Upload
others
View
7
Download
1
Embed Size (px)
Citation preview
1
Water Distribution System SCADA Tutorial
Developed by The University of Missouri
Prepared for the
National Institute of Hometown Security
368 N. Hwy 27
Somerset, KY 42503
May 28, 2013
This research was funded through funds provided by the Department of Homeland Security,
administered by the National Institute for Hometown Security Kentucky Critical Infrastructure
Protection program, under OTA # HSHQDC-07-3-00005, Subcontract # 02-10-UK
2
Table of Contents
2.1 Supervisory Control and Data Acquisition (SCADA) Systems .......................................... 4 2.1.1 Overview ...................................................................................................................... 4
2.1.2 SCADA Concepts ......................................................................................................... 4
2.1.2A - Data Collection, Data Monitoring, and SCADA ....................................................... 4
2.1.2B - SCADA Function ...................................................................................................... 5
2.1.2C - SCADA Equipment ................................................................................................... 6
Figure 2.1.2C1 - Illustration of four SCADA Equipment Categories ..................................... 6
2.1.3 Sensors and Controls Overview ................................................................................... 7
2.1.4 Interface Devices .......................................................................................................... 9
2.1.4A - Remote Terminal Units ........................................................................................... 10
Figure 2.1.4-A1 - Simplified Illustration of RTU Function in a SCADA System ................ 10
2.1.4B - Programmable Logic Controller (PLC) ................................................................... 10
Figure 2.1.4-B1 - Example PLC photographs ....................................................................... 11
2.1.4C - Intelligent End Device (IED) ................................................................................... 11
Figure 2.1.4-C1 - Simplified Illustration of PLC or IED Function in a SCADA System ..... 12
2.1.5 Potential SCADA Uses in a Water Distribution System ............................................ 12
2.1.6 SCADA System Implementation Process .................................................................. 13
2.2 Communications Network ................................................................................................. 14 2.2.1 General Overview of SCADA Communications ........................................................ 14
Figure 2.2.1-A - Illustration of four SCADA Equipment Categories ................................... 14
2.2.2 Communications Network Options ............................................................................ 15
Table 2.2.2-A – Differences between hard-wired and wireless communication systems. .... 17
2.2.3 Communications Network Features and Considerations ............................................ 18
Figure 2.2.3-A: Typical SCADA Communication Network Configuration ........................ 19
2.2.4 – Communication Security ............................................................................................... 19
2.2.5 – Most Efficient Strategy for Designing and Building the Communication System ....... 20
2.3 Hydraulic Sensors .............................................................................................................. 21 2.3.1 - General Overview of Hydraulic Sensors as Pertinent to Water Distribution Systems .. 21
2.3.2 – Uses of Hydraulic Sensor Data ..................................................................................... 21
2.3.3 – Sensor Equipment Sources ............................................................................................ 22
2.3.4 – Most Efficient Strategy for Obtaining Hydraulic Sensors ............................................ 23
2.3.5 – Hydraulic Sensors Costs and Specifications ................................................................. 23
2.4 Water Quality Sensors ............................................................................................................ 26 2.4.1 - Overview of Water Quality Sensors as Pertinent to Water Distribution Systems ......... 26
3
2.4.2 - Sensor Equipment Sources ............................................................................................ 28
2.4.3 - Most Efficient Strategy for Obtaining Water Quality Sensors ...................................... 28
2.4.4 - Water Quality Sensors Costs and Specifications ........................................................... 28
2.5 – Hydraulic and Water Quality Sensor Placement ................................................................. 31
SCADA Sensor Placement Decision-Making Sequence ....................................................... 32
SCADA CWS Sensor Placement Optimization Program Inputs........................................... 33
2.6 Strategies for developing Data Acquisition and SCADA Systems ................................... 34 2.6.1 - Design/Bid/Build Project Delivery Method................................................................... 34
Figure 2.6.1-A – Design-Bid-Build, Owner Equipment Purchase ........................................ 34
Figure 2.6.1-B – Design-Bid-Build, Typical ......................................................................... 35
Figure 2.6.1-C – Design-Bid-Build, Performance Specification........................................... 35
2.6.2 - Engineering, Furnishing, and Installation (EFI) Project Delivery Method ................... 35
Figure 2.6.2-A – EFI Project Delivery .................................................................................. 36
2.6.3 – Considerations for Potential Equipment Suppliers, Engineers and Contractors ........... 36
References ..................................................................................................................................... 39
Appendix A - Listing of Water Related Sensor Manufacturers 2012 ........................................... 42
4
2.1 Supervisory Control and Data Acquisition (SCADA) Systems
2.1.1 Overview
In its essence, SCADA is an automated workforce that helps better operate and manage your
water treatment and distribution system. It can perform tasks such as taking water quality
measurements, controlling equipment, monitoring alarms, and data accumulation and
presentation. The benefit of using SCADA to perform these tasks, especially with respect to
security, is that unlike humans, SCADA never takes a day off. The result of the 365 days of
continuous monitoring with respect to virtually any aspect of a water treatment operation equates
to a greater level of security and overall efficiency. This translates into not only peace of mind,
but a better, more consistent product delivered at a substantial cost savings for both the consumer
and the producer. Furthermore, advances in computer modeling and instrumentation have
enabled water system operators greater levels of water system security as well as improved
production and delivery efficiency.
Currently, hydraulic models are calibrated with samples taken manually over a short period of
time. A troublesome aspect to this method is that the model only represents the data from that
particular snapshot of time, without regard to the dynamic conditions that actually exist within
distribution systems. In not accounting for ever changing conditions, such as water demand or
transient pressures, current hydraulic models cannot be expected to be accurate or reliable given
the static calibration conditions (Allen et al. 2011). This can be overcome by supplying the
model with live data from SCADA systems. SCADA in conjunction with hydraulic modeling
software and water quality monitoring equipment has the potential to keep communities safe
from intentional attack by terrorists while simultaneously increasing the efficiency of treatment
and distribution systems.
2.1.2 SCADA Concepts
2.1.2A - Data Collection, Data Monitoring, and SCADA
The term SCADA is often inappropriately used. SCADA by definition includes some level of
control coupled with real-time data collection and monitoring. Many systems only have data
collection, or the “DA” part of SCADA. With data collection only, water system operators log
data from a facility and make any needed changes at the facility based on interrupting that data at
a later date. Obviously this method requires an operator to occasionally visit the facility and this
system is obviously not real-time.
5
The next level of complexity builds on data collection and adds real-time monitoring of the data.
However, even though the system is collecting data and an operator is able to monitor the data as
it is collected, if any operational changes need to be made to the system an operator would be
required to visit the facility to make the necessary changes. This level of “SCADA” may be
adequate for many systems, but is still be missing many of the monitoring and control features
that make a SCADA such a desirable system to have.
SCADA in its entirety integrates data collection, real-time monitoring, and facility controls into
one package. When discussing the term SCADA, one must keep in mind that many smaller
systems may only have the data collection aspect of a SCADA, but refer to their system as a
“SCADA”.
While SCADA is a necessary tool in most water systems, as illustrated above it is a broad term
that isn’t always easily defined. Generally speaking, SCADA uses fit into on at least one of the
following six areas: alarms and notifications, energy monitoring/management, equipment and
facilities monitoring/control, data management and record keeping, water chemistry/quality and
hydraulics monitoring/control, and water system/supply security monitoring.
When considering SCADA, there are two general areas to consider; Function and Equipment.
2.1.2B - SCADA Function
SCADA Function categories are:
1. Data Acquisition (Collection)
2. Data Communication (Monitoring)
3. Data Presentation
4. Equipment Control
Note that these SCADA function categories are in a specific order; in other words the second,
third and fourth functions all build on the prior functions. The first three SCADA function
categories deal with data acquisition. Many water systems, especially smaller systems, do not
elect to use supervisory control aspects the SCADA in the daily management of their system.
All SCADA systems must have data acquisition and communication before any supervisory
controls can be implemented; therefore, many industry professionals believe that the “DA” of
SCADA, or data acquisition portion of SCADA, is the most important part of the system.
Closely tied to the data acquisition, is the communications and data logging/presentation aspects
to the SCADA
6
Although this report focuses on the entire SCADA system, it can also be used as a reference if a
system is examining the possibility of using only the data acquisition, logging and presentation.
2.1.2C - SCADA Equipment
All of the SCADA Functions are carried out by SCADA Equipment. There are four SCADA
equipment categories that are illustrated in Figure 1:
1. Sensors and Controllers - Sensors (either digital or analog) and control relays directly
interface with the managed system.
2. SCADA Interface Units - Remote Terminal Units (RTUs), Programmable Logic
Controllers (PLCs), and Intelligent End Devices (IEDs) are small computerized units
deployed in the field at the specific sites and locations where sensors and equipment
controllers are utilized. RTUs, PLCs, and IEDs serve as local collection points for
gathering status from sensors and delivering commands to control relays.
3. Communications Network - The data and control command transmission network that
connects the SCADA master unit to the RTUs in the field.
4. SCADA Master - These are larger computer consoles that serve as the central processor
for the SCADA system. Master units provide a human interface to the system and
automatically regulate the managed system in response to sensor inputs.
