,100,684,041
Add Cost of consultancy services at 1% 271,006,840
Add Contingencies at 3% 813,020,521
Total Gross cost 28,184,711,402
Operation & Maintenance cost
…
OP&MAINT COST OF PMC Lahks Rs/year 2017 2018 2019 2020 2021
Water Withdrawal Charges " " / " 2,772 2,857 2,940 3,022 3,104
Salaries of PMC staff (*) " " / " 7,406 7,536 7,668 7,803 7,940
Electricity Charges " " / " 6,798 6,966 7,133 7,301 7,468
Chemicals for WTPs " " / " 517 547 577 607 637
Communications cost (**) " " / " 376 380 384 387 391
Stationery and consumables " " / " 196 198 200 202 204
Maintenance & repair of
Existing Assets
" " / " 2414 2414 2414 2414 2414
Maintenance & repair of
Propsed works
" " / " 3148 3148 3148 3148 3148
Leak detection Charges " " / " 100 100 100 100 100
Leak Repair Charges " " / " 1582 1582 1582 1582 1582
Consultancy Services " " / " 328 328 328 328 328
New Connections " " / " 0 1253 1253 1253 1253
Billing & Collection " " / " 162 171 181 190 200
Total in Lahks Lahks Rs/year 25798 27478 27907 28336 28769
Total in crores R cr/ Year 258.0 274.78 279.07 283.4 287.7
Volume of water sold in PMC
service area( Cum)
269,107,200 284,749,640 300,392,080 316,034,520 331,676,960
Unit cost incidence of O&M /m3
of water sold
Rs/m3 9.59 9.65 9.29 8.97 8.67
FINANCIAL ANALYSIS
Financial Analysis covers:
• Analysis of Pune Water Supply Project on stand alone basis
• Analysis of PMC’s overall finances
• Analysis of project on PMC’s finances and
• Sustainability analysis
Coverage of Financial Analysis
• CAPEX is linked with sequencing of implementation schedule of different components
• Spread over a period of four years (2014 to 2017)
• Expenditure on Pilot DMA, Consumer Survey, Shifting of Utilities included in CAPEX and capitalized as per JNNURM guidelines
• Contingencies provided @ 3% of base cost
• 1% provision for Project Design and Management
• Price contingencies not included in CAPEX
Assumptions for Capital Expenditure (CAPEX)
Capital expenditure
Sr. Component 2014 2015 2016 2017 Total
(Rs. Lakhs)
1 Land Acquisition 4062 - - - 4062
2 Shifting of Utilities 85 170 170 106 531
3 Pilot DMA 1612 - - - 1612
4 Consumer Survey 444 111 - - 555
5 Statutory Compliances 15 25 10 50
6 Physical Infrastructure
6.1 Construction of Reservoirs 3286 9766 9766 6492 29310
6.2 Rehabilitation of Reservoirs 836 949 588 - 2373
6.3 Rehabilitation of WTPs. 189 377 - - 566
6.4 Pumping Stations 2384 7107 4722 - 14213
6.5 Transmission, Distribution, Metering 25057 72538 72590 47549 217734
Total Base Cost 37970 91043 87846 54147 271006
7 Contingencies @ 3% 1139 2731 2635 1624 8130
8 Project Design & Management @ 1% 380 910 878 541 2710
9 TOTAL PROJECT COST 39489 94685 91360 56313 281846
Annual Percentage of Expenditure 14% 34% 32% 20% 100%
FINANCING OPTIONS FOR PROJECT
• Financing Plan based on JNNURM Norms
• Cost of Land Acquisition not considered for Central and State Government financing
• Options available for PMC to raise finance: Own surplus revenue Term Loan from State Government Term Loan from Banks Term Loan from Financial Institutions Debt from Capital Market (Bonds) Private Equity – Capital Contribution
by PPP
• Budgetary Provision for Price Contingencies is Essential
Sources Share Amount (Rs. Lakhs )
Central Government
50% 138811
State Government 20% 55524
PMC 30% 87511
Total Financing 100% 281846
Proposed Sources for PMC’s Share
From own surplus 15% 43756
Term Loan from Financial Institution
15% 43755
Total PMC’s Share 30% 87511
ANNUAL CONTRIBUTIONS AND SOURCES OF FINANCE
Sr. Component Share 2014 2015 2016 2017 Total
(Rs. Lakhs)
1 Central Government
50% 17632 47343 45680 28156 138811
2 State Government
20% 7053 18937 18272 11263 55524
3 Pune Municipal Corporation
3.1 From Revenue Surplus
15% 7402 14203 13704 8447 43756
3.2 Term Loan from Fin. Institution
15% 7402 14203 13704 8447 43756
Sub-total (3) 30% 14804 28406 27408 16894 87511
4 TOTAL FINANCING
100% 39489 94685 91360 56313 281846