Remote Terminal
Unit (RTU),
Programmable Logic Controller (PLC) or
Intelligent End
Device (IED)
SCADA Master with
User Interface
RTUs, PLCs or IEDs Communications Network SCADA Master
Water Levels
Hydraulic Pressure
Motor Speed/Temp
Pump Station Ambient Humidity /
Temperature
Motion Detection
Pump on/off Control
SENSORS/CONTROLS
Figure 2.1.2C1 - Illustration of four SCADA Equipment Categories
7
2.1.3 Sensors and Controls Overview
Before we begin on sensors and controls, we need to cover the two basic types of these devices.
The first type is referred to as discrete, or also called digital. A discrete sensor is a sensor that
only senses two positions; “on” or “off”. It cannot sense anything in between these two
positions. Some consultants will refer to discrete sensors as digital sensors, because in the world
of digital devices, either a “I” or “O” is used, which is why some people still refer to these
devices as “I/O devices”. The second type of sensor is an analog sensor. Analog sensors can
sense and report back specific values in any given range of values. For example, if we wanted to
sense temperature. A discrete sensor could tell the user if the temperature is freezing (32˚F) or if
the temperature is boiling (212˚F). In the same example, an analog temperature sensor can
report back any temperature in a broad range, say any temperature between 32˚F to 212˚F.
Another example is a simple motor. A discrete sensor could tell the user if the motor was on or
off, while an analog sensor could tell the user not only if it was on or off, but even how fast it
was running.
To recap, discrete is simply “on” or “off”, “open” or “closed”, and so on, while analog can report
back specific “how much” values in a pre-programed range.
At the time of this report, the top ten SCADA sensors currently in use, based on sales, are:
1. Temperature Sensors - The most basic way to monitor temperature is a discrete threshold
sensor. This is very similar to a simple home thermostat. You set a high-point threshold
or a low-point threshold (one per sensor). When these presets are exceeded, you get a
contact closure alarm, which translates to a basic high or low temperature alarm. The
downside to this type of alarm is that if your threshold was set to 80°F, you could be at
81°F or 181°F - and you wouldn’t be able to tell the difference! More advanced
temperature sensors output analog values. Analog monitoring allows you to monitor
fluctuating sensor levels at your remote sites. With the right SCADA system, you can use
your analog readings to send alarms based on configurable thresholds. You can have
different thresholds for low, critically low, high, and critically high.
2. Humidity Sensors -Often, humidity monitoring is overlooked, but it is one of the key
environmental conditions to monitor in every unmanned remote site. Looking at both
internal and external humidity ranges, it’s very important to monitor what conditions
your equipment is operating in. If your environmental control unit failed and you didn’t
have adequate monitoring of the humidity at your site, you would be completely unaware
of the damage and would be too late in preventing equipment failure. Humidity can be
monitored with both discrete and analog sensors, much like temperature. Where possible,
look for a sensor that monitors both temperature and humidity.
3. Motion Sensors -The most critical element of physical site security is being able to detect
intruders and receive an immediate alert. Motion sensors provide you with the instant
information you need to react to an intruder before the real damage is done. Discrete
8
motion sensors can even turn on a light and send an immediate intrusion notification
when movement is detected in its field of vision. It’s very important to consider
placement when installing motion sensors. Windows and other possible intrusion points
should be protected by motion sensors.
4. Water (or any liquid) Level Sensors - Water level sensors can be used to monitor water
towers, ground storage tanks and clearwells. This makes them especially useful for alarm
circuits that may tell a motor when to turn on in order to keep a tower full. With a
discrete liquid level sensor, you can configure the sensor to latch a contact closure when
your liquid level has fallen below a critical line. This allows you to receive a notification
when your water tanks are low. With analog sensors, they can be set up to measure any
water level in the tank, rather than just the high and low levels.
5. Water Flow Sensors- Using water flow sensors gives you an accurate picture of your
water flow rates and direction. Most flow sensors can monitor water with an internal
flow meter or a flow data logging device. At a water treatment plant, water flow is one
item on a long list of data that must be collected during the treatment process. It’s
important to find a reliable water flow sensor that produces accurate flow results and
allows you to make quick decisions based on that data. Water flow direction is also very
important to water system managers to determine if “water racing” is occurring. Water
racing is a phenomenon where water in a distribution system “races” around in circles. If
this occurs, it is a huge waste of energy.
6. Smoke Sensors - Smoke sensors are critical safety devices needed in every remote
facility site. There are many possible reasons a fire could break out at a site. Overheated
equipment, electrical short, wildfire . . . the list goes on. In order to save your equipment,
you need to know right away if smoke or fire is present at a remote site. Fires can cause
irreparable damage, and smoke sensors are a good first line of defense.
7. Door and Window Sensors - Whether or not you’ve already experienced theft or
vandalism in your network, your unmanned sites are vulnerable. While you might expect
this type of criminal activity from strangers, an alarming amount of damage is done by
employees, ex-employees, and outside contractors. Door and window sensors keep your
equipment secure. You’ll know the moment someone tries to gain unauthorized access to
one of your remote sites, or if an employee enters when they’re not supposed to. Without
the protection of a door sensor, an unknowing technician could walk into a dangerous
situation. Door and window sensors provide a warning, “Hey, nobody’s supposed to be
there at 3 a.m.!”
8. Power Failure Sensors - The primary damage caused by a power outage is obvious: If
commercial power fails and you don’t have a reliable backup power supply, that site will
eventually go dark. Dark sites mean network downtime, frustrated customers, and lost
revenue. A power failure sensor will send an alarm when power is disrupted. This is a
discrete sensor that outputs a contact closure when power is not detected for a user-
defined amount of time. Most users want to receive a critical alarm after any failure
lasting more than a few seconds.
9. Current Sensors - You must always know whether your battery chargers, backup
generators, and other power sources are outputting power. Analog current sensors tell you
way more than, “They’re outputting power”. You also need to know the current draw.
Measuring AC/DC currents, current sensors isolate the sensor output from the conductor.
9
These types of sensors are highly useful for motor drives, UPS systems, and battery
supplies.
10. Propane Tank Sensors – Another sensor that fall in the category of “not thought of, but
very popular” is a propane tank level monitor. Monitoring your propane tanks can save
you from running out of fuel or notify you of theft. Some propane sensors send an
audible alert when they’re running low. At sites where propane is the only fuel source,
you may need advanced sensors that track gas usage rates and report back to an on-site
RTU with the exact amount left. These types of analog sensors will allow you to order
more propane for your tank - before it runs empty.
Other popular water system sensors include:
The following are just a few examples of items that can be monitored by your SCADA:
Suction and/or Discharge pump pressure
Distribution system line pressure
Stream or lake level monitoring
Equipment Temperature
Water detector alarm (to indicate leaks)
Well head pressure monitoring
Well water drawdown level monitoring
Wet well water level monitoring
Pump on/off/fail status
Valve positions
And various water quality parameters, including:
o Free/Total Chlorine
o pH
o Temperature
o Turbidity
o Or just about anything else you can think of.
2.1.4 Interface Devices
There are two primary types of systems to consider when designing telemetry and
communication systems. In a uni-directional system, remote terminal units report data to a
central location, but do not accept remote command and control instructions. Remote telemetry
is truly bi-directional in nature, reporting both statistics and accepting instructions from a central
computer or controller. In most cases, it is worth remembering that in a uni-directional system,
terminal units only send data, the managing system requires a bi-directional link; the link itself
can usually both send and receive information.
10
2.1.4A - Remote Terminal Units
Before any data collection or remote sensing can be achieved, information needs to be passed
between the sensors and the communications system in a form that is compatible with the
language of the SCADA system. To accomplish this, a field interface unit required. The most
basic of these units are known as Remote Terminal Units, or RTUs. RTUs are used to convert
electronic signals received from field sensors into machine language, known as protocol, and
transmit data over the communications network to the SCADA Master, where a human will then
use and manage that information. RTUs by themselves are not typically used to control
equipment but rather to collect and transmit data to a controller, where controls are then
exercised. When in the field, the RTU appears as a small box-like device (or several, depending
on how many sensors are being utilized) within a panel. When examining an RTU on a sensor or
in a panel, try to keep the simplified illustration shown in Figure 2.1.4-A1 in your mind.
2.1.4B - Programmable Logic Controller (PLC)
A Programmable Logic Controller, PLC or Programmable Controller, is a digital computer used
to monitor and control certain aspects of equipment, such as motor speed, valve actuation, and
other functions. Typically, a PLC has a range of functions, based on the electrical signal it
receives from the sensor. For example, if the pressure drops 10psi from optimum level in a
distribution system, the PLC may “tell” the variable frequency drive (VFD) on the electric motor
to turn the pump motor faster, which would drive the pump to produce an extra 25 GPM.
Similarly, if the pressure in the same system drops by 20psi, the PLC may drive the pump to
produce an extra 50 GPM in order to make up for the increased “demand” being sensed. This
programming is referred to as “ladder logic” and there are limits to this system. In this example,
keep in mind that all these pump speed changes are occurring on-site, without supervisory
control, all because the PLC has been pre-programed to react to a certain condition.
Although PLCs are intended to control equipment, if a condition comes up that is “outside” the
PLCs programming, then supervisory control would need to be exercised.
Sensor RTU Communications
Network
SCADA
Master
Figure 2.1.4-A1 - Simplified Illustration of RTU Function in a SCADA System
Note 1-way arrow, indicating
data transmission ONLY
1-way arrow, indicating
data transmission
ONLY
11
Figure 2.1.4-B1 shows two photographs of open SCADA PLC panels. The PLCs in the first
photo appear in the center of the panel, while the PLCs in the second panel appear in the upper
portion of the panel. A key to identifying the PLC is to identify the wires coming from the
sensor(s), and the wires going to the communications network, by default, the PLC is in between
these two features.
2.1.4C - Intelligent End Device (IED)
Similar to a PLC, and Intelligent End Device (IED) can establish communication between
remote sensors and controllers and the communications network. An IED differs from a PLC in
that a single IED can control several different aspects to a piece of equipment, so that the entire
piece of equipment works in harmony with the rest of the needs of the system and within
established design parameters. IED is a relatively new term and has come about in part because
of confusion between Remote Telemetry Units, with the acronym (RTU) and Remote Terminal
Unit, also with the acronym RTU. To help solve this issue, the industry has begun to call these
more sophisticated interface and controller units, IEDs.
A key difference between the Remote Terminal Unit (RTU) and the PLC or IED is illustrated in
Figure 2.1.4-C1. In this figure, note that the machine language, and hence the data, moves in
both directions, thus allowing for not only data acquisition, but also control.
Typical PLCs
Figure 2.1.4-B1 - Example PLC photographs
12
It is important to note that specific instruction for equipment automation is stored locally, in the
PLC or the IED. This is usually due to the fact that over most Communication Networks, there
is a limited bandwidth, thus limiting the actual control to that which is “pre-programed” into the
PLC or IED. As communication networks and the technology that SCADA is based on
continues to improve in leaps, there will no doubt be a day when true, unlimited control can be
exerted from the SCADA Master to the desired equipment. (Bentley, 2004)
2.1.5 Potential SCADA Uses in a Water Distribution System
A SCADA system is a widely distributed computerized system primarily used to remotely
control and monitor the condition of field-based assets from a central location. Field-based
assets include wells, pump stations, valves, treatment plants, tanks, and reservoirs (Bentley,
2004).
Generic uses of SCADA in distribution systems include:
Security monitoring
Energy management
Monitor equipment operations to forecast maintenance, repair, and replacement
Sub-metering utility usage
Identifying alarm conditions
For water distribution, the operational and managerial uses of a SCADA system include the
following:
Monitor the system
Exercise control over the system and ensure that required performance is continuously
achieved
Reduce operational staffing levels through automation or by operating the system from a
central location
Monitor and store data of a system’s behavior, and use the data to achieve full
compliance with regulatory reporting requirements
Controller IED or
PLC
Communications
Network
SCADA
Master
Figure 2.1.4-C1 - Simplified Illustration of PLC or IED Function in a SCADA System
Note 2-way arrows, indicating
data transmission and reception
ote 2-way arrows,
indicating data
transmission and
reception
13
Obtain information on the performance of the system and establish effective asset
management procedures for the system
Establish efficient operation of the system by minimizing the need for routine visits to
remote sites.
Potentially reduce power consumption during pumping operations through operational
optimization
Provide a control system that will enable operating objectives to be set and achieved
Provide an alarm system that will allow faults to be diagnosed from a central location,
thus allowing field repair trips to be made by suitably qualified staff to correct the given
fault condition and to avoid incidents that may be damaging to the environment.
Monitor system operations to identify excursions of operating equipment from normal
operating conditions/ranges.
Monitor equipment operations to forecast maintenance, repair and replacement.
Use SCADA data to verify hydraulic and water quality models.
Use SCADA data to identify intrusions, leakages, and other variations from normal
system, operations.
2.1.6 SCADA System Implementation Process
When considering a SCADA system, there are traditionally two methods that are utilized for
implementation. These methods are:
Design-Bid-Build Method
EFI (Engineer, Furnish and Install) Method
These methods are discussed in more detail Section 2.6 of this document.
14
2.2 Communications Network
2.2.1 General Overview of SCADA Communications
Without a properly designed communication network system, a SCADA system cannot exist.
All supervisory control and data acquisition aspects of the SCADA system rely entirely on the
communication system to provide a conduit for flow of data between the supervisory controls,
the data acquisition units, and any controllers that may be linked to the system. The purpose of a
communications network within a SCADA system is to connect the Remote Terminal Units
(RTUs) with the SCADA Master.
Referring to Figure 2.2.1-A, we will now discuss the Communications Network of SCADA
Equipment.
Remote Terminal Unit (RTU),
Programmable Logic
Controller (PLC) or Intelligent End
Device (IED)
SCADA Master with
User Interface
RTUs, PLCs or IEDs Communications Network SCADA Master
Water Levels
Hydraulic Pressure
Motor Speed/Temp
Pump Station
Ambient Humidity / Temperature
Motion Detection
Pump on/off Control
SENSORS/CONTROLS
Figure 2.2.1-A - Illustration of four SCADA Equipment Categories
15
2.2.2 Communications Network Options
The data can be transmitted through a variety of different communications platforms such as:
Ethernet - A system for connecting a number of computer systems to form a local area network,
with protocols to control the passing of information
Telephone Line - A system that utilizes electrical signals in order to transmit data over a distance
using a single pair of copper (traditionally) wires.
Optical Fiber Line- Similar to the traditional copper telephone lines, but differs by utilizing
optical fibers made of glass or plastic and uses light to transmit the data, with is faster and has
less losses as compared to copper wires.
Radio/Wireless - A system that uses radio transmitters and receivers to send data over short
distances. Typically requires line of sight for best application.
Cellular - Based on the cellular phone technology to transmit data, regardless of distance, but
dependent on cellular signal coverage.
Satellite - Similar to the cellular phone platform, but utilizing satellites instead of ground-based
cellular towers.
Wi-Fi - A technology increasing in popularity that allows an electronic device to exchange data
wirelessly (using radio waves) over a computer network, including high-speed internet
connections. Earlier generation Wi-Fi systems can be notoriously insecure; Wireless Equivalent
Privacy [WEP] is relatively easy to compromise, so care must be taken when selecting Wi-Fi
equipment to ensure that it supports robust security. WPA2 is present in almost all currently
available equipment, and its use should be mandated.
Microwave – A system for providing long-range connectivity between two sites, utilizing either
inexpensive public frequencies or FCC-licensed spectrum. Some microwave units are an
extension of Wi-Fi – but for long range (20+ miles), others use proprietary protocols.
To meet security and performance specifications, it is important to consider the endpoint of each
connection. Point-to-point connections (such as Ethernet, Fiber, and Microwave) typically
terminate at a central system management facility. Cellular systems may provide an Internet
connection requiring additional security, and phone-line systems must be protected against
security breaches through the standard land-line, twisted-pair copper wire network.
It is also important to consider the privacy offered by a solution; wireless solutions in particular
need to pay attention to the possibility of a nearby device eavesdropping on an otherwise secure
conversation. This can have profound implications if private data such as passwords are included
in the gathered data.
16
Finally, it is important to remember that these technologies are not mutually exclusive. A site can
readily use a combination of Wi-Fi and Ethernet locally, and transmit the entirety of the site’s
data to a central point through fiber, microwave or other longer-range technology.
All of these communications methods fall under either hardwire or wireless category. Hardwire
communication options include dedicated hardwire (i.e. Ethernet cable), fiber optic (i.e. light
pipe), telephone wire (i.e. copper pair), or coaxial cable. Options for wireless data transmission
include but are not limited to include satellite, radio, cellular, and Wi-Fi. Current industry trends
suggest that wireless communication systems will continue to gain a larger market sector of the
SCADA communication platforms, especially for large distributed networks such as water
distribution systems where there is a need for a vast coverage area, perhaps in remote locations
not readily accessible to existing hardwires. The same industry trends indicate that Ethernet is
becoming the preferred communications standard for local area SCADAs, such as a water
treatment plant. (Ritchie, 2011)
Wireless and hardwire options can be used alone or in tandem depending on the size and nature
of the system. Factors to consider in selecting communication options include:
Coverage area of SCADA system. For example, is the SCADA for only for the local water
plant, or does it include an entire, widely dispersed distribution system, as well as the water
plant.
If a system-wide SCADA, then consideration of the size and terrain of the distribution system.
For example, wireless may be a less expensive option, but the communications system would
require adequate line of sight between the radio transmitters/receivers.
Local availability of infrastructure and its proximity to the system feature that will require a
SCADA sensor. For example, if an there is an existing telephone line to a particular site where a
sensor needs to be installed, then that telephone line may be the best option in that case.
Growth of the community could affect the SCADA system performance and future
expandability.
Ability to upgrade the system easily, and
Budget for the system.
Some of the more significant advantages and disadvantages are summarized in Table 2.2.2-A.
Most modern SCADA systems use a variety of communication options within one system to
meet their needs. Typically, there is not a one size fits all solution for SCADA communications
and should be tailor made to fit a utility’s needs.
17
Hardwired
Advantages Disadvantages
Telephone Line May already exist to site(s). Very
mature technology.
May be monthly lease charge(s). Consider who
is responsible for fixing problems on the line and
if it is a third party, what is their track record for
repair responses. Typically slow and limited
data transmission.
Ethernet Good application for local site, such as
a water treatment plant.
Limited application range. Cannot be utilized
over distances greater than 1000’ without
boosting signal. Can be prone to lightning
damage without significant protection measures.