Assumptions for Income and Expenditure Projections – Pune Water Supply Project
Sr. Component Assumption / Basis
1 Revenue Income
1.1 Connection Charges One time connection charges to be recovered in five equal installments
1.2 Usage Charges Based on telescopic tariff with periodical revision to ensure recovery of O&M cost
1.3 Revision in tariff Every five years at the rate of 10% for connection and usage charges
2 Operating Expenditure
2.1 Establishment Charges Based on new staffing pattern proposed for different facilities
2.2 O&M Charges Water Charges, Electricity Charges, Chemicals, Petrol and Consumables, Maintenance and Repairs, Consultancy, New Connections, Billing and Collections
2.3 Debt Service Moratorium Period for repayment of principal – 3 years Interest Rate – 12% Repayment Period – 10 Years
2.4 Contingencies for O&M Water Charges, Salaries and Chemicals for WTP : 3% Other O&M Components – 5%
Assumptions for Financial Indicators to ascertain Project Viability
Sr. Component Assumption / Basis
1 Net Present Value NPV of overall cost (CAPEX + OPEX) and O&M cost (CAPEX) should be positive
2 Internal Rate of Return
IRR should be at least equal to cover cost of finance (interest rate) and if possible some risk factor
3 Coverage of PMC’s contribution to CAPEX
• Overall operating surplus generated by PMC should be sufficient to cover PMC’s share in CAPEX
• Projected allocation to Budget “C” should be sufficient to cover PMC’s annual share in CAPEX
Proposed water tariffs
Type of Connection 2018-2022 2023-2027 2028-2032
One time Connection Charges (Rs. / Connection)
Domestic Connections 5,000 5,500 6,050
Non-Domestic Connections 10,000 11,000 12,100
Water Consumption Charges (Rs. / KL)
0 to 22.5 lpcd (150 Liters) 3.00 4.00 5.00
22.5 to 30 lpcd (150 to 200 Ltrs.) 6.00 7.00 7.00
30 to 37.5 lpcd (200 to 250 Ltrs) 9.00 10.00 11.00
Above 37.5 lpcd (Above 250 Ltrs) 10.00 11.00 13.00
Non-Domestic Connections 35.00 39.00 43.00
Based on telescopic tariff rates. If consumption exceed stipulated limit, entire consumptions will be charged on the basis of applicable rate.
PROJECTED INCOME AND EXPENDITURE PUNE WATER SUPPLY PROJECT (STAND ALONE BASIS)
Sr. Component 2018 2023 2028 2033
1 REVENUE INCOME (Rs. Lakhs)
1.1 Connection Charges 95 489 653 698
1.2 Water Charges (Usage Charges) 29614 43014 49695 63552
TOTAL REVENUE INCOME 29709 43503 50348 64250
2 REVENUE EXPENDITURE
2.1 Establishment Charges 7761 9818 12425 15735
2.2 O&M Charges 20861 27741 36886 48778
2.3 Loan Repayment (Principal) 4376 4376 - -
2.4 Interest 4463 1838 - -
TOTAL REVENUE EXPENDITURE 37460 43772 49312 64512
OPERATING SURPLUS/DEFICIT -7751 -269 1037 -263
OPERATING SURPLUS/DEFICIT WITHOUT DEBT SERVICING
1088 5945 1037 -263
With revised tariff structure, PMC will be able to generate operating surplus up to 2032. Thereafter additional revision in tariffs will be essential.
Impact of Pune Water Supply Project on PMC’s Finances
• PMC’s contribution of Rs. 875 Crores in CAPEX is spread over four years
• Annual CAPEX contribution without debt funding compared to overall Revenue Surplus ranges between 9% to 15% of surplus with annual average of 11%
• Annual CAPEX contribution with debt funding compared to overall Revenue Surplus ranges between 4% to 8% with annual average of 6%
Summary of Financial Indicators
Sr. Description of Indicator Results Remarks
1 NPV of O&M Rs. 84.27 Crores Positive
IRR of O&M 15% Covers cost of finance + Risks
2 NPV of Overall Project Rs. 8.04 Crores Positive
IRR of Overall Project 16% Covers cost of finance + Risks
3 Sustainability of Project
3.1 % of PMC share in new CAPEX to Total Revenue Surplus without debt funding
9% to 15% during construction period PMC can afford allocation of
funds of own contribution (30% of Project Cost) for project 3.2 % of PMC share in new CAPEX to
Total Revenue Surplus with debt funding
4% to 8% during construction period
3.3 Benefit Cost Ratio 1.04 BC Ratio is more than 1
Thank You