Fiber Optic Best direct connection with the fastest
data transmission. Large bandwidth
allows for video applications (i.e.
security cameras) to part of the SCADA
system.
May be significant monthly lease charge(s). If
the fiber does not already exist, the capital costs
for the initial project could have a very high.
Fiber is also typically very expensive to repair.
Coaxial Cable May already exist to the site(s). Very
mature technology. Better data
bandwidth than a telephone line.
May be monthly lease charge(s). Depending on
the setting, this type of hardwire is less common
than a telephone line.
Wireless
Advantages Disadvantages
UHF and VHF
Voice Radio
Generally very low maintenance and
can usually be repaired by a local radio
shop.
FCC license required, along with periodic fees
and renewals.
900Mhz spread
spectrum and
2.4Ghz Data Radio
No FCC license necessary and transmit
data at a higher rate.
Requires line of sight for best application. Some
900Mhz require FCC license.
Wi-Fi Potentially very good option for a local
site application, such as a water
treatment plant.
Very limited ranges (typically 300 ft or less), and
the signal can be significantly diminished by
structures. Wi-Fi requires careful security
assessment.
Microwave Potentially very good option for linking
sites with good elevation, such as water
towers.
Requires expert assistance with installation.
Some frequencies require FCC licensing.
Cellular Quickly gaining in popularity,
especially as pricing continues to
decline and for areas that may not have
strong radio signals or line-of-sight
conditions.
The area for coverage should have good,
consistent cellular coverage.
Satellite Good application where there is no, or
unreliable cell coverage, such as
extreme terrains, very remote locations,
etc.
May become a viable option in the future, but is
currently not cost-effective except in the most
extreme cases.
Table 2.2.2-A – Differences between hard-wired and wireless communication
systems.
18
2.2.3 Communications Network Features and Considerations
When selecting a communications system for plant operations it is common to use only hardwire
to connect remote equipment to the SCADA Master, given the short distances involved. When
using hardwired lines to communicate with remote sites in the distribution system, distance,
reliability and time responses are all limiting factors in the design process. New construction of
hardwire communication networks are not practical when trying to connect to distant system
components, such as a pump station on the other side town. In situations where it is not
economically feasible to run an independent hardwire for each remote site, one may elect to tap
into existing infrastructure or elect to use a form of wireless communication. If a utility elects to
use pre-existing infrastructure several options are available including dial-up or leased telephone
lines or fiber networks. The type of platform selected often depends on the bandwidth required
to perform remote operations such as pumping, or the polling frequency (e.g. how often do you
need to collect data).
Inaccessible sites or lack of “wire” type of infrastructure may necessitate the use of wireless
communications systems, but regardless of terrain, distance, or accessibility, current trends
suggest a growing affinity to use wireless options to replace hardwire systems. Wireless
communication provides utilities with the following benefits versus traditional hardwire systems:
scalability, deployment speed, reduced network and construction costs, and reduced maintenance
and repair of hard wires. The scalability (or ability to quickly expand as the system grows) of a
wireless network is a great advantage over wired systems. Increasing SCADA system coverage
can be achieved without running wire or other costly labor items and can be installed in a
relatively short period of time which offers savings over hardwire systems. Wireless systems
can also expand independent of existing infrastructure to meet the needs of a growing
community. The advantages of wireless can be seen by studying Figure 2.2.3-A. Consider the
image in this figure spread out over a twenty square mile area and the relative costs of a wireless
system versus a hardwire system. Now consider the replacement costs after 20 years of
technological innovation. The ability to upgrade remote sites on an individual basis versus
system wide is a clear advantage and provides a degree of assurance as land lines become phased
out. Existing hardwire systems may also be supplemented with wireless systems on a per unit
level as new operations come on-line. For cellular systems reliability and availability of service
should be taken in to consideration.
19
2.2.4 – Communication Security
Security is an important consideration when designing a SCADA network. Many existing
SCADA systems have been found wanting in this regard, leaving essential systems vulnerable to
outside influence.
Security should be considered on three levels:
Perimeter Security, limiting access to systems and network equipment from
unauthorized sources.
Interior Security, requiring at the very least a login to access important infrastructure.
Transport Security, ensuring that it is difficult to illicitly access a network segment in
an attempt to gain control.
Additionally, a cohesive security plan requires the following components:
Authentication, answering the question “who are you?” This is typically handled with a
login requirement (user’s name and password), although more secure systems are
possible. Ideally, a system should be compatible with a centralized login security system,
Figure 2.2.3-A: Typical SCADA Communication Network Configuration
20
preventing the need to visit each device in order to revoke authorization whenever
personnel changes.
Authorization, answering the question “what are you allowed to do?” This dove-tails
with authentication. Again, an ideal system will centralize this authority permitting rapid
revocation of authorization in the event of personnel changes or a security breach.
Accounting, answering the question “who did what?” In essence, this is an audit-trail,
allowing you to see which user performed what operation, and when they did it. This can
be an essential element of understanding an incident after it occurs, or catching it as it
begins.
2.2.5 – Most Efficient Strategy for Designing and Building the Communication System
When considering a SCADA system, there are traditionally two methods that are utilized for
implementation. These methods are:
Design-Bid-Build Method
EFI (Engineer, Furnish and Install) Method
These methods are discussed in more detail Section 2.6 of this document.
21
www.directindustry.com
www.onicon.com
www.watts.com
www.flowmaxx.com
2.3 Hydraulic Sensors
2.3.1 - General Overview of Hydraulic Sensors as Pertinent to Water Distribution Systems
Hydraulic sensors are common place in most modern water distribution systems. By far, the two
most common hydraulic sensors found in a water distribution system are:
Pressure Sensors – A manual read-out pressure sensor is commonly referred to as a
pressure gage. Pressure gages have been around for several centuries
and are proven accurate and reliable. Pressure gages were one of the
first sensors integrated to meet our digital needs. In modern SCADA
systems, pressure sensors are simply pressure gages
that are connected to a 4-20 mAmp analog signal
and calibrated over a specific pressure range. For
example, if you wanted to measure system pressure
on a scale from 0 to 100 psi. One would simply
calibrate the 4 to 20 mAmp signal over the 0 to 100 psi range on the
pressure sensor. This would translate a 4 mAmp signal to a
corresponding pressure of 0 psi, and a 20 mAmp signal to 100 psi.
Similarly, 50 psi would indicate that there was a 10 mAmp signal
in this example. Pressure can be a function of static water
pressure or dynamic pressure. An example of static water pressure is measuring the
water level in a storage tank, and an example of dynamic water pressure is measuring the
water pressure in a water line in the distribution system, in order to monitor transient
pressures or pipe bursts.
Flow Sensors – Methods to measure flow rates have also been around
for many centuries. Some of the earliest methods are
still in use today, such as pitot tubes, venturi systems
that measure differential pressure, microturbins, or
pressure sensitive probes that measure the bending
force on the sensors tip to measure water velocity, and
thus a corresponding flow rate. More modern flow
meters utilize electromagnetics, vortex swirl
measurement, or Coriolis mass measurement
methods. Similar to the pressure sensors, the
output is analog in nature and is calibrated over the 4-20 mAmp signal
to provide a flow output.
2.3.2 – Uses of Hydraulic Sensor Data
For many system applications flow and pressure sensors give an adequate sense of the current
operating conditions of water distribution systems. A properly designed hydraulic monitoring
system can provide valuable information to water system managers that can be used to analyze
current and historical demand, detect pipe bursts, identify illegal connections, optimize system
efficiency, and a variety of other uses. In addition to operations, hydraulic sensors have the
22
capacity to detect unauthorized intrusions and can be a valuable security tool when combined
with the proper software. When used in tandem with a modern SCADA system these sensors
become the eyes and ears of system managers, providing real time actionable information that
can be used to maintain and optimize a water distribution system.
The typical suite of hydraulic sensors includes flow and pressure. These sensors are used in
conjunction with a SCADA system, hydraulic computer model, or both which provides a means
to analyze the real time or forecasted hydraulic parameters within a water distribution system.
The hydraulic sensors connect to an RTU/PLC via hardwire or wireless connection and stream
hydraulic data through the communication network on demand or at set time intervals. This data
ultimately ends up at the HMI and/or SCADA Master where it is presented to the end user for
analysis, or compiled in a historian (database system) where it can be accessed for forecasting
demand patterns, evaluating system efficiency, and analyzing system hydraulic head
deficiencies.
Hydraulic sensor data plays an important role in distribution system management. Uses of the
data include but are not limited to: 1) assure adequate flow of water for supply and fire-fighting
to industries, schools, and other critical users or locations in the system; 2) identify water
turnover in ground and elevated water storage tanks; 3) detect major water loss incidents; 4)
plan hydrant flushing; 5) verify distribution system hydraulic modeling; 6) verify distribution
system water quality modeling; 7) identify distribution system valve problems; 8) provide data
that is used as a component of a contaminant warning system (DWS), 9) provide an
understanding of flows and pressures in the distribution system to analyze water quality issues,
assure adequate fire flows and system pressures, etc.
In a number of situations, it may be of value to have both hydraulic and water quality sensor data
from the same location in the distribution system for decision making. It should be expected that
combining both types of sensors in the same location will be less costly than having two
monitoring stations. Making this decision must be on a case-by-case basis.
2.3.3 – Sensor Equipment Sources
Several sources for hydraulic sensors are:
ABB, abb.com
Ashcroft, ashcroft.com
Holykell, holykell.com
Honeywell, honeywell.com
Keyence, keyence.com
Truck, truck-usa.com
23
This is a brief list of manufacturers. A more complete list is included in Appendix A.
2.3.4 – Most Efficient Strategy for Obtaining Hydraulic Sensors
When considering a SCADA system, there are traditionally two methods that are utilized for
implementation. These methods are:
Design-Bid-Build Method, described in section 2.1.3.A
EFI (Engineer, Furnish and Install) Method, described in section 2.1.3.B
These methods are discussed in more detail Section 2.6 of this document.
2.3.5 – Hydraulic Sensors Costs and Specifications
A variety of cost components are involved in the installed cost of sensors in a distribution
system. These include land purchase, construction of the vault in which the sensors and
connections to the distribution piping will be located, installation of the sensor, supplying power
to the site, installing the communications equipment, and upgrading/installing equipment at the
central control room (Berry 2005). Other costs include design and bidding the construction and
installation work, access to the site, and security fencing and lighting. Obviously, the more
remote and/or less accessible the location of the sensors, the higher the installed costs will be.
Combining hydraulic and water quality sensors in the same locations should yield lower installed
costs for all the sensors in the system. However, the efficacy of combined installations with
respect to the management, operations, and/or future design decisions needs to be considered.
The authors’ collective experience has shown that some distribution systems have long-standing
water quality problems associated with excess water residence time in some areas in distribution
systems that are a considerable distance from the water treatment. This is especially true of
water supplies that purchase their treated water from other utilities. Because the sensors
themselves are such a small portion of the total installed costs, it appears to be prudent to
optimize the number of locations by carefully deciding the combinations of sensors at each RTU.
Pricing surveys conducted at the time of this report showed as much as two orders of magnitude
cost differences on sensor that appear to be equivalent in nature. Determination of value
(relative to price) is a process that you should rely on your design consultant to help you with.
However, some considerations to try to stay aware of include:
Product customer service and technical support: Customer service is a series of activities
designed to enhance the level of customer satisfaction – that is, the feeling that a product
24
or service has met the customer expectation. Customer service includes providing
technical support in an easy to understand and effective manner.
Warranty: No piece of hardware can be warrantied forever. However, the longer the
warranty the better the indication that the sensor is made from quality materials and
quality components.
Sensor replacement availability: This is an important question that needs to be
considered. If the sensor you plan to install in your system is not readily available, then
perhaps a different sensor or manufacturer should be considered.
Ease of maintenance and testing: A water system operator understands that all equipment
needs to be regularly maintained and/or tested needs to be easily accessible. However,
not all equipment manufacturers understand that the equipment being maintained and/or
tested equally needs to be operator-friendly. Be sure to take into account how easily
regular maintenance and testing can be performed on the sensor.
Compatibility with the rest of the SCADA system: If you have an existing system, new
sensor compatibility is an absolute requirement, or else you are essentially buying a new
stand-alone piece of equipment.
The cost of the sensors is frequently a very small portion of the cost of the sensor installation.
(Berry et al, 2005) Site specific installation cost projections need to be developed. Typical cost
components that will be included in the total cost of a sensor installation at each potential
location.
Land purchase
Construction of the vault in which the sensors and connections to the distribution piping
will be located
Installation of the sensors and RTU
Supplying power to the site
Installing the communications equipment and upgrading/installing equipment at the
central control room
Design and bidding the construction and installation work
Access to site
Security fencing and lighting
There are two generic types of SCADA and sensor specifications. These are the Use
Requirements Specification and the Detailed Technical Specification type. Either type of
specifications should include a complete explanation of the intended uses of the sensor data, and
details of existing SCADA components (system architecture) with which the sensor system will
must be integrated, and require operator training associated with the sensors and sensor data
management.
The Use Requirement Specification identifies the data to be sensed and the uses of the data. It
leaves the technical details up to the suppliers and contractors. In general, this type of
25
specification takes less time and cost to develop that the Detailed Technical Specification. It
may also allow greater competition from bidders. However, it does reduce the ability of the
Utility to control who bids on the project, if that is of interest for any reason.
The Detailed Technical Specification includes detailed specifications for each item in the system
to be constructed/installed. The specifications are usually provided by the supplier who assists
the designer in the design of the sensor system. Detailed specifications are often used to reduce
the number of bidders, or to try to exclude certain products, types of products, or bidders.
However, when federal funds are used to pay a portion of the cost of the
construction/installation, these specifications are required to include multiple supplier names
and/or an “or equal” statement. A potential pitfall to using a Detailed Technical Specification is
not including the specification for one or more of the components of the system.
Technical specifications and costs are impacted by 1. measurement sensitivity, 2. monitoring
range, 3. measurement accuracy, 4. measurement response time, 5. measurement interferences, 6.
installation location restrictions (e.g., turbulence interference), 7. routine maintenance required,
8. sensor life expectancy, 9. calibration methods and frequency, 10. materials of construction, 11.
installation methods, and 12. other technical requirements that are based on the experience of the
distribution system SCADA technical experts. This information should be included in either the
Use Requirement Specification or the Detailed Technical Specification.
26
2.4 Water Quality Sensors
2.4.1 - Overview of Water Quality Sensors as Pertinent to Water Distribution Systems
There is a variety of reasons to employ water quality sensors in water distribution systems.
Contamination by cross-connections with non-potable water, contaminated water entering the
distribution system through leaking pipes in area of low pressure, or microbial growth in the
distribution system pipes is always a management concern (EPA 817-R-07-002). Nationally
recognized water security experts have identified distribution systems as very vulnerable to
attack because of the physical characteristics of the piping systems and the lack of monitoring
and surveillance of the systems (WaterSentinal). Identifiable threats or indications of possible
contamination is a management concern (EPA 817-R-07-002).
Water quality sensor data is used for decision-making on a variety of management issues. These
include but are not limited to: 1) identifying compliance with regulatory water quality
requirements; 2) identifying non-regulatory water quality for critical users (e.g., at industries
requiring certain process water chemistry) and at other important locations throughout the
system; 3) verifying water quality modeling; 4) planning hydrant flushing; and 5) implementing
a contamination warning system (CWS).
A CWS is a proactive operation to generate distribution systems water quality data and combine
that with a variety of other information to continuously monitor for the presence of unexpected
contaminants in the system (Contamination Warning System CIPAC 2012). The intent of a
CWS is to minimize the number of people who are negatively impacted by a contamination
event in a distribution system. The location of the sensors for a CWS is critical to accomplishing
a minimizing of people impacted. A number of computer programs exists that are used to
optimize the location of water quality sensors for a CWS. WaterSentinel is a federal program to
advance the knowledge and use of CWS in water utilities ( see
http://water.epa.gov/infrastructure/watersecurity/index.cfm). Threat Ensemble Vulnerability
Assessment Sensor Placement Optimization Tool (TEVA SPOT) is software that optimizes the
locations of water quality sensors in a distribution system when they are to be used as
components of a CWS (see https://software.sandia.gov/trac/spot).
The chemical, physical and biological conditions of water combined form its quality. Even
minute changes in these characteristics can impact the people and industries that depend on
water. To preserve its quality, monitoring water parameters such as conductivity, pH, salinity,
temperature, dissolved oxygen, chlorine residual and turbidity is crucial. For the same reason,
water quality sensors have become common in most modern distribution systems.
Water quality sensors are employed using one of two main approaches. They are either used to
directly measure constituents of interest (chemical concentrations, solids, etc.) in the water, or tp
measure surrogates. Surrogates are chemical concentrations or solids that may indicate the
presence of unanticipated contaminants in the water.
27
www.veoliawaterst.com
www.geinstruments.com
www.directindustry.com
www2.emmersonprocess.com
Many types of water quality sensors are available in market based on what one wants to measure,
below is the list of most common ones in use and some of their details.
Chlorine Residual Sensor - Measuring chlorine residual in drinking water treatment
plant and distribution systems is a common process and has been necessary as long
as chlorine has been used in water treatment. Chlorine is the most widely used
disinfectant which can be attributed to its efficiency and economical aspects.
Chlorine sensors measure free chlorine, monochloramine, and total chlorine. The
primary application is drinking water disinfection, although total chlorine is often
measured in treated wastewater, including reclaimed wastewater.
TOC Sensor - Total Organic Carbon (TOC) is an important parameter for water
quality analysis. It is used as a direct indicator and a surrogate for many
water quality purposes. There are two different TOC measurements
devices available in the market: TOC analyzers and TOC sensors. If the
intended TOC device use is for regulatory reporting, managing an
important process control variable, real-time release, or other critical-to-
quality product attributes, instrument accuracy is essential. If the intended
use is for general TOC monitoring—not for making critical quality
decisions—then other characteristics may be more important than
accuracy. Sensors are typically used to monitor a process and the data
collected from them is used for information only.
Turbidity Sensor - Turbidity sensors measure suspended solids in water, typically by measuring
the amount of light transmitted through the water. They are used in river and stream gaging,
wastewater and effluent measurement, drinking water treatment process and control, control
instrumentation for settling ponds, sediment transport research, and laboratory measurements.
Conductivity Sensor -Conductivity measurements are carried out in industrial processes
primarily to obtain information on total ionic concentrations (e.g. dissolved compounds)
in aqueous solutions. Widely used applications are water purification, clean in place
(CIP) control, and the measurement of concentration levels in solutions. The measuring
system consists of an appropriate inline sensor directly inserted or in a housing, a cable
connected to a transmitter converting the received signals to a measurement result or
forwarding it to a DCS
pH Sensor - In the process world, pH is an important parameter to be measured
and controlled. The pH of a solution indicates how acidic or basic (alkaline) it is.
pH sensor components are usually combined into one device called a combination
pH electrode. The measuring electrode is frequently glass and quite fragile. Recent developments
have replaced the glass with more durable solid-state sensors. The analyzer or
transmitter has a man machine interface for calibrating the sensor and
configuring outputs and alarms, if pH control is being done.
ORP Sensor - ORP sensors measure the Oxygen-Reduction Potential of a
solution. Used in tandem with a pH sensor, the ORP measurement provides
28
insight into the level of oxidation/reduction reactions occurring in the solution. The ORP Sensor
requires a compatible interface and software to collect data.
For many system applications these sensors provide indication of water quality conditions of
water distribution systems. A properly designed water quality monitoring system can provide
valuable information to operators and engineers that can be used to calibrate their hydraulic
models, predict formation of regulated substances, provide compliance data and track the change
in quality over time which in turn helps system operators make important decisions about water
treatment unit processes and operational conditions. When used in tandem with a modern
SCADA system these sensors become eyes and ears of system operators, providing real time
actionable information that can be used to maintain and optimize the water quality in distribution
systems.
2.4.2 - Sensor Equipment Sources
Several sources of water quality sensors are
ABB, abb.com
GE, ge.com
Hach, hach.com
Siemens, siemens.com
Emerson, emersonprocess.com
Yokogawa, yokogawa.com/us
This is a brief list of manufacturers. A more complete list is included in Appendix A.
2.4.3 - Most Efficient Strategy for Obtaining Water Quality Sensors
NOTE: Information in 2.6.3 is generally a repeat of section 2.1.3, but is kept in tack within this
section to maintain the effort to make each section stand alone.
When considering a SCADA system, there are traditionally two methods that are utilized for
implementation. These methods are:
Design-Bid-Build Method
EFI (Engineer, Furnish and Install) Method
These methods are discussed in more detail Section 2.6 of this document.
2.4.4 - Water Quality Sensors Costs and Specifications
29
Site specific installation cost projections need to be developed. Typical cost components that
will be included in the total cost of a sensor installation at each potential location.
Land purchase
Construction of the vault in which the sensors and connections to the distribution piping
will be located
Installation of the sensors and RTU
Supplying power to the site
Installing the communications equipment and upgrading/installing equipment at the
central control room
Design and bidding the construction and installation work
Access to site
Security fencing and lighting
There are two generic types of SCADA and sensor specifications. These are the Use
Requirements Specification and the Detailed Technical Specification type. Either type of
specifications should include a complete explanation of the intended uses of the sensor data, and
details of an existing SCADA components (system architecture) with which the sensor system
will must be integrated, and require operator training associated with the sensors and sensor data
management.
The Use Requirement Specification identifies the data to be sensed and the uses of the data. It
leaves the technical details up to the suppliers and contractors. In general, this type of
specifications takes less time and cost to develop that the Detailed Technical Specification. It
may also allow greater competition from bidders. However, it does reduce the ability of the
Utility to control who bids on the project, if that is of interest for any reason.
The Detailed Technical Specification includes detailed specifications for each item in the system
to be constructed/installed. The specifications are usually provided by the supplier who assists
the designer in the design of the sensor system. Detailed specifications are often used to reduce
the number of bidders, or to try to exclude certain products, types of products, or bidders.
However, when federal funds are used to pay a portion of the cost of the
construction/installation, these specifications are required to include multiple supplier names
and/or an “or equal” statement. A potential pitfall to using a Detailed Technical Specification is
not including the specification for one or more of the components of the system.
Technical specifications and costs are impacted by 1. measurement sensitivity, 2. monitoring
range, 3. measurement accuracy, 4. measurement response time, 5. measurement interferences, 6.
installation location restrictions (e.g., turbulence interference), 7. routine maintenance required,
8. sensor life expectancy, 9. calibration methods and frequency, 10. materials of construction, 11.
30
installation methods, and 12. other technical requirements that are based on the experience of the
distribution system SCADA technical experts. This information should be included in either the
Use Requirement Specification or the Detailed Technical Specification.
31
2.5 – Hydraulic and Water Quality Sensor Placement
Determining locations where either hydraulic and water quality sensors should be installed
should be driven by exactly what information is needed about the distribution system. For
example, if all that is needed is the water level in an elevated storage tank, then obviously
placing a pressure sensor at or near the base of the tower is probably the logical choice.
However, the placement choices become very complicated when the most logical option is not
economical or a physically optimal option. The remoteness of the location and access to such
facilities sometimes pose questions that are hard to answer. The use of computer modeling for
sensor placement is increasing. The USEPA model Threat Ensemble Vulnerability Assessment-
Sensor Placement Optimization Tool (TEVA-SPOT) is one such computer tool available to assist
in sensor location decisions. Hart and Murray (2010) reported on three sensor placement
strategies that are being applied for deployment of DWS: expert opinion, ranking methods, and
optimization (computer modeling). Berry, et al, (2005) reports that tests of the use of sensor
placement modeling and the decisions made by local experts in a water supply system “…
suggest that a collaboration between modelers and those with practical water system expertise
can improve the effectiveness of sensor placement decisions”. Programs like TEVA-SPOT can
assist in finding optimal locations for each sensor in a distribution system for use as a component
of a drinking water system, while the operators and/or managers need to decide which among the
potential alternative locations are optimal to place the sensor for their purposes.
The placement choices can become very complicated if the purpose of the sensor is to determine
model inputs for a hydraulic model, or if the goal is to monitor for maliciously injected
contaminants, which is termed a contaminant warning system (CWS) or detect pipe bursts and
other leakage. (Mounce, S. et. al., 2003 and 2006), (Berry, J. et. al., 2005) Hydraulic sensors are
very useful for modeling water quality in a distribution system, by monitoring flows, and thus
residence times in the system. This use of hydraulic data also has direct application to regulatory
compliance.
Berry, J, et al (2005) identified placement cost budget, contamination public health impacts, and
potential attack scenarios as considerations in sensor placement. The Public Health Security and
Bioterrorism Preparedness and Response Act of 2002 identified physical security of water supply
distribution systems as a major priority for water utilities. So, in addition to combining hydraulic
and water quality sensors in the same location, consideration of the value of data from these
sensors at locations of security sensing (e.g. water storage towers, basins, and pump stations)
may be worthwhile.
SCADA sensor placement decisions made without the use of computer models are frequently
based on the experience of the decision-maker and his/her support group’s experiences.
Following is a list of sensor placement design issues provided in a sequence used by the authors
(Mounce, S. et. al., 2003 and 2006), (Berry, J. et. al., 2005) in the design of SCADA systems.
32
SCADA Sensor Placement Decision-Making Sequence
1. Intended uses of data
A. hydraulic and water quality monitoring
B. security monitoring
C. energy management
D. equipment management including repair and replacement forecasting
E. sub-metering utility usage
F. identifying alarm conditions
G. verifying hydraulic or water quality modeling
H. provide data as a component of a CWS
2. Parameters of interest & to be monitored
3. Locations/areas for which data is desired
A. areas or location of major public health impacts from contamination (schools, health
care facilities, food preparation, elderly living centers, etc.)
B. potential contamination attack scenarios and locations based on physical
characteristics of distribution system
C. areas of known poor water quality in distribution system based on complaints, etcetera
D. locations of regulatory agency required compliance sampling
4. Locations of other types of sensors currently in distribution system
5. Potential locations of other (security, water quality, etc.) sensors to be added to the system
6. Potential locations based on the above
7. Security & accessibility of potential sensor sites
8. Cost components (relative costs) by location
9. Sensor station design & construction budget available
10. Final sensor placement locations
If a water system SCADA is being planned, sensor placement computer programs (e.g., TEVA
SPOT) are available to optimize the locations of the sensors to minimize the impacts of a
contamination incident. To use one of these programs, complete, accurate and calibrated
33
hydraulic and water quality models of the distribution system are necessary to provide inputs to
the sensor placement program. Following is a list of the information/data needed from the
system operators and/or managers for input to these programs.
SCADA CWS Sensor Placement Optimization Program Inputs
1. Complete and calibrated hydraulic and water quality distribution system models.
2. Simulation time – the length of time (number of hours) the program run should simulate.
3. Time of release – the length of time a contaminant is injected into the distribution system.
4. Mass injection rate (mg/min) – the amount of contaminant that is injected into the distribution
system per unit time.
5. Contaminant – the contaminant(s) that may be injected into the system.
6. Response time delay – the time between initial detecti9on of a contaminant in the distribution
system and when public warnings are issued.
7. Detection limit – some level of contaminant concentration below the health impact level of a n
injected contaminant; this must be in the range between the upper and lower detection limits of
the sensors.
8. Impact metrics – any of a variety of impacts can be used: the number of people ingesting the
contaminant, length of distribution system piping that is contaminated, number of people with
health effects from the contaminant, etcetera.
9. Sensor placement objective - any of a variety of objectives for the placement of sensors can be
used: minimize the number of public health impacts, minimize the extent of distribution system
contamination, etcetera.
34
2.6 Strategies for developing Data Acquisition and SCADA Systems
2.6.1 - Design/Bid/Build Project Delivery Method
As the name implies, this implementation method consists of three distinct project phases; the
design phase, the bid phase and the build phase. This method of project delivery is most
common in utility and other public sector projects. The owner will typically be dealing with at
least two persons or companies to deliver their completed SCADA system, but sometimes many
more than two. There will always be an engineer or other design professional involved.
Depending on if the owner decides to direct purchase the necessary equipment or let the
contractor be responsible for equipment purchases as part of the contract, there can be either one
or more additional entities that the owner will need to engage.
The design-bid-build method requires a set of plans and specifications to be created by an
engineer or other design professional. Traditionally, these plans and specifications contain every
detail of the proposed project, from what kind of SCADA Master, to exact communications
network specifications, to which general types of RTUs, PLCs, to power supplies, to which
equipment sensors and controls will be installed and even where the sensors will be installed on
the specific piece of equipment. This means that the designer needs to finalize every detail of the
project before the project is put out for bids. After these detailed plans and specifications are
completed, the owner chooses one of two routes: either purchasing all the equipment directly,
then receiving multiple, qualified bids for installation (Figure 2.6.1-A), or more simply (and
typically) receives bids from multiple, qualified contractors that include the equipment and the
installation (Figure 2.6.1-B). Once the project is complete the owner must pay the contractor the
bid amount, plus or minus the net amount of contract change orders. After the owner signs a
contract for a bid-build project, they have minimal input in the remaining part of the project,
unless there are any unforeseen obstacles or problems. These often result in “change orders”,
which tend to be costly and all parties try to avoid. Changes to the system can be made after
project completion, but usually at a higher cost.
Engage a
qualified
engineer or
design
professional
Begin the
design process
for complete
set of plans and
specs
Owner
purchases
equipment
specified in
plans and specs
Obtain bids from
multiple qualified
contractors to
install purchased
equipment
Engage a
contractor
to complete
project
Figure 2.6.1-A – Design-Bid-Build, Owner Equipment Purchase
35
A small twist on the design-bid-build project delivery method is something known as issuing a
“performance specification” (Figure 2.6.1-C). This method accomplishes the same end goal but
in this case the engineer simply issues a ultimate project goal to be met. The engineer can even
require certain equipment, but no detailed plans or specifications are produced in this process,
thus transferring much of the project risk to the prospective contractor to deliver the required
final product. Performance specification projects, though convenient for the design professional,
often produce higher bids because the contractor understands the risk of project success has been
transferred to them as the contractor and away from the design professional. It is much less
probable to realize any change orders in a performance spec type of design-bid-build project,
unless the conditions change or the owner initiates the change.
2.6.2 - Engineering, Furnishing, and Installation (EFI) Project Delivery Method
An EFI is a person or company that provides engineering, furnishes necessary equipment,
installs all equipment and commissions the system. Depending on where you are in the nation,
some companies use the term “design-build” instead of EFI. Compared to the design-bid-build
method, where the owner usually only has input in the design phase of the project, the EFI
method combines the engineer, equipment furnisher, and installer into one entity and shifts the
involvement of the owner to the entire life of the SCADA implementation project. Most major
decisions about the system are made up-front, so that a project budget price can be established;
however, many more decisions are made as the project proceeds, so that the final project is able
to perform the best that it can.
While the owner may have more control over their project in an EFI project delivery method,
they will need to devote more time to the project during the building/implementation processes
and have more opportunity to become very involved with the project. Many of the minor
decisions will be made later in the implementation process and only when they are needed. The
Engage a
qualified
engineer or
design
professional
Begin the
design process
for complete
set of plans and
specs
Obtain bids from
multiple qualified
contractors to build
project per plans and
specs
Engage a
contractor to
complete
project
Figure 2.6.1-B – Design-Bid-Build, Typical
Engage a
qualified
engineer or
design
professional
Produce a
“performance
specification”
design
Obtain bids from
multiple qualified
contractors to build
project per performance
spec
Engage a
contractor to
complete
project
Figure 2.6.1-C – Design-Bid-Build, Performance Specification
36
biggest advantage with the EFI project delivery process is the overall simplicity (Figure 2.6.2-A)
and flexibility to change a certain aspect of a project, which helps when you are entering a
project with little certainty of your expectations. In this form of project execution, the owner and
the contractor work together to reach a desired end result and projects are usually paid by a cost-
plus method, where the owner pays for the cost of the project with the addition of profit and
overhead to the contractor. Other arrangements such as fixed-cost are also common, but in an
EFI method, contractors will try to avoid that arrangement because too much risk is assigned to
the contractor.
Figure 2.6.2-A portrays the EFI method as a simple, one-step process. This is may or may not
necessarily be the case, but compared to the previous examples, the EFI method is indeed more
simplistic. There are certain cautions that the owner should be aware of, the first being that the
EFI method may not be allowed by certain state or federal agencies, if their funding is involved
in the project. This is simply because granting or loaning agencies may require competitive bids
as a requirement of the use of their funds. Although and EFI project delivery method can be set
up to be competed on by multiple EFIs in a competitive manner, it is very difficult to arrange this
because unlike the design-bid-build delivery method, the final scope of work and product is not
exactly known before the bid process occurs.
There are distinct advantages to each delivery process and you should take time to educate
yourself on the pros and cons of each before you select your method of choice.
2.6.3 – Considerations for Potential Equipment Suppliers, Engineers and Contractors
Very often, the owner will have an existing relationship with an engineering or design
consultant. This person/company may actually have the in-house talent necessary to design the
entire SCADA system to meet your needs. If they do not have the necessary talent in-house,
then they probably have a relationship with a fellow consultant/company that does that the
necessary skill sets and capacity.
Designing a practical and reliable SCADA system requires a great deal of expertise and time.
There's physical installation, power supplies, communications network, network connections,
and then the even more difficult phases of configuration and data basing. It can be a daunting
task, especially for most engineers that do not necessarily specialize in these projects. It is very
important that the design professional you select has the depth of expertise necessary for the job.
Engage a qualified EFI
to complete project
Figure 2.6.2-A – EFI Project Delivery
37
Below are several items that should be considered before you decide on a specific engineer or
design professional:
Quality Standard Certifications: Many engineers, design professionals, and equipment
manufacturers adhere to procedures certified by industry standards organizations, such as
ISO 9000 or the telecommunications-specific TL 9000 standard.
Experience and Client Testimonials: As with any business-to-business professional
service, you should check carefully for your engineer’s or design professional's
reputation. Find out how long they or their company has been in business, see if it can
offer testimonials from its clients-and check with their clients to get a real sense of how
they rate the company's services.
Vendor Partnerships: Depending on your situation, pre-existing vendor partnerships may
or may not be of concern to you. However, you as the owner need to be aware of any
existing partnerships so you can be aware that you may be “driven” to a certain platform
or product line. Just because you are outsourcing the project design, you should still
retain control. Check what vendors your engineer prefers or works with. You should be
still able to specify the vendor and equipment you want.
Compare Prices, But Don't Be Cheap: The costs of using an engineer or design
professional is usually justified by quality of the plans and specifications. The quality of
the plans and specs is measured by the number of change orders and if the final SCADA
system performs as intended. By all means, look for the best value, but always keep
quality just as high on your list.
If you elect to pursue the SCADA project using the EFI delivery method, many of these same
criteria can be used, but keep in mind that although EFIs will have a broad knowledge base, they
will very likely maintain only a few vendor partnerships and those partnership will be much of
their expertise is focused around. This being said, below are some additional values that an EFI
will bring to the SCADA project.
Product Knowledge: You as the owner may already know quite a bit about the equipment
you use, but you haven't had the time to research everything about it. And when you're
adding new types of equipment to your system, you can never be quite sure how your old
and new equipment will work together. You can turn to old equipment vendors for
assistance, but while they can tell you a lot about their own equipment, they likely will
not know how their older equipment may interact with equipment from other
manufacturers. EFIs usually have broad knowledge of different types of equipment used
throughout the industry, and they have deep experience of integrating different equipment
during installation. That experience and expertise is difficult to reproduce or obtain
elsewhere.
Outsourcing Time and Trouble: You may have been given the responsibility for a system
deployment, but that doesn't mean you have the time, the resources, or the staff to
oversee every detail of the project-especially if managing the deployment is an extra job
that's been added to your everyday duties. If this is your situation, you may have a
classic business case where outsourcing the work will get the job done faster, more
38
efficiently, and even less expensively than trying to do the work entirely in-house or with
a traditional design-bid-build method.
Project Management: Deployments often take longer than planned, especially if you're
working with new equipment. There's a lot you have to learn to execute a successful
implementation, and it's easy to make beginner's mistakes that can extend your time and
budget. The project management experience of an EFI provider can be of real value here.
These are companies with years of experience overseeing telemetry deployments, and
they have highly developed systems for ensuring projects are completed on schedule and
as planned.
So, does this added value justify using an EFI provider for your project? Before you decide yes
or no, ask yourself these questions:
1. Does the deployment project require extra training for your installation technicians?
2. Do you have the time to manage the entire project yourself?
3. Do you have the experience to anticipate and prevent problems and delays with your
implementation?
4. If an EFI project delivery cannot meet your schedule or quality requirements, cheaper and
faster is not necessarily better.
5. Do you have an established data management plan, or does this need to be part of the
overall project?
6. Do you have ability to analyze the data acquired by the SCADA system?
7. Do you have a plan or the ability to use the new data in an intelligent manner in order to
perform advanced planning and management in your system?
39
References
Allen M, Mudasser I, Srirangarajan S, Lim B L, Girod L, Whittle A. 2011. “Real-time In-
network Distribution System Monitoring to Improve Operational Efficiency”. AWWA. 103(7):
63-75.
Bentley Systems Incorporated, 2004. “The Fundamentals of SCADA – A White Paper from
Bentley Systems, Inc”.
Berry, Jonathan W., et al. "Sensor Placement in Municipal Water Networks." Journal of Water
Resources Planning and Management 131.3 (2005): 237-243.
Berry, J., et al. "Water Quality Sensor Placement in Water Networks with Budget
Constraints." Proceedings of the World Water and Environmental Resources Conference. 2005.
Chen A, Haught R C, Goodrich J, Pollack A. 1999. “Options for Remote Monitoring and
Control of Small Drinking Water Facilities”. Columbus (OH): Battelle Press. 318 p.
Clingenpeel, William H., and Don B. Rice. "Development of a Water and Wastewater SCADA
System." Public Works 121.7 (1990): 60-62.
“Contamination Warning System CIPAC Workgroup Final Report”. March 2012.Water Sector
Coordinating Council and Water Government Coordinating Council.
“EPA Software that Models the Hydraulic and Water Quality Behavior of Water Distribution
Piping Systems” [Internet]. c2011.; [cited 2011 June 08]. Available from:
http://www.epa.gov/nrmrl/wswrd/dw/epanet.html
“EPANet 2 Users Manual” [Internet]. c2000. USEPA; [cited 2011 July 11]. Available from:
http://www.epa.gov/nrmrl/wswrd/dw/epanet/EN2manual.PDF
Hart, W., and Murray, W., “Review of Sensor Placement Strategies for Contaminant Warning
Systems in Drinking Water Distribution Systems”. Journal of Water Resources Planning and
Management. ASCE. Nov/Dec 2010. 611:619.
McMillan R. [Internet]. 2010. Siemens: “Stuxnet Worm Hit Industrial Systems”. Networkworld.
com; [updated 2010 Sept 14; cited 2011 July 27]. Available from: http://www.networkworld.com
/new s/2010/091410-siemens-stuxnet-worm-hit-industrial.html
Moore, HD. What happened when one man pinged the whole Internet?
http://www.technologyreview.com/news/514066/what-happened-when-one-man-pinged-the-
whole-internet/
SCADA security training. https://www.sans.org/course/scada-sec-training-2012
Mounce, Stephen R., et al. "Sensor-fusion of Hydraulic Data for Burst Detection and Location in
a Treated Water Distribution System." Information fusion 4.3 (2003): 217-229.
Mounce, Stephen R., and John Machell. "Burst Detection using Hydraulic Data from Water
Distribution Systems with Artificial Neural Networks." Urban Water Journal 3.1 (2006): 21-31.
40
Mulhauser G. “The Benefits of Component Object-Based SCADA and Supervisory System
Application Development. Lake Forest (CA)”. [Internet]. 2010. Wonderware.com; [cited 2011
June 24]. Available from: http://global.wonderware.com/EN/PDF%20Library /The_Benef
its_of_Com pon ent_Object_Based_SCADA_and_ Supervisory_System_Appl ication_Develop
m ent_White_Paper.pdf
MullaneyJ. “Introduction to SCADA and Telemetry. MSE Technology Applications Inc.”.
[Internet]. [cited 2011 June 24]. Available from: http://www.tetragenics.com/
pdf/presentations/scada_2.pdf
Ormsbee, Lindell E. "The History of Water Distribution Network Analysis: The Computer
Age." 8th Annual Water Distribution Systems Analysis Symposium. 2006.
Ormsbee, Lindell E., and Kevin E. Lansey. "Optimal Control of Water Supply Pumping
Systems." Journal of Water Resources Planning and Management 120.2 (1994): 237-252.
Pickard B C, Haas A J, Allgier S C. “Optimizing Operational Reliability of the Cincinnati
Contamination Warning System”. 2011. AWWA. 103(1): 60-68.
Pipe2010: “KYPipe (Steady State Analysis)” [Internet]. c2009. KYPipe; [cited 2011 June 08].
Available from: http://www.kypipe.com/kypipe
Propato, Marco. "Contamination Warning in Water Networks: General Mixed-integer Linear
Models for Sensor Location Design." Journal of water resources planning and
management 132.4 (2006): 225-233.
Propato, M., O. Piller, and J. Uber. "A Sensor Location Model to Detect Contaminations in
Water Distribution Networks." Proc. World Water and Environmental Resources Congress.
2005.
Ritchie, E, 2011. “The New Face of SCADA. Water Efficiency”. Vol. 6, No. 3 (May/June
2011): 28-33.
“SCADA” [Internet]. c2011.Wikipedia; [cited 2011 May 23]. Available from:
http://www.en.wikipedia.org/wiki/SCADA
Serjeantson B, McKinney S, Van Buskirk. 2011. ”Leverage Operations Data and Improve Utility
Performance”. Opflow. 37(2): 10-15.
Stoianov, Ivan, et al. "PIPENET: A Wireless Sensor Network for Pipeline Monitoring”.
"Information Processing in Sensor Networks, 2007. IPSN 2007. 6th International Symposium on.
IEEE, 2007.
“Smart Metering for Water Utilities”. [Internet]. 2009. Oracle; [cited 2011 May 21]. Available
from: http://www.oracle.com/us/industries/utilities/046596.pdf
Stouffer, Keith, Falco, Joe, and Kent, Karen. Guide to Supervisory Control and Data Acquisition
(SCADA) and Industrial Control Systems Security. National Institute of Standards and
Technology, September 2006.
41
Teodor Sommestad, Göran N. Ericsson, Jakob Nordlander. SCADA System Cyber Security – A
Comparison of Standards. IEEE Journal, reprinted online at
http://scadahacker.com/library/Documents/Standards/IEEE%20-
%20Comparison%20of%20SCADA%20Security%20Standards.pdf
“Threat Ensemble Vulnerability Assessment – Sensor Placement Optimization Tool (TEVA-
SPOT) Graphical User Interface User’s Manual”. Version 2.3.1. EPA/600/R-08/147. Sept.
2012.
Uber, James, et al. "Greedy Heuristic Methods for Locating Water Quality Sensors in
Distribution Systems." Proc., World Water & Environmental Resources Congress. Reston, Va:
EWRI-ASCE, 2004.
“US-CERT:United States Computer Emergency Readiness Team”. [Internet]. c2011. US
Department of Homeland Security; [cited 2011 June 14]. Available from: http://www.us-
cert.gov/control_systems/
Van Hemert G. [Internet]. “So You Have a SCADA System What is Next?”. [cited 2011 May
23]. Available from: http://downloads.vertmarkets.com/files/downloads/c1809894-df8a-46ce-
b191-e807e13ae4d5/schneiderelectric_scada.pdf
“Water Security Initiative: Interim Guidance on Planning for Contamination Warning System
Deployment”. EPA Office of Water. EPA 817-R-07-002. May 2007.
“Water Security Initiative: Interim Guidance on Developing an Operational Strategy for
Contamination Warning System”. EPA Office of Water. EPA 817-R-08-002. Sept 2008.
“WaterSentinel System Architecture”. Draft, Version 1.0. EPA. December 2005.
Weickgenannt, Martin, et al. “Risk-Based Sensor Placement for Contaminant Detection in
Water Distribution Systems”. Journal of Water Resources Planning and Management. (Nov-
Dec 2010):629-636.
42
Appendix A - Listing of Water Related Sensor Manufacturers 2012
ABB
Eureka Environmental
Engineering Mena Water
ADS Environmental Service Eutech* Meter Master
Advanced Measurements &
Controls GE METTLER TOLEDO
Anacon Georg Fischer multitrode
Analytical Sensors &
Instruments Ltd
Global Water
Instrumentation, Inc. Oakton Instruments
Analytical Technology Hach OI Analytical
AquaMetrix Hanna Instruments Omega Engineering, Inc.
Arjay Engineering HF Scientific Process Instruments (Pi)
ASA Analytics Honeywell ProViro Instrumentation
Banner Engineering Horiba Real Tech
BeLink Icx Technologies (FLIR) RMS Water Treatment
Cambell Scientific In USA Inc. Rosemount*
Chemical Injection
Technologies, Inc. (Superior) Inficon Scan Measurement Systems
Cole-Parmer Innovative Components Severn Trent Services
Control Micro Systems Innovative Waters Siemens
Datalink Instruments In-Situ Inc Stedham Electronics
DEVAR Inc. Invensys
Stevens Water Monitoring
Systems, Inc
EMEC Liquid Control Systems Itron Thermo Scientific
Emerson ITT Water and Wastewater Vega Controls
Endress + Hauser JMAR Wedgewood Analytical
Entech Design Keco Engineered Controls YSI
Environment SA